[2022] VSC 5
General information, not legal advice.
Supreme Court of Victoria
2022-01-17
Digby J
Original judgment source is linked above.
MISLEADING AND DECEPTIVE CONDUCT - Australian Consumer Law (ACL) ss 236 and 237 - ACL ss 18 and 29(1)(g) - Deemed authority, s 84(2) of the Competition and Consumer Act 2010 (Cth) (CCA); s 29(1)(g) ACL - Contravening conduct including as to performance characteristics, use and benefits of subject systems - Contravening conduct pursuant to s 243 of the CCA - Declarations that contracts in relation to supply and service are void - Orders setting aside contracts.
DAMAGES - Claim for loss of opportunity damages/compensation and Counterclaims.
DAMAGES - Compensation pursuant to s 237 of the CCA - Damages pursuant to s 236 of the CCA - Limitation of liability clauses - Rights of indemnity.
NEGLIGENCE - Existence of duty of care - Breach of duty of care in relation to the commissioning of subject systems.
CONTRACT - Breach of terms - Breach of warranty - Damages.
1 The plaintiff, ProLearn Corporation Pty Ltd (ProLearn), is a company incorporated pursuant to the Corporations Act 2001 (Cth) (Corporations Act) and engaged in the business of operating a telemarketing call centre marketing, vocational education and training programs. ProLearn was incorporated on 8 December 2004.
2 The first defendant, Kytec Pty Ltd (Kytec), is a company incorporated pursuant to the Corporations Act.
3 Kytec is an Information Communication and Technology (ICT) firm and is engaged in the business of providing and installing networking, security and communications solutions.
4 Kytec's core business is the design, deployment and support of Cisco-based solutions. Approximately 60 percent of Kytec's business is related to 'collaboration solutions' which include telephone, video conferencing and contact centre solutions. A 'contact centre solution' is a platform that enables efficient contact between an employee's customer-facing staff members, commonly referred to as 'agents', and the company's customers.
5 Kytec's target market is the 'mid-market', which it defines as organisations with 50 to 3,000 users of the subject system.
6 Kytec employs approximately 35 staff, of whom approximately 25 are engineering staff. Due to the nature of Kytec's business, the majority of the technical staff are 'level 3' engineers. The term 'level 3' is a widely recognised industry term that refers to the most senior engineers in a specific technology.
7 The second defendant, Telstra Corporation Ltd (Telstra), is a company incorporated pursuant to the Corporations Act. Telstra is an Australian telecommunications company which builds and operates telecommunications networks and markets voice, mobile, internet access, pay television and other products and services.
8 In early 2011, ProLearn commenced a digital marketing business with its primary focus being the vocational education and training (VET) sector.
9 Up until the end of 2016, the primary focus of ProLearn's business was the provision of digital and telemarketing services to the Victorian education sector. This part of the ProLearn business came to an end on 31 December 2016, due to legislative changes that came into effect on 1 January 2017.
10 By a Telstra Dealership Agreement between Telstra and Kytec entered into in or about mid 2010, Telstra appointed Kytec as a dealer to promote Telstra's telecommunications services subject to the terms and conditions contained therein (the Telstra Dealership Agreement).
11 In early 2015 ProLearn contacted Telstra and advised that it wished to upgrade its current call centre telephone system. Telstra referred ProLearn to Kytec. Subsequently on 27 April 2015, following discussions between Kytec and ProLearn, ProLearn entered into the following contracts with Telstra:
(a) An agreement titled 'Telstra Business Systems - Corporate Services Agreement' (the Equipment and Services Agreement);
(b) An agreement for the supply of telephone services by Telstra to ProLearn for a term of 36 months pursuant to which ProLearn agreed to pay Telstra a minimum sum of $35,000 per month (the Telephone Contract);
(c) A contract with Telstra for the provision of data for a term of 36 months (the Data Contract).
12 On 7 October 2015, ProLearn also entered into a contract with Kytec entitled Managed Service Agreement (the Kytec Contract).
13 By its Amended Statement of Claim dated 12 September 2018, ProLearn sues Kytec and Telstra for damages and other relief in relation to major alleged failings in a telephone system supplied to ProLearn for use in its telemarketing business (referred to as the NTS or the Solution).
14 ProLearn's claims against Kytec are in substance for:
(a) damages and/or compensation under ss 236 and/or 237 of the Australian Consumer Law (the ACL) (Schedule 2 to the Competition & Consumer Act 2010 (Cth) (the CCA)), arising as a result of misleading or deceptive conduct by Kytec contrary to s 18 of the ACL;
(b) orders that by reason of Kytec's misleading or deceptive conduct, a managed services agreement entered into between ProLearn and Kytec, on or about 7 October 2015 the Kytec Contract[1] is void and of no effect and/or is liable to be set aside with consequential orders;
(c) damages in negligence.
15 It is notable that ProLearn does not prosecute a breach of contract case against Kytec.
16 ProLearn's claims against Telstra are in substance for:
(a) damages and/or compensation under ss 236 and/or 237 of the ACL arising as a result of misleading or deceptive conduct contrary to s 18 of the ACL;
(b) orders that by reason of Telstra's misleading or deceptive conduct, certain contracts entered into between ProLearn and Telstra are void and of no effect and/or are liable to be set aside with consequential orders;
(c) damages for breach of cl 1.1 and/or cl 5.3 of Schedule 2 to the Equipment and Services Agreement.
17 ProLearn also claims damages against Kytec and Telstra on the basis that, in representing that the Solution was appropriate for ProLearn's requirements, both those companies made false or misleading representations with respect to the performance characteristics, use or benefits of the Solution, and thereby contravened s 29(1)(g) of the ACL.
18 By its Defence and Counterclaim dated 12 November 2018, Kytec denies ProLearn's claim, and counterclaims against ProLearn, seeking payment of contractual debts totalling $10,340. In the event that Kytec is liable to ProLearn, Kytec submits that it is entitled to have the amount of the counterclaim set off against amounts owing to ProLearn, in accordance with r 13.14 of the Supreme Court (General Civil Procedure) Rules 2015 (the Rules).
19 By its Defence and Counterclaim dated 23 October 2018, Telstra denies ProLearn's claim, and counterclaims against ProLearn, seeking payment of debts totalling $516,313, owing under contracts for the supply of data and telephone calls, and other charges.
20 Telstra also counterclaims against Kytec, seeking indemnity for any liability which it may have to ProLearn, pursuant to the terms of the Telstra Dealership Agreement.
21 In support of the relief sought, ProLearn relied on the following material:
(i) Opening Submissions dated 22 May 2019 (ProLearn Opening Submissions);
(ii) Closing Submissions dated 18 June 2019 (ProLearn Closing Submissions); and
(iii) Closing Reply Submissions dated 21 June 2019 (ProLearn Reply Submissions).
(e) At trial, ProLearn adduced evidence from Vicki Tutungi and Doris Humunicki, shareholders in and the proprietors of the plaintiff, and Michael Smith.
(f) ProLearn also filed a Witness Statement dated 5 December 2018, containing the Expert Report of Professor Francis Buttle dated 30 October 2018 (the Buttle Report). During the trial, counsel for ProLearn advised that, for medical reasons, Dr Buttle was unable to attend the trial and give evidence.[7] The Buttle Report was ultimately not tendered as evidence.
22 In support of its case, Kytec relied on the following material:
(i) Opening Submissions dated 22 May 2019 (Kytec Opening Submissions);
(ii) Closing Submissions dated 19 June 2019 (Kytec Closing Submissions); and
(iii) Closing Reply Submissions dated 21 June 2019 (Kytec Reply Submissions).
(d) At trial, Kytec adduced evidence from David Okulicz and Michael Green.
23 In support of its case, Telstra relied on the following material:
(c) Joint Expert Report of Michael Smith and Dawna Wright dated 14 May 2019.[15]
(d) Submissions:
(i) Opening Submissions dated 24 May 2019 (Telstra Opening Submissions);
(ii) Closing Submissions dated 18 June 2019 (Telstra Closing Submissions); and
(iii) Closing Reply Submissions dated 21 June 2019 (Telstra Reply Submissions).
(e) At trial, Telstra adduced evidence from Lynette Leondaris, Andrew Asimakidis, Daniel Wolff and Dawna Wright.
24 Vicki Tutungi (Tutungi) is the Managing Director of ProLearn with over 20 years of technology development, project management and board experience. Tutungi became a Director of ProLearn on 16 June 2011 and holds one of the two issued shares in the company.
25 In her role as Managing Director, Tutungi is responsible for the management of administration, IT and property services which includes managing staff working in these areas and managing suppliers. Tutungi is also responsible for building, lease and insurance-related matters and for all contract negotiations, seeking new clients, and compliance and regulatory matters.
(a) Bachelor of Science, Major in Physiology, Monash University, 1990;
(b) Bachelor of Laws, Monash University, 1992;
(c) MBA, Melbourne Business School, 2000;
(d) Graduate Certificate in Australian Company Directors Course, Australian Institute of Company Directors, 2007.
27 In the Tutungi First Witness Statement dated,[16] Tutungi addresses ProLearn's business, its operations and systems, and ProLearn's decision to look at acquiring a more capable call centre telephone system. Tutungi deals with ProLearn's dealings with Kytec and Telstra and the lead-up to the contractual arrangements with Telstra and Kytec. Tutungi also addresses the contractual arrangements in relation to the purchase and installation of the New Telephone System (NTS), or the Solution, to be supplied by Telstra, the pre-implementation and implementation of the NTS, the problems with the NTS and the attempts to remediate and to work around those problems.
28 In the Tutungi Reply Witness Statement,[17] Tutungi addresses ProLearn's responses to the Expert Reports of Daniel Wolff, Dawna Wright and Michael Green, and analyses the contents of documents subpoenaed by Telstra. In her Reply Witness Statement, Tutungi traverses the Expert evidence of Wolff, Wright and Green, and responds to the criticism of ProLearn's case, in particular ProLearn's causation case.
29 Doris Humunicki (Humunicki) is a Director since 29 December 2006 and the Chief Executive Officer of ProLearn. As Chief Executive Officer, Humunicki is responsible for running the day-to-day operations of the ProLearn call centre, for recruiting new clients, and for accounting functions, including invoicing.
30 Humunicki holds a Certificate IV in Training and Assessment from CMC Education.
31 Humunicki has owned and operated several businesses which specialised in providing education and training services over the last 30 years, prior to her involvement with ProLearn.
32 In her witness statement dated 24 August 2018,[18] Humunicki addresses the background and implementation of the NTS, the problems and issues which soon arose with the NTS after installation, the attempts to remediate the practical operational problems with the NTS, and the formal complaints to Kytec and Telstra concerning the NTS. Humunicki also deals with the detail of the effect of the NTS dysfunctionality on ProLearn's operations and revenue, and in Annexure B to her statement Humunicki analyses ProLearn's sales between mid-2014 to November 2016, and the effect of the NTS on ProLearn's sales in the relevant months of 2015.
33 I consider Tutungi and Humunicki to be impressive and credible witnesses. I am also of the view that Tutungi exhibited a deep and detailed knowledge of the ProLearn business and of the features, functions and usability of, and problems with, the Solution. Further, I consider that Tutungi's evidence was enhanced by the degree to which her evidence was frank and she was willing to make appropriate concessions. Further, in relation to the faults and deficiencies which emerged with the Solution and the effect on ProLearn's business, I consider Tutungi's (and Humunicki's) evidence to be the most reliable and helpful evidence adduced. It is also Tutungi's and Humunicki's evidence which I consider to be the most reliable in relation to the factors which really impaired ProLearn's operations in the loss period after the Solution was commissioned.
34 Michael Smith (Smith) is a Chartered Accountant and Director of CFAS Advisory Pty Ltd.
(a) Bachelor of Business (Accounting), Royal Melbourne Institute of Technology, 1988;
(b) Graduate Certificate in Forensic Studies (Accounting), Monash University;
(c) Associate of the Institute of Chartered Accountants, ICAA; and
(d) Accredited ICAA Business Valuation Specialist.
36 In his expert report dated 11 December 2018,[19] Smith stated that by letter dated 6 September 2018,[20] ProLearn's solicitors had requested that he prepare an expert report in relation to the loss and damage suffered by ProLearn, due to a range of deficiencies and defects in the NTS provided and installed by Kytec and Telstra, including:
1. Calculate the additional sales revenue that would have been derived by ProLearn during the period September 2015 to November 2016 ('the Loss Period') on the following premise:
(a) that the number of sales that would have been effected by ProLearn per month would have been:
(i) the same number of sales as the average number of sales made per month during June 2014 to August 2015 ('the First Period');
(ii) the same number as the average number of sales made during the last 6 months of the First Period;
(iii) the same number as the average number of sales made during the last 5 months of the First Period;
(iv) the same number as the average number of sales made during the last 4 months of the First Period;
(v) the same number as the average number of sales made during the last 3 months of the First Period;
and that the average price per sale would have been the same as the average price per sale achieved during the Loss Period ('Scenario 1').
(b) that the number of sales that would have been achieved by ProLearn per month would have been:
(i) the same number of sales per month as the average number of sales per month made during the First Period from courses offered by SWSI IT, SWSI Online, the IT Institute, SWSI and The Online Institute ('the Nominated Education Providers), alternatively;
(ii) the same number as the average number of sales made from the courses offered by the Nominated Education Providers during the last 6 months of the First Period;
(iii) the same number as the average number of sales made from the courses offered by the Nominated Education Providers during the last 5 months of the First Period;
(iv) the same number as the average number of sales made from the courses offered by the Nominated Education Providers during the last 4 months of the First Period;
(v) the same number as the average number of sales made from the courses offered by the Nominated Education Providers during the last 3 months of the First Period;
and that the average price per sale would have been the same as the average price per sale achieved during the Loss Period ('Scenario 2').
2. Calculate the effect on ProLearn's earnings before interest and tax (EBIT) of the additional sales the subject of each scenario set out in question 1(a) and (b). For the purposes of this calculation assume that in order to generate the additional sales, the number of full time equivalents (FTE's) employed by ProLearn would have been such as to be the equal of the number of FTE's that generate the same number of sales in the First Period.
3. Calculate the additional sales revenue (and the corresponding EBIT) that would have been derived by ProLearn during the Loss Period:
(a) on each of the bases set out in question 1(a)( and (b);
(b) on the further basis that ProLearn would have employed additional call centre operators as follows:
(i) an additional 10 FTE's ('Scenario 3');
(ii) an additional 25 FTE's ('Scenario 4');
(iii) an additional 50 FTE's ('Scenario 5');
(iv) an additional 75 FTE's;
(v) an additional 100 FTE's;
and that each additional FTE would have effected sales per month at the following rates:
(A) at the same rate as the average rate of sales per month per FTE during the First Period;
(B) at the same rate as the average rate of sales per month per FTE during the last 6 months of the First Period;
(C) at the same rate as the average rate of sales per month per FTE during the last 5 months of the First Period;
(D) at the same rate as the average rate of sales per month per FTE during the last 4 months of the First Period;
(E) at the same rate as the average rate of sales per month per FTE during the last 3 months of the First Period.
4. Calculate the additional sales revenue and the corresponding EBIT that would have been derived by ProLearn during the Loss period if the number of calls by each FTE were increased by a factor of:
(a) 100%
(b) 200%
(c) 300%
(d) 345%
(e) 400%.
5. Make the same calculation on the further basis that ProLearn would have employed additional call centre operators as set out in paragraph 3(b)(i)-(v).
37 Smith's instructions were revised, by an email dated 6 December 2018, to the following:
1. The additional sales revenue that would have been derived by ProLearn during the Loss Period on the premise that the number of sales that would have been effected by ProLearn per month, would have been:
(vi) the same number as the average number of sales made during the last two months of the First Period;
(vii) the same number as the average number of sales made during the last month of the First Period
and that the average price per sale would have been the same as the average price per sale achieved during the Loss Period.
2. Efficiency calculations be replaced with the following calculations:
(a) an increase of 25%
(b) an increase of 50%
(c) an increase of 75%
(d) an increase of 100% (that is, double the status quo).
38 David Okulicz (Okulicz) is the Managing Director of Kytec since 2006, and has 15 years' experience in the ICT sector.
39 Prior to his involvement with Kytec, Okulicz was employed at Crox Development for five years and was tasked with a broad range of responsibilities, including mastering Cisco technologies and, specifically, the telephony platforms deployed during his employment with Crox Development.
40 In his witness statement dated 29 November 2018,[21] Okulicz addresses Kytec's involvement with ProLearn and technical aspects of the NTS and its operational issues, their causes and the efforts to deal with ProLearn's complaints about the NTS. Okulicz also deals with the parties' dealings leading up to the contracts between ProLearn and Telstra in late April 2015 and the contract between ProLearn and Kytec in October 2015.
41 I found Okulicz's evidence less reliable and less persuasive on matters in issue when compared with the evidence of ProLearn's witnesses Tutungi and Humunicki in relation to those same matters. This includes because in his evidence Okulicz often attempted to give evidence which advocated Kytec's case, and particular points in its case and similarly often strived to negate ProLearn's case and parts of its case, rather than giving frank unembellished evidence on disputed matters and evidence representing the facts without spin, in an accurate way, as I consider Tutungi and Humunicki did in their evidence.
42 In the vein described above, Okulicz on occasions took the opportunity to give evidence not dealt with in his statements filed in the proceeding or mentioned during his cross-examination, but put forward for the first time during his re-examination.
43 I also infer from Okulicz's apparent involvement in a hacking incident in relation to ProLearn's server, that he was willing to go to unacceptable lengths in what he saw as the need to impugn and combat ProLearn.
44 Okulicz's evidence also changed on occasions, as for example, it did with his evidence as to the functionality of the To Do List at the end of August 2015.[22]
45 For these reasons I regard Okulicz's evidence on disputed and uncorroborated matters in dispute as less accurate and less reliable than the evidence given by Tutungi and Humunicki in these proceedings.
46 Michael Green (Green) is an IT consultant, holds a Bachelor of Computer Science, and is a Cisco Certified Internetworking Expert (CCIE) Collaboration Emeritus #16515. Green provided expert evidence on behalf of Kytec.
47 Green has had 14 years of experience as an IT professional. Green was employed by Cisco Systems from 2004 to 2018, where he held various technical roles which focused on Cisco's contact centre products within its Unified Communications Portfolio. From 2004 to 2008, Green worked within Cisco's support organisation and focused on troubleshooting technical problems relating to contact centre products. From 2008 to 2018, Green worked within the contact centre product engineering organisation where he focused on providing technical leadership and facilitating escalated issue resolution between support, field and engineering organisations. From 2014 to 2018, Green was involved in Cisco's 'A2Q team' and was responsible for reviewing and qualifying enterprise contact centre design submissions. Green has also presented technical sessions on Cisco's contact centre products at Cisco's international conferences.
48 In his expert report dated 13 March 2019,[23] Green stated that he was engaged by Kytec's solicitors as an independent expert witness.
QUESTIONS
8. You are requested to provide a report that answers the following questions
General
8.1 Was the selection by Kytec of the Cisco PCCE solution appropriate for the ProLearn Project given the following requirements?
(a) capacity for 83 agents, to expand to 150
(b) To Do Lists (also called Personal Callback Lists) for all agents.
8.2 Can you describe Cisco's A2Q process, its purpose, and what it aims to deliver?
8.3 Based on the design documentation provided, was the set up and configuration of the Solution in line with Cisco best practice standards at that time?
8.4 How long would you expect an installer of a system similar to the Solution to be allowed to test that system prior to it going live? What impact could a shorter testing period have on the long term operation of such a system?
8.5 Would you expect an operator of a system like the Solution to undertake User Acceptance Testing? What would such testing involve?
8.6 What impact could using a temporary ISDN connection during testing, instead of the intended SIP connection, have?
8.7 Does using an ISDN connection and then migrating to SIP increase the chance of issues being experienced relating to the dialler?
8.8 In your opinion, what are the differences in functionality between Cisco Unified Communications Manager and the dialler process that was installed as a component of the Solution?
8.9 On the basis of the outages and issues that ProLearn claims affected the Solution, would you expect at any time that Cisco Unified Communications Manager would have been unavailable, noting the assumption in paragraph 9.7 below?
8.10 Have you identified any evidence that suggests that, at any time during the operation of the Solution, ProLearn's operators would have been unable to lift a handset and manually dial a prospect?
8.11 In your experience, do complex software systems such as a customised Cisco PCCE solution experience software bugs from time to time?
8.12 What is the process for identifying and rectifying a software bug in Cisco's systems?
8.13 What happens when a software bug is experienced that cannot be replicated in a laboratory setting?
8.14 In its management and deployment of the Solution, did Kytec follow the correct procedure and take all necessary steps upon identifying a bug?
8.15 Any other matters that you would like to address.
Personal To Do Lists
8.16 Is the statement:
Customer records can be inserted directly into the Personal Callback List to support scheduling calls between agents and customers for a specific date and time, but this requires special integration with third-party applications to import these records.
The Personal Callback List maintains a list of customer records scheduled to be called back by a specific agent. The Personal_Callback_List is managed by the Campaign Manager.
A Custom application will be utilized to insert customers directly to personal call list table.
In the ProLearn PCCE Solution As-Built v1.0 document dated 28 July 2015 [KYT.001.001.4335] consistent with the Outbound Option Guide for Cisco Unified Contact Center Enterprise and Hosted Release 10.5(2) and the expected requirements of ProLearn with respect to personal callbacks?
8.17 Without custom integration, was the Solution capable of being configured to enable operators to input specific dates and times for callbacks to be made?
Dialling Issues
8.18 What is the most likely explanation(s) for reports made by ProLearn of the Solution calling the same lead more than once?
8.19 If the output of the dialler is not monitored and adjusted by a dialler manager is there an ongoing risk that calls will be 'dialler abandoned'? What happens when a call is abandoned by the dialler, and in what circumstances might that happen?
8.20 What is the primary reason(s) for calls being abandoned by an automated dialler?
8.21 If the dialler process, or baDialer, had to be restarted, what would be the impact on any operators logged in at the time? Specifically, would those operators be logged out of the Solution? Could they continue to make calls manually whilst the dialler restarted? How long would you estimate the automated dialler would take to restart?
Capacity of the Solution
8.22 Given the design specifications of the Solution, would you reasonably expect that it would be capable of supporting up to 200 agents (assuming that ProLearn had purchased the requisite licenses)?
8.23 Could a Cisco UCCX system with an Acqueon integration be used to create personal callback lists for more than 25 operators?
8.24. Based on Cisco Package Contact Centre Enterprise Design Guide, Release 10.5(x) what was the agent capacity of the Solution?
ASSUMPTIONS
In preparing your response to the above questions, you should assume that:
9.1 at the time the Solution was installed, Prolearn employed 83 operators and intended to employ up to 200 operators in the future at any one time. All operators required the ability to create personal call-back lists, and accept dialling lists from an integration such as a text file;
9.2 Prolearn instructed Kytec to design a Solution that was compatible with an SQL based CRM;
9.3 the Solution was designed and installed in accordance with the enclosed documents:
(a) Final Proposal [KYT001.001.1013];
(b) Prolearn PCCE Solution As-Built [KYT.001.001.4335];
(c) Contact Centre Solution Overview [KYT.001.001.1216]; and
(d) Cisco PCCE Solution Managed Service Proposal [KYT.002.001.1411]
9.4 at all relevant times, Prolearn continued to operate the Solution using a manual CRM, and did not upgrade to an SQL based CRM;
9.5 due to the unavailability of Prolearn's premises, Kytec could not commence testing the Solution at the time of installation until 6 days prior to the Solution being commissioned;
9.6 at the time the Solution was installed, Prolearn had not yet had its SIP line installed, and Kytec was therefore required to test and commission the Solution against a temporary ISDN connection installed by Prolearn; and
9.7 at no stage during the operation of the Solution did Prolearn report to Kytec that any more than 3 phones were deregistered.
50 In responding to the questions, Green stated that he relied upon his experience with the Cisco products involved in the Solution and technical product documentation published by Cisco.
51 Lynette Leondaris (Leondaris) has been employed by Telstra for 19 years and has been the Channel Manager in Telstra Business & Enterprise at Telstra since April 2013. Leondaris holds an Associate Diploma in Marketing from Holmesglen Institute.
52 As Channel Manager, Leondaris manages the relationships with the businesses that Telstra engages to provide technology solutions and services to Telstra's customers. These businesses are typically referred to as Telstra's Channel partners or Dealers. Leondaris is also responsible for managing a portfolio of Dealers who provide technology solutions and services to Telstra's customers and was at the time of her evidence managing a portfolio of seven Dealers.
53 Leondaris stated that her role involves being the primary point of contact and interface between Telstra and the Dealers in her portfolio. Leondaris is responsible for monitoring the financial performance of Dealers and updating the Telstra business on their financial performance. She also monitors how Dealers engage with Telstra and reports this back to the Telstra business. Leondaris, from time to time, manages customer complaints and escalations in relation to the Dealers in her portfolio. Leondaris' Dealer portfolio included managing Telstra's relationship with Kytec.
54 In her witness statement dated 23 October 2018,[28] Leondaris addresses the management of Telstra's relationship with Kytec in relation to the Telstra and Kytec and Telstra's Dealership Agreement, including Kytec's accreditation as a Telstra Dealer and Kytec's performance as a Telstra Dealer.
55 Andrew Asimakidis (Asimakidis) has been employed by Telstra for 14 years and since October 2016 has been the Senior Account Executive in Telstra Enterprises - Majors, where he currently manages accounts for Telstra customers.
56 As a Senior Account Executive, Asimakidis is responsible for managing Telstra's relationship with current or prospective business customers and providing them with technology solutions and services. His role also requires him to liaise from time to time with the Dealers which Telstra engages to provide customers with technology solutions and services. Kytec has been a Telstra Dealer since at least 2010.
57 In his witness statement dated 23 October 2018,[29] Asimakidis addresses Telstra's dealings with Kytec as a Telstra Dealer. Asimakidis deals with his dealings on behalf of Telstra with Okulicz of Kytec and Tutungi of ProLearn commencing at the end of January 2015 and the chronology of the Proposals, Quotations and the Contracts entered into by Telstra and ProLearn in relation to the Solution in late April 2015. Asimakidis also explains his role as ProLearn's Account Executive and Telstra's invoicing of ProLearn.
58 Daniel Wolff (Wolff) is the Managing Director of Capstone Education, a management consulting firm servicing the VET sector, and has served 10 years in senior roles in the VET sector. Wolff put on expert evidence for Telstra.
(a) Master of Business Administration, Executive MBA program of Melbourne Business School;
(b) Bachelor of Arts, University of Canberra;
(c) Diploma of Management, Learning Options;
(d) Certificate IV in Training and Assessment, IPS Institute.
1. Vocational Education and Training (VET)
1.1 What is the VET sector in Australia? In answering this question please explain the types of providers in the VET industry (such as Registered Training Organisations), the regulation and funding of those VET providers, and any reporting requirements and data collection obligations imposed upon them.
1.2 How were marketing brokers and/or agents used in the VET industry, how has this changed over time, and how were those brokers and/or agents regulated?
2 VET-FEE HELP
2.1 What is VET-FEE HELP, when was it introduced, when did it end, and how was it administered?
2.2 What, if any, were the commonly known issues with the VET-FEE HELP system and/or the VET industry? In responding to this question, please focus on the period from January 2014 to December 2016.
2.3 What, if any, were the government responses to the issues identified above in question 2.2? In answering this question, please describe any responses including legislative and regulatory reforms as well as marketing, advertising and/or educational campaigns. Please also identify, where possible, when the responses were foreshadowed or anticipated prior to being implemented.
2.4 What, if any was the impact of the responses identified above in question 2.3 on the VET industry generally? In answering this question, please also describe any impact on student numbers, sales or enrolments for courses, and loan amounts. Please consider the calendar years 2014, 2015 and 2016.
3. ProLearn Corporation Pty Ltd as its Customers
3.1 Please describe how the plaintiff, ProLearn Corporation Pty Ltd (ProLearn) operated as a call centre marketing VET courses to prospective students?
3.2 What were the implications, if any, of the governmental responses identified in your answer to question 2.3 and the industry-wide impacts identified in your answer to 2.4 on ProLearn's sales? Please consider the calendar years 2014, 2015 and 2016.
3.3 In your experience, are there any other VET-related factors that would or could have had an impact on ProLearn's sales in the years 2014, 2015 and 2016?
4. Smith Report
4.1 Based on your expertise, do you have any comments on any assumptions contained in the Report of Mr Michael Smith dated 11 December 2018, which has been filed on behalf of the plaintiff to the proceeding?
61 Dawna Wright (Wright) is a qualified Chartered Accountant, Senior Managing Director and leader for Australia of the Forensic Accounting and Advisory Services practice at FTI Consulting. In this role, Wright provides forensic accounting, valuation and financial investigation services. Wright was called on behalf of Telstra to give expert evidence.
(a) Bachelor of Commerce (Honours), University of Manitoba, Canada;
(b) completion of Canadian Institute of Chartered Accountants courses, including further study in accounting, auditing and finance;
(c) completion of conversion courses and procedures to gain membership to the American Institute of Certified Public Accountants and the Institute of Chartered Accountants in Australia;
(d) is recognised as a Business Valuation specialist by Chartered Accountants Australia and New Zealand;
(e) completion of Certified Fraud Examiner courses and examinations.
63 Wright advised that she has more than 25 years of training and experience in firms of chartered accountants, of which more than 15 years have included providing forensic services.
1. Smith Report
1.1 What is your opinion on the methodology, analysis and assumptions contained in the Report of Mr Michael Smith dated 11 December 2018, which has been filed on behalf of the Plaintiff in this Proceeding?
1.2 In your opinion, are there factors that would have impacted ProLearn's sales and/or revenue during the period from January 2014 to December 2016, in addition to those identified in the Smith Report and other than the operation of the telephone system used by ProLearn in its call centre?
In answering this question, to the extent that you consider necessary, please give consideration to the expert report of Mr Daniel Wolff dated 20 March 2019, which has been filed on behalf of the Second Defendant in the Proceeding.
2. Telstra's counterclaim
2.1 Calculate the total amount owed to Telstra by ProLearn under the Telephone Contract and the Data Contract, including any unpaid invoiced amounts and Early Termination Charges (ETC).
For the purposes of calculating the ETCs as set out in Question 2.1 assume that:
- ProLearn entered into a contract with Telstra for certain telephone services on 27 April 2015 (Telephone Contract);
- The Telephone Contract commenced on 12 May 2015;
- ProLearn entered into a contract with Telstra for certain data services on 27 April 2015 (Data Contract);
- ProLearn terminated the Telephone Contract and Data Contract on 22 June 2017;
- ETC charges are payable under clause 3.2 of Schedule 2 of the Data Contract; and
- ETC charges are payable under clause 8 of the Telephone Contract.
65 In the Wright Second Report,[35] Wright stated that in a letter of instruction dated 11 April 2019,[36] Telstra had requested that she calculate the total amount owed to Telstra by ProLearn under the Equipment and Services Agreement signed by ProLearn on 27 April 2015, including any unpaid invoiced amounts. For the purpose of answering Question 2.1 of the letter dated 26 March 2019,[37] lawyers for Telstra requested that Wright assume the amount owing to Telstra in respect of unpaid invoices under the Telephone Contract, Data Contract and Equipment and Services Agreement was the amount set out in the Tax Invoice issued by Telstra on 8 September 2017, and assume that the Equipment and Services Agreement was terminated by Telstra on 23 October 2018.
The Joint Expert Report of Michael Smith and Dawna Wright
66 Pursuant to an Order dated 30 November 2018,[38] Smith and Wright prepared a joint report setting out the issues on which they agreed and any areas of disagreement, together with reasons for disagreement.
67 Smith and Wright produced a Joint Expert Report dated 13 May 2019[39] which was split into three separate sections; methodology; assumptions and loss and damage.
[W]here a party has to prove something and prima facie has available evidence that would directly deal with the question, a court will be very hesitant in drawing an inference in that party's favour from indirect and second-hand evidence, when the party doesn't call the direct evidence that prima facie it could have called, at least unless some explanation is given, or the circumstances themselves provide an explanation.
70 Kytec submit that ProLearn bears the onus of proving liability and loss and damage, but that in this proceedings, without explanation ProLearn:
(a) failed to call any expert evidence concerning the Solution and its recommendation and operation, instead relying on assertions from Tutungi who admitted she had no technical knowledge and did not really understand the 'complexities' of the new Kytec Solution;[42]
(b) failed to call Sudesh Nepal, the only person at ProLearn at the relevant times who was 'IT savvy' and who ran ProLearn's CRM database and was handling some of the issues which were reported as service faults to Kytec's service desk;[43] and
(c) declined to call Peter Roberts (Roberts), the ex CEO of SWSI, who could have given evidence about SWSI's enrolments in 2016, the market and its use of other intermediaries like SEEK and instead ProLearn attempted to make out its case from indirect and second-hand evidence, being material subpoenaed by Telstra, which was then analysed, incorrectly on Kytec's submission - by Tutungi.[44]
71 Kytec also emphasises that the failure to call Roberts occurred in circumstances where ProLearn had filed a witness statement and referred to him in opening and through the course of trial.
72 Kytec submit that ProLearn's failure to call Roberts or anyone else from SWSI to explain why ProLearn's business would have defied the VET market downturn, means that the Court can infer that Robert's evidence would not have assisted ProLearn on this point.[45]
73 Telstra also submit that ProLearn's attempts to draw a distinction between the courses sold by SWSI and TAFE NSW should be rejected because, amongst other reasons, ProLearn failed to call Roberts who could have been expected to give evidence about SWSI's sales during the Loss Period, any differences in sales as compared with TAFE NSW as a whole and the reasons why the extent of ProLearn's sales changed from time to time.[46]
74 In relation to its failure to call Roberts, ProLearn submits that it decided not to call Roberts to give evidence after Kytec made objections to the admissibility of a key part of Roberts' witness statement, which objections ProLearn considered to be well founded.[47] ProLearn also submits that the fact that Roberts was not called does not elevate other evidence.[48]
75 I consider that ProLearn's reliance on Tutungi's evidence and ProLearn's contemporaneous records and recorded instances of failures and difficulties with the Solution, including ProLearn's written communications in that regard to Kytec and Telstra, formed a body of persuasive evidence which established that the Solution suffered from material and significant defects and deficiencies.
76 Those established problems, defects and deficiencies included that the Solution did not have the capacity to generate Personal Call Back Lists or be used by 83 agents at the same time.
77 Accordingly, I reject Kytec's submission that it was a deficit in ProLearn's case that it did not call expert evidence concerning the Solution and its recommendation and operation, but relied on Tutungi's evidence.
78 I also reject that it was in any way necessary for ProLearn to explain why expert evidence of the nature referred to above was not called. Tutungi's evidence as to the Solution's problems, defects, and deficiencies, was admitted into evidence and was probative and persuasive.
79 I also consider that for the same reasons outlined above, it would not be appropriate to draw an adverse inference against ProLearn on the basis that it did not adduce evidence from Sudesh Nepal, an 'IT' savvy ProLearn employee working with ProLearn at the time of some of the problems, defects and deficiencies ProLearn was experiencing with the Solution.
80 As to Mr Roberts, the former CEO of SWSI who may have been able to give evidence about enrolment at SWSI in 2016 and evidence including expert evidence about the state of the relevant market, although ProLearn accepted that the Court could in the circumstances infer that Roberts' evidence would not have assisted ProLearn, in my view, there are two factors justifying not reducing the weight of ProLearn's case that SWSI provided a buffer to ProLearn in relation to downturn in the market in which ProLearn was operating or ProLearn's case in relation to the difference between the SWSI and the TAFE New South Wales courses.
