[2025] NSWCATCD 137
General information, not legal advice.
NCAT Consumer and Commercial
2025-11-20
Original judgment source is linked above.
Civil Procedure Act 2005 (NSW)
Home Building Act 1989 (NSW)
Limitation Act 1969 (NSW)
Public Health Act 2010 (NSW)
Civil Liability Act 2002 (NSW)
ACCC v Dataline.Net.Au Pty [2007] FCAFC 146; (2007) 244 ALR 300
Adecco (Australia) Pty Ltd [2017] NSWCA 121
Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613
BKB Constructions Pty Ltd v Sawan [2022] NSWCATAP 103
Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
Brookfield Mutiplex Ltd v Owners Strata Plan 61288 [2014] HCA 36
BuildPlatinum Pty Limited v Micaleff [2021] NSWCATAP 129
Catapult Constructions Pty Ltd v Denison [2018] NSWCATAP 158
Curtis v Potter & Co Pty Ltd t/as Africa Safari Co [2016] NSWCATAP 196
Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185
Deaves v Sigma Group NSW Pty Ltd [2023] NSWCATAP 94
Fisher v N. Phillips and M. Phillips t/as Arise Building Services [2022] NSWCATCD 80
GIO General Limited v Centennial Newstan Pty Ltd [2014] NSWCA 13
GIO General Ltd v Centennial Newstan Pty Ltd [2014] NSWCA 13
Grygiel v Baine [2005] NSWCA 218
Harrison v Melhem [2008] NSWCA 67; (2008) 72 NSWLR 380
Leung v Alexakis [2018] NSWCATAP 11
Mania v NSW Land and Housing Corporation [2022] NSWCATAP 376
Metricon Homes Pty Ltd as trustee for Metricon Unit Trust v Lipari [2024] NSWSC 566
Minifie v Maxwell [2020] NSWCATAP 30
Oikos Constructions Pty Ltd t/as Lars Fischer Construction v Ostin & Anor [2020] NSWCA 358
Onslow v Cullen [2022] NSWSC 1257
Owers-Brown v The Owners-Strata Plan No 92562; Nakkan v The Owners-Strata Plan No 92562 [2025] NSWCATCD 67
Owners-Strata Plan 94800 v Aushome Constructions Pty Ltd [2025] NSWCD 143
Parkview Constructions v The Owners - Strata Plan No 90018 [2023] NSWCA 66
Re Day [2017] HCA 2; (2017) 340 ALR 368
Sabouni v Revelop Building and Developments Pty Limited [2021] NSWSC 31
Shakiri v Holland [2024] NSWCATAP 28
Syed Ahmad Shoaib Ali Pty Ltd v Jandson Pty Ltd; Jandson Pty Ltd v Syed Ahmad Shoaib Ali Pty Ltd [2018] NSWCATAP 228
Syed Ahmad Shoaib Ali Pty Ltd v Jandson Pty Ltd; Jandson Pty Ltd v Syed Ahmad Shoaib Ali Pty Ltd [2018] NSWCATAP 228
The Owners - Strata Plan 87003 v Raysons Constructions Pty Ltd [2025] NSWSC 66
The Owners - Strata Plan 99960 v SPS Building Contractors Pty Ltd [2024] NSWSC 687
The Owners - Strata Plan No 66375 v King [2018] NSWCA 170
The Owners-Strata Plan No 61288 v Brookfield Australia Investments Ltd [2013] NSWCA 317
The Owners-Strata Plan No 62930 v Kell & Rigby Holdings Pty Ltd [2010] NSWSC 612
The Owners-Strata Plan No 66375 v Suncorp Metway Insurance Ltd (No 2) [2017] NSWSC 739
The Owners-Strata Plan No 93227 v In Style Developments Pty Ltd [2023] NSWCATCD 154
The Owners-Strata Plan No 84674 v Pafburn Pty Ltd [2023] NSWCA 301
Pafburn Pty Ltd v The Owners-Strata Plan No 84674 [2024] HCA 49
Zone Q Milsons Point Development Pty Ltd (Second Respondent)
Southern Cross Climate Control Pty Ltd (Respondent)
Zone Q Milsons Point Development Pty Ltd (Applicant)
Case Number 2022/00400982; Case Number 2023/00385628; Case Number 2023/00414656
(1) Emails between the builder and the sub-contractor for the period between 23 April 2021 and 4 June 2021 including correspondence form Ms Samson, accountant.
(2) Supplementary report by Mr Marshall (expert of the sub-contractor) dated 28 August 2024.
(1) Statutory declaration of Mr Tabet dated 8 August 2024.
(2) Affidavit of Ms Lai dated 4 August 2024.
(1) Mechanical services report of MEFP Engineering Services dated 8 June 2023.
(2) A revised report of MEFP Engineering Services. According to Mr Tabet, the report was received on about 23 June 2023, but the date of the report was again 8 June 2023.
(3) Mechanical as built drawings for the strata building, fire damper schedule, and apartment fan commissioning schedule and stair pressurisation commissioning report.
(1) The contract between the developer and the builder for the design and construction of the strata building dated about 15 December 2017.
(2) Various expert reports that had been obtained by the owners corporation and sent to the developer. Those reports were:
(a) Noviion Engineering dated 3 November 2022 and 7 February 2023.
(b) Mr David Wood dated 7 July 2023 and
(c) Mr Darren Miles dated 21 June 2023.
Owners Corporation's Claim Against Builder and Developer
48K Jurisdiction of Tribunal in relation to building claims
(1) The Tribunal has jurisdiction to hear and determine any building claim brought before it in accordance with this Part in which the amount claimed does not exceed $500,000 (or any other higher or lower figure prescribed by the regulations).
(2) The Tribunal has jurisdiction to hear and determine any building claim whether or not the matter to which the claim relates arose before or after the commencement of this Division, except as provided by this section.
(3) The Tribunal does not have jurisdiction in respect of a building claim relating to building goods or services that have been supplied to or for the claimant if the date on which the claim was lodged is more than 3 years after the date on which the supply was made (or, if made in instalments, the date on which the supply was last made).
(4) The Tribunal does not have jurisdiction in respect of a building claim relating to building goods or services that are required under a contract to be supplied to or for the claimant on or by a specified date or within a specified period but which have not been so supplied if the date on which the claim was lodged is more than 3 years after the date on or by which the supply was required under the contract to be made or, if required to be made in instalments, the last date on which the supply was required to be made.
(5) The fact that a building claim arises out of a contract that also involves the sale of land does not prevent the Tribunal from hearing that building claim.
(6) The Tribunal does not have jurisdiction in respect of a building claim arising out of a building cover contract required to be entered into under this Act if the date on which the claim was lodged is more than 10 years after the date on which the residential building work the subject of the claim was completed.
(7) The Tribunal does not have jurisdiction in respect of a building claim arising from a breach of a statutory warranty implied under Part 2C if the date on which the claim is lodged is after the end of the period within which proceedings for a breach of the statutory warranty must be commenced (as provided by section 18E).
(8) The Tribunal does not have jurisdiction in respect of a building claim relating to -
(a) a contract for the supply of goods or services to which none of subsections (3), (4), (6) and (7) applies, or
(b) a collateral contract,
if the date on which the claim was lodged is more than 3 years after the date on which the contract was entered into.
(9) This section has effect despite clause 5 (Relationship between Tribunal and courts and other bodies in connection with Division functions) of Schedule 4 to the Civil and Administrative Tribunal Act 2013.
Breach of Statutory Warranty-Applicable Principles
18B Warranties as to residential building work
(1) The following warranties by the holder of a contractor licence, or a person required to hold a contractor licence before entering into a contract, are implied in every contract to do residential building work -
(a) a warranty that the work will be done with due care and skill and in accordance with the plans and specifications set out in the contract,
(b) a warranty that all materials supplied by the holder or person will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new,
(c) a warranty that the work will be done in accordance with, and will comply with, this or any other law,
(d) a warranty that the work will be done with due diligence and within the time stipulated in the contract, or if no time is stipulated, within a reasonable time,
(e) a warranty that, if the work consists of the construction of a dwelling, the making of alterations or additions to a dwelling or the repairing, renovation, decoration or protective treatment of a dwelling, the work will result, to the extent of the work conducted, in a dwelling that is reasonably fit for occupation as a dwelling,
(f) a warranty that the work and any materials used in doing the work will be reasonably fit for the specified purpose or result, if the person for whom the work is done expressly makes known to the holder of the contractor licence or person required to hold a contractor licence, or another person with express or apparent authority to enter into or vary contractual arrangements on behalf of the holder or person, the particular purpose for which the work is required or the result that the owner desires the work to achieve, so as to show that the owner relies on the holder's or person's skill and judgment.
(2) The statutory warranties implied by this section are not limited to a contract to do residential building work for an owner of land and are also implied in a contract under which a person (the principal contractor) who has contracted to do residential building work contracts with another person (a subcontractor to the principal contractor) for the subcontractor to do the work (or any part of the work) for the principal contractor.
Although objective standards such as Australian Standards, the Building Code of Australia and the Guide are of significant relevance in establishing whether work has been performed in a proper and workmanlike manner (Wheeler v Ecroplot Pty Ltd [2010] NSWCA 61 at [10]), the absence of such evidence does not automatically mean a homeowner has failed to establish breach of statutory warranty. In our view, the relevant principle was succinctly stated by Senior Member Goldstein in G MacFayden and Anor v G Tadrosse [2014] NSWCATCD 194 at [46] as follows:
...[E]vidence that work does not comply with the Building Code of Australia would establish a basis for a finding that sub section 18B(c) of the Act has been breached. Evidence of the details in which work does not comply with the contractual plans and specifications would form the basis for a finding that sub section 18B(a) of the Act has been breached. Evidence of work not being carried out in a proper and workmanlike manner would in my view involve identification of the work in question, a statement of how the expert would expect it to be carried out in in a proper and workmanlike manner and then identification of the factors which establish that the way in which the work has been carried out falls short of it being carried out in a proper and workmanlike manner. Evidence of this nature, if accepted, would form the basis for a finding that sub section 18B(a) of the Act has been breached.
