[2019] VSC 436
Supreme Court of Victoria
2019-09-24
Digby J
Original judgment source is linked above.
ADMINISTRATIVE LAW - Judicial review - Relief in the nature of certiorari - Whether Adjudication Determination is vitiated by jurisdictional error as a result of a payment claim not served 'on and from' the relevant reference date - Whether an Adjudication Determination is vitiated by jurisdictional error as a result of a failure to determine that a payment claim was made because it was the second payment claim within the one reference date - Adjudication Determination quashed as it was not served on and from the relevant reference date - Building and Construction Industry Security of Payment Act 2002 (Vic), ss 9(1), 9(2)(a), 14(1), (8), .
(a) Ground 1
The Adjudicator committed jurisdictional error, alternatively acted ultra vires or erred in law, in determining that the payment claim served by the first defendant, Carelli Constructions Pty Ltd, on or about 21 December 2018 (December Payment Claim) was valid in circumstances where it was not served 'on and from' the relevant 'reference date'; and
(b) Ground 2
Further, and in the alternative, the Adjudicator committed jurisdictional error, alternatively acted ultra vires or erred in law, in failing to determine that the December Payment Claim was in breach of s 14(8) of the Building and Construction Industry Security of Payment Act 2002 (Vic) (SoP Act (Vic)) in circumstances where it was the second payment claim within the one reference date as prohibited by that provision.
(a) to restrain Carelli Constructions Pty Ltd (first defendant), whether by itself, its servants, or otherwise howsoever from seeking to enforce or take action under the SoP Act (Vic) in relation to the Adjudication Determination;
(b) to restrain the Adjudicator whether by himself, his servants or otherwise howsoever from providing an Adjudication Certificate pursuant to s 28Q of the SoP Act (Vic) in respect of the Adjudication Determination;
(c) a declaration that the Adjudication Determination is unlawful and void; and
(d) an order in the nature of certiorari quashing the Adjudication Determination.
3 In addition to written and oral submissions, the plaintiff relies upon the Affidavit of Paul Graham sworn 27 February 2019, and exhibits thereto.[3]
4 The key non-controversial factual circumstances giving rise to the proceeding are as follows:
(a) on or about 12 December 2017, the plaintiff entered into a written contract with the first defendant to carry out the design and construction of a 17 apartment complex, including a basement, at 780 Whitehorse Road, Mont Albert, in the State of Victoria, for the contract sum of $3,598,000 plus GST (Construction Contract);[4]
(b) pursuant to cl 37.1 and item 33 of Annexure Part A of the Construction Contract, the reference date for making payment claims pursuant to s 9 of the SoP Act (Vic) was nominated as the 25th day of each month;
(c) on 26 November 2018, the first defendant served a payment claim on the plaintiff in the amount of $39,087.48 (including GST);[5]
(d) on 21 December 2018, the first defendant served a payment claim on the plaintiff in the amount of $411,358.36 (including GST) (December Payment Claim);[6]
(e) in response to the December Payment Claim:
(i) on 11 January 2019, the plaintiff replied (to the December Payment Claim) by providing a payment schedule to the first defendant in the sum of $7,182 (excluding GST) (Payment Schedule);[7]
(ii) on 25 January 2019, the first defendant made an Adjudication Application under the SoP Act (Vic) (Adjudication Application);[8]
(f) on 31 January 2019, the Adjudicator accepted the appointment as adjudicator in relation to the first defendant's Adjudication Application;[9]
(g) on 4 February 2019, the plaintiff provided an Adjudication Response to the Adjudication Application (Adjudication Response);[10]
(h) on 7 February 2019, the Adjudicator issued a notice pursuant to s 21(2B) of the SoP Act (Vic), which identified matters in the Adjudication Response which, in the Adjudicator's opinion, were not raised in the first defendant's Payment Schedule and the Adjudicator afforded the first defendant an opportunity to respond to matters raised by the plaintiff;[11]
(i) on 11 February 2019, the first defendant served further submissions in response to the Adjudicator's notice dated 7 February 2019 pursuant to s 21(2B) of the SoP Act (Vic);[12] and
(j) on 18 February 2019, the Adjudicator issued an Adjudication Determination[13] in relation to the Adjudication Application in which he determined that the first defendant was entitled to payment in the sum of $209,470.04 (including GST).
5 The plaintiff's central submissions and primary ground impugn the December Payment Claim because the plaintiff argues that claim was not served in accordance with the provisions of the SoP Act (Vic) in circumstances where it was not served 'on and from' the relevant reference date in compliance with s 9(1) of the SoP Act (Vic).
6 The plaintiff submits that ss 9(1), 9(2)(a) and 14(1) of the SoP Act (Vic) prescribe the circumstances in which a person is entitled to serve a payment claim.