81 The first factor is that I accept that ProLearn did not call Roberts because of justified objections raised in relation to the admissibility of his evidence. The second factor is that it is not clear that the submission made by Kytec in relation to Roberts not being called is well founded in relation to expert evidence.[49]
Kytec's failure to call evidence it had previously designed an out-bound call centre
82 ProLearn submits that a Jones v Dunkel inference can be drawn in relation to Kytec's failure to call evidence in chief as to whether Kytec had ever previously designed a telecommunications system for an out-bound call centre.[50]
83 In relation to this submission, Kytec state that Okulicz was asked about the nature of the specific companies listed as Kytec's customers and gave the following evidence in relation to the nature of Kytec's customer base:
Just because a customer - their business isn't an outbound call centre doesn't mean that they don't have an outbound feature to their business. As an example, we have customers in the financial services industries. They will use an outbound dialler for collections, as an example - so calling back. If you've ever not paid... your credit card, you've probably been called by on of these people that's running off an automatic dialler, which, very likely, if it's a large bank is a Cisco UCCE solution.[51]
84 Kytec also point to Okulicz's evidence that at the time the Kytec solution was deployed there were seven Cisco Packaged Contact Centre Enterprise (PCCE) systems operating within Australia and that Kytec was responsible for three of those deployments.[52] In his witness statement, Okulicz explained that Cisco PCCE is a specific deployment of Cisco Unified Contact Centre Enterprise (UCCE) which controls the maximum number of agents and the supported applications within the solution.[53]
85 Kytec submit that Okulicz witness statement clearly sets out Kytec's qualifications for deploying Cisco PCCE, including the ongoing examination requirements to retain that certification, and his evidence was that the system data sheets indicated that PCCE was capable of meeting ProLearn's requirements.[54]
86 Similarly, Telstra submit that, contrary to ProLearn's submission, the evidence shows that at the time of the Final Proposal, Kytec had substantial experience designing Cisco telephone systems for businesses including call centres and businesses that used an outbound dialler as part of their operations. Telstra contend that ProLearn has adduced no evidence that there is any difference, let alone a material difference, between the design of an 'out-bound' call centre in contrast to any type of call centre.
87 I consider that, although the above evidence highlighted by Kytec does not directly meet ProLearn's point about evidence which establishes Kytec had earlier designed a telecommunications system for an inbound call centre, I am unwilling to draw an inference of the type sought against Kytec. In my view, I should here ultimately and simply take into account whatever direct and probative evidence was tendered as to Kytec's specific past experience in this area.
88 ProLearn also contend that Kytec failed to call several key personnel involved in the installation of the Kytec Solution as witnesses. In particular, ProLearn submits that appropriate inferences should be drawn from Kytec's failure to call Remon Gaber (Gaber), Kytec's lead engineer on the project tasked with its technical design and implementation, and Jonathan Baughen (Baughen), who was tasked with the creation of gadgets and custom reports, both of whom were employed by Kytec as at the date of Okulicz's witness statement.[55]
89 In response to ProLearn's submission that adverse inferences should be drawn from Kytec's failure to call Gaber and Baughen, Kytec submit that Okulicz had the relevant technical expertise and it was reasonable for Kytec to rely on his evidence in relation to the ProLearn project, and Kytec add that Okulicz's witness statement was comprehensive in relation to matters for which Kytec bore an onus and that there is no basis upon which to conclude that Gaber and Baughen would have added anything to Okulicz's evidence.[56] Furthermore, Kytec submit that unlike ProLearn, Kytec did call an independent expert, Green, who specifically addressed the technical design and implementation of Kytec's Cisco Solution.[57]
90 I am satisfied that for the reasons submitted by Kytec and summarised above, in particular because Okulicz could give evidence in relation to any matter which could also be addressed by Gaber or Baughen, that there is insufficient justification to draw an adverse inference against Kytec in any respect because it did not call Gaber or Baughen.
91 In early 2011, ProLearn commenced a digital and telemarketing business primarily focussed on the provision of digital and telemarketing services to the VET sector.[58] From 2012, ProLearn established a number of contracts with various education providers. It is common ground that this part of ProLearn's business came to an end on 31 December 2016, due to legislative changes that came into effect on 1 January 2017.[59]
92 ProLearn's business was in the nature of an outbound call centre from which call centre operators would contact potential customers in order to sell them online vocational, education and training courses on behalf of education providers.[60] However, rather than making unsolicited or 'cold' calls, ProLearn made its outbound calls to 'leads' - prospective students who had indicated their interest in being contacted about further education.[61]
93 In order to obtain leads, ProLearn conducted online marketing which encouraged people interested in further education to register their contact details in an online form in order to receive a call from ProLearn.[62] ProLearn placed its marketing through companies known as lead generator companies and paid these companies per lead.[63] Across the period of June 2014 to November 2016, ProLearn purchased leads from the lead generating companies, Cohort Australia Pty Ltd, Optimise Media Pty Ltd and Omnileads Pty Ltd.[64]
Old telephone system and customer relationship management database
94 Prior to moving to the new Solution which is in issue in this proceeding, ProLearn was using a telephone system provided by CommSys (the CommSys system), and a Customer Relationship Management database (CRM) built and maintained by ProLearn.[65]
95 The functionality of the CommSys system was basic and included the following features:[66]
(a) at the beginning of every day, each Operator logged into his or her phone. This allowed the CommSys system to know the identity of each Operator making and answering a particular call;
(b) Operators manually dialled the phone numbers. Each direct line had a message bank and each Operator would pick up any missed calls from their extension;
(c) the CommSys system recorded every call for compliance purposes;
(d) at the end of each business day, the CommSys System sent a report to management detailing the number of calls made by each Operator and the length of the calls. This assisted management to monitor staff efficiency.
96 The CRM was separate to the CommSys system. Each lead was downloaded into the CRM as part of an individual record for each potential customer. The record kept in relation to each lead was updated after an Operator had spoken with, or attempted to contact, a customer. This record allowed Operators to pick up conversations with customers where they had left off, assisted with the development of rapport between the Operator and potential customers, and also helped ProLearn to project a 'professional image'.[67]
97 The CRM included information as to what stage the potential customer had reached in the buying process, and helped inform when ProLearn should call the potential customer back in an attempt to close the desired sale into an educational course. The CRM also generated a personal call back list for each Operator, detailing each lead wanting to be called back at a later time by ProLearn, or with whom the Operator had not yet been able to make contact flagging the need for a further call.
98 On logging into the CRM, each Operator would be presented with their personal call back list. The Operator would proceed to manually call each person on the list, in order of priority, with those most likely to result in a sale being given higher priority. Operators were only allocated fresh leads after they had finished moving through their personal call back list.[68]
99 The ProLearn VET business experienced sharp growth early in its life, particularly during the 2014 and 2015 financial years, with earnings before interest and tax (EBIT) of $2,695,000 and $9,578,000 respectively in those periods.[69]
100 From April 2011, ProLearn's business was conducted from Suite 3.06, Level 3 of 450 St Kilda Road, Melbourne (the St Kilda Road premises). To accommodate the growth of the business, ProLearn moved into Suite 4.02, and then expanded into Suites 4.06 and 4.07 of the St Kilda Road premises.
101 In early 2014, Tutungi signed a lease proposal in respect of Suites 4.02, 4.06 and 4.07 of the St Kilda Road premises for the period 1 February 2014 to 31 December 2016.[70]
102 In December 2014, Tutungi and Humunicki learned that ProLearn's lease on the St Kilda Road premises would not be renewed beyond December 2016. ProLearn decided to move to larger premises, so as to allow for an increase in the number of call centre operators (Operators) and for further growth. Tutungi and Humunicki also decided to upgrade ProLearn's telephone system.[71]
103 In December 2014, ProLearn had 65 Operators. In or around August 2015, ProLearn entered into a five-year lease of premises at Level 15, 380 La Trobe Street, Melbourne (the La Trobe Street premises), which was fitted with 153 open-plan desks and internet sockets, and which was able to be used as a call centre. ProLearn commenced conducting its business from the La Trobe Street premises on 31 August 2015.[72]
104 On 30 June 2015, ProLearn entered into an agreement with South Western Sydney Institute (SWSI), a division of TAFE New South Wales (TAFE NSW), for a term of five years, under which ProLearn was able to recruit as many students as it could for certain SWSI courses.[73]
Initial dealings between ProLearn, Kytec and Telstra
105 In or around mid-January 2015, Tutungi contacted both Telstra and Optus to discuss ProLearn's phone system, with a view to upgrading its current phone system concurrently with the move to the La Trobe Street premises.[74]
106 Kytec is described by Telstra as a 'Telstra Dealer'. As a Telstra Dealer, Kytec provided services to Telstra customers in relation to the development and installation of phone systems and contact centre solutions, particularly Cisco-based systems.[75] Telstra often referred customers to Kytec through leads which Telstra also received. In some instances, Kytec referred leads that it received to Telstra.[76] Kytec had been considered a Telstra Dealer by Telstra and Kytec since about 2010, and Kytec entered into the Telstra Dealership Agreement with Telstra in that regard on or about 1 August 2010.[77]
107 ProLearn's above enquiry of Telstra by Tutungi was referred to Kytec. This referral was very rapid. As will become apparent, ProLearn contends that the speed with which Telstra referred ProLearn to Kytec is of relevance to ProLearn's claims against Telstra, particularly in relation to its claim that Telstra engaged in misleading or deceptive conduct contrary to s 18 of the ACL. In essence, ProLearn seeks to establish that the Solution which it asserts was the subject of Kytec and Telstra's representations was not able to automatically create personal call back lists, or to be used by 83 telemarketing agents; was not able to be integrated with ProLearn's CRM; did not enhance ProLearn's productivity and was not appropriate for ProLearn's requirements, as specifically identified by ProLearn.
(a) an automatic dial system (Automated Dialler) capable of supporting at least 83 Operators, with the capacity to grow to around 150 to 200 Operators;
(b) the ability to generate personal call back lists (Personal Call Back Lists; also referred to as to-do lists or call back lists) for at least 83 Operators; and
(c) the ability to integrate with ProLearn's CRM;
(collectively, the ProLearn Requirements).
110 As for the Automated Dialler, Okulicz explained the purpose and particulars of this function in his witness statement as follows:[82]
The purpose of an automated dialler is to improve the efficiency of call centre operators. This is done by the dialler automatically dialling multiple numbers simultaneously, and then passing on any calls that are answered to an operator who is waiting to take those calls. This increases the efficiency of operators in a call centre because the only time that the operators spend on the phone is time connected to a potential customer - the dialler takes responsibility for other tasks such as dialling the number, waiting for an answer, and connecting to voicemail recordings. I discussed these efficiencies with Vicki during the meeting, and I agreed that an automated dialler could assist ProLearn to increase its efficiency, by maximising the time spent by its call centre operators on live calls.
111 On 30 January 2015, at the invitation of Okulicz, Tutungi and Humunicki attended a demonstration of the Cisco system at Cisco's premises at 101 Collins Street, Melbourne, also attended by Okulicz and Lukas Carruthers from Cisco.[83]
112 Following the demonstration, Okulicz sent Tutungi a document entitled, 'Contact Centre Solution Overview', dated 11 February 2015 (the First Proposal).[84] The First Proposal from Kytec to ProLearn recommended a Cisco Unified Contact Centre Express (UCCX) solution as being suitable for ProLearn's requirements.[85]
113 The First Proposal also noted that Kytec was an 'expert ICT organisation', and was 'proud to exclusively partner' with Telstra, among others, to deliver on customer requirements.[86]
114 The Executive Summary to the First Proposal also stated among other things:[87]
ProLearn are looking to enhance their existing call centre environment to include an outbound dialler that will integrate with their CRM. The solution will enhance the productivity of ProLearn and assist in driving the business forward as growth is a major focus.
115 The First Proposal also set out the 'Kytec Approach' over four stages, being 'Assess', 'Respond', 'Deploy' and 'Support'. The Kytec Approach included the preamble:[88]
At Kytec, we see each customer as a unique challenge with challenges, plans and requirements that are not the same as any one else. With this in mind, we set out to understand the requirements of our customers both from a business and technical standpoint as an initial step. Once we understand our customers, the rest is easy for us. After all, it is what we do.
116 Tutungi's evidence was that the First Proposal contained no reference to the 'to-do lists', and that:[89]
This was a critical part of ProLearn's business and a fundamental requirement of the system. I could not buy a system that did not have this feature. I raised this during a telephone discussion with Mr Okulicz and Andrew Asimakidis of Telstra on 22 April 2015 ...
117 Tutungi explained that alongside ProLearn's previous CommSys system, ProLearn's CRM provided the following To Do List feature:
The CRM generated a personal call back list, the To-Do List, for each Operator, being a list of customers who had expressed interest in a product and wished to be called back at a later time by the Operator, or who the Operator had not yet been able to make contact with. Upon logging into the CRM the Operator's "To Do List", which was specific to him or her, would be presented to the Operator. It was ordered by priority, with those calls that were most likely to result in a sale taking priority over those calls where the customer had not answered the first time. The CRM would not release new leads to the Operators until he or she had called everyone on his or her To Do List.[90]
(a) the proposed Telstra Corporate Services Agreement, dated 26 March 2015;
(b) the proposed Telstra Business Systems Corporate Services Agreement, dated 26 March 2015;[93] and
(c) the quotation from Telstra to ProLearn, dated 26 March 2015, for the supply of services for a term of three years.
119 The above proposed Telstra Business Systems Corporate Services Agreement was provided under cover of a letter signed by Brendan Donohoe (Donohoe), Director Technical Sales, Telstra Business, which stated:[94]
27 Mar 15
Mrs Vicki Tutungi
ProLearn
ABN 24 542 828 890
St Kilda Rd
MELBOURNE VIC 3004
Telstra Business Systems
Corporate Services Agreement
This Corporate Services Agreement provides a framework for Telstra to assist you to take advantage of today's technology and develop strategic communications solutions for the future.
Your application for the Corporate Services Agreement may be made by signing below and returning the contract to Kytec at Level 1 405 Clarendon Street, SOUTH MELBOURNE, VIC 3205 within 30 days of the date of this letter.
This agreement contains the following Schedules:
- Equipment, Services and Pricing - Schedule 1
- Sale and Installation of Equipment - Schedule 2
- Telstra Business Systems Care - Schedule 3
Please do not hesitate to contact your Telstra Dealer if you have any questions about this letter.
Yours sincerely
Brendan Donohoe
Director Technical Sales, Telstra Business
Telstra Corporation Limited
By signing the below you agree that if your application is successful the terms and conditions detailed in this letter and the attachments to this letter shall be binding on you.
Executed for you by your authorised representative:
Signature Date
Print Name Mrs Vicki Tutungi Position Managing Director
120 Schedule 1, 'Equipment Services and Pricing', to the proposed Telstra Business Systems Corporate Services Agreement (Schedule 1) identified the 'Additional Equipment' to be provided by Telstra as being:[95]
1 x Microsoft and VMWare Licences
1 x 3 Year Cisco Support
1 x 83 Agent Licences + Hardware Infrastructure
1 x Call Recording Solution for 83 Agents.
121 On 21 April 2015, Tutungi emailed Okulicz (of Kytec) and Asimakidis (of Telstra) stating, in part:[96]
Hi David and Andrew,
...
Anyway, I have been through the contract documentation in some detail, and I have a few questions. I suggest a phone hook-up.
The one thing that doesn't seem to be covered in any of the documentation is the agreement with Kytec and what I get in relation to the phone system - Cisco.
I also need to understand down time and speed to recovery.
Also we have signed a lease proposal for level 14, 120 Spencer Street (old AGL call centre), we move in 1 August 2015 and will get early access to cable etc, probably from the 1 July.
A hook up late this afternoon or pretty much anytime tomorrow works for me.
Cheers
Vicki
122 Accordingly, it is to be noted that by 21 April 2015 Tutungi had noticed and raised two things about the Proposal. Tutungi noticed and raised that the Proposal did not refer to a key ProLearn requirement, namely the Personal Call Back List capability. Tutungi also noticed that there was no detail of what the system to be provided would do or what precisely ProLearn was getting.
123 This email was forwarded to Justin McCrae and Cameron Eabry, both of Telstra.[97]
124 Following the 21 April 2015 email, Tutungi telephoned Okulicz and Asimakidis. Tutungi's evidence in relation to that phone call was, in part that:[98]
During that discussion I told them that the contract doesn't reflect what I'm buying - I'm buying a phone system - the contracts need to state what the system will do, including the To Do List functionality. Mr Okulicz assured me that the new telephone system would include the To Do List functionality and agreed to amend the Solution Overview to make that clear.[99]
125 Tutungi was not challenged in relation to the above evidence and neither Okulicz nor Asimakidis gave evidence contradicting this evidence given by Tutungi.
126 At 10:38pm that same day, by email to Tutungi, copied to Asimakidis, Okulicz stated:[100]
Hi Vicki,
Thank you for your time on the phone this afternoon
Proposed inclusions for Cisco solution components as below:
- Inbound/Outbound Licensing for 83 Agents
- Audio recording and Quality Management for 83 Agents
- Dialer functionality capable of running predictive, preview and progressive campaigns
- Integration services to automatically create individual call back lists
- Capacity to run multiple simultaneous campaigns, weighted by skills
- Redundant server hardware architected for 99.999% uptime
- Server licensing to run the solution
Can you confirm the above covers what you want to see in the proposal so we can finalise our response back to you?
Thanks Vicki
Kind Regards
...
127 On 23 April 2015, Tutungi responded to Okulicz, copied to Asimakidis, as follows:[101]
Hi David,
The list looks good, we also need to understand how much agents cost - remember we are on our way to 150. This is actually something we will need to monitor because by the time we get to 1 August we will probably be over 120 at least.
...
thanks
Vicki
128 On 23 April 2015, Okulicz emailed Tutungi, again copying Asimakidis, enclosing the updated proposal and contracts previously provided on 27 March 2015. The email, in part stated:[102]
Hi Vicki,
I have updated our proposal and referenced this from the Telstra TBS contract. Both documents attached.
...
Future Growth - additional SIP services
Telstra response - The proposed Telstra solution is scalable and will meet ProLearn's future growth plans. For an additional SIP Channel the monthly fee will be $61.81 ex gst. This will manage an additional 400 calls.
...
I have re-attached all contracts and proposal (Kytec updated, Telstra unchanged). On the assumption that you are satisfied with the answers above, could you please return these as soon as possible.
...
129 The attachments to this email of 23 April 2015 included:[103]
(a) the updated proposed Telstra Business Systems Corporate Services Agreement;
(b) the updated proposed Contact Centre Solution Overview version 2.1 (the Final Proposal); and
(c) a letter from Donahoe dated 23 April 2015 attaching Equipment, Services and Pricing - Schedule 1; Sale and Installation of Equipment - Schedule 2, and Telstra Business Systems Care - Schedule 3.
130 The Equipment, Services and Pricing document had been amended, to include:
1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal to ProLearn.
131 Tutungi's evidence at T402 in relation to the communications referred to in the last preceding paragraph and relevant contextual matters,[104] included that:
... The view I took was that, Telstra and Kytec were standing behind the proposal, and that the proposal clearly set out what I was going to get for my money and, therefore, the proposal needed to be included in the contract.
132 The above contracts provided by Kytec on 23 April 2015 included the Final Proposal which in turn stated ProLearn's requirement of Personal Call Back Lists for 83 agents (page 5); 'In turn outbound Licencing for 83 agents' (page 6) and 'Integrated services to automatically create individual agent call back lists' (page 6).[105]
133 Subsequently, on 27 April 2015, Tutungi signed and returned the documents on behalf of ProLearn, including:[106]
(a) the Telstra Corporate Services Agreement dated 27 April 2015 (Data Contract);
(b) the Telstra Business Systems Corporate Services Agreement dated 27 April 2015 (Equipment and Services Agreement);
(c) the quotation from Telstra to ProLearn for the supply of services for a term of three years; and
(d) the 'All-4 Biz Order Form' agreement between Telstra and ProLearn (Telephone Contract).
134 Tutungi also initialled every page of the Final Proposal,[107] including the Equipment and Services Agreement, which included a covering letter signed by Donohoe, in the terms outlined above, with the date amended to '23 Apr 15'.[108] Further, the Additional Equipment at Schedule 1 to the Equipment and Services Agreement referred to above had been amended to include (in bold):
1 x Microsoft and VMWare Licences
1 x 3 Year Cisco Support
1 x 83 Agent Licences + Hardware Infrastructure
1 x Call Recording Solution for 83 Agents.
1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal to ProLearn.
(emphasis added).
136 The Final Proposal set out ProLearn's requirements for the Solution, as follows:[111]
ProLearn are seeking a solution that meets the following requirements
- Support of 83 agents
- Voicemail licensing for team leaders (10 users)
- Outbound Preview Dialer
- Personal Call backs for 83 agents
- Integration to web-based CRM for customer information
- Quality Management solution for 83 agents including voice recording and scorecards/KPIs
137 The Final Proposal included reference to the 'core functionality' and the 'Solution Components' of the Solution, being:[112]
Solution Overview
The solution will provide the following core functionality:
Inbound/Outbound Licensing for 83 Agents - Audio recording and Quality Management for 83 Agents
Dialer functionality capable of running predictive, preview and progressive campaigns
Integration services to automatically create individual agent call back lists
Capacity to run multiple simultaneous campaigns, weighted by skills
Redundant server hardware architected for 99.999% uptime
Server licensing to run the solution
16 hour reporting workshop
Solution Components
- Licensing for 83 agents
- 2 x C240 UCS Servers (hardware)
- 83 x 7821 handsets
- Cisco 2921 voice router for SIP connectivity
138 Pages 14 and 15 of the Final Proposal were to similar effect, namely_:_
Solution Overview
- Cisco UC Licensing for 83 users
- 2 x C240 Servers for virtualised UC applications
- Contact Centre Licensing for 83 concurrent users
- Quality Management for 83 Names users
- 83 x 7821 Handsets
- 1 x Cisco 2951 Voice Router with 200 SIP channels
Scope of Works
Planning
- Conduct contact centre planning workshop
- Verify any integrations required
- Verify any 3rd party integrations required
Design
- Document results of contact centre workshop and present results
- Prepare high level contact centre design
- Prepare high level UC design
- Prepare high level network design
- Prepare integration documentation
- Prepare test plans
- Verify contact centre, UC and switching design with ProLearn
Implementation
- Physically mount server and other core equipment
- Configure hypervisors on server equipment (2)
- Install UC applications on server equipment
- Configure call manager and unity connection per uc design documentation
- Configure IM & Presence Server
- Configure jabber client ready for deployment
- Install contact centre enterprise applications
- Configure PCCE Queues as per Contact Centre Design
- Setup agent logins
- Configure teams and supervisors
- Configure Skills Based Routing (SBR) per contact centre design
- Prepare Agent desktop for deployment
- Test agent desktop against up to 3 SoE images
- Performing testing per test plan
- Provide agent training (9 sessions x 10 agents each)
- Provide administrator training - 4 hours
- Document system design
- Go live support
Assumptions
- Customer has adequate UPS power protection
Exclusions
- Troubleshooting of agent issues on multiple machines
- Deployment of Jabber Client
139 The Final Proposal recommended a Cisco Unified Contact Centre Enterprise/Packaged Contact Centre Enterprise (UCCE/PCCE) solution, integrated with a Cisco Unified Communications Manager.
140 The Final Proposal at page 5 also stated that Kytec's business was built on partnerships with its strategic vendor partners, Cisco and Telstra.
141 Further, pages 14 and 15 of the Final Proposal defined the Kytec Scope of Works, including 'Prepare test plans' in relation to Design and 'Test agent desktop against up to 3 SoE images'.
143 On 27 April 2015, Okulicz provided Tutungi with an updated Final Proposal incorporating handsets as requested and confirming other matters.[115]
144 On 7 October 2015, ProLearn entered into the Kytec Contract, an ongoing managed services agreement with Kytec for maintenance and support services in relation to the Solution.
145 Following a pre-implementation phase, the Solution went live at the La Trobe Street premises on 31 August 2015 (the Go Live Date). ProLearn submits that, at this stage, key features of the Solution were not operational, including:[116]
(a) the Automated Dialler - turned on 2 September 2015;
(b) uploading/importing of leads / phone numbers;
(c) the to-do list.
146 Kytec takes issue with ProLearn's submission. Kytec submits that all three functions are related to the Automated Dialler and are not activated until the Automated Dialler is turned on. Kytec submits that those functions were operational on 31 August 2015 but were not switched on at the request of Tutungi.[117]
Onset of problems and deficiencies with the NTS Solution
147 ProLearn submits that the Automated Dialler was not turned on because its staff immediately experienced problems with the Solution, in particular:[118]
(a) the Solution did not have the capacity to generate Personal Call Back Lists; and
(b) the Solution did not have the capacity to be used by 83 Operators at once, and experienced issues when used by more than 30 Operators at the same time.
148 In response to the early problems which the NTS Solution was manifesting, Kytec implemented (what the parties referred to as) a temporary workaround to the Personal Call Back List functionality (the Call Back Workaround).
149 Shortly after the end of August 2015, ProLearn detailed a large number of reoccurring issues experienced with the Solution, many of which affected the Call Back Workaround, including:
(a) Customer information not presenting on the Cisco 'Finesse Screens';[119]
(b) Automated Dialler calling customers numerous times, which ProLearn submits was in breach of the Telemarketing and Research Industry Standard 2007;[120]
(c) Scheduled call backs disappearing from the Finesse Screens;[121]
(d) Calendar in the Call Back Workaround displaying incorrectly;[122]
(e) Customer phone numbers not displaying correctly;[123]
(f) Customer notes not displaying on Finesse Screens when call backs made;[124]
(g) So-called issues relating to 'Orphan Call Backs' - ie, call backs sitting in the system attached to staff who had ceased working at ProLearn;[125]
(h) Capacity-related issues presenting in system crashes and 'freezing' of Finesse Screens or delays in customer information appearing on the Finesse Screens.[126]
150 ProLearn submits that contemporaneous records detail the major problems experienced by ProLearn, and the subsequent damage to its business, including:[127]
(a) Email from Tutungi to Ryan Smith, Gaber and Baughen (all of Kytec), copying inter alia Okulicz and Humunicki, dated 10 September 2015:[128]
This system is far from ready for release, I would like a phone hook up this morning at 10am to discuss, what is going wrong and how it is going to be fixed and by when.
I expected bugs but we are now a week and a half into start up and we haven't had one day when we have had the system fully operational.
This is seriously impacting on the business.
...
(b) Email from Tutungi to Okulicz and Derek Costello (of Kytec), copying Humunicki, dated 11 September 2015:[129]
...
Not on target has been met by your project team, you had extra time before kick off to program the system and set up the reports, but nothing apart from loading the software on the servers was done. You didn't even order the server for the call recordings.
I feel I was misled by you David as your team cannot deliver no the promises you made me when you signed up.
...
(c) Email from Tutungi to Samuel Bolivar (of Kytec), ticket #169406, dated 27 November 2015:[130]
...
Can you look at the stats about how many call backs are connecting? Can you tell me if this is happening to all call backs? What happens to the call backs after it disappears off the screen ... this is a critical step in our business process and we are losing sales over this.
...
(d) Email from Tutungi to Okulicz and Martial Renoult (of Kytec), dated 7 December 2015:[131]
...
It's been 2 weeks since we raised this issue and it appears to be no closer to being solved today than the day I raised it. I know Samuel is working hard, but we are losing sales and this cannot continue. The call back work around was intended to overcome the problem with uploading the to do lists.
I need this fixed ASAP.
Please advise on your strategy to fix.
...
(e) Email from Tutungi to Okulicz and Martial Renoult, dated 13 January 2016:[132]
...
As I am sure you are probably aware the dialler is down again.
I sent the call centre home yesterday at 5pm and half of them have left today at 4pm. Tomorrow I have 28 people starting and I cannot have the dial going down all afternoon.
...
I need to stress that I cannot have the system fail again tomorrow. This is our whole business.
...
(f) Email from Tutungi to Okulicz and Martial Renoult, copying Humunicki, dated 19 January 2016:[133]
...
Unfortunately this year has started with more phone issues.
You instituted a change in the system to eliminate the ever growing number of "orphan" call backs which triggered a complete melt down in the dialer. When this was corrected this triggered a problem with call backs.
So again this year my business is suffering from down time and loss in revenue due to not being able to close sales.
The system has cost my business considerable lost revenue and increased my costs in terms of staff turnover, lost leads and down time.
I would like to arrange a meeting to discuss:
- termination of our contract
- compensation
- plan for moving forward.
Please advise of your availability for next week.
...
(g) Email from Tutungi to Andrea Walk (of Telstra), copying Humunicki, dated 13 May 2016:[134]
...
- None of the work that was meant to be done prior to the launch was completed. This meant that no testing was done prior to launch and for the month of September we had daily issues with the dialler not performing.
- The original specification included the ability for each agents "to do list" or "call back list" to be updated daily. This was abandoned after 2 months of continual crashes and issues. We still to this day manually call people back.
- The system is meant to be able to cope with 200 agents, but every time we get about 30 agents the system fails. This presents as:
- screen freezing.
- lag in presenting customer information
- slow down in dialler
- disconnecting agents to the finesse gadget
...
The impact of all these problems include:
- our costs for buying leads have doubled because we are burning through double the leads with no increase in sales or customer connections.
- our efficiency has halved - eg. Yesterday we had to take all the operators off the diallers as they were totally frustrated. In total we have probably lost no less than 10 full business days over the period since September in down time.
- None of the promised benefits have been delivered.
...
151 ProLearn submits that the issues it faced in using the software were further evidenced by:[135]
(a) ProLearn lodging a compensation claim with Telstra in November 2016 seeking compensation of $9.1 million;
(b) Humunicki's communications in a meeting between Humunicki and Tutungi of ProLearn, and Okulicz and Martial Renoult (Renoult) of Kytec, on 20 January 2016, following Tutungi's email of 19 January 2016 and outlined above;
(c) the fact that Kytec did not provide a definitive As-Built document, and failed to keep an updated record of the build in the document.
Escalation to Telstra: Compensation claim and audit
152 In or around May 2016, ProLearn escalated its complaints with the Solution and Kytec to Telstra.
153 At a meeting between Joe Gillett (Gillett) of Telstra, Tutungi and Humunicki on 30 June 2016, Gillett informed Tutungi and Humunicki that before Telstra could remove Kytec from the project, it required an independent company to conduct an audit of the Solution, and proposed to appoint.[136]
154 A copy of the audit report prepared by TBC (the Audit Report) was provided to ProLearn by Telstra on 29 September 2016, noting several issues with the Solution, including that there appeared to be 'some overly complicated scripts and gadgets', and that the outbound database was running at approximately 80 percent capacity.[137]
155 On 9 March 2017, Gillett emailed Tutungi advising, inter alia, that:
No decision to replace the system will be made until the investigation into all issues raised has been completed and the findings have been presented to you. We expect to present the findings of the investigation to you before the end of the month.[138]
156 On or around 23 August 2016, Tutungi lodged a compensation claim with Telstra in respect of the Solution (the Compensation Claim), in the amount of $9.1 million, identifying three failures:
(a) failure to design and configure the Cisco system to a basic level of competency;
(b) failure to identify and rectify the issues; and
(c) failure on Telstra's behalf to deliver the system as contracted and, in particular, Personal Call Back Lists for 83 Operators.[139]
157 On 31 March 2017, Strickland (of Telstra) emailed Tutungi to formally reject the Compensation Claim.[140]
Legislative changes in the VET sector and the consequential impact for ProLearn's operations
158 It is common ground that ProLearn ceased carrying on its business involving digital and telemarketing services to the VET sector on 31 December 2016, due to legislative changes.[141]
159 On or about 11 June 2017, ProLearn sent letters to the defendants purporting to terminate its contractual arrangements with Telstra and Kytec.[142]
ProLearn's misleading or deceptive conduct claim against Kytec and Telstra
160 ProLearn submits that both Telstra and Kytec made particular representations to ProLearn regarding the Solution, and that such representations were misleading or deceptive in breach of ss 18(1) and 29(1)(g) of the ACL, which provide, inter alia:
Section 18(1)
(1) A person must not, in trade or commerce, engage in conduct that is misleading or deceptive or is likely to mislead or deceive.
...
Section 29(1)(g)
(1) A person must not, in trade or commerce, in connection with the supply or possible supply of goods or services or in connection with the promotion by any means of the supply or use of goods or services:
...
(g) make a false or misleading representation that goods or services have sponsorship, approval, performance characteristics, accessories, uses or benefits ...
161 Further or in the alternative, ProLearn submits that Kytec made particular representations as an agent of Telstra or, alternatively, with the implied consent or agreement of an employee or agent of Telstra, such that the particular representations were also representations made on behalf of Telstra pursuant to s 84(2) of the CCA which provides:[143]
Section 84(2)
(2) Any conduct engaged in on behalf of a body corporate:
(a) by a director, employee or agent of the body corporate within the scope of the person's actual or apparent authority; or
(b) by any other person at the direction or with the consent or agreement (whether express or implied) of a director, employee or agent of the body corporate, where the giving of the direction, consent or agreement is within the scope of the actual or apparent authority of the director, employee or agent;
shall be deemed, for the purposes of this Act and the consumer data rules, to have been engaged in also by the body corporate.
162 ProLearn pleads in its Amended Statement of Claim that Kytec represented to ProLearn that:[144]
(a) the Solution would be able to automatically create Personal Call Back Lists (Representation 'A');
(b) the Solution would be able to be used by 83 agents (Representation 'B');
(c) the pleaded representation at Amended Statement of Claim [8(c)] was not pressed at trial;
(d) the pleaded representation at Amended Statement of Claim [8(d)] was not pressed at trial;
(e) the Solution would enhance the productivity of ProLearn (Representation 'E');
(f) the Solution was appropriate for the ProLearn Requirements (Representation 'F');
(g) such representations were based on reasonable grounds (Representation 'G');
(collectively, the Kytec Representations).[145]
163 ProLearn alleges that Kytec made the Kytec Representations as an agent of Telstra, within the scope of Kytec's actual or apparent authority, or with the implied consent or agreement of an employee of Telstra, with the effect that Telstra is deemed to have engaged in the conduct under s 84(2) of the CCA.[146]
164 Separately, ProLearn alleges that Telstra made representations to ProLearn that:
(a) the Solution would be able to automatically create Personal Call Back Lists (Telstra Representation 'TA');
(b) the Solution would be able to be used by 83 Operators (Telstra Representation 'TB');
(c) the representation at Amended Statement of Claim [11(c)] was not pressed at trial;
(d) the Solution would perform in accordance with supplier (being Kytec) specifications (pursuant to the Final Proposal) for 12 months from the date on which ProLearn completed a customer acceptance certificate (Telstra Representation 'TD');
(e) such representations were based on reasonable grounds (Telstra Representation 'TE');
(collectively, the Telstra Representations).[147]
Alleged Kytec Representation that the Solution would automatically create Personal Call Back Lists
165 Kytec's submission included that the alleged Representation 'A', that 'the Solution would be able to automatically create Personal Call Back Lists', must be read with the alleged representation that 'the Solution would integrate with ProLearn's CRM for customer information'.[148]
166 Kytec submits it is common ground that ProLearn did not have a web-based CRM, but rather one that was run through Microsoft Access. Kytec submits Tutungi accepted that she was told by Okulicz that the Solution would be compatible with a web-based CRM built on Structured Query Language (SQL).[149] Kytec asserts it did not represent that the Solution would integrate with ProLearn's pre-existing manual CRM.[150]
167 Kytec also submitted that this is significant because:
(a) Personal Call Back Lists - when difficulties were encountered with the Personal Call Back List functionality, ProLearn would have been able to leverage the web-based CRM for this functionality, rather than developing the Call Back Workaround; and
(b) Capacity issues - the capacity issues would not have occurred, because the 'custom gadget' (referred to above) installed after the Go Live Date at ProLearn's request, would not have been required.
168 Kytec accepts that the representation that 'the Solution would be able to automatically create Personal Call Back Lists' is a representation as to a future matter; however, it submits this was not misleading or deceptive because the proposed Solution did have the ability to create Personal Call Back Lists, or could be customised to import them from an external source.[151]
Kytec's reasonable grounds to make the Kytec Representations
169 Kytec submits that it had reasonable grounds to make all of the alleged Kytec Representations at the relevant time, namely April 2016, relying on Okulicz's expertise which was not challenged.[152] Kytec submits that ProLearn's case is based on 'hindsight illusion',[153] because it relies on later events and developments to undermine Kytec's reasonable grounds at the time of the alleged Kytec Representations.[154]
170 Kytec submits the Green expert report establishes that it had reasonable grounds to make the Kytec Representations regarding the Solution, and that ProLearn did not seek to prove that the Cisco PCCE system was inappropriate in the circumstances.[155]
171 In the circumstances, Kytec submits that the Kytec Representations were made honestly, and were based on Okulicz's expertise and competence, and the appropriateness of the Cisco PCCE system.
