© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] NSWCA 199
Court of Appeal (NSW)
2020-03-25
Gleeson JA, McCallum JA, Stevenson J
Original judgment source is linked above.
Introduction This appeal arises out of building works carried out between July and November 2010 on land situated on the corner of Manning Road and Pine Hill Avenue, Double Bay (the Development Property). The building works resulted in damage to a three-storey block of 12 apartments (the Building), which stands on land having a frontage to Pine Hill Avenue (the Affected Property), which adjoins the Development Property from the west and uphill. The location of the Building and the Affected Property in relation to the Development Property is shown in the following diagram:
Damage to the Affected Property and Procedural Background
Planning and Design Prior to the Shoring Works
The 2006 J&K Report
The Architect's Plans for the New Apartment Building
Engagement of Hughes
Engagement of Northwood
Engagement of the Builder
The Construction Contract
Engagement of Pile & Bucket
Engagement of J&K and the Monitoring Plan
Engagement of Hughes to Conduct Dilapidation Survey
Northwood's Shoring Wall Proposal
Butter Paper Sketches
Further Correspondence
19 May 2010 Meeting Between Developer, Builder and Architect
Architect Integrates Northwood's Shoring Wall Design
Determining Shoring Wall Design and Temporary Support System
"Reverse Buttressing" Temporary Support System
J&K Required to Conduct Geotechnical Design of Shoring Wall
21 July 2010 Site Meeting Between the Developer, Builder and Architect
J&K Concludes Reverse Buttress Design Infeasible
Investigation of a Lateral Propping System to Support the Shoring Wall
The Course of the Works on the Development Property
30 July 2010 Excavations by Pile & Bucket
4 August 2010 J&K Site Visit and Report
Instructions to Backfill Excavation for Re-benching and Re-battering
Piling for Shoring Wall Commences
Issues Arising out of the Straight Shoring Wall Design
Northwood's Concrete "Pad" Foundation Proposal
Adoption of Laterally Loaded Pile Foundation
Finalisation of Pile Layout and Specification
Pile & Bucket Instructed to Construct Piles for the Light Wells
Northwood Issues Final Plans for Shoring Wall and Shoring Props
Provision for Lateral Piling Design
Provision for Cutting Down Piles in the Northern Light Well
20-23 August 2010 Excavation and Construction of Light Well Piling
20 August 2010 J&K Site Visit
8 September 2010 J&K Site Visit
The Temporary Retaining Propping
10 September 2010 Hughes' Concerns Regarding the Foundation Piles
Cutting of the Northern Light Well Shoring Wall Piles and Capping Beam
11-27 September 2010 Construction of the Shoring Props
22 September 2010 Northwood Site Inspection
6 October 2010 J&K Site Visit and 7 October 2010 Report
J&K Observations About the Light Wells and the Retaining Wall
J&K Observations About the Shoring Props
8 October 2010 Northwood Plans for Temporary Removal of Shoring Props
9-11 October 2010 Preparation for Removing Shoring Props
Installation of the Foundation Piles and Removal of Shoring Props
NMK Excavation of Foundation Piles
Excavation of the Lift Pit by Pile & Bucket
The Survey Monitoring Records
11 October 2010 Architect Notes Neighbour Concerns about Cracking
Lawyers for the Unit Owners Correspond with Builder About Cracking
5 November 2010 Hughes Inspection of Lift Pit
6 November 2010 Builder Shown Cracking
8 November 2010 J&K Email to the Builder About Monitoring Results
Builder Retains Mr Deaker and Constructs New Propping for Retaining Wall
The Cause of the Movement and the Joint Report
Causation
Responsibility
Responsibility for Movement of the Shoring Wall
Responsibility for Movement of the Retaining Wall
The Claims Made by the Owners Corporation and the Unit Owners
Particulars of Negligence Alleged Against the Builder
Particulars of Negligence Alleged Against Hughes
Conclusions of the Primary Judge
Claims of Breach Against the Builder
Claims of Breach Against Hughes
The Appeal
Ground 1: Excavation of the Northern Light Well
Ground 7: Excavation Below RL6.6m Contrary to Geotechnical Advice
Ground 8: Failure to Comply with Development Approval Conditions
Ground 9: Failure to Execute Monitoring Plan
Ground 2: Design of the Northern Light Well
Ground 3: Design of the Lift Pit
Ground 5: Design (Location) of the Basement Level Foundation Piles
Ground 6: Failure by Hughes to Take Action
Ground 11: Causation Generally
Conclusion
Figure A: The Architect's Plan for the New Apartment Building
Figure B: Hughes' Shoring Layout Plan - Issued Late 2009
Figure C: Northwood's Design - Level 0 - Shoring Wall with Straight Western Section, Shoring Props and Lateral Loading Piles with Capping Beams
Figure D: Photograph of 6 October 2010 Looking North Over Shoring Props Against Capping Beam of Shoring Wall - Sand Berm Visible Below Props
Figure G: Architect's Construction Plan for Level 1 - Incorporating Northwood's Proposed Straight Shoring Wall
Figure H: Detail of the Architect's Drawings with New Piles Indicated Around the Light Wells Marked in Black
Figure J: Waler Beam Visible Following Excavation to Level 0 with Foundation Piles Visible Below Shoring Props
Figure K: Northwood Sketches for Temporary Removal of Shoring Props
Figure L: Undated Photograph of Lift Shaft Excavation in Front of Waler Beam
Endnotes
Owners of Strata Plan No 30791
Southern Cross Constructions
Solicitors: Holman Webb Lawyers (Appellants) Thompson Cooper Lawyers (First and Second Respondents) Clyde & Co Australia (Third Respondent) File Number(s): 2019/150753 Publication restriction: Nil Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity - Technology and Construction List Citation: [2019] NSWSC 440 (Substantive); [2019] NSWSC 560 (Costs) Date of Decision: 16 May 2019 Before: Stevenson J File Number(s): 2013/179839
(2012) 246 CLR 182
(1950) 81 CLR 418