7 Sections 9(1), 9(2)(a) and 14(1) of the SoP Act (Vic) provide:
(1) On and from each reference date under a Construction Contract, a person-
(a) who has undertaken to carry out construction work under the contract; or
(b) who has undertaken to supply related goods and services under the contract-
is entitled to a progress payment under this Act, calculated by reference to that date. (emphasis added)
(2) In this section, "reference date", in relation to a construction contract, means-
(a) a date determined by or in accordance with the terms of the contract as-
(i) a date on which a claim for a progress payment may be made; or
(ii) a date by reference to which the amount of a progress payment is to be calculated-
in relation to a specific item of construction work carried out or to be carried out or a specific item of related goods and services supplied or to be supplied under the contract; ... (emphasis added)
14. Payment claims
(1) A person referred to in section 9(1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment. (emphasis added)
8 Pursuant to ss 9(1) and 14(1) of the SoP Act (Vic), the first defendant may serve a payment claim 'on and from each reference date under a construction contract'.
9 The plaintiff emphasises that in the recent decision in Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd,[14] (Southern Han), the High Court of Australia (High Court) held that the existence of a valid reference date is a 'precondition' to the making of a valid payment claim.
The relevant reference date under the Construction Contract
10 The plaintiff submits that the SoP Act (Vic) only operates in respect of contractual rights as between the parties[15] and that cl 37 of the Construction Contract specifies the circumstances in which the first defendant is entitled to make a payment claim.
11 Pursuant to cl 37.1 and item 33 of Annexure Part A of the Construction Contract, the 'reference date' for making payment claims was nominated as the 25th day of each calendar month.
12 The plaintiff submits that prior to the service of the December Payment Claim, the first defendant had served a payment claim on 26 November 2018,[16] and had thereby served another earlier payment claim in respect of the 25 November 2018 reference date.
13 In the result the plaintiff argues that in breach of s 14(8) of the SoP Act (Vic) the first defendant served more than one payment claim in respect of the 25 November 2018 reference date and the plaintiff further submits that thereby the Adjudicator erred in failing to recognise and determine that the December Payment Claim was served in breach of s 14(8) of the SoP Act (Vic) and was thereby invalid.
14 The plaintiff submits that the first defendant made an application which it was not entitled to make under the SoP Act (Vic). The plaintiff submits that the Adjudicator erred in his Adjudication Determination because although the first defendant and the Adjudicator wrongly proceeded upon that basis, the December Payment Claim was not served in accordance with the SoP Act (Vic) in respect of the 25 December 2018 reference date.[17]
The December Payment Claim was not served 'on and from' the relevant reference date
15 The plaintiff submits that because the December Payment Claim was served by the first defendant on 21 December 2018,[18] it was not served 'on and from' the reference date of 25 December 2018 simply by reason of the relationship between those dates and the language of s 9(1) of the SoP Act (Vic).
The effect of the deeming provision in clause 37.1 of the Construction Contract
16 Clause 37.1 (paragraph 3) of the Construction Contract provides that:
An early payment claim shall be deemed to have been made on the date for making that payment claim in accordance with Item 33.
17 The plaintiff submits that the deeming provision in cl 37.1 of the Construction Contract should be viewed consistently with the decisions of other courts in which the effect of terms very similar to cl 37.1 have been considered. In this respect, the plaintiff relies on the decisions of the High Court in Southern Han,[19] the New South Wales Court of Appeal in All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd[20] (All Seasons) and Doyle J (of the Supreme Court of South Australia) in The Trustee for Allway Unit Trust trading as Westside Mechanical Contracting Pty Ltd v R&D Air-Conditioning Pty Ltd & Ors[21] (Westside Mechanical).
18 The plaintiff observes that the deeming provision in the Construction Contract is in very similar terms to the contractual provisions in All Seasons, in which that construction contract provided:
An early progress claim shall be deemed to have been made on the date for making that claim.[22]
19 In All Seasons, Leeming and Payne JJ (with whom White JA agreed, although his Honour added certain additional observations) followed the reasoning of the High Court in Southern Han in determining that such a deeming provision cannot operate in the context of the security of payment legislation to cure the premature service of a payment claim.[23]
20 The plaintiff's submissions point out that the New South Wales Court of Appeal recognised that there were sound policy reasons for not allowing a deeming provision to cure a failure to comply with the strict timelines imposed by the security of payment legislation:
Further, we do not think that the applicant's construction promotes the purpose of the Act. There is sound reason, given the consequences for both parties of engaging the regime established by the Act, for there to be certainty as to precisely when a payment claim has been served. It is easy to see the scope for confusion that could arise if the applicant's construction were accepted. The Act requires people dealing with a builder's accounts to be very concerned to respond to "payment claims" within 10 business days. On the applicant's construction, it would be necessary to have regard not merely to when a document styled a 'payment claim' is received, but also the terms of the particular contract. That is not enhanced by a construction which may give rise to debate as to the effect of a deeming provision on a notice which, at the time it was sent, could not have been an actual payment claim. Not lightly would we conclude that the time-critical regime established by the Act involving as it does a series of exchanges of claims and responses is engaged by the deemed or notional service of a document, rather than actual service.[24]
21 The plaintiff's submissions also point out that the above approach in All Seasons was recently followed in Westside Mechanical.[25]
22 The plaintiff complains that at 5.1 of the Adjudication Determination, the Adjudicator erred in deciding not to follow the decision in All Seasons and concluding that as a result of the 'deeming provision' in cl 37.1 of the Construction Contract that the 'reference date is the deemed date for making the payment claim being 25 December 2018'.