172 In relation to the other alleged Kytec Representations, Kytec submits that:[156]
(a) the Solution would be able to be used by 83 agents:
the Solution could handle up to 1,000 agents, however ProLearn did not ever have that number of Operators.[157]
(b) the Solution would have the capacity to be used in the future by approximately 200 agents when ProLearn wished to expand, with the only additional requirement being that ProLearn would have to pay for additional licences;
the Solution could handle up to 1,000 agents.[158]
(c) the Solution would enhance the productivity of ProLearn;
the Solution could and did enhance ProLearn's productivity, in that average monthly call volume increased.[159]
(d) the Solution was appropriate for the ProLearn Requirements;
the Cisco UCCE/PCCE system was appropriate.[160]
(e) such representations were based on reasonable grounds;[161]
Kytec had reasonable grounds for making each Kytec Representation.
174 Telstra denies that Kytec acted as its agent in providing the Final Proposal or that Telstra is otherwise liable for Kytec's conduct in making the Kytec Representations to ProLearn pursuant to s 84(2) of the CCA.[162]
175 If an agency relationship is found to exist, Telstra submits that it did not extend to making the statements in the Final Proposal so as to affect Telstra's legal relations with ProLearn.[163]
176 Telstra submits that for agency to exist, it must be established that the principal expressly or impliedly assented to the agent acting on its behalf, so as to affect its relations with third parties, and that the agent expressly or impliedly assented to so act on the principal's behalf,[164] and that such conclusions should not simply be drawn from the alleged agent's performance of a function important to the principal's business.[165]
177 Telstra submits that the facts relied on by ProLearn to found the agency relationship cannot support a conclusion of implied agency between Telstra and Kytec, for the reasons outlined below:
(a) Asimakidis (of Telstra) participated in a telephone conversation between Tutungi and Okulicz on 22 April 2015 during which time they discussed the proposed terms of the updated Equipment and Services Agreement. This undermines the alleged agency relationship, because it demonstrates ProLearn's awareness that Okulicz was from Kytec and that Kytec was not authorised to enter into the agreement on Telstra's behalf.[166] Further, there is no evidence that Asimakidis said anything to the effect that Kytec was authorised to act on Telstra's behalf, nor did Tutungi give evidence that she relied on anything said by Asimakidis during that conversation;[167]
(b) Asimakidis was copied into certain emails between Telstra and Kytec, including the email dated 23 April 2015, where Kytec provided the Final Proposal to ProLearn. This does not support an agency relationship in circumstances where the unchallenged evidence of Asimakidis is that he did not have any input in the development of the Final Proposal, or the hardware components of the new telephone system,[168] with his role limited to determining the network infrastructure to be provided by Telstra;[169]
(c) Telstra had already approved the agreements and provided these to Kytec, prior to Kytec forwarding them to ProLearn by email of 23 April 2015,[170] and any changes to the Equipment and Services Agreement required Telstra's approval,[171] indicating that Kytec was not authorised to enter into these agreements with ProLearn on Telstra's behalf;[172]
(d) Telstra supplied equipment to ProLearn, and ProLearn paid Telstra, in accordance with the Equipment and Services Agreement. Kytec was not party to the Equipment and Services Agreement. The agreement referenced the Final Proposal in order to more precisely define the equipment to be supplied by Telstra;[173]
(e) Kytec held itself out as a 'partner' of Telstra. However, this is of no probative value in circumstances where the term was used as a commercial, as opposed to legal, concept. Accordingly, this does not demonstrate Telstra consented to Kytec acting as its agent, and ProLearn adduced no evidence that it relied on this statement.[174]
Kytec acting at the direction or with the express or implied consent of an employee or agent of Telstra
178 In addition, Telstra submits that ProLearn's s 84(2) case omits an essential element of deemed liability, in that conduct must be 'on behalf of' the body corporate.[175] ProLearn does not explain how the conduct of Kytec in making the Kytec Representations was engaged in 'on behalf of' Telstra.[176]
180 Telstra submits that the 'Telstra Response' comments, in the email of 23 April 2015 from Kytec to ProLearn are consistent with Telstra's role being limited to determining the network infrastructure;[179] and further, Telstra submits that there is no evidence that Kytec ever sought or obtained input, consent or agreement from Telstra about the Final Proposal.[180]
Whether Telstra made the Telstra Representations
182 Telstra submits that the alleged Telstra Representations do not arise; in particular, upon proper construction, the reference to the Final Proposal in Schedule 1 of the Equipment and Services Agreement did not incorporate by reference the 'core functionality' section of the Final Proposal, as relied on to found the alleged Telstra Representations.[183]
183 Additionally, Telstra submits that it did not impliedly consent or agree to the Kytec Representations, or adopt the Final Proposal, and that ProLearn was well aware that the alleged representations came from Kytec.[184]
184 To the extent that ProLearn relies on the conversation on 22 April 2015, and various emails between the parties, Telstra contends that there is no evidence of conduct of Telstra indicating its consent or agreement to the Kytec Representations,[185] or that Telstra adopted the Final Proposal.[186]
185 In the event that Kytec's conduct in making the alleged Kytec Representations is deemed to be conduct of Telstra, pursuant to s 84(2) of the CCA, Telstra submits that Kytec had reasonable grounds for making the Kytec Representations at the time, for the purposes of s 4 of the ACL.[187]
186 Telstra disputes that Jones v Dunkel reasoning can be employed to infer that Kytec had never previously designed an out-bound call centre, or that Okulicz lacked the relevant experience;[188] and submits that, although Okulicz had not yet written the custom code at the time alleged to be relevant, this does not constitute an absence of reasonable grounds.[189]
187 Telstra relies on Okulicz's evidence that the Cisco PCCE solution with a Cisco Unified Communications Manager, as described in the Final Proposal (rather than the Cisco UCCX),[190] was the most appropriate solution for ProLearn based on Okulicz's understanding that the system supported Personal Call Back Lists,[191] could support up to 1,000 operators,[192] and could integrate with a web-based CRM.[193]
189 Telstra further submits that Telstra's reasonable grounds or lack thereof is irrelevant to ProLearn's s 84(2) case,[197] and that the question is not whether the Solution was ultimately able to create Personal Call Back Lists and to integrate with ProLearn's CRM, or whether it in act enhanced ProLearn's productivity, or was appropriate for ProLearn's requirements.[198]
190 Telstra submits that if it made the alleged Telstra Representations, it had reasonable grounds to do so at the time, such that the representations were not misleading or deceptive.
191 Telstra submits that it reasonably relied on Kytec as a subject matter expert in respect of the Final Proposal, and that it had no grounds to doubt the experience and expertise of Kytec in this regard.[199] Kytec has been a Telstra Dealer since 2010 and specialises in Cisco systems.[200] Kytec has provided services to Telstra customers on large scale projects in the past without issue.[201]
192 Telstra relies on the unchallenged evidence of Leondaris that, upon having regard to the initial enquiry from ProLearn, the view was formed that Kytec had the experience and capability to fulfil ProLearn's requirements.[202] Telstra submits that, while it did not undertake its own assessment of the matters within the Final Proposal, it does not follow that Telstra lacked reasonable grounds to make the Telstra Representations.[203]
193 Telstra highlights that it was not put to either Asimakidis or Leondaris that reliance on Kytec was unreasonable or inappropriate in the circumstances.[204]
194 In the event that Telstra is found to have made the Telstra Representations, Telstra submits that ProLearn has failed to demonstrate that it relied on the representations in the manner alleged, as distinct from the alleged representations in the Final Proposal.[205]
195 In reply to Kytec's submissions, ProLearn argues:
(a) there is no evidence that ProLearn was unable to purchase sufficient leads to satisfy an increase in demand, or that the leads became poorer or less effective, including through the use of 'back data' or 'reharvested leads';[206]
(b) if staffing issues were encountered both pre- and post-implementation of the Solution, as alleged in Kytec's case, then they can be disregarded as the cause of the loss of sales in the post-installation period;[207]
(c) that ProLearn did not employ a dialler manager is irrelevant. Tutungi gave evidence, and Okulicz conceded, that Okulicz did not at any stage tell ProLearn that it should have appointed a dialler manager;[208]
(d) the assertion that ProLearn received a Solution that was appropriate for ProLearn's requirements, and that was in line with Cisco best practice at the time, is to overstate the evidence;[209]
(e) ProLearn did not insist on the Solution going live on 31 August 2015;[210]
(f) ProLearn's case relied on a substantial body of contemporaneous emails, including tickets raised by Kytec, to clearly establish that the problems were widespread and persistent;[211]
(g) Tutungi did not want Kytec to keep testing the to-do lists because, five weeks after the Go Live Date, the function was still causing crashes and had not worked;[212]
(h) both Tutungi and Humunicki identified several problems with reverting to re-enabling the to-do list functionality in the CRM,[213] or having Operators manually call back leads.[214] Notwithstanding, Tutungi's evidence was that 'we did the best we could to manually dial call backs'.[215]
196 In reply to Telstra's submissions, ProLearn asserts that:
(a) the relevant conduct which gives rise to the making by Telstra of the Telstra Representations is the provision by Okulicz to ProLearn of the amended contractual documents on 23 April 2015, containing both the Telstra contracts and the Final Proposal, which ProLearn submits, in the circumstances, was conduct by Telstra itself or Kytec acting as an agent of ProLearn;[216]
(b) ProLearn submits that Telstra earlier approved the contracts supports this position. Telstra is not disclaiming the truth or falsity of the Final Proposal, or passing it on for what it is worth; Telstra approved the Final Proposal, adopted it, and incorporated it into its contractual arrangements;[217]
(c) an act is 'on behalf of' a corporation for the purposes of s 84(2) of the CCA, if the actor engaged in the conduct either intending to do so 'as a representative of' or 'for' the corporation, or in the course of the corporation's business affairs or activities:[218] it is clear that Kytec was providing the contracts, including the Final Proposal, on behalf of Telstra;[219]
(d) the direct evidence of Tutungi was that she entered into the contracts on behalf of ProLearn, because she believed the Solution would have the functionality described in the Final Proposal. This reliance is entirely consistent with the fact that she requested amendment of the contracts to reference the Final Proposal.[220]
A person must not, in trade or commerce, engage in conduct that is misleading or deceptive or is likely to mislead or deceive.
Section 29(1)(g)
(1) A person must not, in trade or commerce, in connection with the supply or possible supply of goods or services or in connection with the promotion by any means of the supply or use of goods or services:
...
(g) make a false or misleading representation that goods or services have sponsorship, approval, performance, characteristics, accessories, uses or benefits.
199 In relation to the operation and application of the above provisions:
(a) Pursuant to s 4(2) of the ACL, 'conduct' includes doing or refusing to do any act;
(b) Conduct is misleading or deceptive if it has a tendency to lead into error;[221]
(c) The making of a representation may constitute 'conduct' for the purposes of s 18 of the ACL;[222]
(d) Whether the conduct is misleading or deceptive is a question of fact to be resolved considering the whole of the impugned conduct in the circumstances in which it occurred;[223]
(e) Section 18 of the ACL is of application to conduct, whatever form it may take, if that conduct is objectively determined to be misleading or deceptive;[224]
(f) The question of whether conduct is misleading or deceptive (or likely to be so) is to be determined objectively, and in respect of the effect or likely effect of conduct upon the minds of those to whom the impugned representations have been made;[225]
(g) Conduct is likely to mislead or deceive for the purposes of s 18 of the ACL if there is a 'real or not remote chance or possibility regardless of whether it is less or more than fifty per cent';[226]
(h) Although s 29(1)(g) of the ACL uses the words 'false or misleading', there is no material difference between those words and the words 'misleading or deceptive';[227]
(i) The word 'make' in s 29(1)(g) is sufficiently wide in meaning to cover not only the person who 'made' the statement in the sense of being its author, but also persons who published the statement.[228] There may be more than one person who makes the relevant misrepresentation and the level of involvement of each person is to be assessed by whether or not each person is found to have made a relevant representation and depends upon the facts.[229]
200 Section 4(2)(a) of the CCA renders warranties contained in contracts 'conduct' for the purposes of the CCA, and consequently, if false or misleading, such warranties will breach s 18 of the ACL.[230]
201 Where the innocent carriage of a false representation from one person to another occurs in circumstances where the former person is a mere conduit, this will ordinarily not give rise to that person making a false representation, provided that the representation is not communicated in a false circumstance where the person with the carriage of the representation would be regarded by the recipient of the false representation as adopting that representation_._[231]
202 Additional considerations apply to representations as to future matters. Section 4(1) of the ACL provides that:
Section 4(1)
(1) If:
(a) a person makes a representation with respect to any future matter (including the doing of, or the refusing to do, any act); and
(b) the person does not have reasonable grounds for making the representation;
the representation is taken, for the purposes of this Schedule, to be misleading.
Section 4(2)
(2) For the purposes of applying subsection (1) in relation to a proceeding concerning a representation made with respect to a future matter by:
(a) a party to the proceeding; or
(b) any other person;
the party or other person is taken not to have had reasonable grounds for making the representation, unless evidence is adduced to the contrary.
204 In North East Equity Pty Ltd v Proud Nominees Pty Ltd, the Full Court of the Federal Court made the following observations in relation to the equivalent provisions in the Trade Practice Act 1974 (Cth):[232]
However, the question of whether a respondent had, at the time of making the representation as to the future matter, reasonable grounds for making it, is particularly illuminated by the knowledge, understanding, or reasoning of the respondent. Section 51A(2) therefore casts an evidential burden on the respondent to adduce evidence on that issue, that is, some evidence... of reasonable grounds for making the representation, failing which the deeming effect of s 51A(2) is engaged thus making it unnecessary for the applicant to prove the second integer under s 51A(1) in order to establish a contravention of s 52. Once evidence is adduced by a respondent in discharge of the evidential burden, the applicant must satisfy the dispositive burden of showing that the respondent did not have reasonable grounds for making the representation.
205 Accordingly, where a representation is made and that representation is with respect to a future matter, s 4 places an evidentiary burden on the person, making the representation to adduce evidence on the issue of whether, in relation to the representation, there were reasonable grounds for making that representation.
206 In essence the effect of s 4 is to deem a representation as to a future matter misleading unless the person who made the representation adduces evidence that there were reasonable grounds for making it.
207 In determining whether a person had reasonable grounds for making a representation, relevant considerations include reference to the knowledge, understanding or reasoning of the person making the representation, to be evaluated at the date of the representation,[233] however, evidence of later events may be considered in relation to the probability that the representation was reasonable at the relevant time.[234]
209 Set out in detail above are the key contents of, and the circumstances surrounding the email and other significant communications between Kytec and Telstra and ProLearn on, and between, about the end of March 2015 and the end of April 2015, including in particular the emails passing between these parties, and the attachments to those emails, on 27 March 2015, 21 April 2015, 22 April 2015, 23 April 2015 and 27 April 2015.
210 It is convenient at this point to again note that ProLearn's pleaded representations against Kytec are:[237]
(a) the Solution would be able to automatically create Personal Call Back Lists (Representation 'A');
(b) the Solution would be able to be used by 83 agents (Representation 'B');
(c) the Solution would have the capacity to be used in the future by approximately 200 agents when ProLearn wished to expand, with the only additional requirement being that ProLearn would have to pay for additional licences (Representation 'C');
(d) the Solution would integrate with ProLearn's CRM for customer information (Representation 'D');[238]
(e) the Solution would enhance the productivity of ProLearn (Representation 'E');
(f) the Solution was appropriate for the ProLearn Requirements (Representation 'F');
(g) such representations were based on reasonable grounds (Representation 'G');
211 To the extent the representations are found to be contained in the Final Proposal, Kytec accepts the representations were made, however Kytec denies that they were misleading and further or alternatively says that Kytec had reasonable grounds for making the representation. Kytec submits that ' ...the representations made in the proposal document were made honestly, based on Mr Okulicz's experience and competence, and the appropriateness of the Cisco PCCE system'.[239]
The Solution would be able to automatically create Personal Call Back Lists (Representation 'A')
212 In respect of the representation that the Solution would be able to be automated to create Personal Call Back Lists, ProLearn asserts that the representation was partly express, comprising written and oral communications, and partly implied. Insofar as the alleged representation is express, ProLearn relies on the telephone conversation between Tutungi, Okulicz and Asimakidis on 22 April 2015 (see [108]); the email from Okulicz to Tutungi, copying Asimakidis, dated 22 April 2015 (see [109]); and pages 6 and 14 of the Final Proposal ([118] and [119]).[240]
213 I accept Tutungi's evidence as to the telephone conversation with Okulicz and Asimakidis on 22 April 2015 and I am satisfied these communications by Okulicz and Asimakidis establish Representation 'A'. Tutungi's evidence on this aspect included that:[241]
During that discussion I told them that the contract doesn't reflect what I'm buying - I'm buying a phone system - the contracts need to state what the system will do, including the To Do List functionality. Mr Okulicz assured me that the new telephone system would include the To Do List functionality and agreed to amend the Solution Overview to make that clear.
214 I note that Tutungi's evidence set out in the preceding paragraph was not challenged in cross-examination, nor contradicted by evidence of Okulicz or Asimakidis.[242] Asimakidis could, if it was fact, have sought to somehow qualify his involvement in the conversation on 22 April 2015, however he did not. For reasons I have outlined below, I consider that the above conversation which Okulicz and Asimakidis had with Tutungi on 22 April 2015 was one in which Okulicz and Asimakidis were jointly communicating with Tutungi and was one in which those two men in substance spoke with the one voice.
215 I am satisfied that the email from Okulicz to Tutungi of 22 April 2015 in which Okulicz states that the 'proposed inclusions for the Cisco solution components' comprise, among other things, '[i]ntegration services to automatically create individual call back lists',[243] and by which Okulicz invited Tutungi to confirm that the content of the email 'covers what you want to see in the proposal so we can finalise our response back to you', also establishes that Kytec and Telstra made Representation 'A' to ProLearn.[244]
216 ProLearn also relies on page 6 of the Final Proposal, which sets out what the 'core functionality' of the Solution will provide, including, '[i]ntegration services to automatically create individual agent call back lists'.[245]
217 I find that the above statements in the Final Proposal further establish that Kytec and Telstra made Representation 'A' to ProLearn on 22 April 2015.
218 Further, I consider that Representation 'A' was expressly communicated by the Final Proposal which Kytec emailed to ProLearn on 23 April 2015 ([111] and [112]) in response to the conversation between Tutungi, Okulicz and Asimakidis on 22 April 2015, and for reasons I have separately outlined both Kytec and also Telstra made Representation 'A' to ProLearn.
219 I also find that ProLearn communicated to Okulicz of Kytec and Asimakidis of Telstra that the 'to-do list' facility was a critical capability of the required telephone system. In the Tutungi First Witness Statement, Tutungi stated that she communicated to Kytec and Telstra that the 'to-do list' was a critical part of ProLearn's business and she could not purchase a system that did not have this functionality.[246] This evidence was neither contradicted nor challenged by Kytec or Telstra.
220 Tutungi also states in the Tutungi First Witness Statement that, as a result of the telephone conversation between her, Okulicz and Asimakidis on 22 April 2015; Okulicz's emails of 22 April 2015 and 23 April 2015; and the circumstances of the provision of the contractual documents and Final Proposal and their content, she believed that the Solution would have the following features:[247]
(a) it would be able to automatically create Personal Call Back Lists;
(b) it would be able to be used by 83 Operators;
(c) it would be scalable, so that ProLearn could expand the number of operators to as many as 200 if it wished (save that it would have to buy additional handsets);
(d) it would integrate with ProLearn's CRM;
(e) it would enhance ProLearn's productivity;
(f) it was appropriate for ProLearn's requirements;
(g) that Kytec and Telstra believed that the Solution had the features in (a)-(f).
I accept Tutungi's evidence in this regard and I am satisfied that Tutungi held the above belief by about the last week of April 2015.
221 Tutungi's evidence was also that, had she known the Solution did not have the features set out in the preceding paragraph, or had she known that Kytec and Telstra did not have a reasonable basis on which to believe the Solution had those features, she would not have entered the subject agreements.[248]
222 I accept Tutungi's evidence and find that had Tutungi known that the Solution did not have the above features, or had she known that Kytec and Telstra did not have a reasonable basis for believing that the Solution had the said features, she would not have permitted ProLearn to enter into the contracts it did.
The Solution would be able to be used by 83 agents (Representation 'B')
223 ProLearn submits that the representation in substance that the Solution would be able to be used by 83 agents was partly express, comprising written and oral communications, and partly implied. Insofar as it is express, ProLearn contends that the representation arises from a conversation between Tutungi and Okulicz alleged to have taken place in early February 2015. I am however not satisfied on the evidence that a conversation including the substance of Representation 'B' occurred in early February 2015.
224 ProLearn also relies in relation to Representation 'B' on the email from Okulicz to Tutungi dated 22 April 2015; and pages 5, 6 and 14 of the enclosed Final Proposal.[249]
225 I find that the email of 22 April 2015 from Okulicz to Tutungi establishes that Kytec made Representation 'B' to ProLearn on that date because in that written communication Okulicz proposes the 'inclusions for the Cisco solution components' with, amongst other things, 'Inbound/Outbound Licensing for 83 Agents',[250] and 'Audio recording and Quality Management for 83 Agents'.[251]
226 I also find that Representation 'B' was made to ProLearn by Kytec and also by Telstra in the written statements at pages 5, 6 and 14 of the Contact Centre Solution Overview attached to the Telstra letter of 23 April 2015 signed by Donohoe, Director Technical Sales, Telstra Business, which was forwarded to ProLearn by Kytec email, and which refers to '83 agents' and '83 concurrent users'.
227 The written statements at pages 5, 6 and 14 of the Final Proposal, constituted by the Contact Centre Solution Overview dated 23 April 2015, I consider establish that both Telstra and Kytec made Representation 'B' by in substance both communicating their proposed contractual response to ProLearn's requirement for 83 agents, namely 'Personal Call backs for 83 agents'[252] and 'Inbound/Outbound Licensing for 83 Agents - Audio recording and Quality Management for 83 Agents' and 'Contact Centre Licencing for 83 concurrent users'.[253]
228 I also find that there is further implied support for Representation 'B' because Kytec recommended the Solution in circumstances where it knew that ProLearn was going to commence operating from the La Trobe Street premises with 83 Operators.[254] Tutungi received an email from Okulicz on 25 March 2015 advising that the three year price for 83 agents was $285,450.[255]
229 I also accept Tutungi's evidence that, as a result of the matters set out above, including the discussions between her, Okulicz and Asimakidis on 22 April 2015, Tutungi believed the Solution would be able to be used by 83 Operators.[256]
The Solution would have the capacity to be used in the future by approximately 200 agents when ProLearn wished to expand, with the only additional requirement being that ProLearn would have to pay for additional licences (Representation 'C')
230 ProLearn alleged that Representation 'C' set out at [142(c)] was partly express, comprising verbal communications between ProLearn and Kytec, and partly implied.
231 Insofar as it is express, ProLearn pleads that the representation was made in a conversation between Tutungi and Okulicz which took place in early February 2015.
232 However, I am not satisfied that on the evidence a conversation alleged to this effect occurred at about that time, nor am I satisfied as to any implied basis upon which Representation 'C' can be supported.
233 Further, I am unpersuaded that it is open to imply such a representation on the basis that Kytec recommended the Solution in circumstances where it knew that ProLearn intended to expand to using up to 200 Operators.[257]
234 It is not sufficient that Tutungi's evidence is that, following discussions between Tutungi, Okulicz and Asimakidis on 22 April 2015, Okulicz's emails of 22 April 2015 and 23 April 2015, and the provision of the contractual documents and the Final Proposal and their content, she believed the Solution:[258]
...
(c) ...would be scalable, so that ProLearn could expand the number of operators to as many as 200 if it wished (save that it would have to buy additional handsets)...
235 Accordingly, I do not find Representation 'C' to be made out.
236 Finally, I note that although ProLearn did not expressly abandon Representation 'C', the existence of Representation 'C' was not pressed in ProLearn's Closing Submissions (see [50], ProLearn Closing Submissions).
The Solution would integrate with ProLearn's web-based CRM for customer information[259] (Representation 'D')
237 ProLearn alleged that Representation 'D' was partly express, comprising the Final Proposal, and partly implied.
238 At various points of the Final Proposal, including as recorded in the requirements sought by ProLearn, it is reflected that ProLearn required an 'Integration to web-based CRM for customer information'.[260]
239 Representation 'D' was both referred to and expressly made in the Final Proposal, for example, at pages 3, 5, 6 and 16 (see, for example, [117] and [118]).[261] Accordingly, I am satisfied that Kytec represented to ProLearn, by the contents of the Final Proposal, that the Solution would integrate with a web-based CRM for customer information.
240 As part of a number of amendments to ProLearn's Amended Statement of Claim, ProLearn deleted the earlier reference to the Solution integrating with a CRM which was web-based.
241 Further, it is common ground that ProLearn did not move to a web-based CRM.
242 Finally, ProLearn did not press Representation 'D' or ultimately rely on Representation 'D'. This is clear from ProLearn's Closing Submissions at [50]. Further, during his final submissions, Senior Counsel for ProLearn announced that: 'we don't press the claim for a misrepresentation with respect to the integration of the CRM' (T1199.14-16).
243 It is therefore of no moment either that the above mentioned written representations about the Solution integrating with a web-based CRM were made, or that Tutungi's evidence was that she believed the Solution would integrate with ProLearn's CRM.[262]
244 For the above reasons I make no ultimate finding about Representation 'D'.
The Solution would enhance the productivity of ProLearn (Representation 'E')
ProLearn are looking to enhance their existing call centre environment to include an outbound dialler that will integrate with their CRM. The solution will enhance the productivity of ProLearn and assist in driving the business forward as growth is a major focus.
246 I am satisfied that by the second sentence of the Final Proposal, Representation 'E' was expressly made by Kytec to ProLearn at the time the Final Proposal was communicated to ProLearn.
The Solution was appropriate for the ProLearn Requirements (Representation 'F')
247 ProLearn submitted that Representation 'F' is to be implied by the fact that Kytec suggested or recommended the Solution in circumstances where Kytec had relevant specialised skills and knowledge in relation to the implementation of telephone networks and knew of the ProLearn Requirements, and from the statement at page 16 of the Final Proposal.
248 The Final Proposal provided in the 'Conclusions' at page 16 that:
Kytec is of the strong belief that this proposal will provide ProLearn the level of service and IT performance that they require. ProLearn require the services of a company that not only understands the unique requirements of the Business but also possesses the technical expertise to provide user support, network support, monitoring services, systems upgrades and technical advisory services.
249 Further, for the reasons I have outlined in relation to my findings in respect of Representations 'A', 'B' and 'E' above, I consider that Kytec also made Representation 'F'. In my view, it went without saying that each of the said established Representations carried with them the clear representation by Kytec and Telstra that the Solution was appropriate for the ProLearn Requirements.
250 I also consider that the statements under 'Conclusions' summarised at page 16 of the Final Proposal[265] itself establishes that Kytec, and Telstra for the reasons I have separately outlined, made Representation 'F' to ProLearn, at about 22 April 2015 and 23 April 2015.
251 Although her belief is not material to establishing the fact of Kytec making Representation 'E', I also note that Tutungi's evidence was that, based on discussions she had with Okulicz and Asimakidis, and the circumstances around the provision of the contractual documents and the Final Proposal, and the content of those documents, she believed the Solution would enhance ProLearn's productivity and be appropriate for the ProLearn Requirements.[266]
252 On the above bases, I find that Representation 'F' was made to ProLearn by Kytec and by Telstra, including on 22 April 2015 and 23 April 2015.
Each of the Kytec Representations was based on reasonable grounds (Representation 'G')
253 ProLearn submits that Representation 'G' was to be implied based on the fact that Kytec held itself out as having the expertise to provide the Solution and by the subsequent provision of the Solution.
254 I am satisfied that the combination of the circumstances and matters which I have referred to above in relation to the establishment of Representations 'A', 'B', 'E' and 'F' also give rise, by necessary implication, to Representation 'G'. In the established context referred to above in relation to Representations 'A', 'B', 'E' and 'F', I consider that each of those Representations individually and also cumulatively, also represented to ProLearn that Kytec and that Telstra had reasonable grounds upon which they based each of the established Representations.
255 I am also satisfied by Tutungi's evidence that she believed that Kytec had reasonable grounds for making each of the established Representations and that she, and for that reason ProLearn, believed the Solution was capable of meeting the ProLearn Requirements.[267] Further, I am satisfied on ProLearn's evidence that had ProLearn, through Tutungi, known Kytec did not have a reasonable basis to hold such belief, she would not have entered into the subject Contracts and arrangements with Telstra and Kytec.[268]
256 Accordingly, for the above reasons, I find that ProLearn has established that Kytec made Representations 'A', 'B', 'E', 'F' and 'G'.
257 I make no ultimate finding in relation to ProLearn's alleged Representations 'C' and 'D' for the reasons also outlined above and because they were not pressed by ProLearn.
Kytec made the Kytec Representations as an agent of Telstra, or with the express or implied consent of an agent or employee of Telstra
258 I also find that the impugned conduct alleged to give rise to the Kytec Representations is to be imputed to Telstra pursuant to s 82(2) of the CCA. That provision of the CCA is set out earlier in these Reasons.
259 In this regard I find that in making the Kytec Representations, Kytec did so as Telstra's agent within the meaning of s 82(2)(a) of the CCA, and that Kytec made those representations within the scope of its actual or apparent authority, with the effect and consequence that the Kytec Representations were at law also made by Telstra to ProLearn.
260 I consider that the relevant agency relationship and apparent authority is to be implied from the following matters:
(a) ProLearn's early enquiry to Telstra in relation to a new telephone system was immediately passed through to Kytec and Kytec I infer contacted ProLearn to discuss the provision of a telephone system directly as a result of Tutungi initially making enquiries of Telstra;[269]
(b) the above detailed conversations and meetings between ProLearn and Kytec, including meetings and conversations between Tutungi and Okulicz of Kytec and Asimakidis of Telstra referred to above following the receipt of the First Proposal on 11 February 2015 and proposed Telstra contracts on 27 March 2015;
(c) the First Proposal and the Final Proposal provided to ProLearn by Kytec and Telstra expressly stated that Kytec was partnered with Telstra and with Cisco in relation to the provision of the NTS Solution;
(d) Telstra's authorisation of Kytec to deal with ProLearn in relation to contractual communications and negotiations, including the forwarding of Telstra letters addressed to ProLearn and agreements, to which Telstra but not Kytec was party, to ProLearn under cover of emails, for example, the emails from Okulicz of Kytec on 27 March 2015 and 23 April 2015;
(e) that the Solution was to be and was ultimately delivered to ProLearn by the provision of hardware, software and services by Telstra under the Equipment and Services Agreement, the Data Contract and the Telephone Contract;[270]
(f) emails between Kytec and ProLearn in relation to contractual proposals and negotiations in April 2015 were sent by Kytec to ProLearn, with Telstra copied in, and such agreements included were agreements to which Telstra, not Kytec, was party;
(g) the terms of Schedule 1 to the Equipment and Services Agreement, 'Additional Equipment', including, amongst other things, that Telstra was to provide:
1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal to ProLearn
(h) ProLearn made all payments in connection with the Solution to Telstra, with the exception of payments made to Kytec pursuant to the Kytec Contract;[271]
(i) The covering letter for the Equipment and Services Agreement was signed by Donohue of Telstra but was provided by Kytec to ProLearn, and Asimakidis of Telstra was copied in, by email of 23 April 2015.[272]
261 Furthermore, I find for the above reasons that in making Representations 'A', 'B', 'E', 'F' and 'G' Kytec acted with the apparent authority or actual consent of Asimakidis of Telstra, including for the purposes of s 84(2)(b) of the CCA.[273] I am further satisfied on the same bases that Asimakidis of Telstra was acting within his apparent or actual authority from Telstra in doing so. I consider that this is sufficiently established by the following:
(a) Through Asimakidis' involvement, Telstra participated in the telephone call of 22 April 2015;
(b) Telstra was a party to the emails of 22 April 2015 and 23 April 2015;
(c) the attachments to the email of 23 April 2015 included the Final Proposal and Telstra contractual documents, including Schedule 1 to the Equipment and Services Agreement which provided, inter alia, that Telstra was to provide '1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal to ProLearn';
(d) Donohue, Telstra's Director Technical Sales, Telstra Business, signed the letter of 23 April 2015, which included a proposal and Telstra contract documents which was forwarded to ProLearn by Kytec;
(e) the statement in the First Proposal and the Final Proposal that Kytec exclusively partnered with Telstra to deliver on requests from customers (at page 5 of the Proposal);
(f) by emails on 27 March 2015 Kytec was authorised by Telstra to provide Telstra agreements to ProLearn;
(g) the Solution was provided to ProLearn comprising hardware, software and services from Telstra, and ProLearn paid Telstra for the associated services except for those services provided by Kytec, after the Solution had been installed.
262 I consider that in the circumstances established by the above events and communications the active participation of Kytec, by Okulicz, and of Telstra by Asimakidis, and in particular in the conversation outlined above which they had with Tutungi on 22 April 2015, in substance expressly proffering written terms of agreement and deliverables, amended as specifically required by Tutungi of ProLearn, constituted the making of Representations 'A', 'B', 'E', 'F' and 'G' by Kytec and Telstra jointly, and also constituted the making of Representations 'TA', 'TB', 'TD' and 'TE' by Telstra, discussed below.
263 I also find that by providing the Final Proposal in the circumstances outlined above, the Kytec Representations[274] were also made by Telstra, by its agent Kytec in accordance with s 84(2) of the CCA. Kytec's conduct and particularly its conduct by Okulicz, together with Asimakidis, constituted by their conversation with Tutungi on 22 April 2015, and the Kytec emails of 22 April 2015 and 23 April 2015 which contained letters direct to ProLearn from Telstra, and put forward contract documents containing Telstra promises, establish that Okulicz and Kytec had either the actual or at least the apparent authority of Telstra to deal with proposed Telstra contractual promises and warranties in respect of the Equipment and Services Agreement, and specifically Schedule 1 referring to the Solution and the Final Proposal.
264 I also find that for the above reasons, the central representation made by Kytec and Telstra to ProLearn in April 2016 was that the Solution which they would provide had as a core deliverable, personal call backs and automatically created individual agent call back lists for 83 agents.
265 I also find that in the above circumstances ProLearn was entitled to conclude, as I am satisfied it did, that Kytec had Telstra's authority to make the representations it did. Furthermore, I am satisfied that ProLearn was entitled to conclude, as I am satisfied it did, that Kytec had Telstra's apparent authority to make the central representation to ProLearn referred to above. Namely, that the Solution which would be provided by Telstra to ProLearn was one which had as a core capability the ability to make automatic personal call backs for individual agent call back lists for 83 agents.
266 The nature and extent of the apparent authority referred to arose from the above detailed circumstances and communications between Telstra and Kytec and ProLearn, and in particular the circumstances that very promptly after Kytec's initial enquiry of Telstra in relation to a call centre telephone system, Telstra referred ProLearn to Kytec.
267 I also consider that such authority in Kytec was reasonably inferred by ProLearn from the documentation sent to ProLearn from Telstra and Kytec which referred to Telstra and Kytec as partners in relation to recommending and supplying telephone related equipment and from the fact that Kytec was a Telstra 'dealer'.
268 Further key contractual communications such as Okulicz's emails of 27 March 2015 and 22 April 2015 and 23 April 2015 forwarding proposals and letters from Telstra to ProLearn, in a way and in respect of proposed Telstra contractual materials, in my view, made it clear to ProLearn that Telstra had vested authority in Kytec to communicate on Telstra's behalf in relation to what was being promised by Telstra and Kytec in relation to the Solution. The communication to ProLearn of the proposed contract documents, and of the amendments to those documents, from Telstra and Kytec in a co-ordinated and in substance joint manner I consider made that clear to ProLearn, in the circumstances, that Kytec had Telstra's authority to communicate and deal with matters including contractual matters in relation to the subject supply of call centre telephone systems, to ProLearn on behalf of Telstra.
