[2024] NSWSC 566
Supreme Court of NSW
2024-04-11
Nixon J
Original judgment source is linked above.
First Cross-Claim, Cross-Defendant on Second Cross-Claim)
Solicitors: Salim Rutherford Lawyers (Plaintiff/ First Cross-Defendant on First Cross-Claim/ Cross-Claimant on Second Cross-Claim) Barrak Lawyers (Defendant/ Cross-Claimant on First Cross-Claim) Colin Biggers & Paisley Pty Ltd (Second Cross-Defendant on First Cross-Claim, Cross-Defendant on Second Cross-Claim) File Number(s): 2021/95090 Publication restriction: Nil
JUDGMENT
The Contract
Practical Completion and Final Statement
Issue - Extent of Any Set-Off
B. CLAIMS IN RESPECT OF CONCRETE SLAB
The Contract
Borehole Report and Variation 9
Slab is designed and laid
Failure to supply H1 slab
Mr Camenzuli's evidence
Specific instances of non-compliance with AS 2870?
Item 1: Drainage and waterproofing behind the central step
Item 2: Edge Beam Cover to Bottom Reinforcement
Item 3: Slab Mesh for Class H1
Item 5: Piering to internal areas of the slab
Item 6: Lack of full continuity at the step and Item 7: Internal beams not being edge to edge
Item 9: Step stem thickness
Item 10: Beam bottom reinforcement
Conclusion on non-compliances
Consequences of non-compliance with AS 2870?
Proper measure of damage
Relevant Principles
What damages should be awarded in this case?
Metricon's Cross-Claim
Scope of Dispute
Internal Lining $11,015
Air Con Pipe Insulation $710
Air Con recommissioning $360
Electrical Wiring $720
Eaves Trim $1,530
Alfresco Brickwork $800
Laundry Door $475
Front Column $100
Garage Door Lintel $250
Rangehood Ducting $400
Perimeter ceiling trimming $330
Roof bracing $2,630
Ceiling Trimming $1,095
Wall Blocking Pieces $290
Laundry Manhole $400
Ceiling insulation coverage $810
Total: $21,915
Securing roof tiles Admitted $16,020 $3,463
Wall bracing Admitted $8,750 $0
Strengthening of wall Disputed $8,000 If found, $2,500
Roof frame anchors Admitted $4,860 $0
Stormwater repair Disputed $4,400 $0
Water supply repair Disputed $4,400 $0
Bathroom plumbing Admitted $3,300 $575
Kitchen tap repair Disputed $770 $0
Total $50,500 $4,038
Securing Roof Tiles
Wall bracing
Straightening of wall
Roof Frame Anchors
Stormwater Repair and Water Supply Repair
Bathroom plumbing
Kitchen Tap repair
Conclusion: General Defects
Pre-contractual communications
Contract
Variation 2 and subsequent correspondence
Communications between 8 and 10 June 2017
Variation 9 and amended plans
Pool plan dated "8 September 2017"
Events following laying of slab
Installation of the pool
Issues Raised Regarding Variation 9
Claim for Misleading or Deceptive Conduct
Did Metricon make misleading representations to Mrs Lipari on 8 and 9 June 2017?
8 June Representation
9 June Representation
Did Mrs Lipari suffer loss and damage?
Conclusion
Conclusion and Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 16 May 2024
Metricon Homes Pty Ltd as trustee for Metricon Homes Unit Trust
Lipari
[2006] QCA 61
[2004] SASC 81
(2020) 281 FCR 108
(1987) 71 ALR 553
(1954) 90 CLR 613
(1991) 174 CLR 64
(2012) 247 CLR 486
(2019) 101 NSWLR 658
(2009) 236 CLR 272
(1965) 114 CLR 164
(1984) 2 FCR 82
(1986) 64 ALR 347
[2009] HCA 8