"A defect or deficiency is manifested in the structure of the building. A breach of warranty is a conclusion involving one or more of the statutory warranties implied by s 18B (read with ss 18C and/or 18D) concerning the way in which the building was designed or constructed.
That is to say, a defect or deficiency is a physical thing (or the absence of a physical thing). A breach of warranty is a legal conclusion about the way in which residential building work has been performed (or not performed)."
19 Designs and design compliance declarations to be obtained
A building practitioner must not, except with reasonable excuse, carry out any part of building work for which a regulated design is to be used unless -
(a) the practitioner has obtained a design from a registered design practitioner for the work and a design compliance declaration for the design from a registered design practitioner whose registration authorises the practitioner to provide a declaration as to the matters to which the declaration relates, and
(b) the declaration states that the design complies with the requirements of the Building Code of Australia and other applicable requirements prescribed for the purposes of section 8(1).
Maximum penalty - 1,500 penalty units (in the case of a body corporate) or 500 penalty units (in any other case).
7 Building practitioners
(1) In this Act, building practitioner means -
(a) a person who agrees under a contract or other arrangement to do building work, or
(b) if more than one person agrees to do building work, a person who is the principal contractor for the work.
...
48O Powers of Tribunal
(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate -
(a) an order that one party to the proceedings pay money to another party or to a person specified in the order, whether by way of debt, damages or restitution, or refund any money paid by a specified person,
(b) an order that a specified amount of money is not due or owing by a party to the proceedings to a specified person, or that a party to the proceedings is not entitled to a refund of any money paid to another party to the proceedings,
(c) an order that a party to the proceedings -
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.
(2) The Tribunal can make an order even if it is not the order that the applicant asked for.
(3) Sections 79R and 79T-79V of the Fair Trading Act 1987 apply, with any necessary modifications, to and in respect of the determination of a building claim.
95 Joint liability
(cf Act No 52 1970, section 97)
(1) If two or more persons have a joint liability and, in any proceedings, judgment on the liability is given against one or more but not all of them -
(a) the liability of the other or others of them is not discharged by the judgment or by any step taken for the enforcement of the judgment, and
(b) after the judgment takes effect, those of them against whom the judgment is given and the other or others of them become liable, as between those of them against whom the judgment is given on the one hand and the other or the others of them on the other hand, severally but not jointly, and
(c) if there are two or more such persons against whom the judgment is not given, they remain, after the judgment takes effect, jointly liable amongst themselves, and
(d) if the judgment is satisfied wholly or in part by payment or by recovery under execution, the liability of the persons against whom the judgment is not given is taken also to have been satisfied in the amount of the payment or recovery.
(2) This section does not affect a person's right to contribution or indemnity in respect of the person's satisfaction, wholly or in part, of a liability that the person has (whether jointly or severally or jointly and severally) with any other person.
(3) This section does not apply to a judgment to which section 5 (1) (a) of the Law Reform (Miscellaneous Provisions) Act 1946 applies.
(4) In this section, liability includes liability in contract, liability in tort and liability under a statute.
In Little v J & K Homes Pty Ltd [2017] NSWCATAP 84, at [28] the Appeal Panel stated:
Alternatively, s 48O(1)(c)(ii) is clearly intended to authorise the making of orders having wider operation than requiring the performance of building work by the builder. That provision would authorise an order that the builder cause specified work to be completed.
Further in Howe v NSW Coastal Homes Pty Ltd [2016] NSWCATAP 127 the Appeal Panel, at [21] commented upon the breadth of the discretion of the Tribunal when considering making orders pursuant to section 48O of the Act in terms:
Firstly, section 48O of the Home Building Act permits the Tribunal to make a work order to rectify any defective work, but does not require that the Tribunal make such an order. The exercise of that power is a matter of discretion and dependent upon the evidence and findings made by the Tribunal: see for example Jubian v Clark; Clark v Jubian [2016] NSWCATAP 56 at [43]. The power to make such an order against a party, as was made in this matter, relying upon section 48O, was undoubted by the plurality of the Court of Appeal in Italiano v Carbone & Ors [2005] NSWCA 177.
...
Subsection 48O(c)(ii) refers to an order to "do or perform" ..."any specified act, matter or thing", which appears to permit a wider category of actions which might be the subject of an order. Any such order would however have to be based upon some liability to undertake the action on the party who is required to comply. There would need to be some nexus between the necessity for action and a legally enforceable duty to act. There does not seem to be any such nexus involved in the terms of the Orders insofar as they require the builder to engage engineers to advise as to the means of rectification.
Although the Tribunal has wide powers under section 48O of the Act to "determine" a building claim by way of making an order that "specified work" or "specified services" be performed by the builder, an order that a builder engage experts and rectify work in accordance with the recommendations of such experts engaged by the builder should not be made unless the Tribunal identifies a proper basis for such an order. The Tribunal must clearly articulate how such an order is a practical and certain resolution of the dispute to put the homeowner in the position the homeowner should have been had the builder performed its obligations under the contract, particularly if the homeowner has not provided evidence in regards to the manner of rectification of the defect(s).
If it is considering such an order, rather than making an alternative order such as adjourning the proceedings so that the homeowner can obtain evidence regarding a scope of works to rectify the breach by the builder, the Tribunal must be very cautious to avoid any perception that the homeowner in Tribunal proceedings only has to prove that defective work by the builder has occurred, and that it then becomes the responsibility of the builder to establish how to rectify the defect, including the builder engaging expert evidence in that regard. The evidentiary onus remains on the homeowner to prove both breach (i.e. what is the defective work) and the method of rectification (so that the Tribunal can make an appropriate work order for rectification of the defective work; or if a work order is not the preferred outcome, assess damages according to the principles set out in Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613). However, in the circumstances of this matter, there was some evidence (as discussed below) before the Tribunal regarding an appropriate scope of works to rectify the defect.
"In The Owners of Strata Plan No 97315 v Icon Co (NSW) Pty Ltd [2023] NSWCA 303 at [12], Bell CJ (with whom Meagher and Adamson JJA agreed) observed that the qualification as to reasonableness is not confined to the situation described in Tabcorp v Bowen Investments, stating that:
"While it is accepted that the qualification will only apply in 'fairly exceptional circumstances,' it is not confined to where a plaintiff is seeking to rely upon a technical breach to secure an uncovenanted profit."
In that regard, his Honour quoted a passage from the decision of Gleeson JA (with whom White JA and Basten AJA agreed) in Owners SP 92450 v JKN Para 1 Pty Ltd [2023] NSWCA 114 at [67]- [70], which included, relevantly, the following observations at [70]:
"Tabcorp at [16] referred by way of an example of unreasonableness to the situation where the innocent party was 'merely using a technical breach to secure an uncovenanted profit', citing Oliver J in Radford v De Froberville [1977] 1 WLR 1262. Other examples include where the cost of the 'proposed rectification is out of all proportion to the benefit to be obtained': Brewarrina Shire Council v Beckhouse Civil Pty Ltd [2006] NSWCA 361 at [87]- [88], citing South Parklands Hockey & Tennis Centre Inc v Brown Falconer Group Pty Ltd [2004] SASC 81 at 90 (Debelle J); and Scott Carver Pty Ltd v SAS Trustee Corporation [2005] NSWCA 462 at [120] (Ipp JA); see also Wheeler v Ecroplot Pty Ltd [2010] NSWCA 61 at [81] (Macfarlan JA, McColl and Basten JJA agreeing). For a recent application of this principle in this Court, see Renown Corporation Pty Ltd v SEMF Pty Ltd [2022] NSWCA 233."
In Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2006] NSWCA 361 at [89], Tobias JA (with whom Giles and McColl JJA agreed) observed that:
"In summary, the authorities to which I have referred stand for the proposition that whether the rectification work is a reasonable course to adopt is dependent upon a finding of fact that the proposed work was reasonable in order to achieve the contractual objective. The rectification work would be unreasonable if it was out of all proportion to the achievement of that objective or to the benefit to be obtained therefrom."
Has Breach of Statutory Warranty Been Established By the Owners Corporation And If So, What is the Appropriate Remedy?
Alleged Defect M1-Non-Complying Access to Fan Coil Units and Filters
(a) It is not possible to remove or replace the fans and pumps within the fan coil unit without removing the bottom access panel provided by the manufacturer, and this is not possible without a large access panel directly below the FCU; and
(b) Convenient access is necessary to ensure the health and safety of tradespersons doing maintenance on the FCU.
(1) Contrary to manufacturer recommendations.
(2) Contrary to Australian Standard AS 3666.1 and the requirements of the Public Health Act 2010 (NSW).
(3) Indicative of the builder not performing work with due care and skill
Defect
Agreed defect
Rectification Concept
The experts agree that where agreed by each individual lot owner, the rectification concept provided by in the Warner report is appropriate.
Comments
The experts agree that this is primarily a design defect associated with the ceiling of the apartments. Mr Jacotine comments that the design of the ceiling and access panels was completed prior to SCCC being engaged to undertake their works. The experts agree that there is potential that some owners may be unhappy with the installation of access panels, and this is why we have included consultation with the owners.
"Ward J is not to be understood as stating a principle of law in Kell & Rigby. The point made by her Honour is simply that on the facts of that case, she was not satisfied that it could be inferred from the evidence that the identified defect was present in all bathrooms, including those that had not been examined."
"[15] However, the seriousness of an allegation made, the inherent unlikelihood of an occurrence of a given description, or the gravity of the consequences flowing from a particular finding are considerations which must affect the answer to the question whether an issue has been proved to the reasonable satisfaction of the tribunal...