269 I consider that the fact that the Dealership Agreement between Telstra and Kytec characterises Kytec as an 'independent contractor' does not preclude the agency relationship which I am satisfied existed at the relevant time, namely at least throughout April 2015. This is particularly so here in the setting of the above detailed dealings and transactions between the parties in about April 2015, in particular Kytec and Donoghue's email and letter respectively of 23 April 2015 and the conversation between Asimakidis and Tutungi and Okulicz on 22 April 2015 and the Kytec emails of 22 April 2015, earlier detailed.
270 Furthermore, I consider that Telstra's employee Asimakidis by his actions consented to the Kytec representational conduct described above. Furthermore, I also find Asimakidis' consent was, from Tutungi's perspective, within the scope of his authority from Telstra and would also have been so understood from the perspective of any other reasonable commercial person informed by the relevant context.
271 Accordingly, I am satisfied that Asimakidis enjoyed apparent or actual authority, conferred upon him by Telstra for the purposes of s 84(2)(a) and (b) of the CCA in relation to all the communications involving Telstra in connection with all the Representations which have been established.
272 I find that Telstra made representations to ProLearn (Telstra Representations) that:
(a) the Solution would be able to automatically create Personal Call Back Lists (Telstra Representation 'TA');
(b) the Solution would be able to be used by 83 Operators (Telstra Representation 'TB');
(c) the Solution would perform in accordance with supplier (Kytec) specifications (pursuant to the Final Proposal) for 12 months from the date on which ProLearn completed a customer acceptance certificate (Telstra Representation 'TD');
(d) the above representations were based on reasonable grounds (Telstra Representation 'TE');
(collectively, the Telstra Representations).[275]
273 Further, to my finding that for the purposes of s 84(2) of the CCA Kytec communicated with ProLearn with the actual or apparent authority of Telstra. In this regard I am satisfied that Tutungi regarded the amendment to the Equipment and Services Agreement, as a clear statement by Telstra that it was standing behind the Kytec PCCE Proposal, and at that time the Final Proposal, and that Telstra was also promising to provide the Solution to be implemented, and which was capable of performing in accordance with the Final Proposal.
274 ProLearn also relies on the terms of the Final Proposal and the Equipment and Services Agreement; in particular, Schedule 1, which was amended following the telephone discussion between Tutungi, Okulicz and Asimakidis, on 22 April 2015, to include in the schedule of Equipment:
1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal to ProLearn.
275 I consider that by participating in the telephone conversation on 22 April 2015, and being provided by Okulicz with the amended contractual documents on 23 April 2015, and subsequently accepting the updated Equipment and Services Agreement signed and returned by Tutungi, Telstra in substance communicated to ProLearn that Telstra and Kytec invited ProLearn to contract with it on the basis that, amongst other things, Telstra would provide the Solution implemented in accordance with the Final Proposal.
276 I find, in the circumstances outlined above, that both Telstra and Kytec engaged in conduct constituted by representations to ProLearn that Telstra would provide the Solution to be implemented in accordance with the Final Proposal, and that the Solution would have as one of its central capabilities, an automatically generated individual agent call back lists for 83 Operators. These representations (Telstra Representations 'TA' and 'TB') and Telstra Representations 'TD' and 'TE', were made by Telstra, as detailed above in Telstra's letter to Tutungi of ProLearn dated 23 April 2015, enclosed with Kytec's email dated 23 April 2015, and by Asimakidis and Okulicz effectively joint statements, also detailed above, to Tutungi on 22 April 2015.
277 I also find that the representations identified in the last preceding paragraph were made in the Final Proposal which its conduct outlined above, Telstra clearly adopted including by contracting to provide the Solution which was the essence of the Final Proposal.
278 For the reasons I have outlined above, I have also found that Kytec's representational conduct is conduct which is to be imputed to Telstra pursuant to s 84(2) of the CCA.
279 Kytec's conduct which is to be imputed to Telstra includes the provision by Okulicz to Tutungi on 23 April 2015 of:
(a) the Equipment and Services Agreement, specifically Schedule 1 to that agreement, which incorporated by reference to the Solution to be provided by Telstra in accordance with the Final Proposal; and
(b) the Final Proposal as part of the suite of contractual documentation.
280 I have also found the above circumstances gave rise to it being reasonable for ProLearn to infer Telstra's authority, assent and consent to Kytec acting as Telstra's agent in relation to the subject dealings and transactions. I am satisfied that the Telstra Representations were expressly communicated by Telstra to ProLearn by said Contract Centre Solution Overview dated 23 April 2015, and for the same reasons I have outlined above in relation to Representations 'A', 'B', 'E' and 'F', and further were also communicated by Telstra to ProLearn by the Corporate Services Agreement which identified the Additional Equipment to be provided by Telstra via Kytec under cover of a Telstra letter dated 23 April 2015 as comprising:
1 x Soluiton [sic] to be implemented per version 2.1 of the Kytec PCCE Proposal
281 I also find that as a result of both Kytec making Representation 'F', and Telstra also making Representations 'TD' and 'F' by its agent Kytec, both Kytec and Telstra made representations as to the performance characteristics, use and the benefits of the Solution.
282 I note Tutungi's evidence in cross-examination in relation to the circumstances of the amendment of the Equipment and Services Agreement, and the provision of the Equipment and Services Agreement and the Final Proposal on 23 April 2015, was:
Kytec gave me this document. And this document was amended after a conversation I had with Andrew Asimakidis of Telstra and David Okulicz of Kytec. They both contributed to that conversation. And amendments were made to this document specifically at my request, after I had that three-way conversation with them. And the reference to the partner with Telstra - I felt that this was a - this was both of them giving me this proposal - the both of them offering me this opportunity.[276]
So the conversation with Mr Asimakidis and Mr Okulicz was that I was unhappy with the contract as it had been supplied by Telstra and that I wanted changes to the contract. And that I wanted the contract to refer to the proposal and I wanted the proposal to be clearer on what I was getting for my money - the money that I was paying Telstra. I directed that both to Mr Asimakidis and Mr Okulicz.[277]
It's probably a bit of an overreach to - for me to say that I assumed that Telstra were making the comments in the proposal, but I went to the effort of making sure the proposal was included in the contract and I initialled every page of that proposal for the very reason that I wanted to rely on enforcement of that proposal against Telstra, who was the party I was contracting with. That is what I turned my mind to, and that is why I took the action that I took.[278]
The view I took was that Telstra and Kytec were standing behind the proposal, and that the proposal clearly set out what I was going to get for my money and, therefore, the proposal needed to be included in the contract.[279]
283 I am also satisfied that, as a result of the matters referred to in the last preceding paragraph, Tutungi understood the reference to the 'Kytec PCCE Proposal' and the terms of the Equipment and Services Agreement, as tantamount and amounting to a statement, effectively by Telstra that it was binding itself to the provision of the Solution in accordance with the Final Proposal.[280]
284 I find, for the same reasons as I have outlined above in relation to Representation 'G', that Telstra made Telstra Representation 'TE'.
285 I also find for the same reasons as in respect of Representations 'A', 'B', 'E' and 'F', that Telstra Representations 'TA', 'TB' and 'TD' were representations as to future matters, as, I consider, is similarly self-evident in relation to the specified Telstra Representations.
286 Finally, I find that each of the above established Representations made by Kytec and by Telstra were made in trade and commerce, as is in my view clear from the nature of the parties' subject dealings, and the commercial context of those dealings and also from the nature and purpose of the transactions in relation to which those representations were made.
287 I find that, for the purposes of s 18 of the ACL, both the Kytec Representations and the Telstra Representations, other than representations as to reasonable grounds itself, were representations as to future matters, and accordingly s 4 of the ACL applies. This is because it is self-evident from the terms and nature of Representations 'A', 'B', 'E' and 'F' and also Telstra Representations 'TA', 'TB' and 'TD', that those representations are in respect of future matters.
(1) If:
(a) a person makes a representation with respect to any future matter (including the doing of, or the refusing to do, any act); and
(b) the person does not have reasonable grounds for make the representation;
the representation is taken, for the purpose of this Schedule, to be misleading.
(2) For the purposes of applying subsection (1) in relation to a proceeding concerning a representation made with respect to a future matter by:
(a) a party to the proceeding; or
(b) any other person;
the party or other person is taken not to have had reasonable grounds for making the representation, unless evidence is adduced to the contrary.
(3) To avoid doubt, subsection (2) does not:
(a) have the effect that, merely because such evidence to the contrary is adduced, the person who made the representation is taken to have had reasonable grounds for making the representation; or
(b) have the effect of placing on any person an onus of proving that the person who made the representation had reasonable grounds for making the representation.
(4) Subsection (1) does not limit by implication the meaning of a reference in this Schedule to:
(a) a misleading representation; or
(b) a representation that is misleading in a material particular; or
(c) conduct that is misleading or likely or liable to mislead;
and, in particular, does not imply that a representation that a person makes with respect to any future matter is not misleading merely because the person has reasonable grounds for making the representation.
289 By force of the above provisions of s 4 the CCA, an evidentiary onus is placed upon Kytec and Telstra to establish reasonable grounds for making the subject representations. I consider that for the reasons which follow, Kytec and Telstra have failed to do so.
290 Evaluating the state of the representators' state of mind at the date when Kytec and Telstra proffered the relevant contract, namely, 23 April 2015, I find that there is insufficient evidence that Asimakidis, or any person at Telstra, had reasonable grounds for making the Telstra Representations which have been established.
291 This is because I am satisfied that neither Asimakidis nor any other person at Telstra had read, let alone considered or analysed the Final Proposal, prior to it being sent to Tutungi on 23 April 2015. Further, I am also satisfied that Telstra had at that date not turned its mind to the contents of the Proposal and had not formed a view as to both whether the Cisco based Solution could or would have the capacity or functionality to meet ProLearn's requirements, including because ProLearn's requirements were in respects bespoke and unlikely to be satisfied by standard proprietary telephone systems, without undefined customisation, or Telstra's capacity to supply the Solution being represented.
292 Further, I do not consider that Telstra's evidence in the particular circumstances of this matter approaches amounting to prima facie evidence that Telstra had reasonable grounds for making the established Telstra Representations 'TA', 'TB' and 'TD' and Representation 'F' for which it was responsible, as explained above. This is because Telstra gave no substantial thought to identifying or understanding ProLearn's business, its operations or its requirements. In my view, because of this, it does not avail Telstra to attempt to rely on Okulicz's or Kytec's technical skill and experience, or that of Cisco. Telstra could not reasonably conclude that these matters gave it reasonable grounds to make the representations it did because it did not appreciate, or seek to appreciate, ProLearn's business or its requirements and therefore did not know that ProLearn's requirements would necessitate the supply and installation of a bespoke NTS different to any Cisco proprietary product and also therefore did not appreciate that Kytec had not ever itself designed a comparable call back telephone system to the one required.
293 For the above reasons, I consider that Telstra has failed to satisfy the required evidentiary burden and accordingly I am satisfied on the deemed basis arising by operation of s 4 of the ACL, also otherwise, that Telstra had no reasonable grounds to make Representations 'TA', 'TB', 'TD' and 'F'.
294 Furthermore, I am satisfied that Telstra has failed to establish that it had reasonable grounds for any belief on its part that it was able to provide the Solution or its part of the Solution, or that the Solution would, or was likely to, fulfil the established Representations.
295 I also accept that Leondaris forwarded ProLearn's initial enquiry to Okulicz (of Kytec) very promptly after it was received from ProLearn and that Telstra gave no further consideration to ProLearn's specific requirements or the capacity or functionality of any available Telstra supplied telephone system to satisfy ProLearn's specific requirements. I also accept that Leondaris lacked any knowledge at that time of the nature of ProLearn's business and its requirements.
296 In relation to Kytec, I am satisfied and find that Kytec lacked reasonable grounds for making the established Kytec Representations, because I am satisfied that:
(a) There is an insufficient evidentiary basis upon which to conclude or find that Kytec had previously designed a telecommunications system for an out-bound call centre. Okulicz did not purport to establish such prior experience or necessary expertise;[281]
(b) Okulicz had not previously written or designed customisation necessary to provide a telecommunications system with Personal Call Back Lists for 83 Operators, or a similar system. In this regard, Okulicz admitted in cross-examination that he had neither written nor tested the customisation for Personal Call Back Lists at the time of providing the Final Proposal to ProLearn on 23 April 2015.[282]
297 Finally, in respect of both Kytec and Telstra, I reject as insufficient Kytec's assertions that it had reasonable grounds upon which to make the Kytec Representations or the Telstra Representations because they were utilizing a suitably capable Cisco Solution. This is because the evidence establishes that the Cisco proprietary Solution would not itself be suitable for ProLearn's requirements without bespoke modification. Customization in a manner and to an extent undefined at about the end of April 2015 would be necessary.
298 Furthermore, I reject, for reasons which I have earlier outlined, Kytec's submission that the Representations were not misleading and deceptive because it had reasonable grounds to recommend the Solution.
299 I also reject that ProLearn itself did not meet its own requirements, such as moving to a web-based CRM. I consider that ProLearn's conduct, including in relation to moving to a web-based CRM, was not a material cause of the relevant difficulties and disfunctions ProLearn suffered with the Solution. This is because I am not satisfied that there is evidence to conclude that a web-based CRM would have better integrated with the Solution. Furthermore, Okulicz agreed that he did not say that because ProLearn did not convert to a web-based CRM it experienced problems with the Solution.[283]
300 I do not accept Kytec's contention that no witness established that the Solution was inappropriate and, at most times, ProLearn was able to make manual calls and personal call backs, either using the Call Back Workaround, paper lists, or its existing CRM.[284]
301 I am comfortably satisfied that the Solution was, as was evident from early in its deployment, replete with problems and deficiencies, incapacities and dysfunctional features as established, I consider, in detailed by ProLearn's first hand direct evidence and contemporaneously corroborated by ProLearn's written notifications and complaints to Kytec and to Telstra.[285] I consider that this evidence, which I accept, established that the Solution was inappropriate.
302 This same evidence I also consider establishes that ProLearn's limited ability to make call backs (using the Call Back Workaround) Lists or its old CRM was not nearly satisfactory and left ProLearn's call centre operations significantly impaired and inefficient.
303 Further, I am also satisfied for the same reasons as those outlined above in relation to Kytec and Telstra making Representation 'F', such representations also constituted a prohibited representation by both Kytec and Telstra with respect to the performance characteristics, uses and benefit of the Solution.
304 I am satisfied that in entering into the Equipment and Services Agreement, the Data Contract and the Telephone Contract on 27 April 2015, and the Kytec Contract on 7 October 2015, and between late August 2015 and early September 2015 abandoning its old telephone and database system and commencing to use the Solution and relocating its business to the La Trobe Street premises, ProLearn acted on the truth of Representations 'A', 'B', 'E', 'F', 'G' and Telstra Representations 'TA', 'TB', 'TD' and 'TE'.
305 I accept ProLearn's submission that Tutungi's evidence regarding her reliance upon the representations necessary to establish causation, for the purposes of s 236, was 'barely challenged' and ought to be accepted.
306 I am satisfied that ProLearn relied upon each of the established Representations by Kytec and by Telstra, and acting on the truth of those Representations decided to and did enter into the Equipment and Services Agreement, and the Telephone Contract, and the Data Contract and the Kytec Contract, and from September 2015 started using the Solution. This is established by the evidence of Tutungi, which I entirely accept.[286]
307 I reject that it is not established that ProLearn relied on each of the established Kytec Representations and each of the established Telstra Representations. I consider that, in all the circumstances, in particular the circumstances in relation to each of the individual established Representations, ProLearn's evidence established that ProLearn relied on the subject Representations in relation to the Solution and each of its material attributes and ProLearn also relied on the functionality and performance capabilities of the NTS Solution.[287]
308 I also find that the established Kytec Representations and the established Telstra Representations, and each of them, continued until at least the time at which ProLearn entered into the Kytec Contract on 7 October 2015.
309 I do not accept that ProLearn's operational problems and losses were in any substantial respect caused by:
(a) ProLearn's staffing issues both pre- and post-implementation of the Solution, including high turnover and absenteeism.
I am unpersuaded by the above contention because logically any staffing issues causing ProLearn loss both before and after installation would balance each other out and would not cause a comparative loss of sales in the period after the installation of the Solution. I am also not persuaded that staffing issues resulted in any material cause of loss.
(b) ProLearn not employing a dialler manager to manage its phone system.
Similarly, I am not persuaded that a dialler manager to manage the Solution, or the absence of a dialler manager, has been established as having any particular effect on ProLearn's operations. Furthermore, Kytec did not recommend the need for a dialler manager and Tutungi's evidence was that she was not aware that a dialler manager was necessary or desirable.
(c) ProLearn being unable to purchase sufficient leads to satisfy the increase in demand experienced as a result of the Automated Dialler, and the consequence of ProLearn's poor quality leads.
I do not accept that the decline in ProLearn's sales following the installation of the Solution was to any material degree caused by ProLearn not being able to procure the required number of leads, or as a result of the quality of leads. Although Humunicki's evidence mentioned her loosely-founded and aspirational upper level target for leads, in my view there is not firm evidence that ProLearn's revenue was materially reduced because it lacked sufficient leads or materially affected by what have been referred to in the evidence as 'black data' leads, or leads of otherwise poor quality.
In this respect I also do not accept that there is any basis upon which to place weight on what I regard as the unrepresentatively small number of example calls played back during the trial of this matter.
Accordingly, I am not satisfied either that the position with ProLearn's leads was materially different after installation of the Solution or was causative of ProLearn's decline in revenue after installation.
(d) Changes in ProLearn's business, government restrictions, and the loss of credibility of the VET sector generally.
I underscore and highlight my earlier evaluation of the evidence of Tutungi and Humunicki, both of whom were impressive, accurate and frank in their evidence and convincingly established their detailed understanding of ProLearn's operations and what was in fact affecting ProLearn's operations from time to time.
I add that although Humunicki had no formal accounting qualifications or other financial qualification or the like, her evidence exhibited a deep understanding and ability to evaluate ProLearn's operation including its financial operations and the factors impacting ProLearn.
In relation to Kytec and Telstra's case, I am persuaded by the detailed evidence given in the Tutungi First Witness Statement at [222]-[226], that before January 2017, changes to the regulatory environment in which ProLearn's business operated, had no significant impact on ProLearn's business, and caused only negligible increases in operating costs.
Further, the Tutungi Reply Witness Statement at [7]-[27], in particular [8(c)], [10], [19] and [27], provided firm and clear evidence that the legislative changes which occurred in 2015 and 2016 had no material impact on ProLearn's business. Humunicki confirmed the same.[288]
Because of their intimate acquaintance and knowledge of ProLearn's business and the quality of their evidence, I prefer and find persuasive the evidence given by Tutungi and Humunicki on matters in issue, particularly so in relation to the matters relating to the operation of their business, for the reasons I have earlier stated.
I give significantly less weight to the evidence of Wolff and Wright, who were expert witnesses reviewing data and trends and hypothesising about the impact of legislative changes on the relevant industry. Their statistical and more hypothetical expert evidence is, I consider, of significantly less weight and was significantly less persuasive in respect of the present matters under consideration.
In relation to my finding above, I add however that the decline in the VET sector and the effect which that had on ProLearn's sales constitutes a factor and circumstance which is both difficult to quantify, or to relegate. Although I accept ProLearn's evidence that the general decline in the sector had no substantial impact on ProLearn's business, I consider that it did have some negative effect. I also consider that this negative effect likely became more pronounced progressively over 2015 and beyond, as criticisms of and changes to, the sector increased.
(e) ProLearn did not migrate its CRM to a web-based CRM as planned and, Kytec was forced to develop a custom gadget that enabled ProLearn to display additional customer information on the Finesse Screens, causing intermittent capacity issues.
I do not accept that by not migrating its existing ProLearn CRM to a web-based CRM ProLearn caused some of its intermittent capacity issues. This cause and its possible effect of capacity issues was not raised contemporaneously by Okulicz with ProLearn. Furthermore, the evidence does not establish that had ProLearn migrated to a web-based CRM there would have been any improved capacity performance.
(f) ProLearn's delay in confirming that it was moving to the La Trobe Street premises, leaving Kytec only ten days to install, test and implement the Solution,[289] and the consequent delay in Telstra being able to install the SIP line, preventing SIP testing as part of the commissioning phase.[290]
I accept that ProLearn did not, sufficiently in advance of its move to new premises at La Trobe Street, Melbourne, clearly, communicate its planned timing for that move to Kytec. I also accept that as a result, Kytec probably had less time than it planned to test aspects of the NTS before that system went live.
However, I do not consider that ProLearn delays and unsatisfactory communication in relation to its move to the new La Trobe Street premises, in all the circumstances, contributed in any demonstrable and material way to ProLearn's own problems with the new telephone system, although as I have accepted, this lack of timely communication by ProLearn detrimentally affected Kytec's testing program.
Ultimately, as further addressed below in relation to ProLearn's negligence case, I am not persuaded that Kytec's testing of components of the NTS was clearly inadequate or was itself a material cause of the problems and deficiencies with the NTS, or the cause of material delays in such problems and deficiencies being addressed. Nor am I satisfied that any delaying effect ProLearn's conduct had on Kytec caused any of ProLearn's own problems with the NTS.
In my view, ProLearn was under no obligation to do so. Further, I accept ProLearn was not advised or warned by Kytec that it required a certain time to test the NTS or that ProLearn's move would cause testing problems. I am also not persuaded that ProLearn insisted on the Solution 'going live' on 31 August 2015.
(g) The significant increase in the volume of calls initiated by the Automated Dialler[291] and made by ProLearn Operators after the Automated Dialler was turned on, as evidenced by the graphs tendered by Telstra;[292] and the fact that manual calls could still be made through the CommSys and ProLearn was relying successfully on its existing 'to do list' and personal call back system.
I do not accept that the volume of calls made by ProLearn Operators via the Automated Dialler contradicts or reduces the impact on ProLearn of what I regard as the very large and persuasive body of evidence referred to above which establishes what was actually occurring with the NTS after installation in relation to problems, deficiencies, incapacities and dysfunctionality of the Solution.[293]
I have found in substance that the ability to make calls through the existing system and ProLearn's limited ability to use previous 'to do lists' and the existing call back system was far from adequate to address or significantly alleviate the problems caused by the deficiencies, incapacities and dysfunctional aspects of the NTS.
Additionally, I am comfortably persuaded that the large number of contemporaneous communications and records detailed and cross-references in ProLearn's Closing Submissions at [20]-[25], and the extensive and detailed evidence describing the immediately manifest and persistent faults with the Solution very soon after ProLearn commenced to use it, abundantly establish those matters and the significant and sustained ways in which those problems and deficiencies impaired ProLearn's core operations.
I also reject that difficulties with the Automatic Dialler function were the result of ProLearn not moving to a new web-based CRM. I prefer Tutungi's evidence on this point,[294] which I consider to be more persuasive, both because of my separately addressed preference for Tutungi's evidence to that of Okulicz on matters in issue, where Okulicz's evidence is not corroborated, and additionally because I also consider Tutungi more likely to fully appreciate and be focused on, and therefore more likely to be correct in her recollection in respect of, the problems ProLearn was encountering with the Automatic Dialler and ProLearn's plans and issues with relation to changing to a web-based CRM.
310 I have found that the Solution provided was not capable of automatically generating Personal Call Back Lists, nor could it be utilised by 83 operators at once.
311 I am satisfied that the Solution did not have the capacity to generate Personal Call Back Lists,[295] and that Kytec's attempt to address this inadequacy, namely the temporary workaround (the Call Back Workaround) caused serious operational problems for ProLearn and in any event only operated for about a month.[296]
The To Do List was not ready when the New Telephone System was turned on, on 31 August 2015. When the To Do List functionality was turned on during the second week of operation of the New Telephone System, it caused several catastrophic crashes of the whole New Telephone System. This continued until Mr Gaber disabled the To Do List functionality on 9 September 2015 ...[297]
The To Do List was not ready when the New Telephone System was turned on, on 31 August 2105 [sic]. When Kytec turned the To Do List functionality on during the second week of operation, the New Telephone System crashed within about an hour. Kytec restarted the New Telephone System several times over a few days, and each time it crashed. This continued until Mr Gaber disabled the To Do list functionality on 9 September 2015. Around this time Vicki and I had a discussion with Mr Gaber at the La Trobe Street premises. I said words to the effect, what's going on - how are we going to fix this? Mr Gaber said words to the effect, we are going to take the To Do List off line and test it in the law and we will then bring it back and test it live.
Kytec turned on the To Do List functionality on a number of occasions around early October 2015, but each time it caused the New Telephone System to crash. For example, Kytec turned on the To Do List functionality on 2 October and it again caused the system to crash. ...[298]
314 In his witness statement Okulicz suggested that automated uploading and importing of leads and the To Do List functionality was available for use by ProLearn from the 31 August 2015 but that Tutungi chose to implement the Solution in stages.[299] However, later in his witness statement Okulicz stated that 'To Do Lists' function was not available as at 31 August 2015.[300] Elsewhere Okulicz also stated:
As part of the implementation phase of the solution, some preliminary issues were experienced in running the personalised To Do Lists that Kytec had planned and designed. Particularly over the course of September and October 2015, Kytec spent time troubleshooting these issues, and for part of that period, ProLearn was reliant on its existing to do list / personal call-back system that it had utilised prior to moving premises at the end of August 2015.[301]
315 While during cross-examination Okulicz gave the following evidence:
Anyway, so but you accept, do you, that the to-do list wasn't operational on 31 August 2015?---Um, I don't think it was, no.
Can you have a look at paragraph 125 of your witness statement?---Yeah.
See in paragraph 125, which is responsive to Ms Tutungi's paragraph 66 which speaks to the morning of 31 August 2015?---Yeah.
You're saying there that the to-do list was available to be used by ProLearn on 31 August?---Then I stand corrected.
Well, which is correct, the evidence that is in your witness statement that you had time to consider and then swore to its correctness - - -?---Yeah.
Could I just want to clarify. It's your evidence to His Honour that it was the fact that the to do list was operation on 31 August 2015?---So if I think um - - -
It's a yes or no?---Yes, it will be my evidence and I can, as I recall, Your Honour, I can actually back that up, if you would like.
HIS HONOUR: So your statement at paragraph 125 as to the status of these particular features on 31 August 2015 is correct in that you say the to-do list was available on 31 August 2015?---That's right. And, Your Honour, the - in thinking back to the evidence that I've seen today where Ms Tutungi was reporting that the dialler had been crashing all week, when she said that, I think on the 11th, I know that the cause, um, of that was the bug in the to-do list or the personal callback list. So, um, there would have been no dialler crashes save for that bug and if the integration wasn't done, there would be no calls to make and therefore the dialler couldn't have crashed. So I will, I'll retract the comment where I said I wasn't sure and I'll say that I am sure that, in fact, the to-do list was there.
MR OSBORNE: All right. Can you go now, please, to paragraph 150 of your witness statement, 'I refer to paragraph 66 of Vicki's witness statement. With the exception of the to-do lists, all of the functions listed therein were available as at the 31st August 2015'?---No, no. I mean this - - -
Pardon?---There's so must inconsistency between those two, I can't explain that - - -
Well, a couple of minutes ago when I - in fact, probably one minute ago - - -?---Yeah.
No, just let me stop here for a minute. You said, Mr Okulicz, specifically that having reflected on the matter, you are now sure that paragraph 125 is correct. That is to say that the to-do list was operational?---Yeah.
Do you recall giving that evidence?---I recall saying that.
And in fact you went further and said that having now reflected on it, you withdrew what you had said three or four questions earlier?---Yeah.
Which was to the effect that it wasn't - - -?---Yeah.
Well, you just don't know, do you?---No, I - you're right. I don't.
We didn't do your witness statement, you did your witness statement, didn't you?---No. It's absolutely an error.
Yes. I mean, you don't really have a good recollection at all of the relevant events that related to this - - -?---No, look - - -
Yes. I'd suggest that what you are doing, sir, is trying to frame answers in a manner that you consider best advances your defence in this proceeding?---I reject that.
I'm putting that to you. You reject that?---Yeah. And I would also say I'm not qualified to do so. I'm not a lawyer.
Now, see, I'm suggesting to you that in fact it was the case that the to-do list functionality at the very least was not available on 31 August 2015. I'm putting that to you as a proposition?---Yeah, we'll accept that.
316 I am satisfied that the To Do List was not properly functional on 31 August 2015 and I am also satisfied that when the system to provide that functionality was turned on it was not appropriate for the purpose and also caused 'crashes' of the NTS until it was disabled on 9 September 2015.
318 I do not accept Telstra's assertion in the last preceding paragraph, because I accept Tutungi's refuting these matters.[304]
I rang Mr Okulicz at about 9:00 am on 7 October. I said words to the effect, I feel like we are going around in a circle, I don't want to just keep retrying the same thing, you have had it back at the lab and you've promised me it's fixed and every time I try it the whole phone system crashes, I can't afford to keep doing this, this is killing my business, I'm losing sales by not having call backs. Mr Okulicz said words to the effect, how about this, I can give you a "work around" while I take the personal call backs "back to the lab". He also said words to the effect, I can give you the work around really quickly [305]
320 Further, I do not accept that ProLearn did not instruct Kytec to recommence work on the functionality problems with the NTS.[306]
321 I accept Tutungi's evidence that the To Do List functionality was not never forthcoming and there were major problems with the Call Back Workaround throughout 2016.[307]
322 In an email sent by Tutungi to Mr Renault on 15 November 2016,[308] Tutungi attached a list of issues as at 15 November 2016 which included:
5. "Personal Call Back List added to the Dialler". The original brief was to load every agent's personal call back list into the dialler each day. This never worked.
10. "Setting Call backs in Finesse". This was the workaround for call backs that Kytec put in place in October 2015.
Tutungi's evidence was also that the following transpired at a meeting at the La Trobe Street Premises with Okulicz and Gillett on 7 September 2016: [309] "Mr Okulicz also said that Kytec had fixed the call backs. I told Mr Okulicz and Mr Gillett that, as was the case, the callbacks were not working and that they were a workaround and that the original requirement was to have a To Do List. Mr Gillett raised his voice and said to Mr Okulicz, 'You will deliver the To Do List.'"[310]
323 As outlined above, I give much more weight to the evidence of Tutungi and Humunicki as to what was in fact occurring with ProLearn's call centre operations and I give much less weight to the evidence of Okulicz and Green in relation to their views that the system had the capacity to be integrated to deliver Personal Call Back List functionality,[311] and that this integration could be done in accordance with Cisco's published guide.[312]
324 I also consider that the evidence, which I have earlier accepted, that in fact the Final Proposal NTS did not function as required and simply did not work in the key required respects, persuades me even more deeply that Okulicz and Green's above evidence, should on the balance of probabilities, be rejected. My satisfaction in favour of ProLearn on these issues is heightened by the large body of contemporaneous communications from ProLearn, commencing as soon as the NTS Solution was deployed, specifying the NTS Solution's, problems, defects, dysfunctionalities and incapacities.
325 It is common ground that the alleged Kytec Representations and Telstra Representations, if made, were representations as to future matters for the purposes of s 4 of the ACL.[313]
(a) The Kytec Representations and the Telstra Representations were made in trade and commerce.
There appeared to be no dispute between the parties on this issue; and
(b) In making Representation 'F', namely that the Solution was appropriate for the ProLearn Requirements, both Kytec and Telstra represented as to the performance characteristics, uses and benefits of the Solution within the meaning of s 29(1)(g) of the ACL. This is because Representation 'F', in substance, promised Kytec that the NTS Solution had the characteristics necessary to be used by ProLearn and had the capacity and functionality to perform as required by ProLearn and to deliver the benefits ProLearn required;
(c) By reason of the problems, deficiencies, incapacities and dysfunctional aspects of the Solution which I am satisfied ProLearn has stablished, I find that each of the established Kytec Representations and each of the established Telstra Representations were false and untrue;
(d) Accordingly, for the above reasons, I am satisfied that each of the established Kytec Representations and each of the established Telstra Representations constituted contravening conduct by Kytec and Telstra pursuant to s 18 of the ACL.
(e) I further find that Kytec and Telstra's conduct in relation to established Representation 'F' contravened s 29(1)(g) of the ACL, because that joint contravening conduct by Kytec and Telstra represented performance characteristics, and ProLearn's ability to use, and the nature and extent of the benefits to ProLearn of, the Solution, as represented by established Representations 'A', 'B', and 'E'.
(f) Further, for the same reasons referred to in the last preceding subparagraph, I find that Telstra also contravened s 29(1)(g) of the ACL by making Telstra Representation 'TD'.
327 Accordingly, in making Representations 'A', 'B', 'E', 'F' and 'G', for the above reasons Kytec and Telstra, by its agent Kytec, perpetrated conduct prohibited by s 18 of the ACL.
328 Further, in addition for the above reasons Telstra perpetrated contravening conduct prohibited by s 18 of the ACL by making Telstra Representations 'TA', 'TB', 'TD' and 'TE'.
329 Additionally, for the above reasons Kytec and Telstra perpetrated contravening conduct prohibited by s 29(1)(g) of the ACL respectively in relation to Representation 'F', and separately Telstra contravened s 29(1)(g) by Representation 'TD'.
330 ProLearn contends that Telstra breached the Equipment and Services Agreement in two respects:
(a) it breached cl 1.1 of Schedule 2 in that it failed to provide Kytec with that which was identified as the Equipment viz the Solution as described in the Final Proposal; the system installed did not at any time automatically generate Personal Call Back Lists; and
(b) it breached the term in the nature of a Warranty in cl 5.3 of Schedule 2 that the Equipment supplied would perform in accordance with the supplier's (in this case, Kytec/Telstra) specifications for 12 months from the date of acceptance.
Failure to supply the Solution in accordance with cl 1.1 of Schedule 2
331 ProLearn contends that the Equipment and Services Agreement contains a term (the Disputed Term) that the Telstra Supplied Equipment, which Telstra must supply under cl 1.1 of Schedule 2 of the Equipment and Services Agreement, includes a Solution implemented as per the Final Proposal, including:[314]
(a) a telephone and network system which could be utilised by 83 Operators at once;
(b) a telephone and network system that would automatically generate Personal Call Back Lists; and
(c) a telephone and network system which would integrate with ProLearn's CRM.
332 ProLearn submits that it cannot be denied that the Solution did not have the functionality or capacity or that the Personal Call Back Lists did not ever work or that the Solution could not sustain capacity for 83 Operators. In this regard, ProLearn submits that:
(a) on the evidence of Tutungi and Humunicki, the Personal Call Back List function was not operational when the Solution went live on 31 August 2015,[315] and indeed never functioned;[316]
(b) Okulicz ultimately accepted that the Personal Call Back List feature was not functional on 31 August 2015,[317] however, his witness statement put forward two directly opposing positions as to the readiness of this function.[318] ProLearn submits that Okulicz's evidence in cross-examination was not satisfactory[319] and that Tutungi's evidence on this issue should be accepted;[320]
(c) Tutungi's evidence with respect to the Personal Call Back List functionality was, in summary, that:
(i) This function was turned on during the second week of operation of the Solution; however, it caused several catastrophic crashes of the system, and was disabled on 9 September 2015;[321]
(ii) Okulicz ultimately devised an alternative solution to the Personal Call Back List functionality, the Call Back Workaround, which also caused problems; and
(iii) the Solution, as delivered, did not ever provide the Personal Call Back List functionality.
