[2016] WASC 330
Supreme Court of WA
2016-10-24
Beech J
Original judgment source is linked above.
Other Party : Mr S K Dharmananda SC & Mr T J Porter
Other Party : Mr S K Dharmananda SC & Mr T J Porter
Other Party : Mr S K Dharmananda SC & Mr T J Porter
Other Party : Mr S K Dharmananda SC & Mr T J Porter
1 Samsung C&T Corporation (Samsung) is the head contractor for the Roy Hill Iron Ore Project. Samsung and Duro Felguera Australia Pty Ltd (Duro) are parties to a subcontract with a price of just over $500 million. From late last year, Duro has made monthly progress claims for payment under the subcontract, and Samsung has not paid those claims.
2 These proceedings concern five adjudication determinations under the Construction Contracts Act 2004 (WA), made on Duro's application, determining that Samsung pay Duro amounts totalling more than $60 million. Samsung seeks orders to set aside each of the adjudication determinations for jurisdictional error. Duro seeks leave to enforce each of the adjudication determinations.
3 In broad summary, I have reached the following conclusions:
(a) I would set aside the second determination on the ground that the adjudicator's reasons for refusing to give credit to Samsung for a payment on account of more than $6.66 million reveal jurisdictional error.
(b) I would set aside the third determination on the ground that jurisdictional error is revealed by the adjudicator's reasons relating to Samsung's submission to the adjudicator that a substantial element of Duro's claim, exceeding $32 million, was fatally flawed.
(c) I would dismiss Samsung's applications to set aside the other determinations.
(d) I would grant Duro leave to enforce those other determinations, being the first, fourth and fifth determinations.
(5) The grounds of Samsung's applications [37] [41].
(6) Reasons for allowing Samsung's amendment application [42] [77].
(8) Judicial review of determinations under the Act: legal principles [103] [115].
(9) Ground (d): adjudicators' findings that there were no new milestones [116] [140].
(10) Grounds (e) and (f): the third adjudicator's reasoning regarding the $32.4 million 'certified but setoff' [141] [228].
(11) Ground (g): did the first adjudicator fail to consider Samsung's setoff for its payment on account? [229] [259].
(12) Ground (h): did the second adjudicator exceed his jurisdiction in refusing to give Samsung credit for its payment on account? [260] [285].
(13) Ground (i): no payment claim because claim for payment not confined to construction work [286] [412].
(15) Should leave be given to enforce the determinations? [430] [462].
2. Contractual context 2.1 The Project and the Head Contract
5 Samsung is the head contractor with Roy Hill Holdings Pty Ltd for the Roy Hill Iron Ore Project (the Project).
(1) The Project is a 55 million tonne per annum iron ore open cut mining, processing, rail and port project being developed in the Pilbara.[1]
(2) The Project involves the establishment of a new iron ore mine at the Roy Hill deposit about 277 kms south of Port Hedland, a mine process plant, a heavy haul railway system from mine to port and new port facilities.[2]
(3) There are four packages of works under the head contract, termed 'Package 1 - the Mine Process Plant Works'; 'Package 2 - the Rail Works'; 'Package 3 - the Port Landside Works'; and 'Package 4 - the Port Marine Works'. Package 2 concerns the construction of the rail line connecting the mine site with the port from which processed ore would be despatched to customers.[3]
(4) The details of the works to be done, including the various packages and their interfaces, are set out in the document entitled 'Contract Scope of Work for 55 NTPA Integrated Mine Process, Rail and Port Facility' (the Scope of Work) which is an attachment to the '[Project] Subcontract for engineering, procurement, construction and commissioning of mining process plant (Package 1) Subcontract No ROYSCTS009' dated 30 August 2016 (the Original Subcontract).[4] The details of Package 1 are set out in part 4 of the Scope of Work, the details of Package 3 are set out in part 6, and the details of Package 4 are set out in part 7.
7 The Original Subcontract was entered into between Samsung as contractor and Duro and Forge Group Construction Pty Ltd (Forge) (together, the Consortium) as subcontractor.
8 Mr Northcott of Samsung says that, as initially executed, the Original Subcontract concerned only Package 1 and was for a fixed price of $1,327,500,000.[5] After execution, the price was increased to $1.472 billion as a result of two variations. Variation Order 001, dated 13 September 2013, incorporated the supply of equipment for Package 3 and Package 4 under a contract with a company referred to as DHHI. Variation Order 002, dated 20 January 2014, directed the Consortium to perform additional works and services in connection with contracts with DHHI and a company then referred to as TAKRAF.[6]
9 As will be seen, the Original Subcontract contemplated the work the subject of Variation Order 001.
10 There is, broadly, agreement as to the contract sum for the Original Subcontract as varied. Mr Rodriguez of Duro states in his affidavit[7] that the price of the Original Subcontract was $1,471,500,000.
12 It appears to be common ground that the scope of the Consortium's obligations under the Original Subcontract was identified primarily in the Special Conditions and the Scope of Work.[10] By cl 1 of the Special Conditions, the Consortium was obliged to perform engineering procurement, construction and commissioning works for the Mine Process Plant Works (Package 1) as described in the Scope of Work.
13 Clause 7 of the Special Conditions provided that Samsung would as soon as possible direct the Consortium to perform additional works under cl 36 of the General Conditions and that the value of the variation would be $144 million. Thus, the Original Subcontract contemplated Variation Order 001.
14 Under the Original Subcontract, the works were split between the members of the Consortium. Forge performed the engineering, construction and commissioning activities, and Duro performed the procurement (in other words, Duro supplied the major equipment).
15 It is common ground that the subcontract sum of $1.472 billion was split between Duro and Forge, with $642.138 million allocated to Duro and the remaining $830 million allocated to Forge.[11]
16 On 21 February 2014, the Original Subcontract was terminated by Samsung after Forge was placed in administration. In broad terms, Samsung then took over Forge's scope of work, and engaged Duro under a new contract to complete Duro's work under the Original Subcontract.
17 The new contract is referred to as the Interim Subcontract, and was made on 21 February 2014. It comprises a Term Sheet, with schedules, and the terms of the Original Subcontract as modified by the Term Sheet and its schedules. It is for the performance of what are referred to as the Duro Works.
18 The Interim Subcontract is referred to as the Interim Subcontract because, although it is legally binding on the parties, they intended to execute a substitute subcontract that would incorporate the terms and conditions of the Original Subcontract as modified by the Term Sheet and its schedules, together with any other related terms and conditions that Samsung and Duro considered reasonable or necessary (the Substitute Subcontract).
19 The parties did not agree upon the terms to be included in the Substitute Subcontract, and it was never executed.
20 I will set out the detailed provisions of the Interim Subcontract when I deal with ground (d) of Samsung's applications.
3. The adjudication determinations 3.1 The First Determination
21 The first determination concerned Duro's November 2015 progress claim under cl 37 of the Interim Subcontract General Conditions. In response to that progress claim, on 10 December 2015, Samsung issued a progress certificate certifying a negative amount of just under $6.5 million. On 24 December 2015, Duro made an adjudication application.
22 On 20 January 2016, Mr Loots published his determination (the First Determination) of Duro's claim. He determined that the adjudicated amount was a sum just over $9 million, excluding GST, to be paid by Samsung to Duro.
23 The second determination concerns Duro's November 2015 progress claim relating to certain novated contracts.
24 By email of 14 December 2015, Duro made a progress claim for payment of monies comprising four tax invoices for works it claimed were carried out under the novated contracts. On 18 December 2015 Samsung sent an email, attaching a letter dated 17 December 2015 rejecting that claim.
25 On 14 January 2016, Duro made an application for an adjudication. On 10 February 2016, the adjudicator, Mr Machell, published a determination (the Second Determination) that Samsung was to pay Duro $333,199, €182,690.45 and CNY11,617,671.01, plus GST.
26 The third determination concerned Duro's December 2015 progress claim. That claim was made on 31 December 2015 for payment of an amount in excess of $64 million. In response, Samsung issued a progress certificate on 11 January 2016 under which no money was payable to Duro. The terms and effect of this progress certificate are relevant to grounds (e) and (f) of Samsung's application. I will refer to it in detail in the context of dealing with those grounds.
27 On 5 February 2016, Duro applied for an adjudication determination, claiming payment of an amount of $49,642,958.72, plus GST. By his determination published on 3 March 2016 (the Third Determination), the adjudicator, Mr Loots, determined that Samsung was to pay that amount to Duro by 24 March 2016.
28 The fourth determination concerned Duro's progress claim, issued on 29 January 2016, for a sum of just under $60 million, plus GST. Samsung responded to this claim by a progress certificate on 10 February 2016. Samsung did not make any payment in respect of the January 2016 progress claim.
29 On 4 March 2016, Duro made an adjudication application claiming three components of the January 2016 progress claim totalling just over $6.8 million.
30 By a determination published on 8 April 2016 (the Fourth Determination), the adjudicator, Mr Fisher, determined that Samsung was to pay Duro the sum of $2,338,020.05, plus GST.
31 The fifth determination concerned Duro's February 2016 progress claim, made on 29 February 2016. That claim was for a total of just over $614,000.
32 By a progress certificate dated 10 March 2016, Samsung denied that it was liable to make any payment. It did not pay any amount in respect of the February 2016 progress claim.
33 By a determination published on 4 May 2016 (the Fifth Determination), the adjudicator, Mr Chidambara Raj, determined that Samsung was to pay to Duro the sum of $576,284.33, exclusive of GST.
34 There are 10 applications before the court. Five are Samsung's applications to quash the determinations. The other five are Duro's applications for leave to enforce the determinations.
35 All of these applications were programmed to be heard together. One reason for this was that Samsung advanced certain grounds, referred to below as grounds (a) (c), that were common to all of the determinations. Ultimately, at the hearing, Samsung abandoned grounds (a) (c).
36 I will deal with Samsung's applications first, before coming to Duro's applications for leave to enforce.
37 Each of Samsung's applications stated its grounds. It is not necessary for me to detail those grounds, because Samsung set out its grounds in its primary written submissions dated 26 May 2016. It was evident from Samsung's submissions that their statement of the grounds was intended to encapsulate and supersede the grounds stated in the five applications, although in large measure it reflected them. Insofar as the grounds listed in the written submissions went beyond the grounds in the applications, the parties' written and oral submissions dealt with the grounds as formulated in Samsung's submissions (as well, in the case of Duro, as the grounds as formulated in the applications).
38 Samsung's written submissions set out the following eight review grounds:
(a) The relevant adjudicator fell into jurisdictional error by acting on an incorrect view as to the meaning of the term 'construction contract' and thereby misunderstood the limits on the extent of his powers to adjudicate.
(b) The relevant adjudicator lacked jurisdiction because as a matter of objective fact the Interim Subcontract is not a construction contract for the purposes of the Act.
(c) Alternatively to (b), the relevant adjudicator did not form a reasonable state of satisfaction that the contract concerned was a construction contract and therefore the adjudicator had no jurisdiction to make the determination.
(d) The relevant adjudicator ignored the terms of the Interim Subcontract or so fundamentally misconstrued the terms of the Interim Subcontract by adopting reasoning as to the meaning of the contract that was unreasonable, illogical or irrational, such that the adjudications were made without regard to the terms of the construction contract and therefore in excess of jurisdiction.
(e) In dealing with the effect of the progress certificate in the third adjudication, the relevant adjudicator did not consider and provide reasons as to substantial matters raised by Samsung and thereby failed to comply with the Act and failed to afford procedural fairness.
(f) Further and alternatively to (e), the adjudicator in the third adjudication made a decision concerning the effect of a progress certificate that was so unreasonable that it was not the type of determination that the adjudicator was authorised by the Act to make and therefore was in excess of jurisdiction.
(g) In the first adjudication, the adjudicator failed to consider and provide reasons as to whether Samsung was entitled to set off an advance payment on account which had been certified as payable by Duro to Samsung.
(h) In the second adjudication, the adjudicator purported to bring to account a claim for an advance payment that was outside his jurisdiction.
39 On 27 July 2016, the first day of the hearing of the applications, Samsung applied to add a new ground, relating to all of the determinations except the fourth, in the following terms:
The Adjudicator fell into jurisdictional error by determining that each of the Determined Items were in respect of construction work which could be the subject of a payment claim that could be adjudicated under the Act, when the Determined Items included substantial work the subject of the mining exclusion, and the Adjudicator lacked jurisdiction to determine payment claims in respect of work the subject of the Mining Exclusion.
40 On 2 August 2016, I granted leave to Samsung to amend in those terms. The reasons for that decision are set out in the next section of these reasons. I will refer to the additional ground as ground (i).
41 On the second day of the hearing, Samsung abandoned grounds (a) (c).[12]
6. Reasons for allowing Samsung's amendment application 6.1 Introduction
42 As I have said, in the course of the hearing of these applications, Samsung applied to amend to add a new ground of review which I have called ground (i). Duro opposed the application.
43 At the conclusion of the hearing on 28 July 2016, I reserved my decision on the application. At that time I indicated that I was mindful of time passing while my decision on the application was reserved, and would inform the parties of my decision as soon as possible, with reasons to be published later, as part of the reasons on the substantive applications.[13]
44 On 2 August 2016, I informed the parties that leave to amend was granted, on terms that Duro have leave to file submissions and affidavits in response to the new ground by a date to be fixed. I fixed the time for the filing of submissions and any affidavits as 26 August 2016 in accordance with Duro's request. My reasons for my decision to grant leave are as follows.
45 The First Determination was made in January 2016. The proceedings seeking judicial review of the First Determination (CIV 1185 of 2016) and the proceedings seeking leave to enforce it (CIV 1255 of 2016) were commenced in February 2016. In the same month, the Second Determination was made and the proceedings seeking judicial review of it (CIV 1284 of 2016) and the proceedings seeking leave to enforce it (CIV 1257 of 2016) were commenced. The Third Determination was made in March 2016 and the Fourth Determination in April 2016. The judicial review proceedings in relation to these determinations (CIV 1719 of 2016 and CIV 1809 of 2016 respectively) were commenced in May 2016. The proceedings seeking leave to enforce the Third Determination (CIV 1596 of 2016) were commenced in April 2016. Enforcement proceedings in relation to the Fourth Determination (CIV 1773 of 2016) were commenced in May 2016. The Fifth Determination was made in the same month, and the judicial review proceedings (CIV 1905 of 2016) and enforcement proceedings (CIV 1899 of 2016) in respect of it were commenced on 1 June 2016.
46 In February 2016, directions were made for the filing of submissions and evidence in respect of the first and second determinations.
47 In May 2016, the existing programme was adjusted and directions were made in relation to Samsung's application in respect of the Third Determination.
48 Samsung's submissions in respect of the first three determinations were filed by the end of May 2016.
49 On 2 June 2016, orders were made that the applications relating to the fourth and fifth determinations be heard with the earlier applications. Directions were made for Duro to file its outline of submissions and for Samsung to file its submissions in reply by 4 July 2016.
50 Submissions were filed in accordance with those orders.
51 As I have said, Samsung's primary written submissions distilled the grounds of the various applications into eight paragraphs, denoted as (a) (h). Paragraphs (a) to (c) were essentially concerned with whether the Interim Subcontract was a construction contract.
52 Duro's submissions of 22 June 2016 pointed out, correctly, that Samsung's grounds for the applications did not raise any issue regarding the existence of a payment claim or a payment dispute.[14]
53 On 2 June 2016, the hearing of these ten applications was listed for two days, commencing on 27 July 2016.
54 Late in the morning on the first day of the hearing, Senior Counsel for Samsung foreshadowed an application to amend, but did not have the proposed amendment in writing. Immediately after the lunch adjournment, Samsung provided to Duro and to the court a minute of the draft ground of review the subject of the amendment application.
55 In order to allow for an informed assessment of whether leave to amend should be granted, Samsung made its submissions in support of the proposed ground on a provisional basis, subject to the question of whether leave would be granted. I will outline Samsung's submissions in support of ground (i) later in these reasons in dealing with its merits.
56 The next morning, on 28 July 2016, Samsung provided the court and Duro with a further version of the proposed ground of review, incorporating additional detail in respect of several determinations, and adding the fifth determination as part of the subject matter of the ground. I have set out the terms of the proposed ground in section 5 of these reasons.
57 Samsung did not file an affidavit explaining its delay in bringing the amendment application, but the question was addressed in some detail by Senior Counsel for Samsung.
58 In short, Samsung says that the lateness of the application arose from a combination of the delivery by the Court of Appeal on 21 July 2016 of its decision in Laing O'Rourke Australia Construction Pty Ltd v Samsung C&T Corporation[15] and the fact that, in the very late stages of preparation for the hearing, the definition of 'obligations' in s 3 came to the attention of counsel for Samsung for the first time. When attention was directed to this definition, it became apparent that it had consequences for Samsung's then existing grounds (a) (c). Further, it led to the formulation of the new proposed ground.[16]
59 It can safely be inferred from Samsung's written submissions, including its reply submissions of 4 July 2016, that counsel for Samsung had not then adverted to the definition of 'obligations' and its significance. That inference is reinforced by the fact that, on the second day of the hearing, Samsung abandoned grounds (a) (c). The definition of 'obligations' removed or at least substantially diminished one of the central planks of Samsung's contention as to how the term 'construction contract' was to be construed.
60 While the question of the definition of 'obligations' came to counsel's attention only immediately before the hearing of these applications, the attention of Samsung's solicitors was directed to the definition, and its possible consequences in relation to excluded work, by an adjudication between the parties that occurred in June 2016.[17] It is to be inferred that Samsung's solicitors did not appreciate that a possible argument in relation to these applications might arise from analysis of that definition, and did not draw it to the attention of counsel for Samsung.
61 This is not a case where a party has, for tactical reasons, left raising a point until the last minute. The proposed new ground only occurred to those appearing for Samsung at the very last stages of preparation for the hearing.
62 The goal in O 1 r 4A of the Rules of the Supreme Court 1971 (WA) and the objects in O 1 r 4B(1) are to be sought in exercising the power to grant leave to amend.
63 In Aon Risk Services Australia Ltd v Australian National University,[18] the High Court made observations about the considerations relevant to the exercise of a discretionary power to allow or refuse an amendment to a pleading in the Australian Capital Territory. Notwithstanding some differences in the language of the relevant rules, their Honours' observations are of assistance in Western Australia, and have been applied by courts in Western Australia. Those observations include the following:
(a) The effect of an amendment on the court and on other litigants is relevant.
(b) There is no right to amend to introduce an arguable case, and it is wrong to say that only in extreme circumstances would a party be shut out from litigating an arguable case.
(c) Justice requires that parties have a proper opportunity to plead their case, but limits may be placed on repleading when delay and cost are taken into account.
(d) A just resolution does not mean that a party will always be permitted to raise any arguable case at any point in the proceedings on payment of costs, even indemnity costs.
(e) The inevitable strains of litigation must be taken into account in weighing the adverse consequences of delay (this applies to natural persons and other litigants).
(f) The nature and importance of the amendment to the amending party must be taken into account.
(g) Attention must be given to the extent of the delay, the costs associated with it, the prejudice which might reasonably be expected to follow from it, and any prejudice that is shown.
(h) The point in the litigation relative to the trial may be an important consideration.
(i) Where a party seeks to have a discretion exercised in their favour, they will generally need to explain the reason for their application and any delay in bringing it.
(j) The point can be reached where it may be properly concluded that a party has had a sufficient opportunity to put its case and that it is too late for a further amendment.[19]
6.6 Duro's submissions in opposition to the amendment application
64 Duro's submissions in opposition to the application included the following:
(1) The proposed new ground was fundamentally different in character from grounds (a) to (c), and from the other grounds. It was directed to the existence of payment claims and payment disputes, whereas grounds (a) to (c) were about the scope of the term 'construction contract'.
(2) The proposed ground gave rise to the need for considerable further legal and factual analysis.
(3) It could not be said that the evidence relating to whether the items the subject of the Duro Works were construction work would be sufficient to determine the questions that would arise under the proposed new ground. Duro emphasised the width of the words 'in relation to' that are found in the definition of 'payment claim' in the Act. Duro submitted that those words would give rise to wider questions, including as to the connection between the particular works the subject of the proposed ground and other parts of the works under the Interim Subcontract.
(4) Because there is or may be a different test to be applied to payment claims (as opposed to construction contracts) in relation to excluded work, the evidentiary matters raised by the proposed new ground should not be seen as simply involving a subset of the evidence about the extent to which all of the items in the Duro Works are construction work or excluded work.
(5) In any event, the new ground focused specifically on a number of particular items of the claim the subject of each determination. That was a much narrower focus than that required under grounds (a) (c), which involved consideration of all of the Duro Works. Given the critical significance of particular items in relation to the proposed ground, Duro would be entitled to adduce further evidence in respect of those items.
(6) The large amounts of the adjudications cut both ways. While clearly Samsung's applications for judicial review were significant to it, the amounts in question also underscored the significance for Duro of the determinations, and of a timely resolution of its enforcement applications.
(7) The process of adjudication under the Act is designed to produce a rapid outcome, and an amendment would further delay resolution of the parties' disputes.[20]
65 It is important to bear in mind the nature of these proceedings and their subject matter. They are concerned with applications for judicial review in respect of, and applications for leave to enforce, determinations made under the Construction Contracts Act. The essence of the scheme of the Act is to provide for a speedy and informal mechanism for interim payments, pending later determination of the parties' ultimate rights. In that context, the avoidance of delay has a heightened significance.
66 To some extent, as Duro submitted, the large amounts of the adjudications cut both ways.
67 Given the extreme lateness of this application, I was not satisfied that it could safely be assumed that the evidence relating to whether items of the Duro Works were construction work would be sufficient to determine the questions that would arise under the proposed new ground. In response to Duro's submission outlined at (4) above, Samsung submitted that, on a proper construction, that is not the effect of the relevant definitions.[21] However, given the timing of the application, Duro had not had any opportunity to develop its submissions in that respect and, as Samsung accepted,[22] the court was not in a position to determine this question of construction at the hearing or within a short time thereafter.
68 In its particulars, the new ground focuses specifically on a certain number of items of the claim the subject of each determination. I accepted Duro's submission that this is a much narrower focus than that required under grounds (a) (c), which involved consideration of all of the Duro Works. Accordingly, when I granted leave to amend I did so on terms that Duro had leave to adduce further evidence.
69 I also accepted Duro's submission that at the hearing on 28 July 2016 it was not in a position to make a properly informed assessment of what evidence it would adduce in response to the new ground, and thus how long it would need to prepare that evidence. In considering my decision on the application to amend in the days following the conclusion of the hearing, I made the best assessment I could of how long Duro would need, based upon my knowledge of the evidence already exchanged and the relationship between the proposed ground and the previously existing grounds. I formed the view that Duro would be unlikely to require a period of much more than a month.
70 The scope and number of the issues on the ten applications before me and the court's other commitments meant that, putting aside the proposed new ground, the decision on the applications would be reserved for significantly more than a month. The delay in delivery of the reasons arising from allowing the amendment would not equate to the full period that was allowed for Duro's submissions and affidavits. Thus, while the extent of the delay that would have been consequent upon the amendment was uncertain, this was not a case where the amendment would have led to a delay in the conclusion of the proceedings in the order of months.
71 During the hearing of the application I made it clear that, if leave to amend were granted, Samsung would be confined to its oral submissions on ground (i).[23]
72 The consequences for Samsung of the refusal of the application would have been substantial. It would have lost the opportunity to advance an arguable ground to impugn the validity of four determinations, worth approximately $60 million. That consideration weighed significantly in the exercise of the discretion.
73 In the end, the question was whether the extreme lateness of the application, viewed in the context of the nature and subject matter of the proceedings, their history, the explanation for Samsung's delay, the need to determine the proceedings expediently, and the need to ensure that Duro had a fair opportunity to respond to the proposed ground, meant that the application should be refused.
74 While the need to ensure that Duro had a fair opportunity to respond to the proposed ground, and the consequent delay of a somewhat uncertain duration, weighed against the grant of leave, on balance I was satisfied that the interests of justice favoured the grant of leave to enable Samsung to advance the claim the subject of the proposed ground.
75 At the time I reserved my decision on the application on 28 July 2016, I contemplated that I might allow Duro to put on submissions and affidavits in opposition to the amendment application, and as to the merits of the new ground, on the basis that I could take those into consideration in deciding whether to grant leave. On reflection, I determined that such an approach was not in the interests of justice or the efficient progression of the matter. If Duro's submissions and evidence on the merits were comprehensive, by the time they were received there would be little further delay involved in granting, and consequently little reason to refuse, the amendment application. If Duro's evidence was not comprehensive, such an approach was liable to produce further delay.
76 For those reasons, on 2 August 2016 I granted leave for Samsung to add the proposed new ground, as ground (i), on terms that Duro would have leave to file submissions and affidavits in response by 26 August 2016.
77 In the circumstances, my assessment of Samsung's case on ground (i) must be confined to the contentions put in oral submissions.
78 The Construction Contracts Act is, by its long title, intended to prohibit or modify certain provisions in construction contracts; imply provisions in construction contracts about certain matters; and provide a means for adjudicating payment disputes arising under construction contracts.