23 The plaintiff submits that the Adjudicator appears to have reached the above view on the basis of a decision of Vickery J in Metacorp Australia Pty Ltd v Andeco Construction Group Pty Ltd & Ors[26] (Metacorp).
24 The plaintiff argues that reliance on Metacorp is misconceived, in particular because:
(a) Metacorp was decided prior to the High Court decision in Southern Han;
(b) in Southern Han, the High Court determined that it is critical to have regard to the temporal aspect of s 9(1) of the SoP Act (Vic) which turns on the existence of a reference date under a construction contract, which reference date is in turn a precondition to the making of a valid payment claim;
(c) the New South Wales Court of Appeal decision in All Seasons closely follows the reasoning in Southern Han; and
(d) to the extent Metacorp is inconsistent with Southern Han and All Seasons, the Metacorp decision was handed down before the above, subsequent superior court decisions, and should not be followed.
25 Accordingly, on the plaintiff's submissions, the December Payment Claim was served prematurely and did not validly invoke the operation of the SoP Act (Vic) depriving the Adjudicator of jurisdiction.
26 The first defendant rejects the plaintiff's argument that its December Payment Claim was submitted prematurely.
27 The first defendant submits that the plaintiff's reliance upon the judgment in All Seasons is 'problematic'. The first defendant notes that, prior to the decision in All Seasons, Vickery J in Metacorp considered the meaning of the words 'entitled to a progress payment under a construction contract' in s 14(1) of the SoP Act (Vic); his Honour stated in Metacorp:
provided that a person makes a claim to be entitled to a progress payment, and that claim is made bona fide, the claimant is permitted to serve its payment claim pursuant to s. 14(1) of the Victorian Act, and this is so, whether or not there existed an actual entitlement to payment at the time when the payment claim was served.[27]
28 The first defendant's reliance upon Vickery J's statements in Metacorp is founded in particular upon his Honour's judgment in the following paragraphs:
29 Further, the first defendant submits that for this Court to prefer the decision in All Seasons in relation to this aspect of the parties' argument, rather than following Metacorp, would require a finding that Metcorp was wrong in relevant respects.[29]
30 In this regard, the first defendant also submits that it is relevant that the New South Wales Court of Appeal in All Seasons did not consider Vickery J's judgment in Metacorp. The first defendant also submits that this Court should consider the alternative arguments in relation to this issue highlighted by White JA in All Seasons.[30]
31 In All Seasons, in his Honour's separate judgment, White JA observed:
32 The iterations of the first defendant's argument on this aspect, in summary, are as follows:
(a) the first defendant is a person referred to in s 9(1) of the SoP Act (Vic) who, as at 21 December 2018, claimed to be entitled to a progress payment;
(b) the first defendant is a person referred to in s 9(1) of the SoP Act (Vic) because it is a person who has undertaken to carry out construction work under a contract;
(c) by reason of the matters in (b) above, pursuant to s 9(1) of the SoP Act (Vic), the first defendant is entitled to a progress payment under the SoP Act (Vic) on and from each reference date;
(d) the phrase 'on and from each reference date' in s 9(1) of the SoP Act (Vic), properly construed, is to be understood as meaning 'on and with effect from each reference date';[32]
(e) the first defendant's entitlement to a reference date and consequently, a progress payment, cannot be in dispute;
(f) the first defendant's premature service of the December Payment Claim did not affect the entitlement to a reference date under the SoP Act (Vic).[33] This is because, as is supported by Vickery J in Metacorp, the first defendant claimed to be entitled to a progress payment on 25 December 2018 notwithstanding the premature service of same on 21 December 2018;
(g) Southern Han does not address whether the premature service of a payment claim makes that payment claim invalid;[34]
(h) there is no inconsistency between the decisions of Metacorp, Southern Han and All Seasons;
(i) the deeming provision in cl 37 of the Construction Contract does not affect the entitlement the first defendant has to a progress payment. The first defendant's position is that the deeming provision in cl 37.1 only affects service, namely to regularise premature service as occurring on the reference date under the Construction Contract. The first defendant accepts that its entitlement to a progress payment is determined by the Construction Contract and the SoP Act (Vic);[35] and
(j) the deeming provision in cl 37.1 of the Construction Contract is not liable to be struck down by operation of the SoP Act (Vic) and should be construed in a way which gives it some work to do. The first defendant submits that the deeming provision in cl 37.1 brings about service of a progress payment claim 'on a later date therefore has the effect of serving the progress payment on the reference date'.