333 ProLearn submits that Telstra breached cl 1.1 of Schedule 2 because it did not provide ProLearn with that which was contractually promised. ProLearn submits that any interpretation of the Equipment and Services Agreement which does not impose such an obligation on Telstra is inconsistent with the written terms of the agreement, and the aim and genesis of the transaction, and is also contrary to Telstra's subsequent conduct in assuming responsibility for procuring delivery of a telephone system that provided for Personal Call Back Lists.[322]
334 ProLearn further contends that Telstra's conduct supports the existence of a contract for supply of the kind alleged.[323] ProLearn submits that Telstra subsequently assumed responsibility to provide a telephone system to ProLearn which had a Personal Call Back List functionality,[324] as evidenced by:
(a) the meeting between Gillet of Telstra, Tutungi, and Humunicki on 30 June 2016, at which time Gillet informed Tutungi and Humunicki that Telstra intended to engage TBC to conduct an audit, and said in respect of the Solution, 'we'll fix it';[325]
(b) the meeting between Gillet, Okulicz, and Tutungi on 7 September 2016, at which Tutungi states Gillet raised his voice and said to Okulicz in reference to the Personal Call Back List functionality, 'you will deliver the To Do List';[326]
(c) the meeting between Gillet and Keating of Telstra, Tutungi, and Humunicki on 29 September 2016, where Gillet said words to the effect that, '[d]on't worry, we'll fix the system. The only thing we need to decided [sic] is whether Kytec is part of the solution'.[327]
335 Telstra submits that, on its proper construction, the Final Proposal was not incorporated by reference into the Equipment and Services Agreement and as a result there was no term of the Equipment and Services Agreement pursuant to which Telstra was to supply a telephone and network system which could be utilised by 83 Operators at once and which would automatically generate Personal Call Back Lists.[328]
336 Telstra submits that the only part of the Final Proposal that is incorporated by reference into Schedule 1 of the Equipment and Services Agreement is the 'Solution Components'. Telstra argues that the 'core functionality' description is not incorporated.[329]
337 Telstra submits there is a distinction between the Solution 'Components', which are consistent with the definition of 'equipment' (including software licences, handsets, servers and router) in the Equipment and Services Agreement, and the 'functionality' and 'call centre solution', which Telstra asserts are not.[330]
338 In this regard, Telstra emphasises that the definitions of 'Equipment', 'Additional Equipment' and 'Telstra Supplied Equipment' in the Equipment and Services Agreement refer to physical equipment and contrasts this with the warranties and representations being made in relation to the equipment dealt with in cl 5.10 of Schedule 2, in distinction to Schedule 1.[331]
339 Telstra submits that on the above basis, the reference to the Final Proposal in Schedule 1 incorporates only those parts of the Final Proposal which detail the physical equipment.[332]
340 Telstra also submits that the parties intended to reference the Final Proposal to better particularise the Telstra Supplied Equipment described under cl 1.1 of Schedule 2 of the Equipment and Services Agreement. Accordingly, Telstra contends that the Equipment and Services Agreement, by reference to the Final Proposal, comprised:[333]
(a) 83 software licenses for 'Cisco Unified Communications Manager' (support), 'Cisco Packaged Unified Contact Centre Enterprise' (PCCE), 'Cisco Unified Intelligence Centre', Cisco 'Calabrio' (call recording), VMWare and Microsoft;
(b) 83 Cisco '7281' telephone handsets;
(c) 2 'C240 UCS' computer servers; and
(d) 1 Cisco '2921' voice router.
341 Telstra contends that the intention could not have been to incorporate the 'core functionality' section of the Final Proposal into the Equipment and Services Agreement, because to do so would amount to additional representations or warranties by Telstra relating to the Telstra Supplied Equipment. Telstra argues that this would be in conflict with cl 5.10 of Schedule 2, which provides:[334]
5.10 Other than Telstra's warranty in clause 5.3, we make no additional warranties or representations in relation to the Telstra Supplied Equipment, including warranties or representations as to the performance, fitness for purpose and ability of the Telstra Supplied Equipment to operate with other items of equipment.
Telstra submits that a term will not be incorporated by reference from another document if it would conflict with an express term of the contract itself.[335]
342 Telstra further submits that ProLearn cannot, in contravention of the parol evidence rule, rely on evidence of post-contract assumption of responsibility, or pre-contractual communications between the parties regarding ProLearn's requirements for the purpose of construing the terms of the Equipment and Services Agreement.[336]
343 If the Equipment and Services Agreement is found to contain the Disputed Term, which Telstra submits that ProLearn has failed on the evidence to establish, ProLearn submits that that Telstra was in breach of that term, because:[337]
(a) the evidence establishes that the equipment did have the capacity and functionality to deliver Personal Call Back Lists;[338]
(b) the evidence does not establish that the Solution could not be utilised by 83 Operators at once;[339]
(c) ProLearn instructed Kytec to stop work on the Personal Call Back List functionality on 7 October 2015,[340] and the Call Back Workaround was in place from 21 October 2015 and continued to be used by ProLearn until at least May 2016;[341] and
(d) ProLearn failed to migrate to a web-based CRM.[342] Tutungi conceded in cross-examination that ProLearn could not criticise Kytec for not integrating the Solution with ProLearn's non-existent web-based CRM.[343]
344 ProLearn contends that to distinguish between the 'Solution Components' and 'core functionality' of the Final Proposal ignores the plain words of the Final Proposal and the Equipment and Services Agreement.
345 ProLearn submits that Telstra seeks to ignore the communications between Tutungi, Okulicz and Asimakidis prior to the provision of the updated Equipment and Services Agreement on 23 April 2015. ProLearn observes that if Telstra's case was accepted, it would mean that little had changed from the first version of the proposed contract provided to ProLearn on 27 March 2015 and the Equipment and Services Agreement finally agreed late in March 2015.[344] ProLearn also contends that primacy should be given to clauses specifically negotiated with the individual circumstances in mind over those of a standard form.[345]
346 ProLearn contends that there is no impermissible inconsistency between the constraint in cl 5.10 of Schedule 2, and the obligation in cl 1.1 of Schedule 2 to provide the Telstra Supplied Equipment in accordance with the Final Proposal.
347 ProLearn submits that cl 5.3 assumes prior performance of the obligation in cl 1.1, such that, having provided ProLearn with a Solution that has the functionality set out in the Final Proposal, Telstra warrants the performance in accordance with that functionality for a 12-month period.[346]
348 ProLearn highlights that Tutungi's evidence was not to the effect of an instruction to stop work on the Personal Call Back List function, but a complaint about doing the same thing without success. The suggestion that ProLearn did not instruct Kytec to recommence work on the functionality is inconsistent with the evidence.[347] ProLearn also submits that Tutungi's evidence did not establish that an instruction was given by ProLearn to stop work on the Personal Call Back List function. Rather, in substance, Tutungi complained about Kytec doing the same thing again and again in an effort to get the Personal Call Back List function working, without success. ProLearn also rejects that ProLearn did not instruct Kytec to recommence work on the functionality of the Personal Call Back List system.[348]
349 ProLearn submits that Telstra's contention that Cisco was the relevant 'Supplier' for the purposes of the Supplier Specifications ignores that the equipment to be supplied was not standard Cisco equipment, but equipment customised for ProLearn (including software), and no Cisco specifications were provided.[349]
350 Finally, ProLearn submits in relation to the limitation of liability in cls 5.3(c) and 5.4 of the Equipment Contract that those clauses apply to the supply of services, and not to the obligation to supply the Telstra Supplied Equipment in cl 1.1, Schedule 2.[350]
351 The primary enquiry relevant to determining the extent of Telstra's obligations under the Equipment and Services Agreement, and the existence of the Disputed Term, is to interpret the words of the Equipment and Services Agreement, considered together with the context and apparent purpose of the relevant provisions.
352 The legal principles which govern the construction of commercial contracts were summarised by French CJ, Nettle and Gordon JJ in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd as follows:[351]
The rights and liabilities of parties under a provision of a contract are determined objectively, by reference to its text, context (the entire text of the contract as well as any contract, document or statutory provision referred to in the text of the contract) and purpose.
In determining the meaning of the terms of a commercial contract, it is necessary to ask what a reasonable businessperson would have understood those terms to mean. That inquiry will require consideration of the language used by the parties in the contract, the circumstances addressed by the contract and the commercial purpose or objects to be secured by the contract.
Ordinarily, this process of construction is possible by reference to the contract alone. Indeed, if an expression in a contract is unambiguous or susceptible of only one meaning, evidence of surrounding circumstances (events, circumstances and things external to the contract) cannot be adduced to contradict its plain meaning.
However, sometimes, recourse to events, circumstances and things external to the contract is necessary. It may be necessary in identifying the commercial purpose or objects of the contract where that task is facilitated by an understanding 'of the genesis of the transaction, the background, the context [and] the market in which the parties are operating'. It may be necessary in determining the proper construction where there is a constructional choice. The question whether events, circumstances and things external to the contract may be resorted to, in order to identify the existence of a constructional choice, does not arise in these appeals.
Each of the events, circumstances and things external to the contract to which recourse may be had is objective. What may be referred to are events, circumstances and things external to the contract which are known to the parties or which assist in identifying the purpose or object of the transaction, which may include its history, background and context and the market in which the parties were operating. What is inadmissible is evidence of the parties' statements and actions reflecting their actual intentions and expectations.
Other principles are relevant in the construction of commercial contracts. Unless a contrary intention is indicated in the contract, a court is entitled to approach the task of giving a commercial contract an interpretation on the assumption 'that the parties ... intended to produce a commercial result'. Put another way, a commercial contract should be construed so as to avoid it 'making commercial nonsense or working commercial inconvenience'.
These observations are not intended to state any departure from the law as set out in Codelfa Construction Pty Ltd v State Rail Authority (NSW) and Electricity Generation Corporation v Woodside Energy Ltd. We agree with the observations of Kiefel and Keane JJ with respect to Western Export Services Inc v Jireh International Pty Ltd.
353 Clause 1.1 of Schedule 2 of the Equipment and Services Agreement refers to Service Schedules and the terms and states:[352]
We will provide you with the Telstra Supplied Equipment as detailed in Schedule 1, on the terms and conditions in this Schedule.
354 Telstra Supplied Equipment is defined as:[353]
Telstra Supplied Equipment means the Equipment which we will supply to you as set out in Schedule 1 and excludes that Equipment which is Customer Supplied Equipment.
Equipment means all the equipment for a Site as detailed in Schedule 1, as varied from time to time, including without limitation any software contained in that equipment. Equipment includes Core Equipment, Main Equipment, Additional Equipment, Customer Supplied Equipment and Telstra Supplied Equipment except where otherwise specified.
Additional Equipment means that Equipment described as such in Schedule 1 and which we will not maintain under a TBS Care Contract you have with us, if applicable.
357 Schedule 1 contains a table which includes 'Main Equipment' under which no equipment is listed and the upfront price is $0.00. However, that same table identifies 'Additional Equipment', namely the following equipment for a specified Upfront Price of over a quarter of a million dollars:
1 x Soluiton [sic] to be implemented per Version 2.1 of the Kytec PCCE Proposal to ProLearn
358 The dispute between the parties as to the existence of the Disputed Term ultimately hinges on the proper construction of the words '1 x Soluiton [sic] to be implemented per Version 2.1 of the Kytec PCCE Proposal to ProLearn' in Schedule 1 in the overall context of the Equipment and Services Agreement. It is common ground that the Proposal being referred to is the Final Proposal.[354]
359 The Final Proposal referred to in Schedule 1 above includes in its terms that:
ProLearn are seeking a solution that meets the following requirements
360 The Final Proposal also states the following under the heading 'The Solution':
The solution will provide the following core functionality:
361 Further, as well as the substance of the conversation between Tutungi, Okulicz and Asimakidis of Telstra on 22 April 2015 in which Tutungi emphasised ProLearn's critical need for the contract under discussion to include the Personal Call Back List functionality, I have found that Okulicz and Asimakidis agreed that this required functionality would be included in the amended Final Proposal.
362 Indeed, Kytec, in an email communication late the same day of 22 April 2015, copied to Telstra, assured ProLearn that the Equipment and Services Agreement would include that functionality, namely an 'Integration service to automatically create individual agent call back lists'.
363 The effect of the above matters, in my view, is that the Equipment and Services Agreement includes the Disputed Term. I find that this is because on a fair reading of cl 1.1 of Schedule 2 and Schedule 1, Schedule 1 was intended by ProLearn and by Telstra to include the supply by Telstra of the equipment and software necessary to supply and implement the Final Proposal, including the core functionalities referred to in the 'Solution Overview' section of the Final Proposal and warranted as a deliverable by Okulicz and Asimakidis on 22 April 2015. Furthermore, the Final Proposal specified that the Solution would, amongst other things, deliver automatic individual call back list functionality for 83 Agents.
364 I do not accept Telstra's submission that the reference to the Solution in Schedule 1 of the Equipment and Services Agreement refers only to the 'Solution Components' as set out in the Final Proposal. I do not consider that the Final Proposal merely refers to the components of the Solution, in my view it also refers to certain core functionality, as well as ProLearn's requirements which the Final Proposal clearly contemplates the Solution will implement and deliver.
365 The use of the words 'implemented per ... the ... Proposal' in Schedule 1 of the Equipment and Services Agreement belie Telstra's propounded interpretation, because those words by their material meaning contemplate not merely the provision of 'components', but that the components supplied will implement the specifications and requirements as set out in the Final Proposal to ProLearn.
366 If the components of the Solution set out in the Final Proposal were provided without the functionality described in the Final Proposal, and also in the 'Solution Overview' section of the Final Proposal lacking the functionality represented and promised in the contractual conversations and emails referred to above on 22 April 2015, I consider that a reasonable businessperson would not regard the Solution as 'implemented per Version 2.1 of the Kytec PCCE Proposal to ProLearn' and Telstra would, I consider, be in breach of cl 1.1 of the Equipment and Services Agreement.
367 A reasonable businessperson would, I consider, read and understand the reference to the Final Proposal in Schedule 1 of the Equipment and Services Agreement as conveying a promise by Telstra that the Solution would be implemented so as to achieve the core functionalities referred to, including so as to implement Kytec's proposal to ProLearn and the 'Solution Overview' section referenced by Kytec in the conversation with Tutungi of 22 April 2015, including delivery of an automatic individual call back list functionality for 83 Agents.
368 I do not accept Telstra's contention that the various definitions of 'Equipment', 'Telstra Supplied Equipment' and 'Additional Equipment' refer merely to physical equipment such that the reference to the Final Proposal in Schedule 1 of the Equipment and Services Agreement could only relate to the 'Solution Components' mentioned in the Final Proposal.
369 I also accept that the definition of 'Equipment' makes clear that it includes 'without limitation any software contained in that equipment', and that the integration of the Personal Call Back Lists would include the development of a custom application into, and in addition to, the standard Cisco PCCE system.[355]
370 I accept that, as Okulicz stated, this 'customisation' involved the writing of code to be added to the standard Cisco system to enable it to work. I consider that, given the description of the additional equipment in Schedule 1, what was promised included such customisation and not the mere provision of the proprietary Cisco 'Solution Components'.
371 Furthermore, if under the subject contract Telstra wished to contract to provide only proprietary physical components, then the Equipment and Services Agreement could have easily said so; instead, Telstra promised to supply a Solution 'implemented per ... the ... Proposal'.
372 I find that under the subject Contract, the additional 'equipment' which Telstra agreed to supply was not merely the physical components of the Solution, but all necessary required 'equipment' in accordance with, and necessary for the implementation of, the Final Proposal, including specified physical components and software.
373 Further, it was Telstra which covenanted to provide the Telstra Supplied Equipment detailed in Schedule 1 which called up the Additional Equipment including a Solution suitable to be implemented in relation to Kytec's Proposal to ProLearn. In my view it is not to the point in relation to Telstra's promises to ProLearn, that Telstra intended to have Cisco supply the Equipment. Furthermore, I note that beyond the above terms of the Equipment and Services Agreement, there were no Supplier's Specifications provided to ProLearn.
374 For the above outlined reasons, I also find that on about 22 April 2015, ProLearn and Telstra expressly agreed to the scope of supply by Telstra referred to in the last preceding paragraph.
375 I also find that the 'Solution' and 'Proposal to ProLearn' referred to and called up as part of the specification for the Telstra Supplied Equipment under cl 1.1 of Schedule 2 of the Equipment and Services Agreement, read together with Schedule 1 'Additional Equipment', of that Contract, incorporates by express reference the core functionality requirements of the 'Proposal', being the Final Proposal, including those referred to at page 6 of the 'Solution Overview'.
376 I consider that a reasonable commercial person would understand that the words 'Proposal to ProLearn' in the 'Additional Equipment' section of Schedule 1 clarified that the Final Proposal formed part of the specification for the Additional Equipment (including 'the Solution ... Proposed to ProLearn') to be provided by Telstra under Schedule 2, cl 1.1. Furthermore, in my view this goes without needing to be further elaborated in the subject agreement.
377 Further, contrary to Telstra's submissions, in my view the above interpretation of cl 1.1 of Schedule 2 is not inconsistent with cl 5.10 of Schedule 2 of the Equipment and Services Agreement. Schedule 1 describes the equipment which is to be supplied by Telstra under the Equipment and Services Agreement. Clause 5.10 of Schedule 2 provides:
Other than the warranty in clause 5.3, we make no additional warranties or representations in relation to the Telstra Supplied Equipment including warranties or representations as to performance, fitness for purpose and the ability of the Telstra Supplied Equipment to operate with other items of equipment.
We warrant that the Telstra Supplied Equipment will perform in accordance with the Suppliers Specifications for 12 months from the date of Acceptance. This warranty will not apply if the Telstra Supplied Equipment has:
a) been altered, repaired or maintained by a person other than us;
b) not been operated in a suitable environment in accordance with its specifications; or
c) been subjected to abnormal physical or electrical stress, misuse, negligence, or accident.
379 I consider that, read together with the entirety of the Equipment and Services Agreement, the warranty in cl 5.3 assumes performance of the obligation in cl 1.1, such that, by agreeing to provide ProLearn with a Solution in accordance with the Final Proposal, Telstra warrants that the equipment supplied will be suitable to implement the Final Proposal to ProLearn and pursuant to cl 5.3, perform in accordance with the Supplier's Specifications for 12 months from the date of acceptance.
380 Here, as earlier found, there was no Supplier's Specification, however in my view for the reasons explained, Telstra specified aspects of the Equipment it was to supply for the purposes of Schedule 2, cl 1.1, in particular that the Solution to be provided was suitable to implement the Final Proposal to ProLearn.
381 The above construction of the words in Schedule 1 does not involve the making of 'additional' warranties beyond that contained in cl 5.3, but rather gives effect to the parties' description of the equipment which Telstra was obligated to provide under the Equipment and Services Agreement.
382 Furthermore, Telstra's contention that cl 5.10 of Schedule 2 must prevail in accordance with the 'waterfall' provision in cl 1.1, which, Telstra submits, gives contents of the Schedules priority over other parts of the agreement,[356] overlooks that it is the description of the equipment in Schedule 1 and the broad meaning of the fundamental term in cl 1.1 of Schedule 2 which are of primary contractual effect.
383 I also consider ProLearn's contractual case to be assisted by the fact that Schedule 1 has been specially formulated by the parties, with the individual circumstances and the particular terms agreed by the parties in mind, and that when such contract-specific special terms are interpreted along with standard form clauses, such as Schedule 2, greater weight is ordinarily given to specifically negotiated clauses[357] as applicable in this case in relation to the detailed Additional Equipment.
384 I therefore find that the Equipment and Services Agreement contained the Disputed Term and I find that Telstra was in breach of cl 1.1 of Schedule 2 of the Equipment and Services Agreement in the circumstances detailed above, because it failed to provide ProLearn with Equipment able to implement the Solution for the FinalProposal to ProLearn because, amongst other reasons, the Equipment was not capable of automatically generating Personal Call Back Lists in an operational setting involving 83 Operators using the Solution at the same time.
385 I have found that the Solution provided was not capable of automatically generating Personal Call Back Lists, nor could it be utilised by 83 Operators at once.
386 I am satisfied that the Solution did not have the capacity to generate Personal Call Back Lists,[358] and that Kytec's attempt to address this inadequacy, the Call Back Workaround, itself caused serious operational problems for ProLearn and in any event only operated for about a month. Okulicz accepted in his evidence that the To Do List was not functional at the Go Live Date.[359]
387 I am satisfied that the To Do List functionality was not properly functional on 31 August 2015 and I am also satisfied that when the system to provide that functionality was turned on, it was not appropriate for the purpose and also caused 'crashes' of the Solution until it was disabled on 9 September 2015.
389 I do not accept Telstra's assertion in the last preceding paragraph, because I accept Tutungi's refuting of these matters.[362]
I rang Mr Okulicz at about 9:00 am on 7 October. I said words to the effect, I feel like we are going around in a circle, I don't want to just keep retrying the same thing, you have had it back at the lab and you've promised me it's fixed and every time I try it the whole phone system crashes, I can't afford to keep doing this, this is killing my business, I'm losing sales by not having call backs. Mr Okulicz said words to the effect, how about this, I can give you a "work around" while I take the personal call backs "back to the lab". He also said words to the effect, I can give you the work around really quickly [363]
391 Further, I do not accept that ProLearn did not instruct Kytec to recommence work on the functionality problems with the Solution.[364]
392 I accept Tutungi's evidence that the To Do List functionality was never forthcoming and there were major problems with the Call Back Workaround throughout 2016.[365]
393 In an email to Renoult on 15 November 2016,[366] Tutungi attached a list of issues as at that date, which included:
5. "Personal Call Back List added to the Dialler". The original brief was to load every agent's personal call back list into the dialler each day. This never worked.
10. "Setting Call backs in Finesse". This was the workaround for call backs that Kytec put in place in October 2015.
394 Tutungi's evidence was also that the following transpired at a meeting at the La Trobe Street premises with Okulicz and Gillett on 7 September 2016:[367] "Mr Okulicz also said that Kytec had fixed the call backs. I told Mr Okulicz and Mr Gillett that, as was the case, the callbacks were not working and that they were a workaround and that the original requirement was to have a To Do List. Mr Gillett raised his voice and said to Mr Okulicz, 'You will deliver the To Do List.'"[368]
395 I give much more weight to the evidence of Tutungi and Humunicki as to what was in fact occurring with ProLearn's call centre operations and I give much less weight to the evidence of Okulicz and Green in relation to their views that the system had the capacity to be integrated to deliver Personal Call Back List functionality,[369] and that this integration could be done in accordance with Cisco's published guide.[370]
396 I also consider that the evidence, which I have earlier accepted, that in fact the Solution did not function as required and simply did not work in the key required respects, persuades me even more strongly that Okulicz and Green's above evidence should, on the balance of probabilities, be rejected.
397 Further, I accept that Telstra breached the Equipment and Services Agreement because the Solution was not suitable or functional for use by 83 Operators at once.[371] I accept ProLearn's evidence that 83 Operators could not use the Solution and that the Solution experienced problems when used by more than 30 Operators at once.[372]
398 Tutungi's evidence, which I accept, extensively detailed various capacity and growth related issues experienced when using the Solution.[373] In the Tutungi First Witness Statement, Tutungi identified that these issues emerged within the first week of the Solution's operation, stating:
In addition to the issues with To Do Lists and subsequently with the Call Back Workaround, as foreshadowed above issues with the capacity of the New Telephone System emerged during the first week of operation. These issues presented as crashing of the whole New Telephone System or as freezing of the Finesse Screens or as a delay in customer information appearing on the Finesse Screens.[374]
399 Tutungi also gave evidence that:[375]
I sent an email to Ms Walk on 13 May in which I briefly outlined the problems with the New Telephone System and the impact they were having on ProLearn's business (CB 6/4183). I note from Telstra's discovery of documents that Joe Gillett (of Telstra) forwarded this email to Mr Okulicz on 16 May 2016 (CB 6/4194). In my email to Ms Walk I noted that no testing was done prior to launch and for the month of September we had daily issues with the dialler not performing. I also stated in part: (CB 6/4183)
The original specification included the ability for each agents "to do list" or "call back list" to be updated daily. This was abandoned after 2 months of continual crashes and issues. We still to this day manually call people back.
The system is meant to be able to cope with 200 agents, but every time we get above about 30 agents the system fails. This presents as:
400 Telstra contends that the evidence does not establish that the Solution could not be utilised by 83 Operators at once.[377] Telstra submits that the evidence shows that ProLearn was provided with licenses for 83 agents and Okulicz's unchallenged evidence was that the system could support up to 1,000 Operators.[378] Telstra also relies upon Green's evidence that the PCCE solution, as proposed by Kytec in the Final Proposal, is capable of supporting up to 2000 agents.[379] Furthermore, Telstra submits that there is no evidence that there were ever in fact 83 Operators seeking to utilise the telephone and networks system 'at once'.
401 I am not persuaded by the Telstra assertions in the last preceding paragraph for the reasons I have outlined above, and principally because I prefer the evidence from Tutungi and Humunicki refuting those matters and I consider establishing what in fact occurred operationally in ProLearn's call centre.
402 ProLearn also submits that Telstra breached the warranty in cl 5.3 of Schedule 2, in that the Telstra Supplied Equipment did not perform in accordance with the Supplier's Specifications for a period of 12 months from the date of Acceptance.[380]
403 In its closing submissions, ProLearn made clear that this alleged breach was pursued in the alternative to its primary position that there had been a failure by Telstra to supply the Solution in breach of cl 1.1 of Schedule 2 of the subject Contract, resulting in a clear breach of cl 1.1 of Schedule 2 by Telstra and also resulting in it not being necessary for ProLearn to pursue its alleged breach of warranty.[381]
404 ProLearn submits that the term 'Supplier's Specifications' means Kytec's specifications as set out in the Final Proposal, and further that:[382]
(a) in response to Telstra's submission that there were no such Supplier's Specifications identified, ProLearn submits that such an interpretation is contrary to a sensible and businesslike interpretation of the Equipment and Services Agreement in light of the surrounding circumstances; and
(b) in response to Telstra's submission that there is no Customer Acceptance Certificate, ProLearn submits that in substance that Telstra prevented ProLearn from submitting a Customer Acceptance Certificate, and the date of Acceptance for the purposes of commencement of the warranty in cl 5.3 of Schedule 2 should be understood as the date upon which services commenced being supplied, being 31 August 2015.
405 Telstra submits that ProLearn has failed to substantiate its claim that Telstra breached the warranty contained in cl 5.3 of Schedule 2, because it has not adduced evidence of any 'Supplier's Specifications' for the purposes of cl 5.3, nor has it adduced evidence of 'Acceptance' via completion of the customer acceptance certificate so as to trigger operation of the warranty. In these circumstances, Telstra asserts that the warranty did not commence.[383]
406 Telstra submits that ProLearn's contention that Acceptance should be treated as occurring when the Solution was turned on, amounts to an impermissible rewriting of the clause, and that if it were intended that the warranty were to arise from delivery, cl 5.3 could have said so.[384]
407 Telstra contends that in the absence of Acceptance by customer acceptance certificate, the warranty does not arise.[385]
408 In relation to the definition of 'Supplier's Specifications', Telstra emphasises four matters, submitting that:
(a) the natural and ordinary meaning of 'published' is to make public or generally known;[386]
(b) the definition in the Equipment and Services Agreement requires that the Supplier's Specifications have been published by the Supplier, and 'Supplier' means the person supplying the equipment to Telstra, accordingly the Supplier must be the same person that publishes the specifications;[387]
(c) there is a requirement within the definition that the Supplier's Specifications be included with the equipment upon delivery, and 'delivery' means ProLearn's receipt of the Telstra Supplied Equipment;[388] and
(d) the reference to 'the specifications' in the definition is contemplating a singular thing.[389]
409 Telstra further contends that, on proper construction, the relevant 'Supplier' is Cisco, and that this construction is supported by the description of the 'Supplier's Specifications', comprising the 'specifications published by the Supplier ...'. Telstra submits that a reasonable businessperson would expect Cisco to publish specifications for Cisco-branded equipment. Telstra submits that this is consistent with the mutually known objective fact that Cisco was supplying the equipment to Telstra.[390]
410 Telstra submits that even if ProLearn was not given Cisco specifications, such Specifications were publicly available.[391] Furthermore, Telstra submits that Green's evidence was that there appeared to be a Cisco specification for the customisation process involved in the Solution.[392] Telstra also submits that the construction and meaning of 'Supplier's Specifications' is the Cisco specifications.[393]
411 ProLearn submits that Telstra's contention that Cisco was the relevant 'Supplier' for the purposes of the definition of 'Supplier's Specifications' ignores that the equipment to be supplied was not standard Cisco equipment, but equipment customised for ProLearn (including software), and no Cisco specifications were provided.[394]
412 As to acceptance, ProLearn accepts that the obvious commercial purpose of the signing of the Customer Acceptance Certificate in cl 4.8 is to identify a defined start date for the warranty. ProLearn relies upon the principle that where one party prevents the other from doing something under the contract, the obstructing party cannot rely on its own wrong and the contract in question will be construed in a manner as to not permit a party to take advantage of its own wrong.[395] ProLearn adds that the Court should have no difficulty in implying a term that in the event Telstra did not provide ProLearn with a Customer Acceptance Certificate enabling such a certificate to be signed, that the warranty would start at the completion of the relevant services.[396]
413 I consider that my above decision in relation to Telstra being bound by theDisputed Term, and consequently the words 'Proposal to ProLearn' in the 'Additional Equipment' section of Schedule 1 of the Equipment and Services Agreement, reflects the intention of the parties that the Final Proposal to ProLearn formed part of the specification for the Additional Equipment (including the "Solution ... Proposed to ProLearn") to be provided by Telstra under Schedule 2, cl 1.1 of that Contract.
414 I also consider that because ProLearn's above contractual warranty claim is an alternative claim to ProLearn's Schedule 2, cl 1.1 based claim, which I uphold, it is not strictly necessary to determine this alternative contractual warranty claim.
415 Further, I consider that the outcome of ProLearn's Schedule 2, cl 1.1 claim largely also carries the ProLearn contractual warranty claim under cl 5.3 of the same contract.
416 Clause 5.3 of Schedule 2 provides:[397]
We warrant that the Telstra Supplied Equipment will perform in accordance with the Supplier's Specifications for 12 months from the date of Acceptance. This warranty will not apply if the Telstra Supplied Equipment has:
a) been altered, repairs [sic] or maintained by a person other than us;
b) not been operated in a suitable environment in accordance with its specifications; or
c) been subjected to abnormal physical or electrical stress, misuse, negligence or accident.
417 Supplier's Specifications is defined as:[398]
Supplier's Specifications means the specifications published by the Supplier for the Equipment and included with the Equipment upon Delivery.
Acceptance means completion of the customer acceptance certificate.[399]
419 I accept ProLearn's submission that the Final Proposal amounted to the Supplier's Specifications for the Solution and for the purposes of cl 5.3 of Schedule 2.
420 Accordingly, while by cl 1.1 of Schedule 2 Telstra agreed to supply a Solution which was to implement the Final Proposal, under cl 5.3 of Schedule 2 it also warranted that the Solution would perform in accordance with the specifications contained within the Final Proposal for 12 months from the date of Acceptance.
421 The above, I consider, was an additional layer of Telstra obligation pursuant to the Warranty. Telstra was the supplier of the Equipment under the contract. Telstra's procurement from third parties to meet its contractual obligations to ProLearn under the Equipment and Services Agreement was a separate subcontractor/supplier-like arrangement between Telstra and those third parties.
422 No specification, other than the one in Schedule 1 (Additional Equipment) of the Equipment and Services Agreement, was provided at any time to ProLearn.
423 In the circumstances and given the above terms of the subject Contract, in my view, a reasonable businessperson would consider that the Proposal, which is referred to in Schedule 1, referring to the specifications from the Supplier for the 'Soluiton [sic] to be implemented per Version 2.1 of the Kytec PCCE Proposal to ProLearn' was the applicable 'specification', and this is what I consider to be the contractual position.
424 I do not accept Telstra's contention that it met the definition of Supplier's Specification that Cisco's specifications for similar equipment may have been available on the Internet.
425 Under the Equipment and Services Agreement, Telstra agreed to provide ProLearn with a bespoke Solution implemented as per the Final Proposal, and the Final Proposal sets out the specifications for this bespoke Solution. The subject system was bespoke because it was not simply a Cisco proprietary product but required customisation to achieve the specification called up by the Solution in the Proposal to ProLearn.
426 Furthermore, I do not consider that Cisco is the Supplier of the Solution specified in Schedule 1 for the purposes of the warranty in cl 5.3 of Schedule 2. The Supplier of that bespoke Solution is, I consider, Telstra on the above construction and pursuant to Schedule 2, cl 1.1 of the Equipment and Services Agreement. As earlier explained, the Final Proposal amounts to the Supplier's Specifications for the Solution for the purposes of the Warranty in cl 5.3 of Schedule 2. No other contractual specification was provided to ProLearn or has been identified.
427 I reject Telstra's contention that there had been no Acceptance and therefore the warranty in cl 5.3 had not commenced. It is Telstra which has prevented the fulfillment of this administrative requirement under the Contract, including by failing to meet its Schedule 2, cl 1.1 obligations and failing to provide acceptable Equipment. Further, I am not satisfied that Telstra provided any form of Acceptance Certificate for ProLearn to complete and return.
428 In my view, for the above reasons, Telstra is precluded from contending that the Warranty it agreed has not been triggered because ProLearn has not provided an Acceptance Certificate under the Equipment and Services Agreement. I also consider that in the circumstances, the cl 5.3 Warranty commenced on the date the Telstra Supplied Equipment commenced to operate.
429 Finally, I also find that Telstra has breached the cl 5.3 Warranty of the Equipment and Services Agreement on the same basis found above in relation to Telstra's breach of cl 1.1 of Schedule 2 of that Contract, namely that the Telstra Supplied Equipment did not perform in accordance with the Supplier's Specifications (being the Solution to implement the Final Proposal to ProLearn) on the same contractual and factual basis as found above establishing Telstra's breach of cl 1.1 of Schedule 2.
Limitation of liability provisions in the Equipment and Services Agreement
430 Telstra submits that there are two independent pairs of limitation of liability clauses operating in relation to ProLearn's claim.
Clauses 5.3(c) and 5.4 of the Equipment and Services Agreement
431 By cls 5.3(c) and 5.4 of the Equipment and Services Agreement, Telstra submits that the parties agreed that Telstra's liability to ProLearn arising from breach of contract and negligence would be limited to any costs or expenses reasonably incurred by ProLearn as a direct result of, and flowing naturally from, such breach and would exclude loss of profits. On Telstra's case, this would preclude ProLearn's claim against Telstra in this proceeding, which Telstra submits is entirely for loss of profit.[400]
432 Clauses 5.3(c), 5.4 and 5.9 of the Equipment and Services Agreement provide:
5.3 We accept liability arising from our breach of contract or negligence:
...
(c) unless clause 5.2 applies, for any other cost or expense you reasonably incur that is a direct result of, and flows naturally from, such breach or negligence (but excludes loss of profits, likely savings and data), but we limit our liability for all such claims in aggregate to the total amount payable to us under this Agreement during the first year of this Agreement.
5.4 Other than for the liability we accept under clauses 5.2 and 5.3, we exclude all other warranties, rights, remedies and liability to you or a third party for breach of contract, negligence or breach of any other law. For any liability which cannot lawfully be excluded but can be limited, our liability is limited to our choice of resupplying or paying the cost of resupplying services and repairing, replacing or paying the cost of repairing or replacing goods.
5.9 Clauses 5.4 and 5.5 are your sole remedies for breach of clause 5.3. You may have other remedies if there has been a breach of any rights you have under the Australian Consumer Law or other laws.