80 Part 3 provides a means for adjudicating payment disputes arising under construction contracts. It provides that a party to a construction contract can apply to have a payment dispute that arises under that contract adjudicated by an adjudicator,[24] who must either dismiss the application in prescribed circumstances or determine the liability of a party to the payment dispute to make a payment, the amount to be paid, and any interest payable on it.[25]
81 'Construction contract' is defined in s 3 of the Act as follows:
construction contract means a contract or other agreement, whether in writing or not, under which a person (the contractor) has one or more of these obligations -
(a) to carry out construction work;
(b) to supply to the site where construction work is being carried out any goods that are related to construction work by virtue of section 5(1);
(c) to provide, on or off the site where construction work is being carried out, professional services that are related to the construction work by virtue of section 5(2);
(d) to provide, on the site where construction work is being carried out, onsite services that are related to the construction work by virtue of section 5(3)(b).
82 Construction work is defined in s 4. Section 4(1) and (2) are detailed provisions that identify the ambit of construction work. One kind of construction work is constructing the whole or a part of any civil works, or a building or structure that forms or will form a part of land.[26] Civil works include a road, railway, harbour, port or marina.[27] Construction work also includes any work on a site in Western Australia that is preparatory to, necessary for, an integral part of, or for the completion of, these kinds of construction work.[28]
83 Section 4(3) excludes certain work from being construction work. It provides as follows:
(3) Despite subsection (2) construction work does not include any of the following work on a site in WA -
(a) drilling for the purposes of discovering or extracting oil or natural gas, whether on land or not;
(b) constructing a shaft, pit or quarry, or drilling, for the purposes of discovering or extracting any mineral bearing or other substance;
(c) constructing any plant for the purposes of extracting or processing oil, natural gas or any derivative of natural gas, or any mineral bearing or other substance;
(d) constructing, installing, altering, repairing, restoring, maintaining, extending, dismantling, demolishing, or removing, wholly artistic works, including sculptures, installations and murals;
(e) work prescribed by the regulations not to be construction work for the purposes of this Act.
84 Section 5 provides that in certain circumstances, goods, professional services and onsite services are related to construction work. It reads as follows:
Goods and services related to construction work
(1) For the purposes of this Act, goods are related to construction work if they are -
(a) materials or components (whether prefabricated or not) that will form part of any thing referred to in section 4(2)(b) or 4(2)(c) or of any fittings referred to in section 4(2)(d); or
(b) any fittings referred to in section 4(2)(d) (whether prefabricated or not); or
(c) plant or materials (whether supplied by sale, hire or otherwise) for use in connection with the carrying out of the construction work at the site of the construction work; or
(d) goods prescribed by the regulations to be related to construction work for the purposes of this Act.
(2) For the purposes of this Act, professional services are related to construction work if they are -
(a) services that are provided by a profession and that relate directly to construction work or to assessing its feasibility (whether or not it proceeds) -
(i) including surveying, planning, costing, testing, architectural, design, plan drafting, engineering, quantity surveying, and project management, services; but
(ii) not including accounting, financial, or legal, services;
(b) services that are provided by a profession that are prescribed by the regulations to be professional services related to construction work for the purposes of this Act.
(3) For the purposes of this Act, onsite services -
(a) are services other than professional services referred to in subsection (2); and
(b) are related to construction work if they are -
(i) services that relate directly to construction work, including the provision of labour to carry out construction work; or
(ii) services prescribed by the regulations to be onsite services related to construction work for the purposes of this Act.
(4) The regulations may prescribe goods, professional services or onsite services that are not related to construction work for the purposes of this Act.
85 A contract will be a construction contract if it obliges the contractor to supply to the site where construction work is being carried out materials or components that will form part of a building or structure that will form part of the land.[29] Further, a contract will be a construction contract if it obliges the contractor to provide, on the site where construction work is being carried out, onsite services that relate directly to construction work, including the provision of labour to carry out construction work.[30]
86 As I have said, pt 3 of the Act provides for the adjudication of payment disputes under construction contracts.
87 Section 25 provides that, if a payment dispute arises under a construction contract, any party to the contract may apply to have the dispute adjudicated under pt 3 (subject to two exceptions that are not presently relevant).
88 Section 6 provides as follows:
For the purposes of this Act, a payment dispute arises if -
(a) by the time when the amount claimed in a payment claim is due to be paid under the contract, the amount has not been paid in full, or the claim has been rejected or wholly or partly disputed;
(b) by the time when any money retained by a party under the contract is due to be paid under the contract, the money has not been paid; or
(c) by the time when any security held by a party under the contract is due to be returned under the contract, the security has not been returned.
89 Section 6 identifies three categories of payment dispute, each with a different foundation: (a) an unpaid, rejected or disputed payment claim; (b) retention monies that have not been repaid; and (c) a security that has not been returned. The first category, but not the other two, is founded on a payment claim.
90 'Payment claim' is defined in s 3 as follows:
payment claim means a claim made under a construction contract -
(a) by the contractor to the principal for payment of an amount in relation to the performance by the contractor of its obligations under the contract; or
(b) by the principal to the contractor for payment of an amount in relation to the performance or non performance by the contractor of its obligations under the contract.
91 Section 3 provides the following definition of 'obligations':
obligations, in relation to a contractor, means those of the obligations described in the definition of 'construction contract' that the contractor has under the construction contract.
92 Ground (i) concerns the proper construction of these definitions and s 4(2) and s 4(3), when inserted into s 31(2)(b), set out below, and when applied to the work the subject of the first, second, third and fifth determinations.
93 Section 31 of the Act sets out the powers and duties of an adjudicator. It provides as follows:
An appointed adjudicator must, within the prescribed time or any extension of it made under section 32(3)(a) -
(a) dismiss the application without making a determination of its merits if -
(i) the contract concerned is not a construction contract;
(ii) the application has not been prepared and served in accordance with section 26;
(iii) an arbitrator or other person or a court or other body dealing with a matter arising under a construction contract makes an order, judgment or other finding about the dispute that is the subject of the application; or
(iv) satisfied that it is not possible to fairly make a determination because of the complexity of the matter or the prescribed time or any extension of it is not sufficient for any other reason;
(b) otherwise, determine on the balance of probabilities whether any party to the payment dispute is liable to make a payment, or to return any security and, if so, determine -
(i) the amount to be paid or returned and any interest payable on it under section 33; and
(ii) the date on or before which the amount is to be paid, or the security is to be returned, as the case requires.
94 The object of the adjudication process is to determine the dispute fairly and as quickly, informally and inexpensively as possible.[31]
95 Section 31 prescribes a short timeframe (14 days) within which an adjudicator is required to make a determination. That timeframe can only be extended with the consent of the parties.[32]
96 Section 32 makes provision for matters of procedure. It provides, among other things, that appointed adjudicators must act informally; are not bound by the rules of evidence and may inform themselves as they see fit; may request further submissions or information from the parties; and may, unless all parties object, inspect any work or thing to which the payment dispute relates, or arranging testing or expert investigation of it.
97 If an appointed adjudicator either dismisses an application under s 31(2)(a) or makes a determination under s 31(2)(b), they must provide the parties with written reasons for doing so.[33] I will set out s 36, dealing with reasons, during my analysis of ground (g).
99 Division 5, comprising s 42 and s 43 of the Act, deals with the enforcement of determinations. Section 42 provides for a form of 'self help'. By that section, if a determination requires a principal to pay the contractor an amount, and the principal does not pay, the contractor may suspend the performance of its obligations pending payment without becoming liable for any loss or damage suffered by the principal and while retaining its rights under the contract. Section 43 provides for the curial enforcement of determinations, as a judgment or order of the court, if the court grants leave.
100 By s 45, an adjudication does not prevent the parties from instituting proceedings before an arbitrator or other person, or a court, and the adjudication will proceed despite the institution of proceedings unless the parties agree otherwise.
101 An adjudicated amount must be paid, but is on account only and is subject to a final determination of the parties' rights by a court or arbitrator.[34]
102 Section 46 provides for a limited right of review for a person who is aggrieved by a decision made under s 31(2)(a).
8. Judicial review of determinations under the Act: legal principles
103 A determination made pursuant to s 31(2)(a) or s 31(2)(b) of the Act can be challenged by proceedings for judicial review.[35] Section 46 does not preclude judicial review for jurisdictional error.[36]
104 Insofar as the distinction between an inferior court and an administrative tribunal has utility,[37] an adjudicator under the Act is more akin to an inferior court.[38] An adjudication determination is not susceptible to judicial review for a nonjurisdictional error, such as an error of law on the face of the record.[39]
105 When an application is made to have a dispute adjudicated under the Act, an adjudicator has two distinct and alternative functions. An adjudicator cannot proceed under s 31(2)(b) to determine an application on its merits if the application is one which must be summarily dismissed under s 31(2)(a). The power under s 31(2)(a) must be exercised 'in its own right'.[40] If an adjudicator were to proceed under s 31(2)(b) to determine an application which ought to have been dismissed under s 31(2)(a), they would be acting without power.[41]
106 In other words, the criteria in s 31(2)(a)(i) - (iv) are jurisdictional facts which must be established in order to enliven the adjudicator's power to make a determination under s 31(2)(b).[42] Whether the criteria in s 31(2)(a)(i) (iii) are jurisdictional facts in the broad or narrow sense is controversial. I will return to that question in determining ground (i).
107 An adjudicator's power to act under s 31(2)(b) also depends upon the existence of a payment dispute within the meaning of the Act.[43]
108 As I have said, an adjudicator's determination under s 31(2)(b) can be the subject of judicial review for jurisdictional error. The categories of jurisdictional error are not closed. It is not possible to make a comprehensive statement of the boundaries of jurisdictional error.[44] It can often be difficult to draw the distinction, in a given fact situation, between a jurisdictional error and an error in the exercise of jurisdiction.[45]
109 Some categories of jurisdictional error in respect of inferior courts and analogous bodies are well established:[46]
First, if an inferior court or an anomalous tribunal mistakenly asserts or denies the existence of jurisdiction. Second, if it misapprehends or disregards the nature or limits of its functions or powers in a case where it correctly recognises that jurisdiction does exist. Third, if it is an essential condition of the exercise of jurisdiction with respect to a particular matter that a certain event or requirement has in fact occurred or been satisfied (which I understand to be a reference to a jurisdictional 'fact') there will be jurisdictional error if the court or a tribunal purports to act in circumstances where that event has not in fact occurred or that requirement has not in fact been satisfied even though the matter is the kind of matter which the Court has jurisdiction to entertain. Fourth, jurisdictional error will occur where an inferior court disregards or takes account of some matter in circumstances where the statute establishing it and conferring its jurisdiction requires that that particular matter be taken into account or ignored as a precondition of the existence of any authority to make an order or decision in the circumstances of the case. Fifth, it will exceed its authority and fall into jurisdictional error if it misconstrues the statute establishing it and conferring jurisdiction and thereby misconceives the nature or the function which it is performing or the extent of its powers in the circumstances of the case.
110 Another wellestablished category of jurisdictional error is where a decision is made in breach of the requirements of procedural fairness.[47]
111 Often, the identification of a jurisdictional error is not assisted by applying descriptive verbal formulations or characterisations of what the decisionmaker did.[48] The preferable approach in the context of the Act is to identify precisely what the adjudicator did, and then, having construed the Act as a whole, to decide whether what the adjudicator did constitutes a determination of the kind for which the Act provides.[49]
112 In determining whether an error is of a kind which is within jurisdiction, or which exceeds jurisdiction, regard must be had to the statute as a whole. It is obvious from the scheme of the Act that it contemplates that adjudicators may make some errors without exceeding their jurisdiction. In that regard, relevant elements of the statutory scheme include the following:
(1) The adjudication process is intended to be a trade off between speed and contractual and legal precision.
(2) Determinations are not final - they are taken to be payments on account.
(4) An adjudicator is required to act informally, is not bound by the rules of evidence and is largely entitled to determine their own procedure.[50]
113 An adjudicator does not exceed their jurisdiction simply by misconstruing the construction contract, or by making an error in the application of the terms of the contract to the facts found.[51] Examples of errors of this kind, as errors within jurisdiction, may be found in Laing O'Rourke v Samsung [2016].[52] Obviously, the making of an error in a finding of fact does not in itself constitute jurisdictional error.
114 In proceedings for judicial review of a determination, the character of which includes the features outlined in (1) (4) of [112], a court must not scrutinise the reasons for the determination with an eye 'keenly attuned to the perception of error'.[53]
9. Ground (d): adjudicators' finding that there were no new milestones 9.1 Introduction
116 In the Second Determination and the Fourth Determination, Samsung claimed before each adjudicator that it was entitled to setoff liquidated damages for delay against claims made by Duro. Both adjudicators rejected Samsung's claim on the basis that under the Interim Subcontract there were no new milestones, so that liquidated damages did not apply.
117 By ground (d) Samsung claims that, in so finding, each adjudicator made a jurisdictional error in that they made their determination without regard to the Interim Subcontract, or because they adopted a construction of it that was outside reasonable bounds.
118 Samsung did not pursue a similar ground in the application relating to the Third Determination.[54]
119 In order to understand this ground, it is necessary to set out the provisions of the Interim Subcontract in some detail.
120 The recitals of the Term Sheet were as follows:
(a) Samsung, entered into a subcontract with Duro and Forge Group Construction Pty Limited (Forge) (Subcontract) in relation to the engineering, procurement and construction of certain works in respect of the Roy Hill iron ore mining project (Project).
(b) An administrator and receiver have been appointed to Forge. Forge has also committed other acts and omissions that constitute defaults of the Subcontract.
(c) Samsung terminated the Subcontract on 21 February 2014.
(d) This term sheet (Term Sheet) sets out the key terms and conditions (as set out in Schedule 1) that will form a replacement subcontract between Samsung and Duro (Substituted Subcontract).
(e) The parties agree to cooperate in good faith in the preparation of a Substitute Subcontract and any Substitute Subcontract will reflect the terms and conditions of this Term Sheet.
121 By cl 1, the parties acknowledged and agreed that the Term Sheet would take effect on and from the Start Date, 21 February 2014.
The parties agree and acknowledge that, on and from the Start Date, Duro will continue to perform the scope of works set out in Schedule 2 (Duro Works) under this Term Sheet which will become legally binding on the parties and will apply as a binding agreement between the parties (Interim Subcontract), and Duro shall in good faith continue to perform the Duro Works under the Interim Subcontract. The Interim Subcontract is on the same terms as the Subcontract as modified by the terms set out in this Term Sheet and its schedules for the performance of the Duro Works. The parties acknowledge and agree to negotiate in good faith and make such additional changes as are logically or practicably required considering the Duro Works and execute a Substitute Subcontract which is based on the terms of the Subcontract as modified in this Term Sheet, as soon as reasonably possible.
(a) The terms and conditions set out in Schedule 1 are made a part of this Term Sheet and the Interim Subcontract and shall apply from the Start Date.
(b) Subject to clause 2.1(a), if directed to in writing by Samsung, Duro undertakes to execute, as soon as reasonably practicable after receipt of that direction, a Substitute Subcontract that incorporates the terms and conditions of the Subcontract as modified by Schedules of this Term Sheet, together with any other terms and conditions that Samsung and Duro consider are reasonable or necessary that directly relate to the terms and conditions as set out in Schedules of this Terms Sheet.
(c) The Substitute Subcontract will, upon execution, supersede this Term Sheet and bind Samsung and Duro in relation to its subject matter.
124 Schedule 1 set out terms and conditions which, by cl 2.2(a), were made part of the Term Sheet and the Interim Subcontract. Schedule 1 relevantly included the following:
Duro will perform the works referred to in Schedule 2 (Duro Works).
Samsung will pay Duro for performance of the Duro Works.
125 Schedule 2 was headed 'Duro Works', as referred to in cl 2.1(a). In fact, what followed in sch 2 were provisions for liquidated damages and milestones, the subject of sch 3. Contained in sch 3, but evidently intended to be the contents of sch 2, was a spreadsheet setting out the Duro Works. For convenience and consistency with the Term Sheet, I will refer to the schedules as if their contents were correct.
126 In broad summary, both adjudicators accepted Duro's submission that the new procurement milestones set out in sch 3 were, by item 4 of sch 1, applicable to the Substitute Subcontract, but not the Interim Subcontract.
127 In the Second Determination, Mr Machell addressed the proper construction of the Interim Subcontract at pages 19 to 21 of his reasons. He found that the Interim Subcontract does two things. First, it expresses the contractual relationship between the parties. Secondly, it expresses their intention to enter into a subsequent Substitute Subcontract, and indicates some of the terms that they intended to incorporate into that Substitute Subcontract.[55]
128 Mr Machell set out recitals (d) and (e) of the Term Sheet, as well as cl 2.1(a) and cl 2.2(a). He then set out parts of sch 1 items 1 4. He emphasised that these items referred to the Substitute Subcontract, not the Interim Subcontract.[56]
129 The adjudicator found that, as the only reference to a contract sum in the Interim Subcontract was to the sum that would be included in the Substitute Subcontract, the parties had not agreed a contract sum for the Interim Subcontract in writing.[57]
130 Mr Machell found that the Interim Subcontract did not make provision for liquidated damages and did not contain milestones for the completion of various works.[58]
131 In the Fourth Determination, Mr Fisher rejected Samsung's contention that the milestones and liquidated damages set out in sch 3 applied to the Interim Subcontract. He stated that the words of sch 1 in item 4 were conclusive.[59] He quoted those words, which were that the '[n]ew procurement Milestones and liquidated damages will apply to the Substitute Subcontract, as attached to the Term Sheet at sch 3'. Mr Fisher found that this was the only place where sch 3 was mentioned in the Term Sheet and that the milestones and liquidated damages in sch 3 did not apply to the Interim Subcontract.[60]
132 Mr Fisher then proceeded to deal with Samsung's alternative contention that the intention of the Interim Subcontract was that the unmodified Original Subcontract milestones would continue to apply to the Interim Subcontract until the Substitute Subcontract was agreed and signed.[61]
133 The adjudicator found that there was no provision in the Interim Subcontract for completion of the works within a fixed time, so that there was no room for liquidated damages. Rather, the obligation of Duro was to complete the works within a reasonable time.[62]
134 Mr Fisher also found that the lump sum price specified in item 2 of sch 1 to the Term Sheet did not apply to the Interim Subcontract. Mr Fisher highlighted the fact that this item referred specifically to the Substitute Subcontract and not the Interim Subcontract. He said that if the drafter of cl 2 had intended to include the price in the Interim Subcontract that would have been spelt out.[63]
135 Samsung contends that it is clear that the milestones and liquidated damages set out in sch 3 to the Term Sheet were to apply as part of the Interim Subcontract from 21 February 2014.[64] In support of that contention, Samsung points to the following matters:
(1) The Term Sheet provided for Duro to perform the Duro Works from the Start Date of the Term Sheet.
(2) Clause 2.1(a) expressly provides for the Interim Subcontract to be 'on the same terms as the [Original] Subcontract as modified by the terms set out in this Term Sheet and its schedules for the performance of the Duro Works'.
(3) Clause 2.2(a) provides that the terms and conditions set out in sch 1 are made a part of the Term Sheet and the Interim Subcontract and shall apply from the Start Date. The terms and conditions in sch 1 include, as item 4, the term that new procurement milestones and liquidated damages will apply to the Substitute Subcontract.
(4) All of the obligations in sch 1 are expressed by reference to the Substitute Subcontract. Accordingly, on the adjudicators' approach, there was no agreed contract sum, no agreement concerning deduction of advance payments and no limit on Duro's aggregate liability under the Interim Subcontract.
(5) The parties' obligations under cl 2.1(a) were to negotiate in good faith and make such additional changes as were logically or practically required, and then to execute a Substitute Subcontract based on the terms of the Original Subcontract as modified in the Term Sheet as soon as was reasonably practicable. These obligations reflect an intention that the terms and conditions in sch 1 would apply immediately and were not a matter for further negotiation.[65]
136 In its written submissions, Samsung asserted that an adjudicator's determination must be within the bounds of what a reasonable adjudicator might consider to be a reasonably available construction of the relevant construction contract that justifies a progress payment being required to be made on a provisional basis. It submitted that, in order to be within jurisdiction, the construction adopted by an adjudicator must be one that is reasonably likely to be accepted ultimately by a court or arbitrator finally determining the rights of the parties.[66] However, in light of the decision of the Court of Appeal in Laing O'Rourke v Samsung [2016], delivered after those submissions were filed and before the hearing of these applications, Samsung did not pursue these contentions. Rather, Samsung submits that the approach to be adopted, in light of the decision in Laing O'Rourke v Samsung [2016], is as I have outlined it in [111] [113] above.[67]
137 There is force in Samsung's submissions as to why its construction of the Interim Subcontract is to be preferred. However, that is not the question on an application of this nature. There is no doubt, as Samsung accepts,[68] that an adjudicator has jurisdiction to err in the construction of a contract. Samsung emphasises that the statutory task of an adjudicator is to determine whether a party is liable to make a payment on the balance of probabilities by reference to an assessment of the parties' contractual rights, applied to the facts found by the adjudicator.[69] Samsung emphasises, and I accept, that this task may be contrasted with one where a decisionmaker is entitled to take into account the contractual position, but also other, broader factors.[70]
138 Both adjudicators focussed their attention on the relevant contractual provisions, and came to a conclusion as to how those provisions were to be construed.
139 On my analysis of what the adjudicators did, I am not persuaded that any error on the part of the adjudicators in determining whether milestones applied to the Interim Subcontract was anything more than an error in construing the Interim Subcontract. Samsung's submissions fall well short of persuading me that, insofar as the adjudicators in the Second Determination and the Fourth Determination found that there were no new milestones under the Interim Contract, those determinations were not of a kind for which the Act provides.
10. Grounds (e) and (f): the third adjudicator's reasoning regarding the $32.4 million 'certified but setoff'
141 These grounds impugn the validity of the Third Determination. They relate to a significant element, more than $30 million, of Duro's claim the subject of that determination.
142 The Third Determination concerned Duro's December 2015 progress claim.
143 The nature of these grounds, and the competing submissions on them, make it necessary to give detailed attention to the submissions made by Duro and Samsung to the adjudicator.
144 In the application the subject of the Third Determination, Duro claimed payment of an amount exceeding $49.6 million. That amount comprised three components. One was an amount of $34,186,114.38 said to have been 'certified [by Samsung]' as payable, but setoff in Samsung's December 2015 progress certificate issued on 11 January 2016.[71]
145 Duro asserted that the Duro Works were 99% complete, but a significant proportion of the contract sum remained unpaid.[72]
146 Duro said that Samsung had previously setoff and withheld amounts in relation to defect rectification and modularisation costs, but had subsequently conceded that its setoffs for defect rectification were wrongful, and reversed them.[73]
147 In its application and its adjudication submissions, Duro stated that on 31 December 2015 it had issued the payment claim constituted by its December 2015 progress claim. Duro's adjudication submissions outlined the amounts the subject of that claim, stating that it totalled over $64.3 million.[74]
148 Duro stated that on 11 January 2016, Samsung issued its December 2015 progress certificate, which certified the sum of $34.186 million as payable to Duro, but asserted that none of that amount was payable because of setoffs effected in previous progress certificates.[75] Duro also stated that in the December 2015 progress certificate Samsung rejected a further $14.7 million worth of Duro's claims relating to a car dumper and rejected Duro's claims for Paradigm's commissioning works.[76]
149 Duro's submissions to the adjudicator annexed copies of the December 2015 progress claim and progress certificate.[77]
151 Duro's submissions to the adjudicator stated that its claim to the amount of $34.18 million, 'the amount certified but setoff', was described in detail in section 15 of its submissions. That section of Duro's submissions can be summarised as follows:
(1) The majority of the amount of $34.1 million, namely $32,428,183, related to a reversal by Samsung of a prior setoff claim relating to defect rectification.[79]
(2) Samsung had purported to setoff amounts which it asserted were its costs of rectifying defects for which Duro was responsible and, as at 10 December 2015, the date of Samsung's November progress certificate, the total amount setoff was $32,428,183.[80]
(3) Samsung was not entitled to setoff any amount against the amount said to be certified for payment.[81] That was so for two reasons. First, Samsung did not satisfy the contractual preconditions in cl 29.3 of the General Conditions, which must be satisfied for Samsung to have a right to claim defect rectification costs. Secondly, Samsung claimed defect rectification costs from Duro in respect of works that were not part of the Duro Works under the Interim Subcontract.
(4) In December 2015, following repeated statements by Duro that Samsung's failure to comply with cl 29.3 was a potentially repudiatory breach of the Interim Subcontract, Samsung agreed to 'reverse' its previous setoffs in respect of defect rectification.[82]
(5) Since then, the parties have corresponded about conducting a detailed review of the alleged defects and only when that review is completed will Samsung have any entitlement to setoff amounts in respect of defect rectification.[83]
(6) In recognition of that position, Samsung has certified the amount previously setoff as an amount now payable to Duro.[84]
(7) Samsung's only basis for refusing to pay Duro that amount and the balance of the certified amount is its reliance on its remaining setoff claims relating to liquidated damages, modularisation costs and TAKRAF vendor assistance. Duro's position as to these setoffs is set out in parts 5 and 6 of its adjudication submissions.[85]
(8) If the adjudicator accepted that the setoffs could not be considered in the application, or found that they were without merit, then it would follow that Samsung had to pay Duro the certified amount.[86]
152 Duro's submissions to the adjudicator then proceeded to explain the additional claims, including five claims relating to the car dumper.[87]
153 The remainder of Duro's submissions to the adjudicator dealt with the merits of Samsung's claimed prior setoffs.[88]
154 Section 1 of Samsung's adjudication submissions was entitled 'Executive Summary'. It identified three key issues. The first key issue related to jurisdiction, and had three elements. First, Samsung asserted that the Interim Subcontract was not a construction contract and so the adjudicator had no jurisdiction. Secondly, it asserted that the application should be dismissed because of its complexity.
