[2019] NSWSC 440
Supreme Court of NSW
2019-02-28
Stevenson J
Original judgment source is linked above.
d (Fifth Defendant) Hughes Trueman Pty Limited (Sixth Defendant) NMK (Aust) Pty Limited (Seventh Defendant) QBE Underwriting Limited as Managing Agent for the Members of Lloyd's Syndicate 386 (Eighth Defendant) Representation: Counsel: A Ogborne with A Avery-Williams (Plaintiffs) R A Cavanagh SC with S Blackman (First and Third Defendants) D Hand (Sixth Defendant) G Ng (Eighth Defendant)
Solicitors: Holman Webb Lawyers (Plaintiffs) Thompson Cooper Lawyers (First and Third Defendants) Clyde & Co (Sixth Defendant) Yeldham Price O'Brien Lusk (Eighth Defendant) File Number(s): SC 2013/179839
table of contents Judgment The parties Conclusion The common property issue The limitation issue The onus issue The Owners Corporation's case as finally presented The expert conclave and concurrent evidence The events leading to the Shoring Works The 13 March 2006 Jeffery and Katauskas geotechnical investigation The 2 October 2007 Development Consent The Architect's July 2009 plans The July 2009 retainer of Hughes Trueman The 20 August 2009 retainer of Jeffery and Katauskas The changes made to the Hughes Trueman Shoring Layout plan by Northwood The 25 March 2010 contract between the Developer and Southern Cross Mr Walsh's suggestions incorporated into the Architect's plans Mr Walsh's "for costing" drawings Hughes Trueman's 20 July 2010 reissued draft shoring plan Mr Speechley's geotechnical modelling The 21 July 2010 site meeting The 30 July 2010 subcontract between Southern Cross and Pile & Bucket The Shoring Works The 30 July 2010 excavation Survey monitoring commences The Architect's 9 August 2010 instruction concerning the light wells 18 August 2010 exchange between Hughes Trueman and Mr Walsh Northwood's final drawings Construction of piles for the light wells Hughes Trueman's 30 August 2010 "for construction" drawings Mr Speechley's site visit on 8 September 2010 The 8 September 2010 survey monitoring Construction of laterally loaded piles for props to the Shoring Wall Hughes Trueman's 9 September 2010 re-issued "for construction" plans Cutting of the capping beam and piles at northern light well Mr Speechley's site visit on 6 October 2010 The 7 October 2010 survey monitoring Hughes Trueman's 8 October 2010 re-issued footing plan Removal of the props 11 October 2010 "neighbour concerns" about cracking 29 October 2010 excavation for the lift pit 1 November 2010 direct observation of cracking 5 and 6 November 2010 excavation for foundation pile caps 8 and 10 November 2010 survey monitoring Retaining Wall propped - no further movement What caused the movement of the Building's foundations? Inadequate design A passive, rather than active design A design that did not show design excavation depth The Owners Corporation's claims Negligence - general principles Breach under s 5B Breach under s 177 Causation The Owners Corporation's case against Southern Cross 1. Failure to comply with the Development Consent conditions 2. Failure to obtain advice prior to the 30 July 2010 excavation 3. Failure to execute the Monitoring Plan 4. Failure to take steps to maintain support of the Retaining Wall 5. Failure to implement a lateral support system for the Retaining Wall 6. Failure to implement Mr Speechley's recommendations The 20 August 2010 excavation The temporary propping of the Retaining Wall 7. Directing Pile & Bucket to excavate below RL 6.6 m 8. Directing NMK to excavate below RL 6.6 m Conclusion concerning the case against Southern Cross Owners Corporation's case against Hughes Trueman 1. The design and location of the northern light well 2. The design of the lift pit 3. The location of the foundation piles 4. The location of foundation piles at the basement level 5. Failure to take action when informed of reports of cracking Conclusion concerning the case against Hughes Trueman Conclusion
Judgment
The parties
Conclusion
The common property issue
The limitation issue
The onus issue
The Owners Corporation's case as finally presented
The expert conclave and concurrent evidence
The 13 March 2006 Jeffery and Katauskas geotechnical investigation
The 2 October 2007 Development Consent
The Architect's July 2009 plans
The July 2009 retainer of Hughes Trueman
The 20 August 2009 retainer of Jeffery and Katauskas
The changes made to the Hughes Trueman Shoring Layout plan by Northwood
The 25 March 2010 contract between the Developer and Southern Cross
Mr Walsh's suggestions incorporated into the Architect's plans
Mr Walsh's "for costing" drawings
Hughes Trueman's 20 July 2010 reissued draft shoring plan
Mr Speechley's geotechnical modelling
The 21 July 2010 site meeting
The 30 July 2010 subcontract between Southern Cross and Pile & Bucket
The 30 July 2010 excavation
Survey monitoring commences
The Architect's 9 August 2010 instruction concerning the light wells
18 August 2010 exchange between Hughes Trueman and Mr Walsh
Northwood's final drawings
Construction of piles for the light wells
Hughes Trueman's 30 August 2010 "for construction" drawings
Mr Speechley's site visit on 8 September 2010
The 8 September 2010 survey monitoring
Construction of laterally loaded piles for props to the Shoring Wall
Hughes Trueman's 9 September 2010 re-issued "for construction" plans
Cutting of the capping beam and piles at northern light well
Mr Speechley's site visit on 6 October 2010
The 7 October 2010 survey monitoring
Hughes Trueman's 8 October 2010 re-issued footing plan
Removal of the props
11 October 2010 "neighbour concerns" about cracking
29 October 2010 excavation for the lift pit
1 November 2010 direct observation of cracking
5 and 6 November 2010 excavation for foundation pile caps
8 and 10 November 2010 survey monitoring
Retaining Wall propped - no further movement
What caused the movement of the Building's foundations?
Inadequate design
A passive, rather than active design
A design that did not show design excavation depth
The Owners Corporation's claims
Negligence - general principles
Breach under s 5B
Breach under s 177
Causation
The Owners Corporation's case against Southern Cross
Failure to comply with the Development Consent conditions
Failure to obtain advice prior to the 30 July 2010 excavation
Failure to execute the Monitoring Plan
Failure to take steps to maintain support of the Retaining Wall
Failure to implement a lateral support system for the Retaining Wall
Failure to implement Mr Speechley's recommendations
The 20 August 2010 excavation
The temporary propping of the Retaining Wall
Directing Pile & Bucket to excavate below RL 6.6 m
Directing NMK to excavate below RL 6.6 m
Conclusion concerning the case against Southern Cross
Owners Corporation's case against Hughes Trueman
The design and location of the northern light well
The design of the lift pit
The location of the foundation piles
The location of foundation piles at the basement level
Failure to take action when informed of reports of cracking
Conclusion concerning the case against Hughes Trueman
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 18 April 2019
The Owners - Strata Plan 30791
Southern Cross Constructions
(2014) 223 FCR 295
(2013) 247 CLR 613
(2014) 224 FCR 519
(2010) 246 CLR 182