[18] The tribunal must feel an actual persuasion of the occurrence or existence of a fact before it can be found. Where direct proof is not available and satisfaction of the civil standard depends on inference, "there must be something more than mere conjecture, guesswork or surmise" - there must be more than "conflicting inferences of equal degrees of probability so that the choice between them is [a] mere matter of conjecture." An inference will be no more than conjecture unless some fact is found which positively suggests, or provides a reason in the circumstances particular to the case, that a specific event happened or a specific state of affairs existed."
Builder's Solicitor: I understand that's your evidence on the 17 units you inspected, but you actually haven't inspected the other units, have you?
Warner: No, I've only looked at the plans in those.
Builder's Solicitor: So in respect of the units you didn't inspect, you wouldn't be able to say, would you, whether or not there was access that allowed maintenance, would you?
Warner: Well, based on the probability of that I would, yes.
Builder's Solicitor: Well, you haven't seen the units, have you?
Warner: Well, you know, probability is a, is a part of engineering science and if you compare it to flipping a coin, the probability is about that type of thing. So if you flip a coin and get heads 17 times in a row there's either something wrong with the coin or it's a very improbable event, so-
Builder's Solicitor: Yes, but you haven't been into the apartments to see.
Warner: No I haven't, no but I'm-
Builder's Solicitor: But if you went-
Warner: Trying to explain to you why it's my opinion that this would be a systemic issue. I've looked at the drawings, I can see on the drawings all the way through, and on the basis of every single one of them was defective, the probability is-it's a very strong probability that it's defective in those others as well.
Builder's Solicitor: You can see the access panels on the drawings, can you?
Warner: Yes, there are.
...
Alleged Defect M2-Non Complying Refrigeration Pipework Insulation
(1) PairCoil that is "characterised by its white coloured covering that has a textured appearance."
(2) A "similar product" to PairCoil, that has a black textured covering; and
(3) K-Flex ST that is a "black elastomeric foam product."
"It is my opinion that a contractor should have been aware of the BCA requirements for particular Fire hazard properties and insulation values when considering the type of refrigeration pipework insulation, and by applying due diligence and due care would have determined the PairCoil type insulation (both the white Standard PairCoil and the black textured product) was not tested to confirm compliance with the BCA requirements for Fire hazard properties, did not meet the required insulation values, and was therefore unsuitable to install in the Strata Scheme.
Further to this it is my opinion that a contractor should have been aware of the BCA requirements for particular insulation values and when considering the type of refrigeration pipework insulation, and by applying due diligence and due care would have determined that the K-Flex insulation of insufficient thickness (e.g. less than 19mm thickness for a 15 mm pipe) was therefore unsuitable to install at the Strata Scheme.
In terms of the insulation values for the various types of pipe insulation installed at the Strata Scheme, this is a technical defect. However, I acknowledge that rectifying this defect may not provide significant returns to the Owners compared to the significant inconvenience of the rectification works.
I further acknowledge that, in terms of fire hazard properties of the pipe insulation, it may be possible to provide a fire engineered solution to achieve a performance solution."
"In my opinion, rectification of this defect involves an aspect of the building element that is required to achieve compliance with the BCA, and therefore the DBPA requires the preparation of a Regulated Design for the rectification works."
systemic defect." However, it is clear from his report that the scope of works identified is subject to a suitably qualified person preparing a design under the provisions of DBP Act. 2. In the Joint Scott Schedule prepared with Mr Jacotine, Mr Warner states, as the first item in the proposed scope of works:
"Engage an appropriately qualified and experienced person to prepare a Regulated Design for the rectification works."
Defect
Agreed defect.
Rectification concept
1. In respect of the fire performance, it may be possible to undertake a fire engineering performance analysis report that would support the insulation material remaining in the building. This would need to be introduced to the building's approval via a CDC or DA/CC.
2. In the alternative, if the fire engineer process is unable to support the insulation material remaining in the building, under take the removal and replacement of the insulation material described in the Warner report of 7 September 2023".
(1) Standard Pair Coil;
(2) Pair Coil Max;
(3) K-Flex ST;
(4) Aramaflex FRV;
"I agree with Ross Warner (paragraph 149 of his report) that the Standard Pair Coil pipe insulation does not have an AS 1530.3:1999 test to meet the required fire indices to support its use in a Class 2 building such as (the strata building). I therefore agree the use of the Standard Pair Coil is a defect."
(1) He observed Standard Pair Coil White; and also observed Standard Pair Coil Black within unit 902, on the rooftop plantroom; and within the common corridor on Level 9.
(2) At paragraph 24 of his report of 28 August 2024, Mr Marshall conflated Pair Coil and Pair Coil Max as a single product. They are two separate products. However, Mr Marshall did not observe any Pair Coil Max in his investigation.
(3) Although Mr Marshall did not observe any Standard Pair Coil in the common areas "in the white colour," he observed "Standard Pair Coil that was black within the common corridor of level 9 and in both the lower and rooftop plantroom locations.
(4) Mr Marshall now considers that a "performance solution" can be developed to retain Standard Pair Coil on the rooftop plantroom. However, he does not identify what that "performance solution" is, or provide a scope of works.
There is sufficient evidence as to what is required to be done to provide a Performance Solution for the purpose of making an order that is sufficiently certain and specific. A fire performance analysis is to be carried out and a report prepared (TB 1452). The NCC sets out the assessment methods that are available to address the relevant performance requirements (TB 166 [46]). The fire safety schedule would be prepared referring to the Performance Solution and an updated occupation certificate issued. If, the analysis requires some work, the party who is subject to the order would be responsible for carrying out that work and the costs involved in any part of the process. Thes steps are easy to understand and the results as to compliance measurable.
The removal and replacement "rectification concept," while like the Performance Solution, will remedy the defect, it would do so at a substantial disruption to the unit owners, their property and costs for no material benefit from a fire risk perspective compared to the current situation. In the circumstances, such a work order would be unreasonable (TR2 27). The only circumstances it should be ordered is if the Performance Solution order is not complied with."
(1) There is a mixture of types of pipe insulation in the building, as set out in the reports of Mr Warner and Mr Marshall.
(2) Of those types of pipe insulation Standard Pair Coil (both Black and White) does not meet Australian Standards, because it has not been tested and certified as appropriate for Class 2 buildings. The Tribunal does not accept the submission of the builder that it is only White Standard Pair Coil that is non-compliant with the BCA because it has not been tested. That is not a fair reflection of the evidence of Mr Warner in his report, nor what he said at the hearing (T:28/8/24:L15-17; T:28/8/24:P37:L42-45). The evidence of Mr Jacotine and Mr Marshall is consistent with the evidence of Mr Warner that Standard Pair Coil (whether White or Black) does not comply with the BCA, rather than a distinction being drawn between compliant "Black" and non-compliant "White." That is sufficient to establish breach of statutory warranties under s 18B(1)(c) of the HB Act.
(3) There is a further defect in the pipe insulation where K-Flex insulation of insufficient thickness (e.g. less than 19mm thickness for a 15 mm pipe) has been used. That is also failure to comply with the BCA (because the Tribunal accepts the evidence of Mr Warner, which Mr Jacotine agrees with) although the insulation has been tested, it is of insufficient thickness to comply with the applicable Australian Standard.
(4) In respect of both the areas of pipe insulation where Standard Pair Coil and insufficiently thick K-Flex have been used, the work has also not been performed with due care and skill as a builder exercising due care and skill would have ensured that it used pipe insulation material that had been tested and was suitably compliant with the BCA (s 18B(1)(a)) of the HB Act.
(5) The defect is a systemic defect throughout the building. The Tribunal accepts the evidence of Mr Warner in this regard, for equivalent reasons that were expressed in respect of Item M1.
(6) In respect of Standard Pair Coil insulation, there is a mixture of White and Black. Even if the Tribunal was satisfied that only White was non-compliant with the BCA, the evidence does not establish that the mixing of insulation could be easily separated such that one type of insulation removed. If there was removal, it would involve both White and Black.
(7) All experts agree that there are further testing and potential works that may achieve a "performance solution" with the BCA in respect of the Standard Pair Coil. However, the Tribunal does not accept the submission of the sub-contractor that the "performance solution" can be easily and clearly defined.
Alleged Defect M3-Incorrect Size Condensate Drains to Fan Coil Units
Defect
Agree that this is a technical defect
Rectification Concept
Refer comments
Comments
The experts agree that this is a technical defect that is unlikely to cause an ongoing loss to the owners. The 20mm drain size is expected to be adequate for the installed unit sizes.
The experts agree that the work required to replace the drains would be unnecessarily disruptive and would be unlikely to provide any tangible benefit to the owners.
It is further agreed that a performance solution to deal with this issue would be permitted in other states under the BCA hover in NSW because the issue is covered by the PHA and AS3666, a performance solution is not technically permitted.
For the above reasons we have not provided a rectification concept to this defect.
Owners Corporation Counsel: So you say it's a defect?
Warner: It's a technical defect, yes.
Owners Corporation's Counsel: What does "technical defect" mean?
Warner: Yes, I know, its-so it's, it's a breach of the legislation and the Code that is not likely to result in tangible loss or problem for the owners.
Owners Corporation's Counsel: Just so the Member can perhaps understand the problem in lay terms?
Warner: The-there's the potential for more blockages or more frequent blockages when the pipe diameter starts to get smaller. There's also a potential for the pipe to start to boy(sic) between, between support points, which creates like a little dip where again you may get material forming as the moisture evaporates of its little tray there. But at 20 millimetres I'm quite satisfied that it's an arrangement that will perform adequately".