33 In my view on the proper construction of ss 9(1) and 14(1) of the SoP Act (Vic), the first defendant's December Payment Claim was an invalid claim because it was served before the relevant reference date of 25 December 2018. Accordingly, the Adjudication Determination made on 18 February 2019 upholding part of the first defendant's December Payment Claim is void because it lacked jurisdictional foundation and should be quashed.
34 It is well established that the correct starting point for the analysis of a statutory provision is the text of the provision itself so as to ascertain the intent of the enacting Parliament.[36] Sections 9(1) and 14(1) are set out at paragraph [7] above.
35 Given that the word 'on' in the phrase 'on and from each reference date' in s 9 of the SoP Act above clearly relates to a particular date, in my view there is strong reason to conclude the word 'from' in the same phrase was intended by the legislature to refer to the period of time following that date. In my view, with great respect to White J, there is no justification for the importation of the words 'with effect' into the phrase 'on and from each reference date'.
36 In my view the natural and ordinary meaning of the words of ss 9(1) and s 14(1) of the SoP Act (Vic), considered in their context and together with the scheme and purpose of that Act, make it plain that pursuant to s 9(1); 'on and from each reference date' an eligible person, 'is entitled to a progress payment ... calculated by reference to', each reference date under the construction contract, and that pursuant to s 14(1) of the SoP Act (Vic) such a person may serve a payment claim on the person who under the construction contract is liable to pay.
37 In my view, the language of ss 9(1) and 14(1), in their context, taking into account the scheme and purpose of the SoP Act (Vic), support an interpretation of the words 'on and from each reference date under the construction contract ...' of s 9(1) of the SoP Act (Vic), read in conjunction with the text and ordinary meaning of ss 9(2)(a)(i) and (ii) and s 14(1) of the SoP Act (Vic), as authorising the service of a compliant progress claim, only on and from each relevant reference date, and not before the date of the applicable reference date.
38 Such a construction is strongly indicated by the words of s 9(1) of the SoP Act (Vic), which prescribes the date after which an entitlement to a progress payment arises under the SoP Act (Vic). Furthermore, s 9(1) expressly provides in relation to a person's entitlement to a progress payment under the SoP Act (Vic), that such entitlement is to be calculated by reference to the date on or from which such progress payment entitlement arose.
39 Section 9(2)(a)(i) and (ii) of the SoP Act (Vic) (subject to other matters referred to in s 9(2) which are not presently material) defines the reference date in s 9(1) of the SoP Act (Vic) to mean the date on which the contract stipulates that a claim for a progress payment may be made, or the date by reference to which the amount of the progress claim is to be calculated.
40 Section 14 of the SoP Act (Vic) entitles a person who is referred to in s 9(1) of the SoP Act (Vic) to serve a payment claim on the person who is, or may be, liable to pay that payment claim, and s 14(4) of the SoP Act (Vic) also limits the time within which a payment claim may be served to three months after the reference date fixed by s 9(2) of the SoP Act (Vic).
41 However, although s 14 of the SoP Act (Vic) does not expressly provide that a person entitled to a progress payment may not serve a payment claim before the reference date which gave rise to that person's entitlement to a progress payment, the operation of the provisions of the SoP Act (Vic) outlined above give rise to a clear statutory implication that such an untimely payment claim would not be compliant with the SoP Act (Vic). In particular ss 9(1) and (2) and s 14(1) of the SoP Act (Vic) contemplate progress payment claims on the basis of an entitlement to a progress payment on and from each reference date, because under ss 9(1) and 9(2)(a) and (b) of the SoP Act (Vic), it is the occurrence of a reference date (established by means of the operation of the terms of the construction contract or the operation of the SoP Act (Vic)) which triggers the entitlement to make a progress payment claim by a claimant who is, or who claims to be, entitled to a progress payment.[37]
42 Therefore, under the scheme of the SoP Act (Vic), a progress payment claim is to be made on and from the reference date which triggers that person's entitlement to a progress payment, although I observe that a claimant may include in a payment claim an amount that has been the subject of a previous claim if that amount has not been paid.[38]
43 If it were otherwise, for example if a payment claim was ambulatory in the sense that it could be submitted before its relevant reference date, the operation of the SoP Act (Vic) would give rise to uncertainty and confusion. In such circumstances a progress payment claim might be submitted without identifying an applicable reference date; a progress payment claim might be submitted a lengthy period of time before the reference date later asserted as applicable by the claimant and by way of a further example the receipt of progress payment claims by the respondent party might well occur in circumstances where the respondent party was uncertain about what reference date was to be asserted by the claimant as the date by reference to which the respondent was required to respond. Further, usually such a response is to be provided within only ten business days under s 15(4) of the SoP Act (Vic). These possibilities, and likely many others, are antithetical to the clearly ascertainable, expeditious and effective operation of the SoP Act (Vic).