155 The third element of the jurisdictional issue was expressed as follows:
[Duro] is not entitled to payment of $32,428,183, which is the amount [Samsung] previously set off for defective works in the November Progress Certificate, and subsequently included on the December Progress Certificate. If [Duro] wanted to have this payment dispute adjudicated, it was obliged to do so by 7 January 2016. Accordingly, this claim is out of time and cannot be adjudicated (see section 4 of this response).[89]
156 Part A of Samsung's adjudication submissions related to jurisdiction. Section 2 set out a summary of Samsung's key contentions. The first was expressed in the following terms:
In the November Progress Certificate issued on 10 December 2015 [Samsung] set off $32,428,183 for defective works. In the December Progress Certificate, as a sign of good faith and without prejudice to its previous position, [Samsung] reversed $32,428,183 for defective works. As a matter of jurisdiction, the reversal of $32,428,183 on the December Progress Certificate:
(1) does not give rise to a payment claim for the purposes of the Act;
(2) [Alternatively is time barred];
(3) [Alternatively was the subject of a previous adjudication determination].[90]
157 The second and third contentions were that the application should be dismissed because of its complexity, or because the Interim Subcontract was not a construction contract.
158 Section 4 of the submissions dealt with Duro's claim for the 'amount certified but setoff'.
159 Samsung submitted that this part of Duro's claim had not been included in its progress claims.[91] It stated that 'the certified amount of $34,186,114.38 is made up of the following amounts:
160 Samsung stated that its jurisdictional submissions related primarily to the $32,428,183 for defective works.[93]
161 In section 4.1, Samsung's submissions set out a chronology of events relating to the progress certificates and the amount said to be certified but setoff.[94] Subject to one qualification, the chronology is accurately summarised in Samsung's submissions in these proceedings.[95] In summary:
(1) In the October progress certificate, issued on 10 November 2015, Samsung setoff an amount of just over $25,000,000 for defective works against the amounts owing to Duro. The total amount certified by Samsung in that certificate was $87,621,000, meaning that, on that certificate, Duro owed Samsung an amount in excess of $87,000,000.
(2) On 9 December 2015, Samsung provided Duro with an updated figure as to its accumulated claim for defective works, being $32,428,183 (in substitution for the amount of $25,062,587 used in the October progress certificate).
(3) In the November progress certificate, issued on 10 December 2015, Samsung setoff that sum of $32,428,183. The total amount certified by Samsung in the November progress certificate was negative $6,475,886.
(4) On 15 December 2015, Duro wrote to Samsung stating that in failing to comply with cl 29.3 Samsung had repudiated the Interim Subcontract.
(5) In response, on 24 December 2015, Samsung wrote to Duro proposing to confer in good faith in relation to the defective works and, in the meantime, to remove the defective works claims from the December progress certificate, without prejudice to its rights.
(6) In the December progress certificate, issued on 11 January 2016, the negative amount for defective works was reversed.
162 The qualification I referred to in [161] is that, in its submissions to the court, Samsung says that its adjudication submissions stated that only the amount of $1,757,931 was certified as payable to Duro.[96] I do not accept that this was stated in Samsung's submissions to the adjudicator. Those submissions focused on whether the reversal of the setoff for defective works gave rise to a payment claim, and not on whether the amount of $34,186,114 was certified by Samsung as payable to Duro.
163 Samsung made the following submissions to the adjudicator:
(a) referred to a previous letter by [Samsung] to [Duro], in which [Samsung] agreed to remove the amount setoff for defective works pending the process described in that letter;
(b) reiterated [Samsung's] agreement in good faith to remove the amount set-off for defective works in the November Progress Certificate, without prejudice to its rights under the Interim Subcontract; and
(c) stated that [Samsung] was expressly reserving its rights to set-off the amounts for defective works in future progress certificates.
164 Paragraphs 42 to 48 of Samsung's adjudication submissions developed its alternative contention that Duro was time barred from seeking payment of the $32.4 million. Paragraphs 49 to 64 developed Samsung's alternative contention that the adjudicator had no jurisdiction in relation to the claim for $32.4 million because the claim was recycled. The submissions made clear that these contentions were put in the alternative, and only arose if Samsung's primary contention - that there was no payment claim by Duro for the amount of $32.4 million - was rejected.[97]
165 Part 6 of Samsung's adjudication submissions dealt with its contention that Duro's application should be dismissed under s 31(2)(a)(iv) because of its complexity. Part 7 dealt with Samsung's contention that the application should be dismissed because the Interim Subcontract was not a construction contract, and part 8 dealt with the merits of Duro's six additional claims.
166 In the introductory part of his reasons, the adjudicator stated, without discussion, and apparently by way of general background, that:
(1) on 31 December 2015, Duro issued its monthly progress claim seeking payment totalling $64,361,606, plus GST;
(2) on 11 January 2016, Samsung issued a progress certificate 'certifying an amount of $34,186,114.38 as payable to [Duro] ... but asserted that none of that amount would be paid because of setoffs effected in previous progress certificates; and rejected the remainder of [Duro's] claim';
(3) in its application Duro claimed payment of $49,642,958 of the total amount claimed in the payment claim of 31 December 2015, made up as follows:
(a) the amount certified as payable but setoff ($34,186,114);
(b) the amount claimed in respect of the car dumper; and
(c) part of the amount claimed for commissioning of a control system.[98]
167 The adjudicator then dealt with the question of his jurisdiction in [21] [23] of his reasons. He stated that Samsung submitted that he 'must dismiss the application under s 31(2)(a)(ii) of the Act without making a determination of its merits'.[99] He identified that in order for him to have jurisdiction he had to be satisfied that there was a construction contract, a payment claim and a payment dispute, and that the payment dispute had arisen under the construction contract.[100]
168 The adjudicator found that all of those elements existed. After referring to the definition of 'payment claim', he found that:
(2) that a payment dispute arose on 11 January 2016, when Samsung issued the progress certificate certifying the amount of $34,186,114 as payable to Duro, but asserted that none of that amount would be paid because of setoffs effected in previous progress certificates and rejected the remainder of the payment claim, being the amount claimed in respect of the car dumper and part of the amount of the claim for commissioning of a control system.[102]
169 Nothing more was said in relation to those conclusions.
(a) the Interim Subcontract was a 'construction contract';[103]
(b) the payment dispute had arisen under that construction contract;[104]
(d) the complexity of the matter was not such as to make it impossible to make a determination fairly within the prescribed time.[106]
171 The adjudicator stated that he had referred to the documents comprising the application and the response, and listed them.[107]
172 The adjudicator set out his findings in relation to Duro's claim for the 'amount certified but setoff' in [33] [110] of his reasons. Those paragraphs deal with questions about whether Samsung was entitled to setoff various counterclaims against what was said to be the certified amount. The adjudicator determined those questions favourably to Duro. He referred to Samsung purporting to setoff its claims against 'amounts it concedes are due to [Duro]'.[108]
173 The balance of the adjudicator's reasons dealt with Duro's other six claims. In his conclusion, the adjudicator set out a table summarising his findings. Relevantly, he referred to the amount of $34,186,114 as the 'amount certified but setoff' and awarded that amount in full.[109]
10.4 The evidentiary material before the adjudicator
174 The evidentiary material before the adjudicator included the following. Samsung provided a statutory declaration by Mr Northcott which set out the chronology of events, essentially as I have summarised them in [161] above.[110]
175 Nothing in Duro's application was factually inconsistent with the chronology set out in Mr Northcott's statutory declaration.
176 Duro's December 2015 progress claim, made on 31 December 2015, was annexed to Duro's application to the adjudicator.[111] As Samsung submits, nothing in the progress claim is referrable to the amounts of $32.4 million or $34.1 million claimed by Duro.
177 Samsung's December 2015 progress certificate, dated 11 January 2015, was also before the adjudicator. It comprised a sevenpage letter, with tables embedded, together with three appendices.[112]
178 The letter broke up various components of the December 2015 progress claim and identified, in respect of each component, the amount certified for payment. For example, for the first component, 'preliminary', Duro's claim is for $1.162 million, in respect of which an amount of $76,208 is certified.
179 The letter stated that Samsung had certified an amount of $1,472,415.02 against directed variations.
180 The letter also responded to 14 claims by Duro, set out on the third and fourth pages of the letter. The six additional claims made by Duro in the adjudication application comprised some of these.
181 The letter stated that Duro's claim for DHHI commissioning works was rejected. Part of that claim was also an element of Duro's adjudication application.
182 In relation to liquidated damages, the letter stated that:
(1) Samsung had notified Duro of Duro's liability for liquidated damages which, to date, were $73,389,414;
(2) in accordance with the Interim Subcontract, the liquidated damages were capped at 10% of the contract sum, being a total of $64,213,886;
(3) the liquidated damages assessed to date were in excess of the cap and Samsung had applied the damages up to the capped amount; and
(4) in the October progress certificate Samsung had certified $51,042,537.40 for payment by Duro, and this amount remained unpaid. Samsung reserved its rights in that regard.
183 Under the heading 'defective works', Samsung referred to an earlier letter setting out the identified and allocated actual costs for defective works of $32,428,183. Samsung also referred to a letter in which it had agreed to remove the amount setoff pending the process described in that letter. Samsung stated that it undertook those actions without prejudice to its rights under the Interim Subcontract and reserved its right to setoff the amount in future progress certificates.
185 The progress certificate itself was embedded on page 6 of the letter. It dealt with three broad subjects: 'progress payment', 'advance payment', and 'adjustment'. Under 'progress payment', the certificate set out seven subcategories. For each subcategory, it stated the certified total amount up to November 2015, and the amount certified for December 2015. The four amounts said to be certified for December reflected amounts referred to in earlier parts of the letter, including the amount of $1,472,415 in respect of directed variations. The subtotal for progress payments was an amount of $1,757,931.38.
186 There were no certifications for December under 'advance payment'.
187 In the category of 'adjustment', the subcategory of 'defective works' had an amount certified up to November of -$32,428,183. In other words, that was an amount said to be payable by Duro to Samsung in respect of defective works. For December, an amount of $32,428,183 was certified, bringing the total for defective works to $0. The subtotal for the category of 'adjustment' for December was the amount of $32,428,183.
188 The total column for December, reflecting the sum of the three subtotals, was the figure of $34,186,114.38.
189 The next three paragraphs of the letter read as follows:
[Samsung] has assessed [Duro's] monthly progress and certified the progress at $34,186,114.38.
[Samsung] refers to the October and November Payment Certificates and notes that the money owing from [Duro] to [Samsung] has not been paid. [Samsung] further notes that to date [Samsung] has paid [Duro] approximately $592,000,000. [Samsung] has certified the works complete to date as $530,434,334.59. [Samsung] has made significant overpayments and this money has not been repaid.
[Samsung] therefore certifies the December Payment Certificate as $0.
190 In considering the adjudicator's reasons it must be borne in mind that adjudicators are not necessarily legally qualified, act informally and must give their determinations and reasons within 14 days. The reasons are not to be scrutinised with an eye keenly attuned to the perception of error (see [114] above).
192 I do not accept that Samsung's submissions to the adjudicator squarely denied that Samsung had certified the amount of $34.1 million as payable to Duro. Duro's submissions to the adjudicator repeatedly asserted that this had occurred. That was not directly challenged in Samsung's submissions. Rather, Samsung's submissions to the adjudicator focused on whether there was a payment claim in relation to the $32.4 million.
193 In my view, Samsung's primary submission to the adjudicator about the $32.4 million was that the reversal in the December 2015 progress certificate did not give rise to a payment claim on the part of Duro, so that there was no payment claim in respect of that sum, with the result that the adjudicator had no jurisdiction in relation to that part of Duro's claim.[115] In support of that contention Samsung's submissions explained the history of the setoff regarding the defective works, and the reversal of that setoff. The contention was clearly put, highlighted, and repeated. It related to a very substantial component - more than $32 million and about two thirds - of the amount claimed by Duro in the adjudication application.
194 Before me, Duro submits that although Samsung submitted to the adjudicator that there was no payment claim in relation to the $32.4 million, ground (e) (and, perhaps, ground (f)) is restricted to a complaint about the adjudicator's finding that Samsung had certified the $32.4 million as due for payment, and does not encompass a complaint about whether and how the adjudicator dealt with Samsung's contention that there was no payment claim in relation to the $32.4 million.[116] I do not accept that submission.
195 In my view, the two complaints are not distinct; they are closely wrapped up with each other, and that is how Samsung's case before me was presented in written and oral submissions. A central element of Samsung's complaint on these grounds is the question of whether, and, if so, how, the adjudicator dealt with Samsung's primary submission to the adjudicator that there was no payment claim for the $32.4 million, with the result that the adjudicator had no jurisdiction in relation to that part of Duro's claim.[117] Moreover, Duro's written and oral submissions before me addressed the question of whether and in what manner the adjudicator dealt with Samsung's primary submission about the $32.4 million.[118]
196 The adjudicator did not say in his reasons that, notwithstanding Samsung's submissions, there was a payment claim in respect of the $32.4 million. Nor did he say that, regardless of whether there was a payment claim for the $32.4 million, he had jurisdiction in respect of the whole of Duro's application. The adjudicator's reasons did not say anything at all about the $32.4 million, as opposed to the $34.1 million as a whole. Nor did they specifically refer to Samsung's primary submission about the $32.4 million.
197 In essence, Samsung's primary submission involved two propositions:
(1) There was no payment claim by Duro for the $32.4 million.
(2) Consequently, the adjudicator had no jurisdiction to determine that this sum was payable by Samsung to Duro.
198 In making the determination that he made, the adjudicator acted inconsistently with Samsung's primary submission. Logically, there are four potential inferences available as to the basis on which he did so. One is that the adjudicator rejected Samsung's first proposition and found that Duro had made a payment claim for the $32.4 million. Another is that he rejected Samsung's second proposition and found that, although there was no payment claim for that amount, this did not limit his powers; it was enough that there was a payment claim before him. Thirdly, the adjudicator may have misunderstood Samsung's submission as an attack on whether he had jurisdiction to hear Duro's application at all, and believed that he had answered it in [21] [23] of his reasons. Fourthly, the adjudicator may have overlooked Samsung's primary submission.
199 The adjudicator found that there was a payment claim constituted by Duro's December 2015 progress claim.[119] Duro submits that, in so finding, the adjudicator dealt specifically with the jurisdictional issues raised by Samsung, including its primary submission about the $32.4 million.[120] There are difficulties in accepting this submission. The finding that Duro's December 2015 progress claim was 'a payment claim' is generic in nature. Samsung's submissions to the adjudicator did not deny that a payment claim existed at all, or that the December 2015 progress claim was a 'payment claim' for the purposes of the Act. Samsung's primary submission about the $32.4 million was more confined. It was directed to a specific, albeit very large, element of what was claimed by Duro in the adjudication, namely the amount of $32.4 million. It was only that 'to the extent that the [adjudication application] contains a claim for $32,428,183 ... it should be summarily dismissed'.[121] The adjudicator's finding that the December 2015 progress claim was a payment claim does not speak to whether the adjudicator accepted or rejected Samsung's submission that there was no payment claim for $32.4 million of the amount claimed by Duro.
200 I think an inference that the adjudicator found that Duro had made a payment claim for the $32.4 million can be confidently excluded given that, as I explain below in resolving ground (f), there was no submission or evidence before the adjudicator that suggested, much less was capable of establishing, that Duro had made a payment claim for that amount.
201 The choice is between the remaining three inferences I have identified.
202 Duro points out,[122] correctly, that the adjudicator referred to Samsung's submission that he was obliged to dismiss the application without making a determination of its merits.[123] In that passage of his reasons, the adjudicator referred to Samsung's submission by reference to s 31(2)(a)(ii) of the Act. The reference to subpar (ii) - that the application was not prepared and served in accordance with s 26 - is curious, given that Samsung's submissions had invoked s 31(2)(a)(i) - that the contract concerned was not a construction contract - and s 31(2)(a)(iv) - that it was not possible to fairly make a determination in the prescribed time given the complexity of the application.
203 Samsung's submissions to the adjudicator grouped its contentions about the $32.4 million with its contentions that Duro's application should be wholly dismissed under s 31(2)(a).[124] When the adjudicator's reasons are read in light of that, it may be open to infer that he proceeded on the basis that, once he had found that there was a payment claim, Samsung's primary submission about the $32.4 million fell away. In other words, the third of the inferences I have identified may be drawn.
204 A court will be slow to infer that a decisionmaker has overlooked or failed to grasp a significant argument if other inferences are available. While the matter is by no means free of doubt, on balance I would infer that the adjudicator proceeded on the basis that, one way or the other, his finding that there was a payment claim addressed Samsung's primary submission in relation to the $32.4 million. In other words, I would draw the second or third inference I have identified, in preference to the fourth.
205 In my opinion, whichever of these possible inferences is drawn, the adjudicator has acted outside his jurisdiction. If the second or third is drawn, ground (f) succeeds. If the fourth is drawn, ground (e) succeeds. I proceed to explain those conclusions.
10.6 Ground (f): adjudication not the type of determination authorised by the Act?
206 To demonstrate that an adjudication is not a determination of a kind for which the Act provides is to clear a very high hurdle, as the Court of Appeal decision in Laing O'Rourke v Samsung [2016] demonstrates. Nevertheless, for the reasons that follow, I am satisfied that, insofar as the adjudicator determined that Samsung was liable to pay Duro the $32.4 million, he made a determination that was not of a kind authorised by the Act, and thereby exceeded his jurisdiction.
207 Duro's claim in the December 2015 progress claim was for an amount of about $64 million, comprising four elements outlined in Duro's submissions to the adjudicator.[125] The December 2015 progress claim was said in those submissions to comprise:
(a) claims in relation to directed variations totalling about $19.99 million;
(b) 14 additional claims totalling about $22.9 million;
(c) commissioning work performed by Paradigm totalling $3,114,885; and
(d) other amounts previously said to have been withheld by Samsung the subject of two identified letters, totalling $18,321,513.[126]
208 Thus, on the face of Duro's submissions to the adjudicator, nothing in Duro's December 2015 progress claim was referrable to the $32.4 million.
209 Samsung's December 2015 progress certificate dealt with each of those components, and allowed the following amounts respectively:
(d) $285,516.36, being the difference between $1,757,931.38 and $1,472,415.02.[130]
210 Thus, it was clear on the face of Samsung's progress certificate that of the total amount Duro claimed in the December 2015 progress claim - exceeding $64 million - Samsung accepted liability for, and certified for payment, the sum of $1,757,931.38.
211 Duro's adjudication application was founded upon, and was expressed to be founded upon, its December 2015 progress claim. That was the only payment claim that had given rise to a payment dispute within 28 days of the application.[131]
212 In my view, it is apparent that, as Samsung submitted to the adjudicator, the sum of $32.4 million, credited in reversing a setoff in an earlier progress certificate, was not referrable to, or connected to any part of, the claim for payment for work done made in Duro's December 2015 progress claim.
213 Duro contends that there is an intelligible basis for the adjudicator's finding.[132] That contention is founded on its submission that, in finding that the December 2015 progress claim was a payment claim, the adjudicator rejected Samsung's submission that he had no jurisdiction to determine Duro's claim because it was not a payment claim.[133] I have already explained why I do not accept that submission.[134] While the adjudicator found there was a payment claim, he did not address Samsung's contention that there was no payment claim in relation to the $32.4 million and that, consequently, the adjudicator had no jurisdiction in relation to that part of Duro's claim.
214 I am unable to discern any basis on which it could be said that Duro's December 2015 progress claim, the foundation of the adjudication application, contained any payment claim in respect of the $32.4 million. For the reasons I have explained, it was and is unmistakeably clear that it did not.
215 If and insofar as it might be inferred that the adjudicator found or proceeded on the basis that the absence of any payment claim by Duro for the $32.4 million did not affect his power to determine that Samsung was liable to pay that sum, for the reasons that follow, the adjudicator thereby misapprehended or disregarded the limits of his function and exceeded his jurisdiction.
216 The definition of 'payment dispute' in s 6 identifies when a payment dispute arises, and identifies the payment dispute.[135] Section 6(a) directs attention to the identification of the payment claim giving rise to a dispute.[136] There is a payment dispute under s 6(a) if and when a party to a construction contract receives a payment claim and rejects it, disputes it, or fails to pay.
217 I repeat what I said in Alliance Contracting v James:[137]
In my view, the determination by an adjudicator of whether any party to a payment dispute is liable to make a payment involves, and is limited to, determining whether the recipient of the payment claim (the non-payment or rejection of which constitutes the payment dispute) is liable to make a payment in respect of that payment claim. So, on my construction, the adjudicator's power is confined to accepting, wholly or in part, or rejecting that the recipient of that payment claim must pay that claim to the party which made the claim. The function of the adjudicator is to determine the merits of the payment claim the disputing of which constitutes the payment dispute, and to determine whether any party to that payment dispute is liable to make a payment in respect of that payment claim.
218 As a result, once it was found, as in my view was inevitable, that Duro had not made a payment claim in relation to the $32.4 million in its December 2015 progress claim, it followed that the adjudicator had no power to determine that Samsung was obliged to pay that sum to Duro. In so determining, the adjudicator exceeded his statutory authority.
219 Nothing in Duro's written submissions in response to ground (f) explained how there was any basis in the Act for the determination in relation to the $32.4 million that was consistent with the adjudicator's statutory function. That was pointed out in Samsung's oral submissions.[138] Subsequently, in Duro's oral submissions, nothing was said in this respect.
220 In its supplementary submissions[139] (which were to be directed solely to ground (i)) Duro asserted that the $34.1 million was 'part of the amount claimed in the December payment claim (which totalled more than $64 million)'. For the reasons that I have given, I do not think the material before the adjudicator or before the court provides any reasonable basis for that assertion. The fact that $34.1 million is less than $64 million is of no consequence and does not sustain Duro's assertion. The $64 million claim was comprised of other, independent claims.
221 Duro's supplementary submissions also assert that the $34.1 million 'was the value of some works performed by Duro, but for which Duro had not been paid because of Samsung's setoffs'.[140] That way of expressing the position misses or avoids the point: what works, performed when? The material before the adjudicator and the court compel the conclusion that it was not work performed in the period the subject of the December 2015 progress claim.
222 For the reasons I have given I am satisfied that, in determining that Samsung was liable to pay Duro a sum that included the $32.4 million, the adjudicator made a determination of a kind that was not authorised by the Act and thereby exceeded his jurisdiction. Thus, I would uphold ground (f).
10.7 Ground (e): breach of the requirements of procedural fairness?
223 This ground falls to be determined on the basis that I draw the fourth inference identified in [198]: that the adjudicator overlooked and failed to respond in any way to Samsung's primary submission in respect of the $32.4 million. As I have said, in Samsung's response to the adjudicator, that submission was clearly put, highlighted, and repeated. It related to a very substantial component of the amount claimed by Duro in the adjudication application.
224 It is a fundamental element of the right to procedural fairness in the setting of the Act that the respondent to an application has the opportunity to put a response to the adjudicator in accordance with s 27 of the Act. Section 32(1) provides that when making a determination, an adjudicator must, if possible, do so on the basis of the application and its attachments and, if served, the response and its attachments. Like Le Miere J,[141] I consider that this provision and the Act as a whole reveal that, in exercising their power under s 31(2)(b), an adjudicator is obliged to consider the application and the response (if any).
225 In some circumstances, to fail to respond to a substantial and clearly articulated argument put by a party is to fail to accord procedural fairness to that party.[142] In my view, in the circumstances of this case, in failing to respond to Samsung's primary submission about the $32.4 million, the adjudicator failed to accord procedural fairness to Samsung.
226 In coming to this conclusion, I do not overlook the considerable challenges faced by an adjudicator dealing with an adjudication application. An adjudicator is required to determine a dispute and give reasons within a very short time. The dispute may be substantial and complex, and the parties may rely on a large volume of material. This dispute had those features. All of those considerations require a court to take care to ensure that it does not impose expectations or obligations upon an adjudicator that are too demanding. Nonetheless, in the circumstances of this case, I think that, in failing to respond at all to Samsung's primary submission about the $32.4 million, the adjudicator breached the requirements of procedural fairness.
227 For these reasons, if the fourth inference I have identified is drawn, I find that the adjudicator failed to afford procedural fairness to Samsung. That amounts to a jurisdictional error.[143]
228 That conclusion is sufficient to dispose of ground (e). Samsung also put ground (e) on the further footing that, in failing to give reasons in relation to this substantial element of Samsung's response, the adjudicator failed to provide reasons for his determination as required by the Act, and thereby made a jurisdictional error. It is not necessary to deal with that alternative contention.
