Plain English Summary
7/10 complexity
These regulations set how licensed water and sewerage operators may restrict water use, notify the Minister and the public, and grant exemptions (regs 4–8). They require timed service‑response standards for developers and certificates, ban specified trade‑waste substances and prescribe numeric acceptance limits (regs 9A–9C, 15; Schedules 2–3), and fix infringement penalties (reg 16; Sch 4). Who pays: water users, developers and operators incur compliance costs and possible fines. Decision‑makers: regulated entities and the Minister; behaviour changes: timely notices, applications, and meeting waste standards.
These regulations set operational rules for Tasmania’s water and sewerage industry under the Water and Sewerage Industry Act 2008. They (a) prescribe how regulated entities may impose and publicise water restrictions; (b) prescribe service standard timeframes and procedures for interactions between developers, planning authorities and the licensed water/sewerage provider (called a relevant or regulated entity); (c) define what counts as development or work for planning purposes in relation to water and sewerage infrastructure; (d) set the mandatory form and fee for a land information certificate; (e) set enforceable requirements and acceptance standards for liquid trade waste; and (f) fix infringement notice penalties for specified offences. Key cross-references in the regulations link to specific Act provisions, including s 56L (restrictions on supply of water), s 56H/s 56I (development/work exclusions), s 56W (consent to build over infrastructure), and s 56ZQ (land information certificates).
Mechanically, the regulations require a regulated entity that commences restricting water supply to notify the Minister in writing within 21 days, and to give public notice in at least two prescribed ways (regulations 5, 7 and 8). The Minister may add to classes of persons exempted from a restriction (regulation 6). The regulations create a new Part 2A of service standards, imposing fixed timeframes for a relevant entity to respond to requests for information, approvals, consents, inspections, certificates of practical completion and final acceptance for small and large developments; they also specify how periods are calculated and how requests for further information suspend time limits (regulations 9A-9C). For trade waste the regulations (regulation 15 and Schedules 2 and 3) prohibit certain substances in waste, require operators to accept only wastes meeting specified parameters unless an exception applies, and forbid dilution to meet acceptance criteria. Regulation 14 prescribes the certificate form and prescribes a fee of 25 fee units for the land information certificate under s 56ZQ of the Act. Regulation 16 maps infringement notice penalties to a table in Schedule 4, applying different penalty-unit levels to natural persons and bodies corporate when an infringement notice is served under s 100 of the Act.
Current sections
Direct links to the current provisions in Water and Sewerage Industry (General) Regulations 2019.
(2) In these regulations, a reference to a restriction of the supply of water is a reference to a restriction, by a regulated entity under section 56L of the Water and Sewerage Industry Act 2008 , of the quantity of water supplied to any person.
Part 2
Water Restrictions
Part 2 Water Restrictions
4
Duration and form of water restriction
4 Duration and form of water restriction
(1) A regulated entity may restrict the supply of water by any or all of the following means:
(a) by restricting the purposes for which the water may be used;
(b) by specifying the purposes for which the water may not be used;
(c) by restricting the days or times, or both, when the water may be used;
(d) by restricting the quantity of the water that may be used by a person, or at premises, in a specified period;
(e) by restricting the means or methods by which the water may be used.
(2) A regulated entity may apply a restriction of the supply of water to all, or part only, of the area to which the regulated entity ordinarily supplies the water.
(3) A regulated entity may exempt classes of persons, in whole or in part, from a restriction of the supply of water.
5
Minister to be notified of proposed water restriction
5 Minister to be notified of proposed water restriction
(1) A regulated entity must notify the Minister in writing within 21 days after beginning to restrict the supply of water.
(a) the details of the restriction of the supply of water; and
(b) the area to which the restriction of the supply of water is to apply; and
(c) the dates between which the restriction of the supply of water is to apply; and
(d) the class of persons, if any, exempted from the restriction of the supply of water.
6
Minister may add to classes of persons exempted from restrictions
6 Minister may add to classes of persons exempted from restrictions
(1) After being notified under regulation 5 of a restriction of the supply of water by a regulated entity, the Minister may declare, by notice, in addition to those persons already exempted by the regulated entity under regulation 4(3) –
(a) further classes of persons who are exempted from the restriction of the supply of water; and
(b) the extent to which members of those further classes of persons are exempted from the restriction of the supply of water.
(2) The Minister may only include in a notice under subregulation (1) a class of persons if he or she is satisfied that –
(a) it is unreasonable or unnecessary; or
(b) it would cause unreasonable or unnecessary hardship to members of the class –
if the members were not exempted, in the manner specified in the notice, from the restriction of the supply of water specified in the notice.
(3) A regulated entity is to publish in a newspaper, circulating generally in the area to which a restriction of water supplied by the entity applies, a copy of a declaration of the Minister under subregulation (1) that relates to the restriction.
7
Form of newspaper notice for purposes of section 56L(2) of Act
7 Form of newspaper notice for purposes of section 56L(2) of Act
(1) A notice for the purposes of section 56L(2) of the Act in relation to a restriction of water supplied must contain the necessary details in relation to the restriction.
(2) For the purposes of subregulation (1) , the necessary details in relation to the restriction of water supplied are –
(a) a description of the restriction; and
(b) the area to which the restriction relates; and
(c) the dates between which the restriction is to have effect; and
(d) the classes of persons, if any, who are to be exempted in whole or in part from the restriction; and
(e) a statement as to how a person may apply, to the regulated entity publishing the notice, to request that a class of persons be exempted in whole or in part from the restriction.
8
Public notice of water restriction
8 Public notice of water restriction
(1) A regulated entity that imposes a restriction of the supply of water must give the necessary notice to the public in relation to the restriction of water supplied.
Penalty: Fine not exceeding 50 penalty units.
(2) For the purposes of subregulation (1) , the necessary notice to the public in relation to a restriction of the supply of water consists of giving notice in accordance with at least 2 of the following paragraphs:
(a) publishing on the regulated entity's website a notice containing the necessary details of the restriction referred to in regulation 7 , as added to, if at all, by any declaration under regulation 6(1) in relation to the restriction;
(b) broadcasting, by a radio transmission that transmits to the public in the area to which the restriction relates, the details of the restriction;
(c) installing signs, on the major roads in the area to which the restriction relates, specifying the dates between which, and the way in which, the restriction is to have effect.
9
Compliance with water restriction
9 Compliance with water restriction
A person must not, without reasonable excuse, contravene a necessary detail contained in accordance with regulation 7 in a notice published in accordance with section 56L(2) of the Act, as modified, if at all, by a notice published in a newspaper under regulation 6(3) .
average sewage rate means the average rate, as determined by the relevant entity, of sewage discharge under dry weather flows;
average water rate means the average rate, as determined by the relevant entity, of water usage;
certificate for certifiable work (building) has the same meaning as in section 56TA of the Act;
certificate for certifiable work (plumbing) has the same meaning as in section 56TA of the Act;
equivalent tenement means an average single residential house on a standard residential lot;
final acceptance, in relation to water and sewerage assets, means the acceptance by a relevant entity, after the end of the defect liability period in relation to the water and sewerage assets, of the water and sewerage assets as being complete and without defects;
large development means –
(a) a subdivision, or a proposed subdivision, in relation to which works for the purposes of more than 10 lots are to be required; and
(b) a development, of a building to be used for commercial or industrial purposes, that a relevant entity considers to be a development in relation to which the average water rate, or average sewage rate, is likely to be greater than the average water rate, or average sewage rate, for 10 equivalent tenements;
relevant entity means the person holding a licence, or an interim licence, granted under the Act;
small development means –
(a) a subdivision, or a proposed subdivision, in relation to which works for the purposes of 10 or fewer lots are to be required; and
(b) a development, of a building to be used for commercial or industrial purposes, that a relevant entity considers to be a development in relation to which the average water rate, or average sewage rate, is likely to be greater than the average water rate, or average sewage rate, for 10 or fewer equivalent tenements;
(1) If a relevant entity receives from a person a request to provide to the person information in relation to a small development, or the construction of water and sewerage assetsfor a small development, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity provides the information to which the request relates – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, provide to the person the information to which the request relates.