Builder's Solicitor: I'm not sure. I don't want to mislead you. Does that say 20 millimetres is okay? I don't think that's the right reference. I might've misled you. You can just flick through the following pages because that's where you put your documentation. I'm just looking for the recommendation you are referring to. Is it on tender bundle page 436
Warner: I'm just checking that. Yes. Yeah. So it says 32-millimeter OD and ID of 25 millimetre. And the, the logic there that Mr Jacotine and I, correct me if you think I'm wrong-
Jacotine: Yeah
Warner: Mr Jacotine, was that if it's okay for the smaller sized units that are on page 430 of the bundle, you know, why isn't it logically required to be larger when they're pretty much the same capacity for the units that are on 436 of the bundle? So that's why we, we agree that in this case it probably wouldn't cause any issue for the owners should they decide not to press the issue.
Alleged Defect M4-Condensate Drains Do Not Terminate at Air Gap
"I recommend that this defect also be referred to an Hydraulics Expert for review. The arrangement of the sewer pipework under the sinks and through the slab may not be complying."
"Comments
The experts agree that the plumbing contractor has not provided a typical tundish, which we would expect to have a conical shape where there is a larger opening at the top to accept the condensate. On this basis, the experts agree that it would be preferrable for a plumbing contractor (be) engaged to modify the sanitary drainage pipework cap and facilitates the necessary 40mm airgap".
Alleged Defect M6-Non-Complying Flexible Duct Installation
"...has a requirement that these types of installations are carried out in accordance with AS 4254.1, which is a flexible duct Standard, and that Standard requires a flexible duct if fixed that there be a device called a draw band, which is a bit like a cable tie or Utilux type clip, to support the ductwork and hole (sic) in place mechanically and then tape is only used as a sealing mechanism over the top of that arrangement. I observed a number of installations were it was not done that way."
Defect
Agreed defect
Rectification concept
Inspect the ductwork in each apartment to determine the locations where draw bands are not installed in accordance with AS4254.1 and where it is determined that they are missing, undertake the works described in the Warner report.
Alleged Defect M9-Non-Balancing Dampers in Mechanical Ventilation Systems
"In my opinion, rectification of this defect involves an aspect of a building element that is required to achieve compliance with the BCA, and therefore the DBPA requires preparation of a Regulated Design for the rectification works."
"Engage an appropriately qualified and experienced person to prepare a Regulated Design for the rectification works."
"Defect
Agreed defect
Rectification concept
The experts agree with the following modified rectification concept:
Engage an appropriately qualified and experienced mechanical services engineer to produce a Regulated Design for the rectification works.
Travel to the site to assess the works.
Obtain the required quality of a suitably sized balancing dampers and fabricated sheet metal grille surrounds (to facilitate the depth of the new damper and to permit inspection of the fire damper vial a spring clip).
Attend site to conduct the works.
Disconnect the grilles.
Install the new balancing dampers.
Install spring mounted grille surrounds and paint to match wall colour.
Reinstall the grilles.
Set the balancing dampers to achieve the required air flow rates to each room served, based on the original design (air balancing).
Make good and clean up.
Update the "as installed" drawings and Operations & Maintenance Manual."
Jacotine: I couldn't see it but, there's a grill, there's a fire damper, and exactly where it connects to the riser, I can't physically see whether there's a balancing damper hidden somewhere behind there. To be honest, I can't be certain."
"Despite the expert's agreement that balancing dampers are required and a failure to provide them with a defect, there is no evidence that they are not present in the system and no evidence the system is not correctly balanced."
Alleged Defect Item M11-Pipe Insulation Exposed to Weather and Sunlight
Alleged Defect Item M13-Non-Complying Fire-Rated Stair Pressurisation Fan
"In my opinion, rectification of this defect involves an aspect of a building element that is required to achieve compliance with the BCA, and therefore the DBPA requires preparation of a Regulated Design for the rectification works."
(1) it does not fall within the sub-contractor's contractual scope of works with the builder; and
(2) it is not a "major defect" under s 18E of the HB Act.
Alleged Defect Item M14-Diesel Pump Room Ventilation Non-Operational During Loss of Electrical Power
"If this defect was not rectified, there would be an increased level of risk during a fire, and it might not be possible to obtain correct annual fire safety statements.
The Builder should have installed a power supply system that was capable of operating the fan during a simultaneous fire/power failure scenario.
The Builder should have engaged an appropriately qualified and experienced mechanical engineer to review the mechanical services design (and drawings) and to conduct regular site inspections to ensure compliance with statutory requirements was achieved.
...
The rectification concept for this defect is to provide a UPS to allow the fan to operate for the necessary time during a fire scenario (when there is a simultaneous building power failure), or as an alternative, provide a fan that can operation on 12-volt DC current and connect this to an alternator installed on the diesel pump motor".
Defect
The experts agree that the existence of a defect must be confirmed by testing the conditions in the room at full load while the ventilation fan is not operational.
Rectification concept
The experts agree that should testing of the temperature rise in the diesel pump room indicate that there is adequate ventilation (for temperature control without mechanical ventilation), then there is no need for rectification work.
In the alternative, if temperature testing indicates that there is inadequate ventilation (for temperature control without mechanical ventilation) then adopt either, on of the two rectification concepts provided in the Warner report, or replace the double door to the diesel pump room with louvre doors to allow the heat to dissipate into the car park."
"The experts agree that the diesel pump room ventilation would not be operational during a loss of electrical power to the building and that the diesel pump needs to operate under such circumstances. We also agree that the temperature within the diesel pump room must not exceed certain limits during operation, and that ventilation is one method of achieving suitable room temperature.
The experts agree that the applicable standards do not specifically provide requirements for ventilation to diesel pump rooms. The need to ventilate such rooms can be interpreted as an implied requirement that should be obvious during the application of due diligence during design.
The experts agree that there is a possibility that the room temperature rise during pump operations may be slowed as a result of thermal intertia of the room, and therefore it may not be necessary to provide mechanical ventilation. This could easily be tested.
(1) Mr Jacotine does not clearly agree there is a defect, in the sense that a builder, exercising reasonable care and skill, would have installed a separate back up power source.
(2) Both experts say in the Joint Scott Schedule that the existence of a defect "must be confirmed" by testing the room, and no such testing has occurred;
(3) Mr Warner's comment at paragraph [470] of his report that the builder should have engaged an expert to "review" the design and conduct "regular site inspections" is not sufficient for the Tribunal to be satisfied a builder exercising due care and skill would have taken such measures, and even if the builder had done so, there would have been a backup power source installed;
(4) There was no clear agreement between the experts at the hearing of the existence of a defect by reason of the failure to install the backup power source; and
(5) Neither expert's opinion was more logical, rational or probative that the other expert on the issue of whether a builder exercising due care and skill would have installed a separate back up power source,
Alleged Defect Item M15.1 and M15.2-Non-Complying Ventilation to Some Enclosures
(1) The cleaners room on the lower ground level;
(2) The plant room and its antechamber on the lower ground level; and
(3) The water meter room on the lower ground floor.
"In my opinion, each of these rooms has a reason why it might be occupied by a person, either to maintain/repair/operate equipment contained in the room or for other similar reasons. On this basis it is my opinion that BCA Clause F4.5 requires each to be ventilated.
None of the rooms that I have noted above as having non-compliant ventilation are connected directly to outside via openings (such as those required by BCA clause F4.6(a)(ii)) and therefore it is not possible for them to be naturally ventilated in accordance with BCA clause F4.6.
On the basis that natural ventilation has not been provided and compliance with BCA cause F4.5 is required, this in my opinion only leaves the option of providing mechanical ventilation in accordance with the requirements of AS 1688.2-2012".
"In my opinion, rectification of this defect involves an aspect of a building element that is required to achieve compliance with the BCA, and therefore the DBPA requires the preparation of a Regulated Design for the rectification works."
"Defect
Agreed defect.
Rectification concept
The experts agree that a capacity test of the nearby toilet exhaust system should be undertaken, and if this indicates that the additional air flow demand for the cleaner's room could be accommodated by the toilet exhaust system then the following rectification concept would apply:
Engage an appropriately qualified and experienced person to prepare a Regulated Design for the rectification works, which would include:
Visit site to investigate the works and measure up.
Prepare workshop drawings for the works.
Procure the necessary ductwork, grille, mounting hardware and other materials as required.
Attend site to conduct the works.
Create the required penetration for passage of ducts (building work)
Connect the new flexible ductwork and grille to the ceiling in the cleaner's room and the existing toilet exhaust system in accordance with the regulated design and the workshop drawings.
Test and commission the mechanical ventilation systems to ensure the required airflow is achieved.
Make good and clean up.
Update the "as-installed" drawings and the operations maintenance manual.
In the event that capacity testing of the nearby toilet exhaust system indicates that it is unable to accommodate the required airflow rate for the cleaner's room, the rectification concept in the Warner report should be applied."
"I would generally provide ventilation of a storeroom" (T:28/8/24:P96:L6); and
"My only thing about this was that...I agreed with Mr Warner that it's a defect..." (T:28/8/24:P96:L44-45).
(1) What is the intended use of a room is to be determined at the date of the contract, not a future time.
(2) The plans make no reference to the use of the room.
(3) The room was "not designed for habitation, in the normal sense of that word."
(1) The plans make no reference to the use of the room.
(2) It is "difficult to see" how the room falls within the definition in BCA F4.5.
(3) The scope of works proposed by Mr Warner involves engaging the preparation of a design under the DBP Act, and "does nothing more than simply require some other professional to work out what is required." The proposed scope is too vague and uncertain to make a work order.
Alleged Defect Item M16.1 and M16.2-No Filters in Various Supply Air Ventilation Systems
(1) The carpark supply air system that includes fan CSF-G located in the plant room on ground level.
(2) The lobby supply air system that includes fan LSF-R.1 located in the roof plant enclosure.
"equipment providing air movement (such as a fan) and;
as well as equipment for the purpose of controlling the direction, rate of airflow, division of airflow, and condition of air (such as grilles, balancing dampers, cooling/heating coils etc)."