11. Ground (g): did the first adjudicator fail to consider Samsung's setoff for its payment on account? 11.1 Introduction
229 Ground (g) relates to Mr Loots' treatment of one aspect of Samsung's response in the First Determination; namely, that it was entitled to a setoff of just over $6.66 million for a payment on account it had made. Samsung claims that the adjudicator failed to consider that claim or provide reasons in relation to it.
230 In section 13 of its submissions to the adjudicator, Samsung submitted that a payment it had made to Duro on account should be setoff against any amount otherwise found to be due in favour of Duro.[144] Samsung said that in May or June 2015, after it became aware that Duro was suffering cash flow issues, Samsung paid Duro a total of $7,000,000 on account for variation work completed but not yet claimed or still under assessment. Samsung submitted that some of that money had subsequently been allocated, leaving a balance of over $6,660,177.31 that had been paid on account and, despite request, had not been repaid.
231 Samsung also made other claims to setoffs, based upon rights it asserted to liquidated damages and modularisation costs, in amounts, respectively, of $64,213,886.40 and $3,914,083.[145]
232 Duro's adjudication application and submissions (filed before Samsung's response) dealt at length with Samsung's claims for setoffs for liquidated damages, defects and modularisation costs. Duro's submissions did not deal with the payment on account. The adjudicator did not request any further submissions from Duro in relation to that payment.[146]
233 In his reasons for the First Determination, Mr Loots dealt first with his jurisdiction.[147] He then made findings as to the merits of the various components of Duro's application.[148] The next part of his reasons was headed 'Set Off for Liquidated Damages', referring to an amount of $73,389,414.
234 In this part, the adjudicator set out cl 37 of the General Conditions, stating that he accepted that Samsung had an express contractual right of setoff under that clause.[149] The adjudicator then outlined setoffs made by Samsung in the April 2015 progress certificate, and in the October 2015 progress certificate.[150] He referred to the fact that, in the October 2015 progress certificate, Samsung setoff three amounts, the first of which was $6,660,177.31 in respect of a payment on account. There was also an amount of almost $24,000,000 in respect of defective works and an amount of just over $51,000,000 for liquidated damages. He recorded that, in the November 2015 progress certificate responding to the payment claim the subject of his determination, Samsung certified that Duro owed it $6,475,886.[151] The adjudicator outlined some of Samsung's submissions, concluding that Samsung submitted that:
(a) [the] evidence establishes that [it] appropriately set off its claims against [Duro] against amounts claimed by [Duro] in the Progress Claim and previous progress certificates issued by [Samsung]; and
(b) that [the adjudicator] should reduce any amounts [he found] otherwise payable to [Duro] by the amount of [Samsung's] set off claims - totalling $6,660,177.31 in respect of the payment on account and various other set offs described in sections 14 to 16 of the Response (liquidated damages and Modularisation).[152] (original emphasis).
235 The adjudicator referred to letters from Samsung of 10 November 2015 notifying Duro of liquidated damages totalling $73,389,414, and recorded that in the October 2015 progress certificate Samsung setoff the liquidated damages it claimed were due to it.[153]
236 The adjudicator stated that because of his 'findings below' it was not necessary for him to deal with Duro's submissions and Samsung's response on issues other than whether the Interim Subcontract contained an enforceable delivery date for the relevant package, and, if it did not, whether there was any valid mechanism by which that date might be extended.[154]
237 The adjudicator found that there were no fixed dates in the Interim Subcontract for delivery of any aspect of the Duro Works.[155] He also found that Samsung did not have any rights to insist on particular dates for completion under cl 34 of the General Conditions.[156] Further, the adjudicator found that, even if there had been procurement milestones under the Interim Subcontract, there was no mechanism for extending them and Samsung's various acts of prevention caused delays to the Duro Works that set time at large.[157] The adjudicator found that Samsung had failed to show that Duro had not completed the relevant work within a reasonable time.[158]
238 The adjudicator then concluded in the following terms:
240 Next, the adjudicator considered Samsung's claim to a setoff for modularisation costs in an amount just over $3.9 million.[161] He concluded that Samsung had no basis for that setoff, and that he should not have regard to it.
241 Finally, the adjudicator set out a table summarising his determination and dealt with costs, time for payment and interest.[162]
(1) although the adjudicator dealt with its claims for setoffs for liquidated damages, defects and modularisation costs, he did not deal at all with its claim for a setoff based on the payment on account;
(2) although Samsung's submission about the payment on account was recorded by the adjudicator (at [207]), it was never dealt with;
(3) all of the reasons given by the adjudicator from [191] [249] related to liquidated damages, and did not logically bear on whether the payment on account should be setoff;
(4) it must be concluded that the adjudicator failed to deal with, and failed to give any reasons in relation to, Samsung's submission that it was entitled to setoff the $6.66 million;
(5) the adjudicator's failure to consider this significant part of Samsung's submissions, accounting for most of the claim allowed by him, and to provide any reasons in relation to it, amounted to jurisdictional error.[163]
243 Section 36 of the Act provides that an adjudicator's decision made under s 31(2)(b) must:
(a) be in writing; and
(b) be prepared in accordance with, and contain the information prescribed by, the regulations; and
(c) state -
(i) the amount to be paid and the date on or before which it is to be paid; or
(ii) the security to be returned and the date on or before which it is to be returned,
(d) give reasons for the determination; and
(e) identify any information in it that, because of its confidential nature, is not suitable for publication by the Building Commissioner under section 50; and
(f) be given to the parties to the adjudication; and
(g) be given to the Building Commissioner.
244 The Act does not expressly deal with the content of the reasons required by s 36(d). Assessment of the required content or standard of reasons is an exercise in statutory construction.[164]
245 Accordingly, in identifying what constitutes adequate reasons on the part of an adjudicator, it is important to take into account the statutory context. The Act contemplates that the process of adjudication will produce decisions that, to a degree, sacrifice legal and contractual precision for expedition. Adjudicators need not be legally qualified. Their decisions are interim in character and must be handed down within 14 days.
246 Section 32(1) provides that for the purpose of making a determination an adjudicator must act informally and, if possible, make their determination on the basis of the application and its attachments and, if served, the response and its attachments. As I have said in [224], I consider that this provision and the Act as a whole reveal a legislative intention to oblige an adjudicator to consider the application and any response.
247 An adjudicator must dismiss an application without determining its merits if satisfied that it is not possible to fairly make a determination for reasons including its complexity and the prescribed time frame.[165]
248 The reasons of an adjudicator need not be lengthy or detailed. However, they must show that the adjudicator has engaged actively with the dispute entrusted to their determination, and has addressed the issues raised by the parties in support of, or opposition to, the application.[166]
249 In assessing the adequacy of the reasons for decision of a judge, the reasons must be read as a whole and, if necessary, considered in the context of the evidence and, I would add, the submissions made.[167] Account may be taken of what can be legitimately inferred from the reasons.[168] The same is true when a court is reviewing the reasons of an adjudicator. The matters I have referred to in [245] above mean that greater latitude is to be afforded to an adjudicator than to the court when the adequacy of their reasons is assessed.
250 Samsung's submissions are not without some force. The adjudicator's reasoning in relation to Samsung's claim for a setoff for the payment on account is, with respect, by no means easy to follow. There is room for wondering whether he confused that claim with Samsung's claim for a setoff for liquidated damages, or overlooked it. The second inference, but not the first, is the subject of ground (g). This ground alleges a failure to consider and to provide reasons; it does not allege that jurisdictional error is revealed by the adjudicator's reasoning.
251 The heading to the section of the adjudicator's reasons encompassing [191] [251] is 'Set Off for Liquidated Damages', and the stated amount of $73,389,414 is solely referable to liquidated damages.[169] That is the amount which Duro submitted to the adjudicator had been claimed by Samsung for liquidated damages, before Samsung applied the contractual cap on damages under the Interim Subcontract.[170] Thus, the heading provides some support for Samsung's contention that in this part of his reasons the adjudicator dealt only with Samsung's claimed setoff for liquidated damages, and did not deal, at all, with Samsung's claim to setoff the $6.66 million payment on account.
252 Further, the adjudicator's reasoning in [213] [249] is directed to explaining why Samsung was not entitled to liquidated damages, so that it could not claim a setoff for them. It is by no means obvious how and why that conclusion would mean there was no setoff available for the payment on account.
253 However, a court should be slow to infer that a claim or significant submission was entirely overlooked by a decisionmaker if other inferences are open. In this regard, it is significant that the adjudicator twice specifically referred in his reasons to Samsung's claim to setoff the amount of $6,660,177.31 in respect of the payment on account in a manner that distinguished it from Samsung's other claimed setoffs, before concluding at [251] that a setoff in that sum should not be allowed.[171]
254 On any view of the adjudicator's reasons, there is some form of error in the reference in [251] to 'the amount of [Samsung's] setoff claims - totalling $6,660,177.31'. On Samsung's reading of the reasons, the adjudicator was not dealing with the $6,660,177.31 amount paid on account at all; he was dealing only with liquidated damages in a different and substantially greater amount. On my preferred reading and on my alternative reading, both of which I will explain immediately below, the adjudicator was intending to refer both to the $6,660,177.31 payment on account and to liquidated damages.
255 On balance, I am persuaded that the adjudicator's reasons should be read substantially in the manner invited by Duro.[172] The adjudicator referred several times to setoffs that had been asserted by Samsung in relation to progress certificates prior to the November 2015 progress certificate the subject of the dispute before him.[173] He referred to Samsung setting off over $51 million in relation to liquidated damages in October 2015.[174] He also stated that, in May 2015, Samsung purported to certify liquidated damages against Duro in the April progress certificate in the amount of $13,171,349.[175] The adjudicator recorded Samsung's submission that it had appropriately setoff its claims against amounts claimed by Duro in the November progress claim and in previous progress certificates.[176] He found that Samsung had not appropriately setoff its claims against amounts claimed by Duro in the November progress claim and in previous progress certificates.[177]
256 In my view, these elements of the adjudicator's reasons sustain reading them as a whole in the following way. Because Samsung had inappropriately claimed setoffs for liquidated damages for an amount exceeding $13 million in the April progress certificate, and an amount exceeding $51 million in the October progress certificate, Samsung should not be entitled to setoff its payment on account of the substantially lesser amount of $6.66 million.
257 In oral submissions in reply, Samsung submitted that if that were how the reasons were to be read, Samsung 'would have another ground of review of the same character [as ground (h), relating to the Second Determination]'.[178] There was no application by Samsung to amend its grounds to add any further ground in relation to the First Determination. Samsung's submission in response to this reading of the adjudicator's reasons was that it does not reflect what the adjudicator did and said in his reasons, and the order in which he dealt with various matters. Samsung submits that the adjudicator dealt with other setoffs later in his reasons, and there is no sufficient basis to read his reasons at [251] as being in any way based upon subsequent parts of his reasons.[179] I accept that this is so. However, that does not answer the point in relation to the adjudicator's view of liquidated damages. The adjudicator reached the view that, for the reasons he gave, Samsung was not entitled to any setoffs in respect of liquidated damages. That reasoning led directly to his conclusion in [251].
258 Even if I did not favour the reading of the adjudicator's reasons that I have identified, I would not uphold ground (g). In my view, there is another reading of the reasons that is to be preferred to Samsung's reading. This alternative reading is that the adjudicator reasoned that because Samsung had no right to a setoff for liquidated damages, it followed that it also had no right to a setoff for its payment on account. That reading involves flawed logic, but ground (g) does not encompass an attack on the adjudicator's reasoning. The flawed logic inherent in this reading tends against its adoption. Nevertheless, to my mind the following features of the reasons make this reading preferable to Samsung's reading. In his reasons, the adjudicator twice specifically referred to Samsung's claim for a setoff for the payment on account.[180] In each case, he expressly identified that this claim was separate from Samsung's claims for setoffs for liquidated damages, defective works and modularisation costs. Further, the adjudicator specifically referred to the amount of $6,660,177.31 when stating his conclusion that Samsung was not entitled to a setoff. These elements of the adjudicator's reasons militate against Samsung's reading of them, and support the alternative reading I have identified.
12. Ground (h): did the second adjudicator exceed his jurisdiction in refusing to give Samsung credit for its payment on account? 12.1 Introduction
260 Ground (h) relates to the treatment by Mr Machell in the Second Determination of the payment on account of just over $6.66 million made by Samsung to Duro. By this ground, Samsung asserts that the adjudicator's reasons for refusing to credit Samsung with the payment on account reveal jurisdictional error.
261 Duro's October 2015 progress claim is not the subject of a determination impugned in the applications before me.
262 Duro made two November 2015 progress claims, one under cl 37 of the General Conditions, relating to the bulk of the subject matters of the Interim Subcontract, and the other under cl 37C of the General Conditions, relating to novated contracts. The Second Determination relates to the latter of these progress claims, which I will refer to as the November NC Progress Claim. The first November progress claim, which I will refer to as the Main November Progress Claim, was the subject of the First Determination, made by Mr Loots.
263 Duro made the November NC Progress Claim by email on 14 December 2015.[181]
264 By email on 18 December 2015, Samsung sent a letter to Duro dated 17 December 2015 that essentially rejected that claim.[182]
265 In its response to Duro's adjudication application, Samsung submitted to the adjudicator that he should reduce any amounts he found were otherwise payable to Duro by the amounts of various setoffs claimed by Samsung. One of these was for the $6.66 million payment on account.[183] Other setoffs were identified and elaborated in different sections of Samsung's submissions.
266 In his reasons for the Second Determination, the adjudicator accepted that Samsung had the right to setoff the amount of just over $6.66 million in respect of the payment on account.[184]
267 However, the adjudicator did not deduct that amount from the amount which he found was otherwise owed by Samsung to Duro. Rather, he had regard to the progress certificate dated 10 November 2015, relating to an earlier progress claim. He found that in that progress certificate, Samsung had stated that, up to that time, it had setoff liquidated damages in the amount of $13,171,349.[185] The adjudicator said that, in considering the setoff to be applied in the adjudication before him, he took into account the liquidated damages that had been, as he found, incorrectly withheld in relation to that (earlier) progress claim.[186] The adjudicator concluded that, taking into account the liquidated damages incorrectly withheld in the amount exceeding $13 million, and the fact that the available setoff for the payment on account was just over $6.6 million, no setoff amount existed in favour of Samsung.[187]
268 A question emerged during oral submissions before me as to whether the adjudicator's reference to the progress certificate dated 10 November 2015 was intended to be a reference to the progress certificate dated 10 December 2015.[188]
270 The October 2015 progress certificate was before the adjudicator, as it was an attachment to Mr Rodriguez's statutory declaration.[189] That progress certificate is denoted LET1559, and is dated 10 November 2015.[190] It is one of the progress certificates referred to in Samsung's letter of 17 December 2015.[191] The other is the Main November Progress Certificate dated 10 December 2015.
271 The sum of $13,171,349 referred to by the adjudicator would seem to derive from the contents of the 10 December 2015 progress certificate, rather than from the 10 November 2015 progress certificate (although, as an aside, the logic for the derivation of that sum is less than clear).
272 In any event, whether the reference was intended to be to 10 November 2015 or to 10 December 2015 is not important. As I will explain, what is important is that the adjudicator brought to account his view of the merits of a setoff by Samsung in relation to an earlier and separate progress claim.
12.4 The disposition of the ground: did the adjudicator exceed his statutory function?
273 What the adjudicator did, and his reasons for doing it, are not in dispute. The following summary is consistent with Duro's submissions.[192] The adjudicator found that Samsung had the right to setoff the payment on account of $6.6 million against amounts it owed to Duro under his determination.[193] However, he declined to bring that setoff to account in his determination on the ground that he found that, in an earlier progress certificate, in relation to a different progress claim, Samsung had wrongly setoff an amount of $13.1 million, which exceeded the payment on account.[194]
274 In my opinion, for the reasons that follow, in so determining, the adjudicator exceeded the limits of his statutory powers.
275 Duro submits that, in proceeding in the way I have outlined, the adjudicator was determining 'on the evidence before him, the amount of money, if any, presently payable by Duro to Samsung'.[195] Duro submits that this was a finding of fact that was within jurisdiction regardless of whether it was correct.[196]
276 I do not accept those submissions. In essence, that is because, in my opinion, they are founded on an unduly broad view of the function and powers of an adjudicator. An adjudicator's function of determining, on the evidence before them, the amount of money, if any, presently payable by one party to the other is not at large. It is confined, relevantly, by the payment claim founding the parties' payment dispute.
277 The function of an adjudicator is to determine the merits of the payment claim, the nonpayment or disputing of which constitutes the payment dispute, and to determine whether any party to that payment dispute is liable to make a payment in respect of that payment claim.[197]
278 In this case the adjudicator's function was to determine, and was limited to determining, whether Samsung was liable to make a payment to Duro in respect of the payment claim constituted by the November NC Progress Claim. The payment dispute the subject of the adjudication application was about whether, as Duro claimed, Samsung was liable to pay the sum claimed by Duro in its November NC Progress Claim, or any lesser sum. Part of Samsung's response to the adjudication application was to assert setoffs and counterclaims. In determining the payment dispute, part of the function of the adjudicator was to assess the merits or otherwise of Samsung's asserted setoffs and counterclaims.[198] The adjudicator was required to do this in order to determine whether Samsung was liable to pay any sum and, if so, what sum, in respect of Duro's November NC Progress Claim. The adjudicator found that Samsung was entitled to credit the $6.6 million it had paid on account against its liability in respect of the November NC Progress Claim.
279 The adjudicator's statutory function and powers do not direct attention to the merits of competing claims, counterclaims or setoffs made in, or in response to, earlier or separate payment claims. Rather, they require attention to the merits of the payment claim the subject of the payment dispute before the adjudicator, including the merits of any counterclaims or setoffs asserted in the response to the adjudication application.
280 In the adjudication, Samsung claimed that it was entitled to setoff an amount for liquidated damages against amounts it owed to Duro in relation to the November NC Progress Claim.[199] The adjudicator determined that Samsung was not entitled to such a setoff.[200] In so determining, the adjudicator was performing his statutory function under s 31(2)(b). What the adjudicator was not empowered to do was to apply his conclusion that Samsung was not entitled to a setoff for liquidated damages to Samsung's response to an earlier, separate payment claim, and then to credit Duro with the amount of that 'wrongful' setoff against Samsung's right to credit for its payment on account.
281 The scheme of the Act is founded on the fact that contractors under construction contracts will often make regular claims for progress payments. Generally, each progress claim will be a separate payment claim, the rejection or nonpayment of which gives rise to a separate payment dispute.[201] It is an element of the scheme of the Act that disputes in respect of each payment claim are kept separate; each dispute has its own time limit under s 26(1) and each is to be the subject of a separate adjudication, unless the parties consent under s 32(3)(b). It is not open to an adjudicator to find that the amount payable by a party in relation to the payment claim before the adjudicator is to be increased (or decreased) on the ground that the adjudicator considers that a party wrongfully denied liability (or wrongfully made a claim) in relation to an earlier, different payment claim. That is what the adjudicator did in this case.
(1) In Samsung's response to the November NC Progress Claim, Samsung said, in a number of places, that Duro was referred to the October 2015 progress certificate and the main November 2015 progress certificate, which set out moneys owed by Duro to Samsung, and stated that in accordance with cl 37.8 of the General Conditions the full amount certified in each certificate was to be setoff against the moneys owing to Samsung.[202]
(2) In the main November 2015 progress certificate, Samsung referred to liquidated damages said to be certified at $51 million for payment by Duro.[203]
(3) Thus, Samsung's response to Duro's payment claim specifically referred to the main November 2015 progress certificate and the imposition of a deduction by way of a setoff for liquidated damages. The adjudicator had to consider Samsung's response to the payment claim and the validity of that response, including the validity of the setoff, as he was obliged under the Act to examine all of the assertions giving rise to the payment dispute.[204]
283 In my view, those submissions do not sustain a conclusion that the adjudicator was acting within his jurisdiction in denying Samsung a setoff in relation to the payment on account because of what he considered to be a wrongful setoff by Samsung in relation to an earlier and separate payment claim. As I have said, an adjudicator's statutory function and powers direct attention to the merits of the payment claim the subject of the payment dispute before them, and the merits of the setoffs or counterclaims asserted in the response to the adjudication application. They do not require or involve attention to the merits of the response to the payment claim that was made by the recipient when the claim was received, except to the extent that the response to the adjudication application incorporates that earlier response by reference.
284 For the reasons I have given, the adjudicator's statutory function under s 31(2)(b) did not empower him to bring to account an amount in favour of one party on the ground that the other party had wrongfully claimed a setoff in its response to an earlier and separate payment claim.
13. Ground (i): no payment claim because claim for payment not confined to construction work 13.1 Samsung's submissions
286 Samsung's oral submissions in support of ground (i) may be summarised as follows:
(1) In order for an adjudicator's power under s 31(2)(b) to arise, there must be a payment dispute.
(2) On an application for judicial review of an adjudicator's determination, the existence of a payment dispute is a matter to be determined objectively by the court as a narrow jurisdictional fact.[205]
(3) These first two propositions are established or supported by the decisions of the Court of Appeal in Laing O'Rourke v Samsung [2016] and of Mitchell J in Laing O'Rourke v Samsung [2015].
(4) (a) The definition of 'payment dispute' in s 6 of the Act encompasses three categories of disputes, being those set out in paragraphs (a), (b) and (c) of the definition. The first of those categories, under paragraph (a), relates to payment claims, but not the other two.[206] Under paragraph (a), a payment dispute arises if, by the time when the amount claimed in a payment claim is due to be paid under the contract, that amount has not been paid in full, or the claim has been rejected or wholly or partly disputed.
(b) Where, as here, a payment dispute is founded on a payment claim that has not been paid, or has been rejected or disputed, the scope of the payment dispute is limited by the scope of the payment claim.[207] If there is no payment claim, then there is no payment dispute within the meaning of par (a).
(5) The definition of 'payment claim' in s 3 of the Act directs attention to the 'obligations' of the contractor under a construction contract.[208] 'Payment claim' is defined to mean a claim made under a construction contract:
(a) by the contractor to the principal for payment of an amount in relation to the performance by the contractor of its obligations under the contract; or
(b) by the principal to the contractor for payment of an amount in relation to the performance or nonperformance by the contractor of its obligations under the contract (emphasis added).
'Obligations' is defined in s 3 to mean: 'in relation to a contractor, those of the obligations described in the definition of "construction contract" that the contractor has under the construction contract'. That meaning of 'obligations' is to be given to that word in the definition of 'payment claim'. When that is done, it is only a claim for payment of an amount in relation to the performance of obligations within paragraphs (a) to (d) of the definition of 'construction contract' in s 3 that gives rise to a payment claim.[209]
The definition of 'construction contract' in s 3 is as follows:
construction contract means a contract or other agreement, whether in writing or not, under which a person (the contractor) has one or more of these obligations -
(a) to carry out construction work;
(b) to supply to the site where construction work is being carried out any goods that are related to construction work by virtue of section 5(1);
(c) to provide, on or off the site where construction work is being carried out, professional services that are related to the construction work by virtue of section 5(2);
(d) to provide, on the site where construction work is being carried out, onsite services that are related to the construction work by virtue of section 5(3)(b).
I will refer to obligations within paragraphs (a) (d) of the definition of 'construction contract' as Construction Work or Related Obligations.
(6) A payment claim must be confined to a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations.[210] A claim that is not so confined is not a payment claim. For that reason, an adjudicator has no power or jurisdiction to determine a dispute in relation to a claim which included a claim for payment in relation to work that was not Construction Work or Related Obligations.[211]
(7) As an element of the court's objective determination of whether there was a payment dispute before the adjudicator, whether the claim the subject of the dispute was confined to a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations is to be determined objectively by the court as a narrow jurisdictional fact.[212]
(8) On an objective determination, there was work that was excluded under s 4(3) of the Act, and that therefore was not Construction Work or Related Obligations, within the claims for payment the subject of each of the first, second, third and fifth determinations.[213] Thus, each of these claims was not confined to a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations and so they were not payment claims. Consequently, the adjudicators had no jurisdiction in relation to these determinations.
287 The first seven of these propositions involve questions of law relating to the proper construction of the Act. The eighth involves matters of fact and evidence.
13.2 Jurisdictional facts and s 31(2)(a) of the Act
288 A 'jurisdictional fact' is a fact or matter the existence of which is a condition of the existence of a statutory power.[214] In other words, it is a criterion the satisfaction of which enlivens the exercise of a statutory power, so that if the criterion is not satisfied a decision will have been made without statutory authority. A 'jurisdictional fact' need not be a single fact. It may be a 'complex of elements'[215]
289 Sometimes, the matter upon which the existence of a power is conditioned is an objective fact. Sometimes it is a satisfaction or other state of mind on the part of the decisionmaker in relation to a stipulated fact or circumstance. In some cases, the first of these is referred to as a jurisdictional fact in the narrow sense, and the second as a jurisdictional fact in the broad sense. Some of the cases are discussed by Murphy JA in Perrinepod.[216]
290 Whether a statutory power is conditioned upon the existence of any fact or matter, and if so, whether it is conditioned upon the actual existence of the fact or matter, or a state of satisfaction on the part of the decisionmaker in relation to it, is a question of statutory construction.[217]
291 In this court, a number of single judge decisions have held, or assumed in the absence of contrary argument, that in proceedings for judicial review of an adjudication determination, the question is not whether the criteria in s 31(2)(a) were actually met. Rather, the court's focus should be on the conclusion drawn by the adjudicator in that regard and the process by which they came to that conclusion.[218] In other words, in these decisions the criteria in s 31(2)(a) were treated as broad jurisdictional facts.