(2) If a relevant entity receives from a person a request to provide to the person information in relation to a large development, or the construction of water and sewerage assetsfor a large development, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity provides the information to which the request relates – within 10 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 20 business days of receiving the request from the person, provide to the person the information to which the request relates.
(3) If a relevant entity receives a request from a person (including a planning authority) to issue the relevant entity’s consent to the sealing or registration of a plan or document that imposes or creates obligations or rights, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity may consent to the sealing or registration of the plan or document – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, consent to the sealing or registration of the plan or document or refuse to consent to the sealing or registration of the plan or document.
(4) If a relevant entity receives from a person a request for approval of the engineering design of a small development, or of water and sewerage assets, of a small development, that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity approves, or refuses to approve, the engineering design of the development or assets – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, approve, or refuse to approve, the engineering design of the development or assets.
(5) If a relevant entity receives from a person a request for approval of the engineering design of a large development, or of water and sewerage assets, for a large development, that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity approves, or refuses to approve, the engineering design of the development or assets – within 10 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 20 business days of receiving the request from the person, approve, or refuse to approve, the engineering design of the development or assets.
(6) If a relevant entity receives from a planning authority a request to provide to the planning authority the relevant entity’s opinion in relation to a proposed amendment, under section 56 of the Land Use Planning and Approvals Act 1993 , of a permit within the meaning of that Act, the relevant entity is to –
(a) if the relevant entity requires further information from the planning authority before the relevant entity provides to the planning authority the relevant entity’s opinion in relation to the proposed amendment – within 7 business days of receiving the request from the planning authority, by notice in writing request the planning authority to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the planning authority, provide, or refuse to provide, to the planning authority the relevant entity’s opinion in relation to the proposed amendment.
(7) If a relevant entity receives from a person a request for an amendment of a certificate for certifiable work (plumbing) or of a certificate for certifiable work (building), the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity amends the certificate or refuses to amend the certificate – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, amend the certificate or refuse to amend the certificate.
(8) If a relevant entity receives from a person a request for a permit to construct water and sewerage assets that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity determines the request from the person – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, issue, or refuse to issue, the permit to construct.
(9) If a relevant entity receives from a person a request to inspect, at a site, water and sewerage assets in relation to a development, the relevant entity is to –
(a) within 7 business days of receiving the request, conduct the inspection at the site; and
(b) within 5 business days of conducting the inspection, provide to the person a document indicating the decision of the relevant entity, in relation to the assets, as a result of the inspection.
(10) If a relevant entity receives from a person a request to issue a certificate of practical completion, the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity determines the request – within 15 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 15 business days of receiving the request from the person, issue, or refuse to issue, to the person a certificate of practical completion.
(11) If a relevant entity receives from a person a request for final acceptance of all water and sewerage assets in relation to a development, all inspections of the assets have been completed and all documents that the person is required to provide to the relevant entity have been provided to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity determines the request from the person – within 10 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, notify the person of final acceptance of, or of the relevant entity’s refusal to provide final acceptance of, the water and sewerage assets.
(12) If a relevant entity receives from a person an application under section 56TD(3) of the Act to issue under section 56TD(4) a certificate in respect of certifiable work, the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity determines the application – within 10 business days of receiving the application, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the application, issue the certificate or refuse to issue the certificate.
9C
Request for further information and calculation of periods for compliance with service standards
9C Request for further information and calculation of periods for compliance with service standards
(1) If a relevant entity has requested a person to provide information under a provision of regulation 9B or this subregulation, the relevant entity, if it is not satisfied with the information provided by the person pursuant to the request, is to, within 8 business days after receiving the information, give to the person a notice in writing specifying –
(a) that the relevant entity is not satisfied with the information; and
(b) that the person is requested to provide to the relevant entity the further information specified in the notice.
(2) If a relevant entity gives to a person a request under a paragraph of a subregulation in regulation 9B –
(a) the period in which the relevant entity may give a request under the paragraph of a subregulation in regulation 9B does not run during the period beginning on the day on which the request is made and ending on whichever is the later of the following days:
(i) the day on which the information to which the request relates is provided to the relevant entity;
(ii) if a notice under subregulation (1) that relates to the request is given – the day on which further information is provided to the relevant entity in accordance with the notice under subregulation (1) ; and
(b) the period in which the relevant entity is to take any other action referred to in another paragraph of the subregulation in regulation 9B does not run during the period beginning on the day on which the request is made under a paragraph of the subregulation and ending on whichever is the later of the following days:
(i) the day on which the information, satisfactory to the relevant entity, to which the request relates, is provided to the relevant entity;
(ii) if a notice under subregulation (1) that relates to the request is given – the day on which further information, that is satisfactory to the relevant entity, is provided to the relevant entity in accordance with the notice under subregulation (1) .
Part 3
Miscellaneous
Part 3 Miscellaneous
10
Subdivisions that are not development under Land Use Planning and Approvals Act 1993
10 Subdivisions that are not development under Land Use Planning and Approvals Act 1993
(1) For section 56H(1)(b) of the Act, the area of the land is to be not greater than 800 square metres.
(2) For the purposes of section 56H(1)(c) of the Act, the requirements are that the proposed use of the land is to be –
(a) the installation or erection, and the use, of a pump station associated with the distribution or removal of water or sewage; or
(b) the laying, removal, repair, maintenance or modification, and the use, of a pipeline and ancillary works associated with the distribution or removal of water or sewage; or
(c) the laying, removal, repair, maintenance or modification, and the use, of a drainage channel associated with the distribution or removal of water; or
(d) the installation or erection, and the use, of a fluoridation station; or
(e) the installation or erection, and the use, of a chlorination station, if the chlorine used or stored is not at any time in a gaseous form; or
(f) the installation or erection, and the use, of a Level 1 wastewater treatment plant associated with the treatment of water or sewage; or
(g) the installation or erection, and the use, of a sludge farm or a sludge storage area associated with the treatment of water or sewage.
(3) In this regulation –
Level 1 wastewater treatment plant means a plant –
(a) that is used for the purpose of carrying out wastewater treatment which involves the discharge of treated or untreated sewage, septic tank effluent or industrial or commercial wastewater to land or water; and
(b) with a design capacity to treat an average dry-weather flow of less than 100 kilolitres per day.
11
Work that is not use or development under Land Use Planning and Approvals Act 1993
11 Work that is not use or development under Land Use Planning and Approvals Act 1993
For section 56I(b) of the Act, the following kind of work, and criteria in relation to that work, are prescribed:
(a) the removal, repair, maintenance, modification, installation, erection or use of a pump station associated with the distribution or removal of water or sewage;
(b) the removal, repair, maintenance, modification, installation, erection or use of a fluoridation station associated with the provision of water;
(c) the removal, repair, maintenance, modification, installation, erection or use of a chlorination station associated with the provision of water, if the chlorine used or stored is not at any time in a gaseous form;
(d) the laying, removal, repair, maintenance, modification or use of any underground pipeline for the removal or distribution of water or sewage;
(e) the installation, removal, repair, maintenance, modification, replacement or use of a meter for water infrastructure, whether the meter is above or below ground, if the installation, removal, repair, maintenance, modification, replacement or use is associated with the provision of water by a regulated entity;
(f) the clearing or lopping of trees, branches or other vegetation to the extent necessary to protect water infrastructure, sewerage infrastructure or water quality, except if those trees are on –
(i) the Register of the National Estate kept by the Australian Heritage Commission; or
(ii) the National Trust Register.
12
When planning authority not required to notify regulated entity about planning application
12 When planning authority not required to notify regulated entity about planning application
(1) For section 56O(2)(b) of the Act, an application is exempted from the requirement for notice to be given of it to a regulated entity if the application does not relate to a development that –
(a) shows on a plan a structure 2 metres or less from any underground infrastructure of the regulated entity; or
(b) involves non-residential, commercial, industrial or other processes that generate trade waste for discharge to a sewer; or
(c) involves non-residential, commercial, industrial or other processes and has, or will require, a connection to the reticulated water supply; or
(d) is likely to increase the demand for water or sewerage services or will require an increase in the connection size for the property on which the development is to occur; or
(e) involves work, in a water supply catchment, that may affect water quantity or quality; or
(f) is within an area of land that the regulated entity has declared, by notice to the relevant planning authority, to be a buffer zone; or
(g) includes, or will affect, infrastructure that crosses over, or will cross over, any of the entity's water infrastructure or sewerage infrastructure; or
(h) consists of or includes a subdivision of land into 2 or more lots, the issue of 2 or more strata titles or a consolidation of 2 or more lots into one lot or 2 or more strata titles into one lot; or
(j) involves demolition of a structure or works that are connected to a regulated entity's water infrastructure or sewerage infrastructure.