"AS 3666.1 clause 1.5.4 defines air handling system as "A system for the purpose of directing air in a positive and controlled manner to and from specific enclosures by means of air handling plants, ducts, plenums, air-distribution devices and control devices." In my opinion, this applies to the mechanical ventilation systems for the enclosures listed above. In the specific case of the carpark, the air handling system includes the supply air system and the exhaust system which jointly serve to direct air "in a positive and controlled manner to and from" the enclosure (the carpark)."
Alleged Defect Item M17-Non-Complying Access to Air Conditioning Condensers
(1) "Negotiations with Council" to "establish if there are any limitations associated with extending either the plan dimensions, or the height of the louvre enclosure on the roof to make more room for the access to the equipment located therein." Mr Warner comments that his rectification concept "assumes there is scope to expand the volume of this enclosure."
(2) Engaging an Architect to "prepare drawings and liaise with Council;"
(3) Engaging a Structural Engineer to "prepare drawings of the necessary support system for the new louvre locations."
(4) Producing mechanical services workshop drawings of the necessary works and submitting them to Council for approval. Mr Warner states that "Development consent is likely to be required from Council."
Alleged Defect Item M19-Condensor Unit Plant Room Has Inadequate Openings to Outdoors
"In my opinion the failure to provide adequate ventilation for the condenser units is a defect that must be rectified. A competent and experienced designer, exercising due diligence would have realised that adequate ventilation of the plant room and/or careful placement of the condenser units was critical to the proper operation of the air conditioning systems, and would have designed the systems accordingly."
(a) Increase the ventilation provisions to the plant room sufficiently to maintain reasonable temperature at all times, or
(b) Relocate some or all of the condenser units to a location which will provide sufficient ventilation and not subject them to excessive heat."
Alleged Defect Item M20-Excessive Corrosion on Equipment
"The rectification concept for this defect is likely to involve replacing the corroded fittings and fixtures with new fittings and fixtures manufactured from appropriate corrosion resistant materials (such as stainless steel, or mild steel that has been appropriately galvanized). In some cases, it may be sufficient to treat and remove the corrosion, then paint with a corrosion resistant coating (cold galvanizing, paint etc as appropriate."
Defect
Agreed defect
Rectification concept
The experts agree with the associated rectification concept in the Warner Report
Comments
The experts would like to note the importance of the relocation of the sewer vents as described in Defect M10. If the vents were not relocated, the corrosion of the nearby ductwork would return."
Alleged Defect Item M22-Non-Complying Stair Pressurisation Relief Systems
"smoke exhaust system inlets shall be located at a high level within the smoke control zone."
"In my opinion, rectification of this defect involves an aspect of a building element that is required to achieve compliance with the BCA, and therefore the DBPA requires the preparation of a Regulated Design for the rectification works.
The rectification concept for this defect would likely include the following (at each level):
Engage an appropriately qualified and experienced person to prepare a Regulated Design for the rectification works.
Install appropriately sized exhaust grilles in the ceiling of the lobby (at least 5m from the fire exit doors). Grille sizes: for example, 2 off 900 x 600 or 3 off 600 x 600.
Remove the existing relief air grille in the wall to allow access to the shaft.
Build a box (walls) around the opening to connect it into the ceiling void (to convey smoke from the lobby ceiling cavity to the existing exhaust grille opening).
Provide an access panel into the new box to facilitate maintenance access to the existing damper actuators.
Plaster and repaint walls.
Make good and clean up.
Test and commission the stair pressurisation relief systems. Ensure the correct airflows are being achieved.
Update the "As Installed" drawings and Operating and maintenance manual."
"...could require the movement of the sub-duct connection to the shaft and the grille to the underside of the ceiling. An assessment of site conditions would be required to understand any particular constraints involved in the current installation. An alternative fire engineered solution/assessment could also be investigated."
"Defect
Agreed defect
Rectification concept
The experts agree that in the event that a fire engineering performance solution can be developed to support the existing arrangement, then no further physical work is required.
It would be necessary to adopt the fire engineering report into the building's approvals via a CDC or a DA/CC process.
Should the fire engineering process not be able to adopt the existing arrangement being retained, adopt the rectification concept set out in the Warner report."
"Relocation of the stair pressurisation relief louvres would require works to relocate both the louvres as well as the associated sub-ducts within the stair pressurisation relief riser, and would therefore require removal of the lobby wall and would result in disruption to occupants while the works were carried out."
"If the stair pressurisation relief system was provided with natural ventilation in accordance with Cause 10.4.2(c) of AS 1668/1:2015 two vents each at low level, on opposite sides of the building would comply with the provisions of the code as there is no provision to design the inlets in accordance with Clause 4.4 as smoke exhaust system.
A Performance Solution to support the stair pressurisation relief vents being retained in their current location could be developed based on the existing locations and taking into consideration the disruption the works would cause. A comparative analysis to compare a natural stair pressurisation relief system with the building at (address) could be developed as part of a Performance Solution retrospectively being applied.
The adaption of a Performance Solution to rectify this defect would require the preparation of appropriate documentation and a relevant approval mechanism to update the building fire safety schedule to incorporate a Performance Solution, such as a Complying Development Certificate (CDC) or voluntary Fire Safety Order."
"Contrary to Builder CS [276] there is sufficient evidence on which to make an order giving effect to the process outlined in Mr Marshall's evidence in relation to the Performance Solution. The NCC sets the assessment methods that are available to address the relevant performance requirements (TB 166 [46]). It will involve the carrying out of a comparative analysis, require preparation of appropriate documentation and a relevant approval application to update the Building's fire safety schedule to incorporate the Performance Solution, such as a complying development certificate or voluntary safety order. The costs of such steps and approvals should be borne by the party responsible under the order.
The 'rectification concept' in the Warner Report is unreasonable, and its current description is under-developed for a work order (TB1439[34])."
Alleged Defect Item M23-Mechanical Installation Not In Accordance With Drawings
(1) A section of the duct on level B3 not installed but indicated on the Aerow Drawing -201 along gridline A between gridlines 3 and 4.
(2) A section of duct on level B1 installed differently to that shown on Aerow Drawing M-203 near the intersection of gridlines C and 2.
(3) The configuration of the plant room on levels LG and Grounds as indicated on Aerow Drawing M-204 between gridlines C-E and 1-2.
(4) The layout of the plant in the louvered roof enclosure.
"...likely include updated the "as installed" drawings to accurately represent the mechanical services installation."
Defect
Agreed defect
Rectification concept
The experts agree that the following amended rectification concept should be applied:
The rectification concept for this defect would likely include updating the "as installed" drawings (including the background architecture and mechanical services) to accurately represent the mechanical services installation.
Comments
The experts agree that the main areas that are not depicted accurately are the lower ground floor (as built drawing M. 08) and the roof (as built drawing M. 18). Mr Jacotine notes that the architectural drawings presented to him also do not reflect the architectural layout of the lower ground floor, and without correct architectural backgrounds to use for the production of mechanical built drawings, it follows that the mechanical as built drawings will also not be an accurate representation of the layout.
1. Revised mech layout to be advised by a Mechanical engineer
2. Kitchen exhaust documented as per CEE-GCOr 003233
3. Ceerose to advice (sic) on building maintenance equipment.
4. Mechanical layout to be revised to be accommodated within roof plan enclosure and to ensure no clashes with the structure".
Alleged Defect Item M24-No Relief Air for Basement Stair Pressurisation System
"On the basis of the above, neither the as-built arrangement nor the drawn arrangement have the necessary air relief and therefore both would be incapable of achieve the necessary door velocity to comply with the performance requirements of AS1668.1.
In addition to the above, the relief air to either the fire pump room (in the drawn arrangement) or the small interconnection room (in the as-built arrangement) is required to be provided by a smoke exhaust system designed in accordance AS1668.1. This is because there is no natural relief air provisions with louvers (or relief vents) on both sides of the building."
In my opinion, rectification of this defect involves an aspect of a building element that is required to achieve compliance with the BCA, and therefore the DBPA requires the preparation of a Regulated Design for the rectification works.
In my opinion the most practical solution is to develop a fire engineering solution (a performance solution) which would address this defect. A Fire Engineer would have to be engaged to assess and develop such a solution."
"Defect
Agreed defect
Rectification concept
The experts agree that in the event that in the event that a fire engineering performance solution can be developed to support the existing arrangement, then no further physical work is required.
It would be necessary to adopt the fire engineering report into the building approvals via a CDC or a DA/CC process."
Warner. Yes, I just need to absorb it.
Sub-contractor's Counsel: Yes
Warner: Okay, so correct me if I'm wrong, but what I believe you're saying is that providing you've got 8 cubic metres a second going into the stairs, and with all those doors opened, that he considers that to be a solution that complies, that will achieve the performance requirements.
Sub-contractor's Counsel: Yes
Jacotine: Yes, in lieu of the one meter per second... (not transcribable) open simultaneously.
Warner: Absolutely, Okay.
Sub-contractor's Counsel: And I haven't asked Mr Marshall or Mr Jacotine to comment at this point, but at least Mr Jacotine and in fairness, you only saw this yesterday as well, but does it affect your identification of the, your opinion about the identification of the defect, this item number?
Jacotine. Yes it does. So, provisionally we...(not transcribable) the degree that...(not transcribable) ...a fire engineering performance solution...(not transcribable).
Sub-contractor's Counsel: Just a bit louder.
Jacotine: So, the experts agree that in the event that a fire engineering performance solution can be developed to support the existing arrangement and no further physical work is required. So this is basically proof that there is a fire engineering solution.
Sub-contractor's Counsel: Would you agree with that Mr Warner?
Warner: I agree.
Sub-contractor's Counsel: Mr Marshall, would you like to..
Marshall: I don't..
Sub-contractor's Counsel: You haven't looked at this issue, to be fair I won't..
Marshall: (Not transcribable... I have, but yeah, just (not transcribable)
Sub-contractor's Counsel: Would you also agree it is not a defect?
