[2023] VCC 1527
General information, not legal advice.
County Court of Victoria
2023-08-31
Original judgment source is linked above.
9](/cgi-bin/LawCite?cit=%281992%29%20110%20ALR%20449 "View LawCiteRecord"); TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93; MPA Construction Pty Ltd v Profine Construction Pty Ltd [2020] VCC 1035; Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172; Plaza West Pty Ltd v Simon's Earthworks (NSW) Pty Ltd & Anor [2008] NSWCA 279; BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd [2012] QSC 214; Yuanda Vic Pty Ltd v Facade Designs International Pty Ltd [2021] VSCA 44; Hanson Construction Materials Pty Ltd v Brolton Group Pty Ltd [2019] NSWSC 1641; The Trustee for Allway Unit Trust Trading as Westside Mechanical Contracting Pty Ltd v R&D Airconditioning Pty Ltd [2018] SASC 46; ;
(a) No reference date has been identified by Diamond, and due to contractual breach, no reference date has accrued under s9 of the SOP Act;
(b) That a due date has not arisen pursuant to s12 of the SOP Act because certain contractual preconditions have not been complied with;
(c) Diamond has failed to establish that the payment claim does not include excluded amounts as per s10B of the SOP Act; and
(d) That it submitted a payment schedule.
(a) Gilridge is the principal;
(b) The stated contract sum in the contract is $5,355,547.00 (including GST);
(c) Fordev Pty Ltd is the current superintendent under the Contract ("Superintendent");
(d) Diamond commenced the works under the Contract on the site, in or around December 2020;
(e) The time for payment claims is the 25th day of each month.
(a) Diamond had wrongfully suspended the works, was suspension as only permitted under clause 44.9 of the Contract or as directed or approved by the superintendent;
(b) Diamond had delayed progress by failing to obtain all the required building permits;
(c) Diamond had not executed its works to the standard of workmanship required by the Contract;
(d) Diamond failed to satisfy certain legislative requirements;
(e) Diamond had not installed compliant fire screens;
(f) Diamon had wrongfully suspended works leading to under delay.
(a) "construction contract" is a contract or other arrangement under which one party undertakes to carry out construction work, or to supply related goods and services for another party;[3]
(b) "construction work" is defined under s5;
(c) "related goods and services" is defined under s6.
(a) must be in the prescribed form (if any) and contain the prescribed information (if any) - neither is prescribed;
(b) must identify the construction work or related goods and services to which it relates;
(c) must indicate the amount of progress payment that the claimant claims to be due;
(d) must state that it is made under the SOP Act; and
(e) must not include any "excluded amounts" (being amounts referable to particular categories of variations).
(a) the period determined in accordance with the construction contract "in respect of the carrying out of the item of construction work or the supply of the item of related goods and services to which the claim relates"; or
(b) the period of 3 months after the "reference date referred to in s9(2) that relates to the progress payment".
(a) a date on which a claim for a progress payment may be made; or
(b) a date by reference to which the amount of a progress payment is to be calculated,
(c) in relation to a specific item of construction work "carried out or to be carried out" or a specific item of related goods and services "supplied or to be supplied" under the contract.
(a) does not relate to a "construction contract" (including because it does not involve carrying out "construction work"), or it relates to a construction contract excluded from the operation of the Act under s7 (for example, a construction contract that forms part of a loan agreement, or one that is a domestic building contract under the Domestic Building Contracts Act 1995);
(b) fails to satisfy the formal requirements of s14(2) (for example, by failing to identify the construction work or failing to state that it is made under the SOP Act);
(c) was made when no valid reference date existed,[6] including where it is served before an applicable reference date or relies on a reference date that has already been used up by an earlier payment claim;[7]
(d) includes variations that are "excluded amounts" under s10B; and
(e) was not validly served on the respondent under either the terms of the contract or under s50.
"It is also true that the 'failure' to identify any particular reference date in the payment claim did not invalidate that payment claim. While the existence of an available reference date is a precondition to a valid payment claim, the identification of the reference date in the payment claim is not". [footnote omitted]
"The suspension of payment was a suspension of the totality of the rights conferred and obligations imposed in relation to payment by cl 37. The rights so suspended included Lewence's right to make a progress claim under cl 37 for work carried out up to the time of the work being taken out of its hands".
"It is settled law that after the valid service of a take out notice, the contractor's rights are thereafter suspended, including the right to claim progress payments under cl 37, which in turn has the result that the statutory entitlement under s 8 will thereafter no longer arise. Westbourne Grammar School is to the same effect...It cannot be the case that a statutory entitlement to make a progress claim, which Trinity undoubtedly enjoyed on, say, 1 September 2019, ceased or was modified or extinguished after 3 September 2019 by dint of Parrwood exercising some right under the contract. That would invert the relationship between statute and contract... Parrwood sought to say, in various ways, that the reference date of 25 August 2019 became invalid, or ineffective, following the service of the take out notice. Purely as a matter of contract, two parties may as between themselves agree to proceed on a particular and even counterfactual basis. But the obstacle confronting this submission is the effect of statute. After 25 August 2019, not only had Parrwood and Trinity as a matter of contract agreed that that date was a date on which Trinity could make a payment claim. Section 8 applied then and there and gave Trinity a statutory entitlement to invoke the procedures under the Act. Nothing in the contract, and no exercise of powers under the contract thereafter could alter or modify, let alone extinguish, the rights created by statute on 25 August 2019".
