[2021] VSC 358
Supreme Court of Victoria
2021-06-21
Stynes J
Original judgment source is linked above.
(a) in relation to Issue 2, the Adjudicator did consider the submissions, including a defects report, duly made by the plaintiff;
(b) in relation to Issue 3, the Adjudicator did properly value the provisional sum allowance claimed by the first defendant; and
(c) in relation to Issue 4, a valid reference date had not arisen under the contract in relation to the relevant payment claim.
(a) complete the building works in accordance with the definition of Completion under the Contract within 74 days of the date of the order;
(b) carry out the domestic building work in accordance with the Building Act 1993 (Vic), any regulations made under that Act and any relevant building permit; and
(c) notify the Chief Dispute Resolution Officer and the plaintiff that the work required by the order has been carried out, within two days of completion.
Can you confirm that all items are complete now and the Owners are satisfied the dwellings are completed? We may not need to issue a Breach of Dispute Resolution Order Notice (BODRON) if the Owners agree the build is complete post-report.
... it appears that only the intercom issue noted in the report were still outstanding post-assessment. Could you please confirm that this has been completed with your client?
If the items listed in the assessor's report have been completed, DBDRV would not be comfortable issuing a breach of dispute resolution audit notice (BODRON) based on the report issued to the parties. It may be that we assess the completion of the property again in the new year to confirm before making a determination.
(a) the adjudication application was invalid because the plaintiff was not in the business of building residences;
(b) the deduction to be made in respect of estimated cost of rectification;
(c) the Payment Claim is invalid as no reference date arose for the purpose of the SOP Act because certain pre-conditions under the Contract were not met;
(d) the inclusion of variations in the Payment Claim constitute excluded amounts; and
(e) the inclusion of excessive prime cost items in the Payment Claim, which cannot be claimed under the Contract.
C Issue 1 - Was the plaintiff in the business of building residences
(a) it appeared to the Adjudicator that the directors of the plaintiff had substantial experience and expertise in land acquisition, design, town planning and construction of this type of multi-unit project albeit that they may have genuinely intended the development to become a residence for the respective family members;[8]
(b) the unit trust structure, created to acquire and develop the Property, was to the Adjudicator in the nature of a vehicle which had as its purpose a commercial enterprise to generate profit for those engaged in it or who had an interest in it;[9]
(c) irrespective of the desire to provide residences to family members as a primary purpose of the Project, profit-making was an equally true primary purpose;[10] and
(d) the Project was so substantial that it was more consistent with a professional property development project for profit than a domestic building contract of the nature that might be expected to fall outside the SOP Act.[11] I note that the contract sum for the Project comprising all four units was $1,215,000.00.
(a) the Court must determine the question of fact for itself on the evidence placed before it;[13]
(b) the burden of establishing the facts which show an absence of jurisdiction always rests on the party applying for relief;[14]
(c) the standard of proof is high, requiring 'clear proof leading unmistakably to [the] conclusion' that there was an excess of jurisdiction;[15] and
(d) the Court will hesitate before interfering if the adjudicator has investigated the facts upon which the jurisdiction depends and the finding is not manifestly wrong.[16]
C.3.2 "in the business of building residences"
(a) the expression 'in the business of building residences' connotes the construction of dwelling houses as a commercial enterprise on the basis of a going concern, that is, an enterprise engaged in for the purpose of profit on a continuous and repetitive basis;[19]
(b) s 7(2)(b) of the SOP Act 'speaks in terms of the actual business which the builder owner undertakes, not whether a party in the position of the building owner has the power to undertake the activity';[20]
(c) the determination of the question of whether a 'building owner is in the business of building residences' does not depend on the scale of the business, the success of the business, the number of projects undertaken either in the past or at any one time, or as contemplated for the future;[21]
(d) 'what constitutes being "in the business of building residences" for the purposes of s 7(2)(b) of the [SOP] Act is in each case an issue of fact to be determined on a case by case basis';[22]
(e) a single joint venture may be sufficient to fall within the concept [of carrying on a business], in spite of the apparent absence of the element of a going concern conducted on a continuous and repetitive basis.[23] In Ian Street Developer Pty Ltd v Arrow International Pty Ltd, Riordan J confirmed that special purpose entities or companies incorporated for a single project may be 'in the business of building residences' even where the entity or company intends to sell the residences through another entity or company.[24] It was considered relevant in Ian Street Developer that a special purpose vehicle was incorporated with the sole purpose of constructing the project and the units in the project being resold to a related corporation for profit.[25]
(a) there is no evidence of an intention on the part of the plaintiff to make a profit. To the contrary, the plaintiff is a special purpose vehicle created to build four units for occupation by the two families of the two directors;
(b) the company structure was employed on the advice of an accountant, not with the intention of making a profit;
(c) the plaintiff has no prior involvement in any other development or business of building residences. By their affidavits the directors of the plaintiff addressed their personal involvement (as distinct from the plaintiff's involvement) in construction projects and expressly deny any involvement in a business of building residences. Mr Chempakasseril deposed that he had never built before or been involved in any property development prior to the Project. Mr Zamir has had experience building homes. He addresses that experience in some detail. In summary, in around 2001 he engaged a builder to build a home which he and his family lived in for about 12 years and in around 2014 he and one of his sons engaged a builder to build three units to be occupied by Mr Chempakasseril and his two sons; and
(d) the directors are not builders or subcontractors, but are naval engineers.
