; Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2005] NSWCA 49; (2005) 62 NSWLR 385; 3D Flow Solutions Pty Ltd v LTP Armstrong Creek Pty Ltd [2018] VCC 674; SJ Higgins v The Bays Healthcare Group Inc [2018] VCC 805; Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd [1992] HCA 66; (1992) 110 ALR 449; John Beever v Roads Corporation [2018] VSC 635; Best Fab Pty Ltd v Australian High Bay Installations Pty Ltd [2018] VCC 1053; Shaw v Yarranova Pty Ltd [2006] VSCA 291; (2006) 15 VR 289; Mirvac (Docklands) Pty Ltd v Philp [2004] VSC 301 ; ; ; ; ; ;
(a) Building Principals would provide services to Chapter 03 (set out under the heading titled "Scope of Services") including:
(i) pre-construction consulting services (including design management, program sequencing and builder appointment);
(ii) project management and superintendent services during the construction phase; and
(iii) assistance with managing the defects liability period and contract administration after practical completion;
(b) Chapter 03 would pay for Building Principals' services (tabulated under the heading titled "Fee") as follows:
(i) $3,300.00 (excluding GST) per week for pre-construction design management, for an estimate of eight weeks;
(ii) $6,000.00 (excluding GST) for the appointment of a builder;
(iii) $7,850.00 (excluding GST) per month during the construction phase (comprising project management and superintendent services); and
(iv) $11,775.00 (excluding GST) as a total twelve month fee for managing the defects liability period;
(c) Chapter 03 would pay all fees within 30 days of receiving a tax invoice from Building Principals (pursuant to clause 4.2(b) of the "Terms and Conditions" of the Contract);
(d) either party may terminate the Contract by giving ten business days' notice of a breach (pursuant to clause 13(a)(i) of the "Terms and Conditions" of the Contract); and
(e) the Contract is governed by the laws of Victoria (pursuant to clause 14.12 of the "Terms and Conditions" of the Contract).
(a) prior to the construction works commencing, design management and builder appointment services between May 2023 and August 2023;
(b) following the commencement of the construction works, project management services between August 2023 and November 2024. These services involved, but were not limited to:
(i) monitoring the contractor's OHSE management to ensure that health and safety requirements were complied with whilst the construction works were undertaken;
(ii) reviews of the construction works' progress against the agreed construction program and the contractor's project cashflow; and
(iii) site inspections to review the construction works' general compliance with project documents.
(a) 31 May 2023 (INV 0019), in the sum of $7,260.00;
(b) 30 June 2023 (INV 0025), in the sum of $10,890.00;
(c) 31 July 2023 (INV 0045), in the sum of $3,630.00;
(d) 31 July 2023 (INV 0046), in the sum of $3,300.00;
(e) 31 August 2023 (INV 0056), in the sum of $8,635.00;
(f) 31 August 2023 (INV 0057), in the sum of $3,300.00;
(g) 30 September 2023 (INV 0074), in the sum of $8,635.00;
(h) 30 September 2023 (INV 0075), in the sum of $7,700.00;
(i) 31 October 2023 (INV 0096), in the sum of $8,635.00;
(j) 30 November 2023 (INV 0111), in the sum of $8,635.00;
(k) 21 December 2023 (INV 0125), in the sum of $8,635.00;
(l) 31 January 2024 (INV 0144), in the sum of $8,635.00;
(m) 29 February 2024 (INV 0171), in the sum of $8,635.00;
(n) 22 June 2024 (INV 0232), in the sum of $8,635.00;
(o) 31 July 2024 (INV 0250), in the sum of $8,635.00;
(p) 31 August 2024 (INV 0265), in the sum of $8,635.00;
(q) 16 September 2024 (INV 0272), in the sum of $8,635.00;
(r) 16 September 2024 (INV 0273), in the sum of $8,635.00; and
(s) 30 November 2024 (INV 0308), in the sum of $8,635.00.
(a) must be in the prescribed form (if any) and contain the prescribed information (if any) - neither is prescribed;
(b) must identify the construction work or related goods and services to which it relates;
(c) must indicate the amount of progress payment that the claimant claims to be due;
(d) must state that it is made under the SOP Act; and
(e) must not include any "excluded amounts" pursuant s10(3).
(a) the period determined in accordance with the construction contract "in respect of the carrying out of the item of construction work or the supply of the item of related goods and services to which the claim relates"; or
(b) the period of three months after the "reference date referred to in s9(2) that relates to th[e] progress payment".
(a) a date on which a claim for a progress payment may be made; or
(b) a date by reference to which the amount of a progress payment is to be calculated -
in relation to a specific item of construction work "carried out or to be carried out" or a specific item of related goods and services "supplied or to be supplied" under the contract. The rest of s9 concerns situations where the contract makes no express provision for reference dates.