292 More recently, a different approach to what is or may be a related question has been taken by some first instance judges. In Delmere Holdings Pty Ltd v Green,[219] Kenneth Martin J held that the existence of a payment claim and a payment dispute arising under a construction contract are narrow jurisdictional facts. In Laing O'Rourke v Samsung [2015],[220] Mitchell J held that the actual existence of a payment dispute and a payment claim arising under a construction contract, not merely an adjudicator's reasonable satisfaction as to their existence, are conditions of the valid exercise of the power conferred by s 31(2)(b).
293 There was an appeal against the decision of Mitchell J. The starting point of Samsung's submissions on ground (i) was its contention that, in that appeal, Laing O'Rourke v Samsung [2016], both Martin CJ and McLure P held that the existence of a payment dispute is a narrow jurisdictional fact upon which an adjudicator's power to make a determination under s 31(2)(b) depends.[221] I will say more about the decision on appeal in the next section of these reasons.
294 Samsung's submissions did not identify whether it contended that the adjudicators were obliged to dismiss Duro's adjudication applications under s 31(2)(a), or whether it contended that the obligation arose in the exercise of power under s 31(2)(b). Samsung submitted that the obligation may have arisen under subsection (2)(a) or subsection (2)(b), or both.[222] It did not develop any submissions as to how s 31(2)(a) requires an adjudicator to dismiss an adjudication application if there is no payment claim. Nor did it make any submissions as to the proper construction of s 31(2)(a)(ii).
295 In my opinion, on a proper construction of the Act, a finding by an adjudicator that there was no payment dispute because there was no payment claim would not engage the adjudicator's power under s 31(2)(a)(ii), or any other subparagraph of s 31(2)(a). My reasons for that opinion are as follows.
296 Section 31(2)(a)(ii) provides that an adjudicator must dismiss an application without making a determination of its merits if 'the application has not been prepared and served in accordance with s 26'. Section 26(1) requires a party making an adjudication application to do certain things within 28 days after a payment dispute arises. It provides that, within that time, the party must:
(a) prepare a written application for adjudication;
(c) serve it on any appointed adjudicator or prescribed appointor; and
(d) provide any deposit or security for the costs of the adjudication required by the adjudicator or prescribed appointor.
297 Section 26(2) sets out requirements for the preparation and content of the application.
298 The language of s 31(2)(a)(ii) - not 'prepared and served in accordance with s 26' - reflects the language of s 26(1)(a), (b) and (c), but not (d). It also reflects the language of s 26(2). In my view, in order for an application to be 'prepared and served in accordance with s 26' within the meaning of s 31(2)(a)(ii), the following requirements must be met:
(1) There must be prepared a written application that meets the requirements of s 26(2).[223]
(2) The application must be served in accordance with s 26(1)(b) and (c).
(3) Both of these things must be done in the time prescribed by s 26.
299 In my view, a reading of s 31(2)(a)(ii) that includes the third requirement is supported by the fact that the temporal requirement in s 26 links to the temporal element of the definition of 'payment dispute'. Further, as a matter of ordinary language, if the preparation and serving of an application does not meet the temporal requirement in s 26 then it cannot be said that the application has been prepared and served in accordance with that section.
300 In Laing O'Rourke v Samsung [2016],[224] McLure P said that s 31(2)(a)(ii) does not extend to whether a payment dispute has arisen and, if so, when. In Delmere Holdings v Green,[225] Kenneth Martin J appeared to accept a submission that s 31(2)(a) is engaged by a finding that there is no payment claim and no payment dispute.[226] In Re AnsteeBrook; Ex parte Karara Mining Ltd [No 2],[227] Le Miere J said that s 31(2)(a)(ii) encompasses compliance with the temporal requirement of s 26. Pritchard J recently proceeded on that basis in M&W Singapore Pte Ltd v AnsteeBrook.[228]
301 In my respectful opinion, for the reasons I have given, s 31(2)(a)(ii) does direct attention to the temporal element of s 26. In any event, a contrary view would not make any difference to my disposition of ground (i).
302 To the extent that s 31(2)(a)(ii) directs attention to the temporal element of s 26, it is necessary for an adjudicator to determine when the payment dispute arose. That in turn involves identifying the payment dispute and, where the payment dispute is founded on an unpaid, disputed or rejected payment claim, it involves identifying that payment claim.
303 However, on my construction of s 31, an adjudicator who found that there was no payment claim and consequently no payment dispute would not, on that account, conclude that the application 'was not prepared and served in accordance with s 26' within the meaning of s 31(2)(a)(ii). Rather, the consequences of such a finding would fall to be considered in the exercise by the adjudicator of their power under s 31(2)(b). I think that the language of s 31(2)(a)(ii) is directed to the requirements as to time, service, form and content in s 26, and does not naturally encompass the questions, of a fundamentally different character, of whether there is a payment dispute or payment claim at all. That reading of s 31 is consistent with Murphy JA's observation in Perrinepod[229] that the criteria in s 31(2)(a)(ii) should generally be amenable to determination by fairly routine enquiry (although sometimes 'hard cases' may arise involving determinations of fact and law). I think it is also supported by the decision of the Court of Appeal in Laing O'Rourke v Samsung [2016].
304 In that case, Martin CJ (Newnes JA agreeing) and McLure P held that an adjudicator's power to determine a payment dispute under s 31(2)(b) depends upon the existence of a payment dispute within the meaning of the Act.[230] Neither of their Honours relied on s 31(2)(a) in reaching that conclusion. Martin CJ pointed to the language of s 31(2)(b),[231] and McLure P to the requirement under s 25, for the making of an application, that 'a payment disputes arises under a construction contract'.[232]
(1) Section 31(2)(a) is linked to an obligation imposed by s 37 to provide reasons and a right of review in s 46. These sections provide safeguards where an adjudication application is dismissed under s 31(2)(a).[233]
(2) Perrinepod establishes that s 31(2) creates two alternative powers, so that if the power to dismiss under s 31(2)(a) is not exercised, the power to determine under s 31(2)(b) arises and is to be exercised.[234]
(3) Section 31 should be construed so that s 31(2)(a) is treated as an exhaustive code of jurisdictional facts for the exercise of power under s 31(2)(b).[235]
306 For the reasons in [304] I do not think the third contention is consistent with the decision of the Court of Appeal in Laing O'Rourke v Samsung [2016].
307 In that case, McLure P specifically addressed the question of whether the existence of a payment dispute was a jurisdictional fact in the broad or narrow sense. Her Honour said that, prima facie, it was a jurisdictional fact in the narrow sense.[236] Martin CJ did not expressly refer to that question. Before me, Samsung submitted that Martin CJ's reference to the 'existence' of a payment dispute, which followed detailed reference to the reasons of Mitchell J below, should be taken as an adoption of Mitchell J's decision that jurisdiction depends upon the actual existence of a payment dispute.[237]
308 Earlier in his reasons,[238] Martin CJ specifically referred to Mitchell J's decision that jurisdiction depended upon the actual existence of a payment dispute. His Honour said that this decision had not been the subject of argument, and that in determining the first issue in the appeal he would simply assume its correctness. In those circumstances, it is not clear to me that the later passage in Martin CJ's reasons should be read in the manner invited by Samsung. In any event, I do not consider it is necessary to determine that question. As I will explain, ground (i) can be determined on the basis of assumptions, favourable to Samsung, that:
(1) the actual existence of a payment dispute is an essential condition of the existence of the power under s 31(2)(b); and
(2) if the payment dispute is founded on a payment claim, the actual existence of a payment claim is also an essential condition of the existence of that power.
309 In essence, this is because there is a vital element of Samsung's contentions in support of ground (i) which I do not accept. That element is the sixth proposition I have set out at [286].
310 Before dealing with Samsung's sixth proposition, I will explain why I accept Samsung's fourth and fifth propositions.
311 As to Samsung's fourth proposition, the definition of 'payment dispute' in s 6 identifies when a payment dispute arises, and identifies the payment dispute.[239] Section 6(a) directs attention to the identification of the payment claim that gave rise to the dispute.[240] There is a payment dispute under s 6(a) if and when a party to a construction contract receives a payment claim and rejects it, disputes it, or fails to pay.
312 In such a case, the subject of the power under s 31(2)(b) is the payment claim. An adjudicator must determine if the recipient of the payment claim is liable to make a payment of the amount the subject of that claim, or part of it, to the party that issued it.[241]
313 I refer to what I have said in [216] [217].
314 I am satisfied that the text, context and evident object of the definitions of 'obligations' and 'payment claim' in the Act support Samsung's fifth proposition that only claims for payment of an amount in relation to Construction Work or Related Obligations give rise to a payment claim, including when that term is inserted into the definition of 'payment dispute', which is itself inserted into s 25, s 26 and s 31 of the Act.
315 As Duro (has always) contended, and as, in abandoning ground (a), Samsung accepted, on a proper construction of the Act, the term 'construction contract', when inserted into the various operative provisions in which it appears, is not restricted to contracts under which the sole or primary obligations of the contractor are, in substance, Construction Work or Related Obligations. Rather, contracts imposing obligations on a contractor, some of which are of that character and some of which are not (for example, because they are excluded under s 4(3)) are within the ambit of the term 'construction contract' and so are subject to the various provisions of the Act. The application of many provisions of the Act to such contracts is delineated by reference to 'obligations', thereby excluding the application of those provisions to parts of a construction contract imposing obligations that are not Construction Work or Related Obligations. That seems to me to reflect a deliberate choice by the legislature. Division 2 of pt 2 of the Act, which implies certain provisions in a construction contract, provides examples of this exclusion mechanism. Another is provided by s 42. The contractor's selfhelp rights under that section in the event of a principal's failure to pay a determined amount are confined to suspension of performance by the contractor of its 'obligations'. I think par (a) of the definition of 'payment claim' is another example of a provision of the Act that intentionally limits its application by reference to 'obligations'.
316 Other provisions of the Act are expressed to apply to construction contracts, without any restriction to 'obligations'.
317 In this way, I accept Samsung's submission[242] that the Act reveals an intention that some of its provisions apply only to those of the contractor's obligations under a construction contract that are Construction Work or Related Obligations, and that one such provision is par (a) of the definition of 'payment claim'.
319 It is an essential element of Samsung's case on ground (i) that, in order for a claim for payment to be a 'payment claim' within s 3 of the Act, the claim must be for payment of an amount all of which is in relation to the performance by the contractor of Construction Work or Related Obligations. Samsung did not contend in support of ground (i) that the claims for payment the subject of each relevant determination contained no claim for an amount in relation to the performance of Construction Work or Related Obligations. Rather, Samsung's case is that the inclusion within a claim for payment of one or more items of excluded work means that the claim for payment is not a 'payment claim'.[243] While, at an early stage of the hearing, I formed a different impression,[244] it is not Samsung's case that each adjudicator exceeded their jurisdiction only to the extent that the claim before them included excluded work. Rather, Samsung submits that a payment claim must be confined to a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations.[245] Samsung contends that an adjudicator does not have jurisdiction to determine a claim for payment that is not confined in that way.[246] In other words, Samsung's case is that, if a claim for payment includes one or more items of excluded work, an adjudicator is obliged to dismiss the adjudication application; they cannot determine so much of the claim as is for Construction Work or Related Obligations. Consistently with that formulation, Samsung submits that its sixth proposition can be seen as requiring an adjudicator to exercise the power under s 31(2)(a) to dismiss an application.[247] A requirement to dismiss under s 31(2)(a) is inconsistent with a power to determine only as much of the claim as is for Construction Work or Related Obligations.
320 Samsung's submissions on ground (i) did not make entirely clear whether its sixth proposition directed attention to the nature and content of the claim for payment when it is made by the contractor to the principal, or to that part of the claim for payment that is claimed in the adjudication application. The reference, in the ground itself, to 'the determined items' might suggest the latter. However, the logic of the analysis informing Samsung's submissions directs attention to the claim as made by the contractor to the principal, not to the claim made by the applicant in the adjudication application. That is because, on Samsung's case, an adjudicator's jurisdiction depends upon the objective existence of a payment dispute and a payment claim. The definition of 'payment claim' directs attention to the claim made by the contractor to the principal (or vice versa). That is the claim the nonpayment, rejection or disputing of which is said to constitute a payment dispute. My reasons proceed on that basis. In any event, if Samsung's sixth proposition is intended to be directed to the claim made by the applicant in the adjudication application, I would reach the same conclusion.
321 I have accepted Samsung's fifth proposition, that it is only a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations that gives rise to a payment claim. Samsung's sixth proposition goes much further. It asserts that it is only if a claim for payment is wholly of that character that it is a 'payment claim', and that only a claim for payment that is so confined can give rise to a payment dispute and become the subject of an adjudication application.
322 For the reasons that follow, I do not accept Samsung's sixth proposition. In summary, that is because it involves a restrictive reading of the statutory language that finds no support in the text, and, bearing in mind the evident object of the Act, gives rise to consequences that are unlikely to have been intended. Two alternative constructions are available, both of which are consistent with the language of the relevant provisions and operate in a way that is distinctly more likely to have been objectively intended.
323 My preferred construction is that a claim for payment is a 'payment claim' if and to the extent that it claims an amount in relation to the performance of Construction Work or Related Obligations. An alternative construction, advanced by Duro, is that a claim for payment is a 'payment claim' if, on an overall assessment of the claim as a whole, a substantial amount of the work described in the claim is Construction Work or Related Obligations.[248]
324 Samsung's sixth proposition is about the proper construction of the definition of 'payment claim'. In considering this proposition, it must be borne in mind that statutory definitions are not to be construed in isolation; they are to be inserted into the relevant operative provision(s), and the operative provision(s) construed accordingly.[249] In this case, the definition of 'payment claim' is to be inserted into the definition of 'payment dispute' which, in turn, is to be inserted into s 25, s 26 and s 31. That is the framework in which I have considered Samsung's sixth proposition, although to avoid repetition I will not express it in that way at every stage of my analysis.
325 As I have said, a construction contract may include some Construction Work or Related Obligations and some excluded work. It follows that a claim for payment made under such a contract may include items of Construction Work or Related Obligations, as well as items of excluded work. In my view, as a matter of ordinary language, that part of a claim for payment that is within the definition in s 3 is a 'payment claim'. There does not seem to me to be anything in the language of s 3, or any relevant provision of the Act, that supports reading 'payment claim' as being restricted to a claim for payment of an amount that exclusively relates to the performance by the contractor of Construction Work or Related Obligations. Samsung's sixth proposition involves reading the definition of 'payment claim' as if it contained the word 'only' or 'solely': 'a claim by the contractor ... (solely or only) for payment of an amount in relation to the performance by the contractor of its obligations under the contract'. No such words of restriction are used in the definition. The language of s 3 is entirely consistent with reading the definition of 'payment claim' to mean that, if and to the extent that a claim for payment is a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations, it constitutes a 'payment claim'. There is no textual support for the restrictive reading of the definition of 'payment claim' for which Samsung contends.
326 As I have explained, the scheme of the Act contemplates that a construction contract may include some Construction Work or Related Obligations and some excluded work. I think the legislature can be taken to have contemplated that, not infrequently, a construction contract of this kind will provide a single mechanism for progress claims. In other words, it is not to be expected that the provisions of the construction contract would require or invite the submission of two separate progress claims, one for Construction Work or Related Obligations and one for excluded work. Any such requirement might reasonably be thought to be highly inconvenient. But on Samsung's construction, a contractor must separate claims for Construction Work or Related Obligations from claims in relation to the performance of excluded work, or else lose the benefit of the adjudication process. Moreover, on Samsung's construction, if the contractor makes an error in characterising an amount as being in relation to Construction Work or Related Obligations rather than excluded work, there is consequently no 'payment claim' and the contractor loses the right to apply for an adjudication if their claim is not paid. Both of these features of Samsung's construction seem to me to indicate that it is unworkable, and involves consequences that are highly unlikely to have been intended.
327 Samsung appears to accept that the submission of two separate progress claims is an element of its construction. It submits that, if a construction contract confers only a right to make a single progress claim in relation to all work done (whether Construction Work or Related Obligations, or excluded work), then because that is not the confined payment claim required by the Act, the Act would operate to imply the terms in sch 1 div 3.[250] I do not accept that, in those postulated circumstances, the Act would operate to imply those terms. Section 15 provides that the terms in sch 1 div 3 are implied in a construction contract if the contract 'does not have a written provision about whether or not the contractor is able to make a claim to the principal for a progress payment for the obligations the contractor has performed'. A contractual provision entitling the contractor to make a (single) claim for a progress payment for all work done under the contract, whether in the performance of 'obligations' or not, is a provision of the character stipulated in s 15. It provides that the contractor is able to make a claim to the principal for a progress payment for all of the work they have performed, including Construction Work and Related Obligations.
328 Thus, in my opinion, on Samsung's restrictive construction of 'payment claim', a contractor under a construction contract that includes both Construction Work or Related Obligations and excluded work, and that provides for a single progress claim, would or may be unable to make a claim for payment that engages the Act. A single claim would not come within Samsung's construction, but the contractor would not or may not be entitled to make two separate claims under the contract.
329 On my preferred construction, a claim for payment that comprises or includes a claim for payment of an amount in relation to the performance of Construction Work or Related Obligations is, to that extent, a 'payment claim'. That will be so regardless of the fact that the claim for payment also includes one or more items of excluded work.
330 In my view, for the reasons that follow, that construction produces results that are distinctly more likely to have been intended than those produced by Samsung's construction.
331 First, unlike Samsung's construction, my preferred construction would not require a contractor to make separate progress claims in relation to Construction Work or Related Obligations and excluded work. Rather, it would operate sensibly in the framework of a construction contract that includes both excluded work and Construction Work or Related Obligations: a contractor could make a single progress claim, and only if no element of the amount claimed in the progress claim was in relation to the performance of Construction Work or Related Obligations would there be no payment claim.
332 As I have said, the question of whether there is a payment claim and a payment dispute directs attention to the original claim for payment made by the contractor or principal. However, in the exercise of power under s 31(2)(b), the adjudicator's attention will also be directed to the claims the subject of the adjudication. The claims made in the adjudication may comprise the whole of the original claim or a subset of that claim, and the Act is to be construed in that framework.[251] In exercising their power under s 31(2)(b), the adjudicator's function is to determine whether any party is liable to make a payment in respect of the relevant payment claim. The scope of that question is framed by the claims made in the adjudication. By definition, an adjudicator cannot determine that a party is liable to make a payment of an amount that the other party did not claim in the adjudication application.
333 So, in identifying the scope of the payment claim the subject of the adjudication, the adjudicator's attention will focus on the claims made in the adjudication. If none of the claims made in the adjudication is for payment of an amount in relation to the performance of Construction Work or Related Obligations, then there is no payment claim before the adjudicator capable of sustaining a determination that a party is liable to make a payment. However, on my construction, if some of the claims made in the adjudication application are for Construction Work or Related Obligations, and some are for excluded work, then there is a payment claim before the adjudicator to the extent of the claims of the first kind. Thus, in exercising their power under s 31(2)(b), the adjudicator must identify the scope of the payment claim the subject of the application. In doing so, they will identify such of the claim made in the original claim for payment and maintained in the adjudication application as is for an amount in relation to the performance of Construction Work or Related Obligations, and exclude such of the claim for payment as is in relation to the performance of excluded work.
334 That seems to me to be an approach which is distinctly more workable, and distinctly more likely to have been intended, than the construction advanced by Samsung.
335 On my construction of the Act, a factual error in relation to a particular item of a payment claim made by an adjudicator in the course of the identification process described in [333] would not amount to a jurisdictional error invalidating their determination.
336 On my reading of the relevant determinations, each of the adjudicators acted consistently with my preferred construction. Each recognised that he had the power to make a determination in favour of Duro in respect of a claim for payment for work done by Duro only if that work was Construction Work or Related Obligations. Each adjudicator identified that insofar as Duro's claim was for work excluded under s 4(3), he did not have jurisdiction to deal with the claim.[252] Leaving aside the Third Determination, about which Samsung's complaint is of a different nature, in each case the adjudicator addressed the question of whether the items of work referred to in ground (i) were Construction Work or Related Obligations or were excluded under s 4(3) and determined that question adversely to Samsung.
337 Before me, Samsung did not submit otherwise. In fact, in its written submissions in support of ground (a), Samsung submitted (correctly, in my view) that each adjudicator found he had jurisdiction in relation to claims for construction work, but not claims for excluded work.[253] In any case, ground (i) does not complain of any error in applying my preferred construction; it is founded on Samsung's construction, reflected in its sixth proposition.
338 On Samsung's construction, it is necessary for an adjudicator to ensure that no part of the amount claimed in the original claim for payment was claimed in relation to the performance of excluded work. That does not sit easily with the fact that, under s 26 of the Act, it is not necessary for an applicant to provide a copy of the payment claim giving rise to the payment dispute to the adjudicator. Under s 26(2)(b)(ii), the adjudication application need only set out details of the payment claim. In my view, compliance with that section does not require an applicant to set out detail of every item of work in the payment claim. Thus, an adjudicator will not necessarily have sufficient information to determine whether a claim for payment contains any claim for an amount in relation to the performance of excluded work.
339 For these reasons, I prefer my construction of the definition of 'payment claim' to the construction advanced by Samsung in its sixth proposition.
340 I think that the alternative construction advanced by Duro is also preferable to Samsung's construction. It avoids reading into the definition a restriction that lacks textual support. Further, it does not have the consequence of requiring a contractor to make two separate progress claims.
341 To my mind, the choice between my preferred construction and Duro's construction is finely balanced, unlike the choice between Samsung's construction and the other two competing constructions. Of course, whichever of my construction or Duro's construction is adopted, the result is the same - Samsung's sixth proposition is rejected. Samsung's case on ground (i) does not complain that each adjudicator failed to characterise the substance of the relevant claim for payment as a whole. In other words, it does not complain of the adjudicators' failure to adopt Duro's construction.
342 My reasons for adopting my construction in preference to Duro's are as follows.
343 The result of Duro's construction is that so long as a substantial part of the work the subject of a claim for payment is Construction Work or Related Obligations, the whole of that claim is a 'payment claim', and thus capable of engaging the adjudication process. By contrast, on my construction only the part of the claim that relates to Construction Work or Related Obligations is a 'payment claim'. The definition of 'obligations' in s 3 reveals and reflects an intention to confine the application of those of the Act's provisions that operate upon a contractor's 'obligations' to Construction Work or Related Obligations. These are the obligations, set out in the definition of 'construction contract' in s 3, that give a contract its character as a construction contract. It is that character that is the foundation of the application of the Act to a contract. Thus, to my mind, confining the adjudication process to that part of a claim for payment that relates to Construction Work or Related Obligations better reflects the legislative intention revealed by the definitions of 'obligations', 'payment claim' and 'payment dispute' when they are read into s 25, s 26 and s 31 of the Act.
344 Duro's construction requires an adjudicator to make a single assessment of the overall character of a claim for payment, whereas my preferred construction requires an adjudicator to assess each item of work the subject of the claim. Given the emphasis in the Act on a speedy and informal process of adjudication, that can be seen as a factor distinctly favouring Duro's construction. However, under my preferred construction, in a case where the work under the construction contract is not or may not all be Construction Work or Related Obligations, for practical purposes an adjudicator can simply focus on the claims made in the adjudication application. They need not refer to the initial claim to assess its overall character. Focusing on the character of each item of work the subject of an application will not ordinarily be unduly burdensome since it is likely that, in the course of deciding its merits, an adjudicator will in any case give close attention to the items of work the subject of the application.
345 By contrast, in a case of that kind, Duro's construction would require the adjudicator to assess the character of the original claim as a whole. As not all of the components of the claim would necessarily be pursued in the application, and since, as I have explained, it is not necessary for a copy of the original claim to be attached to the application, that may cause practical difficulty. An assessment of the overall character of the initial claim would usually, if not always, require information as to all of the items of work the subject of the claim, which an adjudicator may not always have.
346 For the reasons I have given, I reject Samsung's sixth proposition.
347 That conclusion is fatal to ground (i). However, in case I am found to be wrong in my conclusion on the sixth proposition, I will state my views in relation to Samsung's eighth proposition.
348 What follows in section 13.4 assumes the correctness of Samsung's sixth and seventh propositions.
13.4 Were some of the Determined Items excluded work?
349 Samsung contends that each of the first, second and fifth determinations included an allowance for specific items of work (the Determined Items) which were within the mining exclusion under s 4(3)(c) and thus not Construction Work or Related Obligations.
350 Duro joined issue with Samsung on whether that was so. Both parties relied on a substantial volume of factual material to support their respective positions. However, the major difference between those positions lies in the approach to be taken to the question, rather than in differences as to factual matters.