433 Telstra rejects ProLearn's contention that the operative terms of cls 5.3(c) and 5.4 are limited to the provision of the installation and/or TSB Professional Services 'Services' under Schedule 1 and cl 3.1 of the Equipment and Services Agreement, and therefore are not relevant in this instance where, on ProLearn's case, Telstra did not supply any services.[401]
434 Telstra submits that cls 5.3(c) and 5.4 are contained within the Terms of the subject Contract which apply generally and to the whole of the Contract, in accordance with cl 1.1, including to the supply of the Telstra Supplied Equipment pursuant to cl 1.1, Schedule 2.[402]
436 Telstra argues that, even on ProLearn's case, the limitation would still apply in these circumstances because the 'Services' referred to in cl 3.1 of the Contract comprise the provision of the Telstra Supplied Equipment and Installation Services, in accordance with Schedules 1 and 2 of the Equipment and Services Agreement.[405]
Clauses 5.5 and 5.9 of Schedule 2 of the Equipment and Services Agreement
437 Telstra submits that additionally, cls 5.5 and 5.9 of Schedule 2 of the Equipment and Services Agreement apply to limit Telstra's liability. Telstra says that there is no ambiguity in the language of cls 5.5 and 5.9 of Schedule 2,[406] and whether these clauses benefit ProLearn is not to the point, as a matter of construction.[407] In the premises, Telstra disputes ProLearn's submitted application of the contra proferentem rule of construction.[408]
439 Telstra submits that, contrary to ProLearn's contention, whether Telstra in fact repaired or replaced the Telstra Supplied Equipment has no bearing on the operation of the limitation in cls 5.5 and 5.9.[411] In the event of breach of the warranty, ProLearn could claim for these costs, however it has not done so.[412]
440 ProLearn submits that Telstra is not able to rely upon the limitation clause in cl 5.9 in answer to the claim for the breach of warranty in cl 5.3.[413] ProLearn contends that cl 5.9 is only referable to the breach of warranty in 5.3 and does not answer a failure to supply under cl 1.1 of Schedule 2, submitting that these provisions are not intended to be a code relating to limitation of liability because the wording of the relevant clauses is clearly limited to a breach of cl 5.3.[414]
441 ProLearn submits that cl 5.9 should be interpreted such that in order for Telstra to be able to benefit from cl 5.9, it was required to fulfil its obligations under cls 5.4 and 5.5. ProLearn submits that while there were discussions between ProLearn and Telstra about repairing and replacing the equipment, Telstra ultimately refused to repair or replace and therefore did not meet its obligation in that regard.[415]
442 ProLearn contends that the opening words of cl 5.9, namely '[c]lauses 5.4 and 5.5 are your sole remedies for a breach of clause 5.4', are ambiguous, including because cls 5.4 and 5.5 alone confer no benefit to ProLearn.[416] Accordingly, it is argued that the alternative interpretations of cl 5.9 are to the effect that either:
(a) 'the rights under clauses 5.4 and 5.5 are your sole remedy for a breach of clause 5.3'; or
(b) 'repair and replacement by Telstra pursuant to clause 5.4 and payment of the costs specified in clause 5.5 are your sole remedies in relation to a breach of clause 5.3'.[417]
ProLearn submits that while both interpretations are arguable, the alternatives are important in circumstances where Telstra did not repair or replace. ProLearn submits that a reasonable businessperson in the position of the parties would have considered that, provided that Telstra repaired or replaced the Solution and paid the cl 5.5 costs, ProLearn would have no right to further monetary redress.[418] However, a reasonable businessperson would not have interpreted the clause as entitling Telstra to immunity from damages for a breach of the warranty in circumstances where Telstra had not repaired or replaced and had in fact refused to do so.[419]
443 ProLearn submits that the above interpretation of cl 5.9 is consistent with the contra proferentem rule of construction applicable generally to exclusion clauses, the fact that the clause was contained in a contract prepared by Telstra itself, the proposition that a contract will be construed as far as possible in a manner as not to permit one party to take advantage of their own wrong, and is also consistent with an interpretation that avoids a capricious, unreasonable, inconvenient or unjust result.[420] ProLearn also points out that the language of cl 5.9 is dissimilar to cl 5.3(c) of the Equipment and Services Agreement, and argues that if so intended, that clause could readily have stated that Telstra did not accept liability for any other cost or expense or for loss of profits.[421]
444 In its written closing submissions, ProLearn submits that the following principles are relevant to the interpretation of exclusion or exemption clauses:[422]
A supplier of goods is unable to hide behind an exclusion where that which is supplied is fundamentally different from that which is contracted for.[423] The contracting parties can hardly be supposed to contemplate such a mis-performance or to have provided against it without destroying the whole contractual substratum; there is no difficulty in holding exclusion clauses to be inapplicable to such cases. Similarly, a contractor who breaches the contract by stepping outside the four corners of the contract will generally lose the protection of an exclusion clause.[424]
445 In this regard, ProLearn contends that in this case the disconformity between what was promised and what was supplied was so vast with respect to the provision of the Solution that Telstra's reliance upon an exclusion clause would amount in practical terms to it being able to rely upon the clause in circumstances where what it did provide was fundamentally different to that which it was contracted to provide.[425]
446 Furthermore, ProLearn submits that in circumstances where Telstra did not repair or replace, Telstra was itself in breach of the implied obligations set out in cls 5.3 and 5.5 that it would repair and replace, and Telstra has therefore departed from the obligations imposed upon it under the contract such that it has taken itself out of the 'four corners' of the contract in a relevantly similar way to that which disentitled the contracting party in Sydney City Council v West (West)[426] from relying upon an exclusion clause.[427]
447 In my view, cls 5.5 and 5.9 both when read individually and when read together give rise to no ambiguity of the type argued for by ProLearn, or otherwise. The plain meaning of the language employed by the parties is clear and to the effect outlined below.
448 The limitation of liability terms in cls 5.5 and 5.9 of Schedule 2 of the Equipment and Services Agreement appear to reflect the parties' intention that those terms dove-tail with the terms of cls 5.3 and 5.4 of the general conditions of that same agreement, so as to provide by these terms of Schedule 2 a limited liability for Telstra in respect of breach of warranty arising in respect of cl 5.3 of that Schedule and by cls 5.3, 5.4 and 5.9 to provide for limitation of liability for Telstra for any breach by Telstra.
449 I consider that the above clauses operate to effectively limit Telstra's liability to ProLearn to liability for the costs of repairs or replacement if Telstra fails to pay for any parts required to repair or replace the relevant Telstra Supplied Equipment. I consider that the above clauses also operate in a complementary manner with the overarching cap on Telstra's liability for breach of contract or negligence, limited by the earlier cl 5 to the total amount payable by Telstra during the first year of operation of the Equipment and Services Agreement.
450 Furthermore, I reject ProLearn's argument that Telstra has somehow by its conduct taken itself out of the scope of the agreement it had with ProLearn and therefore Telstra cannot, in the circumstances, rely upon the exclusion of liability clause. I am not satisfied that Telstra's actions, and inaction, in relation to repair and replacement of the Telstra Supplied Equipment amounted to conduct which was in fundamental breach or repudiatory in nature. Nor am I satisfied that Telstra's conduct could be characterised as taking Telstra outside the 'four corners' of the Contract.[428]
451 Nor, notwithstanding the contravening representations and Telstra's above established breaches of the Equipment and Services Agreement, am I satisfied that Telstra's supply was fundamentally different from that which was contracted for, so as to render the parties' agreements in relation to the exclusion clauses in issue ineffective or unenforceable.
452 In relation to its negligence claims against Kytec, ProLearn pleads:[429]
[31] In providing the Kytec Services, Kytec:
(a) held itself out as having specialised skills and expertise in the area of designing and installing telephone and network services;
(b) knew or ought to have known that ProLearn was relying on its skills and expertise in providing the Kytec Services;
(c) knew of the ProLearn Requirements;
...
(d) knew or ought to have known, and further, or in the alternative, it was reasonably foreseeable that ProLearn would or could suffer economic loss of the nature referred to in paragraph 38 below, if Kytec failed to take reasonable care in installing the Solution.
[32] In the circumstances, Kytec owed ProLearn a duty to provide the Kytec Services with due care and skill.
[33] Negligently, and in breach of its duty to ProLearn Kytec, failed to provide the Kytec Services with due care and skill in that it:
(a) failed to test the Solution adequately or at all prior to the Solution being switched on;
(b) programmed the Scripting and Finesse client components of the Solution in a manner which caused extra load on the system and resulted wholly or in part in the Deficiencies identified ...
...
453 ProLearn submits that, in the circumstances, Kytec owed ProLearn a duty to act with due care and skill in installing the Solution at the La Trobe Street premises and programming the Solution components (the Kytec Services).[430]
454 ProLearn accepts that the existence of a contract between Telstra and ProLearn is a factor that contradicts the existence of a duty of care owed by Kytec to ProLearn.[431] However, ProLearn submits that there is no blanket rule denying the existence of a duty of care owed by a person who is also in a contractual relationship with the person asserting the existence of the tortious duty of care.[432]
455 ProLearn had further alleged that Kytec breached its duty of care by programming the 'Scripting' and 'Finesse' client components in a manner which caused extra load on the system.[433] ProLearn does not, however, press this breach of duty of care against Kytec.
456 Accordingly, the only breach ultimately pressed by ProLearn at trial was Kytec's breach of duty of care in failing to adequately test the Solution prior to the Solution being switched on.[434]
ProLearn's delays in confirming the location of its new premises, and the truncated period between it obtaining possession of its new premises and the ProLearn Project going live, meant that Kytec was unable to conduct the extent of tests that it would ordinarily conduct in a new system.
458 ProLearn submits that Okulicz's evidence stands as an admission that there was a failure to properly test the Solution.
459 ProLearn submits that Kytec's contention that any failure to conduct the ordinary level of testing was caused by ProLearn's own conduct is unsupported by the evidence, and further:[437]
(a) ProLearn was not ever informed about Kytec's inability to conduct the desired level of testing;[438]
(b) on 14 August 2015, Okulicz responded to an email from Tutungi stating, amongst other things, that he understood the 'importance of the solution for your business', and was 'confident that the solution will cut over correctly and function has [sic] planned however there are risks in any deployment ...', to which Tutungi replied, inter alia, 'I am just getting edgy about the move, and can't afford for any mis-steps';[439] and
(c) in the face of criticism from ProLearn, Kytec did not contemporaneously assert the position it now argues, namely that it was ProLearn's own acts or omissions that prevented adequate testing. ProLearn submits that this argument is one of recent invention.[440]
460 As to the email exchange of 14 August 2015, Tutungi questioned the use of the ISDN connection as a provisional measure in circumstances where it would not work with the phone system, and relayed her concerns about the 'go-live date', saying amongst other things: 'as you know our whole business is call centre based and we cannot generate any revenue if the phone system is not working'. Okulicz responded:
The ISDN order was a contingency plan. We can have the phone system integrated with ISDN however it would have been at an additional (hardware) cost. If it were between going live and not going live, you would have had the flexibility to make this call. Without ordering the services when we did, we would not have had this option.
The decision to cancel ISDN in the mean time may be a little risky considering the SIP services are not yet terminated in 380 La Trobe Street and if I were in your position at this point, I would allow the service to be installed as a contingency plan and cancel once we have successfully commissioned and tested on SIP, in relation to the cutover, I understand the importance of the solution for your business and am confident that the solution will cutover correctly and function as planned however there are risks in any deployment. A strong testing plan from the SIP commissioning date until the cutover date will help migrate this. I will get updates from the team today and if there are any additional risks, I will give you a call and we can talk about them.
461 In response to the 'inadequate testing' allegation, Kytec submits that the delay on the part of ProLearn in confirming and granting access to the La Trobe Street premises was responsible for the truncated testing period,[441] and that Kytec did the best it could with ProLearn's 'drop dead' Go Live Date of 31 August 2015.[442]
462 Kytec submits that, contrary to ProLearn's contention, Okulicz did not admit negligence.[443] Kytec submits that it did not breach any duty of care, and if it did, there is no evidence that the limited testing caused any loss or damage to ProLearn. In support of its position, Kytec observes that:
(a) on 30 August 2015, Okulicz and Ryan Smith (of Kytec) were on site at the La Trobe Street premises for testing;[444]
(b) Tutungi accepts that she had made an overstatement when she said in an email that Kytec undertook no testing prior to launch;[445]
(c) Tutungi accepts ProLearn's delay in moving was 'in part' responsible for reducing the time available for testing[446] and was a contributing factor;[447]
(d) no user acceptance testing was carried out by ProLearn's operators, as is common practice according to Green's expert report;[448]
(e) further testing may not have identified the Personal Call Back List issue,[449] and no amount of pre-installation testing would have identified the system capacity issue.[450]
463 In response to Kytec's submissions, ProLearn submits that in relation to ProLearn's allegation of 'inadequate testing', Okulicz conceded that he did not advise or warn ProLearn that it had not done the extent of testing which would ordinarily be conducted, which would be expected by a Cisco partner,[451] and accordingly, there were resultant risks in the deployment of the Solution on 31 August 2015.[452]
464 I reject ProLearn's negligence case for the following reasons:
(a) I am not persuaded in the circumstances that Kytec owed the alleged duty of care to ProLearn;
I reject ProLearn's claim that Kytec owed ProLearn the duty of care asserted. The parties' rights and obligations in this matter were the subject of four detailed written Contracts, and accordingly, in my view, the legal relationship between ProLearn and Kytec was governed, and I consider comprehensively governed, by the Final Proposal and the Solution and the Contracts between ProLearn, Kytec and Telstra, which informed the nature and extent of Kytec's obligations and liabilities.
As earlier alluded to, ProLearn itself recognised that the formal contractual relationship referred to above was a contradiction to the asserted existence of a duty of care.
It is trite at law that a contracting party may owe a duty of care concurrently with that party's contractual obligations. However, here I perceive it to be clear from the nature of the subject matter; the engagement by ProLearn of Kytec; the formal written Final Proposal and the terms of agreements between ProLearn and Telstra, including the Scope of Work (including limited testing)[453] and between ProLearn and Kytec and further the contractual context, which included the Equipment and Services Agreement, the Telephone Contract and the Data Contract, that the parties, including ProLearn and Kytec, sought and agreed formal written terms and conditions intended to circumscribe their rights, obligations and liabilities. Those terms and conditions were, in my view, also intended to define and specify what equipment was to be provided to ProLearn and what technical services and other input Kytec agreed and was obliged to provide.
In these circumstances, I do not accept that Kytec's obligations and liabilities extend beyond those which are contractually defined as outlined above. This is especially so in relation to subject matter in the nature of technical services in connection with the installation of the Solution and where Kytec's Scope of Work and other deliverables were defined.
(b) further, for the following reasons, Kytec was, in any event, not negligent in relation to testing the Solution.
I accept that ProLearn's negligent testing case should fail both because ProLearn, by its delay in moving premises and its own conduct in failing to adequately foreshadow the timing of its intended move to the La Trobe Street premises, impaired Kytec's ability to test by restricting Kytec's time in which to do so, and because lack of, or inadequacies with, the testing of the NTS by Kytec has not been established to my satisfaction as a material cause of the problems and deficiencies with the NTS.
I accept Okulicz's evidence that the time available in the circumstances to Kytec to undertake the testing it wished to undertake was insufficient before the Go Live Date.[454]
I am satisfied that the delay in ProLearn confirming and granting access to the La Trobe Street premises truncated the testing period available to Kytec, and I also accept Okulicz's evidence that Kytec did its best to meet ProLearn's 'drop dead go live date' of 31 August 2015. I also accept the below chronology as accurate:
On 15 June 2015, Kytec provided ProLearn with its project plan,[455] which allowed for 46 days worth of work from design to "go live", including 10 days onsite to install, test, implement and commission the Kytec Solution (after design and assembly offsite).
By mid July 2015, being six weeks before the project was scheduled to go live, ProLearn had still not confirmed where its new premises would be located. It was still deciding between taking space at 120 Spencer Street, Melbourne or 380 Latrobe Street, Melbourne.[456]
Mr Okulicz had told ProLearn that it should allow at least six weeks to install and test the Kytec Solution. It was not until 3 August 2015[457] that ProLearn confirmed that it would be relocating its premises to Level 15, 380 La Trobe Street. Before this, ProLearn had also been incorrectly advising Kytec that its proposed new premises was Level 13, 380 Latrobe Street.
As noted by Mr Okulicz in paragraph [99] of his witness statement, until the location of ProLearn's new premises was confirmed, including the level, Kytec was unable to cause install the Telstra ISDN services to be installed or commence on-site activities that would usually include pre-installation testing, or confirm the installation timetable.
Kytec ultimately had only ten days to install, test and implement the Kytec Solution. Ms Tutungi admitted that at this stage there was tight timing for Kytec to do the testing.
Until the Kytec Solution was installed and connected to the actual carriage services from Telstra no use acceptance or pilot testing was possible. The delay in confirming its new premises caused a consequent delay in Telstra being able to install the SIP line, the SIP testing was unable to occur as part of the commissioning phase.[458]
Kytec was unable to test the Kytec Solution on the SIP connection before it went live. Testing, using the temporary ISDN line, was unable to commence until Friday 21 August 2015.[459] The SIP service was enabled once delivered by Telstra in November 2015.
Mr Green gave evidence that offsite testing could not be done without the carriage service being installed.[460]
On Sunday 30 August 2015, Ryan Smith of Kytec and Mr Okulicz were on site at ProLearn's new premises for testing.[461]
Ms Tutungi accepted that she was incorrect when she said in an email that Kytec undertook no testing prior to launch.[462] Ms Tutungi also accepted that ProLearn's delay in moving was "in part" responsible for reducing the time available for testing[463] and was a contributing factor.[464]
Ms Tutungi gave evidence that ProLearn was trying to do its own user accepting testing around that time (27 August 2015) and that "Doris actually did the user testing with the operators on-site".[465] Ms Humunicki admitted that, during the lead up to 31 August 2015, she did not do user acceptance testing herself or with the operators.[466]
(a) no meaningful user acceptance testing was carried out by ProLearn's own operators, and ProLearn created the truncated timetable for Kytec testing leading up to the 31 August 2015 Go Live Date;
(b) further testing may not have identified the Personal Call Back List issue and pre-installation testing would probably not have identified the system capacity issue, which was eventually found to have resulted from four intermittent issues in March - May 2016 caused by a single wild card entry in a 'gadget' installed at ProLearn's request after the Go Live Date.
466 In my view, it is also of no moment that Okulicz conceded that he did not advise or warn ProLearn that it had not done the extent of testing which would ordinarily be conducted and, accordingly, that there were resultant risks in the deployment of the Solution on 31 August 2015. Okulicz's evidence under cross-examination was:
Your real point is that it was ProLearn's conduct which meant that Kytec was unable to conduct the extent of testing it would ordinarily conduct. That's the point you are seeking to make in paragraph 108, isn't it?---That's - that's the point definitely, yes.
Yes. And so that has as its premise, doesn't it, that you didn't do the amount of testing that you ordinarily would conduct prior to deployment?---Yeah, that's exactly what - - -
Yes?--- Yeah.
And what you are simply saying is that it was ProLearn's fault?---I think that's where that leads, yes.
Yes. Now, of course you understood, didn't you, that ProLearn had come to you for your expertise in relation to the design and installation of these type of systems?---Yes.
Yes. And see, I want to suggest to you that in the period prior to the system going live on 31 August 2015, you never told Ms Tutungi at ProLearn that Kytec hadn't done the extent of the testing that it would ordinarily conduct. Do you accept that you never told ProLearn of that fact?---I accept that it was never told.
So you accept you never told ProLearn?---Not directly. There were definitely project plans put forward that showed more testing, and I think that's in evidence, than was feasibly possible given when we got access to the building.
Let's break this down. You agree with me that you never said, 'Vicki, we haven't been able to properly test this before the solution going live'. You never told her that orally?---We never said those words.
Yes. And you never sent an email to that effect?---No.
And you never said anything along those lines to Ms Tutungi, did you?---No.
No. And you never told Ms Tutungi that because of that there were tasks in the deployment that would not have arisen had you been able to undertake sufficient testing?---No.
And so you deployed for ProLearn a telecommunications system with respect to the operation of the call centre that, on the logic of your own evidence, had not been sufficiently tested; you would agree with that?---That's - that's what my statement says.
Yes. And you say it was their - but you concede, don't you, that you never told them - - -?---I think - - -
- that you were deploying a system that had never been sufficiently tested?
---As I said before, I think it was number one in a project plan and I also recall evidence put to your client about some yelling in an email about the date that it had to go live and the first time I heard that date could have been slipped was in cross-examination late last week.
Yes, but of course if you hadn't said to them, 'Vicki, we haven't been properly able to test this', you wouldn't expect her to say that, 'we can delay the move', would you?---I would also say that we're talking about putting in temporary solutions because SIP wasn't available. There was no conduct that would have ever suggested that we could have moved that go live date.
...
But you wouldn't have expected her to tell you that, 'we can delay the move'. Sorry, I will withdraw that. The only circumstance where she would tell you that they could delay the move was that if you had told her that there was a risk in deploying because there had been insufficient testing?---So I wasn't the project manager on this project and, no, I don't think that's the only time that they would raise that.[467]
467 Furthermore, I observe that ProLearn did not adduce expert evidence to support that a lack of, or inadequately performed, testing of the NTS caused, or was a material contributing cause of, the problems and deficiencies with the NTS.
468 Neither am I persuaded that ProLearn's reliance on Green's evidence establishes negligence by Kytec in relation to testing. Green stated:
So the long and the short of it is that the level of testing that's done can depend on a variety of factors, depending on the particular customer and the circumstances of the particular case?---Ah, correct.
Yes. But within that framework you would agree, wouldn't you, that you would expect a Cisco partner to liaise with the customer about those sorts of issues - about how much testing should be done - - -?---Yes.
- and to inform the customer as part of that if the Cisco partner thought inadequate time existed for testing the solution?---Ah, ideally that dialogue would happening between partner and customer.
Yes?---Yes.
So that you'd expect the Cisco partner to say, 'Look, you know this timeframe's too tight. We haven't got enough time to test this properly, and this poses a risk for how the solution's going to work when it goes live'. You'd expect that sort of discussion to take place, wouldn't you?---I would, ah - - -
Yes?--- - - - in - yes.
And, indeed, I suggest to you that the that evidence you've just given is influenced by the opinion you've expressed at paragraph 31 of your report that if less than adequate time is allowed between the dates for testing and a target go-live date, the capacity to correct any issues prior to target go-live date is reduced; that's a risk, isn't it?---Yes.
Yes. And another risk is the risk you point to at paragraph 32 over the page that, in your experience, 'the severity and number of unexpected issues encountered in the first few weeks after going live is typically directly proportional to the time allocated and the quality of the testing performed on the solution prior to going live'?---It's a bit of a generalisation, but in my 13 years' experience I would agree with that.
And by 'generalisation' what you mean - it's not the fact that in every case where there's a bit less testing that necessarily means, as night follows day, that there will be a lot of problems?---Yes.
But it, sort of, increases the risk; can I put it that way?---Correct.
Yes. And so they're all reasons why - I withdraw that. And of course, a PCCE system is a reasonably complex system?---Correct.
And it's a matter where the expertise really resides in the Cisco partner, not in the customer?---Correct.
And for all those reasons you'd expect the Cisco partner to advise and warn their customer if they thought there wasn't sufficient time for proper testing and that might cause problems?---Ah, ideally, yes.[468]
469 Green's expert evidence was to the effect that there are no rigid periods for testing, and it depends on various factors and importantly the customer.
470 I have accepted that Kytec did all that it could based upon ProLearn's 'drop dead' Go Live Date of 31 August 2015.
471 I accept that in the circumstances it was reasonable for Kytec to interpret Tutungi's use of capitals in an email of 18 August 2015 referring to 31 August as emphasising the need for Kytec to undertake all that it needed to undertake by 31 August.[469]
472 I accept that there was a significant compression of time available for Kytec to undertake testing of the NTS because Kytec personnel were working towards the Go Live Date of 31 August 2015, and I accept that date had been indicated by ProLearn to Kytec as ProLearn's move in day.
473 I am not, however, persuaded that ProLearn's delays and unsatisfactory communication in relation to its move to the La Trobe Street premises, in all the circumstances, contributed in any demonstrable and material way to ProLearn's own problems with the Solution, although I have accepted this lack of timely communication by ProLearn did detrimentally affect Kytec's testing program.
474 Furthermore, I am not persuaded that Kytec's testing of components of the NTS was clearly inadequate, nor that Kytec's failure to test in any way, or Kytec's deficient testing or delayed testing, was a material cause of the problems and deficiencies with the NTS or delayed the remediation of such problems and deficiencies.
475 Neither, as I have stated above, am I satisfied that any delaying effect ProLearn's conduct had on Kytec's testing caused any of ProLearn's own problems with the NTS.
476 For the above reasons, I reject ProLearn's negligence claim against Kytec.
Section 236
(1) If:
(a) a person (the claimant) suffers loss or damage because of the conduct of another person; and
(b) the conduct contravened a provision of Chapter 2 or 3;
the claimant may recover the amount of the loss or damage by action against that other person, or against any person involved in the contravention.
(2) An action under subsection (1) may be commenced at any time within 6 years after the day on which the cause of action that relates to the conduct accrued.
237 Compensation orders etc. on application by an injured person or the regulator
(1) A court may:
(a) on application of a person (the injured person) who has suffered, or is likely to suffer, loss or damage because of the conduct of another person that:
(i) was engaged in a contravention of a provision of Chapter 2, 3 or 4; or
(ii) constitutes applying or relying on, or purporting to apply or rely on, a term of a contract that has been declared under section 250 to be an unfair term; or
(b) on the application of the regulator made on behalf of one or more such injured persons;
make such order or orders as the court thinks appropriate against the person who engaged in the conduct, or a person involved in that conduct.
(2) The order must be an order that the court considers will:
(a) compensate the injured person, or any such injured persons, in whole or in part for the loss or damage; or
(b) prevent or reduce the loss or damage suffered, or likely to be suffered, by the injured person or any such injured persons.
(3) An application under subsection (1) may be made at any time within 6 years after the day on which:
(a) if subsection (1)(a)(i) applies--the cause of action that relates to the conduct referred to in that subsection accrued; or
(b) if subsection (1)(a)(ii) applies - the declaration referred to in that subsection is made.
479 As also separately noted, ProLearn seeks orders that the Equipment and Services Agreement, the Telephone Contract, the Data Contract and the Kytec Contract each be declared void and set aside. This relief is not sought in the alternative by ProLearn.
480 In order to recover damages under s 236 of the ACL, ProLearn must prove that the loss or damage it claims was suffered 'because of' conduct in breach of the ACL. The approach to damages assessment under s 236 of the ACL is analogous to the approach in tort.
481 ProLearn also seeks damages at common law for breach of contract and breach of warranty against Telstra. The approach to damages for breach of contract and breach of warranty is different to the approach the Court adopts when assessing damages under s 236 of the ACL, or in tort. In contract, damages are designed to put ProLearn into the position it would have been in had the contract been adhered to.
482 ProLearn, however, describes its damages case as being based on its loss of opportunity of deriving sales from its call centre by use of a properly functioning outbound call centre telephone system with the functionality described in the Final Proposal. ProLearn also explains in its closing submissions that its damages claims are calculated on this same basis for both its breach of contract and breach of warranty claims against Telstra, and also its claim for damages in negligence against Kytec and in relation to its claim for damages pursuant to s 236 of the ACL.[472]
483 ProLearn also submits that although its claims for contractual damages are not subject to the limitation imposed on the loss of opportunity applicable to damages based on its other above causes of action, the essential valuation method ProLearn submitted was appropriate, and which it advanced, in relation to its contractual damages claim is the same as that upon which its s 236 of the ACL and tortious recovery claims were based.[473]
The correct approach to causation, loss and damage: loss of opportunity or 'global loss' claim?
484 ProLearn's case is that it relied on the truth of the Kytec Representations and the Telstra Representations in entering the Telstra contracts and installing the Solution, and that it would not have entered the Telstra contracts and installed the Solution had it not been for those representations. I have found in ProLearn's favour that these matters have been established.
485 ProLearn alleges that, in entering into the Telstra contracts and installing the Solution, it lost the opportunity to earn the profits it would have earned had it not installed the Solution and had continued using the CommSys system (the Existing System Counterfactual), or alternatively had it acquired an alternate system which had the capacity to perform in a manner consistent with the Kytec Representations, the Telstra Representations and the Final Proposal (the Alternative System Counterfactual).[474]
486 ProLearn submits that the correct approach in considering its causation and damages case is a loss of opportunity to earn the profits it otherwise would have earned on either the Existing System Counterfactual or the Alternative System Counterfactual.
487 ProLearn's damages case is based on its lost opportunity to earn the profits it would have earned, had it not installed the Solution and continued using its existing CommSys system; or alternatively, had it acquired an alternate system which had the capacity to perform in a manner consistent with the Kytec and Telstra Representations.[475]
488 ProLearn's case on loss and damage is that it lost the opportunity of deriving sales for its call centre by the use of a properly functioning outbound call centre telephone system with the functionality described in the Final Proposal.[476]
489 In these circumstances, ProLearn submits that damages should be calculated by reference to the Alternative System Counterfactual in respect of both its breach of contract and breach of warranty claims, and also with respect to its claim for damages in negligence or pursuant to s 236 of the ACL, if ProLearn is able to establish that it was likely to have been able to enter into contractual arrangements with another telecommunications provider who had the capacity to deliver a new telephone system with the same functionality as that described in the Final Proposal.[477]
490 Alternatively, in respect of the claim for damages under the ACL, ProLearn submits that its damages should appropriately be calculated by reference to the loss of opportunity to continue to derive sales from its existing CommSys system.[478]
491 Regardless of which alternative scenario is invoked, ProLearn accepts that it must establish on the balance of probabilities that, by reason of the contravening conduct of Telstra and Kytec, by entering into the arrangements with Telstra and thereby using the Solution, ProLearn lost an alternative opportunity which had some value not being negligible. Whilst contractual damages or breach of warranty does not import this limitation; the damages measure in contract being designed to place ProLearn in a position that it would have been in had the contract been adhered to, ProLearn submits that the valuation methodology does not differ.[479]
492 ProLearn submits that 'global loss' cases provide some analogy to the instant case, insofar as it is not possible to segregate the causative effect of each different deficiency in the Solution.[480] However, ProLearn submits that there are critical differences, particularly in cases where the Court must determine future possibilities and past hypothetical situations, as with the matter at hand, where, in particular in relation to the assessment of damages, the civil standard of proof does not apply.[481]
493 ProLearn submits that the assessment task involves comparing a hypothetical counterfactual scenario and that which resulted; the essence of such a comparison being the difference between the number of sales actually achieved, and the hypothetical number of sales that would have been achieved had the system performed as represented, or had Telstra complied with the contract; or that which would have been achieved had ProLearn entered into contracts providing for an alternative system with the same functionality represented, or had it stayed with ProLearn's previous system. ProLearn observes that such a process of assessment necessarily involves uncertainty and a degree of speculation, as is inherent in the hypothetical.[482]
494 ProLearn identifies two alternative scenarios from Smith's expert report, dated 11 December 2018,[483] which it submits may be used to calculate the value of its alleged lost opportunity in the 15-month post-installation period (Loss Period). The Loss Period represents the 15-month post-installation period from September 2015 to November 2016.[484]
496 Scenario 1 is one referred to in ProLearn's Expert Quantum Report by Michael Smith at [9], that relates to Additional Sales and Impact on ProLearn's EBIT based on the average sales per month over a range of timeframes. Scenario 2 is referred to at [10] of Smith's expert report, relating to the Additional Sales and Impact on EBIT based on the averages sales per month made from Courses offered by Nominated Education Providers over a range of timeframes.[487]
497 ProLearn contends that a three-month pre-installation comparator is unfair and artificial,[488] because Humunicki gave unchallenged evidence that sales were down in July and August 2015 as she was distracted by other business matters, including the move to the La Trobe Street premises, and was not able to 'patrol the centre' as she usually would.[489]
498 Using three months as the comparator, ProLearn submits that its loss and damage is $4,812,505 (on scenario 1) and $2,679,557 (on scenario 2).[490]
499 ProLearn submits that it is appropriate to consider sales to all education providers (as opposed to nominated providers only) in the pre-installation period. ProLearn submits that the alternative approach (sales to nominated providers only, for example, SWSI) fails to take into account the essential substitutability between courses sold for one provider, and those sold for another; or that Operators previously selling courses for other providers would be redistributed to selling courses for nominated providers.[491]
500 ProLearn submits that using the scenario 1, six-month pre-installation period comparator is a conservative approach, particularly in the context of a claim for expectation loss relating to a contractual claim based on an alternative system.[492] ProLearn also submits that it did not have an Automated Dialler, and that it had used between 19 and 60 FTE Operators during this time.[493]
501 ProLearn submits that, to the extent that the defendants point to other factors as being causative of ProLearn's loss, at their highest, those factors may have affected the extent of loss and damage but not the incident of loss and damage. ProLearn contends that other factors did not cause ProLearn to suffer the harm occasioned by the deployment of the faulty and inadequate NTS, as compared to the existing system or an available alternative.[494]
502 ProLearn submits that there is no evidence that the relevant legislative changes had any discernible impact on ProLearn's business.[495]
503 ProLearn also submits that the alternative causal hypothesis is of limited utility to the defendants in circumstances where ProLearn's decline was far in excess of the decline in the VET sector generally, and that of TAFE NSW (of which SWSI is a division);[496] in short, the decline across the sector was not uniform.[497]
504 Kytec criticises ProLearn's reliance on Annexure B to Humunicki's witness statement to quantify its alleged loss, given that Humunicki has no relevant expertise or qualifications in finance, accounting, or the quantification of loss and damage.[498] Further, Humunicki did not produce the worksheets or underlying data used to construct Annexure B.[499]
505 Kytec contends that Annexure B is based solely on data from the CRM, which is unreliable, and includes data entered manually by Operators that is therefore susceptible to human error.[500]
506 Kytec submits that extrapolating pre-implementation sales data over the loss period in order to determine loss, as ProLearn has done, is unsound[501] because sales rose and fell over the pre-implementation period in a manner that has not been rationally explained by ProLearn;[502] and there were other factors affecting performance in the post-implementation period.[503]
507 Kytec further submits that ProLearn did not have any contemporaneous business plan, or sales projections, for the post-implementation period. On that basis Kytec submits that all projected figures are necessarily a reconstruction for the purpose of this proceeding.[504]
508 As to ProLearn's loss of opportunity damages case, Kytec submits that ProLearn approaches its claim on a 'global loss' basis, using 'linear extrapolation', and based on the number of sales identified in Annexure B.[505] Kytec also adopts the submissions of Telstra concerning 'global loss' cases.[506]
509 Kytec submits that there is no cogent or detailed evidence as to an alternative system, therefore the proper counterfactual scenario references the existing CommSys system.[507]
510 Kytec submits that ProLearn's loss of opportunity claim glosses over various significant matters which expose the burden faced by ProLearn, in establishing that the factual scenario was worse than the counterfactual. Further, ProLearn did not call any evidence from SWSI to explain why ProLearn's business with SWSI would have defied the VET market downturn.[508]
511 Telstra submits that ProLearn's case is that the whole difference in sales and profits between the pre- and post-installation period was caused by the alleged deficiencies in the Solution.[509] Telstra submits that the way in which ProLearn puts its loss and damage case in this proceeding invites comparisons with the causation analysis applied in 'global loss' claims.[510]
512 Telstra submits that, on a 'global loss' analysis, ProLearn bears the onus of establishing the absence of any alternative causes for its claimed loss and damage.[511]
513 Even on ProLearn's loss of opportunity case, the plaintiff still bears the onus of establishing the impugned conduct for which the defendant is liable and which caused, on the balance of probabilities, the plaintiff to lose a commercial opportunity that had a substantial or real (not merely speculative) value.[512]
514 Telstra disputes ProLearn's loss of opportunity thesis and submits that ProLearn's performance in the pre-installation period and the loss period is a matter of historical fact. The correct causation question is whether the impugned conduct of Telstra caused the whole of the difference between those historical periods.[513]
515 Telstra submits that ProLearn has not sought to prove the absence of any alternative causes of the loss and damage claimed.[514] Telstra submits that, in the circumstances, the evidence demonstrates that there were numerous other causative factors impacting on the difference in sales and profits in the pre- and post-implementation periods which have not been considered in ProLearn's loss and damage formulation, including:[515]
(a) there was a substantial decline in ProLearn's sales prior to implementation of the Solution;[516]
(b) ProLearn sold different courses in the pre-implementation period as compared to the post-implementation period;[517]
(c) the price of courses offered by ProLearn changed over time;[518]
(d) there were changes in staff between the pre- and post-installation periods, which may have affected ProLearn's sales;[519]
(e) there were changes in enrolment success rates prior to and following the installation of the system;[520]
(f) there was a decline in the VET Fee-Help market.[521] It is common ground that all of the courses sold by ProLearn, save for potentially one course, were VET Fee-Help courses.[522] Telstra contests that ProLearn's decline was in excess of the decline in the VET sector generally.[523]
516 Telstra submits that ProLearn failed to conduct a comprehensive comparison between the performance of the Solution and that of the CommSys system, or of the unidentified alternative, which is fundamental to establishing that the alleged opportunity had real or substantial value;[524] and that ProLearn is singularly focussed on the call back functionality of the Solution.[525]
517 Telstra submits that Annexure B to Humunicki's witness statement is of no probative value in an assessment of whether the alleged opportunity had real or substantial value, as it only looks at sales from call backs, ignoring other components of the Solution. Telstra submits that the evidence shows that the NTS made substantially more calls than the CommSys system - both in aggregate and on a per FTE basis. More calls using the NTS increased ProLearn's prospects of selling courses.[526] Telstra says further that there was significant variation in the percentage of sales from call backs from month to month prior to installation,[527] and ProLearn has failed to adduce worksheets and underlying data informing the basis of Annexure B.[528]
518 As for quantification of loss and damage, Telstra submits that there is a lacuna of evidence called by ProLearn to establish the sales volume assumptions that underpin the opinions in Smith's expert report,[529] including that ProLearn would have achieved sales results in the loss period equivalent to the average sales achieved in the pre-installation comparator period,[530] and that these and other assumptions underpinning Smith's report are unsafe and unreasonable based on the expert evidence of Wright.[531]
519 As to ProLearn's submission on the 'essential substitutability' of the courses offered, Telstra contends that this is contrary to the evidence of Tutungi that course sales were a function of the particular course being sold.[532]
520 Telstra submits that ProLearn's loss and damage must be heavily discounted to a fraction of the amount claimed to take account of various matters impacting on the assumptions, including:[533]
(a) the decline in sales that occurred prior to the loss period;
(b) the decline in VET Fee-Help loans that occurred during the loss period;
(c) the various other risks and contingencies impacting on any comparison of ProLearn's performance between the pre-implementation periods and the loss period; and
(d) the benefit achieved by ProLearn from the NTS being able to make more calls than the CommSys system.