44 Furthermore, both the High Court in Southern Han, and the New South Wales Court of Appeal in All Seasons, have clarified the meaning and operation of provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) (SoP Act (NSW)), analogous in the relevant above respects to s 9(1) and s 14(1) of the SoP Act (Vic).
45 In Southern Han[39] the High Court has stated that:
46 In Southern Han, the High Court considered the SoP Act (NSW), which corresponds, in relevant respects, with the SoP Act (Vic).[40] The High Court highlighted the important distinction between a progress payment to which a person is entitled (s 8 of the SoP Act (NSW) and s 9(1) of the SoP Act (Vic)) and the amount of the progress payment to which that person is entitled (referred to in s 9 of the SoP Act (NSW) and s 10 of the SoP Act (Vic)).
47 The High Court also observed in Southern Han that by force of s 8(1) of the SoP Act (NSW) (s 9(1) of the SoP Act (Vic)), a person who has undertaken to carry out construction work or to supply related goods and services under a construction contract is immediately 'entitled to a progress payment' on and from each reference date under the construction contract.
48 The High Court also noted that the amount of the progress claim to which the claimant under the construction contract is entitled is not fixed by s 8 of the SoP Act (NSW) but is to be ascertained by reference to the relevant reference date, and the provisions of s 9 of the SoP Act (NSW) (equivalent in substance to ss 9 and 10 of the SoP Act (Vic)) and ultimately in the event of disputes in the amount determined by an Adjudicator as provided for in the SoP Act (NSW).
49 Further, relevantly to the present issues in Southern Han, the High Court stated:
50 Accordingly, the High Court has clarified,[41] amongst other things, that an entitlement to a progress payment under the SoP Act:
(a) is enlivened by an undertaking to carry out construction work or supply related goods and services under the construction contract;[42]
(b) arises on and from each reference date under the construction contract; and[43]
(c) can be made by the person entitled to serve a payment claim in the form and within the periods prescribed in s 13 of the SoP Act (NSW) (s 14 of the SoP Act (Vic)).
51 As earlier observed, the relevant substantive language of ss 9 and 14 of the SoP Act (Vic) are, in relation to the questions raised in the present case, congruous with ss 8 and 13 of the SoP Act (NSW).
52 In All Seasons,[44] the New South Wales Court of Appeal stated in relation to the SoP Act (NSW) as follows:
The construction of s 13(1) consonant with the structure of the Act is accordingly that advanced by Southern Han. The description in s 13(1) of a person referred to in s 8(1) is of a person whom s 8(1) makes entitled to a progress payment. Section 8(1) makes a person who has undertaken to carry out construction work or supply related goods and services under a construction contract entitled to a progress payment only on and from each reference date under the construction contract. In that way, the existence of a reference date under a construction contract within the meaning of s 8(1) is a precondition to the making of a valid payment claim under s 13(1). (emphasis added.)
53 Here the first defendant also argues that the law in Victoria prior to the decision in All Seasons, was that which was enunciated by Vickery J in Metacorp and that neither Southern Han nor All Seasons properly understood, sought to interpret the language in the New South Wales security of payment legislation which is analogous to s 9(1) and s 14(1) of the SoP Act (Vic).
54 In Metacorp, it was alleged that the claimant had failed to enliven jurisdiction under the SoP Act (Vic) on the basis that it served the subject payment claim on the respondent on 24 October 2009 in circumstances where the relevant reference date was 25 October 2009.[45] In Vickery J's decision, analysis of the SoP Act (Vic) included focus on the introductory words of s 14(1) of the SoP Act (Vic), in particular, 'entitled to a progress payment under a construction contract'.
(1) A person who is entitled to a progress payment under a construction contract (the "claimant") may serve a payment claim on the person who under the contract is liable to make the payment.
Whereas s. 14(1) of the Victorian Act as it presently stands provides:
(1) A person referred to in section 9(1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
The words "or who claims to be entitled" have been added to the text of s. 14(1) of the Victorian Act, as they have also been added to s. 13(1) of the NSW Act.
