Release of Security
47 As I have indicated above, the August Payment Claim included a claim for $930,000 described as "Completion Security Release". In the Determination, the Adjudicator referred to Dickson having acknowledged in the adjudication response that it had had recourse to two performance bonds in the sum of $930,000 each (at [22]), but the Adjudicator found that Dickson was not entitled to claim liquidated damages and that the Works had reached Completion by 30 June 2023 and accordingly Dickson was not entitled to have recourse to the performance bonds (at [24]). The Adjudicator accepted Core's position that the cash value of the performance bonds held by Dickson was to be treated as retention money held by Dickson as Security, and thus allowed for return of $930,000, being 50% of the cash value of the performance bonds, leaving Dickson with the remaining 50% to be held as retention for Security (at [35]).
48 Dickson submits that Core was not able to claim for the return of those monies as they never had the character of monies held by Dickson under the Contract which was due for release, and thus were not capable of being claimed under s 15(3)(b) of the Act. Dickson submits that s 15(3)(b) is directed to retention monies which the claimant asserts are due for release, citing Ceerose Pty Ltd v A-Civil Aust Pty Ltd (No 2) [2023] NSWSC 345 at [39] (Richmond J). Dickson submits that a retention is not the same as a performance bond, in that a retention is comprised of amounts withheld from each progress payment due to the contractor until the amount retained reaches a certain cap as agreed between the parties, and is thus a portion of the contract sum payable for construction work which has been retained as security. A performance bond, by contrast, provides the principal with the right to call on a specified amount, and is not comprised of amounts included in the Contract Sum. In the present case, Dickson submits that the Security under the Contract is in addition to the defined Contract Sum, which is the amount that is being paid as consideration for completing the Works. Dickson submits that the performance bonds are therefore not payment for construction work; rather, they are provided by Core for all of Core's liabilities and obligations under the Contract, including the obligation to pay liquidated damages and to claim an indemnity for damage caused by Core. Dickson submits that that interpretation is consistent with the reasoning of White J concerning the reinstatement of the security in Patterson Building Group Pty Ltd v Holroyd City Council [2013] NSWSC 1484 at [73]-[74]. Further, Dickson submits that the monies received from Dickson's call upon the security bonds issued by Vero Insurance were never monies held by Dickson under the Contract, but were monies received by Dickson from Vero Insurance in satisfaction of Core's obligations, and thus fell outside s 15(3)(b). Accordingly, Dickson submits that the Determination should be set aside to the extent of $930,000 plus GST (assuming no other grounds of review are successful).
49 Core submits that the relevant question (as to whether the money received by Dickson from the bonds provided under cl 16 of the Contract should be found to be an amount "held under the construction contract by the respondent and that the claimant claims is due for release" as contemplated by s 15(3)(b)) was a matter for the Adjudicator to determine. Core submits that it is not a question for this Court to determine, as this is not a merits review. Core submits that Dickson's submissions wholly ignore that an error in the interpretation of the Act on the part of the Adjudicator (for which Dickson contends) does not prevent a determination from being valid, citing Downer Construction (Australia) Pty Ltd v Energy Australia at [87] (Giles JA, with whom Santow and Tobias JJA agreed).
50 It is now clear that the scheme established by the Act excludes the jurisdiction of the Court to make an order in the nature of certiorari to quash an adjudicator's determination for non-jurisdictional error of law on the face of the record: Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd at [35] (Kiefel CJ, Bell, Keane, Nettle and Gordon JJ), [55] (Gageler J), and [108] (Edelman J). In respect of the Act, that is also the effect of s 43(1), although there was no corresponding provision in the NSW counterpart legislation considered by the High Court in that case. I note that, although s 43(2) and (3) allow for leave to appeal on a question of law, that has not been pursued by Dickson in these proceedings. The issue therefore is whether the element of s 15(3)(b) that an amount is "held under the construction contract by the respondent" is a precondition to the jurisdiction of an adjudicator to determine that any such amount is payable.
51 As I have indicated above, in Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd at [47], the High Court referred to the term "jurisdictional fact" as a label for a criterion, satisfaction of which enlivens the power of a decision-maker, and stated that such usage was not inappropriate and served to emphasise that the existence or non-existence of the particular matter was not within the jurisdiction of the decision-maker to determine. However, the High Court said that that was the limit of its utility, and that the terminology of "jurisdictional fact" was no more than a label for the conclusion for which the appellant in that case contended, and that appending that label to the conclusion added nothing to the requisite antecedent statutory analysis.
52 The High Court then engaged with the statutory analysis required to resolve the competing constructions of the NSW counterpart to s 15(1) of the Act. In the course of that analysis, the High Court expressed the following views at [59]-[60], which I paraphrase as follows. The High Court said that within Pt 2 of the NSW Legislation (corresponding to Pt 3 of the Act) an important distinction is drawn between a progress payment to which a person is entitled and the amount of the progress payment to which that person is entitled. Section 8(1) (corresponding to s 10(1) of the Act) makes clear that a person who meets the description of a person who has undertaken to carry out construction work or supply related goods and services under a construction contract is immediately by force of that provision "entitled to a progress payment" on and from each reference date under the construction contract. By contrast, s 9 (corresponding to s 11 of the Act) makes clear that the amount of a progress payment to which the person is so entitled is not fixed by force of that section but is to be ascertained in the manner prescribed by that section, and quantifies the amount of the progress payment to which a person is entitled by force of s 8(1) (corresponding to s 10(1) of the Act).