Marshall: Yes.
"Builder CS (Annexure A [97]) confirms that item M24 is not pressed by the Builder against the Subcontractor.
This concession is properly made by the Builder following all three experts agreeing during cross examination that, having regard to Performance Solution 8 in the Fire Safety report dated January 2021 (nor the September 2020 report, neither of which were considered in the Warner Report) pursuant to which the airlocked room was intentionally created, that this item is not a defect and no work is required."
Alleged Defect Item M25.1-Miscellaneous Defects-Building Materials Left on Roof and Alleged Defect Item M25.2-Miscellaneous Defects-Drain Pipes Not Fixed In Place
Summary of Findings on Defects and Method of Rectification
Warner report paragraph [120] and Joint Scott Schedule p 1451
Warner report paragraph [244] and Joint Scott Schedule p 1455).
Warner report paragraph [529] and Joint Scott Schedule (pp 1455 and 1456)
Warner paragraph [528] and Joint Scott Schedule pp 1463 and1465.
Warner paragraph [638] (p 260 Joint Tender Bundle) and Joint Scott Schedule (p 1470 Joint Tender Bundle)
Warner paragraphs [685] and [695] and Joint Scott Schedule (p 1472 Joint Tender Bundle)
The Owner's Corporation's Submission That the Tribunal Should Incorporate Into the Rectification Order Statutory Warranty Requirements
"6. The relief sought is, per HBA sec (sic) 48O(1)© for the respondents (Builder and Developer) to be ordered to rectify the Defects
7. With respect to those 'work orders' sought the Owners say:
(a) The Builder holds a license under the HBA, and so can be ordered to do the work itself:
(b) The Developer does not hold a license under the HBA, but the breadth of the Tribunal's powers per sec (sic) 4O(1)(c) is such that it can be ordered to do all things as necessary as to effect the undertaking of the work-essentially for it to be directed to engage a suitably qualified license holder to do the work on its behalf.
(c) Because the performance of the residential building work under the 'work order' does not of itself carry the obligations to provide Statutory Warranties with respect to the work subject to the order, the Owners say the Tribunal would direct the warranties in the same terms as the Statutory Warranties be provided by each of the Builder and Developer with respect to such work as subject to the work order.
..."
(1) If the Tribunal work order is not complied with, the owners corporation can renew the proceedings in the Tribunal under Cl. 8 of Sch. 4 of the NCAT Act within 12 months of the date that the orders were due to be complied with. The owners corporation has rights under that provision if the work orders are not complied with.
(2) To impose further statutory warranty time periods in respect of the work ordered to be performed to rectify defects would be an inappropriate extension of the statutory warranty period, contrary to the principles referred to by Adamson J in Onslow v Cullen [2022] NSWSC 1257 at [51]- [62] in the context of whether a term of the contract referring to, in substance, statutory warranty obligations has a different limitation period to s 18E of the HB Act.
(3) There are other protections to the owners corporation. If the work order is not complied with, the builder may lose its building license under the HB Act (see s 48R of the HB Act and Division 1 of Part 6C of the HB Act). Accordingly, it is in the interest of any licensed builder to comply with the order, and imposing a condition equivalent to the statutory warranty periods under s 18E will cause uncertainty in circumstances where there may be a dispute about whether the builder has complied with a work order extending up to 6 years beyond the date that the order is to be complied with.
(4) Either party can seek an extension of time to comply with the work order, if there appropriate reasons to do so, under s 41 of the NCAT Act.
(1) Clause 2.1-the sub-contractor performing works in accordance with the contract and the directions of the builder.
(2) Clause 2.2(a)(v)-the works be performed and completed in accordance with the design documents; be fit for purpose; and comply with the requirements of the contract.
(3) Clause 35A-the works be performed in a proper and workmanlike manner and in accordance with the plans and specifications under the contract; the works be performed in accordance with the HB Act and any other law; and the works result in a dwelling reasonably fit for occupation.
(4) Clause 1.1. of the scope of works-the Sub-Contract would design and construct the works and all associated works in accordance the contract documents such that the works are fit for their intended purpose.
(5) Clause 2.6.18 of the scope of works-the Sub-contractor has allowed for the design to comply with Australian Standards; the BCA; the Australian Refrigeration and Air-conditioning Code; any acoustic report; the BASIX and authority requirements.
(6) Clause 3.1.4 of the scope of works, that the works were to be in accordance with all relevant statutes; the BCA; codes, standards and requirements of all authorities and be completed to the satisfaction of the builder.
Jurisdiction of the Tribunal in the Builder's Claim Against the Sub-Contractor
(1) The date of the contract between the builder and the sub-contractor is 10 March 2019.
(2) The sub-contractor completed its works (i.e. was last on site performing work) in November 2020.
(3) The Occupation Certificate for the strata building was issued 6 November 2020; and
(4) The builder's proceedings against the sub-contractor in the Tribunal was filed on 14 July 2023.
Can the Builder Rely on Breach of Contract Other Than In Respect of Breach of Statutory Warranties Against the Sub-Contractor?
(1) Onslow can be distinguished because it involved a different building contract between an owner and a builder.
(2) Onslow is inconsistent with the principles in The Owners-Strata Plan No 61288 v Brookfield Australia Investments Ltd [2013] NSWCA 317 (Brookfield-Court of Appeal) at [134] and Brookfield Mutiplex Ltd v Owners Strata Plan 61288 [2014] HCA 36 (_Brookfield-_High Court) at [133] that statutory warranties do not limit existing rights but supplement them.
(3) The builder relies on part of the NSW Parliament second reading speech in 2011 that "the scheme does not prevent the builder or developer from pursuing their sub-contractors or other third parties under the general law".
(4) The interpretation of s 18G of the HB Act in Onslow is incorrect.
"Section 7(a) of the Limitation Act has the effect that, if there is another limitation period specified in another "enactment", the other limitation period will apply rather than the one specified in the Limitation Act. Thus, if the owners' claim is properly to be characterised as one for breach of statutory warranty, the limitation period of two years in s 18E applies and not the limitation period of six years in s 14 of the Limitation Act for claims for breach of contract.
In the present case, the owners argued, and the Court below found, that the owners' claim was not one for breach of a statutory warranty, but rather a claim for breach of contract. Thus, it is necessary, for the purposes of ground 1 to examine this proposition to assess whether such a distinction is maintainable in the present case.
It was common ground that, if cl 39 had not been included in the contract, the owners had a claim against the builder for breach of statutory warranty (under s 18B) but that their right to commence proceedings had become statute-barred by the time they in fact commenced proceedings either in NCAT or in the Court below: (s 18E).
Section 7(2)(f) of the Act required that the statutory warranties (defined as a warranty established by Part 2C) be included in the contract. If her Honour's construction were correct, it would mean that a builder who complied with s 7(2)(f) by expressly including the warranties implied by s 18B into the contract would be in a worse position than a builder who was party to a contract which did not contain warranties in its written form. On her Honour's construction, a builder who had not included the warranties would be entitled to rely on s 18E but one who had would not be.
It is important to read the contract in light of the Act. Clause 39 of the contract is plainly designed to comply with s 7(2)(f) and replicate the warranties in s 18B. The prefatory words of the clause, "[t]o the extent required by the [Act], the builder warrants that" (emphasis added) are, in my view significant because the warranties in sub-clauses (a)-(f) are given subject to the rider in the prefatory words. Thus, the objective intention of the parties is that the warranties are given only in so far as they are required by the Act. The Act requires only warranties in respect of non-major works that are enforceable for two years. In these circumstances, the builder ought not to be taken to have given wider warranties than those which the Act implied into the contract.
If there is any ambiguity in cl 39, regard can be had to the surrounding circumstances: Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337 at 352 (Mason J); [1982] HCA 24. Such surrounding circumstances include matters known to both parties at the time the contract was entered into. In the present case, such matters included the Consumer Building Guide which was Attachment B to the contract which said in part, of the statutory warranties (in s 18B):
"These warranties are time-limited: legal proceedings to enforce them must be commenced within 2 years for all defects and 6 years for 'major defects'."
Nor is there a sensible distinction in these circumstances between an action for "breach of statutory warranty" and an action for "breach of contract." A warranty is merely a term of a contract, which is neither a condition (any breach of which will entitle the injured party to terminate), nor an innominate or intermediate term (a fundamental breach of which will entitle the injured party to terminate), breach of which will not entitle a party to terminate: see the summary of principles in Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; [2007] HCA 61 at [47]-[53] (Gleeson CJ, Gummow, Heydon and Crennan JJ) and the discussion in John Carter, Carter on Contract (7th ed, 2018, LexisNexis) at Ch 14 "Classification of Terms". A statutory warranty is a term which is implied, by legislation, into a contract, irrespective of the intentions of the parties. It thereby becomes a term of the contract between the parties. In the present case, the warranties in cl 39 did not lose their character as statutory warranties merely by having been expressed in the contract document. As referred to above, s 7(2)(e) required that they be included in the contract.
Further, s 18G makes it clear that the parties cannot exclude the statutory warranty "to remove the rights of a person" and any provision which purports to do so, is void. It is significant that s 18G refers to "rights of a person". The word "person" in this context includes not only the owners but also the builder. The owners have a right to the benefit of the statutory warranties in terms but the builder has the right not to be sued in respect of non-major defects after the two year period has elapsed. That "person" ought be construed in this way derives some support from the use of the different expression "person entitled to the benefit of a statutory warranty under this Act" in s 18D(1). The owners might reasonably be thought to be the persons entitled to the benefit of a statutory warranty but "person," without that qualification in s 18G, includes not only the owners but also the builder. "
"First, one of the primary judge's principal reasons for finding that no common law duty of care existed in favour of the appellant was that Part 2C of the Home Building Act was of limited reach only and did not confer any relevant rights on the appellant. In my view this circumstance did not militate against the imposition of a common law duty of care as there is nothing in the Act to suggest that it was intended to abrogate any common law rights of action. Furthermore the passages in the 1993 Report of Commissioner Dodd, which preceded the enactment of Part 2C of the Act, and in the relevant Second Reading Speech to which the Court was referred, if anything, implied that the Part was intended to supplement, rather than limit, existing rights."