(a) the use of the corporate trustee. It was submitted that this is a relevant factor on the basis that when someone is engaging in a project for profit they are more likely to engage the protections of a corporate structure and to use a trustee arrangement. Counsel for the first defendant noted that cl 13.17 of the relevant trust deed permitted the plaintiff to carry on a business;
(b) the use of a fixed unit trust, as opposed to a discretionary trust or other more common family arrangement;
(c) the trust bears the property name raising an inference that it is a special purpose vehicle;
(e) the trust is registered for GST. It was submitted that s 23.10 of A New Tax System (Goods and Services Tax) Act 1999 (Cth) permits an entity to be registered only if it carried on, or intends to carry on an 'enterprise'. Section 9.20 relevantly defines the expression 'enterprise' to include an activity or series of activities done in the form of a business. It is submitted that the implication is that the plaintiff has represented to the tax office, at least for GST purposes, that it is developing the Property as a business;
(f) the contract was entered into in accordance with the business the subject of the ABN;
(h) a four unit development for a contract sum of $1,215,000.00 is a substantial property development more in the nature of a professional property development project than a domestic building project of the nature that might be expected to deprive the builder of the ability to leverage rights available under the SOP Act.
(a) if registration for GST was a mistake then it was a mistake, but that does not transform the activity of the plaintiff into a business; and
(b) the plaintiff has not lodged any business activity statements.
(a) Mr Zamir and Mr Chempakasseril explained that the corporate trustee was employed on the advice of an accountant for personal liability purposes and was not driven by a desire to conduct a business. They were not subjected to cross examination. I accept that evidence;
(b) the fact that the plaintiff was created for a single purpose is entirely consistent with the plaintiff's position that its sole purpose was to build residences for occupation by the two families and that there was no intention that it engage in an enterprise for the purpose of profit on a continuous or repetitive basis;
(c) I do not consider a four unit development for a contract sum of $1,215,000.00 to be such a substantial development to support the proposition that it is in the nature of a professional development; and
(d) in my opinion an inference to be drawn from the collection of factors relied on by the first defendant relating to the creation of a corporate vehicle and the registration for GST is not as persuasive as the direct and uncontested evidence of the plaintiff's directors as to the sole purpose of the plaintiff to build dwellings for the personal use by the directors and their families.
(b) in determining that the SOP Act applied to the Contract, the Adjudicator has made a jurisdictional error; and
(c) I order that the Adjudication Determination be quashed.
D Issue 2 - Did the Adjudicator fail to have regard to the submissions made by the plaintiff pursuant to s 23(2)(d) of the SOP Act
(a) in his view the very late delivery of the highly detailed Buildspect Report, together with the adjudication response, made it impossible as a matter of practicality for the first defendant to be able to properly respond within the two business days allowed in s 21(2B) of the SOP Act. As a matter of natural justice, he determined to err on the side of not placing the first defendant at a disadvantage by being unable to respond to the Buildspect Report within the two business days available;[28]
(b) considering the Buildspect Report would be inconsistent with the interim nature of the SOP Act, and the plaintiff is not prevented from relying upon it in any further proceeding;[29]
(c) the plaintiff had produced a number of previous lists of defects;[30]
(d) the conclusions in the Buildspect Report were not easily reconciled with the Defects List Report and/or 'the plaintiff's report to DBDRV dated 10 December 2020';[31] and
(e) the conclusions in the Buildspect Report could not reasonably have been anticipated by the first defendant on the basis of the material contained in the Payment Schedule.[32]
I adopt the estimates of cost of rectifying defective work assessed in the Jeffery Report dated 6 January 2021 in preference to the estimated cost of rectifying defective work assessed in the Buildspect Report dated 3 December 2020. In my view, the cost analysis in the [sic] looks high relative to the nature of the defects identified in the DBDRV report dated 11 December 2020. On balance, in my view, the cost assessments contained in the Jeffery Report dated 6 January 2021 look reasonable.
