[2025] VCC 399
General information, not legal advice.
County Court of Victoria
2025-04-07
Original judgment source is linked above.
(a) Payment claim 12, comprising invoice 21130 submitted on 28 March 2023 with a claimed amount of $61,603.71 (PC 12). The defendant paid the sum of $40,000.00 for PC 12 on 12 May 2023, and the plaintiff claims the balance of $21,603.71;
(b) Payment claim 17, comprising invoice 21161 submitted on 8 October 2023 with a claimed amount of $74,255.68 (PC 17). The plaintiff has not received any payment in relation to PC 17; and
(c) Payment claim 18, comprising invoice 21163 submitted on 28 November 2023 with a claimed amount of $20,233.06 (PC 18). The plaintiff's evidence appears to be that has not received any payment in relation to PC 18 (see discussion at paragraph 28 below).
(a) the existence of a construction contract for the progress payment;
(b) the existence of a reference date for the progress payment;
(c) a valid payment claim for the progress payment;
(d) no payment schedule having been given; and
(e) that the respondent has failed to pay the whole or part of the claimed amount.
(a) does not relate to a "construction contract" (including because it does not involve carrying out "construction work"), or it relates to a construction contract excluded from the operation of the Act under s 7 (for example, a construction contract that forms part of a loan agreement, or one that is a domestic building contract under the Domestic Building Contracts Act 1995);
(b) fails to satisfy the formal requirements of s14(2) of the Act (for example, by failing to identify the construction work, or failing to state that the claim is made under the SOP Act);
(c) was made when no valid reference date existed, including where it is served before an applicable reference date, or relies on a reference date that has already been used up by an earlier payment claim;
(d) includes variations that are "excluded amounts" under s 10B of the Act;
(e) was not validly served on the respondent under either the terms of the contract, or under s 50 of the Act; and
(f) in rare circumstances, where a defendant alleges that they are not party to, or are not liable under the contract.[3]
(a) In respect of PC 12, it concedes an amount of $21,603.71 remains outstanding.
(b) In respect of PC 17, the defendant says the claim was submitted out of time on 8 October 2023, that is not being on or before the 28th day of the previous month, and accordingly, no payment is due.
(c) In respect of PC 18, the defendant provided an email response on 28 December 2023 with an attached payment schedule, which states that the plaintiff is entitled to a credit in relation to PC 18 of $13,474.71.
Has the plaintiff satisfied the requirements of s 16?
Is there a construction contract for the progress payments?
Is there a reference date/s for the progress payments?
The Trade Contractor shall claim payment progressively in accordance with Item 28 and in any event no later than 3 months after the relevant 'reference date' as that term is defined in section 9 of the Security of Payment Act.
An early payment claim shall be deemed to have been made on the date for making the claim in accordance with subclause 37.1(b).
Times for progress claims: 28th day of each month for work done to the end of the month...
Was there a valid payment claim/s for the progress payments?
Has the respondent failed to pay the whole or part of the claimed amount?
Interest is payable on the unpaid amount of a progress payment that has become due and payable in accordance with subsection (1) at the greater of the following rates -
(a) the rate for the time being fixed under section 2 of the Penalty Interest Rates Act 1983; or
(b) the rate specified under the construction contract.
(a) PC 12, dated 28 March 2023, due 30 April 2023;
(b) PC 17, dated 28 September 2023, due 30 October 2023; and
(c) PC 18, dated 28 November 2023, due 30 December 2023.
...an applicant for a stay must demonstrate the existence of special or exceptional circumstances. Special circumstances may exist where there is a real risk that an appeal, if successful, would be rendered nugatory in the absence of the grant of a stay. In such a case, the Court will be required to balance the prospect that an appeal may be rendered nugatory in the absence of a stay, against the principle that the successful party in the proceeding should be entitled to the fruits of the judgment. Further, a stay should not be granted unless the applicant has demonstrated at least an arguable ground of appeal.
(a) the starting presumption is that successful litigant is entitled to the fruits of judgment in the absence of "special or exceptional circumstances;"
(b) the threshold for a stay under the Act is higher than an ordinary judgment - there must be "more than a 'real risk" (as opposed to the ordinary standard of a "real risk") that rights to recover amounts paid under the Act would be rendered nugatory before a stay would be ordered;
(c) given the "pay now, fight later" policy behind the Act, the legislature has imposed on the paying party the risk that the receiving party might not be able to refund money which is paid under the Act. The Court ought not reverse that allocation of risk lightly.
I accept that, given the public policy of the SOP Act and following the NSW lines of authority, [the paying party] is required to establish that there is more than a real risk that [the receiving party] might not be able to refund moneys such that [the paying party's] rights would be rendered nugatory in the absence of a stay.
(a) By 14 April 2025 at 4.00pm the plaintiff must file and serve a breakdown of the calculation of $72,384.68, by reference to each of PC 12, PC 17 and PC 18. If further evidence is relied on, it must be provided in an affidavit.
(b) By 14 April 2025 at 4.00pm the plaintiff must file and serve the amounts of interest claimed, calculated in accordance with these Reasons.
(c) By 21 April 2025 the defendant must file and serve any submissions or affidavits in reply.
(d) By 28 April 2025 at 4.00pm the parties must have consulted and must file proposed orders (preferably by consent, or if not agreed, each party's proposed orders) for the future conduct of the first proceeding, CI-24-00723.
I certify that these 14 pages are a true copy of the judgment of her Honour Judge Kirton delivered on 7 April 2025.
[1] Building and Construction Industry Security of Payment Act 2002 (Vic) s 7(2)(b) (the 'Act' or 'SOP Act').
[2] Defendant's Outline of Submissions dated 20 June 2024 and 22 July 2024.
[3] Diamond Builders Pty Ltd v Gilridge Investments Pty Ltd [2023] VCC 1527, 7 - 9 [38] - [40], citing Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340, [44], [61]-[62].
[4] Affidavit of Stephen Spencer, dated 8 May 2024, 1 [4] ('First Spencer Affidavit').
[6] Ibid, Exhibit SS-1, Part A, Annexure, 57, [item 28]. .)
[7] Affidavit of Joseph Princi, dated 11 June 2024, 3 [14] ('Princi Affidavit').
[8] Affidavit of Stephen Spencer, dated11 June 2024, 4 [15(c)], [18(c)], Exhibit SS-10 ('Second Spencer Affidavit').
[9] First Spencer Affidavit (n 4), Exhibit SS-1, 39 [cl 37.1].
[10] Ibid, Exhibit SS-1, Part A, Annexure, 57 [item 28].
[11] Second Spencer Affidavit (n 8), 4 [15(d)], [18(d)], Exhibit SS-11.
[12] Princi Affidavit (n 7), Exhibit JP-1, 46 - 48.
[13] First Spencer Affidavit (n 4), 1 [5]; Exhibit SS-1, 40, [cl 37.2].
[14] Defendant's Outline of Submissions dated 22 July 2024 [8].
[15] First Spencer affidavit (n 4), Exhibit SS-2, 113; Second Spencer Affidavit (n 8), 5 [23].
[16] [2020] VSCA 269, 7 [23].
[17] [2023] VCC 2418, 5-7 [17] - [24] (citations omitted).
Spentek Electrical Pty Ltd
487 Whitehorse Road Pty Ltd [2025] VCC 399
(2016) 260 CLR 340