"Statutory provisions may supplement the common law of contract by providing for special protection to identified classes of purchasers on the ground, for example, that they may not be expected to be sufficiently astute to protect their own economic interests. Part 2C of the Home Building Act 1989 (NSW) is an example of such a statutory regime.
By enacting the scheme of statutory warranties, the legislature adopted a policy of consumer protection for those who acquire buildings as dwellings. To observe that the Home Building Act does not cover claims by purchasers of serviced apartments is not to assert that the Act contains an implied denial of the duty propounded by the respondent. Rather, it is to recognise that the legislature has made a policy choice to differentiate between consumers and investors in favour of the former. That is not the kind of policy choice with which courts responsible for the incremental development of the common law are familiar**[175]**; and to the extent that deference to policy considerations of this kind might be seen to be the leitmotif of this Court's decision in Bryan v Maloney, the action taken by the New South Wales legislature served to relieve the pressure, in terms of policy, to expand the protection available to consumers."
**"**The general principles applicable to the precedential weight of obiter dicta, including the role of the appellate court hierarchy, were largely agreed in these appeals. They can be summarised as follows:
(1) Decisions are only authority for what they decide, as opposed to what was held without argument: Randren House Pty Ltd v Water Administration Ministerial Corporation [2020] NSWCA 14 at [45] ; Spence v Queensland 93 ALJR 643; [2019] HCA 15 at [294] (Edelman J).
(2) An intermediate appellate court should not decline to apply a legal principle which has been set out in "seriously considered dicta" by a majority of the High Court, and which is otherwise consistent with a substantial line of common law authority: Farah Constructions at [134].
(3) Although "considered dicta" of an intermediate appellate court is not strictly binding on courts in a lower or equal position within the judicial hierarchy, it must be afforded great weight and should be departed from only with the greatest of caution: Ying v Song at [19] ; Fullerton Cove at [279].
(4) Intermediate appellate courts should not depart from the decisions of intermediate appellate courts in other jurisdictions in relation to the interpretation of the same legislation or of common law principles: Farah Constructions at [135]; Gett v Tabet at [286] ; Australian Securities Commission v Marlborough Gold Mines Ltd (1993) 177 CLR 483; [1993] HCA 15 at [4] .
(5) The same principle should apply when the Court is asked to depart from one of its own decisions that is on point, and when it is confronted with a decision of an Australian intermediate appellate court of comparable jurisdiction in relation to similar legislation: Harrison v Melhem [2008] NSWCA 67 at [188] (Mason P).
(6) Generally speaking, intermediate appellate courts are not legally bound to follow their own earlier decisions (including statements made in ratio decidendi). However, as a matter of practice, they should only depart from such authority, or the authority of courts of coordinate jurisdiction within the national system, if they are of the view that the decision is "plainly wrong": Gett v Tabet at [273] , [277] -[278] , [281] .
(7) As a matter of comity, single judges of the NSW Supreme Court will generally follow an earlier decision of another single judge, although they are not legally bound to do so: see eg Segal v Waverley Council [2005] NSWCA 310 at [48] , [57] -[59] ; New Cap Reinsurance Corporation Ltd (in liq) v A E Grant [2008] NSWSC 1015 (New Cap Reinsurance) at [109] (White J).
(8) Statements made in obiter dicta have varying degrees of authority. For example, a "mere passing remark or a statement or assumption on a matter that has not been argued" or "broad observations made on the spur of the moment" will have less weight than "a considered judgment on a point fully argued": Nowicka at [21]-[25].
(9) The weight accorded to obiter dicta will vary depending on the circumstances in which it was made: Ying v Song at [19] , [23] .
(10) In circumstances where a matter was not fully argued before the earlier court, and "relevant material" was not drawn to its attention, a subsequent court of coordinate jurisdiction may consider that a party before it should not be "disadvantaged" by reason of the earlier obiter conclusion: Sok at [34] (per Branson J, with Marshall J agreeing); see also New Cap Reinsurance at [109].
(11) In order to depart from such earlier authority, a court must have a "strong conviction" that the earlier decision was erroneous (not merely that the former approach is no longer preferred), and must be able to clearly demonstrate "the nature of the error ... by the application of correct legal analysis": Gett v Tabet at [294] -[295] .
(12)That reasonable minds may differ on a question is not a foundation for a conclusion that a decision supported by exposed reasons for judgment after full argument is "plainly wrong": Nowicka at [21]-[22]."
18E Proceedings for breach of warranty
(1) Proceedings for a breach of a statutory warranty must be commenced in accordance with the following provisions -
(a) proceedings must be commenced before the end of the warranty period for the breach,
(b) the warranty period is 6 years for a breach that results in a major defect in residential building work or 2 years in any other case,
(c) the warranty period starts on completion of the work to which it relates (but this does not prevent proceedings from being commenced before completion of the work),
(d) if the work is not completed, the warranty period starts on -
(i) the date the contract is terminated, or
(ii) if the contract is not terminated - the date on which work under the contract ceased, or
(iii) if the contract is not terminated and work under the contract was not commenced - the date of the contract,
(e) if the breach of warranty becomes apparent within the last 6 months of the warranty period, proceedings may be commenced within a further 6 months after the end of the warranty period,
(f) a breach of warranty becomes apparent when any person entitled to the benefit of the warranty first becomes aware (or ought reasonably to have become aware) of the breach.
(1A) If a building bond has been lodged for building work under Part 11 of the Strata Schemes Management Act 2015, the period of 2 years specified for commencing proceedings for a breach of a statutory warranty for that work is extended until the end of 90 days after the end of the period within which a final inspection report on the building work under that Part is required.
(1B) Subsection (1A) does not limit any other law that permits the period for commencement of proceedings to be extended.
(2) The fact that a person entitled to the benefit of a statutory warranty specified in paragraph (a), (b), (c), (e) or (f) of section 18B has enforced the warranty in relation to a particular deficiency in the work does not prevent the person from enforcing the same warranty for a deficiency of a different kind in the work (the other deficiency) if -
(a) the other deficiency was in existence when the work to which the warranty relates was completed, and
(b) the person did not know, and could not reasonably be expected to have known, of the existence of the other deficiency when the warranty was previously enforced, and
(c) the proceedings to enforce the warranty in relation to the other deficiency are brought within the period referred to in subsection (1).
(3) The regulations may prescribe defects in a building that are not (despite any other provision of this section) a major defect.
(4) In this section -
major defect means -
(a) a defect in a major element of a building that is attributable to defective design, defective or faulty workmanship, defective materials, or a failure to comply with the structural performance requirements of the National Construction Code (or any combination of these), and that causes, or is likely to cause -
(i) the inability to inhabit or use the building (or part of the building) for its intended purpose, or
(ii) the destruction of the building or any part of the building, or
(iii) a threat of collapse of the building or any part of the building, or
(b) a defect of a kind that is prescribed by the regulations as a major defect, or
(c) the use of a building product (within the meaning of the Building Products (Safety) Act 2017) in contravention of that Act.
Note.
The definition of major defect also applies for the purposes of section 103B (Period of cover).
major element of a building means -
(a) an internal or external load-bearing component of a building that is essential to the stability of the building, or any part of it (including but not limited to foundations and footings, floors, walls, roofs, columns and beams), or
(b) a fire safety system, or
(c) waterproofing, or
(d) any other element that is prescribed by the regulations as a major element of a building.
The Appeal Panel in Ashton v Stevenson; Stevenson v Ashton [2020] NSWCATAP 233 ('Ashton') considered the applicable principles for whether or not a defect was a "major defect" under Section 18E (1) (b) and (4) of the HB Act. Such principles are summarised as follows:
(a) The test under s 18E (4) of the HB Act has two parts. The first is that there must be a defect in "a major element of the building" attributable to one of the specified mattes. The second is that the defect must "cause" or "is likely to cause" (a) the inability to inhabit or use the building (or part of the building) for its intended purpose; or (b) the destruction of the building or any part of the building; or (c) a threat of collapse of the building or any part of the building (Ashton at [63]);
(b) Expert evidence may be necessary to establish the fact of the defect and the likely effect on the ability to inhabit the building or cause the destruction of the building. However, the homeowner may also give lay evidence on such issues, including matters such as observations about the absence of relevant elements of the work; the location of water staining; the fact of water ingress during a rain or flooding event; photographs of such matters; or other observations about which a non-expert could give evidence and which could rationally affect the determination of what is likely in the future (Ashton at [68]).
(c) Whether a particular defect is likely to cause the relevant consequences in the future is evaluated in the context of (a) how long the defect has existed; and (b) whether the defect has resulted in any damage that might indicate the likelihood the premises will become uninhabitable or destroyed in the future by reason of the defect (Ashton at [69]).
(d) The design life of the structure and materials used may be relevant considerations (Ashton at [70]).
(e) Determination of the matters in s 18E (4) (a) (i)-(ii) are questions of fact (Ashton at [130]-[131]). Evidence is required from which it can be concluded the defects will likely cause the specified outcome (Ashton at [134]).
(f) Defects in the drainage system (and the roof structure) designed to keep rainwater from entering the dwelling is a major element under s 18E (4) (c) of the HB Act; and evidence may establish defects are likely to cause the premises to become uninhabitable in the future due to flooding, even if such a rain event has not yet occurred (Ashton at [169]-[170]).