(a) the whole of the content and tenor of an adjudication may be called in aid in deciding whether particular submissions were considered in the way the SOP Act requires. Inference is permissible. The question is not to be approached solely by reference to the presence or absence of explicit statements referring expressly to the submissions;[34]
In my view, the obligation to consider matters imposed by [the equivalent section in the NSW legislation to s 23(2)] should ... [require] an active process of intellectual engagement. It may be thought that this imposes a substantial burden on adjudicators. That may be so; but there are at least two reasons why, even if that is correct, it does not justify reading down the statutory obligation to "consider". The first is that adjudicators are not forced to accept nomination. They may decline nomination; or they may accept only on the condition that they are given some longer period of time than ten working days to produce their determination. The second reason is that the outcome of the adjudicators consideration may have very significant consequences.
(c) '... the reasons given by adjudicators for their determinations are not to be analysed closely and parsed pedantically, with a predisposition to discerning error';[37]
(e) '[t]he [SOP] Act does not contemplate the reception of evidence which would be admissible under the laws of evidence in a court of law. Documentary evidence in the nature of submissions and relevant documentation is to be considered by an adjudicator';[40]
(f) 'it is unrealistic to expect that those reasons will treat minutely and in detail with each and every aspect of the parties' submissions and each and every aspect of the evidence. Having said that, adjudicators' reasons should be sufficiently detailed to enable parties to understand that their contentions, as advanced in the payment claim and payment schedule, and relevant material in support, have been considered, and to understand the process of reasoning that led to the particular conclusion';[41] and
(g) 'any failure by the Tribunal to consider, and record in its reasons its consideration of, the consistency and probative value of evidence [does not necessarily amount] to an error of law or jurisdictional error'.[42] Further, 'issues of weight' are intended for the Tribunal to determine.[43] Relevantly, 'if the conclusion cannot be challenged as legally erroneous, the reasoning cannot be challenged as legally inadequate to justify the conclusion'.[44]
(a) there is a preliminary issue as to whether the Adjudicator was required to have regard to defective works in valuing the Payment Claim. If he wasn't so required, then the Adjudicator could not have fallen into jurisdictional error as alleged by the plaintiff; and
(b) if the Adjudicator was required to have regard to defective works in valuing the claim, a review of the Adjudication Determination reveals that the Adjudicator did have regard to the Buildspect Report but decided not to allow it to supplant the previous lists of defects.
'not take the Buildspect Report ... into account in assessing the estimated cost of rectifying defect work' and the complete absence of his consideration of the Buildspect Report in relation to his determination of the existence of a reference date, it is tempting to conclude that his consideration of the Buildspect Report was inadequate to satisfy the requirement of s 23(2) of the SOP Act. However, his comments that:
(a) the conclusions in the Buildspect Report were not easily reconciled with the Defects List Report and/or the plaintiff's report to DBDRV; and
(b) in his view the cost analysis in the Buildspect Report looked high relative to the nature of the defects identified in the DBDRV report,
make it clear that he did consider the Buildspect Report as required by s 23(2) of the SOP Act in the sense that he engaged with the merits of it and compared its contents with other evidence going to the identification of defects and the costs of rectification.
E Issue 3 - Did the Adjudicator fail to value the payment claim, specifically a provisional sum allowance claimed by the first defendant
(a) the kitchen & joinery was a provisional sum item. This conclusion is not disputed in this proceeding;
(b) the first defendant had spent $144,700.00 in respect of that item; and
(c) the first defendant is entitled to an adjustment to the contract sum of $144,700.00.