56 I reject the first defendant's submission outlined in paragraphs [29] and [53] above because in my view the statements extracted above from Southern Han and All Seasons, in particular as extracted at paragraphs [45], [49] and [52] hereof respectively, explain and clarify the language and operation of the provisions in the SoP Act (NSW), which in material respects are analogous to ss 9(1) and 14(1) of the SoP Act (Vic) as outlined in the above referenced paragraphs of those judgments, and in my view the High Court and the New South Wales Court of Appeal overrule Metacorp in that regard.[46]
57 Vickery J's judgment in Metacorp and in particular his conclusions in relation to the operation of s 9 of the SoP Act (Vic) and the meaning of the words 'on and from' in s 9 of the SoP Act (Vic) long preceded the High Court's pronouncements highlighted above in Southern Han and the recent decision in All Seasons.
58 The first defendant argued that Metacorp remains good law in Victoria, a proposition asserted on the basis that Southern Han and All Seasons did not engage in explaining the interpretation of the High Court or the New South Wales Court of Appeal in relation to the words 'on and from' each reference date, employed in s 8(1) of the SoP Act (NSW).
59 The first defendant's implied submission was to the effect that the High Court and the New South Wales Court of Appeal, in the extracts cited above, sought to do no more than extract the words of the SoP Act (NSW), which did not necessarily contradict Vickery J's reasoned explanation of the construction of ss 9(1) and 15(4) of the SoP Act (Vic) in Metacorp.
60 In my view, although neither the High Court in Southern Han nor the New South Wales Court of Appeal in All Seasons simply and succinctly express the effect of the language which is pivotal in this case, namely the words 'on and from each reference date' in s 8(1) of the SoP Act (NSW) (also appearing in s 9(1) of the SoP Act (Vic)), it is sufficiently clear in light of Southern Han and All Seasons[47] that s 9 and s 14 of the SoP Act (Vic) do not operate so as to permit the valid service of a payment claim prior to the relevant reference date which itself establishes a valid foundation for that payment claim to be made under the SoP Act (Vic); the statements in Southern Han and All Seasons in paragraphs [45], [49] and [52] hereof respectively clarify that.[48]
61 The first defendant also relies on the separate judgment of White JA in All Seasons.[49] The relevant sections of White JA's judgment are extracted at paragraph [31] hereof. In this judgment, his Honour states that "it would be arguable that the phrase 'on and from each reference date' is to be understood as meaning 'on and with effect from each reference date', rather than 'on and after each reference date".[50]
62 The plaintiff, as earlier outlined, submits that the ordinary meaning of the words 'on and from' is that a payment claim must be submitted 'on or after' the occurrence of a reference date.[51]
63 I do not accept the first defendant's argument that the obiter observations of White JA in All Seasons at [50] and [51] thereof, identify a preferable construction of s 9(1) of the SoP Act (Vic) by analogy, and further I consider that I am bound in that regard, for the reasons I have outlined, by the decision of the High Court in Southern Han and the majority in All Seasons.
64 In my view for the reasons I have outlined above, there is no justification for implying the inclusion of the words 'with effect' in relation to s 9(1) of the SoP Act (Vic) as White JA did in relation to the equivalent s 8(1) of the SoP Act (NSW) in All Seasons. Likewise in my view, there is insufficient justification on any basis relating to the scheme of Part 2 of the SoP Act (Vic), or the provisions of s 14(1), to alter the plain and ordinary meaning of the words 'on and from each reference date' in s 9(1) of the SoP Act (Vic) as was decided in Metacorp, six years before Southern Han and eight years before All Seasons.
470 St Kilda Road Pty Ltd v Reed Constructions Australia Pty Ltd & Anor
65 I also reject the plaintiff's contention that by Vickery J's judgment in 470 St Kilda Road Pty Ltd v Reed Constructions Australia Pty Ltd & Anor[52] (470 St Kilda Road) at [45]-[47], his Honour departed from his decision in Metacorp in relation to when a progress payment claim might be permissibly served in relation to a reference date.[53] I consider that at [45]-[47] of 470 St Kilda Road Vickery J explained that in his view there was no departure from or material qualification in respect of his earlier conclusions about the permissible timing of a progress payment claim, but rather his Honour departed from his earlier conclusions in Metacorp that a payment claim 'must be made bona fide in order to be valid'.
66 Finally, in the above circumstances it is not in my view necessary to express a view about whether Vickery J's interpretation of s 9(1) of the SoP Act (Vic) in Metacorp was correct. His Honour's interpretation of s 9(1) at [107] hereof does not accord with authority binding on me in Southern Han and All Seasons. Furthermore, for the reasons I have advanced in paragraphs [33] to [44] of these Reasons, and in my view consistently with the abovementioned binding authorities, I consider the SoP Act (Vic) does not contemplate or permit a payment claim to be made under s 14(1) of that Act by a person referred to in s 9(1) of that Act, before each relevant reference date.
The first defendant's reliance on cl 37.1 of the Construction Contract
67 Clause 37.1 of the Construction Contract provides that:
An early payment claim shall be deemed to have been made on the date for making that payment claim in accordance with Item 33.