"there is no requirement in the Act for payment claims to be accompanied by such a declaration. The applicant's payment claims in this matter are therefore not invalid in the absence of a declaration under clause 7(d)(iii)".
"...the interpretation which best accords with the policy of the Act should be preferred. In our opinion, that is the more limited construction on which the primary judge relied. The enforcement process is not intended to be an inquiry into the merits of the claim. That is obvious from the prohibition on the respondent advancing a cross-claim or raising a defence. It is also apparent more generally from the 'pay now, argue later' scheme of the Act as a whole and, within that scheme, the provision for adjudication (and adjudication review) in respect of disputed excluded amounts. An interpretation which gives the Court a limited role is to be encouraged as consistent with the Act's preference for adjudication to resolve disputes about the contents of a payment claim".
"The structure, intent and purpose of the Act and the procedure for payment and objections to payment in relation to excluded amounts are predicated on a relatively quick summary procedure for allocation of risk pending any final determination. A full investigation of alleged excluded amount or the suggested digging exercise are entirely contrary to the intended purpose. Rather, it is up to the respondent to identify, in the manner provided for, the excluded amount and set in train the adjudication process. If the respondent fails to do so, it is not open to the respondent to later contest and request a full investigation or digging exercise (a suggested lesser review) in relation to an alleged excluded amount that it should have raised earlier, particularly in circumstances where the enquiry is not directed to a final determination of the rights of the parties, but rather what interim accommodation is appropriate and indeed required based on a face of the claim consideration".
Other arguments raised under the payment schedule
Compliance with formal requirements of s14 of the SOP Act
(a) was issued on Gilridge, and indicated the amount for construction work due (discussed above);
(b) adequately identified the works to which the payment claim related;
(c) stated that it was made under the SOP Act;
(d) had a valid reference date (discussed above); and
(e) was validly served on Gilridge (discussed above).
I certify that these 28 pages are a true copy of the judgment of her Honour Judge Burchell delivered on 31 August 2023.
[4] Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340 at [44].
[6] Ibidat [61]-[62]; Vanguard Developments v Promax [2018] VSC 386 per Kennedy J at [121].
[8] Shells Venture Management v Agresta [2019] VSC 863.
[9] Baron Forge Contractors Pty Ltd v Vaughan Constructions Pty Ltd [2015] VCC 1424.
[10] Grave v Blazevic Holdings Pty Ltd [2010] NSWCA 324; (2010) 79 NSWLR 132.
[11] Collective Crane Hire Pty Ltd v ICR Steel Pty Ltd [2021] VCC 132.
[12] 3D Flow Solutions Pty Ltd v LTP Armstrong Creek Pty Ltd [2018] VCC 674.
[13] Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & Anor [2009] VSC 156; (2009) 26 VR 112 at [2] and [43]-[46] per Vickery J, cited with approval in Pearl Hill Pty Ltd v Concorp Construction Group (Vic) Pty Ltd [2011] VSCA 99 at [11].
[14] Falgat Constructions Pty Ltd v Equity Australia Corp Pty Ltd [2005] NSWCA 49; (2005) 62 NSWLR 385 at [22] per Handley JA, with whom Santow JA and Pearlman AJA agreed.
[15] Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & Anor [2009] VSC 156; (2009) 26 VR 112 at [2] and [43]-[46].
[16] 3D Flow at [39]- [54]. See also SJ Higgins v The Bays Healthcare Group Inc [2018] VCC 805 at [26].
[17] Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd [1992] HCA 66; (1992) 110 ALR 449, 449-450 per Mason CJ, Brennan, Deane and Gaudron JJ.
[19] The Trustee for Allway Unit Trust Trading as Westside Mechanical Contracting Pty Ltd v R&D Airconditioning Pty Ltd [2018] SASC 46.
[20] TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93 at [27].
[21] MPA Construction Pty Ltd v Profine Construction Pty Ltd [2020] VCC 1035.
[23] Hanson Construction Materials Pty Ltd v Brolton Group Pty Ltd [2019] NSWSC 1641 at [32].
[25] Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172 at [31]- [32].
[26] Plaza West Pty Ltd v Simon's Earthworks (NSW) Pty Ltd & Anor [2008] NSWCA 279 [2008] NSWCA 279 at [8].
[27] BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd [2012] QSC 214 [2012] QSC 214 at [17].
[28] Yuanda Vic Pty Ltd v Facade Designs International Pty Ltd [2021] VSCA 44.
[32] John Beever (Aust) Pty Limited v Paper Australia Pty Ltd [2019] VSC 126 at [83].
[33] See, for instance, Cidec Pty Ltd v Citi-Con Pty Ltd34 and Seabay v Galvin [2011] VSC183 at [139]-[149].
Diamond Builders Pty Ltd
Gilridge Investments Pty Ltd [2023] VCC 1527
(2016) 260 CLR 340
(2010) 79 NSWLR 132
(2009) 26 VR 112
(2005) 62 NSWLR 385
(1992) 110 ALR 449