521 In response to both Kytec and Telstra's submissions, ProLearn says that:
(a) ProLearn did not call Roberts (the CEO of SWSI) to give evidence, after Kytec objected to the admissibility of a key part of his witness statement. That he was not called does not elevate other evidence;[534]
(b) even if Kytec's criticisms of Annexure B were accepted, this would not materially affect the data in Annexure B;[535]
(c) as to the alternative system, it is the foundation of Kytec's defence that the Solution had the functionality to comply with ProLearn's requirements; accordingly, such a system was available and could have been provided, whether by Optus/Avaya, who had provided a quote to ProLearn, or by Telstra itself via a more competent dealer than Kytec;[536]
(d) ProLearn accepts that it must establish, on the balance of probabilities, that its causal hypothesis (that its decline in profitability was caused by the defects in the Solution) is more probable than the alternative hypothesis contended by Kytec and Telstra (that ProLearn's decline in profitability was caused by other matters unrelated to the Solution).[537] ProLearn does not accept that this task requires ProLearn to entirely eliminate all matters not the responsibility of the defendant from the quantification of loss and damage.[538]
(e) it is not in dispute that ProLearn's revenue and EBIT declined substantially following installation of the Solution, and that ProLearn's sales from call backs dropped from 67 percent to 28 percent;[539]
(f) sales data prior to installation of the Solution shows a fairly consistent rate of approximately five sales for an FTE Operator per month;[540] however, the fact of business variability does not mean that the plaintiff cannot recover;[541]
(g) Annexure B to Humunicki's Witness Statement accounts for the sales that ProLearn did achieve utilising the Solution.[542] Humunicki was not challenged as to the reliability of Annexure B,[543] which was not undermined by Wright; and Smith verified Annexure B,[544] reporting that any discrepancy between his analysis and Humunicki's figures was minor.[545]
522 In closing oral submissions, ProLearn confined the past hypothetical for the purposes of its loss of opportunity case to the sales it would have achieved had it stayed with the existing CommSys system, or, in other words, the Existing System Counterfactual.[546]
523 In Sellars v Adelaide Petroleum NL (Sellars),[547] the High Court identified that the loss of an opportunity to obtain a commercial advantage is a compensable form of economic loss where the opportunity is itself valuable. Where the alleged loss suffered is the loss of a valuable opportunity, the plaintiff must establish causation in relation to that loss by proving, on the balance of probabilities, that the defendant's contravening conduct caused the loss of that opportunity. The assessment of the value of that lost opportunity is then undertaken by reference to the value of the opportunity had it materialised, and the degree of probabilities or possibilities that would occur.
524 The plaintiff in Sellars sued for damages under s 82 of the Trade Practices Act 1974 (Cth) (the Trade Practices Act), on the basis that the defendant's alleged misleading or deceptive conduct in contravention of s 52 of the Trade Practices Act had caused an alleged loss of opportunity or chance to secure a commercial advantage or benefit, being the opportunity or chance to secure benefits that entering into a contract with another purchaser would have brought.
525 In finding that damages for such loss were available under s 82 of the Trade Practices Act, the trial judge cited the joint judgment of Mason, Wilson and Dawson JJ in Gates v City Mutual Life Assurance Society Ltd.[548] Here, their Honours stated that where reliance on a misrepresentation has deprived a person of the opportunity of entering a different contract on which a profit would have been made, that person may recover that profit in an action in tort or under s 82 of the Trade Practices Act, the lost benefit being referable to the opportunity forgone by reliance on the misrepresentation.[549] Their Honours said further that it was for the aggrieved party to establish that they could and would have entered into another contract, and that that contract would have yielded the benefit claimed.[550]
526 In Sellars, the trial judge found that it was more likely than not that the plaintiff would have concluded the contract with the other purchaser. His Honour also accepted that, had the contract been completed, the plaintiff would have derived the benefit claimed, save for certain capital losses. However, owing to several conditions precedent to completion of that contract, his Honour found that there was only a 40 percent chance of the plaintiff completing the contract and deriving the benefits from that contract.
527 Despite being unable to find, on the balance of probabilities, that the various conditions precedent to the contract would have been satisfied and the plaintiff would have completed the agreement and derived the associated benefits, the trial judge accepted that, had the contract been completed, the plaintiff would have derived the benefits claimed and awarded the plaintiff damages on this basis, calculated at 40 percent of the benefit to be acquired upon completion.[551]
528 The High Court accepted the trial judge's assessment of damages. Mason CJ, Dawson, Toohey and Gaudron JJ said that, assuming a lost opportunity or chance has value, it is a compensable form of economic loss,[552] and further:
... [W]here there has been an actual loss of some sort, the common law does not permit difficulties of estimating the loss in money to defeat an award of damages. The damages will then be ascertained by reference to the degree of probabilities, or possibilities, inherent in the plaintiff's succeeding had the plaintiff been given the chance which the contract promised.[553]
529 The majority found that while causation and the suffering of some loss must be proven to the ordinary civil standard, being on the balance of probabilities, the amount of the loss is to be determined by reference to the degree of probabilities and possibilities involved, observing:
... [T]he general standard of proof in civil actions will ordinarily govern the issue of causation and the issue whether the applicant has sustained loss or damage. Hence the applicant must prove on the balance of probabilities that he or she has sustained some loss or damage. However, in a case such as the present, the applicant shows some loss or damage was sustained by demonstrating that the contravening conduct caused the loss of a commercial opportunity which had some value (not being a negligible value), the value being ascertained by reference to the degree of probabilities or possibilities. It is no answer to that way of viewing an applicant's case to say that the commercial opportunity was valueless on the balance of probabilities because to say that is to value the commercial opportunity by reference to a standard of proof which is inapplicable.[554]
530 Their Honours distinguished between a hypothetical situation where a plaintiff seeks to recover the profit the plaintiff would have made on another contract had he or she not been deprived of the opportunity to do so as a result of the defendant's conduct,[555] and a claim for damages for loss of the opportunity or chance to secure such profit. In a separate opinion, Brennan J explained that if the loss had been identified as the financial benefits that would have flowed to the plaintiff had the contract been concluded and completed, the plaintiff would have failed because they did not prove all the links in the chain of causation.[556]
531 Justice Brennan also distinguished between breach of a contractual promise to afford the plaintiff an opportunity to acquire a benefit, and cases under s 82 of the Trade Practices Act and in tort, where damage is the gist of the action. In doing so, his Honour found that, in cases arising under s 82 of the Trade Practices Act and in tort, the plaintiff, who bears the onus of proving loss suffered as the result of the defendant's contravening or tortious conduct, cannot look to an antecedent contractual promise to prove the existence and causation of a compensable loss, and must do so in another way.[557]
532 Justice Brennan said that the loss of an opportunity to acquire a benefit will be compensable if the plaintiff can prove that they would have taken the opportunity and that the benefit would have resulted.[558] His Honour explained that the opportunity must have offered a substantial and not merely speculative prospect of acquiring the benefit that the plaintiff sought to acquire.[559] If the prospect was substantial, then the opportunity is valuable.
533 As to the distinction between causation and fact of loss on the one hand, and the assessment of the amount of loss on the other hand, Brennan J said:
Although the loss of a valuable opportunity and the assessment of its amount are concepts that can be logically separated, in practice it will usually be the same body of evidence that tends to establish both the existence of a loss and the amount to be recovered. That evidence may establish the loss of a valuable opportunity more clearly than the value of the opportunity lost...
To prove the substantiality of a prospect of acquiring a benefit or of avoiding a detriment and what would have been the plaintiff's actions if the opportunity had been offered, it will usually be necessary to tender evidence to establish the plaintiff's objectives and the contingencies in the way of their achievement. Evidence of that kind will bear upon both the existence and the value of the lost opportunity.[560]
Where a loss is alleged to be a lost opportunity to acquire a benefit, a plaintiff who bears the onus of proving that a loss was caused by the conduct of the defendant discharges that onus by establishing a chain of causation that continues up to the point when there is a substantial prospect of acquiring the benefit sought by the plaintiff. Up to that point, the plaintiff must establish both the historical facts and any necessary hypothesis on the balance of probabilities. A constant standard of proof applies to the finding that a loss has been suffered and to the finding that that loss was caused by the defendant's conduct, whether those findings depend on evidence of historical facts or on evidence giving rise to competing hypotheses. In any event, the standard is proof on the balance of probabilities.[561]
535 Both the majority's and Brennan J's reasoning in Sellars considered the decision of the High Court in Malec v JC Hutton Pty Ltd,[562] where Deane, Gaudron and McHugh JJ (with whom Brennan and Dawson JJ agreed on this point) distinguished between past hypothetical fact situations and future possibilities on the one hand, and matters of historical fact on the other. Their Honours said:
When liability has been established and a common law court has to assess damages, its approach to events that allegedly would have occurred, but cannot now occur, or that allegedly might occur, is different from its approach to events which allegedly have occurred. A common law court determines on the balance of probabilities whether an event has occurred. If the probability of the event having occurred is greater than it not having occurred, the occurrence of the event is treated as certain; if the probability of it having occurred is less than it not having occurred, it is treated as not having occurred. Hence, in respect of events which have or have not occurred, damages are assessed on an all or nothing approach. But in the case of an event which it is alleged would or would not have occurred, or might or might not yet occur, the approach of the court is different. The future may be predicted and the hypothetical may be conjectured.[563]
536 In Badenach v Calvert,[564] summarising the principles in Sellars, French CJ, Kiefel and Keane JJ said:
It remains necessary to prove, to the usual standard, that there was a substantial prospect of a beneficial outcome. This requires evidence of what would have been done if the opportunity had been afforded. The respondent has not established that there is a substantial prospect that the client would have chosen to undertake the inter vivos transactions. Therefore, the respondent has not proven that there was any loss of a valuable opportunity.
The onus of proving causation of loss is not discharged by a finding that there was more than a negligible chance that the outcome would be favourable, or even by a finding that there was a substantial chance of such an outcome. The onus is only discharged where a plaintiff can prove that it was more probable than not that they would have received a valuable opportunity...[565]
537 More recently, in Berry v CCL Secure Pty Ltd,[566] the majority of the High Court affirmed the approach to loss of opportunity cases articulated in Sellars. Although Bell, Keane and Nettle JJ found it unnecessary to apply on the facts of that case, their Honours said:
The established authority of this Court governing the assessment of damages under s 82 of the [Trade Practices Act] for the loss of a commercial opportunity caused by misleading or deceptive conduct contrary to s 52 of the [Trade Practices Act] is relevantly as laid down in Sellars. Where a claimant establishes on the balance of probabilities that misleading or deceptive conduct contrary to s 52 has caused the loss of a commercial opportunity of some value (not being a negligible value), the value of the lost opportunity is to be ascertained by reference to hypotheses and possibilities which, though they may not be capable of proof on the balance of probabilities, are to be evaluated as a matter of informed estimation.[567]
538 By parity of reasoning with the above authorities, the loss of an opportunity to obtain a commercial advantage is a compensable form of economic loss where the opportunity is itself valuable. Where the alleged loss suffered is the loss of a valuable opportunity, the plaintiff must establish causation of that loss by proving on the balance of probabilities that the defendant's contravening conduct caused the loss of that opportunity. The assessment of the value of that lost opportunity is then undertaken by reference to the value of the opportunity if it had materialised and the degree of probabilities or possibilities.
539 The defendants, particularly Telstra, disagree with ProLearn's loss of opportunity formulation. Telstra, with which Kytec agrees, contends that the way in which ProLearn puts its case is analogous to a global loss case as, contrary to ProLearn's submissions, it concerns matters of historical fact, being ProLearn's performance in the Loss Period and the First Period, as opposed to future possibilities or past hypotheticals, and then seeks to claim, based on the alleged contravening conduct of the defendants, the whole of the difference between those historical periods.[568]
540 Telstra submits in summary that consequently, in accordance with the relevant authorities on global loss cases,[569] ProLearn bears the onus of establishing the absence of any alternative causes for its claimed loss and damage.[570] Telstra submits that ProLearn has not done this, and therefore has failed to establish causation.
541 For its part, ProLearn concedes that 'global loss' cases provide some analogy to the instant case insofar as it is not possible to segregate the causative effect of each different deficiency in the Solution. However, ProLearn submits that there are critical differences, in particular that in cases where the Court must determine future possibilities and past hypothetical situations, as with the matter at hand, the civil standard of proof does not apply and one undertakes an evaluation of the additional causative factors that may have impacted sales which might have been achieved during the Loss Period on the counterfactual at the assessment stage.
542 A global claim is a contractual claim where the claimant does not seek to attribute any specific loss to a specific breach.[571]
543 Normally individual causal links must be demonstrated between each of the events for which the defendant is responsible and particular items of loss and expense. Frequently, however, the loss and expense results from delay and disruption caused by a number of different events, in such a way that it is impossible to separate out the consequences of each of those events. In that event, the events for which the defendant is responsible may interact with one another in such a way as to produce a cumulative effect. If, however, the claimant is able to demonstrate that all of the events on which it relies are in law the responsibility of the defendant, it is not necessary for it to demonstrate causal links between individual events and particular heads of loss. In such a case, because all of the causative events are matters for which the defendant is responsible, any loss and expense that is caused by those events and no others must necessarily be the responsibility of the defendant.[572]
544 In my view, however, it is not correct to characterise ProLearn's claim at law as a global claim in the sense argued by Telstra and Kytec. This is not a case where there are a multitude of interacting and cumulative breaches such that the causal links between the loss suffered and breaches cannot be seen. Here the Solution was afflicted with two significant defects, being that it was unable to create Personal Call Back Lists, and it lacked capacity. I consider there to be no unresolvable difficulty in establishing causal links between these deficiencies and the loss suffered by ProLearn. Further, I consider it to be unnecessary to dissect this loss into its component parts at the causation stage, to attempt to identify and relegate matters not the responsibility of the defendants in the way it may be necessary to do so in relation to a true global loss claim. However, I add that matters which are not the responsibility of Kytec and Telstra which have negatively impacted ProLearn's earnings in the period of projected loss are matters which may be taken into consideration at the assessment stage in considering the value of the loss with reference to the degree of probabilities or possibilities in relation to ultimate loss, in accordance with the decision in Sellars.
545 Further and significantly, contrary to Telstra's submissions, in my view the way in which ProLearn puts its case is properly comprehended as a loss of opportunity claim, where the loss is referable to the value of the opportunity as opposed to a historical fact, although Telstra's submission is correct insofar as Telstra observes[573] that the fact of ProLearn's earnings in the Loss Period is a matter of history.
546 Whether ProLearn relied on the Kytec Representations and the Telstra Representations in entering the Telstra contracts and implementing the Solution, as I have found ProLearn did, and whether the alleged deficiencies in the Solution can be said to have caused ProLearn's reduced earnings in the Loss Period are also matters of history. Both these matters are ascertainable and I have ascertained on the balance of probabilities that both are established in ProLearn's favour, as further addressed below.
547 By contrast, the value of ProLearn's claimed lost opportunity, namely the opportunity to earn the profits it says it would have earned had it not installed the Solution and continued using the CommSys system, or alternatively acquired an alternate system, is referable to a past hypothetical situation. The enquiry as to what ProLearn's earnings would have been in the Loss Period if it had not installed the Solution requires an evaluation by the Court.
548 ProLearn adduced evidence of its performance in the First Period, which is a matter of historical fact, and did so to project forward and inform the assessment of ProLearn's earnings in the Loss Period. This counterfactual, and the ascertaining of the value of the counterfactual at the assessment stage, will involve an evaluation of possibilities, not the establishment of fact as a matter of history.[574] Proof on the balance of probabilities does not inform the evaluation of such hypotheses or possibilities. This evaluation is a matter of informed estimation.[575]
549 Justices Dawson and Brennan observed in Malec v JC Hutton Pty Ltd:[576]
Hypothetical situations of the past are analogous to future possibilities: in one case the court must form an estimate of the likelihood that the hypothetical situation would have occurred, in the other the court must form an estimate of the likelihood that the possibility will occur. Both are to be distinguished from events which are alleged to have actually occurred in the past.
550 In my view, for the above reasons ProLearn's causation and damages case is properly understood as a loss of opportunity claim. Accordingly, ProLearn must prove on the balance of probabilities that the defendants' wrongdoing has caused the loss of a valuable opportunity. Once that is established, the Court then assesses the value or extent of the loss by reference to the degree of probabilities. Where causation and the fact of loss end, and valuation of the loss on the degree of probabilities begins, will vary from case to case and may depend on the way the plaintiff has framed its case, including its evidentiary case. Proof on the balance of probabilities will not end before the point at which the prospect of acquiring the benefit becomes substantial,[577] however it may continue past that point, if the plaintiff has framed its case in that way.
551 As accepted by ProLearn, regardless of which counterfactual scenario is invoked as the relevant opportunity, at the causation stage ProLearn must establish on the balance of probabilities that by reason of the contravening conduct of Telstra and Kytec, ProLearn entered into the arrangements with Telstra, and thereby implemented the Solution, and also thereby lost an opportunity which had some value not being a negligible value.[578]
552 Accordingly, causation must be established to the usual standard and in accordance with accepted principles.
Has ProLearn established on the balance of probabilities that the contravening conduct caused it to lose a commercial opportunity of a more than negligible value?
553 The enquiry at this stage is whether on the balance of probabilities, ProLearn has satisfied the Court that the contravening conduct of Telstra and/or Kytec caused it to lose an opportunity of some value, not being a negligible value. If an opportunity is valuable, the loss of that opportunity is 'loss' or 'damage' for the purposes of s 236 of the ACL.
554 The task of this Court, applying the relevant authorities, is thus to determine whether there is in fact a loss which could be said to be consequential upon the misleading conduct.
555 Causation is a question of fact, to be resolved on the balance of probabilities as a matter of common sense and not in accordance with any philosophical or scientific theory.[579] The impugned conduct does not have to be the sole cause; rather it must be a sufficient cause.[580] References to reliance must not be permitted to obscure the need to identify contravening conduct and a causal connection between that conduct and the loss and damage allegedly suffered.[581]
556 Accordingly, at the causation stage, as accepted by ProLearn,[582] ProLearn must establish on the balance of probabilities that by reason of the contravening conduct of Telstra and/or Kytec, ProLearn entered into the arrangements with Telstra and thereby implemented the Solution and in doing so lost an opportunity which had some value not being a negligible value.[583]
557 This enquiry gives rise to two interrelated factual issues that must be determined on the balance of probabilities:
(a) Did ProLearn rely on the Kytec Representations and/or the Telstra Representations in entering the Telstra contracts and installing the Solution?
(b) Did ProLearn lose an opportunity of a more than negligible value in entering the Telstra contracts and installing the Solution?
Did ProLearn rely on the Kytec Representations and/or the Telstra Representations in entering the Telstra contracts and installing the Solution?
558 In order to prove its causation case, ProLearn must establish that it relied on the Kytec Representations and/or the Telstra Representations in entering the Telstra contracts and installing the Solution, and that but for those representations, ProLearn would not have entered into the Telstra contracts and installed the Solution, and would have instead adopted a different course.
559 ProLearn submits that, in acting on the truth of the Kytec Representations and the Telstra Representations and each one of them, it entered into the Telephone Contract, the Equipment and Services Agreement, the Data Contract and the Kytec Contract, ceased using the CommSys system and commenced using the Solution. On those same bases ProLearn submits that it also relocated to the La Trobe Street premises; and commenced using the Solution.[584]
560 In my view, for reasons earlier outlined in relation to ProLearn's actions in 2015 and relevant reliance by ProLearn and for the additional reasons outlined below, ProLearn has comfortably established that it relied on both the Kytec Representations and the Telstra Representations in entering into the above agreements, ceasing use of the CommSys system and installing the Solution. Given these findings, in my view it is unnecessary in the circumstances to consider whether ProLearn relied on those representations in relocating to the La Trobe Street premises.
[47] On 27 April 2015 I signed the following documents on behalf of ProLearn:
(a) Telstra Corporate Services Agreement (Data Contract) (CB 3/1864-1901).
(b) Telstra Business Systems - Corporate Services Agreement (Equipment and Services Contract) (CB 3/1902-1913).
(c) All-4 Biz Order Form (Telephone Contract) (CB 3/1921-1931).
(d) Telstra Quotation dated 26 March 2015 (CB 3/1914-1916).
I also initialled every page of the updated Contact Centre Solution Overview that was referred to in schedule 1 of the Equipment and Services Contract, which was incorrectly marked as Date of Issue: 23 April 2015 and referred to as version 2.1, but was actually Version 2.3 of the Kytec PCCE Proposal to ProLearn and sent to me on 27 April (CB 8/6060-6091).
[48] As a result of the discussions with Mr Okulicz and Mr Asimakidis on 22 April 2015, Mr Okulicz's emails of 22 April 2015 and 23 April 2015, the provision of the documents set out in paragraph 24 and their content, I believed that the New Telephone System would have the following features:
(a) it would be able to automatically create Personal Call Back Lists;
(b) it would be able to be used by 83 agents;
(c) it would be scalable, so that ProLearn could expand the number of operators to as many as 200 if it wished (save that it would have to buy additional handsets);
(d) it would integrate with ProLearn's CRM;
(e) it would enhance ProLearn's productivity;
(f) it was appropriate for ProLearn's requirements;
(g) that Kytec and Telstra reasonably believed that the New Telstra System had the features in (a)-(f).
[49] Had the New Telephone System as described to me not had the features in paragraph 47 [sic, probably a reference to paragraph 48] above (or any of them), or had I known that Kytec and Telstra did not have a reasonable basis to believe that the system had those characteristics, I would not have procured ProLearn's entering into of the agreements referred to in paragraphs 46(a) to (c). ProLearn would instead have continued with communications it was having with Optus and Avaya about the supply of a new telephone system by them. Had Optus and Avaya not been able to supply a system that met ProLearn's requirements, we would have continued to use the CommSys System. Had ProLearn not entered into the agreement in paragraphs 46, there would have been no need for it to enter into the agreement with Kytec on 7 October 2015 referred to in paragraph 71.[585]
562 Tutungi's evidence at paragraph 71 of the Tutungi First Witness Statement was also in substance to the effect that as a matter of practical necessity the operation of the Solution meant having to engage Kytec to support that system.
563 Those features Tutungi referred to in her above evidence at [48] included those in relation to which I have found representations were made by Kytec and Telstra in contravention of s 18 and also s 29(1)(g) of the ACL.
564 Further, the unchallenged evidence of Tutungi, which I accept, was that the Personal Call Back List functionality was a critical part of ProLearn's business and she could not purchase a system that did not have this feature.[586] In particular, the Personal Call Back List functionality enabled ProLearn to prioritise 'hot leads' over 'fresh leads', which I accept was an important aspect of ProLearn's sales strategy.[587]
565 Further, I add that I understand and readily accept that the features referred to in the last preceding paragraphs were fundamental to ProLearn's efficient functionality capacity to make sales, generate revenue and derive profits.
566 I am also persuaded that at the time of entering the Telstra contracts, Tutungi and Humunicki were planning to expand the ProLearn business by increasing the number of Operators. The evidence of both Tutungi and Humunicki was that they planned to expand the business from approximately 65 Operators in December 2014 to 150 Operators.[588] This is supported by the fact that, when Tutungi and Humunicki were told that ProLearn's lease on the St Kilda Road premises would not be renewed, they acted to have ProLearn enter a lease agreement for the La Trobe Street premises, which was fitted with facilities (desks and internet sockets) for 153 staff.[589]
567 In my view, it is sufficiently evident in the circumstances and firmly established by the above evidence that it was a most significant matter to Tutungi, indeed a fundamental necessity for ProLearn, that the Solution had Personal Call Back List functionality and was able to be used by at least 83 Operators.
568 For the above reason, and those earlier outlined, I am persuaded that ProLearn relied on the established Representations of both Kytec and Telstra equally in entering the Telstra contracts, and thereafter the Kytec contract, and in installing the Solution. Accordingly, I am satisfied ProLearn has established that it relied, as it alleges, on the established contravening conduct of both Kytec and Telstra**.**
569 Telstra denies that ProLearn has established that it relied on the Telstra Representations, saying that ProLearn has not adduced any direct evidence of such reliance, and that Tutungi's evidence was that had she known the Solution did not have the features described in the Final Proposal then she would not have signed the contracts, which begs the question of whether Tutungi relied on any representations of Telstra.[590] I reject Telstra's contentions in this regard.
570 I do not understand Tutungi's evidence to be to the effect referred to by Telstra, or so limited, in relation to the representations contained in the Final Proposal. In the Tutungi First Witness Statement, Tutungi stated that she formed her understanding of the relevant features of the Solution "[a]s a result of the discussions with Mr Okulicz and Mr Asimakidis on 22 April 2015, Mr Okulicz's emails of 22 April 2015 and 23 April 2015, the provision of the documents set out in paragraph 24 and their content".[591]
571 I am quite satisfied that, contrary to Telstra's submission, the above representations and Tutungi's, and thereby ProLearn's, reliance on those representations did not arise from the Final Proposal in isolation, but from the Final Proposal surrounding circumstances relied on by ProLearn in relation to the provision of the Final Proposal, including the communications detailed above on 22 April 2015 relating to the Telstra contracts, and including the related discussions between Tutungi, Asimakidis and Okulicz. In my view, the Final Proposal was a key component, but not the only element, of the established relevant contravening conduct by Kytec and by Telstra.
572 The above findings and conclusions are also supported by Tutungi's evidence in cross-examination. Although Tutungi conceded that "it's probably a bit of an overreach ... for me to say that I assumed that Telstra were making the comments in the proposal",[592] in my view this aside by Tutungi in her evidence was consistent with the fact that Tutungi sought to have, and was successful in having, the Equipment and Services Agreement amended to make reference to certain of ProLearn's specific key requirements the Final Proposal. Tutungi's evidence included:
I went to the effort of making sure the proposal was included in the contract and I initialled every page of that proposal for the very reason that I wanted to rely on enforcement of that proposal against Telstra, who was the party I was contracting with. That is what I turned my mind to, and that is why I took the action that I took.[593]
573 Tutungi also gave evidence that she took the view that both Telstra and Kytec were standing behind the Final Proposal[594] and that she considered that it was both Telstra and Kytec that were offering ProLearn the opportunity and the features and benefits of the relevant system as set out in the Final Proposal.[595]
574 In this regard, I give no weight adverse to ProLearn's case to Tutungi having read and understood cl 5.10 of Schedule 2 of the Equipment and Services Agreement, and having recognised that cl 5.10 stated that Telstra was not making any representations or warranties in relation to the Telstra Supplied Equipment beyond the warranty in cl 5.3. Under cross-examination, Tutungi gave evidence that she did not think about whether Telstra was making any warranties outside of that contract. In my view, Tutungi's evidence on these aspects is of no moment because it is erroneously predicated on both it being relevant that the witness had a view as to the proper legal construction of the warranty provisions of the Equipment and Services Agreement, and also erroneously predicated on a construction of cl 5.10 of Schedule 2 which I have held is not sound.
575 Accordingly, I am comfortably satisfied that ProLearn relied on the Kytec and Telstra established Representations as outlined above.
Did ProLearn lose a valuable opportunity in entering the Telstra contracts and installing the Solution?
576 So as to ascertain whether the alleged lost opportunity had a more than negligible value and whether it gives rise to some actionable loss or damage, the opportunity alleged to have been lost must be identified.
577 The opportunity ProLearn claims it lost in this case is that which is described in the Existing System Counterfactual; that is, the opportunity to earn the profits it would have earned in the Loss Period had it not installed the Solution and had continued to use the CommSys system.
578 I am satisfied on the balance of probabilities that ProLearn's opportunity to continue to earn the substantial profits it was earning for some time using the existing CommSys telephone system were lost as a result of being enticed by Kytec and Telstra to purchase the NTS Solution, deploy the Solution, and entering into the four subject contracts.
579 Here, I am also satisfied on the balance of probabilities that ProLearn would have earned more than negligible profits based on the Existing System Counterfactual; I am satisfied that ProLearn would have earned profits substantially greater than it earned in the relevant period using the Solution had ProLearn continued to use the CommSys system.[596]
580 Separately and additionally, I am also satisfied on the balance of probabilities that ProLearn's transition to the Solution and its abandonment of the CommSys system caused ProLearn to suffer substantial loss of profits.[597]
581 In this regard, principal amongst the evidence which persuades me that ProLearn's transition to the Solution was a very substantial cause of its loss of profits which commenced immediately following deployment of the Solution is both the evidence of ProLearn's sales in the First Period utilising its existing system and that from the beginning of the NTS Solution deployment period, it is clear that ProLearn suffered not a gradual but a precipitous decline in sales and corresponding profits to a degree which in my view is not satisfactorily explained by any other factor.
582 Therefore, I consider that for the above reasons ProLearn lost an opportunity of some considerable value, and I further find for those same reasons that the value of ProLearn's opportunity was not negligible. Put another way, I am satisfied that ProLearn was substantially worse off financially as a result of attempting to utilise the Solution rather than staying with the CommSys system.
583 ProLearn has, I conclude and find, clearly established on the balance of probabilities that it was worse off purchasing and attempting to deploy the Solution than it would have been in continuing to use the CommSys system.[598]
584 It is not disputed that Kytec ultimately did not deliver the Personal Call Back List customisation in a contractually compliant and fit for purpose working order, or as represented to ProLearn.[599]
585 Although I accept that Kytec eventually ceased working on the Personal Call Back List functionality and instead provided the Call Back Workaround on the request of Tutungi, I find that this was as a result of a desire to avoid further failure and not, per se, a direction to Kytec not to fix the Personal Call Back List functionality, but I consider, a reasonable request by ProLearn which was in the circumstances the result of Kytec's conduct.[600]
586 I have earlier found that the Solution suffered from material substantial problems, defects, dysfunctionality and incapacities which manifested as occurrences of crashing or freezing of the Finesse Screens on a significant number of occasions and resulted in many lengthy delays in customer information being displayed on the Finesse Screens. I also find found that the Call Back Workaround reconfiguration and remediation suffered from many significant issues which were not effectively remediated.
587 It is significant in my view that there was a substantial decline in the percentage of sales that ProLearn achieved from call backs during the First Period as compared with the Loss Period.
588 Humunicki's evidence, ProLearn's MYOB records and the CRM data for the relevant periods, establishes that ProLearn's sales from call backs fell from approximately 67 percent in the First Period when ProLearn was using the CommSys system to approximately 28 percent in the Loss Period when ProLearn was using the Solution.[601] Humunicki's calculations are supported by the following evidence from Smith, who was an expert witness put forward by ProLearn:[602]
589 The unchallenged evidence of Tutungi was that this was critical to ProLearn's business to have Personal Call Back List functionality.[603] It is not disputed by Kytec or Telstra that call backs were an important aspect of ProLearn's business. I am considerably persuaded in the above regard by the fact that in the period immediately after deployment of the Solution, ProLearn's sales and profits declined to a far greater extent than the general decline in sales in the sector in which ProLearn's business was operating. I am persuaded by this that a factor or factors, quite apart from the VET sector changes and decline, very significantly and negatively impacted ProLearn's sales in the relevant periods.
590 Accordingly, having found that there were material and substantial defects and deficiencies with the Solution, I also find that the decline in the percentage of sales achieved from call backs following installation of the Solution is persuasive evidence that, by installing the Solution, ProLearn lost an opportunity of substantially more than negligible value.
591 I am similarly satisfied in relation to the assessment of ProLearn's loss and damage that the decline in percentage of sales achieved from call backs is otherwise unable to be adequately explained.
592 In my view, the above conclusions and findings are also supported by the evidence of the conversion rate of leads to sales which declined substantially from the First Period to the Loss Period, falling from approximately one sale per 142 leads in the First Period to approximately one sale per 495 leads in the Loss Period.[604]
593 Finally, I accept ProLearn's substantial body of contemporaneous evidence of its complaints to Kytec in the first instance in relation to the defects with, and deficiencies in the Solution and the impact on its business, and thereafter also to Telstra.
594 Further, the burden of this ProLearn evidence was consistent throughout the Loss Period, which I consider provides considerable contemporaneous support to my earlier conclusion that ProLearn's deployment of the Solution was the greatest cause of ProLearn's decline in sales during the Loss Period, and from the outset of that period. This evidence is also wholly consistent with ProLearn's version of events, and strongly contradicts Kytec's submission that ProLearn relies on a flawed and retrospective reconstruction in order to extrapolate its boom year into the Loss Period.[605] The ProLearn evidence I have referred to also tells strongly against Kytec's submission that Humunicki and Tutungi's Witness Statements paint an exaggerated picture of dire crashes and dysfunction[606] in an attempt to create that false picture. I reject both limbs of Kytec's submissions in that regard for the reasons I have outlined.
595 Insofar as Kytec and Telstra contend that the factors which they raise so as to show that factors other than the Solution caused all or most of any relevant loss which ProLearn suffered, I am unpersuaded by Kytec and Telstra's arguments, for reasons I have outlined both above, including in relation to causation as it arose in relation to ProLearn's ACL case, and also below, including in relation to causative issues raised by Kytec and Telstra in connection with the assessment of the compensable value of ProLearn's loss and damage.
596 I am comfortably persuaded for the above reasons that the evidence adduced by ProLearn establishes that, in entering the Telstra contracts and installing the Solution, ProLearn lost a valuable opportunity, and that, had ProLearn stayed with its existing CommSys system, it would have been significantly better off financially.
597 Both Telstra and Kytec submit that ProLearn's decline in profitability was caused by other matters unrelated to the Solution.