351 Duro's submissions are put in the framework of an assertion that ground (i) can succeed only if the Determined Items are related to processing a mineral bearing substance to the degree required by what Duro calls the 'Karara test'.[254] Duro relies on the following statement by Le Miere J in Re AnsteeBrook; Ex parte Karara Mining:[255]
Whether the pipeline is part of any plant for the purposes of extracting or processing any mineral bearing substance, in this case iron ore, depends upon whether the pipeline, and the function performed by it, is so related to the extraction or processing of iron ore that it warrants being held to be plant.
352 In my view, Duro's submissions seek to transpose what was said by Le Miere J in one factual context into a very different situation. His Honour was not stating, and did not purport to state, a universal test in relation to s 4(3)(c). What his Honour said is to be understood in the context of the circumstances of the case before him. That case concerned a contract the entire subject matter of which was the construction of a water pipeline. Obviously, a water pipeline is not, by its nature, plant for the purposes of extracting or processing a mineral bearing substance. In that context, Le Miere J directed attention to whether the pipeline and its intended function were so related to the extraction or processing of iron ore that the pipeline warranted being held to be plant for the purpose of extracting or processing a mineral bearing substance. His Honour held that they were not.[256]
353 Thus, in Karara, Le Miere J's analysis was directed to the entire subject matter of the contract. The same is true of Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd,[257] in which Mitchell J applied Le Miere J's approach in determining that a contract relating to the construction of a gas pipeline was not within s 4(3)(c). By contrast, in the present case, Duro seeks to apply that approach to individual items of work, each of which is part of a package of works under the Interim Subcontract. In my view, consideration of the terms of the Interim Subcontract makes it clear that each of the Determined Items is an element of one (or more) of the packages of works comprising the subject matter of the Interim Subcontract.[258]
354 In determining whether s 4(3)(c) applies, the question is whether the relevant work is the construction of any plant for the purpose of processing iron ore. In assessing whether that is so, a particular item of work is not to be viewed in isolation from its contractual context, including whether it is an element of one or more of packages 1, 2, 3 or 4. The character and purpose of the package(s) of works as a whole may reveal the character and purpose of the component item of work in question.
355 If and to the extent that my approach reflects a different construction of s 4(3)(c) from that adopted by an adjudicator, no complaint about the construction of s 4(3)(c) adopted by an adjudicator is made in ground (i) (or in any other ground). As I have said, given the circumstances and timing of the amendment adding ground (i), that ground must be confined to the complaint articulated in Samsung's oral submissions.
356 To the extent that a specific item of work the subject of a determination involves the provision of goods, professional services or onsite services, the obligation to provide those goods or services will be a Related Obligation (in other words, within pars (b) (d) of the definition of 'construction contract') if and only if the provision of them is related to construction work under s 5 of the Act. If the provision of goods or services is related to excluded work, then the obligation to provide them will not be a Related Obligation. Thus the character of the primary work, as construction work or excluded work, will determine whether the provision of goods or services related to that work constitutes Related Obligations within pars (b) (d) of the definition of 'construction contract'. In making findings below I will express my conclusions in terms of whether work is Construction Work or Related Obligations, on the one hand, or excluded work on the other. In using the expression 'excluded work', I do not overlook that Duro's work may have included the provision of goods or professional or onsite services.
357 I turn to each of the determinations impugned by Samsung.
358 Samsung contends that four items of work for which the adjudicator determined that Duro was entitled to payment were work the subject of the mining exclusion in s 4(3)(c) and thus not Construction Work or Related Obligations.
359 First, the adjudicator allowed an amount of $2,830,101 in respect of the provision of the Data Centre.[259]
360 The Data Centre is, as Mr Perez of Duro described in his statutory declaration to the adjudicator, a facility for the remote storage and processing of data generated by the various components of the mine process plant, and is located at the site of the mine process plant.[260]
361 It is true, as Duro emphasises,[261] that no mineral processing takes place in the Data Centre and no iron ore enters it. However, in assessing whether the provision of the Data Centre is the constructing of plant for the purpose of processing iron ore, the Data Centre is not to be viewed in isolation from its contractual context. The Data Centre is one element of an integrated mine process plant. That can be seen from the contractual documents, especially pt 4 of the Scope of Work, including cl 4.2.7.[262]
362 In substance, if not entirely, the provision of the Data Centre relates to Package 1 - the Mine Process Plant Work.[263] In his affidavit of 25 August 2016, Mr Perez says that he believes that the reason that Samsung increased the size of the Package 1 Data Centre was so that it could include within it equipment for Package 2.[264] In my view, that speculative statement is inadmissible or, if admissible, entitled to little or no weight.
363 Application of s 4(3)(c) invites attention to the purpose of the plant that is being constructed. I find that the provision of the Data Centre was the constructing of plant for the purpose of processing iron ore in that the Data Centre is one of many elements of the integrated mine process plant the subject of Package 1.
365 There are 26 switchrooms to be constructed across the mine site that provide electricity and control systems to the whole mine process plant.[267]
366 In his statement in support of Duro's adjudication application, Mr Perez said:[268]
Switchrooms are modularised rooms which house switchgear for plant equipment and other things, including medium voltage switchgear, Motor Control Centres, medium and low voltage variable speed drives, distribution boards, free issued equipment provided by others and so on.
The design of the switchrooms is heavily dependent on the design of the surrounding plant. If the design of a piece of plant changes or new equipment is added, the design of the switchroom which houses the switchgear and other equipment related to that piece of plant may also change.
368 Each switchroom is installed on top of a steel support structure.[270]
369 Mr Perez's affidavit details the role of each of the 26 switchrooms at [30]. Duro submits that, while some of the switchrooms are connected to equipment which 'might be said to process iron ore', others are connected to equipment which 'plainly performs no processing function', like the Data Centre.[271] As I have said, I do not think that individual items of work are to be assessed in isolation from their contractual context. The switchrooms, including the switchroom steel structures, are an element of the integrated mine process plant the subject of Package 1.[272]
370 In my view, the switchroom steel structures are properly seen as a component of the mine process plant, and are constructed for the purpose of processing iron ore. Accordingly, I find that provision of the switchroom steel structures is excluded work and not Construction Work or Related Obligations.
371 Thirdly, the adjudicator allowed $1,145,478 for modifications to belt feeders.[273]
372 As Mr Rodriguez said in his statement to the adjudicator, and as the adjudicator found, belt feeders transport ore from bins (hoppers) to crushers.[274]
373 The supply of three belt feeders by Duro was part of the Duro Works set out in section 2 of sch 2 of the Term Sheet.[275]
374 The belt feeders are an integral part of the mine process plant. They feed the ore that is being processed from the hoppers to the tertiary crushers.[276] They are part of Package 1.
375 Duro points out, correctly, that nothing happens to the iron ore while it is being fed on the belt feeders from the hoppers to the tertiary crushers.[277] For the reasons I have already given, that in itself is not significant, because the belt feeders are not to be viewed in isolation.
376 Further, Duro submits that because the belt feeders are not physically connected to the tertiary crushers, and the two equipment packages 'can' be commissioned separately, the belt feeders are not sufficiently connected to any mineral processing.[278]
377 As I have said, I do not think that each individual component of the integrated mine process plant the subject of Package 1 should be viewed in isolation to assess the purpose of its construction under section 4(3)(c).
378 I find that the work involved in modifying the belt feeders was an element of the construction of the mine process plant, and is the constructing of plant for the purpose of processing iron ore. Thus, it is excluded work within section 4(3)(c).
379 Fourthly, the adjudicator allowed an amount of $1,364,820.56 in relation to DHHI commissioning works.[279]
380 Duro's claim in relation to DHHI commissioning works was a claim for a variation. Before the adjudicator, the primary issue in relation to that claim was whether the works were a variation, or whether they were part of the Duro Works under the Interim Subcontract.
381 Samsung requested that Duro provide services in relation to the commissioning of the control systems for DHHI machines. For example, Samsung directed Duro to mobilise to site two control engineers from Paradigm for the commissioning of a fixed stacker.[280] This fixed stacker is part of the mine process plant. It stacks unprocessed ore that has been crushed by the primary and secondary crushers onto the coarse ore stockpile.[281]
383 I am satisfied that the work involved in the commissioning of the control systems at the mine process plant is excluded work. The position seems to me to be different in relation to the commissioning of the control systems at the port. Duro's claim in relation to DHHI commissioning works included elements of both. The evidence does not identify how much of the claim related to one site or the other.
384 Given my findings in relation to the first three Determined Items in the First Determination, it is not necessary for me to decide whether the inclusion of a substantial but unidentified element of a claimed item that is excluded work in Duro's claim would (assuming this is a matter for the court to objectively determine) result in a finding that the adjudicator exceeded his jurisdiction.
385 In summary, given my findings in relation to the first three Determined Items, if, contrary to my view, a claim for payment that includes a claim for work that is, on the court's objective determination, not Construction Work or Related Obligations is therefore not a 'payment claim', then in making the First Determination the adjudicator exceeded his jurisdiction, and the determination is liable to be set aside accordingly.
386 Samsung contends that, in two respects, the amount awarded in the Second Determination included payment for works the subject of the mining exclusion.
387 First, the adjudicator allowed a claim by Duro relating to a novated contract between Duro and IMP. That claim was allowed in the amounts of €182,690.45 and AUS$333,119.[284]
388 In his statement to the adjudicator Mr Rodriguez said that, as part of the Duro Works, Duro was required to supply a mine pit laboratory and a mine process plant laboratory at the Project site. The laboratories are used for the regular sampling of ore during processing to ensure that strict quality consistency is maintained.[285]
389 There were separate contracts for IMP's delivery of these laboratories to the mine site (the IMP Mine Contract) and for its delivery of a laboratory to the port site.[286] In the Second Determination, Duro claimed payment under the IMP Mine Contract.
390 The laboratory equipment supplied under the IMP Mine Contract is part of the mine process plant; it is used to test and monitor iron ore immediately before and after processing and prior to load out by rail to the port.[287] It is used to test ore samples from the pit, and to test processed ore from the process plant.[288] The purpose of the testing is to assess the quality of the processing done, and then to make adjustments, as required, to the processing equipment for the future processing of ore.[289]
391 Again, in my view the enquiry under s 4(3)(c) as to the purpose of the laboratories must take account of the fact they are an element of an integrated mine process plant.
392 I find that the works the subject of the IMP Mine Contract are an element of the construction of the mine process plant, and fall within the mining exclusion in s 4(3)(c).
393 Part of Duro's claim for payment for the works under the IMP Mine Contract the subject of the Second Determination was its claim for retention release in the amounts of €182,109.45 and AUS$208,684.[290] The other component of the claim was for payment for installation, supervision and commissioning works.
394 Samsung submits that the reference to retention amounts in Duro's claim is a reference to amounts retained under the novated contract between Duro and IMP and subsequently claimed by Duro under the Interim Subcontract. Samsung submits, and I accept, that, to the extent there is a payment dispute under the Act about the retention amounts, it should be characterised as one founded on a payment claim under s 6(a) of the Act and not one based on the retention of money under s 6(b).[291] That is because, although the amounts were retained under the IMP Mine Contract, they were included in a claim for payment made by Duro under the Interim Subcontract.[292]
395 Secondly, the adjudicator allowed a claim by Duro in an amount of CNY11,617,671.01 for the completion of approved design work and for DHHI onsite assistance.[293] This claim arose under a novated contract between Duro and DHHI (the DHHI Contract).
396 Under the DHHI Contract, DHHI was engaged to design, manufacture and supply, and to provide vendor assistance on the installation and commissioning, start up, and performance testing of, nine machines (the DHHI Machines). The DHHI Machines comprised:
(a) a fixed stacker, a mine lump stacker, a mine fines stacker and a mine reclaimer, to be located at the site of the mine process plant for Package 1;
(b) a car dumper, a port lump stacker, a port fines stacker and a port reclaimer to be located at the port, which were part of Package 3; and
(c) a ship loader to be located at the port for Package 4.[294]
397 The fixed stacker, lump stacker, fines stacker and reclaimer located at the site of the mine process plant form part of that plant and perform the functions explained by Mr Northcott.[295] The fixed stacker stacks unprocessed ore that has been crushed by the primary and secondary crushers onto the coarse ore stockpile. The lump and fines stackers stack saleable processed ore into separate lump and fines stockpiles. The reclaimer reclaims processed ore from the fines and lump stockpiles and loads that ore onto conveyor belts for loading onto trains.
398 The Package 3 machines relate to the port landside stockpiling and screening facility. The car dumper empties the lump and fines ore from the train wagons arriving from the mine site by rotating the wagons. The unloaded lump and fines products are then conveyed to the stockyard, where they are delivered to the two stackers, or directly to the lump rescreening plant or fines surge bins for ship loading. The lump stacker and the fines stacker stack the processed ore in the port stockyard into lump stockpiles and fines stockpiles. The reclaimer reclaims the processed ore from those stockpiles. The lump ore is then conveyed to nine bins while the fines product is conveyed to the screening facility and fed to three bins.[296]
399 The ship loader located at the port transports the products that have been through the processing procedures to a ship for delivery to customers.[297]
400 The supply of the DHHI Machines for Package 3 and Package 4 was incorporated into the Original Subcontract by Variation Order 001.[298]
401 I find that the provision of the DHHI Machines, and associated works and services, for Package 1, at the site of the mine process plant, are part of the constructing of plant for the purpose of processing iron ore, and so are excluded work under s 4(3)(c). However, I am not satisfied that this is the position in relation to the DHHI Machines for Package 3 and Package 4, to be located at the port.
402 Duro's claim in relation to DHHI design and onsite assistance includes both kinds of work. The evidence does not identify how much of the claim related to machines to be supplied to, or associated works or services to be provided at, one site or the other.
403 Given my findings in relation to the allowance for the IMP claims, and given the hypothetical, contingent nature of the findings in this section, it is not necessary to decide whether inclusion of a substantial but unidentified element of excluded work in a claim for payment would result in a finding that there was no 'payment claim'.
404 In summary, if, contrary to my view, a claim for payment that includes a claim for work that is, on the court's objective determination, not Construction Work or Related Obligations is therefore not a 'payment claim', in making the Second Determination the adjudicator exceeded his jurisdiction and the determination is liable to be set aside accordingly.
405 Given that I have concluded that the adjudicator did not find that there was any payment claim in respect of the $32.4 million, and given that I have found that the Third Determination should be set aside on ground (f), or alternatively on ground (e), ground (i) does not arise for consideration in relation to the Third Determination.
406 Samsung contends that two items of work which the adjudicator allowed in favour of Duro are work the subject of the mining exclusion and thus not Construction Work or Related Obligations.
407 First, the adjudicator allowed an amount of $123,525 in respect of the supply of RTD boxes.[299]
408 RTD boxes are used in connection with resistance temperature detectors (RTDs) that are situated on the motors on equipment in the mine process plant. The Principal's Project Requirements in the Interim Subcontract stipulated various requirements in relation to the motors used on that equipment. One requirement was the use of stipulated RTDs to safeguard the motors.[300] The RTDs required converters known as RTD boxes in order to function properly.
409 Under the Scope of Work, part of the engineering, procurement construction and commissioning works for the mine process plant was, by cl 4.2.1, the inclusion of all electrical and mechanical equipment necessary to complete the processing units comprising the processing facilities.[301]
410 I find that the supply of the RTD boxes is the construction of plant for the purpose of processing iron ore at the mine process plant, or is the provision of goods related to the construction of such plant, and thus is excluded work under s 4(3)(c).
411 Secondly, the adjudicator allowed an amount of $394,325.28 in relation to the commissioning of a control system.[302] What I said in relation to the evidence about the fourth of the Determined Items in the First Determination, the DHHI commissioning works, applies equally here. Again, given my finding as to the RTD boxes, it is not necessary to deal with this item.
412 If, contrary to my view, the inclusion in a claim for payment of an amount in relation to the performance of excluded work means that the claim is not a 'payment claim', the claim the subject of the Fifth Determination was not a 'payment claim' and that determination is liable to be set aside accordingly.
413 I have concluded that there was a jurisdictional error in each of the second and third determinations. The jurisdictional error relating to the Third Determination concerned a substantial part, but not the entirety, of the adjudicated amount of $49,642,958.72, plus GST. Duro submits that, in those circumstances, the Third Determination should not be set aside in its entirety. Rather, the affected part of the determination should be severed, so that only that part is quashed, and the remainder should stand.
414 In my opinion, for the reasons that follow, once it is found that an adjudication determination is affected by jurisdictional error, it follows that the entire determination is invalid and must be quashed; there is no room for severance.
415 An adjudicator's determination under s 31(2)(b) must meet the requirements of s 36. It must be in writing and must state the amount to be paid and the date on or before which it is to be paid.[303] On a proper construction of the Act, there is only one determination made by an adjudicator under s 31(2)(b). It is this determination that is the subject of an application for judicial review, not the component claims which together make up the adjudicated amount, and not the various elements of the adjudicator's reasoning. In proceedings like these the question is whether the adjudicator's exercise of statutory power, constituted by their determination, is affected by jurisdictional error. If it is, it is, on that account, invalid, and the court should give relief to reflect that position.
416 In my view, in proceedings for judicial review of an adjudication determination, the court has no power to substitute a different adjudicated amount to reflect that part of the amount that is unaffected by jurisdictional error. To do that would be to exercise a statutory power that is given only to an adjudicator. In proceedings for judicial review, it is not the court's function, and the court has no power, to step into the shoes of the repository of the statutory power the exercise of which is the subject of judicial review. Nothing in the Act gives the court any power to make a varied or substituted determination.
417 The statement of the position that I have just made reflects views I expressed in Alliance Contracting v James.[304] It also reflects the position adopted in other States to security of payment legislation in the absence of any specific legislative provision to the contrary. In Multiplex Constructions Pty Ltd v Luikens,[305] Palmer J said as follows in relation to the New South Wales security of payment legislation:
It seems to me that because the Act requires a determination to produce only one amount for payment pursuant to a payment claim served under s 13(1), despite the fact that the payment claim might have comprised numerous claims for separate and distinct items of work, and because the Act does not provide for variation of the adjudicated amount, or the judgment debt, if the adjudicator's decision as to any component part of the adjudicated amount is shown to be liable to be set aside on judicial review, the consequence is that, subject to other discretionary considerations, the whole of the determination must be quashed if jurisdictional error infects any part of the process whereby the adjudication amount has been produced. This is, no doubt, a highly inconvenient result. However, I do not see any means of avoiding it, as the Act presently stands.
418 That passage has been cited with approval and adopted in many cases in New South Wales[306] and in Queensland.[307] Thus, in cases concerned with security of payment legislation in other States, it has been consistently held that, absent specific legislative provision to the contrary, an adjudication determination that a party is liable to pay a specified amount that is affected by jurisdictional error is void in its entirety, even if the error infected only an identifiable part of the determined amount.[308]
419 In BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd,[309] the appellant had commenced proceedings for a declaration that an adjudication decision was void as a result of two jurisdictional errors. The primary judge upheld the appellant's case in respect of only one of the errors, but in the exercise of discretion refused to make the declaration of invalidity sought by the appellant. Instead, the primary judge dismissed the application upon an undertaking by the respondent to repay to the appellant the portion of the adjudicated amount in respect of which the adjudicator had made a jurisdictional error. The Queensland Court of Appeal unanimously upheld an appeal from that decision. The court held that the appellant was entitled to a declaration of invalidity of the whole of the adjudication. Muir JA (with whom Holmes JA & Lyons J agreed) held that once a court determines that an adjudication decision is affected by jurisdictional error, that decision cannot give rise to legal consequences.[310]
420 Duro relies heavily on the decision of the Victorian Supreme Court in Gantley Pty Ltd v Phoenix International Group Pty Ltd.[311] Unlike the Act, the Victorian security of payment legislation examined in that case contains provisions which can render an adjudicator's decision partially void.[312] Section 23(2B) states that an adjudicator's determination is void to the extent that it has been made in contravention of s 23(2) or to the extent that it is based on a matter that, under s 23(2A), must not be taken into account.
421 Duro also relies on the approach which it contends has been generally taken by the Court of Appeal in this State in relation to severing parts of an administrative decision that are not affected by jurisdictional error.[313] It points to what was said by RobertsSmith J (Murray & Barker JJ agreeing) in Re Narula, Ng & Hammersley; Ex parte Atanasoski.[314] In that case, RobertsSmith J observed that where only part of a decision of an administrative tribunal is beyond power, the court may quash that part without interfering with the remainder, provided the bad can be cleanly severed from the good. His Honour also stated that on judicial review, an administrative decision should not be struck down to any greater extent than a defect has affected it.
422 These propositions must be understood in the context in which they were stated. Re Narula concerned an application for a writ of certiorari against a panel that had made a determination under the Workers Compensation and Rehabilitation Act 1981 (WA). The panel's determination had separate components, some of which related to the worker's physical disability, and others to the worker's psychiatric disability.[315] The application challenged the panel's reasoning relating to its determination that the worker did not have a physical disability. The Full Court held that the determination and reasons of the panel going to the worker's physical condition were severable from those relating to his psychiatric conditions.[316]
423 The point is that, in Re Narula, unlike in this case, the determination under review itself had separate components, some only of which were challenged on the basis of jurisdictional error. The same is true of the other decisions relied on by Duro.[317] In each of those cases the decision (as distinct from the reasons) under review had distinct components, only one or some of which were found to have involved jurisdictional error.
424 By contrast, as I have explained, in the present case there was only a single determination by each adjudicator, with the result that severance is unavailable. Since the statutory power that was exercised involved making a single order, there is no room for severance.[318]
425 Finally, Duro submits that the Act's purpose of keeping the money flowing while sidelining protracted disputes is better advanced by an approach to judicial review that is flexible and permits severance.[319] In my view, the question is not whether permitting severance would better advance the objects of the Act. Rather, it is whether, on a proper construction of the Act, taking into account its text and evident purpose and policy, the court has the power to order that only part of a determination is rendered invalid by a jurisdictional error infecting it. For the reasons I have given, I consider that the court has no such power. As Palmer J observes in the passage in Multiplex Constructions v Luikens I have set out above, there is room for the view that this is an inconvenient or less than optimal position. Nevertheless, that is the effect of the silence of the Act on this point.
426 For these reasons, I would reject Duro's submission that any parts of the adjudicators' reasoning that reveal jurisdictional error only affect the component of the adjudicated amount that is based on that reasoning. The jurisdictional error of the adjudicator in each of the second and third determinations renders both of them wholly invalid. I would quash each of them accordingly.
427 For the reasons I have given, I would dismiss Samsung's applications to set aside the first, fourth and fifth determinations, which were the subject of grounds (d), (g) and (i), all of which I have rejected.
428 That brings me to Duro's applications for leave to enforce the determinations. As I would set aside the second and third determinations, I would not grant leave to enforce those determinations.
429 The next section of these reasons concerns Duro's applications to enforce the other determinations.
15. Should leave be given to enforce the determinations? 15.1 Legal principles
A determination may, with the leave of a court of competent jurisdiction, be enforced in the same manner as a judgment or order of the court to the same effect, and if such leave is given, judgment may be entered in terms of the determination.
431 The following principles regarding an application for leave to enforce under s 43(2) are well established:
(1) The role of the court on an application for leave to enforce is not purely mechanical but requires the court to itself determine, in all the circumstances, that the relevant determination should be enforced as a judgment of the court.
(2) Section 43 confers a discretion upon the court in that regard.
(3) Given that the Act does not expressly identify the matters to which regard should be had on the question of leave, consideration must be given to the context, objects, purpose and policy of the Act. The object of the Act is to keep the money flowing in the contracting chain by enforcing timely payment and sidelining protracted or complex disputes.
(4) That object gives rise to a predisposition in favour of the grant of leave. It is for the party obliged to pay to show a reason why the determination should not be enforced.
(5) The fact that a party resisting enforcement alleges that it has other pending claims which could be setoff against the adjudicated amount will not ordinarily justify the refusal of leave.
(6) An application for leave to enforce a determination is not an occasion to challenge the correctness of the determination or, in the absence of a pending application for judicial review, its validity.
(7) There are no closed categories of circumstances that may be relevant to the question of whether leave should be granted.[320]
432 Samsung accepts that it must show a reason why each determination should not be enforced.[321]
433 In its written submissions, Samsung points to the following matters as, together, justifying the refusal of leave:
(1) Duro is a wholly owned subsidiary of Duro Felguera SA (Spain) (Duro Spain).
(2) Duro is not involved, and is not likely to be involved, in any other construction projects in Australia.
(3) Duro has not released sufficient current information to show whether it is solvent.
(4) The available financial information concerning Duro indicates that it does not have assets that it could use to repay Samsung if it distributed amounts that Samsung paid to it to Duro Spain.
(5) Duro Spain is outside the jurisdiction and, by virtue of the fact that Duro has no other projects in Australia, there is reason to believe that any funds paid to Duro will be remitted to Duro Spain.
(6) Samsung has not received confirmation as to whether Duro Spain has provided any guarantees or indemnities to cover Duro's liabilities other than the Deed of Guarantee and Indemnity between Duro Spain and Samsung dated 11 September 2013. This will be a key issue for Samsung in the event that leave to enforce is granted and there is a dispute about the application of this deed to the repayment of any amount paid to Duro pursuant to the adjudication determinations.
