Iskra v MMIR Pty Limited
[2019] NSWCA 126
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2019-05-20
Before
Bathurst CJ, Gleeson JA, Payne JA, Parker J
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Background
- In about mid-2016, the owner engaged the builder to perform construction work for the upgrade, refurbishment and fit out of the restaurant and function centre at Crown Street, Wollongong. On 4 September 2018, the builder served a payment claim under the SOP Act, s 13(1) for $165,829.95. The claim consisted of a two-page invoice and supporting documents. The progress claim plus GST totalled $615,829.95 for 15 items of work and included a six per cent "project management fee" of $31,689.36. The invoice allowed a credit of $450,000 for amounts already paid, leaving the sum outstanding of $165,829.95.
- In response, the owner, on 14 September 2018, served a payment schedule under s 14(1) certifying $nil as the amount it proposed to pay. This was justified on four bases: (a) the works were not undertaken on the basis claimed by the builder; (b) payment had already been made for some amounts claimed; (c) the claim had not been "progressed"; and, (d) the owner was entitled to a set-off in relation to the works.
- On 27 September 2018, the builder applied for adjudication of its payment claim under s 17(1). Its application asserted that the contract was an oral "do and charge" contract whereby the builder, as the head contractor, received instructions for the works proposed by the owner from time to time and directed the trades and suppliers to perform the works as instructed. The builder also performed some works.
- On 8 October 2018, the owner lodged its adjudication response under s 20 in which it asserted that the construction contract arose from its acceptance of a written quote provided by the builder on about 3 August 2016 for a price of $225,000 (the quote). The owner admitted having paid the builder $450,000 for works performed and stated that it had paid a further $514,200 for further works performed by another builder.
- With respect to the amount of the payment claim, the owner asserted that it had not had the opportunity to properly analyse the builder's claim, but the amounts claimed may relate to payments not related to the building works and/or are grossly excessive, and the owner will require the obtaining of expert advice and opinion to properly support its response. In addition, the owner asserted that, in making the claim, the builder had either fraudulently claimed, duplicated his claims, inflated his claims, or acted negligently in carrying out the building works.