85 Mr Saad and Ms Constantine claimed $32,272 for the construction of new gates at the front of their property. This claim related to the full cost of these works. However, the RTA had constructed part of the works sought by Mr Saad and Ms Constantine and, insofar as they went, these works were to their satisfaction. However, the gates and associated electronic equipment have not yet been installed and the RTA subsequently unilaterally deleted an additional column and extension of the wall from the works, which Mr Saad considered representatives of the RTA had agreed would be constructed. Mr Jones on behalf of the RTA agreed that the extended wall and additional column had been shown on the sketch plan submitted to Mr Saad, but did not accept that any binding agreement had been reached about the extent of the works. The RTA had subsequently instructed the contractors to delete the additional column and extension of the wall from the works on Mr Saad's property, apparently on the ground that they would extend into the road reserve (possibly in anticipation of the foreshadowed second acquisition). I am not satisfied on the evidence that this claim, insofar as it relates to the additional column and wall extension, falls within any statutory head of compensation. In particular, I do not accept that Mr Saad and Ms Constantine might reasonably incur some cost relating to those works as a direct and natural consequence of the acquisition. I am also not satisfied that I can make any meaningful adjustment to the claim of $32,272 when so much of the work has been completed, the RTA has indicated its preparedness to complete the work that it is in the middle of carrying out, and Mr Saad and Ms Constantine have no complaint about the quality of the work to date. In the particular circumstances of these proceedings, I propose to reserve the position of the parties with respect to the completion of the works associated with the gates identified in Exhibit 22 (Mr Jones' affidavit), excluding any claim relating to the additional column and wall extension to the current boundary, which I do not accept.