(7) Samsung has a significant bona fide offsetting claim in an amount that far exceeds the adjudicated amounts.[322]
434 It is convenient to outline the factual framework in which Samsung put its submissions, before turning to Samsung's oral submissions.
435 Under the Original Subcontract, Duro Spain provided a guarantee and indemnity. It did so by a Deed of Guarantee and Indemnity (the 2013 Parent Company Guarantee) dated 11 September 2013 between Duro Spain and Samsung.[323]
436 By cl 3.1(a) of the 2013 Parent Company Guarantee, Duro Spain unconditionally and irrevocably guaranteed to Samsung on demand the due and punctual performance by Duro of its obligations under the Original Subcontract. Clause 3.1(b) provided that Duro Spain separately, unconditionally and irrevocably indemnified Samsung in connection with any failure by Duro to duly and punctually perform its obligations or satisfy its liabilities under the Original Subcontract.
437 By cl 5(a)(i), the deed extended to cover the Original Subcontract 'as amended, varied or replaced, whether with or without the consent of [Duro Spain]'.
438 Item 2 of sch 1 to the Term Sheet provides that 'Duro will procure a new Deed of Guarantee and Indemnity for the Substitute Subcontract on the same terms and from the same guarantor as was provided under the Original Subcontract'.
439 Under the Original Subcontract and the Interim Subcontract, Duro was obliged to provide security for claims by Samsung, which it provided in the form of performance bonds worth about $140 million. In late 2015, Samsung called on the performance bonds in an amount of about $64 million. Proceedings brought by Duro to restrain Samsung from enforcing the bonds were unsuccessful.[324] In early 2016, Samsung made a further call on the performance bonds in an amount of approximately $67 million. Duro's application to this court for an order restraining Samsung from obtaining payment in relation to this call was also unsuccessful.[325]
440 On 18 April 2016, Samsung made a demand on Duro Spain under the 2013 Parent Company Guarantee.[326]
441 By letter of 30 June 2016,[327] Samsung's solicitors wrote to Duro's solicitors. The letter:
(1) raised concerns about Duro's solvency and its ability to repay any adjudicated amounts, referring to the following matters:
(a) the last financial report filed by Duro was for the year ended 31 December 2014, notwithstanding that the report for the following year was overdue;
(b) Duro's net assets as at 31 December 2014 were about $5.6 million. Since then Samsung had converted performance bonds provided by Duro in the amount of more than $131 million;
(c) Duro did not appear to have any real property holdings in Australia;
(d) it appeared that Duro had no other current or future Australian projects;
(2) requested that in light of those concerns Duro provide, by 5.00 pm on 1 July 2016:
(a) the most up to date version of Duro's 2015 financial statement and management accounts;
(b) any reports or updates to Duro's financial position provided to relevant financial institutions or financiers over the last six months; and
(c) confirmation as to whether Duro Spain had provided any guarantees or indemnities to cover Duro's liabilities other than the 2013 Parent Company Guarantee and, if it had, copies of those instruments.
442 The following day, Duro's solicitors responded to that letter.[328] They asserted that Samsung had no entitlement to the information requested and said that Duro rejected Samsung's assessment of its financial position and allegations as to its solvency.
443 By letter of 25 July 2016,[329] Samsung's solicitors wrote to Duro's solicitors. The letter referred to the demand of 18 April 2016 made under the 2013 Parent Company Guarantee. It requested advice, by 4.00 pm the following day, as to whether, if the court granted leave to enforce the determinations and Samsung paid Duro pursuant to its orders, Duro Spain would assure repayment of any of the adjudicated amounts subsequently determined in arbitration not to be owed by Samsung to Duro. Duro's solicitors responded by letter of 28 July 2016.[330] Relevantly, the letter stated that Duro's solicitors had been 'advised by our client that [Duro Spain] intends to meet any obligations to [Samsung] that it may have under the [Parent Company Guarantee]'.
444 Ms Strong, Duro's Legal and Commercial Manager, attached a copy of Duro's audited financial report for the financial year ended 31 December 2015 to her affidavit sworn on 28 July 2016.[331]
445 In oral submissions, Samsung put two alternative contentions:
(1) Having regard to the very large amounts involved in the determinations, and in Samsung's claims in the arbitration between the parties, and to the fact that Samsung has raised its concerns regarding the financial health of Duro and Duro Spain, and given the nature and paucity of the information that has been provided by Duro, there is no assurance as to Duro's solvency or as to the financial position of Duro Spain and the applications for leave to enforce should be stayed until the financial positions of Duro and Duro Spain are revealed before the court.[332]
(2) Alternatively, the grant of leave should be made conditional, with a condition or conditions to ensure:
(a) that there is a guarantee by Duro Spain that applies to Duro's obligations under the Interim Subcontract; and
(b) that there is no uncertainty as to whether that guarantee would encompass money that had to be repaid by Duro after having been paid by Samsung in satisfaction of the judgment after a grant of leave to enforce.[333]
Samsung did not provide the terms of the proposed condition(s) until the day after the completion of the hearing. The condition it proposes is in the following terms:
UPON [Duro] providing a deed duly executed by [Duro Spain] in favour of [Samsung] pursuant to which it acknowledges and confirms that it unconditionally and irrevocably guarantees to [Samsung] on demand the due and punctual performance by [Duro] of any obligation to repay any amounts paid pursuant to any of the determinations under the Construction Contracts Act 2004 the subject of these orders which obligation arises by reason of an arbitrator or other person or a court or other body dealing with a matter arising under the contract between [Duro] and [Samsung] recorded by an instrument between them described as a Term Sheet dated 21 February 2014, including any appeal from these proceedings, making orders for restitution of any amount or other appropriate orders as to any such determination or by reason of any order of this Court (Guaranteed Obligations) and separately unconditionally and irrevocably indemnifies [Samsung] against all demands, claims, suits, actions, damages, liabilities, losses, costs and expenses which may be brought against or suffered by [Samsung] in connection with a failure by [Duro] to duly and punctually perform the Guaranteed Obligations.
446 For the reasons that follow, I am not persuaded by either of Samsung's contentions.
448 In support of its primary contention Samsung submits[334] that:
(1) the most recent financial information provided by Duro is from 31 December 2015;
(2) that information must be viewed in light of the fact that in early 2016 Samsung drew on the performance bonds in an amount of approximately $67 million;
(3) the notes to the financial statements in Duro's 2015 annual financial report suggest that Duro has not accounted for this call on the performance bonds;
(4) given that the report shows net assets of about $4 million, and given that Duro has no other ongoing business, there is cause for concern about whether Duro would be able to repay the adjudicated amounts; and
(5) Duro Spain's consolidated balance sheet shows an excess of current assets over current liabilities of about €170 million, and net losses of about €80 million, which means that claims of the order of the adjudicated amounts or Samsung's claims in the arbitration would be significant for Duro Spain.
449 Thus, Samsung submits that, in light of the available financial information, the applications for leave to enforce should be stayed.[335] That invites the question: stayed pending what? As I understood Samsung's submission, it proposes a stay pending Duro's provision of further information about its (and possibly also Duro Spain's) financial position, or other information sufficient to resolve the question of whether Duro will be able to repay any adjudicated amounts if it is ultimately unsuccessful in the arbitration between the parties.
450 For the reasons that follow, I am not persuaded that the applications for leave to enforce should be stayed on this basis.
451 Both Samsung and Duro Spain are foreign entities. Samsung and Duro are both big companies. In their contracts they made provision for security to be provided by Duro. That security has been provided and has been substantially drawn upon by Samsung. Any concerns now arising about Duro's (or Duro Spain's) financial strength should be viewed in that framework.
452 The existence of a concern about whether the party in whose favour an adjudication was made will be in a position to repay the adjudicated amount, when and if it is subsequently found by a court or arbitrator not to be due, will not ordinarily be a sufficient ground on which to refuse leave to enforce.[336]
453 In any event, it is not incumbent on such a party to produce, upon request by the other party, management reports or reports as to its financial position provided to financiers in the preceding six months, in order to provide 'assurance' as to its financial position. There is nothing in the Act which suggests that a contractor's entitlement to receive progress payments depends upon it establishing a capacity to repay those sums if, subsequently, there is a final judgment or arbitration unfavourable to it.[337]
455 The adjudicated amounts are payable by Samsung to Duro under the Interim Subcontract. If the Interim Subcontract required Duro to procure a new deed of guarantee by Duro Spain of Duro's obligations under the Interim Subcontract, and if, despite demand, no such guarantee had been procured by Duro, there would be much to be said for a condition of enforcement that ensured due performance by Duro of its obligation to procure the further guarantee.
456 However, there is no evidence that at any time before the hearing of these applications Samsung made any demand to Duro for Duro to procure a new deed of guarantee from Duro Spain. Samsung's solicitors' letter of 30 June 2016 is not such a demand. It is a request for information as to the existence of any other guarantees by Duro Spain of Duro's liabilities, made in the context of the earlier expression of Samsung's concerns about Duro's financial health. In its context, the request was reasonably to be understood as directed to ascertaining whether Duro Spain had guaranteed other obligations of Duro, rather than to ascertaining whether Duro Spain had executed a deed of guarantee in relation to Duro's obligations under the Interim Subcontract. In any case, it was a request for information, not a demand.
457 Samsung's written enforcement submissions in these proceedings do not clearly articulate a complaint that Duro has failed to procure Duro Spain to execute a new deed of guarantee and indemnity. Paragraph 5 of these submissions is a summary of Samsung's contentions. Paragraph 5(f) refers to the absence of confirmation by Duro to Samsung as to whether there are any guarantees by Duro Spain, apart from the 2013 Parent Company Guarantee, of Duro's obligations, in the context of the concern expressed by Mr Son[338] that there might be a dispute about whether the 2013 Parent Company Guarantee applies to repayment by Duro of amounts paid to it under the determinations upon the grant of leave to enforce. On a careful analysis that may indicate a concern that Duro Spain has not executed a guarantee of Duro's obligations under the Interim Subcontract. However, the position is less than crystal clear. Nothing else is said on this topic in Samsung's written submissions. A complaint that Duro had failed to procure Duro Spain to execute a new deed of guarantee and indemnity was clearly articulated for the first time in oral submissions at the hearing on 27 July 2016.[339]
458 Whether Duro is obliged to procure Duro Spain to execute a new deed of guarantee in respect of Duro's obligations under the Interim Subcontract is not clear beyond argument. In the Term Sheet, Duro's obligation is expressed to be to procure a new deed of guarantee and indemnity for the Substitute Subcontract, rather than for the Interim Subcontract. The immediately preceding dot point refers to security in respect of the Interim Subcontract.
459 Samsung submits that Duro's oral submissions highlighted the absence of a prior demand, but did not deny Duro's obligation to procure the execution of a further guarantee.[340] In circumstances where, as I have explained, Samsung clearly articulated a complaint about the absence of a further guarantee for the first time at the hearing of these applications, I do not think that significant weight should be given to the fact that Duro's submissions did not address the question of whether it was obliged to procure Duro Spain to execute a guarantee of Duro's obligations under the Interim Subcontract.
460 As a general proposition, I do not accept Duro's submission[341] that any questions of breach or interpretation of the Interim Subcontract should be the subject of separate proceedings, and cannot be ventilated in the context of the applications for leave to enforce the determinations. However, in the circumstances I have outlined in the preceding four paragraphs, I am not persuaded that the grant of leave to enforce should be conditioned on the execution by Duro Spain of any new deed of guarantee and indemnity.
461 Further, the condition sought by Samsung goes beyond ensuring that there is a guarantee by Duro Spain of Duro's obligations under the Interim Subcontract. It seeks to remove any uncertainty about whether Duro Spain guarantees any obligation of Duro to repay money paid by Samsung in satisfaction of this court's judgment upon the grant of leave to enforce. I am not persuaded that the grant of leave should be conditioned by Duro Spain's execution of a deed in terms of the proposed condition, specifically acknowledging and confirming a guarantee to Samsung of Duro's performance of any obligation to repay any adjudicated amounts pursuant to the orders of an arbitrator or a court, or any other person or body, including orders made in any appeal from these proceedings. The legal regime under the Act for the adjudication of payment disputes was part of the context in which the parties contracted. Both parties are large commercial entities. It was open to them to make specific provision in their contractual arrangements as to whether any required guarantee was to encompass money paid under an adjudication determination and later ordered by a court or arbitrator to be repaid. Samsung's contractual rights to any guarantee or indemnity from Duro Spain are those created by the 2013 Parent Company Guarantee and cl 2 of sch 1 to the Term Sheet. To the extent that there may be doubts about whether those rights encompass any obligation of Duro to repay to Samsung money the subject of an adjudication in respect of which leave to enforce was granted, I do not think that the discretion to grant leave to enforce is to be exercised with the object or effect of removing these doubts by resolving them in favour of Samsung through the imposition of the condition that it seeks. In my view, to do so would be to improve Samsung's contractual position under the 2013 Parent Company Guarantee and the Term Sheet.
462 For these reasons, Samsung has not persuaded me that there is any sufficient basis to refuse to give leave to enforce the determinations, to stay Duro's enforcement applications, or to impose the condition it sought upon the grant of leave. I would grant leave to enforce the first, fourth and fifth determinations accordingly.
463 My major conclusions may be summarised as follows:
(1) I would set aside the Second Determination on ground (h): in refusing to credit Samsung with its payment on account, the adjudicator exceeded his jurisdiction.
(2) I would set aside the Third Determination on ground (f), alternatively ground (e), relating to the adjudicator's response to Samsung's submission to him that there was no payment claim for the $32.4 million so that he had no jurisdiction to make any determination in relation to that sum.
(4) I would dismiss Samsung's applications to set aside the first, fourth and fifth determinations.
(5) I would grant leave to Duro to enforce the first, fourth and fifth determinations.
464 I will hear from the parties as to the orders to be made, and as to costs.
CITATION : SAMSUNG C&T CORPORATION -v- LOOTS [2016] WASC 330 (S)
Practice and procedure - Costs - 10 applications heard together - Appropriate costs orders - Turns on own facts
1 On 14 October 2016, I published reasons for decision on the ten applications before me.[342] The applications concerned five determinations under the Construction Contracts Act 2004 (WA). Samsung made five applications, each an application to set aside one of the determinations on grounds of jurisdictional error. Duro made five applications, each an application for leave to enforce one of the determinations.
2 Samsung succeeded in its applications to set aside the second and third determinations. It failed in relation to the first, fourth and fifth determinations. I granted leave to Duro to enforce the first, fourth and fifth determinations.
3 On 14 October 2016, I made orders to that effect. I also ordered that the parties file written submissions on the question of the costs of the applications, with those costs to be determined on the papers.
4 Samsung submits that orders to the following effect should be made:
(1) The costs of initiating the ten applications should be dealt with individually, with, in each application, those costs following the event.
(2) Otherwise, Duro pay 50% of Samsung's costs of Samsung's applications, such costs to be taxed as one set of costs.
(3) Samsung pay Duro's costs thrown away by reason of Samsung's abandonment of grounds (a) to (c).
(4) Subject to (1), Samsung pay Duro's costs of Duro's applications for leave to enforce.
(1) Samsung pay 80% of the costs incurred by Duro in the period prior to 27 July 2016;
(2) Samsung pay 60% of Duro's costs incurred on 27 July and 28 July 2016; and
(3) Samsung pay Duro's costs incurred after 28 July 2016.
6 The parties agree that, whatever costs orders are made, costs should be taxed without regard to the limits in the relevant items of the applicable scales.
7 Duro also seeks orders that its costs include its costs of the transcripts of the hearings on 25 May 2016 and 27 and 28 July 2016, as well as the costs of two instructing solicitors on 27 and 28 July 2016.
8 I begin with the broad question of the approach to be taken to costs in circumstances where ten applications were heard on 27 and 28 July 2016, and both parties had some success. There are many cases explaining the approach to be taken to questions of costs in an action where the ultimately successful party failed on some claims and issues in the action. For example, in Souter v Condor Developments Pty Ltd,[343] Newnes JA set out a helpful outline of the approach to be taken in such circumstances. The fact that there were ten applications in these proceedings adds a complicating factor: it cannot be assumed that, because the applications were heard together, they can be treated in all respects and for all purposes as one action.
9 In the circumstances of these ten applications, I do not think justice as to costs would be served by treating them as if they are, in substance, one action, and then seeking to identify the successful party in that action. Nor, at the other extreme, would it be appropriate to assess the costs of each application in isolation, with costs following the event in each. The nature and subject matter of the applications, the issues that arose in them, and the course of the applications call for a more nuanced approach that will better reflect the many and varied considerations relevant to the exercise of the costs discretion. Moreover, individual costs orders in each application would give rise to significant practical difficulties on a taxation.
10 From an early stage, on Samsung's application, and with the concurrence of Duro, the various applications were dealt with together by way of both evidence and submissions. In its written submissions on its applications, Samsung articulated its grounds, some of which related to more than one determination. Samsung put its written and oral submissions in the framework of those grounds, not in the framework of its individual applications to set aside the determinations. The orders for costs should reflect that position.
11 I think separate costs orders should be made in relation to Duro's applications for leave to enforce, on the one hand, and Samsung's applications to set aside the determinations, on the other. That position is adopted in Samsung's written submissions on costs and was adopted by Duro at the hearing on 14 October 2016.[344] Separate submissions and evidence were filed on the enforcement applications.
12 In my view, the orders proposed by Samsung in relation to Duro's applications for leave to enforce are the appropriate costs orders. Duro succeeded on the contests regarding leave to enforce. However, (of course) leave was not granted to enforce the determinations which were set aside. I accept, as Samsung submits, that:
(1) Duro should have its costs of initiating the applications for leave to enforce the first, fourth and fifth determinations;
(2) Duro should bear its own costs of initiating the applications for leave to enforce the second and third determinations, in respect of which leave was not given (because the determinations were set aside); and
(3) otherwise, Duro should have its costs of the applications for leave to enforce, taxed as one set of costs and without regard to the relevant scale limits.
13 The substantial issues between the parties relate to the costs of Samsung's applications.
14 Both parties assert that they were substantially successful on Samsung's applications.
15 Samsung submits that it should be awarded 50% of its costs of its applications.[345] In summary, it submits that:
(1) it substantially succeeded on the factual issues about what work was construction work, on which there was substantial evidence and conferral;[346]
(2) it was substantially successful in commercial terms, as it set aside determinations with a dollar value of 80% of the total value of the five determinations;[347] and
(3) it was substantially successful on the legal issues, apart from those relating to ground (i).[348]
16 I do not accept that Samsung was substantially successful on its applications, and do not accept the first and third supporting submissions summarised in [15] above.
17 I do not accept Samsung's submission that the exercise of the costs discretion should be substantially influenced by its contention that it was successful on the factual issues concerning construction work.[349] In more detail, Samsung submits that:
(a) in relation to grounds (a) to (c), there was considerable competing evidence and conferral about whether the Duro Works were construction work;[350]
(b) in that context, Duro maintained that all the work at the site of the process plant was construction work;[351]
(c) some of Duro's contentions were 'tenuous';[352]
(d) when Samsung abandoned grounds (a) to (c) and added ground (i), the issue narrowed to whether particular Determined Items were construction work. In that context, Duro maintained its earlier approach;[353]
(e) Duro was unsuccessful on this factual issue;[354] and
(f) not all of the work done in relation to grounds (a) to (c) was thrown away by the abandonment of those grounds, since some of it was relevant to ground (i);[355]
18 In my view, the starting point is that, since Samsung abandoned grounds (a) to (c) and failed on ground (i), it should be liable for Duro's costs in relation to all aspects of those grounds, including costs associated with the evidence led by the parties on those grounds, and related conferral. To my mind, given the way in which these proceedings were framed around the grounds, the wellknown caution about the severing of issues and claims within an action for the purposes of costs applies to each ground. Breaking up a ground into subissues, so that a party who was unsuccessful on the ground but successful on a subissue can have their costs of that subissue, is an exceptional course that requires clear and cogent justification. I am not persuaded that this course is appropriate in the circumstances of these applications. In my view, the parties' costs relating to each ground, encompassing the costs of submissions and evidence, should follow the event of the abandonment or dismissal of the ground.
19 Moreover, in circumstances where Samsung abandoned grounds (a) to (c), it seems to me to be inappropriate to enter into an assessment of the merits of the factual issues involved in those grounds.[356] That is what Samsung's submissions call for. For example, those submissions raise questions as to whether and how findings made in relation to particular Determined Items indicate what the court's assessment of the overall character of the Duro Works would have been. They also invite a comparative analysis of Duro's submissions and evidence on grounds (a) to (c) and those on ground (i). Further, Samsung's submissions invite attention to whether some (and if so which) of Duro's contentions in relation to grounds (a) to (c) were 'tenuous'.
20 As to Samsung's sixth proposition, set out in [17(f)], insofar as any costs incurred in relation to grounds (a) to (c) were not thrown away, they were relevant to ground (i) and no other ground. Given that Samsung failed on ground (i), I have given I think Duro should have those costs.
21 For the reasons I have given, I do not accept that Samsung's success on the provisional factual findings I made in relation to ground (i) in section 13.4 of the Primary Reasons justifies any costs order in favour of Samsung. In my view, the cost orders should be framed on the footing that Duro should have the costs of grounds (a) to (c) and (i).
22 I do not accept Samsung's submission that a consideration weighing in its favour in the exercise of the costs discretion is that it was successful on the legal issues in its applications, apart from those in relation to ground (i). In short, that is because, apart from ground (i), I do not think that Samsung's applications gave rise to or turned upon any substantial legal issues. Rather, the grounds on which Samsung succeeded turned upon the proper analysis and characterisation of what the adjudicator had, in each case, done and, in relation to ground (f), an analysis of the evidentiary material and submissions before the adjudicator, and what findings that material was capable of sustaining. Leaving aside ground (i) (and grounds (a) to (c)), I do not think the parties joined issue to any substantial degree on the applicable legal principles.
23 I accept that, in broad terms, Samsung enjoyed substantial commercial success in its applications. The applications concerned the validity of five determinations worth approximately $65 million. The two determinations in respect of which Samsung succeeded totalled about $52 million and thus approximately 80% of the total value of the five determinations. I accept that this commercial success is relevant to the exercise of the costs discretion. However, I do not think it has anything like the same significance in the present context, in which there were five different applications and determinations and nine grounds advanced, six of which were pressed, as it would in a context where there was one proceeding in which a party obtained relief worth 80% of the relief it claimed.
24 I accept Samsung's submission that its costs of initiating each of its five applications are discrete and readily identifiable, and are appropriately the subject of specific orders reflecting the outcome of each particular application. Consequently, I would order that Duro pay Samsung its costs of initiating its applications to set aside the second determination and the third determination, and that Samsung bear its own costs of initiating the first, fourth and fifth determinations. The 'costs of initiating' a proceeding refers to the costs of preparing, filing and serving the initiating application and the accompanying affidavit. As I have said, a like approach should be taken in relation to Duro's costs of initiating the enforcement applications.
25 Thereafter, the costs of Samsung's five applications should be dealt with globally. It seems to me that separate costs orders should be made in relation to three phases of the proceedings: prior to the hearing; the two days of the hearing; and after the hearing. That is because in the period prior to the hearing grounds (a) to (c) loomed large, Samsung abandoned those grounds on the second day of the hearing, and the appropriate apportioning of costs should reflect that. After the hearing, the only costs incurred were Duro's costs in relation to ground (i). For the reasons I have given, I think Duro should have those costs. Thus, distinct orders for these three phases will better reflect the justice of the parties' claims to costs. Such orders will not unduly complicate the taxation process.
26 I turn to the question of the appropriate costs orders for the period prior to the hearing of Samsung's five applications.
27 Samsung's five applications were heard together substantially, if not entirely, because grounds (a), (b) and (c) were common to all of them. I think it can fairly be said that a substantial majority of Samsung's written submissions, both in chief and in reply, and a very substantial proportion of the evidence it filed, related to grounds (a), (b) and (c). A substantial part of Duro's primary written submissions related to grounds (a), (b) and (c). Further, after a request from the court, Duro filed supplementary submissions[357] relating to those grounds. Given that it was not until the second day of the hearing that Samsung abandoned grounds (a) to (c), it can safely be inferred that a substantial part of Duro's preparation for the hearing would have been concerned with those grounds.
28 As I have said, in circumstances where Samsung abandoned grounds (a) to (c), I think the costs of those grounds should be accounted for in favour of Duro.
29 Ultimately, Samsung succeeded in relation to grounds (e), (f) and (h), and failed on grounds (d), (g) and (i). Ground (i) is not relevant to the prehearing phase. Each of grounds (d) to (h) occupied a relatively confined portion of the parties' written submissions. Ground (f) involved evidence of all the material before the relevant adjudicator.
30 In its costs submissions, Duro estimates that grounds (e), (f) and (h) occupied about 20% of the preparation of the proceedings.[358] It then submits that it should be awarded 80% of its costs of the period prior to the hearing. I do not accept the logic inherent in that contention. Samsung succeeded on grounds (e), (f) and (h). Samsung should be credited with its costs in relation to those grounds. That entitlement should be netted off against the 80% on which (on Duro's estimate) Duro succeeded. So, on Duro's estimate of the proportion of time taken up with the preparation of grounds (e), (f) and (h), Duro should have 60% of its costs, not 80%.