(a) the absence of relevant material from the respondent, or the presentation of material in an incoherent fashion, does not entitle an adjudicator to simply award the amount of the claim. As a minimum, the adjudicator is obliged to determine whether the construction work identified in the payment claim has been carried out, and what is its value.[47] The adjudicator is obliged to make these findings on the evidence before him or her;[48]
(b) nevertheless, if the claimant has put on material as to the value of a claim, but the respondent has not, the adjudicator in assessing the value is entitled to draw any necessary inference from the absence of controverting material from the respondent, including an inference that no credible challenge can be made to the value of the claim advanced by the claimant. Such an inference may not be conclusive, but it may be taken into account in assessing the evidence of value overall;[49]
(c) an adjudicator is not required to act as an expert building valuer;[50]
(d) what is required is for an adjudicator in each case to consider and assess the valuation evidence presented in the course of the adjudication, and arrive at a rational assessment of value on the basis of that evidence;[51]
(e) given the severe statutory time constraints placed on adjudicators to perform their tasks,[52] an analysis undertaken on judicial review of the valuation exercise documented in the adjudicator's adjudication determination ought not to be approached from an unduly critical viewpoint.[53] Rather, the SOP Act calls for a practical and robust approach to the assessment process on the part of adjudicators and their expressed reasons;[54]
(f) the adjudicator must proceed with their task by:
(i) fairly assessing and weighing the whole of the evidence which is relevant to each issue arising for determination at the adjudication;
(ii) drawing any necessary inferences from the evidence, or from the absence of any controverting material provided by the respondent, including an inference that if there is no controverting material, no credible challenge can be made to the value of the claim advanced by the claimant. Such an inference may be considered in the context of the evidence as a whole;
(iii) arriving at a rational conclusion founded upon the evidence;
(iv) in so doing, is not called upon to act as an expert; and
(v) is not entitled to impose an onus on either party to establish a sufficient basis for payment or sufficient basis for withholding payment;[55] and
(g) the legislative scheme is such that the standard of reasons delivered by an adjudicator within the time constraints required by the SOP Act, and given the nature of the decision to be delivered in this demanding context, and by persons who are often not legally qualified, of necessity means that it falls towards the lower end of the scale.[56]
(a) it was not in dispute that the works the subject of this ground were performed;
(b) the first defendant identified the value of the work claimed, supported by:
(i) the Sagor Declaration dated 21 December 2020;[57]
(ii) the Sagor Declaration dated 6 January 2021;[58] and
(iii) a number of remittances and invoices annexed to the Sagor Declaration dated 6 January 2021 and marked DS-12;[59] and
(c) the plaintiff did not put on material to contradict the quantum of the sum claimed,
I am satisfied that the Adjudicator's assessment of the value of the claim was sufficient and not in error.
F Issue 4 - Did the Adjudicator err by finding that the works were at completion and that therefore a valid reference date had arisen under the Contract
(a) 'Completion' within the meaning of the Contract did not require there to be zero defects and/or incomplete work items. Rather, under the Contract, 'Completion' required that the Works are complete to the point where the builder notifies that the Works have been completed in accordance with the Plans and Specifications, and delivers a Certificate of Occupancy. Separately, in relation to defects and/or incomplete work, the builder is obliged to comply with the terms of cls 17.1 and 17.5-17.7;[64] and
(b) accordingly, the service of Certificates of Occupancy on 9 July 2020, a Notice of Completion on 22 July 2020 and a Notice of Completion of Items on 5 November 2020 by the first defendant was collectively sufficient to constitute 'Completion'.[65]
(a) Certificates of Occupancy were issued on 9 July 2020;
(b) the first defendant issued a Notice of Completion of Items under cl 17.1 on 22 July 2020, advising that the Works achieved Completion on 20 July 2020;
(c) a contractual final inspection took place on 31 July 2020;
(d) the plaintiff provided the Defects List Report to the first defendant under cl 17.5 on 10 August 2020;
(e) the first defendant subsequently returned to site and addressed each defect. This was and continues to be disputed by the plaintiff;
(f) the first defendant notified the plaintiff that it had completed the defects on 5 November 2020;
(g) the plaintiff took possession of the site on 12 November 2020; and
(h) on 27 November 2020, the first defendant issued the Payment Claim the subject of this proceeding.
(a) trivial failures of failures born of impracticalities do not preclude effective and satisfactory completion;[67] and
(b) in any event, the fact that the plaintiff has taken possession of the Property means that it has waived any condition precedent requiring entire performance. It relies only on the decisions of Hoenig v Isaacs[68] and Murphy Corporation Ltd v Acumen Design and Development (Qld) Pty Ltd[69] in support of this submission.