53 I note at this point that there is a difference in the language between the Act and its NSW counterpart in that in s 11 of the Act, the amount of a progress payment to which a person is entitled in relation to a construction contract "is" the amount worked out under the contract, whereas in s 9 of the NSW counterpart the word "is" is replaced by "is to be". The High Court treated the expression "is to be" in the NSW provision as being cast in the future tense, in contrast to the use of the present tense in s 8(1) of the NSW Legislation (corresponding to s 10(1) of the Act). Accordingly, it would appear that the contrast drawn by the High Court between the use of the present and future tense in the two provisions respectively in the NSW Legislation may not apply to ss 10(1) and 11 of the Act, although it might be observed that the opening words of both s 11 in the Act and s 9 in the NSW Legislation use the present tense in the expression "is entitled". In my view, that difference in language does not affect the application of the High Court's conclusion at [59], namely that s 9 of the NSW Legislation anticipates the procedure for recovery of a progress payment, to s 11 of the Act. Although s 11 of the Act is expressed in the present tense, it still anticipates the procedure for recovery set out in Pt 4 of the Act. Part 3 of the Act (like Pt 2 of its NSW counterpart) deals only with the right to progress payments, which is a step towards the exercise of the procedure for recovering progress payments laid down in Pt 4 of the Act (corresponding to Pt 3 in its NSW counterpart). In my view, the difference in language between the word "is" in s 11 of the Act and "is to be" in s 9 of its NSW counterpart is far too subtle to affect the application of the High Court's ultimate conclusion that under the procedure for recovery of a progress payment, in the event of a dispute between a claimant and a respondent, the ascertainment of the amount, if any, of the progress payment to be recovered is committed to the jurisdiction of an adjudicator to determine under s 22 of the NSW Legislation (corresponding to s 24 of the Act).
54 The High Court then dealt with the description in s 13(1) of the NSW Legislation (corresponding to s 15(1) of the Act) of a person who is able to make a payment claim so as to trigger the procedure for recovery set out in Pt 3 (or Pt 4 of the Act). I note that the description of that person in s 15(1) of the Act is different from that in s 13(1) of its NSW counterpart, but the common language between the two is the reference to a person who "is or who claims to be entitled to a progress payment". As to that language, the High Court said that that description recognises, consistently with s 9 (corresponding to s 11 of the Act), that the amount of the progress payment to which that person is entitled might ultimately be ascertained, according to the procedure set out in Pt 3 (or Pt 4 of the Act), to be less than the amount that the person claims to be due, and might even be ascertained according to that procedure to be nothing.
55 The High Court concluded from that analysis that the description in s 13(1) (corresponding to s 15(1) of the Act) of a person referred to in s 8(1) (or s 10(1) of the Act) is of a person whom s 8(1) makes entitled to a progress payment, and s 8(1) makes a person who has undertaken to carry out construction work or supply related goods and services under a construction contract entitled to a progress payment only on and from each reference date under the construction contract: [61]. In that way, the High Court said that the existence of a reference date under a construction contract within the meaning of s 8(1) is a precondition to the making of a valid payment claim under s 13(1): [61].
56 For present purposes, the importance of that reasoning is the distinction drawn between a progress payment to which a person is entitled, and the amount of the progress payment to which that person is entitled. As the High Court said at [59], in the event of a dispute between a claimant and a respondent, the ascertainment of the amount, if any, of the progress payment to be recovered is committed to the jurisdiction of an adjudicator to determine under s 22 of the NSW Legislation (corresponding to s 24 of the Act). That is, the ascertainment of the amount in question is not a precondition to the exercise of jurisdiction by the adjudicator, nor would it be appropriate to use the label "jurisdictional fact" to describe any of the elements of the exercise of ascertaining the amount. Section 15(3) is concerned with what may be included in the claimed amount. The first element, set out in para (a) of that provision, is any amount that the respondent is liable to pay the claimant under s 29(3), being a claim for loss or expense incurred in exercising the right to suspend carrying out construction work or supplying related goods and services. That is plainly a matter for the adjudicator to determine in the event of a dispute. The second element, set out in para (b) of the provision, is any amount that is held under the construction contract by the respondent and that the claimant claims is due for release. That too is a matter for the adjudicator to determine in the event of a dispute, because it concerns the amount to which the claimant is entitled. The issues raised by that paragraph may well include questions of law, but they are not jurisdictional questions to be determined by the Court. Accordingly, it was a matter for the adjudicator to determine the application of s 15(3)(b) in the circumstances of the present case. Accordingly, I reject Dickson's submission that the elements of s 15(3)(b) are for this Court to determine as a precondition to the exercise of jurisdiction by the Adjudicator.