68 In All Seasons Leeming and Payne JJ (with whom White JA agreed) followed the High Court in Southern Han in determining that a deeming provision, in very similar terms to cl 37.1 of the subject Construction Contract, could not permissibly operate to render a progress payment claim served before the relevant reference date, compliant and valid.[54]
69 At [41] in All Seasons, the Court also recognised sound policy reasons for concluding that a deeming provision, very similar to cl 37.1 in the subject Construction Contract, should not be permitted to cure failure by a potential claimant under the security of payment legislation to comply with the strict requirements and timelines of that legislation:
Further, we do not think that the applicant's construction promotes the purpose of the Act. There is sound reason, given the consequences for both parties of engaging the regime established by the Act, for there to be certainty as to precisely when a payment claim has been served. It is easy to see the scope for confusion that could arise if the applicant's construction were accepted. The Act requires people dealing with a builder's accounts to be very concerned to respond to "payment claims" within 10 business days. On the applicant's construction, it would be necessary to have regard not merely to when a document styled a "payment claim" is received, but also the terms of the particular contract. That is not enhanced by a construction which may give rise to debate as to the effect of a deeming provision on a notice which, at the time it was sent, could not have been an actual payment claim. Not lightly would we conclude that the time-critical regime established by the Act involving as it does a series of exchanges of claims and responses is engaged by the deemed or notional service of a document, rather than actual service.
71 In this case, the first defendant's submission in relation to the deeming provision in the Construction Contract is as follows:
Finally, consideration must be had to the deeming provision contained in clause 37.1 of the Contract. Carelli submits that the deeming provision does not affect the entitlement of Carelli to a progress payment - it agrees that those matters are determined by the Contract and the Act. In the circumstances, the only issue which the deeming provision can address is that of service, the effect of which is to regularise premature service as occurring on the reference date.
72 I note that I understood the first defendant's submission referred to in the last preceding paragraph to accept that if on the proper construction of the SoP Act (Vic) a payment claim cannot be valid if served prior to the relevant reference date, then the deeming provisions in cl 37.1 of the subject Construction Contract, is not argued by the first defendant to be capable of affecting that position.
73 I am of the view that the Adjudicator erred in concluding in the Adjudication Determination under review that the progress payment claim in question was effectively deemed to have been made on 25 December 2018. In my view, the Adjudicator's decision in relation to this aspect erroneously relies upon cl 37.1 of the Construction Contract to enable the first defendant to avoid the strict temporal requirements of s 9(1) of the SoP Act (Vic), that is to deem the first defendant's payment claim to have been made on the contractually defined reference date, even if the payment claim was served before the contractually defined reference date.
74 In my view to construe cl 37.1 of the Construction Contract as having the effect which the first defendant asserts would contradict the intent and purpose of the SoP Act (Vic) which seeks to establish a strict and time critical regime for the submission of the response to and the adjudication of payment claims. Confusion and uncertainty would be likely to arise if by the deeming clause at 37.1 of the Construction Contract the legislative regime established by the SoP Act (Vic) was circumvented in the manner clause 37.1 seeks to effect.
75 For these reasons, and in accord with the approach and conclusions referenced to above in All Seasons, I consider that cl 37.1 of the Construction Contract is ineffective to cure what I have decided is non-compliant early service of the first defendant's December Payment Claim.
76 Finally, insofar as the Adjudicator's above conclusion was based upon the decision in Metacorp, for the reasons I have earlier outlined, both in relation to the proper construction of the relevant provisions of the SoP Act (Vic) and by reason of the binding authority of statements in Southern Han and All Seasons, the Adjudicator's reliance was erroneous.
77 The first defendant concedes that if the plaintiff succeeds on ground 1, then ground 2 does not need to be considered because the December Payment Claim is invalid for premature service.[57]
78 Because I have decided that Ground 1 is made out and the Adjudication Determination dated 18 February 2019 is void, I do not consider it necessary to further address Ground 2.
79 The Adjudicator erred in law in determining that the December Payment Claim was valid in circumstances where it was not served 'on and from' the relevant 'reference date'.
80 Because I have decided that Ground 1 is made out and the Adjudication Determination dated 18 February 2019 is void, I do not consider it necessary to further address Ground 2.
(a) the Adjudication Determination be quashed.
(b) the first defendant is restrained from seeking to enforce or take action under the SoP Act (Vic) in relation to the Adjudication Determination; and
(c) the Adjudicator is restrained from providing an Adjudication Certificate pursuant to s 28Q of the SoP Act (Vic) in respect of the Adjudication Determination.
82 I shall hear the parties, if necessary, as to the final form of orders, including any orders as to costs.
[2] By letter dated 8 March 2019 the second defendant advised the Court he does not intend to take any active role in the proceeding and will abide the decision of the Court, save for any costs order being considered against him.