31 I think other considerations come into play in determining the appropriate apportionment of the costs of preparation. First, there is a certain amount of work of a general or introductory nature, relating to matters such as the background to the applications and the contractual framework, that was relevant to and necessary for all of Samsung's applications and all of its grounds. Since Samsung has succeeded on some of its grounds and applications, I think there should be some allowance for Samsung's costs of this work. Secondly, there are the commercial considerations arising from the overall outcome that I have already mentioned.
32 In all the circumstances, I think it is appropriate that Samsung pay 40% of Duro's costs of Samsung's applications prior to the hearing.
33 I turn to the costs of the hearing. I think it can fairly be said that both parties had a significant measure of success in respect of the matters argued at the hearing. The question is, upon more detailed consideration of the parties' respective successes and failures, where the balance lies. Duro's costs submissions set out a summary of the number of pages of transcript concerned with each of the various grounds, including enforcement. My analysis of the transcript differs somewhat, although not markedly, from Duro's.[359] Leaving the time taken up with enforcement to one side (as it is the subject of separate costs orders), on my assessment about 67 pages were taken up with grounds on which Duro succeeded, and about 48 pages with grounds on which Samsung succeeded. About 10 or 12 pages were taken up with general or introductory matters. As already mentioned, I think some credit should be given to Samsung in that regard. Of course, a comparison of the number of pages of transcript devoted to grounds on which each party succeeded is not of controlling significance, but it provides some broad guidance. Here, again, I would give some (but not great) weight to Samsung's overall commercial success.
34 In all the circumstances, I think each party should bear its own costs of Samsung's applications incurred on the hearing days.
35 For the reasons I have already given, I think there should be an order that Samsung pay Duro's costs after the hearing.
36 The parties accept that orders for costs, in whoever's favour they are made, should be taxed without regard to the relevant items in the applicable scales. I accept that this is appropriate. These matters were complex, important to the parties, and unusually difficult. I am satisfied that there is a fairly arguable case that the bill to be presented to the taxing officer may tax in an amount greater than the limit imposed by the applicable costs determinations, and that arises from the complexity, importance and unusual difficulty of these matters.
37 As I would make no order as to the costs of the hearing on 27 and 28 July 2016, Duro's application for orders regarding transcript and two solicitors for that hearing does not arise for determination. I will order that Duro's costs of Samsung's applications include the costs of the transcript of 25 May 2016.
38 For the reasons I have given, I make the following orders:
CIV 1255, 1257, 1596, 1773 and 1899 of 2016 (Enforcement)
CIV 1185, 1284, 1719, 1809 and 1905 of 2016 (Judicial Review)
(a) Items 11 and 28(a), (b) and (c) of the Legal Profession (Supreme Court) (Contentious Business) Determination 2014 (WA); and
(b) Item 11 of the Legal Profession (Supreme Court) (Contentious Business) Determination 2016 (WA),
[1] Affidavit of Daniel Ben Northcott sworn 3 March 2016 (Northcott 1) [23].
[4] Affidavit of Ante Golem sworn 5 February 2016 (Golem 1), annexure AG 1, pages 65 178.
[6] Copies of the Variation Orders are annexure DN 2 to Northcott 1.
[7] Affidavit of Eduardo Rodriguez Rodriguez sworn 12 July 2016 [6].
[9] Affidavit of Victoria Elizabeth Strong sworn 22 June 2016, annexure VES 2; affidavit of Ante Golem sworn 24 February 2016 (Golem 2), annexure AG 1, pages 56 62.
[10] See, in this regard, Northcott 1 [32] and Duro's submissions dated 22 June 2016 [88] and following.
[11] Northcott 1 [31]; Mr Rodriguez's affidavit [12].
[15] Laing O'Rourke Australia Construction Pty Ltd v Samsung C&T Corporation [2016] WASCA 130. This case was an appeal from the decision of Mitchell J in Laing O'Rourke Australia Construction Pty Ltd v Samsung C&T Corporation [2015] WASC 237. To avoid confusion, I will refer to Mitchell J's decision as Laing O'Rourke v Samsung [2015] and the decision on appeal as Laing O'Rourke v Samsung [2016].
[18] Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; (2009) 239 CLR 175.
[19] Aon Risk v ANU [89] - [103], [111] - [112].
[33] s 36(d) and (f), s 37(1)(a) and (b).
[35] Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217; (2011) 43 WAR 319 [7] [8], [92].
[36] Perrinepod [7] [8], [121] [126].
[37] As to which see Kirk v Industrial Court of New South Wales [2010] HCA 1; (2010) 239 CLR 531 [67] [70]; Laing O'Rourke v Samsung [2016] [94].
[38] Perrinepod [118]; Cape Range Electrical Contractors Pty Ltd v Austral Construction Pty Ltd [2012] WASC 304 [83]; Re Ellis; Ex parte Triple M Mechanical Services Pty Ltd [No 2] [2013] WASC 161 [75], [79]; WQube Port of Dampier v Philip Loots of Kahlia Nominees Ltd [2014] WASC 331 [14] [15], [28].
[39] Perrinepod [118]; Re Ellis [79]; WQube v Philip Loots of Kahlia Nominees [28].
[42] Perrinepod [10] [12], [115]; Laing O'Rourke v Samsung [2016] [97], [198].
[43] Laing O'Rourke v Samsung [2016] [97], [199].
[44] Kirk [71]; Laing O'Rourke v Samsung [2016] [90].
[45] Laing O'Rourke v Samsung [2016] [90], and see the cases referred to by Martin CJ in fn 38.
[46] Re Carey; Ex parte Exclude Holdings Pty Ltd [2006] WASCA 219; (2006) 32 WAR 501 [181]; Re The State Administrative Tribunal; Ex parte McCourt [2007] WASCA 125; (2007) 34 WAR 342 [16]; Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163, 177 178.
[47] Kirk [60]; Minister for Immigration and Border Protection v SZSSJ [2016] HCA 29 [81] [82].
[48] Laing O'Rourke v Samsung [2016] [95].
[49] Laing O'Rourke v Samsung [2016] [95], [102].
[50] Laing O'Rourke v Samsung [2016] [98] [100]; Cape Range [50] [58].
[51] Laing O'Rourke v Samsung [2016] [101].
[52] Laing O'Rourke v Samsung [2016] [105], [107], [121] [122], [130].
[53] Collector of Customs v Pozzolanic Enterprises Pty Ltd [1993] FCA 322; (1993) 43 FCR 280, 287; Laing O'Rourke v Samsung [2016] [109].
[55] Second Determination reasons, lines 826 - 831.
[56] Second Determination reasons, lines 833 - 889.
[57] Second Determination reasons, lines 904 910.
[58] Second Determination reasons, lines 1095 1110.
[59] Fourth Determination reasons [141].
[60] Fourth Determination reasons [142].
[61] Fourth Determination reasons [143].
[62] Fourth Determination reasons [147].
[63] Fourth Determination reasons [72].
[64] Samsung's submissions dated 26 May 2016 [124].
[65] Samsung's submissions [127] - [133].
[66] Samsung reply submissions dated 4 July 2016 [51] [55].
[68] Samsung's submissions [17]; ts 53.
[71] Duro's adjudication submissions [1.4], [2.1], [2.2], [7.3] [7.4].
[72] Duro's adjudication submissions [1.3], [5.1], [5.2].
[73] Duro's adjudication submissions [5.3(c)].
[74] Duro's adjudication submissions [7.1] [7.2].
[75] Duro's adjudication submissions [7.3(a)].
[76] Duro's adjudication submissions [7.3(a)], [7.3(c)].
[77] Duro's adjudication submissions [10.6], [11.2], annexure B and annexure C.
[78] Duro's adjudication submissions [12.1].
[79] Duro's adjudication submissions [15.1].
[80] Duro's adjudication submissions [15.2].
[81] Duro's adjudication submissions [15.3] [15.14].
[82] Duro's adjudication submissions [15.12].
[83] Duro's adjudication submissions [15.13] [15.14].
[84] Duro's adjudication submissions [15.15].
[85] Duro's adjudication submissions [15.16].
[86] Duro's adjudication submissions [15.17].
[87] Sections 16 22 of Duro's adjudication submissions.
[89] Samsung's adjudication submissions [1].
[90] Samsung's adjudication submissions [11(a)].
[91] Samsung's adjudication submissions [17].
[92] Samsung's adjudication submissions [18].
[93] Samsung's adjudication submissions [19].
[94] Samsung's adjudication submissions [20] [32].
[97] Samsung's adjudication submissions [44], [49].
[98] Third Determination reasons [18] [20].
[99] Third Determination reasons [21].
[100] Third Determination reasons [22].
[101] Third Determination reasons [23(g)].
[102] Third Determination reasons [23(i)].
[103] Third Determination reasons [23(a) - (e)].
[104] Third Determination reasons [23(j)].
[105] Third Determination reasons [23(k) and (l)].
[106] Third Determination reasons [23(p)].
[107] Third Determination reasons [24].
[108] Third Determination reasons [33], [110].
[109] Third Determination reasons, table under [216].
[110] Affidavit of Ante Golem sworn 29 April 2016 (Golem 3), annexure AG 6, pages 496 497.
[112] Golem 3, annexure AG 6, pages 647 660.
[113] See, for example, Third Determination reasons [19].
[115] Samsung's adjudication submissions [11(a)(i)], [40] [41], [44], [49].
[116] Duro's submissions [168]; ts 116 - 117, 120.
[117] Samsung's submissions [140] - [142]; Samsung's reply submissions [58] - [60], [62]; ts 21, 23, 27, 35 36, 70, 138, 139.
[118] Duro's submissions [165], [167], [172], [173]; ts 118 119; Duro's supplementary submissions dated 26 August 2016 [173] [176].
[119] Third Determination reasons [23(g)].
[120] Duro's submissions [165]; ts 119.
[121] Samsung's adjudication submissions [41]; see also [11(a)].
[123] Third Determination reasons [21].
[124] See Samsung's adjudication submissions [1], [11].
[125] Duro's adjudication submissions [7.1].
[126] Duro's adjudication submissions [7.1].
[132] Duro's submissions [171] [175].
[133] Duro's submissions [172] [173].
[135] Laing O'Rourke v Samsung [2016] [200]; O'Donnell Griffin Pty Ltd v John Holland Pty Ltd [2009] WASC 19 [75]; Alliance Contracting Pty Ltd v James [2014] WASC 212 [58].
[136] O'Donnell Griffin v John Holland [77]; Alliance Contracting v James [58].
[137] Alliance Contracting v James [60]; adopted by Mitchell J in Laing O'Rourke v Samsung [2015] [186].
[141] Zurich Bay Holdings Pty Ltd v Brookfield Multiplex Engineering and Infrastructure Pty Ltd [2014] WASC 39 [16].
[142] Dranichnikov v Minister for Immigration and Multicultural and Indigenous Affairs [2003] HCA 26; (2003) 197 ALR 389 [24] [25], [95]; Plaintiff M61/2010E v The Commonwealth [2010] HCA 41; (2010) 243 CLR 319 [83], [84], [90]; Rodger v De Gelder [2015] NSWCA 211 [93].
[143] Kirk [60]; Rodger v De Gelder [94]; Minister for Immigration and Border Protection v SZSSJ [81] [82].
[144] Samsung's adjudication submissions [183] - [188].
[145] Samsung's adjudication submissions, sections 14 and 16.
[146] The power to do so is in s 32(2)(a) of the Act.
[147] First Determination reasons [16] - [18].
[148] First Determination reasons [32] - [190].
[149] First Determination reasons [191] - [199].
[150] First Determination reasons [200] - [201].
[151] First Determination reasons [202].
[152] First Determination reasons [207].
[153] First Determination reasons [209].
[154] First Determination reasons [212].
[155] First Determination reasons [213] - [226].
[156] First Determination reasons [227] - [232].
[157] First Determination reasons [233] - [248].
[158] First Determination reasons [249].
[159] First Determination reasons [252] - [269].
[160] First Determination reasons [263], [269].
[161] First Determination reasons [270] - [282].
[162] First Determination reasons [283] - [289].
[163] Samsung's submissions [148] - [150]; ts 39 - 45, 143 - 146.
[164] Wingfoot Australia Partners Pty Ltd v Kocak [2013] HCA 43; (2013) 252 CLR 480 [43], [45].
[165] Section 31(2)(a)(iv) of the Act.
[166] Zurich Bay Holdings [15] [16]; BGC Construction Pty Ltd v Citygate Properties Pty Ltd [2016] WASC 88 [145]. A similar approach has been taken in other jurisdictions: see Sierra Property Qld Pty Ltd v National Construction Management Pty Ltd [2016] QSC 108 [39] [43] and the cases referred to.
[167] Stone v Braun [2015] WASCA 103 [91]; Falkingham v Hoffmans [2014] WASCA 140; (2014) 46 WAR 510 [304].
[168] Stone v Braun [91]; Bennett v Carruthers [2010] WASCA 131 [27] - [28]; Falkingham v Hoffmans [304].
[169] First Determination reasons [209].
[170] Duro's adjudication submissions [25.2]; cf Samsung's adjudication submissions [190].
[171] First Determination reasons [201], [207].
[173] First Determination reasons [200], [201], [207(a)], [208].
[174] First Determination reasons [201].
[175] First Determination reasons [208].
[176] First Determination reasons [207(a)].
[177] First Determination reasons [250].
[180] First Determination reasons [201], [207].
[181] Golem 2, annexure AG 2, pages 138 - 143.
[182] Golem 2, annexure AG 2, pages 144 - 150.
[183] Samsung's adjudication submissions [188].
[184] Second Determination reasons, lines 1343 - 1344.
[185] Second Determination reasons, lines 1253 - 1255.
[186] Second Determination reasons, lines 1258 - 1260.
[187] Second Determination reasons, lines 1346 - 1351.
[190] Golem 3, annexure AG 6, page 620.
[191] Golem 2, annexure AG 2, pages 148, 149.
[192] Duro's submissions [181] - [184]; ts 125.
[193] Second Determination reasons, lines 1343 - 1344.
[194] Second Determination reasons, lines 1346 - 1351.
[196] Duro's submissions [185] - [186].
[197] Alliance Contracting v James [60], quoted in [217] above.
[198] Alliance Contracting v James [65] - [66].
[199] Samsung's adjudication submissions, section 15.
[200] Second Determination reasons, lines 1249 - 1251.
[201] O'Donnell Griffin v John Holland [78] - [79].
[202] Golem 2, annexure AG 2, pages 148, 149.
[203] Golem 2, annexure AG 5, page 621.
[212] ts 60 - 64, 77, 101 - 102, 160 - 162.
[214] Corporation of City of Enfield v Development Assessment Commission [2000] HCA 5; (2000) 199 CLR 135 [28]; Gedeon v Commissioner of the New South Wales Crime Commission [2008] HCA 43; (2008) 236 CLR 120 [43].
[215] City of Enfield [28]; Plaintiff M70/2011 v Minister for Immigration and Citizenship [2011] HCA 32; (2011) 244 CLR 144 [57], [111].
[217] City of Enfield [28] - [34]; Plaintiff M70/2011 [57], [107] - [109]; Perrinepod [11], [106]; Timbarra Protection Coalition Inc v Ross Mining NL [1999] NSWCA 8; (1999) 46 NSWLR 55 [39] [41]; Laing O'Rourke v Samsung [2016] [198].
[218] See Thiess Pty Ltd v MCC Mining (Western Australia) Pty Ltd [2011] WASC 80 [60] - [73]; Cape Range [74] - [75], [81] - [84]; Re Ellis [84] - [88]; WQube v Philip Loots of Kahlia Nominees [77] [83]; Red Ink Homes Pty Ltd v Court [2014] WASC 52 [85] - [90]; Hamersley Iron Pty Ltd v James [2015] WASC 10 [53] [54].
[219] Delmere Holdings Pty Ltd v Green [2015] WASC 148 [88] - [103].
[220] Laing O'Rourke v Samsung [2015] [170] [190].
[223] WQube v Philip Loots of Kahlia Nominees [99].
[225] Delmere Holdings v Green [109].
[226] See [109] but compare [102].
[227] Re AnsteeBrook; Ex parte Karara Mining Ltd [No 2] [2013] WASC 59 [27].
[228] M&W Singapore Pte Ltd v AnsteeBrook [2016] WASC 310 [39].
[230] Laing O'Rourke v Samsung [2016] [97], [199].
[233] Duro's supplementary submissions [19] - [21].
[234] Duro's supplementary submissions [15] - [18].
[235] Duro's supplementary submissions [50] - [55].
[236] Laing O'Rourke v Samsung [2016] [199].
[238] Laing O'Rourke v Samsung [2016] [73] - [74].
[239] Laing O'Rourke v Samsung [2016] [200]; O'Donnell Griffin v John Holland [75]; Alliance Contracting v James [58].
[240] O'Donnell Griffin v John Holland [77]; Alliance Contracting v James [58].
[241] Alliance Contracting v James [60].
[248] Duro's supplementary submissions [126], [136].
[249] Kelly v The Queen [2004] HCA 12; (2004) 218 CLR 216 [84], [103]; Epic Energy (Pilbara Pipeline) Pty Ltd v Commissioner of State Revenue [2011] WASCA 228; (2011) 43 WAR 186 [42], [150], [218].
[251] O'Donnell Griffin v John Holland [83].
[252] First Determination reasons [18], [148], [152], [172]; Second Determination reasons, lines 379 389; Fifth Determination reasons [6.5], [7.7], [9.1], [9.2], [11.2], [11.3].
[253] Samsung's submissions [61], [70], [82]; Samsung's supplementary submissions dated 1 June 2016 [7].
[254] Duro's supplementary submissions [144] - [145].
[255] Re AnsteeBrook; Ex parte Karara Mining [16].
[256] Re AnsteeBrook; Ex parte Karara Mining [16].
[257] Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60 [87].
[258] For example, as to Package 1, see pt 4 of the Scope of Work.
[259] First Determination reasons [32] - [63], [282].
[260] Golem 1, annexure AG 5 [13], [33]; see also Northcott 1 [85].
[261] Duro's supplementary submissions [148], [149].
[262] Golem 1, annexure AG 1, pages 94 - 95; see also Northcott 1 [33], [83].
[263] Golem 1, annexure AG 1, pages 89 - 101; Northcott 1 [83].
[264] Affidavit of Carlos Gonzales Perez sworn 25 August 2016 [46].
[265] First Determination reasons [64] - [79], [282].
[266] First Determination reasons [33].
[271] Duro's supplementary submissions [152(b)].
[272] See part 4 of the Scope of Work, Golem 1, annexure AG 1, pages 89 - 101 (including cl 4.2.4); Northcott 1 [33].
[273] First Determination reasons [123] - [145], [282].
[274] First Determination reasons [125]; Golem 1, annexure AG 7 [9].
[277] Duro's supplementary submissions [154].
[278] Duro's supplementary submissions [155].
[279] First Determination reasons [174] - [190], [282].
[282] Golem 1, annexure AG 6 [152], [159].
[283] Golem 1, annexure AG 6 [153]; Northcott 1 [99] - [100].
[284] Second Determination reasons, lines 1140 - 1158.
[285] Golem 2, annexure AG 3 [32] [33].
[286] Golem 2, annexure AG 3 [38]; Northcott 1 [46], [115].
[287] Northcott 1 [33], [116]; Golem 1, annexure AG 1, pages 89 - 101 (including cl 4.2.3); affidavit of Daniel Ben Northcott sworn 22 July 2016 (Northcott 3) [4] [15]; affidavit of Ruben Rodriguez Fernandez sworn 23 August 2016 [11].
[288] Northcott 3 [5]; Mr Fernandez's affidavit [11].
[289] Mr Fernandez's affidavit [13] - [17].
[290] Golem 2, annexure AG 3 [63]; Second Determination reasons, lines 46 50.
[292] See Golem 2, annexure AG 3 [58] [63].
[293] Second Determination reasons, pages 905, 929 930.
[295] Northcott 1 [99(a)]; see also Golem 2, annexure AG 6 [133] - [137].
[298] Golem 2, annexure AG 6 [33]; Northcott 1 [30(a)].
[299] Fifth Determination reasons [12.9].
[300] Affidavit of Ante Golem sworn 1 June 2016 (Golem 5), annexure AG 4 [10] [14], annexure AG 7 [93].
[301] Golem 1, annexure AG 1, page 89.
[302] Fifth Determination reasons [20.12].
[304] Alliance Contracting v James [84] - [91].
[305] Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 [92].
[306] Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2007] NSWSC 1298 [16]; Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 657 [9].
[307] Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373 [61]; Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2013] QSC 141 [28] [29]; James Trowse Constructions Pty Ltd v ASAP Plasterers Pty Ltd [2011] QSC 145 [55].
[308] See the cases referred to in the two previous footnotes.
[309] BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2013] QCA 394; [2015] 1 Qd R 228.
[310] BM Alliance Coal Operations v BGC Contracting [71].
[311] Gantley Pty Ltd v Phoenix International Group Pty Ltd [2010] VSC 106; Duro's submissions [192] [195].
[313] Duro's submissions [196], [202(a)].
[314] Re Narula, Ng & Hammersley; Ex parte Atanasoski [2003] WASCA 156 [48] [51].
[317] Cheatley v The Queen [1972] HCA 63; (1972) 127 CLR 291, 308 309; Strother v Tavener [2016] WASC 85 [124]. It is also true of the cases relied on by Pritchard J in Strother v Tavener.
[318] Anderson v Judges of the District Court of NSW (1992) 27 NSWLR 701, 712 713; Director of Public Prosecutions (NSW) v Ede [2014] NSWCA 282; (2014) 289 FLR 82 [45]. See also M&W Singapore v AnsteeBrook [43] [44].
[319] Duro's submissions [191] - [195], [202(b)].
[320] Laing O'Rourke v Samsung [2016] [139] - [143]; O'Donnell Griffin Pty Ltd v John Holland Pty Ltd [2008] WASC 58; (2008) 36 WAR 479 [13], [41] [45]; Hamersley Iron v James [116].
[321] Samsung's enforcement submissions dated 4 July 2016 [2].
[322] Samsung's enforcement submissions [5].
[323] Affidavit of Juyeul Son sworn 4 July 2016, annexure JS 1.
[324] Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2015] WASC 484.
[325] Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2016] WASC 119.
[326] Affidavit of Ante Golem sworn 26 July 2016 (Golem 7), annexure AG 1.
[327] Affidavit of Ante Golem sworn 4 July 2016 (Golem 6), annexure AG 21.
[330] Affidavit of Victoria Elizabeth Strong sworn 28 July 2016, annexure VES 10.
[331] Ms Strong's affidavit, annexure VES 9.
[335] Samsung's enforcement submissions [16]; ts 166.
[336] See, by analogy, RJ Neller Building Pty Ltd v Ainsworth [2008] QCA 397; [2009] 1 Qd R 390 [39] [41]; Chase Oyster Bar v Hamo Industries [2010] NSWCA 190; (2010) 78 NSWLR 393 [207]; Re AnsteeBrook; Ex parte Karara Mining [19] [21].
[337] RSA (Moorvale Station) Pty Ltd v VDM CCE Pty Ltd [2012] NSWSC 861 [12], citing Taylor Projects Group Pty Ltd v Brick Dept Pty Ltd [2005] NSWSC 571 [59].
[342] Samsung C&T Corporation v Loots [2016] WASC 330 (Primary Reasons).
[343] Souter v Condor Developments Pty Ltd [2012] WASCA 227 [28] - [30].
[345] Samsung's costs submissions [20] - [22].
[346] Samsung's costs submissions [10] - [11], [19], [20].
[347] Samsung's costs submissions [5], [20].
[348] Samsung's costs submissions [12], [13], [20].
[349] Samsung's costs submissions [19], [20].
[350] Samsung's costs submissions [10] and annexure.
[351] Samsung's costs submissions [10].
[352] Samsung's costs submissions, annexure [2].
[353] Samsung's costs submissions [11].
[354] Samsung's costs submissions [11], [20].
[355] Samsung's costs submissions [11], [14].
[356] See, by analogy, Re Minister for Immigration and Ethnic Affairs; Ex parte Lai Qin [1997] HCA 6; (1997) 186 CLR 622, 624 625.
[357] Duro's submissions on effect of Samsung's interpretation of 'construction contract' dated 12 July 2016.
[359] On my analysis, a few less pages of transcript were concerned with the grounds on which Duro succeeded than is suggested in Duro's submissions.
(2009) 239 CLR 175
(2011) 43 WAR 319
(2014) 46 WAR 510
(2000) 199 CLR 135
(2008) 236 CLR 120
(2011) 43 WAR 186
(1972) 127 CLR 291
(2010) 78 NSWLR 393
(1997) 186 CLR 622
(2006) 32 WAR 501
(2007) 34 WAR 342
(1995) 184 CLR 163
(1993) 43 FCR 280
(2003) 197 ALR 389
(2010) 243 CLR 319
(2013) 252 CLR 480
(2011) 244 CLR 144
(1999) 46 NSWLR 55
(2004) 218 CLR 216
(1992) 27 NSWLR 701
(2014) 289 FLR 82
(2008) 36 WAR 479
(2010) 239 CLR 531