(a) does not relate to a "construction contract" (including because it does not involve carrying out "construction work"), or it relates to a "construction contract" excluded from the operation of the SOP Act under s7 (for example, a construction contract that forms part of a loan agreement or one that is a domestic building contract under the Domestic Building Contracts Act 1995 (Vic) ("the DBC Act"));
(b) fails to satisfy the formal requirements of s14(2) (for example, by failing to identify the construction work or failing to state that the claim is made under the SOP Act);
(c) was made when no valid reference date existed,[5] including where it is served before an applicable reference date or relies on a reference date that has already been used up by an earlier payment claim;[6]
(d) includes variations that are "excluded amounts" under s10B; and
(e) was not validly served on the respondent under either the terms of the contract or under s50.
(a) applies "to any construction contract, whether written or oral, or partly written and partly oral, and so applies even if the contract is expressed to be governed by the law of a jurisdiction other than Victoria" (s7(1)); but
(b) does not apply to "a construction contract which is a domestic building contract within the meaning of the Domestic Building Contracts Act 1995 between a builder and a building owner (within the meaning of that Act), for the carrying out of domestic building work (within the meaning of that Act), other than a contract where the building owner is in the business of building residences and the contract is entered into in the course of, or in connection with, that business" (s7(2)(b)). (emphasis added).
(a) Base stage: 10% of contract price;
(b) Frame stage: 15% of contract price;
(c) Lock up stage: 35% of contract price; and
(d) Fixing stage: 25% of contract price.
"The plaintiff is an electrical contractor. The defendant is a developer and builder. The plaintiff was engaged to carry out electrical works at a multi residential unit development ...
Although the building works were to construct a domestic building, there is no dispute that the [SOP] Act applies, as the defendant is a special purpose entity that was effectively the developer for the project and was 'in the business of building residences'".
"...if the contract makes no express provision with respect to the matter, the date occurring 20 business days after the previous reference date or (in the case of the first reference date) the date occurring 20 business days after -
(i) construction work was first carried out under the contract; or
(ii) related goods and services were first supplied under the contract."
(a) had expired under s9(2)(d)(iii)(A) of the SOP Act; or
(b) had not yet accrued.
"[A] statutory payment claim served before the relevant reference date is not served 'on or from' that reference date for the purpose of the NSW SOP Act, the effect being that the phrase 'on or from' when properly construed, is to be understood as meaning 'on or after' the relevant reference date."[23]
"In my view ... it is sufficiently clear in light of Southern Han and All Seasons that s 9 and s 14 of the SoP Act (Vic) do not operate so as to permit the valid service of a payment claim prior to the relevant reference date which itself establishes a valid foundation for that payment claim to be made under the _SoP A_ct (Vic) ...". (references omitted)[24]
I certify that these 21 pages are a true copy of the judgment of Her Honour Judge Burchell delivered on 8 September 2025.
[3] [2016] HCA 52; (2016) 260 CLR 340 at [44] ("Southern Han").
[5] Southern Han at [61]-[62]; Vanguard Developments v Promax [2018] VSC 386 at [121] per Kennedy J.
[7] Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & Anor [2009] VSC 156; (2009) 26 VR 112 at [2] and [43]-[46] per Vickery J ("Hickory Developments"), cited with approval in Pearl Hill Pty Ltd v Concorp Construction Group (Vic) Pty Ltd [2011] VSCA 99 at [11].
[8] Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2005] NSWCA 49; (2005) 62 NSWLR 385 at [22] per Handley JA, with whom Santow JA and Pearlman AJA agreed.
[9] Hickory Developments at [2] and [43]-[46].
[10] 3D Flow Solutions Pty Ltd v LTP Armstrong Creek Pty Ltd [2018] VCC 674 at [39]-[54] ("3D Flow Solutions"). See also SJ Higgins v The Bays Healthcare Group Inc [2018] VCC 805 at [26] ("SJ Higgins").
[11] Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd [1992] HCA 66; (1992) 110 ALR 449 at 449-450 per Mason CJ, Brennan, Deane and Gaudron JJ.
[12] 3D Flow Solutions at [51]-[54].
[13] John Beever v Roads Corporation [2018] VSC 635. See also Best Fab Pty Ltd v Australian High Bay Installations Pty Ltd [2018] VCC 1053.
[15] [2006] VSCA 291; (2006) 15 VR 289 at [85] ("Shaw v Yarranova").
[17] (2021) 65 VR 117 at [64].
[18] Cameron & Anor v Stephens [2021] VCC 127.
[19] [2017] VSCA 168 ("Imerva").
[20] [2021] VCC 784 at [53] ("Diako").
[21] [2025] VCC 399 at [1] and [2] ("Spentek Electrical").
[23] [2017] NSWCA 289 at [14].
[24] [2019] VSC 436 at [60].
Building Principals Pty Ltd
Chapter 03 Pty Ltd [2025] VCC 1294
(2016) 260 CLR 340
(2009) 26 VR 112
(2005) 62 NSWLR 385
(1992) 110 ALR 449
(2006) 15 VR 289
(2021) 65 VR 117