(2) A regulated entity may, in a notice under subregulation (1)(f) , declare an area of land to be a buffer zone if, in the opinion of the entity, the area of land is sufficiently close to the point at which wastewater enters, or is emitted from, a sewage treatment works of the entity that the entity ought to assess the suitability of a proposed use of the land.
13
Prescribed structures
13 Prescribed structures
(1) For section 56W(1)(a) , (b) and (c) of the Act, all structures that are not minor structures are prescribed structures.
(2) For the purposes of subregulation (1) , a minor structure is one of the following structures:
(a) a driveway;
(b) a railway crossing;
(c) an outbuilding, if –
(i) it is the only building of its type on the site; and
(ii) the total area of the outbuilding does not exceed 9 square metres; and
(iii) no side is longer than 3 metres; and
(iv) no part is more than 2.4 metres above the ground;
(d) a pergola, garden arch, trellis or frame, if the structure –
(i) does not exceed 20 square metres in total area; and
(ii) is no more than 3 metres above the floor or ground; and
(iii) is not covered or is covered only by open-weave material which allows water through;
(e) a swimming pool, if –
(i) the maximum possible water surface area is not more than 9 square metres; and
(ii) the maximum possible water depth is not more than 300 millimetres;
(f) a non-roofed windmill, a mast, antenna or flagpole, if –
(i) it is not attached to a building and is not more than 6 metres high; or
(ii) it is a dish antenna with a diameter of not more than 2 metres and the total area of the dish antenna attached to the supporting structure is not more than 4 square metres;
(g) a fence or wall constructed of masonry or concrete, if it is not higher than 1.2 metres;
(h) a fence constructed of a material other than masonry or concrete, if it is not higher than 2.1 metres;
(i) a retaining wall, if –
(i) it retains a difference in ground levels of less than one metre; and
(ii) it is situated more than 1.5 metres from a boundary or way;
(j) a water tank, if it has a capacity of less than 45 kilolitres;
(k) a water tank stand, if it is not higher than 1.2 metres;
(l) a builder's site shed, if it is to be –
(i) used in connection with building work for which a building permit under the Building Act 2016 is in force; or
(ii) stored in a location permitted by the building surveyor;
(m) an explosives magazine, a tank containing dangerous goods or a gas installation, if the Competent Authority, within the meaning of the Dangerous Goods (Road and Rail Transport) Act 2010 , controls how the magazine, tank or installation may be used;
(n) a non-habitable underground structure on a mining lease;
(o) a temporary structure that is required under the Building Act 2016 to have a temporary occupancy permit or that is exempted from that requirement.
(b) the questions set out in Part 2 of Schedule 1 are prescribed.
(2) For section 56ZQ(4) of the Act, a fee of 25 fee units is prescribed.
15
Requirements in relation to trade waste
15 Requirements in relation to trade waste
(1) A person must not cause or permit trade waste to be placed in a sewerage system if the waste contains a substance specified in Schedule 2 .
Penalty: Fine not exceeding 20 penalty units.
(2) A person who operates sewerage infrastructure must not accept liquid trade waste for placement in the sewerage infrastructure unless the waste complies with the standards for acceptance of the waste that are specified in Schedule 3 .
Penalty: Fine not exceeding 20 penalty units.
(3) Despite subregulation (2) , a person may accept for placement in sewerage infrastructure trade waste that does not comply with the local acceptance criterion specified in item 1 of Schedule 3 if he or she is satisfied that the infrastructure is capable of satisfactorily handling the trade waste even though it does not comply with that criterion.
(4) A person must not dilute trade waste to achieve compliance with the standards for acceptance of the waste that are specified in Schedule 3 .
Penalty: Fine not exceeding 20 penalty units.
16
Infringement notice offences and penalties
16 Infringement notice offences and penalties
(1) The penalty specified in column 3 of the table in Schedule 4 is the prescribed penalty for an offence, against a provision of the Act or these regulations specified in respect of the offence in column 2 of the table, that is –
(a) committed by a natural person; and
(b) specified in an infringement notice served on the person under section 100 of the Act.
(2) The penalty specified in column 4 of the table in Schedule 4 is the prescribed penalty for an offence, against a provision of the Act or these regulations specified in respect of the offence in column 2 of the table, that is –
(a) committed by a body corporate; and
(b) specified in an infringement notice served on the body corporate under section 100 of the Act.
SCHEDULE 1 - Prescribed form o
SCHEDULE 1 - Prescribed form of certificate and questions
SCHEDULE 1 - Prescribed form o SCHEDULE 1 - Prescribed form of certificate and questions
| Column 1 | Column 2 |
| Number | Substance |
| 1. | Flammable or explosive substances that – |
| | (a) exceed 10% of the lower explosive limit at 25ºC; or |
| | (b) could cause an explosion or fire in the sewerage system. |
| 2. | Radioactive material, other than in accordance with the Radiation Protection Act 2005. |
| 3. | Medical, clinical, veterinary or other pathological wastes that may pose a threat to the health and safety of sewerage system operations or maintenance personnel or the community. |
| 4. | Genetically engineered organisms or mutant bacteria, except as authorised by the relevant regulated entity. |
| 5. | Rainwater, groundwater, uncontaminated yard drainage or other uncontaminated water, except where the sewerage system has been designed for their conveyance and treatment. |
| 6. | The contents of any sewage eductor vehicle, septic tank pump-out, pan closet, storage device or treatment device, except at designated receiving stations operated under the control and supervision of the relevant regulated entity. |
| 7. | Any substance that is – |
| | (a) likely to cause serious or material harm to the receiving environment after passing through a treatment plant or outfall; or |
| | (b) harmful, or liable to form compounds that may be harmful, to sewerage system operations or maintenance personnel or the community; or |
| | (c) likely to cause an obstruction or blockage of a sewer or drain or treatment apparatus. |
SCHEDULE 3 - Standards for acc
SCHEDULE 3 - Standards for acceptance of liquid trade waste
SCHEDULE 3 - Standards for acc SCHEDULE 3 - Standards for acceptance of liquid trade waste
These regulations are administered in the Department of Primary Industries, Parks, Water and Environment.
Source text: opening excerpt
Sourced from Tasmanian Legislation Online (legislation.tas.gov.au), CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
1 Short title
1 Short title
These regulations may be cited as the Water and Sewerage Industry (General) Regulations 2019 .
2 Commencement
2 Commencement
These regulations take effect on 1 July 2019.
3 Interpretation
3 Interpretation
(1) In these regulations –
Act means the Water and Sewerage Industry Act 2008 .
(2) In these regulations, a reference to a restriction of the supply of water is a reference to a restriction, by a regulated entity under section 56L of the Water and Sewerage Industry Act 2008 , of the quantity of water supplied to any person.
Part 2 Water Restrictions
Part 2 Water Restrictions
4 Duration and form of water restriction
4 Duration and form of water restriction
(1) A regulated entity may restrict the supply of water by any or all of the following means:
(a) by restricting the purposes for which the water may be used;
(b) by specifying the purposes for which the water may not be used;
(c) by restricting the days or times, or both, when the water may be used;
(d) by restricting the quantity of the water that may be used by a person, or at premises, in a specified period;
(e) by restricting the means or methods by which the water may be used.
(2) A regulated entity may apply a restriction of the supply of water to all, or part only, of the area to which the regulated entity ordinarily supplies the water.
(3) A regulated entity may exempt classes of persons, in whole or in part, from a restriction of the supply of water.
5 Minister to be notified of proposed water restriction
Who pays, and who makes decisions: regulated entities decide the content and geographic scope of water restrictions subject to notification obligations and Ministerial power to add exemptions (regs 4-6). Relevant entities decide whether a development is large or small for service standard purposes (regulation 9A definitions). Developers, landowners, operators of sewerage infrastructure, planning authorities and trade waste producers bear compliance costs and potential penalties where breaches occur (see regulations 5, 8, 9, 15; Schedule 4). The instrument establishes clear process constraints and disclosure duties that change administrative timing and communications behaviour between these parties.