Completion - when the Works to be carried out under the Contract:
(a) was satisfied Completion had been achieved by reference to the following documents provided by the first defendant to the plaintiff: Certificates of Occupancy on 9 July 2020; a Notice of Completion on 22 July 2020; and a Notice of Completion of Items on 5 November 2020;[74] and
(b) failed to have regard to whether the Works had in fact been completed in accordance with the Plans and Specifications.
I do further observe that for the Court to determine that there was 'clear proof leading unmistakably to [the] conclusion'[77] that there had been no act of repudiation, it would have been necessary to adopt the ordinary procedure for determining such questions, being the exchange of pleadings, full evidence in admissible form and cross‑examination.[78]
The adoption of such a process 'would drive a horse and cart (or perhaps a B-double) through the legislative scheme',[79] and neither party sought to do so. If a party does apply to conduct a fully blown trial in a future application under this Act, it may be necessary for the Court to consider whether, in exercising its residuary discretion in a judicial review proceeding, it should refuse such an application.[80]
(c) the Buildspect Report, relied on by the plaintiff; and
(d) the Jeffery Report, relied on by the first defendant.
(a) on 16 March 2020, to provide a list of defects;
(b) on 31 July 2020, to determine if the Works had achieved Completion and whether the building Works were compliant;
(c) on 20 November 2020, to assess defective and incomplete works and assess the completion of identified defects noted on 31 July 2021;
(d) on 16 December 2020, to review the unit three garage store room; and
(e) on 28 December 2020, to update the report with recent photographs.
(a) the backfill to the retaining wall: item 1.1 in the Defect List Report and item 1 in the Buildspect Report;
(b) the entrance floor heights: item 1.7 in the Defect List Report and item 4 in the Buildspect Report;
(c) the foundation to the letter box: item 1.8 in the Defect List Report and item 5 in the Buildspect Report;
(d) the construction of steps in the concrete pathway: item 1.11 in the Defect List Report and item 2 in the Buildspect Report;
(e) blocked weepholes in masonry: item 1.17 in the Defect List Report and item 9 in the Buildspect Report;
(f) installation of external weatherboards cladding without a gap to the transition flashing: item 1.36 in the Defect List Report and item 14 in the Buildspect Report;
(g) the installation of the feature aluminium pickets: item 1.42 in the Defect List Report and item 16 in the Buildspect Report;
(h) the transition flashing between blockwork and weatherboard cladding is proud of the wall face: item 1.51 in the Defect List Report and item 19 in the Buildspect Report;
(i) pressure flashing installation: item 1.57 in the Defect List Report and item 21 in the Buildspect Report;
(j) overflows to balconies: item 1.119 in the Defect List Report and item 27 in the Buildspect Report.
(a) item 2 - the construction of steps to the path at the eastern elevation was assessed as failing to comply with the Lexicon Engineering civil drawing 1522D which indicated a sloped path;
(b) item 3 - the omission of Aerofoam at pipe penetrations in concrete paving was assessed as failing to comply with Lexicon Engineering drawing 1522, sheet 13 dated 31 July 2015;
(c) item 16 - the installation of the feature aluminium pickets to the western elevation failed to comply with the LRW Design building permit drawing number A10 because the pickets had not been installed straight and level at their lower edge; and
(d) item 53 - a bulkhead and storage room has been constructed to the rear of the garages to all units contrary to the LRW Design drawing A04 revision B which details no bulkhead or storeroom.
(a) item 15 - air conditioning pipe work penetrations in wall cladding had been sealed with silicone only. Further Mr Holt observed that the pipework had been wrapped in electrical tape through the penetration, and that the silicone had adhered to the electrical tape which was deteriorating and separating from the pipe work. Mr Holt assessed this finish as failing to comply with the weatherproofing required under the BCA; and
(b) item 19 - Mr Holt records his observations that:
(i) transition flashings between the blockwork wall, the rendered EPS wall and the weather board cladding are up to 20mm proud of the wall surface and have gaps into wall cavities to the southern elevation; and
(ii) windows to the southern elevation of unit 1 and the eastern elevation of all units have been installed at a height that does not allow for an upstand in the transition flashing. He opined that the omission of an upstand to the transition flashing is likely to allow the ingress of water.