[14] [2016] HCA 52; (2016) 260 CLR 340, [2].
[15] [2016] HCA 52; (2016) 260 CLR 340, [66]-[71].
[19] [2016] HCA 52; (2016) 260 CLR 340, [2].
[21] [2018] SASC 46, [135]-[144].
[22] [2017] NSWCA 289, [2].
[23] [2017] NSWCA 289, [32]-[36].
[24] [2017] NSWCA 289, [41].
[25] [2018] SASC 46, [135]-[144].
[27] [2010] VSC 199, [101].
[28] [2010] VSC 199, [101] and [102].
[30] [2017] NSWCA 289, [50] and [51].
[31] [2017] NSWCA 289, [50] and [51].
[32] This matter was not considered by the High Court in Southern Han as identified by White JA in All Seasons at [50].
[33] The first defendant does not understand the plaintiff to be making this submission, however, it is not apparent from the Submissions filed on 16 April 2019.
[34] See such identification by White JA in All Seasons, [51].
[36] Visy Paper Pty Ltd v Australian Competition and Consumer Commission [2003] HCA 59; (2003) 216 CLR 1, [24]. It has also been established that the object of interpreting the text of a statute is to ascertain the intention of the enacting Parliament. In Project Blue Sky Inc & ors v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR 355 [69], the High Court stated that:
The primary object of statutory construction is to construe the relevant provision so that it is consistent with the language and purpose of all the provisions of the statute. The meaning of the provision must be determined "by reference to the language of the instrument viewed as a whole".
[37] Section 9(2) (a)(ii) of the SOP Act enables the progress payment claim to be made by establishing a reference date arising by means of the construction contract providing for a date at which the amount of a progress payment under the construction contract is to be calculated.
[40] The following sections of the New South Wales SoP Act are equivalent in their substantive relevant parts, to the sections (in bold) of the Victorian SoP Act, s 8(1) (s 9(1)), 59 (s 10(1)) and s 13(1) (s 14(1) and (2)).
[41] By reference to the SoP Act (NSW).
[42] [2016] HCA 52; (2016) 260 CLR 340, [59].
[43] [2016] HCA 52; (2016) 260 CLR 340, [59] and [61].
[47] Southern Han paragraphs [41]-[42], [44], [55]-[57] and [59]-[60] and All Seasons paragraphs [11]-[13], [32]-[33], [36] and [38]-[41].
[48] Southern Han, including at [55], [60] and [61] and All Seasons, including at [11], [13], [32], [36], [40] and [41].
[49] First Defendant's Outline of Submissions, [10]-[11].
[50] [2017] NSWCA 289, [50].
[51] Plaintiff's Outline of Submissions, [16].
[53] Refer: first defendant's submissions, [7] and Vickery J's decision in 470 St Kilda Road and in particular plaintiff's reply submission at [3] as follows:
3. At paragraphs [6] to [8] of its submissions, the First Defendant submits the Court remains bound by paragraphs [101] and [102] of Metacorp. However, the First Defendant has overlooked that Vickery J subsequently determined that those paragraphs were wrongly decided in 470 St Kilda Road Pty Ltd v Reed Constructions Australia Pty Ltd & Anor. His Honour held:
In Metacorp the court was called upon to consider the validity of a payment claim that had been served prematurely, that is before the appointed "reference date" as defined in s 9(2) of the Act. In the course of considering the issue I observed:
...under the legislation as it now stands, the class of persons who may serve a payment claim has been extended to include persons "who claim to be entitled" to a progress payment, in addition to those who may actually be so entitled. In my view, provided that a person makes a claim to be entitled to a progress payment, and that claim is made bona fide, the claimant is permitted to serve its payment claim pursuant to s 14(1) of the Victorian Act, and this is so, whether or not there existed an actual entitlement to payment at the time when the payment claim was served.
In the light of the authorities I have cited in these reasons, which were not referred to the court in Metacorp, on reflection and with the benefit of full argument on the matter, I am persuaded that I was wrong insofar as it is said in that case that a payment claim, whether served prematurely before the due reference date or served on and from each reference date, must be made bona fide in order to be valid, and I decline to follow myself.
There is no implied precondition to the making of a valid payment claim under s 14 of the Act that the claimant has made the claim with a bona fide belief in its entitlement to the moneys claimed or that otherwise the claim is made in good faith.
[54] [2017] NSWCA 289, [32]-[36].
[56] [2018] SASC 46, [143].
[57] First defendant's written submissions, 26 April 2019, [18].
MKA Bowen
Carelli Constructions [2019] VSC 436
(2016) 260 CLR 340
(2010) 30 VR 141
(2003) 216 CLR 1
(1998) 194 CLR 355