Main concepts
The regulations turn statutory concepts in the Water and Sewerage Industry Act 2008 into operational rules and prescriptive standards. Core concepts and their regulatory treatment include:
Restriction of the supply of water (regulation 3(2) and Part 2): The regulations specify permissible forms of restriction (regulation 4(1)): limiting purposes, banning certain uses, restricting days or times, limiting quantities in specified periods, and restricting means or methods of use. Entities may impose restrictions over all or part of their supply area (regulation 4(2)) and may exempt classes of persons (regulation 4(3)). Notification and public notice requirements are specified (regulations 5-8), including the required content of newspaper notices (regulation 7) and the minimum public notice methods (regulation 8(2)). Non-compliance by a person with a necessary detail in a published restriction is an offence (regulation 9).
Ministerial intervention on exemptions (regulation 6): After being notified of a restriction, the Minister may add further exempt classes, but only if satisfied it would be unreasonable or cause unreasonable or unnecessary hardship not to do so (regulation 6(2)). The Minister’s declaration must be published by the regulated entity in a newspaper circulating in the area (regulation 6(3)).
Service standards, response times and procedural stops (Part 2A, regulations 9A-9C): The regulations define small and large developments, equivalent tenements, average water/sewage rates and what constitutes relevant entities (regulation 9A). They set discrete timeframes for a relevant entity to request further information and to provide responses across a range of common interactions: information requests for small vs large developments, consent to sealing or registration, engineering design approvals, opinions on planning amendments, amendments to certifiable work certificates, permits to construct, site inspections and provision of inspection decisions, certificates of practical completion and final acceptance, and certificates issued under s 56TD(4) of the Act (regulation 9B). Regulation 9C prescribes how a request for further information affects calculation of those periods, including a stop-the-clock mechanism until satisfactory information is supplied.
Land information certificates and fees (regulation 14 and Schedule 1): The form for information issued under s 56ZQ is prescribed in Schedule 1 (Part 1 and Part 2), and a fee of 25 fee units is prescribed (regulation 14(2)).
Development/work thresholds and prescribed structures for planning interaction (regulations 10-13): Regulations 10 and 11 specify dimensions and classes of land or works to be treated as not being development or not being use or development under the Land Use Planning and Approvals Act 1993, by reference to s 56H and s 56I of the Act. Regulation 13 prescribes which structures are prescribed structures under s 56W, with a schedule of "minor structures" that are excluded from prescription.
Trade waste prohibition and acceptance criteria (regulation 15 and Schedules 2 and 3): The regulations identify substances that must not be present in trade waste (Schedule 2), establish local and general acceptance criteria with specific numeric standards for parameters such as BOD5, COD, TDS, metals and a range of organic compounds (Schedule 3), require operators not to accept liquid trade waste that fails to meet standards (regulation 15(2)), allow a specific exception where the operator is satisfied the infrastructure can handle the non-complying waste (regulation 15(3)), and forbid dilution to meet standards (regulation 15(4)).
Infringement notice penalties (regulation 16 and Schedule 4): The regulations prescribe the penalty-unit amounts for specified offences if an infringement notice is served under s 100 of the Act; different penalty units apply for natural persons and bodies corporate (Schedule 4).
These are working rules that convert policy and statutory delegations into specific administrative duties, procedural timelines and technical acceptance standards. Several defined terms, including "relevant entity", "large development", "small development" and "equivalent tenement", allocate discretion to the licensed entity to classify developments and calculate average rates (regulation 9A).
Who it affects
Primary regulated actors:
Regulated entities and relevant entities: The person holding a licence or interim licence under the Act, who decides and implements water restrictions (regulations 4-9), publishes notices (regulations 7-8), issues land information certificates (regulation 14; Schedule 1), assesses, accepts and operates sewerage infrastructure and trade waste (regulation 15), and performs the operational functions subject to service standards under Part 2A (regulations 9A-9C). These entities bear notification duties to the Minister (regulation 5) and public notice obligations (regulation 8).
The Minister: Exercises a specific discretionary power to add classes of exemptions to a restriction notified by a regulated entity (regulation 6), subject to a statutory satisfaction test that it would be unreasonable or cause unreasonable or unnecessary hardship not to exempt the class (regulation 6(2)).
Secondary affected actors:
Developers, landowners and builders: Persons who request information, engineering approvals, consents to sealing or registration, permits to construct, certificates of practical completion and final acceptance from relevant entities engage the service standards in Part 2A (regulation 9B). For these actors, the regulations set predictable response periods and specify the right of the relevant entity to request further information and thus suspend timeframes (regulation 9B and 9C).
Planning authorities: The regulations interact with the Land Use Planning and Approvals Act 1993. Regulation 12 lists circumstances in which a planning authority need not notify a regulated entity about a planning application (regulation 12(1)), and provides for a regulated entity to declare buffer zones where the entity considers the area sufficiently close to sewage treatment works that the entity ought to assess a proposed use (regulation 12(2)).
Operators of sewerage infrastructure and trade waste producers: Operators must ensure liquid trade waste meets Schedule 3 standards before accepting it (regulation 15(2)); producers must not place prohibited substances into the sewerage system (regulation 15(1)) and must not dilute waste to comply (regulation 15(4)). Operators may, however, accept non-complying waste if satisfied their infrastructure can handle it (regulation 15(3)).
Property purchasers, conveyancers and prospective buyers: The prescribed land information certificate form in Schedule 1 (regulation 14(1)) and the prescribed fee (regulation 14(2)) affect conveyancing processes and due diligence: regulated entities must fill out the prescribed certificate and answer prescribed questions about connections, infrastructure under the land, notices to repair, and consents to build over infrastructure.
General public and road users: Public notice requirements for water restrictions include signs on major roads in the affected area as an option (regulation 8(2)(c)), and radio or website notices (regulation 8(2)(a) and (b)); the public is subject to the offence in regulation 9 for non-compliance with notice details.
Who pays and bears the burden:
Regulated entities carry administrative burden: preparing and publishing notices, responding within specified timeframes to many classes of requests (Part 2A), maintaining records enabling completion of land information certificates (Schedule 1), and applying trade waste acceptance criteria.
Developers and applicants incur direct costs of supplying requested information, waiting for approvals or paying fees for land information certificates (25 fee units, regulation 14(2)), and potential delays when a relevant entity requests further information.
Trade waste producers may need pretreatment or monitoring to meet Schedule 3 parameters, or face refusal or prohibition under regulation 15(1) and (2). Dilution is expressly forbidden (regulation 15(4)), which imposes a compliance requirement on producers to meet standards without resort to simple dilution.
Planning authorities may reduce notification workload for regulated entities in cases prescribed by regulation 12(1), while regulated entities can declare buffer zones and thereby increase their own planning scrutiny obligations.
Collective market effect: The regulations impose predictability and minimum service standards that reduce informational asymmetry between developers and relevant entities, but they also transfer operational and administrative costs to regulated entities and require trade waste producers to conform to quantified environmental and operational standards.
Key duties and rights
Duties of regulated and relevant entities
Restricting water: A regulated entity may restrict supply by the enumerated means in regulation 4(1) and may apply restrictions to all or part of its supply area (regulation 4(2)). The entity may exempt classes of persons (regulation 4(3)), but must notify the Minister within 21 days after beginning to restrict the supply of water and specify details (regulation 5(1)-(2)). Failure to notify attracts a penalty of a fine not exceeding 50 penalty units (regulation 5(1)).
Public notice obligations: The regulated entity imposing a restriction must give necessary notice to the public, using at least two of the methods listed in regulation 8(2): website publication, radio broadcast to the affected area, or signs on major roads specifying dates and how the restriction operates. A failure to give the necessary public notice is a fine not exceeding 50 penalty units (regulation 8(1)). Regulation 7 prescribes the required content of notices under s 56L(2) of the Act.
Ministerial declarations: Upon notification under regulation 5, the Minister may declare additional exempt classes and the extent of exemption, but only if satisfied of the "unreasonable or unnecessary" test or that non-exemption would cause "unreasonable or unnecessary hardship" to members of the class (regulation 6(1)-(2)). The regulated entity must publish the Minister’s declaration in a newspaper circulating generally in the area (regulation 6(3)).