Even if entire performance was a condition precedent, nevertheless the result would be the same, because I think the condition was waived. It is always open to a party to waive a condition which is inserted for his benefit. What amounts to a waiver depends on the circumstances. If this was an entire contract, then, when the plaintiff tendered the work to the defendant as being a fulfilment of the contract, the defendant could have refused to accept it until the defects were made good, in which case he would not have been liable for the balance of the price until they were made good. But he did not refuse to accept the work. On the contrary, he entered into possession of the flat and used the furniture as his own, including the defective items. That was a clear waiver of the condition precedent.
Ordinarily the best evidence that such a stage has or has not been reached will be a certification from the contract Superintendent. But that does not mean, in my view, that in the absence of a certification for practical completion the contractor can never prove in legal proceedings that such a stage had in fact been reached. One situation where the contractor could prove that such a stage had been attained in the absence of a certification would be where the employer had taken possession of the works as completed on the express or implied understanding that a stage of practical completion had been reached and then used them for the intended purpose; that would particularly be so where the intended use involved opening the works to the public for the profit of the employer. I find that that is what happened here. The first defendant impliedly represented to the plaintiff that the exhibit had been substantially completed as at 17th December, 1989 and was ready for opening to the public. The plaintiff, through its numerous representatives (including Ellick), who inspected on 17th December, accepted the exhibit as presented, took possession of it, and thereafter immediately put it to its intended public use. There was at that time no reservation by the plaintiff of any rights, nor did it then raise any issue that the exhibit had not been completed in accordance with the contract. It was obvious to all that some minor work (for example, the fibre optics) still had to be done, but that did not alter the fact that there had then been substantial compliance with the contractual requirements. Certainly there had been substantial compliance in accordance with the test applied in Hoenig v Isaacs [1952] EWCA Civ 6; (1952) 1 TLR 1360; the reasoning in that case appears to be particularly relevant here because of the rather indefinite nature of the contractual obligations imposed on the first defendant.
The findings of fact I have made and outlined above establish, in my view, that Ellick only directed his mind to the question of practical completion after the plaintiff, and Murphy in particular, had expressed serious disappointment with the public response to the exhibit. Notwithstanding the fact that people such as Gair and the second defendant raised questions as to the sufficiency and accuracy of the advertising material, and questions as to the adequacy of the access to the first floor level, those matters were not specifically addressed by the plaintiff early in 1990; rather the plaintiff sought to put the responsibility for the apparent poor public response back on the first defendant by asserting that the project had not been properly completed.
Against that background I accept the argument of the defendants that by accepting the project on 17th December, 1989, opening the exhibit to the public on that date, thereafter operating it and receiving revenue therefrom, the plaintiff waived any right it had to take the point that the Superintendent had not in fact issued a certificate of practical completion as at 17th December. Even if the plaintiff did not so waive that right by its conduct on 17 December 1989, there was, in my view, a waiver once it failed to raise the issue of practical completion within a reasonable time after that date. The question of practical completion was not raised at the first control meeting, and was not referred to at all until Ellick mentioned it in passing in his letter of 31st January.
(a) initially refused to do so on the basis that the Works were defective and had not been completed; and
(b) was compelled to do so because the Property had been left by the first defendant unlocked, unsecure and the defendant had indicated it would not be returning.
(b) the first defendant pay the plaintiff's costs of and incidental to this proceeding, to be taxed on a standard basis if not agreed.
[1] Affidavit of Mr Zamir affirmed on 22 March 2021 at [46] 2080 of the Court Book.
[3] DBDRV Report dated 10 December 2020 at 124 of the Court Book.
[4] I refer to the face of the correspondence itself and the Adjudication Determination at [110.19] 2017 of the Court Book (Adjudication Determination).
[5] Adjudication Determination at [177]-[186] 2042-3 of the Court Book.
[9] Ibid [105] 2016 of the Court Book.
[10] Ibid [106] 2016 of the Court Book.
[11] Ibid [107] 2016 of the Court Book.
[12] [2020] VSC 414 (Watpac).
[13] Ibid [39]-[40] (Riordan J), citing R v Marshall; Ex parte Baranor Nominees Pty Ltd [1986] VicRp 2; [1986] VR 19, 32-3 (Brooking J) (Marshall).
