114 If the base is constructed to a depth of 500mm, there is an additional cost of $70,000. That amount includes $12,540 to excavate the extra 200mm. I accept Mr Finlay's evidence which requires that the excavation be to a depth of 350mm, with the rest of the 500mm base being above ground level. The total cost in excavating the extra 200mm is $12,540. It is reasonable to conclude that the additional cost of excavation for the extra 50mm is $3,135, being one quarter of $12,540. The plaintiffs must pay the cost of $3,135 as it is a cost associated with a thicker base. The cost of providing 200mm of fill is $57,570. As mentioned above, that amount must be offset by the fact that the plaintiffs have already incurred the cost of filling to provide the initial 150mm base. They are not liable to incur that cost again. The plaintiffs are liable only for one quarter of that cost for the extra 50mm, namely $14,392.50. The plaintiffs must pay the sum of $14,392.50 and $3,135 which must, therefore, be added to the sum of $165,000. The balance of the estimate of $70,000 is to be paid by the defendants.