Service standards response obligations: The relevant entity must meet the response timeframes throughout regulation 9B. These include initial requests for further information (specified short notice periods) and maximum time limits for responses: 10 business days for information relating to a small development (regulation 9B(1)(b)); 20 business days for large development information (regulation 9B(2)(b)); 10 business days for consent to sealing or registration (regulation 9B(3)(b)); 10 business days for approval or refusal of engineering design for a small development (regulation 9B(4)(b)) and 20 business days for a large development (regulation 9B(5)(b)); 10 business days for opinions on planning amendments requested by a planning authority (regulation 9B(6)(b)); 10 business days for amendments to certificates for certifiable work (regulation 9B(7)(b)); 10 business days to issue or refuse to issue a permit to construct (regulation 9B(8)(b)); conduct site inspections within 7 business days and provide a decision within 5 business days (regulation 9B(9)); issue or refuse to issue a certificate of practical completion within 15 business days (regulation 9B(10)); and notify a person of final acceptance, or refusal, within 10 business days when all inspections and documents are completed (regulation 9B(11)). The entity may request further information within shorter initial notice periods as specified in each subparagraph; such requests affect the calculation of time periods under regulation 9C.
Information requests and calculation of timeframes: If a relevant entity requests further information, regulation 9C(1) requires the entity to say within 8 business days if the information provided is unsatisfactory and to specify further information required. Regulation 9C(2) suspends the running of the relevant response period from the day the request is made until the later of the day the information is provided or, where a notice under 9C(1) is given, the day further information is provided.
Duties of the public, developers and trade waste producers
Compliance with water restriction notices: A person must not, without reasonable excuse, contravene a necessary detail contained in a published restriction notice under s 56L(2) of the Act, as modified by any Minister’s newspaper declaration (regulation 9). Penalty is a fine not exceeding 50 penalty units.
Trade waste prohibitions and acceptance: A person must not cause or permit trade waste containing substances in Schedule 2 to be placed in the sewerage system (regulation 15(1)), penalty up to 20 penalty units. A person operating sewerage infrastructure must not accept liquid trade waste unless it meets the standards in Schedule 3 (regulation 15(2)), penalty up to 20 penalty units. The operator may accept a waste that fails local acceptance criteria if satisfied the infrastructure can handle it (regulation 15(3)). Diluting trade waste to meet standards is expressly prohibited (regulation 15(4)), penalty up to 20 penalty units.
Rights and procedural protections
Right to information and time certainty: Developers and planning authorities gain statutory guarantees for maximum response times from relevant entities across a range of routine approvals and inquiries (regulation 9B). The entity retains the right to request further information and to suspend time limits until satisfactory information is supplied (regulation 9C), providing a limited procedural protection against premature refusal.
Ministerial discretion with a stated satisfaction test: The Minister may expand exempt classes under restriction decisions, but only upon satisfaction that not doing so would be unreasonable or cause unreasonable or unnecessary hardship (regulation 6(2)). The satisfaction requirement frames the exercise of Ministerial discretion, but the regulations do not prescribe processes for affected persons to seek review of Ministerial declarations within the instrument.
Right to prescribed form answers: Parties seeking land information certificates receive standardised responses on the prescribed form in Schedule 1; regulated entities certify answers are true and accurate according to their records (Schedule 1 Part 1).
Enforcement mechanism
Infringement notices under s 100 of the Act: Regulation 16 uses Schedule 4 to prescribe penalty-unit amounts for specified offences when dealt with by infringement notices; the table distinguishes penalties for individuals and corporate bodies (regulation 16(1)-(2) and Schedule 4).
Penalties and enforcement
The regulations specify both traditional criminal penalties and infringement penalties administered under s 100 of the Act. Enforcement tools include fines for offences in the regulations, the Act’s infringement notice scheme, and prescribed penalties in Schedule 4 for a set of Act sections and regulations.
Direct penalties in the regulations
Failure to notify the Minister about a proposed water restriction is an offence punishable by a fine not exceeding 50 penalty units (regulation 5(1)). Failure to give the necessary public notice about a restriction is also punishable by a fine not exceeding 50 penalty units (regulation 8(1)). Contravention of the published restriction details is punishable by a fine not exceeding 50 penalty units (regulation 9). These are primary regulatory penalties expressed as maximum fines rather than fixed penalty units.
Trade waste offences carry maximum fines of 20 penalty units: causing or permitting prohibited substances to be placed in the sewerage system (regulation 15(1)), operators accepting waste that fails standards (regulation 15(2)), and diluting trade waste to meet standards (regulation 15(4)) each carry penalties of fines not exceeding 20 penalty units.
Infringement notice framework (regulation 16 and Schedule 4)
Regulation 16 makes the table in Schedule 4 the prescribed penalty for a range of offences if committed by a natural person and specified in an infringement notice served under s 100 of the Act. Column 3 of Schedule 4 lists penalty units for individuals; Column 4 lists units for bodies corporate. For example, contravention of section 56ZI or section 56ZJ(1) of the Act attract 10 penalty units for an individual and 50 for a corporate body (Schedule 4 items 15-16). Some offences attract very small infringement penalties, for example many procedural or record-keeping offences are 1 or 2 penalty units for individuals (Schedule 4 entries).
The Schedule lists specific Act sections and some regulations (for example, Regulation 5(1), Regulation 8(1), Regulation 9, Regulation 15(1), 15(2), 15(4)) and maps these to an infringement penalty. For offences that are included, enforcement officers may elect to issue an infringement notice rather than proceed by criminal prosecution, as provided by s 100 of the Act, with the prescribed penalty-unit amounts in Schedule 4.
Operational enforcement and discretion
The Minister’s power to add to exempt classes (regulation 6) is an executive discretion exercised after notification. The regulations require public publication of the Minister’s declaration (regulation 6(3)), but they do not set an internal review or appeal mechanism in the instrument itself. Enforcement of trade-waste acceptance standards rests partly on the operator’s ability to refuse non-complying waste and partly on penalties for acceptance of non-complying waste (regulation 15(2)).
Stop-the-clock and information requests (regulation 9C) affect enforceability of service-time targets: the entity’s right to request information and its subsequent ability to treat information as unsatisfactory for up to eight business days allows the entity procedural leeway that affects the practical enforceability of timeframes in 9B. The regulations do not, within the instrument, set an express penalty for failure to meet the Part 2A timeframes.
Who enforces and how
Infringement notices are served under s 100 of the Act; the regulations prescribe the amounts in Schedule 4 (regulation 16). Criminal penalties (fines not exceeding given penalty units) can be sought by prosecution under the Act or the regulations as applicable. The instrument itself is administered by the Department of Primary Industries, Parks, Water and Environment, as noted at the end of the regulations; operational enforcement will therefore involve departmental officers and authorised persons under the Act.
Uncertainties and implementation risks regarding enforcement
The regulations prescribe certain maximum fines as "not exceeding" amounts, leaving sentencing choice to courts where prosecutions proceed. For many procedural timeframes in Part 2A there is no express penalty stated in the regulations for failing to meet those timeframes, so enforcement may be more administrative (complaints, internal departmental oversight) than punitive. The stop-the-clock provisions in regulation 9C give relevant entities a clear procedural avenue to extend response times; this will affect how strictly the timeframes are enforced in practice. The regulations do not themselves create an express statutory right to compensation or expedited judicial review where an entity misses a service standard timeframe.
How it interacts with other laws
The regulations are tightly cross-referenced with statutory provisions in the Water and Sewerage Industry Act 2008 and with planning, building and other regulatory regimes. The instrument operationalises and supplements those Acts in the following ways:
Interaction with the Water and Sewerage Industry Act 2008
Many provisions implement or flesh out sections of the Act. For example, regulation 4 implements the means by which a "restriction of the supply of water" under s 56L of the Act may operate (see regulation 3(2) and regulation 7 which cross-references s 56L(2)). Regulation 5 creates a specific duty to notify the Minister under the Act. Regulation 14 prescribes the form and fee for a land information certificate under s 56ZQ of the Act. Regulation 15 operationalises trade waste prohibitions and acceptance standards that link to the Act’s regulatory scheme in relation to sewerage infrastructure.
