[2018] VCAT 696
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2018-05-08
Original judgment source is linked above.
Building Contract - AS 4300-1995 form of contract - security - bank guarantee - injunction to restrain recourse to - when granted - interpretation of security clause - whether a mere security or also a risk allocation clause -whether entitlement to payment under contract required - allocation of risk pending determination of entitlement to payment - determination by superintendent of liquidated damages due to Principal - amount of determination paid to Principal by Contractor - Principal seeking recourse to security to obtain a further payment for liquidated damages in addition to those assessed
Orange Building Solutions Pty Ltd (ACN 167 079 781)
Orange Building Solutions Pty Ltd v Inkerman Property Group Pty Ltd (Building and Property) [2018] VCAT 696
"5.6 Conversion of security and recourse to retention monies
The principal may have recourse to security, retention monies or both and may convert into money all or part of the security that does not consist of money where the principal has become entitled to use the proceeds or the security in accordance with the terms of the contract.
The principal may use the proceeds of the security, retention monies or both in connection with any costs, expenses, losses or damages of any kind which the principal has incurred or claims that it has incurred or might in the future incur in connection with what the principal contends constitutes any act, default or omission of the contractor.
(a) the party has given the other party notice in writing, for the period stated in Annexure Part A of the party's intention to have recourse to the security, retention monies or both; and
(b) the period stated in Annexure Part A has or have elapsed since the notice was given".
The purpose of notice under this clause 5.6 is to give the contractor an opportunity to remedy the circumstances giving rise to the proposed recourse to the security. The contractor covenants with the principal and it will not institute any proceedings whatsoever or exercise any rights or take any steps whatsoever to enjoin the issuer of any security or the Principal from having recourse to the security or in any way seek to restrain the Principal from exercising its rights under this clause 5.6."
"5.6 Conversion of security and recourse to retention monies
The Principal may have recourse to security, retention monies or both and may convert into money a Security that does not consist of money where -
(a) the Principal has become entitled to exercise a right under the contract in respect of the security, retention monies or both;
(b) The Principal has given the other party notice in writing, for the period stated in Annexure Part A or, if no period is stated, five days of the party's intention to have recourse to the security, retention monies or both; and
(c) The period stated in Annexure Part A or, if no period is stated, five days, has or have elapsed since the notice was given".
"There are broadly two reasons why the beneficiary may have stipulated for a guarantee. One is to provide security. If it has a valid claim and there are difficulties about recovering from the party in default, it has recourse against the bank. The second reason, which is additional to the first, is to allocate the risk as to who shall be out of pocket pending resolution of a dispute. The beneficiary is then able to call upon the guarantee even if it turns out, in the end, that the other party was not in default ... It is a question of construction of the underlying contract whether the guarantee is provided solely by way of security or also as a risk allocation device. Remembering that we are speaking of guarantees in the sense of standby letters of credit, performance bonds, guarantees in lieu of retention monies and the like, the latter purpose is often present and commercial practice plays a large part in construing the contract. No implication may be made that is inconsistent with an agreed allocation of risk as to who shall be out of pocket pending resolution of a dispute and clauses in the contract that do not expressly inhibit the beneficiary from calling upon the security should not be too readily construed to have that effect."
"138 The principles, relating to the construction of security clauses in construction, and similar, contracts, have been discussed in a number of the authorities. They were helpfully outlined by the Full Court of the Federal Court in Clough Engineering (2008) 249 ALR 458. For present purposes, the principles may be stated as follows:
(1) Subject to three principal exceptions, a court will not enjoin a party from recourse to a performance guarantee. Those exceptions are:
(a) The court will enjoin a party in whose favour the guarantee has been given from acting fraudulently.
(b) The court will enjoin such a party from acting unconscionably in contravention of the Competition and Consumer Act 2010 (Cth).
(c) The court will restrain such a party from acting in breach of a contractual promise made by it not to call on the guarantee in particular circumstances (Ibid [77]; Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158, 164-5 (Austin J); Ceresola TLS AG v Thiess Pty Ltd & John Holland [2011] QSC 115 (Daubney J)).
(2) A recourse provision should be construed in light of all the other relevant provisions of the contract, including the terms of the security which formed part of the contract (Clough Engineering (2008) 249 ALR 458, 480 [85]; Fletcher Construction [1998] 3 VR 812, 828-9 (Callaway JA); Bachmann Pty Ltd v BHP Power New Zealand Ltd [1991] 1 VR 420, 435-7 (Brooking JA)).
(3) In construing any contractual limitation on the exercise by a party to have recourse to its rights to the security, the court should take into account the commercial purposes served by security clauses in construction contracts, and to which I have referred (Clough Engineering (2008) 249 ALR 458, 479).