[14] Watpac (n 12), [39] (Riordan J), citing Marshall (n 13) 32-3 (Brooking J); R v Foster; Ex parte Commonwealth Life (Amalgamated) Assurances Ltd [1952] HCA 10; (1952) 85 CLR 138, 153 (Dixon, Fullagar and Kitto JJ).
[16] Watpac (n 12) [39] (Riordan J), citing R v Yaldwyn (1899) 9 QLJ 242, 244 (Griffiths CJ); R v Blakeley; Ex parte Association of Architects, Engineers, Surveyors and Draughtsmen of Australia [1950] HCA 40; (1950) 82 CLR 54, 92 (Fullagar J).
[17] Golets v Southbourne Homes Pty Ltd [2017] VSC 705, [42] (Vickery J) (Golets).
[18] BWay Group v Pasiopolous [2019] VCC 691, [26]-[29] (Marks J) (Bway).
[19] Director of Housing (Vic) v Structx Pty Ltd [2011] VSC 410, [28] (Vickery J) (Structx), quoted in Vinson v Neerim Properties Developments Pty Ltd [2016] VSC 321, [32] (Vickery J).
[21] Promax Building Developments Pty Ltd v PCarol & Co Pty Ltd [2017] VCC 495, [27] (Anderson J), quoted in Golets (n 17) [40] (Vickery J).
[23] Ibid [37] (Vickery J), quoting United Dominions Corp Ltd v Brian Pty Ltd [1980] HCA 16; (1980) 144 CLR 1, 15 (Dawson J) (United Dominions Corp).
[24] [2018] VSC 14; (2018) 54 VR 721, 749 [102(d)] (Ian Street Developer), quoting United Dominions Corp (n 23) 15 (Dawson J) and Golets (n 17) [37] (Vickery J).
[28] Ibid [128] 2023 of the Court Book.
[30] Ibid [129], [132] 2023 of the Court Book.
[31] Ibid [130] 2023 of the Court Book. I understand the reference to the plaintiff's report to DBDRV 'dated 10 December 2020' to be a reference to the plaintiff's updated list of defective or incomplete works sent to DBDRV on 19 November 2020 referred to by the Adjudicator at paragraph 125.5 of the Adjudication Determination.
[33] Ibid [135] 2024 of the Court Book. I note that the Adjudicator refers to a DBDRV report dated 11 December 2020. I understand that to be a reference to the DBDRV report dated 10 December 2020.
[34] Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152, [20] (Barrett J), quoted in Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2010] QSC 95, [12] (Martin J).
[35] Laing O'Rourke Australia Construction Pty Ltd v H & M Engineering & Construction Pty Ltd [2010] NSWSC 818, [38]-[39] (McDougall J) (Laing O'Rourke); Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410, [35(e)] (Bond J).
[37] Southern Cross Electrical Engineering v Steve Magill Earthmoving [2018] NSWSC 1027, [34] (McDougall J).
[38] Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd [2018] NSWCA 107; (2018) 97 NSWLR 773, 777 [17] (Basten JA) (Cockram), cited in Iskra v MMIR Pty Ltd [2019] NSWCA 126, [49] (Gleeson JA) (Iskra).
[39] Cockram (n 38) 777 [17] (Basten JA); Iskra (n 38) [49] (Gleeson JA). See also 1155 Nepean Highway Pty Ltd v Promax Buildings Pty Ltd [2020] VSCA 253, [50] (Beach, Kyrou and McLeish JJA).
[40] Grocon Constructors Pty Ltd v Planit Cocciardi Joint Venture (No 2) [2009] VSC 426; (2009) 26 VR 172, 206 [126] (Vickery J) (Grocon).
[42] Health Care Complaints Commission v Sultan [2018] NSWCA 303, [166] (Meagher JA) (Health Care Complaints Commission).
[43] Ibid, citing Abebe v The Commonwealth [1999] HCA 14; (1999) 197 CLR 510.
[45] [2020] VSC 557, [66] (Stynes J) (Citi-Con).
[46] [2015] VSC 631, [76]-[108] (Vickery J) (SSC Plenty Road).
[52] Citi-Con (n 45) [66(e)] (Stynes J)]. The time within which an adjudicator is to deliver a determination (including in relation to claimable variations) is strictly limited, namely within 10 business days of the adjudicator accepting nomination or within a shortly extended period of 15 days if agreed to by the claimant (SOP Act s 22(4)).