Interaction with planning law: Land Use Planning and Approvals Act 1993
Regulations 10 and 11 refer directly to s 56H and s 56I of the Act which themselves import or interact with the Land Use Planning and Approvals Act 1993. Regulation 10 prescribes the maximum land area (800 square metres) for the s 56H(1)(b) exception and prescribes the types of uses that qualify under s 56H(1)(c), such as pump stations, pipelines and fluoridation stations. Regulation 11 specifies types of work that are not "use or development" under s 56I(b), listing pump stations, fluoridation and chlorination works, pipeline works, meters, and vegetation clearing to protect infrastructure, subject to heritage exclusions.
Regulation 12 sets circumstances under which a planning authority is not required to notify a regulated entity about a planning application under s 56O(2)(b) of the Act. It lists conditions where the application is exempted from notice, for example where a proposed structure is 2 metres or less from underground infrastructure, or if the development shows commercial processes generating trade waste, or is a subdivision into 2 or more lots (regulation 12(1)). It also allows a regulated entity to declare buffer zones by notice to planning authorities where the entity considers the area sufficiently close to a sewage treatment works that it ought to assess proposed uses (regulation 12(2)).
Interaction with the Building Act 2016 and certification regime
Regulation 9A imports terms from the Act such as "certificate for certifiable work (building)" and "certificate for certifiable work (plumbing)" as defined in s 56TA of the Act, and Part 2A prescribes timeframes for amendment requests and issuance of certificates (regulation 9B(7) and 9B(12)). Regulation 13 references the Building Act 2016 in defining temporary structures and site sheds that are minor structures exempt from prescription.
Interaction with environmental and dangerous goods regimes
Regulation 13 lists "explosives magazine, a tank containing dangerous goods or a gas installation" as minor structures if the Competent Authority under the Dangerous Goods (Road and Rail Transport) Act 2010 controls their use (regulation 13(2)(m)). Regulation 15 references the Radiation Protection Act 2005 as to when radioactive material is permitted in trade waste (Schedule 2 item 2). The trade waste criteria in Schedule 3 dovetail operationally with environmental and public health obligations; however, the regulations do not displace other environmental licensing regimes but work alongside them.
Interaction with publication and administrative law
The instrument’s publication requirements (regulations 7-8 and 6(3)) interface with traditional administrative law norms about notice and natural justice. For example, the Minister’s ability to declare exemptions (regulation 6) requires satisfaction of specified tests but the regulations do not prescribe appeal or merits review mechanisms within the instrument; such challenges would proceed under broader administrative or judicial review mechanisms outside the instrument.
Fee and penalty definitions
Regulation 14 prescribes the fee as "25 fee units" for a land information certificate under s 56ZQ; this links to the statutory framework that defines fee units for the relevant jurisdiction. Regulation 16 and Schedule 4 use "penalty units", which interact with the State’s Penalty Units regime for converting units to monetary amounts.
Taken together, the regulations are an implementing instrument that converts Act delegations into operational rules for the water and sewerage sector while explicitly aligning with related planning, building, dangerous goods and radiation regimes. They do not purport to override other statutory obligations; rather, they prescribe administrative mechanics that sit alongside other regulatory requirements.
Amendment history
The regulations commenced on 1 July 2019 (regulation 2). The instrument’s Gazettal is noted as 26 June 2019 at the end of the document. The regulations include at least one recorded amendment: Regulations 9A, 9B and 9C in Part 2A were inserted by Statutory Rule 2020, No. 79, and applied on 30 November 2020, as flagged in each of those regulation headings and by the insertion notes: "[Regulation 9A Inserted by S.R. 2020, No. 79, Applied:30 Nov 2020]" and similarly for 9B and 9C. These inserted provisions create the service standards framework and the stop-the-clock mechanism for information requests.
No other amending instruments are recorded within the text provided. The instrument’s administration is ascribed to the Department of Primary Industries, Parks, Water and Environment, and the display conforms with the Rules Publication Act 1953.
What the amendment history concretely reveals in the source
The original 2019 regulations established the baseline rules on water restrictions, trade waste standards, planning interaction, the land information certificate form and infringement penalties. The 2020 amendment (S.R. 2020 No.79) added Part 2A (regs 9A-9C) to introduce prescriptive service standard timeframes and procedural rules for information requests and the calculation of time periods. The presence of the insertion notes means that the service standards were not part of the original 2019 instrument but were added later to formalise response-time expectations between relevant entities and applicants.
The instrument itself does not record any other changes, savings, or transitional provisions in respect of the 2020 amendment within the provided text. It does not display a running consolidated history beyond the insertion notes. For a practitioner or researcher wanting a full amendment chronology, the source indicates the 2020 insertion and the original commencement date, but further historical amendments (if any) are not contained in this text and would require checking the consolidated statute database or the Tasmanian legislation register for subsequent S.R. amendments.
Practical implications of the amendment
The 2020 insertion of service standards is an operational change that affects developers, planning authorities and regulated entities by imposing measurable response obligations (see regs 9B and 9C). Entities that operated under less prescriptive expectations prior to November 2020 would have had to adjust procedures and resourcing to meet the new timeframes and the stop-the-clock rules. The instrument as provided does not show any later amendment to those inserted provisions.
Litigation history
The legislation text supplied does not record any judicial decisions, appeals or administrative review outcomes relevant to these regulations. There are no cases named in the instrument, and no references to litigation or formal disputes within the text. The instrument therefore contains no internal litigation history.
What that absence means for users of this note
The absence of litigation information in the regulations does not mean there has been no litigation in practice about any of the matters covered. It only means the instrument itself does not contain or reference cases. For any party seeking to understand how courts or tribunals have interpreted provisions such as the Minister’s discretion to add exemptions (regulation 6), obligations to notify and publish water restrictions (regulations 5-8), the application of trade waste standards (regulation 15 and Schedules 2-3), or the operation of service standards (regs 9A-9C), a search of Tasmanian case law, administrative decisions, tribunal determinations and decisions under the Water and Sewerage Industry Act 2008 will be required. The instrument itself supplies the statutory mechanics but not judicial interpretation.
If an enforcement action under the Act or these regulations proceeds to court, or if a party seeks judicial review of a Ministerial declaration or an entity’s refusal to meet a Part 2A timeframe, those decisions will be found outside the text of this instrument. Readers should therefore combine this statutory analysis with a case-law search to see how tribunals and courts have applied the provisions in practice.
Gotchas
Practical pitfalls and counterintuitive features in the regulations that practitioners and compliance officers should note:
Ministerial exemptions are discretionary but framed by a subjective satisfaction test (regulation 6(2)). The Minister may only add classes of exempted persons if satisfied that it is unreasonable or unnecessary, or that not exempting would cause unreasonable or unnecessary hardship. The regulation does not define “unreasonable” or “unnecessary hardship”, nor does the instrument prescribe a review route for persons affected by a Ministerial decision; administrative law avenues would be the external route. Because the regulated entity must publish the Minister’s declaration in a newspaper (regulation 6(3)), the effect is immediate in publicity terms but procedurally opaque in review terms.
Definition of large versus small development contains entity discretion (regulation 9A). A large development is partly defined by whether a relevant entity "considers" the average water or sewage rate is likely to be greater than for 10 equivalent tenements. This gives the relevant entity scope to classify a development differently based on its internal assessment of likely average rates. That classification has legal consequences for the applicable service standard timelines (regulation 9B(1)-(5)). Developers should not assume objective thresholds only.
Stop-the-clock on timeframes can extend response times considerably (regulation 9C). When a relevant entity requests further information, the period for action under regulation 9B does not run from the day the request is made until the later of the day the information is provided or, if a notice under regulation 9C(1) is given, the day further information is provided. Additionally, a relevant entity can say within 8 business days that it is not satisfied with the information and ask for further information. This procedural right grants entities a controlled way to extend statutory timeframes; applicants should therefore budget for multiple rounds of requests when relying on the statutory deadlines.
Trade waste local acceptance criteria are variable and can be departed from (regulation 15(3)). Schedule 3 sets local acceptance criteria in item 1 and general acceptance criteria in item 2, with metals and organics in further items. Regulation 15(3) allows an operator to accept trade waste that fails the local acceptance criterion in item 1 if it is satisfied its infrastructure can handle the waste. This creates potential variation between operators and a risk of inconsistent acceptance practices across service areas; it also creates a factual assessment for operators that may be scrutinised by regulators in the event of environmental harm.