(4) In particular, the commercial background for the contract informs the construction of a security clause, so that the court should not too readily favour a construction, which is inconsistent with an agreed allocation of risk as to who is to be out of pocket pending resolution of the dispute about breach (Clough Engineering (2008) 249 ALR 458, 479;Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812, 827 (Callaway JA); Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420, 436-7 [53] (Brooking JA)).
(5) Accordingly, clear words are required to support a construction that inhibits a beneficiary of a security clause from calling on a performance guarantee where a breach is alleged in good faith (that is, non-fraudulently)" (Clough Engineering (2008) 249 ALR 458, 480).
"A party shall not convert into money security that does not consist of money until the party becomes entitled to exercise a right under the contract in respect of the security. The party shall not be liable for any loss occasioned by conversion pursuant to the contract".
"The purchaser may deduct from monies otherwise due to the supplier any monies due from the supplier to the purchaser and if those monies are insufficient the purchaser can have recourse to the security under the contract."
"In the present case the matters of conversion of and recourse to the security are dealt with by two general conditions, which should if possible be construed so as to work in harmony. Clause 5.5 prohibits conversion into money until the purchaser becomes entitled to exercise a right under the contract in respect of the security. Clause 22.4 entitles the purchaser to deduct from moneys otherwise due to the supplier any moneys due from the supplier to the purchaser and, if those moneys are insufficient, entitles the purchaser to have recourse to the security. Like Clause 3.13(b) in Fletcher, it confers a right of recourse against the security to obtain the balance if the exercise of the right of set-off which it also confers leaves a balance outstanding in favour of the purchaser. It would, as Charles, J.A. said in Fletcher, be strange if the clauses concerned in that case and this - Clause 3.13(b) and Clause 22.4 - conferred the practical right of recourse only where moneys were "due" from the supplier to the purchaser in some such sense as actually or indisputably due. I would treat Clauses 5.5 and 22.4 of the present contract, read in conjunction, as entitling the purchaser, as between itself and the supplier, to have recourse to the security where according to a bona fide claim made by the purchaser moneys are due to it from the supplier which exceed any moneys due from it to the supplier."
"30. Brooking JA, in the passage from the Bachmann case which I have quoted, places some emphasis upon the reasoning of the Court of Appeal in the Fletcher Construction case. This case involved the construction of a contract very different from the present; it contained no comparable qualification upon the right to convert or to have recourse to the non-cash security. It does not appear to be a Standards Australia form of contract or, indeed, any of the standard forms then in use. Clause 3.13 in that case permitted the principal to have recourse to the security where the contractor was obliged to pay liquidated damages for late completion and where it failed to do so. In these circumstances, it is, with respect, scarcely surprising that counsel for the contractor was unable to persuade the court to infer in the contract a term which enabled the Contractor to prevent the principal from converting the security into money so as to give effect to cl. 3.13."
"3.3.3 The Company shall have the right under this guarantee to invoke the Banker's guarantee and claim the amount there under [sic] in the event of the Contractor failing to honour any of the commitments entered into under this Contract."
"Here, the terms of cl 3.3 of the contract, read with cl 2 of the guarantee, show that the commercial purpose of the contract was to allocate the risk of who should be out of pocket notwithstanding that there may be a genuine dispute as to whether Clough had failed to honour commitments under the contract. The risk was allocated to Clough, there being no clear words to inhibit ONGC as a beneficiary of the guarantee from invoking it: Fletcher Construction at [821] and [827]".
"34.2 Banker's Undertaking purpose and call down procedure
(a) The purpose of the Banker's Undertaking is to ensure payment due by the Company to the Contractor of all amounts due under this Document.
(b) Prior to being entitled to request payment of the Banker's Undertaking:
(i) the Contractor must be due a payment from the Company which remains unpaid and outstanding under the terms of this Document;
(ii) the Contractor must provide the Company with written notice asserting an amount is due and outstanding; and
(iii) 5 Business Days has passed since the Contractor's notice under clause 34.2(b)(iii) [sic (ii)] was received by the Company and the amount due and outstanding has not been paid." (my emphasis)
"16.2 If the contractor has not materially complied with its obligations under this contract, the principal may give a written notice to the contractor stating:
16.2.2 What the principal requires the contractor to do to remedy the breach.
16.2.3 A specific reasonable time in which the contractor must remedy the breach".
"37 The primary judge relied upon the decision in Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [No 3] [2007] FCA 2082 and, on appeal, at [2008] FCAFC 136; (2008) 249 ALR 458, in support of this view. In that case the Full Federal Court placed considerable weight upon the fact that the clause there under consideration required provision of a performance guarantee in the form of that set out in an appendix and that the form referred to the payment by the guarantor "notwithstanding any dispute(s) pending", without reference to the contractor and "without any demur, reservation, contest or protest" (249 ALR 458 at [30] and [88] - ...). Whilst the Clause pursuant to which the bonds were provided in the present case (Clause 6.1) refers to "unconditional undertakings" the Contract does not contain any wording such as was contained in the pro forma performance bond regarded in Clough as effectively qualifying the terms of the condition precedent stated in the relevant clause. Clough is accordingly distinguishable.