[57] Statutory Declaration of Mr Sagor dated 21 December 2020 at [24]-[25] 3175 of the Court Book.
[60] Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340, 345 [2] (Southern Han).
[64] Ibid [79] 2001 of the Court Book.
[65] Ibid [80] 2001 of the Court Book.
[66] Ibid [195] 2044 of the Court Book.
[67] Cardona v Brown [2012] VSCA 174; (2012) 35 VR 538, 556 [74] (Tate JA) (Cardona).
[68] [1952] EWCA Civ 6; [1952] 2 All ER 176 (Somervell, Denning and Romer LJJ) (Hoenig).
[69] (1995) 11 BCL 274 (Williams J) (Murphy).
[70] Clause 17.1 and the definition of 'Final Claim' in cl 1 of Contract.
[71] Transcript at T92.30-93.20 and T94.25-27.
[75] Grocon (n 40) [104] (Vickery J), quoting Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163, 179-80.
[78] Castle Constructions Pty Ltd v N & R Younis Plumbing Pty Ltd [2019] NSWSC 225, [89] (Parker J).
[79] Abergeldie Contractors Pty Ltd v Fairfield City Council [2017] NSWCA 113, [47] (Basten JA, with whom Beazley ACJ and Meagher JA agreed) with reference to the prospect of the Court being required to consider when practical completion had been achieved, rather than when an appropriate certificate had been issued.
[80] An invalid administrative decision may be treated as valid if a court refuses to set it aside for a discretionary reason: Leung v Minister for Immigration and Multicultural Affairs [1997] FCA 1313; (1997) 79 FCR 400, 413. The prospect of a court refusing relief on discretionary grounds in a valid claim against a decision of an adjudicator was noted but not further considered by Basten JA in Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393, 417 [104].
Saath Pty Ltd
Seascape Constructions Pty Ltd & Anor [2021] VSC 358
BUILDING CONTRACTS - Trial - Judicial review - Adjudication - Whether plaintiff is in the business of building residences - Whether Adjudicator considered the first defendant's submissions and related material - Whether Adjudicator properly valued the payment claim - Whether works were at completion and a corresponding reference date arose - Building and Construction Industry Security of Payment Act 2002 (Vic) ss 7(2)(b), 9(2) and 23(2) - Watpac Constructions Pty Ltd v Collins & Graham Mechanical Pty Ltd [2020] VSC 414, applied - R v Marshall; Ex parte Baranor Nominees Pty Ltd [1986] VicRp 2; [1986] VR 19, applied - Golets v Southbourne Homes Pty Ltd [2017] VSC 705, applied - Republic of Turkey v Mackie Pty Ltd [2012] VSC 309, applied - BWay Group v Pasiopolous [2019] VCC 691, applied - Director of Housing (Vic) v Structx Pty Ltd [2011] VSC 410, applied - Ian Street Developer Pty Ltd v Arrow International Pty Ltd [2018] VSC 14; (2018) 54 VR 721, applied - Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152, applied - Laing O'Rourke Australia Construction Pty Ltd v H & M Engineering & Construction Pty Ltd [2010] NSWSC 818, applied - Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410, applied - Southern Cross Electrical Engineering v Steve Magill Earthmoving [2018] NSWSC 1027, applied - Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd [2018] NSWCA 107; (2018) 97 NSWLR 773, applied - Iskra v MMIR Pty Ltd [2019] NSWCA 126, applied - Grocon Constructors Pty Ltd v Planit Cocciardi Joint Venture (No 2) [2009] VSC 426; (2009) 26 VR 172, applied - Health Care Complaints Commission v Sultan [2018] NSWCA 303, applied - SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631, applied - Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340, applied - Cardona v Brown [2012] VSCA 174; (2012) 35 VR 538, applied - Hoenig v Isaacs [1952] EWCA Civ 6; [1952] 2 All ER 176, distinguished - Murphy Corporation Ltd v Acumen Design and Development (Qld) Pty Ltd (1995) 11 BCL 274, distinguished - Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163, applied.
(2018) 54 VR 721
(2018) 97 NSWLR 773
(2009) 26 VR 172
(2016) 260 CLR 340
(2012) 35 VR 538
(1995) 184 CLR 163
(1952) 85 CLR 138
(1950) 82 CLR 54
(1980) 144 CLR 1
(1999) 197 CLR 510
(1997) 79 FCR 400
(2010) 78 NSWLR 393