Dilution is explicitly prohibited (regulation 15(4)). Operators and producers must not rely on dilution to meet acceptance standards. Operationally, this means pretreatment or segregation will often be required rather than dilution.
Prescribed structures are "all structures that are not minor structures" (regulation 13(1)). The definition of "minor structures" is detailed (regulation 13(2)), and many common items (driveways, small outbuildings, pergolas, small water tanks, certain fences) are minor and therefore excluded. However, anything not matching those precise criteria will be a prescribed structure, which carries implications for consent under s 56W of the Act.
Land information certificate form is mandatory with a fee of 25 fee units (regulation 14). The prescribed questions in Schedule 1 require the regulated entity to certify whether records show water and sewer connections, proximity to infrastructure, records of infrastructure under the land, notices to owners to repair, and consents to build over infrastructure. Incomplete records may therefore produce "no" or "unknown" answers; regulated entities must certify their answers are true according to existing records (Schedule 1 Part 1).
Penalty units in Schedule 4 apply to infringement notices, but the instrument uses "penalty units" and "fee units" without numerical monetary conversion. Practitioners must convert units to currency using the current state rate for penalty units and fee units applicable at the relevant time. Schedule 4 differentiates natural persons and bodies corporate with significantly different unit amounts for serious offences.
Public notice requirement uses at least two methods (regulation 8(2)). Relying on a single method will not comply. The available options (website, radio broadcast to the affected area, signs on major roads) have different reaching capabilities; careful selection is needed to ensure effective public communication.
No express statutory remedy for service standard breaches in the instrument. The regulations create timeframes but do not set a penalty for failing to meet most of those timeframes, so redress for applicants may be limited to complaint processes under the Act or external judicial review, not direct monetary compensation triggered by a missed deadline.
Vagueness of "major roads" (regulation 8(2)(c)) and "area to which the restriction relates" (regulations 4(2), 7(2)(b)) leaves room for debate about sufficiency of signage and the appropriate geographic scope for notice publication.
How to comply
Practical, step-by-step compliance checklist tailored to the main affected actors, driven strictly by the text of the regulations.
For regulated entities imposing water restrictions
Before or as you begin restricting water, determine the form of restriction in terms of the methods in regulation 4(1) (purposes, prohibited purposes, days/times, quantity limits, or means/methods), and decide the geographic scope (regulation 4(2)) and any classes of exempt persons you will apply (regulation 4(3)).
Notify the Minister in writing within 21 days of beginning the restriction (regulation 5(1)). The notice must specify the restriction details, the area it applies to, the dates between which it applies, and any classes of persons exempted (regulation 5(2)). Be mindful that failure to notify carries a penalty up to 50 penalty units (regulation 5(1)).
Prepare public notices that meet the content requirements in regulation 7(1)-(2), ensuring the notice describes the restriction, the area affected, the effective dates, classes exempted, and provides a statement on how to apply to the regulated entity for class exemption.
Provide necessary public notice by at least two methods listed in regulation 8(2): publish the notice on the entity’s website (regulation 8(2)(a)); broadcast by radio to the affected area (regulation 8(2)(b)); and/or install signs on major roads in the area specifying the restriction dates and manner (regulation 8(2)(c)). Failure to give necessary notice attracts a fine up to 50 penalty units (regulation 8(1)).
If the Minister declares additional exempt classes under regulation 6(1), promptly publish the Minister’s declaration in a newspaper circulating generally in the affected area (regulation 6(3)).
Monitor compliance with published restriction details and enforce rules; know that contravening a necessary detail in a published restriction is an offence with penalty up to 50 penalty units (regulation 9).
For relevant entities responding to developer, applicant and planning authority requests (service standards)
Classify requests as relating to small or large development according to regulation 9A. Document the basis for any subjective assessment that a development is “large” because this determines longer timelines (regulation 9B(1)-(5)).
For each request, operate the two-step process: (a) if you require further information, issue a written request within the initial days specified in the relevant paragraph of regulation 9B (for example, within 5 business days for small development information requests under regulation 9B(1)(a)); (b) provide the substantive response within the maximum days specified (for example, within 10 business days for small development information under regulation 9B(1)(b)). Keep copies of written requests as they suspend the statutory period.
If you receive information that you consider unsatisfactory, give notice in writing within 8 business days under regulation 9C(1) specifying what further information is required. Track the dates carefully because regulation 9C(2) suspends the running of the response period until satisfactory information is provided.
For consents to sealing or registration (regulation 9B(3)), issue either consent or refusal within 10 business days; for approvals of engineering design, use the 10/20 business day split for small/large developments (regulation 9B(4)-(5)); for site inspections, conduct within 7 business days and provide a decision within 5 business days after the inspection (regulation 9B(9)).
Establish internal process flows, staffing and document templates to meet these timeframes and to document any requests for further information and subsequent replies. Keep an audit trail of requests and any notices under regulation 9C.
For operators and producers of trade waste
Review Schedule 2 to ensure none of the prohibited substances will be present in trade waste you place in the sewerage system. Prohibited items include flammable/explosive substances above specified thresholds, radioactive material except as permitted under the Radiation Protection Act 2005, pathological wastes, genetically engineered organisms without authorisation, certain uncontaminated waters, and substances likely to harm receiving environments or cause blockages (Schedule 2).
Ensure accepted liquid trade waste complies with Schedule 3 local and general acceptance criteria. For local acceptance criteria (Schedule 3 item 1), parameters such as BOD5 (600 mg/L), COD (1 500 mg/L), TDS (10 000 mg/L) and SS (600 mg/L) are listed and may be varied under regulation 15(3). For general criteria (Schedule 3 item 2) and the metals and organic compounds sections, ensure monitoring and pretreatment measures allow compliance with the listed numeric limits.
Do not dilute trade waste to meet the acceptance criteria (regulation 15(4)). Dilution is an express offence. Instead, use appropriate pretreatment, segregation or off-site disposal options if the waste cannot be treated to meet standards.
If you are an operator and you believe your infrastructure can safely accept waste that fails local acceptance criteria, document the technical assessment justifying that satisfaction before accepting the waste, because regulation 15(3) permits such acceptance only if the operator is satisfied their infrastructure is capable of satisfactorily handling the waste.
For planning authorities and planning applicants
Before notifying a regulated entity of a planning application, check regulation 12(1) to determine whether the application falls into one of the exemptions that relieve the planning authority of the obligation to notify (for example, where the application does not involve certain proximity to infrastructure, trade waste-generating processes, connections to reticulated water or subdivisions).
If notified by a regulated entity under regulation 12(2) of a buffer zone, treat the area as one where the regulated entity has signalled a need to assess proposed uses, and seek the entity’s opinion where necessary.
For conveyancers and purchasers
Use the prescribed land information certificate form in Schedule 1 when seeking information under s 56ZQ (regulation 14(1)), and budget the prescribed fee of 25 fee units (regulation 14(2)). Expect the regulated entity to certify answers according to its existing records (Schedule 1 Part 1).
Pay attention to answers to questions about connections, infrastructure under or through the land, recorded notices to owners to repair (Section 56Y notices), and consent to build over existing infrastructure (s 56W consents). Unknown answers in the certificate are permissible where records do not show a connection, but that will affect conveyancing risk.
General compliance controls and record-keeping
Keep contemporaneous records of all written requests for information, inspection scheduling, notices published in newspapers and on websites, radio broadcasts, sign installation (including locations), Ministerial communications, and all technical assessments for trade waste acceptance. These records support compliance with specific documentary certification requirements (Schedule 1) and with Part 2A timeframes and stop-the-clock rules.
Convert penalty units and fee units to dollar amounts using the current State conversion rates for penalty units and fee units. Do not assume static monetary amounts; confirm the current value when assessing fines and fees.
Coordinate across teams: regulatory affairs, operations (trade waste treatment, network capacity assessments), planning liaison, and communications (public notices) to ensure the multiple overlapping duties in these regulations are discharged in a timely, documented way.