Security shall be subject to recourse by a party who remains unpaid after the time for payment where at least 5 days have elapsed since that party notified the other party of intention to have recourse."
"Any security provided by the Contractor in accordance with the Contract shall be available to the Principal whenever the Principal may claim (acting reasonably) to be entitled to:
(i) the payment of monies or an indemnity by the Contractor under or in consequence of or in connection with the Contract;
(ii) reimbursement of any monies paid to others under or in connection with the Contract; or
(iii) other monies payable by the Contractor to the Principal (whether by way of set off or otherwise).
Recourse to security shall only be subject to the Principal having given the Contractor five days' notice of its intention to have recourse to the security for the purpose of allowing the Contractor to replace the security with cash where it has been issued in a form other than cash. Where the Principal has recourse to security in accordance with clause 37.3, the Contractor shall provide replacement security in accordance with clause 37.3."
"120 In the present case, it is not suggested that the construction of GC 5.2 would involve or require evidence as to the factual matrix in which the contract was concluded.... The construction of clause 5.2 is a discrete question, which did not involve consideration of any detailed or complex material. The resolution of the application before the court was not urgent, as the respondent's rights had been protected by an interim injunction. While it was important that the judge deliver his decision expeditiously, nevertheless the judge did have some time to consider the issues raised by the parties before him."
"Security shall be subject to recourse by a party who remains unpaid after the time for payment where at least 5 days have elapsed since that party notified the other party of intention to have recourse."
"By cl 5.2 of the Subcontract in this case, the security was subject to recourse "where [the Principal] remains unpaid after the time for payment." On the ordinary meaning of those words, the precondition to recourse to the security was the fact of money being unpaid to the Principal. Clause 5.2 was not in terms which referred to a belief, or grounds for a belief, that money remained unpaid. Because recourse to the security was permitted only where in fact money remained unpaid, in my view it was necessarily implied that recourse was not permitted, and that the Principal should not attempt to have recourse to the security, where there was not money which remained unpaid to it. There was thereby a negative stipulation which could be the basis for an injunction restraining Forge from making demand on the bank guarantees."
"The implication that a security could be called upon merely where there was a claim in good faith could have no operation once the absence of merit in that claim was established."
"GC 35.3 (a) Contractor may have recourse to the Bank Guarantee(s) at any time in order to recover any amounts that are payable by Subcontractor to Contractor on demand.
(b) Subcontractor waives any right that it may have to obtain an injunction or any other remedy or right against any party in respect of Contractor having recourse to the Bank Guarantee(s).
(a) If Contractor calls on a Bank Guarantee or a Parent Company Guarantee at any time, the balance of the proceeds (if any) after deducting amounts due and payable to Contractor by Subcontractor must be deposited by Contractor into an interest bearing account with an Australian bank (as defined in the Corporations Act 2001 (Cth)) in the name of Contractor.
(b) Any interest accrued on the account balance must be retained by Contractor in the account and added to the balance of the proceeds held.
(c) Contractor is entitled to withdraw from the account amounts due and payable to it by Subcontractor from time to time."
"5.5 The Principal may make a demand on and use any security and/or retention moneys:
(a) to pay for any costs, expenses, loss or damage which the Principal claims it has incurred, or might in the future incur, as a consequence of any act or omission of the Contractor which the Principal asserts constitutes a breach of the Contract by the Contractor;
(b) to satisfy any amount which the Principal asserts is payable by the Contractor pursuant to the Contract;
(i) a termination of the Contract, except where the Contract is terminated by the Principal under Clause 45A; or
(ii) an event described in Clause 44.11 affecting the Contractor; or
"93 However, Clause 5.5 qualifies the Principal's claims by providing that the subject claims are claims for cost, expense, loss or damage incurred or which might be incurred in the future as a consequence of any act or omission of the Contractor which the Principal asserts constitutes a breach of the Contract by the Contractor. The parties' express requirement that the Principal's entitlement to recourse need only be triggered by such "claims" by the Principal, and which the Principal "asserts constitute a breach of the Contract by the Contractor" clearly reflects the parties' intent that the Principal may access the security without having to establish any relevant breach of Contract by the Contractor or the existence of any relevant extant contractual claim or entitlement in the Principal.