Further, the Appeal Panel stated in Ashton at [135]:
Whilst it is inappropriate to try and catalogue all evidence that might be relevant to resolving the issue of whether the defects are likely to cause the building to become uninhabitable or to be destroyed in whole or in part, it can be readily accepted that the fact of water ingress arising from one or more of the defects would be relevant even though such an outcome had not presently manifested itself. The nature, location and extent of the defects would also be relevant in assessing the likelihood of the prescribed outcome. Lastly, expert evidence assessing the likelihood of the particular defects causing the prescribed outcome would be relevant, it being noted that the evidence must be of a type which is "comprehensible and reach conclusions that are rationally based" in order to "furnish the trier of fact with criteria enabling the evaluation of the validity of the expert's conclusion" .
In Stevenson v Ashton [2019] NSWSC 1689, the Supreme Court (Harrison AsJ) stated at [74]-[76] that the legal test for whether the defect in s 18E (4) of the HB Act is a "major defect" does not require proof that the defect is "presently manifested and dire" or "imminent".
The Owners' Corporation drew my attention to and extracted in its written outline of submissions certain propositions enunciated by Harrison AsJ in Stevenson v Ashton [2019] NSWSC 1689 concerning the expression 'major defect' in s 18E(4). These were:
(a) A claimant must establish that a defect is "likely to" cause any of the consequences in s 18E(4)(a)(i)-(iv). It is unnecessary to prove that a defect has already caused one or more of those matters (at [51]);
(b) It is unnecessary for the claimant to demonstrate any degree of imminence to damage (at [76]);
(c) When considering expert evidence adduced to establish a major defect (relevantly, in that decision, waterproofing), it is unnecessary to prove the manifestation of consequences (in s 18E(4)(a)(i)-(iv)). It is enough to establish the consequences that the defect is likely to cause (at [87]).
**"**The nature and extent of such a power was considered by Hope JA in State Rail Authority of New South Wales v Consumer Claims Tribunal (1988) 14 NSWLR 473 in the context of the provisions of s 23(2) of the previously repealed Consumer Claims Tribunal Act 1974 (NSW) (CCT Act). That section was in the following terms:
(2)In exercising its powers under subsection (1) (a), (b), (c) or (d) a consumer claims tribunal shall make such an order as is, in its opinion, fair and equitable to all the parties to the proceeding before it.
... I would respectfully agree with the conclusion reached by Yeldham J in Fairey Australasia Pty Ltd v Joyce [1981] 2 NSWLR 314 at 321 that the tribunal is not concerned with "palm tree justice, and with the conclusion of Hunt J in Jet 60 Minute Cleaners Pty Ltd v Brownette [1981] 2 NSWLR 232 at 236, that save in relation to the selection with the form of order the tribunal must act in accordance with and apply the general law in determining the claim which has been made to it.
Whether there is ... a claim or obligation is to be determined by applying the general law. It is only where the tribunal proposes to make an order in favour of the claimant that in some cases the form of the order in his favour is to be determined according to the opinion of the tribunal as to what is fair and equitable to all parties.
Unlike s 23(2) of the CCT Act, s 79U(1) of the FT Act is not confined to particular types of orders that might be made. However, as with the CCT Act, the FT Act does not displace the requirement for claims to be determined in accordance with the general law. Rather, as Hope JA found in State Rail, once liability and an entitlement to a remedy is established, s79U provides scope to fashion the form of orders in a manner that "will be fair and equitable to all parties to the claim".
The Owners Corporation's Proceedings Against the Developer
The Developer's Proceedings Against the Owners Corporation
(1) Clauses 2(a), 2(c) and 2.1-the builder was required to perform works in accordance with the contract, and do everything necessary to give effect to the contract.
(2) Clauses 2.2. and 7(a)-the works would comply with applicable building codes, standards and any law.
(3) Clause 2.3-the s 18B(1) HB Act statutory warranties apply to the works.
(4) Clause 37-the builder provides a warranty when it submits a payment claim that the works are, when completed, fit for purpose; comply with the terms of the contract; comply with the Building Code of Australia; comply with legislative requirements; comply with the project requirements; and are to the reasonable satisfaction of the builder.
Clause 54K(k) states as follows:
(k) Each indemnity in the Contract is a continuing obligation, separate and independent from the other obligations of the Parties and survives termination of the Contract.
(i) It is not necessary for a Party to incur expense or make payment before enforcing a right of indemnity conferred by the Contract; and
(ii) damages incurred, and liability suffered by a Party covered by indemnification by another Party under the Contract will include all related costs and other expenses (including reasonable legal fees).
2. Representations and Warranties
The Contractor unconditionally and irrevocably represents and warrants that for the period to which the payment claim relates:
...
(g) It has carried out the Works:
(i) in accordance with the Contract so that the Works, when completed, will be fit for its Stated Purpose and comply with all the requirements of the Contract, the Building Code of Australia and all relevant Legislative Requirements; and
(ii) in accordance with the express provisions of the Contract, including the Principal's Project Requirements, and where no more specific and/or higher standard is specified, with due expedition and diligence, with sound workmanship and materials, safely and in accordance with Good Industry Practice, applicable Legislative Requirements and to the reasonable satisfaction of the Principal.
3. Indemnity
The Contractor indemnifies the Principal against any breach of the Contractor's representations and warranties provided in clause 2.
"The Tribunal made a preliminary determination as to jurisdiction on 13 December 2026. It appears both parties agreed that the Tribunal had jurisdiction to hear the Builder's claim against both the Owner and Guarantor pursuant to the terms of s 48K of the HBA".
48O Powers of Tribunal
(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate -
...
(c) an order that a party to the proceedings -
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.
...
"As noted by Hoeben J in Pritchard v Trius Constructions Pty Ltd [2011] NSWSC 749 at [109], although Giles JA and McClellan CJ at CL were not entirely in agreement in Erect Safe Scaffolding v Sutton as to how to interpret the indemnity clause under consideration, both agreed on the relevant principle of construction:
"5 The operation of any contractual indemnity must be found in the application to the facts of the words of the relevant clause, construed as part of the contract as a whole. Decisions on the operation of contractual indemnities in different words in different contracts are likely to be of limited assistance." (Giles JA)
"154 The resolution of any disagreement about a particular clause in a contract must be approached by considering the terms of the relevant document. Although the resolution of disputes in other cases may provide guidance, each dispute must be resolved by the application of the accepted principles of construction to the particular contract." (McClellan CJ at CL)
The critical issue of construction in Erect Safe Scaffolding (Australia) Pty Ltd v Sutton concerned the meaning to be given to the words "arising out of the performance of the Subcontract Works" in a contractual indemnity afforded by the subcontractor to the head contractor against all damage, expense, or liability of any nature suffered or incurred by the head contractor. Those words were construed as not providing the head contractor with indemnity in respect of its own liability for negligence. At [12], Giles JA reasoned that the basis for the head contractor's liability was breach of its own duty of care to the injured person although the subcontractor's performance of the works provided the occasion for it to occur. His Honour considered that was insufficient for liability to have arisen out of the performance by the subcontractor of the subcontract works and its other obligations. Similar reasons were given by McClellan CJ at CL at [157] - although the occasion for the liability of the head contractor was the erection by the subcontractor of the faulty scaffold, the liability of the head contractor arose from its own independent act of negligence in failing to maintain an appropriate safety regime for the site.
The terms of the Agreement in the present case are quite different. First, the terms of the indemnities afforded by Advantage to Centennial under cl 8.1 of the Standard Conditions are clear. There is an express carve out from those indemnities where the relevant claim has arisen as a result of Centennial's negligence or breach of contract."
18G Warranties may not be excluded
A provision of an agreement or other instrument that purports to restrict or remove the rights of a person in respect of any statutory warranty is void.
(1) The owners corporation has succeeded against the builder and developer for some of the defect items claimed in respect of breach of the statutory warranties under the HB Act.
(2) It is appropriate that the Tribunal make a work order under s 48O of the HB Act against the builder and developer to rectify the defects found by the Tribunal. The Tribunal regards the period of 5 months from the date of this decision as an appropriate period for the works to be performed. If a party seeks an extension of the date of completion of the works under s 41 of the NCAT Act, it must file and serve a miscellaneous orders application, which will be dealt with separately.
(3) The builder has failed in its proceedings against the sub-contractor.
(4) The developer has failed in its proceedings against the builder.
(1) In Case Number 2022/00400982, Ceerose Pty Ltd and Zone Q Milsons Point Development Pty Ltd are to perform, or cause the performance of, the scope of works identified in paragraph [494] of the reasons and the references to the Joint Tender Bundle referred to therein by 20 March 2026.
(2) The work in order 1 is to be performed by suitably licensed and insured persons or entities using due care and skill.
(3) The Owners-Strata Plan No 102171 is to provide reasonable access to the strata building so that the works in order 1 are capable of being performed.
(4) Case Number 2022/00400982 is otherwise dismissed.
(7) The issue of costs of the related proceedings is to be determined in the following manner:
(a) Any costs applicant is to lodge with the Tribunal and serve on the costs respondent all documents and submissions on the issue of costs by 14 days from the date of this decision.
(b) Any costs respondent is to lodge with the Tribunal and serve on the costs applicant all documents and submissions on the issue of costs by 28 days from the date of this decision.
(c) Any costs submissions in reply are to be lodged with the Tribunal and served on the costs respondent by 35 days from the date of this decision.
(d) The costs submissions of the parties is to include whether the party consents with a hearing being dispensed with on the issue of costs under s 50(2) of the Civil and Administrative Tribunal Act 2013 (NSW) and the issue of costs determined on the papers.
(e) Costs submissions are to be lodged with the Tribunal in hard copy in addition to being lodged electronically.
(f) Any party may apply to vary the timetable for costs submissions and documents in writing to the Tribunal with a copy served on the other parties.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
(2007) 244 ALR 300
(2008) 72 NSWLR 380
(1982) 149 CLR 337
(2007) 233 CLR 115
(1954) 90 CLR 613
(2017) 340 ALR 368
(1993) 177 CLR 483
(1988) 14 NSWLR 473