Update standard operating procedures to reflect the 2020 insertion of Part 2A timeframes, the need for at least two public notice methods for water restrictions, and the prohibition on dilution of trade waste.
Following these steps will align regulated entities, relevant entities, developers, planning authorities and trade waste producers with the procedural and technical obligations set out in the regulations. Where legal uncertainty exists , for instance, in the interpretation of “unreasonable or unnecessary hardship” under regulation 6(2), or in factual assessments under regulation 15(3) , parties should obtain legal advice and be prepared to document decision-making rationales that would be relevant in any administrative review or enforcement context.
5 Minister to be notified of proposed water restriction
(1) A regulated entity must notify the Minister in writing within 21 days after beginning to restrict the supply of water.
Penalty: Fine not exceeding 50 penalty units.
(2) A notice to the Minister under subregulation (1) must specify –
(a) the details of the restriction of the supply of water; and
(b) the area to which the restriction of the supply of water is to apply; and
(c) the dates between which the restriction of the supply of water is to apply; and
(d) the class of persons, if any, exempted from the restriction of the supply of water.
6 Minister may add to classes of persons exempted from restrictions
6 Minister may add to classes of persons exempted from restrictions
(1) After being notified under regulation 5 of a restriction of the supply of water by a regulated entity, the Minister may declare, by notice, in addition to those persons already exempted by the regulated entity under regulation 4(3) –
(a) further classes of persons who are exempted from the restriction of the supply of water; and
(b) the extent to which members of those further classes of persons are exempted from the restriction of the supply of water.
(2) The Minister may only include in a notice under subregulation (1) a class of persons if he or she is satisfied that –
(a) it is unreasonable or unnecessary; or
(b) it would cause unreasonable or unnecessary hardship to members of the class –
if the members were not exempted, in the manner specified in the notice, from the restriction of the supply of water specified in the notice.
(3) A regulated entity is to publish in a newspaper, circulating generally in the area to which a restriction of water supplied by the entity applies, a copy of a declaration of the Minister under subregulation (1) that relates to the restriction.
7 Form of newspaper notice for purposes of section 56L(2) of Act
7 Form of newspaper notice for purposes of section 56L(2) of Act
(1) A notice for the purposes of section 56L(2) of the Act in relation to a restriction of water supplied must contain the necessary details in relation to the restriction.
(2) For the purposes of subregulation (1) , the necessary details in relation to the restriction of water supplied are –
(a) a description of the restriction; and
(b) the area to which the restriction relates; and
(c) the dates between which the restriction is to have effect; and
(d) the classes of persons, if any, who are to be exempted in whole or in part from the restriction; and
(e) a statement as to how a person may apply, to the regulated entity publishing the notice, to request that a class of persons be exempted in whole or in part from the restriction.
8 Public notice of water restriction
8 Public notice of water restriction
(1) A regulated entity that imposes a restriction of the supply of water must give the necessary notice to the public in relation to the restriction of water supplied.
Penalty: Fine not exceeding 50 penalty units.
(2) For the purposes of subregulation (1) , the necessary notice to the public in relation to a restriction of the supply of water consists of giving notice in accordance with at least 2 of the following paragraphs:
(a) publishing on the regulated entity's website a notice containing the necessary details of the restriction referred to in regulation 7 , as added to, if at all, by any declaration under regulation 6(1) in relation to the restriction;
(b) broadcasting, by a radio transmission that transmits to the public in the area to which the restriction relates, the details of the restriction;
(c) installing signs, on the major roads in the area to which the restriction relates, specifying the dates between which, and the way in which, the restriction is to have effect.
9 Compliance with water restriction
9 Compliance with water restriction
A person must not, without reasonable excuse, contravene a necessary detail contained in accordance with regulation 7 in a notice published in accordance with section 56L(2) of the Act, as modified, if at all, by a notice published in a newspaper under regulation 6(3) .
Penalty: Fine not exceeding 50 penalty units.
Part 2A Service Standards
Part 2A Service Standards
9A Interpretation of Part 2A
9A Interpretation of Part 2A
[Regulation 9A Inserted by S.R. 2020, No. 79, Applied:30 Nov 2020] In this Part –
average sewage rate means the average rate, as determined by the relevant entity, of sewage discharge under dry weather flows;
average water rate means the average rate, as determined by the relevant entity, of water usage;
certificate for certifiable work (building) has the same meaning as in section 56TA of the Act;
certificate for certifiable work (plumbing) has the same meaning as in section 56TA of the Act;
equivalent tenement means an average single residential house on a standard residential lot;
final acceptance, in relation to water and sewerage assets, means the acceptance by a relevant entity, after the end of the defect liability period in relation to the water and sewerage assets, of the water and sewerage assets as being complete and without defects;
large development means –
(a) a subdivision, or a proposed subdivision, in relation to which works for the purposes of more than 10 lots are to be required; and
(b) a development, of a building to be used for commercial or industrial purposes, that a relevant entity considers to be a development in relation to which the average water rate, or average sewage rate, is likely to be greater than the average water rate, or average sewage rate, for 10 equivalent tenements;
relevant entity means the person holding a licence, or an interim licence, granted under the Act;
small development means –
(a) a subdivision, or a proposed subdivision, in relation to which works for the purposes of 10 or fewer lots are to be required; and
(b) a development, of a building to be used for commercial or industrial purposes, that a relevant entity considers to be a development in relation to which the average water rate, or average sewage rate, is likely to be greater than the average water rate, or average sewage rate, for 10 or fewer equivalent tenements;
water and sewerage assets means –
(a) sewerage infrastructure; and
(b) water infrastructure.
9B Service standards
9B Service standards
[Regulation 9B Inserted by S.R. 2020, No. 79, Applied:30 Nov 2020]
(1) If a relevant entity receives from a person a request to provide to the person information in relation to a small development, or the construction of water and sewerage assetsfor a small development, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity provides the information to which the request relates – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, provide to the person the information to which the request relates.
(2) If a relevant entity receives from a person a request to provide to the person information in relation to a large development, or the construction of water and sewerage assetsfor a large development, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity provides the information to which the request relates – within 10 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 20 business days of receiving the request from the person, provide to the person the information to which the request relates.
(3) If a relevant entity receives a request from a person (including a planning authority) to issue the relevant entity’s consent to the sealing or registration of a plan or document that imposes or creates obligations or rights, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity may consent to the sealing or registration of the plan or document – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, consent to the sealing or registration of the plan or document or refuse to consent to the sealing or registration of the plan or document.
(4) If a relevant entity receives from a person a request for approval of the engineering design of a small development, or of water and sewerage assets, of a small development, that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity approves, or refuses to approve, the engineering design of the development or assets – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, approve, or refuse to approve, the engineering design of the development or assets.
(5) If a relevant entity receives from a person a request for approval of the engineering design of a large development, or of water and sewerage assets, for a large development, that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires further information from the person before the relevant entity approves, or refuses to approve, the engineering design of the development or assets – within 10 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 20 business days of receiving the request from the person, approve, or refuse to approve, the engineering design of the development or assets.
(6) If a relevant entity receives from a planning authority a request to provide to the planning authority the relevant entity’s opinion in relation to a proposed amendment, under section 56 of the Land Use Planning and Approvals Act 1993 , of a permit within the meaning of that Act, the relevant entity is to –
(a) if the relevant entity requires further information from the planning authority before the relevant entity provides to the planning authority the relevant entity’s opinion in relation to the proposed amendment – within 7 business days of receiving the request from the planning authority, by notice in writing request the planning authority to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the planning authority, provide, or refuse to provide, to the planning authority the relevant entity’s opinion in relation to the proposed amendment.
(7) If a relevant entity receives from a person a request for an amendment of a certificate for certifiable work (plumbing) or of a certificate for certifiable work (building), the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity amends the certificate or refuses to amend the certificate – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, amend the certificate or refuse to amend the certificate.
(8) If a relevant entity receives from a person a request for a permit to construct water and sewerage assets that are to be transferred to the relevant entity, the relevant entity is to –
(a) if the relevant entity requires information from the person before the relevant entity determines the request from the person – within 5 business days of receiving the request from the person, by notice in writing request the person to provide to the relevant entity the information specified in the notice; and
(b) within 10 business days of receiving the request from the person, issue, or refuse to issue, the permit to construct.