Security shall be provided in accordance with Item 14 or 15. All delivered security_,_ other than cash or retention moneys, shall be transferred in escrow.
Security shall be subject to recourse by a party who remains unpaid after the time for payment where at least 5 days have elapsed since that party notified the other party of intention to have recourse.
Within 14 days of the date of practical completion, the Principal will release and return letter of credit 1 (see item 14) to the Contractor.
Upon payment of any amount of the Lump Sum Amount to the Contractor, the Contractor's entitlement to security shall be reduced by the percentage or amount In Item l5(d) and the reduction shall be released and returned within 14 days to the Principal.
A party's entitlement otherwise to security shall cease 14 days after final certificate. Upon a party's entitlement to security ceasing, that party shall release and return forthwith the security to the other party."
The Principal may set-off any amount due and payable by the Contractor to the Principal against any amount that the Principal owes the Contractor under the Contract.
If the moneys payable to the Contractor are insufficient to discharge the liability of the Contractor to pay such sum to the Principal, the Principal may have recourse to the security provided by the Contractor.
Where, within the time provided by the Contract, the Contractor fails to pay the Principal an amount due and payable under the Contract, the Principal may have recourse to security under the Contract and any deficiency remaining may be recovered by the Principal as a debt due and payable from the Contractor to the Principal."
"105 The first question, then, is whether the contract contained a relevant qualification or restriction on the right of the respondent to have recourse to the guarantee. In my view, it is plain that the contract does contain such a qualification. Apart from cl 39.7 and cl 39.9, which do not apply in this case, the only other provision, contained in the contract, entitling the respondent to have recourse to the security, is cl 5.2. That clause contained the express prescription that recourse is permitted where a party 'remains unpaid after the time of payment'. That requirement constituted a contractual qualification on the respondent's powers in relation to the exercise of the security. In terms of the authorities, it was an implied negative stipulation in the contract that the respondent would not invoke recourse to the security in the absence of there being an account 'unpaid' by the applicant to the respondent 'after the time for payment'."
"134 The foregoing analysis of the judgment of Brooking JA, in Bachmann, reveals that there were three important factors which distinguish the contract in Bachmann from the contract in the present case.
"Liquidated damages for delay in reaching practical completion
If the contractor fails to reach Practical Completion by the Date for Practical Completion, the contractor shall be indebted to the principal for liquidated damages at the rate stated in Annexure Part A for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated pursuant to Clause 44, whichever first occurs.
The Principal may recover liquidated damages progressively following the Date for Practical Completion:
(a) on demand from the Contractor; or
- (b) by deducting such amount from any amount certified by the Superintendent under Clause 42.1 or from any security held under clause 5,
notwithstanding that Practical Completion has not occurred."
"The rights and liabilities of parties under a provision of a contract are determined objectively, by reference to its text, context (the entire text of the contract as well as any contract, document or statutory provision referred to in the text of the contract) and purpose.
In determining the meaning of the terms of a commercial contract, it is necessary to ask what a reasonable businessperson would have understood those terms to mean. That inquiry will require consideration of the language used by the parties in the contract, the circumstances addressed by the contract and the commercial purpose or objects to be secured by the contract.
Ordinarily, this process of construction is possible by reference to the contract alone. Indeed, if an expression in a contract is unambiguous or susceptible of only one meaning, evidence of surrounding circumstances (events, circumstances and things external to the contract) cannot be adduced to contradict its plain meaning.
However, sometimes, recourse to events, circumstances and things external to the contract is necessary. ..."
Without limiting the Principal's other rights and remedies under the Contract or otherwise, the principal may at any time and from time to time deduct from monies otherwise due to the contractor (including from an amount certified in a payment certificate) any money due from the contractor to the principal (including liquidated damages under clause 35.6) whether under the contract or otherwise and if those monies are insufficient, the principal may, subject to clause 5.6, have recourse to retention monies and, if they are insufficient, then to security under the Contract."
Where, within the time provided by the contract, a party fails to pay the other party an amount due and payable under the contract, the other party may, subject to 5.6, have recourse to retention monies, if any, and, if those monies are insufficient, then to security under the contract and any deficiency remaining may be recovered by the other party as a debt due and payable."
"147 Although, as mentioned, the application before the judge was for an interlocutory injunction, I have reached a concluded view as to the correct construction of the contract between the parties. In those circumstances, the question of which side is favoured by the balance of convenience has become irrelevant. In the course of submissions, counsel for each side accepted that if this Court were to reach a concluded view as to the meaning of the contract, as I have, then, logically, the issue of balance of convenience is otiose."
Orange Building Solutions Pty Ltd
Inkerman Property Group Pty Ltd
(2008) 249 ALR 458
(2015) 256 CLR 104