598 ProLearn accepts that it must establish, on the balance of probabilities, that its causal hypothesis, namely that its decline in profitability was caused by the defects and deficiencies with the Solution, is more probable than the alternative hypothesis contended for by defendants, namely that ProLearn's decline in profitability was caused by other matters unrelated to the Solution.[607]
599 ProLearn does not accept that this task rises to the level of requiring ProLearn to eliminate entirely from the quantification of loss and damage all matters not the responsibility of the defendants.[608]
600 On the other hand, Telstra, and Kytec in adopting Telstra's submissions, submits that, in accordance with a 'global loss' analysis, ProLearn must prove the absence of any alternative causes for the loss and damage claimed.[609]
601 I have earlier rejected the applicability of Telstra and Kytec's 'global claim' characterisation of this part of ProLearn's claims, and for that same reason I reject this argument. I do not consider that it is incumbent upon ProLearn to establish that there was no factor contributing to its losses which was not caused by the adoption and deployment of the NT Solution. I so conclude both because as explained above, it is incorrect to characterise ProLearn's claim as a 'global claim' in the present circumstances and context, and because neither the determination on the balance of probabilities of loss being caused of some value, nor the assessment of the extent of that loss on an informed basis at the next stage, requires the moving party to preclude all other possible causes which were not the responding parties' responsibility.
602 For the reasons I have outlined above, I have concluded and decided that ProLearn has established on the balance of probabilities that the established Kytec and Telstra Representations have caused ProLearn to lose an opportunity of some value, and in this instance, of some substantial value.
603 ProLearn must also establish on the balance of probabilities that it is more likely that ProLearn's decline in profitability was caused by the problems with the Solution than by matters unrelated to the Solution. This does not require ProLearn to prove that the alternative suggested causes raised by the defendants had no impact on its business, nor in my view is ProLearn required to positively prove that there were no factors unrelated to the deployment of the Solution which caused ProLearn's sales and profits to decline.
604 Rather, ProLearn must prove that the defects, deficiencies and incapacities within the Solution were a substantial cause of ProLearn's loss; they need not be the only cause.
Decline in VET sector generally - Legislative changes
605 Kytec and Telstra allege that the decline in ProLearn's sales is referable to the decline in the wider VET Fee-Help market generally, and rely on the opinion in the expert report of Wolff, amongst other things, that the decline in ProLearn's sales was referrable to a wider market deterioration. Kytec and Telstra contend in summary that it can be inferred that the downturn in the wider VET Fee-Help market caused by legislative changes, including those referred to in the expert evidence given by Wolff impacted ProLearn and was a causative factor in ProLearn's decline in profitability during the Loss Period.
606 In his expert report, Wolff identified legislative reforms, including the following relevant principal reforms to the VET Fee-Help sector introduced by the Commonwealth Department of Education and Training (the Commonwealth DET) in 2015 and 2016:
(a) April 2015 reforms banning the use of inducements to entice students to enrol under the VET Fee-Help scheme;
(b) July 2015 reforms strengthening provider requirements, banning certain marketing practices, introducing written agreements between agents and providers, removing barriers to a student withdrawing from study before the census date and improving information for students around different providers and course fees; and
(c) significant reforms in January 2016, including freezing VET Fee-Help loan amounts at 2015 levels, strengthening student eligibility requirements and ensuring that debt is only incurred in line with course delivery.
607 In addition to those regulatory reforms, Wolff also identified that both the Commonwealth DET and Fair Trading New South Wales (NSW Fair Trading) engaged in communication campaigns aimed at informing prospective students about the risks involved in enrolling in a VET Fee-Help funded course.
In November 2014, in a brief to the Minister for Education, the Commonwealth DET identified the need to strengthen communication for students and developed a number of consumer videos through the studyassist website.
In February 2015, NSW Fair Trading in collaboration with the ACCC, launched a national campaign to raise awareness of inappropriate marketing practices within the VET sector; the campaign was titled A Free Gift Could Cost You Thousands and it was promoted through their respective websites with services providers, educators and community-based organisations encouraged to distribute and share the available posters and fact sheets.
In September 2015, the Commonwealth DET launched its Savvy Student campaign which presented fact sheets and videos, accessible through the studyassist website, and a VET FEE-HELP Anti-Scam brochure which was distributed through Centrelink offices.[610]
609 It is not in dispute that the decline in the wider VET Fee-Help sector was correlative with the government-initiated reforms in the sector. In my view, however, there is no direct evidence as to where the Commonwealth DET campaign was focused, and I note that the NSW Fair Trading campaign is described as a national campaign. This evidence is, for these reasons of little weight.
610 I find, however, as already alluded to, that ProLearn has demonstrated that its sales were not materially impacted by the downturn in the wider VET sector. In my view ProLearn has done so by:
(a) persuasive direct evidence of Tutungi and Humunicki that they were able to adjust their operations in response;
(b) the fact of the SWSI Agreement which allowed ProLearn to recruit as many students as it was able, and quarantined ProLearn from the wider VET sector downturn;
(c) showing that ProLearn's decline was greater than the decline in the wider VET sector, which I accept establishes on the balance of probabilities that there was a substantial additional cause impacting ProLearn's sales and doing so from the time the Solution was deployed by ProLearn.[611]
611 In relation to the above mentioned decline in the wider VET sector as compared to ProLearn's decline during the Loss Period, Wolff's expert report also records a decline in enrolments for TAFE NSW of 35 percent.
612 It is, however, not contested that ProLearn did not enrol students for TAFE NSW, but for SWSI, a subsidiary of TAFE NSW.
613 I also note that Wolff's expert report did not undertake an analysis sufficient in my view to reliably identify relevant decline to SWSI enrolments.
614 I am also satisfied that the evidence subpoenaed and tendered at trial from SWSI showed a decline in enrolments for SWSI of 6.6 percent and in relation to NCVER a decline of 16.7 percent. This data, in my view, is not of significant weight on the issue under consideration because it was not limited to VET-funded courses, for which ProLearn enrolled students, but also included paid courses.
615 I consider that this evidence is an insufficient basis upon which to conclude that the issues ProLearn experienced with the Solution were not, on the balance of probabilities, either the material cause of loss of opportunity or a substantial cause of that loss of opportunity.
616 I accept, as highlighted by the defendants, that in comparing the calendar years 2015 and 2016, there was a decline in course enrolments funded by VET Fee-Help loans of approximately 31.8 percent.[612]
617 I accept ProLearn's evidence, including in particular from Tutungi and in parts extracted below in these reasons, that the sector decline in 2016, and in particular over the Loss Period, did not have a material impact on ProLearn.[613]
618 It is very significant in my view, that ProLearn's sales declined by significantly more than the wider sector (73.6 percent compared to the wider sector decline of 31.8 percent). This I regard as prima facie evidence of the effect on ProLearn of a substantial additional causative factor or factors negatively impacting upon ProLearn's business beyond any impact caused by background industry decline.
619 The above evidence and the above factors I have identified as establishing that the negative effect on ProLearn was most substantially caused by the problems, defects, deficiencies and dysfunctionalities with the NTS and concomitantly the factors and evidence referred to explaining why the factors which the defendants argued impaired ProLearn's sales, revenue and profits, in combination persuade me that possible factors, apart from problems with the Solution did not explain the incident of ProLearn's loss although altogether they may well have had some negative effect on ProLearn's sales.
620 Further, the wider VET sector data relied on by the defendants is to be evaluated in the overall evidentiary setting, including the evidence of Tutungi and Humunicki, ProLearn's directors who were intimately familiar with what was happening in their business at the critical times and who were, in my view, uniquely placed to ascertain the factors that were impacting ProLearn's business, turnover and profits.
621 I consider that for these reasons, ProLearn's management evidence is much more persuasive as to the crucial issue of what impacted ProLearn's sales and profits, and provides a much more probative basis for a decision as to what factors were responsible, or mainly responsible for a decline in those sales and profits at the relevant time.
622 For these reasons, I reject Kytec's submissions that at ProLearn did not have an understanding of what was happening within its own business at the time ProLearn was seeking to scale up its business in mid-2015, and I also for those reasons reject that ProLearn was oblivious of the drop in sales in the last quarter of the 2014-2015 financial year at that time. Nor do I accept that a lack of projections or business plan on ProLearn's part negated or greatly reduced the reliability and weight of Tutungi and Humunicki's evidence on these issues. Finally, I am also not at all persuaded, as Kytec suggested, that ProLearn ran its business simply proceeding on the assumption that more Operators would lead to more sales.
623 In relation to the decline in the VET sector more generally, Telstra and Kytec submit that evidence of a decline in ProLearn's sales prior to the Loss Period shows that there was some other factor causing a decline in ProLearn's profitability, and that this decline continued into the Loss Period.[614]
624 I accept that it is likely that in a business such as ProLearn's, there would be variability in sales.
625 Further, although I accept the evidence of Humunicki that she was somewhat distracted by other business matters and not closely supervising the ProLearn call centre floor as she usually would,[615] I do not consider that Humunicki's evidence in this regard sufficiently explains the degree to which that period of being less 'hands on' in July to August 2015 convincingly explains the extent of the deterioration of sales in that important period of downturn in the months leading up to the installation of the Solution. I also, however, accept Humunicki's evidence that the matters taking her away from the call centre floor were largely resolved following the installation of the Solution. I consider that the most concrete evidence Humunicki gave on this point was at T440-441:
You couldn't possibly measure that impact could you?---It's measurable in the sense that, um, we, um - you need a manager to manage a team, you know. Without that you have a whole heap of people on their iPhones and on their - they're not focused.
You're surely not suggesting to His Honour that the reason why sales dropped from, let's just say, 260 in November 2014, if we take out the business sales, through to 113 in August 2014 was because you weren't there in the call centre in August 2015?---Well, the sales as the months go by, you know - look, not being there makes a big difference and I wasn't there in July and August and that has a - had a big impact.
You were there in June?---In June, I was on and off there. In June, we were doing the move, we were negotiating, um - - -
There must be other reasons, Ms Tutungi [sic], to explain these drop in sales, must there not?---There was no other drop in - there was no other reason - - -
That you're aware of?--- - - - for the drop in sales that I'm aware of. No. I mean, we were excited. We were going to grow. We were taking on capacity that we've taken on before - taking on all these huge costs to grow the business, um, even further. Um, our headspace was an exciting headspace of growth.
626 Humunicki's above evidence on this particular aspect is I consider largely conjecture on her part and was not supported by any further detail or analysis. For the above reasons, I am not satisfied that the decline in sales referred to prior to the installation of the Solution sufficiently evidences some other causative factor or factors, for example Humunicki's absences and distraction with other issues, which explain that decline in ProLearn's sales and profits..
627 Nevertheless, I accept that certain factors and circumstances which are difficult to quantify, were negatively impacting ProLearn's sales in the First Period and continued to do so at and after the deployment of the Solution.
628 Those difficult to quantify factors and circumstances negatively effecting ProLearn's sales, albeit in my view to a much lesser extent than the major disabling impact of the introduction of the Solution, were:
(a) The decline in ProLearn's sales caused to a minor degree by the wider decline in the VET Fee-Help market as a result of legislative changes and public disenchantment with that industry.
I consider that it is logical and reasonable to regard this phenomena as having an increasingly negative impact on ProLearn's sales, including from June to December 2015, because of unfavourable publicity of the VET industry and increasing awareness of the government's tighter control of and end plan for the VET industry.
(b) The likely continuation to at least some small degree of the decline in ProLearn's sales in the period prior to the end of August 2015;
(c) An at least minor decline in operator quality and efficiency together with staffing issues with ProLearn and the inherent variability of sales in ProLearn-type businesses;
(d) The at least minor negative affect of Humunicki's absence from operation at ProLearn in about July and August 2015.
Changes in courses offered, changes in the prices of courses and changes in enrolment success rates; staff turnover
629 As regards changes, and the effect of such changes, in courses offered, changes in the prices of courses and changes in enrolment success rates and staff turnover, I accept that changes in the nature of courses offered would be expected in a business such as ProLearn's.[616] Further, the evidence is that ProLearn made a strategic decision to focus on courses from SWSI and the Online Institute. Absent evidence to the contrary, I consider it reasonable to infer that this decision by ProLearn was taken in the interests of ProLearn's profitability, and that ProLearn's focus on SWSI courses largely quarantined ProLearn from the vicissitudes of the broader market.
630 I also accept that high staff turnover is inherent in a telemarketing business such as ProLearn's.[617] However, I do not consider that the evidence establishes that ProLearn was experiencing any unique staffing issues during the Loss Period nor is there evidence of the actual effect of staffing difficulties in the Loss Period.
631 In relation to changes in the price of courses offered, I accept ProLearn's submission that Wright's evidence was that she had not conducted any external analysis of the price elasticity of the relevant courses.[618] While the increase in prices of courses she observed prior to September 2015 appeared to show a correlation to the subsequent drop in sales, Wright accepted that there is a difference between correlation and causation. Wright's opinion on this aspect was that 'it is possible' that the change in ProLearn's sales may be due to price sensitivities and expectations of prospective leads'.[619]
632 Accordingly, I am not persuaded as to any relevant material effect on ProLearn's sales as a result of change to the price of courses.
633 In addition to Kytec and Telstra's case on the decline in the VET sector generally, Kytec and Telstra submit that ProLearn has failed to account for the higher number of calls made by the Solution, as compared with the existing CommSys system, due to the Automated Dialler.
634 While it may be accepted that, as submitted by Telstra and Kytec, the Solution made more calls than the CommSys system,[620] this submission is in my view unpersuasive. It fails to account for the persistent problems, inadequacy and inefficiencies associated with the Automated Dialler, including the inability of the Solution to provide for automatic Personal Call Back Lists, which ProLearn emphasised in its evidence was a critical part of ProLearn's business model and was integral to its sales success. I consider that ProLearn's evidence establishes that the problems ProLearn had with the Automated Dialler, and the Automated Dialler's significant operational limitations, meant that the additional calls the Automated Dialler initiated did not materially increase ProLearn's efficiency or its sales.
635 As earlier alluded, in my view, for the reasons outlined below, ProLearn has not sufficiently established the existence of what it has defined as the Alternative System Counterfactual such that it has been sufficiently established as a valuable opportunity that was probably available to ProLearn at the time of the contravening conduct.[621]
636 Therefore, in respect of ProLearn's proffered Alternative System Counterfactual, ProLearn has failed to establish causation.
637 To sufficiently prove the substantiality of the prospect of acquiring a benefit or avoiding a detriment, it will ordinarily be necessary for a moving party to tender evidence establishing the plaintiff's objectives and any likely contingencies affecting the achievement of the counterfactual propositions sought to be relied on. Evidence of this kind will usually bear upon both the existence and the value of the lost opportunity.[622] Proof as to the balance of probabilities of a postulated counterfactual will not run its course until the point at which the prospect of acquiring the benefit of the subject counterfactual becomes substantial.[623]
638 In my view, the establishment, on the balance of probabilities, of the Alternative System Counterfactual requires establishing that there was a substantial, that is probable, prospect of ProLearn acquiring an alternate system which had the capacity to perform in a manner consistent with the Kytec Representations, the Telstra Representations and the Final Proposal.
639 As I have earlier emphasized, the largely unchallenged evidence of Tutungi is that, had she known that the Solution did not have the ability to inter alia automatically create Personal Call Back Lists, or be used by 83 Operators, she would not have allowed ProLearn to enter into the Equipment and Services Agreement, and would have instead continued the communications ProLearn was having with Optus.
640 Tutungi's evidence was also that in the event that Optus was unable to supply a system that met the ProLearn Requirements, ProLearn would have continued to use the CommSys system.[624]
641 In the Tutungi First Witness Statement, Tutungi states that ProLearn contacted Optus in mid-January 2015, when ProLearn began searching for a provider for its new telephone system.[625]
642 ProLearn relies on an email from Tutungi to Okulicz on 17 March 2017 (5:37 pm), and subsequent discussions,[626] where Tutungi provided Okulicz with a breakdown of pricing ProLearn had received from Optus, it appears, to facilitate Kytec and Telstra providing a competitive response.[627] Okulicz later communicated to ProLearn '[b]ased on the figures you have provided, the 3 year cost for Avaya is $243,000 (cost provided + 2 years support)'.[628]
643 However, the price breakdown referred to provides no relevant detail of the functionality of the Optus/Avaya system which I consider would be sufficient to provide a cogent and proper basis for inferring that the system would have been able to meet the ProLearn Requirements, particularly given the system does not mention whether it was capable of providing a Personal Call Back List functionality.
644 ProLearn also relies on emails between Asimakidis and Helen Walker (Walker), of Telstra, among others, between 19 February 2015 and 25 February 2015,[629] discussing the Telstra response. The high point of this email chain appears to be when Asimakidis writes, 'ProLearn have also met with Optus who are proposing an Avaya solution with their contact centre' (19 February 2015, 12:16pm).[630] On 25 February 2015 (9:48pm),[631] Asimakidis appears to forward this email chain to Okulicz and writes, inter alia, '[e]nd of the day, if we can't win this with Cisco then we need to put forward an Avaya solution', and further, appears to quote Walker, 'Avaya are very well known for Call Centre capability'.
645 On the question of the establishment of the Alternative System Counterfactual, Telstra and Kytec submit that ProLearn has failed to adduce evidence that it would have been able to secure an alternative system, and of the functionality such a system would have had had it done so.[632] In particular, Kytec submits that:
(a) ProLearn did not lead any evidence from an alternative provider such as Optus;
(b) ProLearn's directors were not qualified to give any evidence about an alternative system as they had no relevant technical expertise; and
(c) nothing about an alternative system was put to Okulicz or Green.[633]
646 Kytec therefore submits that because there is no evidentiary basis to undertake a comparison with an alternative provider or system, the inquiry can only proceed on the basis of the Existing System Counterfactual, comparing the factual scenario which occurred with the Solution and that which existed with the CommSys system.[634]
647 Telstra similarly submits that there is no evidence of any alternative system which could have been delivered.[635]
648 While I accept that Tutungi was in discussions with Optus, I do not accept that these conversations were sufficiently progressed or developed such that the Optus/Avaya system has been sufficiently established as one which represented a real opportunity available to ProLearn, nor one which had the capacity to perform in a manner consistent with the Kytec Representations, the Telstra Representations and the Final Proposal.
649 ProLearn did not adduce evidence from Optus or Avaya and ProLearn has adduced no evidence about the functionality of the Optus/Avaya system.
650 I do not consider that the emails referred to above provide a sufficient basis on which to conclude that the Optus/Avaya system was capable of performing in a manner consistent with the Kytec Representations, the Telstra Representations and the Final Proposal, or to some other capability resulting in an ascertainable operational functionality for ProLearn's business. As highlighted above, and by Kytec, ProLearn did not seek to call evidence from Optus or Avaya.
651 Furthermore, there is no evidence of discussions between representatives of Optus/Avaya on the one hand and Tutungi on the other to establish what Tutungi informed those organisations as to ProLearn's requirements. There is also no evidence that the Optus/Avaya quotation[636] was accompanied by a detailed proposal document which might have assisted in understanding the features and capabilities of that alternative system, and which might have assisted with an assessment as to whether that alternative system represented a realistic and sufficiently probable alternative way of ProLearn implementing a new telephone system likely to compare to the represented characteristics of the Solution.
652 ProLearn submits that it is the foundation of Kytec's defence that the Solution had the functionality to comply with the ProLearn Requirements, and that such a system is available and could have been provided, whether by Optus/Avaya, or by Telstra itself via a more competent dealer other than Kytec.[637] This is put at [61] of the ProLearn Reply Submissions in the following manner:
The assertion that ProLearn has not identified an alternative telecommunications system with the same functionality[638] can be disposed of shortly. It is the essence of Kytec's defence that the NTS should have been able to comply with ProLearn's requirements: see Green [17].[639] Such a system was available and could have been provided (whether by Optus/Avaya) who had quoted for ProLearn[640] or by Telstra itself via a more careful and competent dealer than Kytec.
653 I have found that the Solution as delivered was not suitable for the ProLearn Requirements and in particular did not have the capacity to provide Personal Call Back Lists for 83 agents and was not able to be used by 83 agents simultaneously. There is no evidence that Telstra, working with a dealer other than Kytec, was, or would probably have been, able to procure and install a sufficiently capable and otherwise suitable alternative new telephone system at about that time, or deliver an opportunity that ProLearn would have considered.
654 Tutungi's evidence was that, had she been aware that the Solution was not able to, amongst other things, provide Personal Call Back Lists for 83 agents, ProLearn would have continued its discussions with Optus/Avaya, and had such discussions been unsuccessful, ProLearn would have stayed with the CommSys system.
655 Accordingly, as to the Alternative System Counterfactual_,_ I am not satisfied that ProLearn has established a chain of causation continuing up to the point where ProLearn had a substantial prospect of acquiring the benefit sought by it by acquisition and deployment of any viable and suitable alternative telephone system, namely the opportunity to derive profits from its business using another similarly capable and suitable new telephone system which had the capacity to perform in a manner consistent with the Kytec Representations, the Telstra Representations and the Final Proposal.
656 However, I consider that the Existing System Counterfactual[641] of staying with the CommSys system must be accepted as being an appropriate and adequate base from which to evaluate what ProLearn would have continued to earn but for the loss of revenue and profit ProLearn suffered as a result of implementing the Solution.
657 ProLearn presents the Existing System Counterfactual alternative loss of opportunity case, based on ProLearn having continued to use the CommSys system. ProLearn ultimately argues as to quantification/assessment on the Existing System Counterfactual.
658 ProLearn also argues that if the Existing System Counterfactual is adopted (including for expectation loss for any breach of contract) the Court could assess higher damages on the basis that ProLearn would have engaged more Operators.
659 I also observe at this point that any evaluation of damages, or compensation, to ProLearn on the Existing System Counterfactual basis would not need to be reduced on the basis of the possible benefit ProLearn received by way of the Automated Dialler being able to make a higher number of calls during the Loss Period. There would be no Automated Dialler on the Existing System Counterfactual.
660 I also note that ProLearn's case, although that case postulates alternative counterfactuals, does not argue the appropriateness of a lower level of probability in respect of the prospect of acquiring the Optus/Avaya system. In this way, ProLearn's case presents the alternatives referred to above but does not assist in the application of some intermediate position, nor does ProLearn provide reasons why such an intermediate position would be acceptable in identified hypothetical circumstances.
661 Finally, I note that Kytec and Telstra did not appear to challenge the Existing System Counterfactual, but focused on there being causes other than the adoption of the Solution for ProLearn's reduction in revenue and consequential loss of profits.
Telstra and Kytec's criticisms of Annexure B to Humunicki's witness statement
662 As part of its case seeking to establish its loss, ProLearn relies upon Annexure B to Humunicki's witness statement which is titled 'Sales Spreadsheet' (Annexure B). Annexure B sets out details of the following for each of the months from June 2014 to November 2016:
(a) Total number of sales made;
(b) Number of sales made from call backs;
(c) Percentage of sales from call backs;
(d) Call centre Operator attendance (hours);
(e) Average number of full-time equivalent (FTE) Operators per day;
(f) Total sales per FTE Operator;
(g) Value of sales;
(h) Average value of each sale; and
(i) Value of invoices raised.
663 In her witness statement, Humunicki explained that Annexure B was based on information extracted from ProLearn's CRM, which had been entered by ProLearn's call centre Operators, and from ProLearn's MYOB accounting software.[642]
664 Telstra and Kytec both submit that ProLearn has failed to adduce evidence of the underlying data used by Humunicki to prepare Annexure B and as a result neither the defendants nor the Court can test the veracity of the data analysis.[643]
665 By way of illustration, Telstra refers to what it contends to be confusion in the evidence of Tutungi and Humunicki regarding the extent to which the sales in the First Period included business to business sales, and submits that without the worksheets and source data, this confusion cannot not be resolved.[644] Telstra submits that, for this reason, the Court should be careful in adopting the figures contained in Annexure B as precise figures and contends that, at most, they should be treated as providing a guide to the matters to which they refer.[645]
666 Kytec submits that the CRM data, upon which Annexure B is based, is unreliable, including as to sales from call backs, for the following reasons:[646]
(a) The data was entered by Operators, who as accepted by Humunicki, made errors with the data entry, with the Operator manual aiming for 80 percent accuracy in the first week and no more than three errors per Operator per shift.
(b) As accepted by Humunicki, paper call back lists were used during the Loss Period by ProLearn's operators, and the data from the paper call back lists was not entered in the CRM instantly. While Humunicki said that if there was a sale, the data was then entered in the CRM, she accepted that:
An operator might have entered it into it as sale call made and not bother putting in anything more than that because a sale is a sale.[647]
(c) When constructing Annexure B and calculating the number of sales made from call backs, Humunicki did not compare the numbers for sales against phone bill data from Telstra to validate her analysis by checking how many calls were made to the numbers that were allocated to sales in the CRM.
(d) The definition of a call back was loose and did not necessarily refer to a 'warm lead' or 'a fish that was on the hook'. A call back had to be set and entered for every lead according to the ProLearn Office Handbook, and call backs included people who might be scheduled to be called back weeks or months later.
667 Kytec submits that using call data provided by Telstra would have been a better measure than sales from call backs based on the CRM data and Tutungi's evidence.[648]
668 In relation to these criticisms of Annexure B, ProLearn submit that Humunicki was cross-examined on a basis which accepted the accuracy of Annexure B, and both Telstra and Kytec rely upon parts of Annexure B to support their own case.[649]
669 Furthermore, ProLearn submits that Wright had access to the CRM and Humunicki's witness statement and made no comments about any inaccuracies, and furthermore, Smith verified Annexure B and his evidence was that any differences between his CRM analysis and Humunicki's figures were minor, with Annexure B actually conservative when compared to data from MYOB.[650]
670 ProLearn also submits that, even if Kytec's criticisms of Annexure B were accepted, this would not materially affect the data within it.[651]
(a) the lack of consistency in the sales figures during the First Period as set out in Annexure B, and the inability of ProLearn's witnesses to explain this (see, eg, [125] of the Telstra Closing Submissions).
(b) The lack of probative value of the 'Percentage of Sale from Callbacks' figures in Annexure B to an assessment of whether the alleged opportunity had value, because the figures only take into account call-backs and not other components of a system, such as its ability to make calls.[652]
672 I accept Humunicki's evidence, including Annexure B, for the earlier addressed reasons as to why I have found her evidence reliable and persuasive.
673 I also give significantly less weight to Kytec and Telstra's criticisms of Humunicki's Annexure B in their submissions because Humunicki was cross-examined on a basis which accepted the accuracy of Annexure B and Telstra and Kytec themselves rely upon parts of Annexure B to support their case.[653]
674 Additionally, my acceptance of Humunicki's Annexure B evidence is also based on the fact that Wright did not comment adversely on the inaccuracy of Annexure B and Smith verified Annexure B,[654] and stated that any differences between his CRM analysis and Humunicki's figures were minor and that her evidence in this respect was conservative compared to data from MYOB.[655]
675 I also accept Tutungi's evidence including for the earlier addressed reasons as to why that evidence is in my view reliable and persuasive. In relation to matters which Kytec and Telstra submitted against ProLearn, including in relation to Humunicki's Annexure B evidence, I have also given substantial weight to Tutungi's evidence in reply of 24 April 2019. The Tutungi Reply Witness Statement responds to the expert reports of Wolff, Wright and Green, and I accept and I am persuaded by Tutungi's below responses and explanations in relation to the matters which she addresses below in response to the criticisms made of ProLearn's case and evidence, by these three experts.
676 In response to the Green report, Tutungi states:
(a) ProLearn was not provided with a copy of Kytec's Assessment to Quality (AQ2) submission.[656]
(b) Kytec never advised ProLearn of the risks associated in deploying a single voice gateway.[657]
(c) ProLearn is not aware of Kytec raising a support ticket with Cisco in relation to the To Do List problems or the capacity related freezing issues.[658]
677 In relation to the regulatory changes in the VET Fee-Help sector outlined in the Wolff report, Tutungi states that:
(a) the bans on inducements in April 2015 and January 2016 had no effect on ProLearn's business because ProLearn did not and had never offered inducements.[659]
(b) Prior to the July 2015 reforms, ProLearn had written agreements in place with the education providers with which it dealt and, therefore, the July 2015 reforms did not impact on ProLearn.[660]
(c) The removal of barriers to a student withdrawing from study before the census date was introduced to stop providers from charging students a withdrawal fee and, to Tutungi's knowledge, the TAFEs and RTOs with which ProLearn dealt did not charge a withdrawal fee and, as such, those changes did not impact ProLearn.[661]
(d) The reforms introduced in July 2015 to improve information for students in relation to providers and course fees had no impact on ProLearn's business, because prior to July 2014, ProLearn had introduced a checklist that set out key information about the program which a student was enrolling in, which the student was required to sign and return. From November 2014 the checklist became a Student Commitment Form which explicitly required students to confirm they knew the details of the provider, the course and the course fees.[662]
(e) She recalls being informed by a representative of SWSI, whose identity she could not recall, that the January 2016 VET Fee-Help loan freeze did not apply to TAFEs. While she could not find written communication with SWSI referring to this, Tutungi says that the SWSI enrolments for 2016, as shown in the SWSI subpoenaed documents, is consistent with the VET Fee-Help loan freeze not applying to TAFEs.[663]
(f) The January 2016 reforms relating to strengthened student eligibility requirements, ensuring that debt was only incurred in line with course delivery and creating a requirement to have at least three census dates for Diploma level courses, had no impact on the number of sales as opposed to the manner in which ProLearn was paid (through three instalments rather than one).[664]
(g) The January 2016 marketing reforms, which included a ban on unsolicited contact and cold calling, had no impact on ProLearn's business because ProLearn did not make unsolicited contact with, or cold call, prospective students, with all leads that ProLearn used coming from people who had submitted their contact details online.[665]
(h) ProLearn sent all students an email containing the information required under the January 2016 reforms.[666]
678 As to the communications campaigns conducted by the Commonwealth DET and NSW Fair Trading,[667] Tutungi's evidence is that the methodology used by ProLearn to enrol students was designed to ensure that all students enrolled by ProLearn were fully aware of their obligations prior to enrolling, and while there was considerable adverse publicity about unethical behaviour in the sector, this related to RTOs, not TAFEs.[668] Tutungi states that ProLearn did not engage in any of the unethical practices identified by Wolff in his report,[669] and that from about 2013 ProLearn's procedures included a quality control call that was made by someone who was not a call centre operator before the enrolment of a prospective student was completed. This quality control call included asking the prospective student a series of questions aimed at ensuring the student was fully aware of the details of their course and the obligations they were undertaking.[670]
679 In relation to Wolff's statement that course enrolments funded by VET Fee-Help loans reduced by 31.8 percent from 2015 to 2016, Tutungi says that the data used by Wolff shows that the reduction in enrolments was not homogenous across the industry and that while the data shows that 57 percent of providers saw decreased enrolments from 2015 to 2016, 35 percent of providers increased their enrolment numbers and 8 percent saw no increase or decrease in enrolments.[671]
680 Furthermore, while Wolff states that TAFE NSW suffered a VET Fee-Help supported student enrolment reduction of 35 percent between 2015 and 2016,[672] Tutungi states that ProLearn was not enrolling for TAFE NSW but for SWSI.[673] She states that TAFE NSW was made up of 10 different institutes with different management, and Wolff does not differentiate between those 10 institutes.[674] She states that the SWSI subpoena documents and the NCVER subpoena documents show the following VET FEE HELP supported enrolments at SWSI in 2015 and 2016:[675]
681 As to Wolff's statement that the reduction of the ProLearn RTO and TAFE partnership group to a single provider also reduced the scope of courses available to ProLearn's customers and that this may have negatively impacted sales,[676] Tutungi responds that ProLearn sold 17 courses during the period June 2014 to August 2015 and 14 courses during the period September 2015 to November 2016.[677]
682 Tutungi further explains that ProLearn sought to market courses that it considered were in high demand and that she and Humunicki made assessments as to which courses ProLearn should seek to market based on information as to skill shortages, feedback from prospective students, discussions with educational institutions and information gleaned from their membership of the TAFE Directors Association.[678] Tutungi states that with SWSI, ProLearn selected the courses it wished to market and from 11 April 2014 all of the courses ProLearn marketed for SWSI were online courses, with ProLearn's digital marketing targeted to people looking for the types of courses they were selling.[679]
Tutungi's response to the First Wright Expert Report
683 In response to the First Wright Expert Report, Tutungi states that the prices of the courses that ProLearn offered were set by the relevant TAFE or RTO and did not change during the period September 2015 to November 2016. Tutungi states that the cost of only one of the courses that ProLearn sold for SWSI increased during 2015, being the Dual Diploma of Business and Marketing, which increased from $12,000 to $17,000 under the new contract with SWSI of 30 June 2015.[680]
684 Tutungi also states that Wright incorrectly identified that the Diploma of Information Technology (Networking) increased by more than 800 percent from $2,340 in November 2012 to $20,000 in July 2015, as the course offered at the lower price was a recognition of prior learning program whereas the more expensive course was a traditional study-based diploma which was not based around experience.[681] As to Wright's references to the fact that the price of courses marketed by ProLearn increased over time, Tutungi points to Annexure F of the First Wright Expert Report as showing that the percentage of customers who gave the reason 'Too Expensive' for why they did not want to enrol remained at 0.1 percent from April 2015 to November 2016 after having ranged between 0.5 percent and 0.2 percent in the period July 2014 to March 2015.[682]
685 As to Wright's statements in relation to changes in personnel agency providers,[683] Tutungi states that ProLearn did not have fixed term or exclusivity arrangements with the agencies that it used over the period June 2014 to November 2016, and was able to use whatever agencies it chose to recruit staff.[684]
686 In relation to Wright's analysis of ProLearn's CRM database and in particular her analysis of the trends in the different 'stage names' over time,[685] Tutungi states that Wright analysed the data at the enrolment complete stage but did not analyse the data that related to call backs. Tutungi states that, adopting Wright's methodology, the number of leads spoken to by Operators for which a scheduled call back was recorded in the CRM, but was never made, increased significantly in the post-installation period, with the number going up from 2810 in the period from June 2015 to August 2015 to 5089 in the period from September 2015 to November 2015, an increase of 81 percent.[686] Tutungi identifies that there were three stages that relate to a situation where an operator spoke to an individual and agreed to a time to call them back: Continuous Discussion; Enrolment Date Agreed; and Potential Enrolment. These stages were intended to differentiate the likelihood of a sale from a particular call back, although operators tended to use them interchangeably. Tutungi set out the relevant data as follows:[687]
687 Tutungi notes that, as discussed in the Tutungi First Witness Statement, there were a number of call backs not recorded in the CRM which were recorded in the NTS as part of the Call Back Workaround. Tutungi states that there were 1167 call backs in the NTS in July 2016 and estimated that 80 percent of these were orphan call backs and would not be called back by the NTS.[688]
688 Tutungi also states that the change in the percentage of customers who declined to enrol because they were not interested from the period July 2014 to August 2015 compared to the period September 2015 to November 2016 was modest, increasing from 23.40 percent to 27.95 percent.[689]
689 In relation to Wright's identification that the decline reason of 'do not call' increased over the period from July 2014 to November 2016,[690] Tutungi explained that ProLearn had changed the way it used the Do Not Call (DNC) register after receiving a warning from ACMA by email on 31 March 2016 suggesting that ProLearn had made two calls that may have contravened DNC rules.[691]
690 In relation to Wright's analysis of exchange data relating to ProLearn operations, Tutungi explained the 1 percent increase of 'No route to destination' calls from November 2015 to November 2016 as being in part the result of an issue with the NTS in May 2016 where it incorrectly characterised 14,559 phone numbers as phone numbers with no dial tone.[692]
691 As to Wright's statement that she had not been provided sufficient information to assess the reasonableness of a number of assumptions in Smith's expert report relating to ProLearn's costs, Tutungi states that the defendants were provided with ProLearn's MYOB general ledger for 2013/2104 financial year (ECB No. 945), ProLearn's MYOB transaction accounts for 2014/2015 financial year (ECB No. 943) and ProLearn's MYOB general ledger for the 2015/2016 financial year (ECB No. 944). Tutungi states that the general ledgers and transaction accounts include all invoices for leads purchased by ProLearn as well as details of all payments made to personnel agencies. Document KYT.001.001.0189 (CB 4/3124-3125), is an email that Ryan Smith of Kytec sent to her, setting out the additional handset and licence cost of $2435.45 (excluding GST).[693]
692 As to other assumptions made by Smith which Wright stated she was not provided sufficient information to assess, Tutungi states that:
(a) ProLearn used agencies to recruit operators and there was no delay in recruiting new operators if they were required.
(b) The old CRM, which ProLearn used in the period June 2014 to 30 November 2015, captured student name, invoice number, full course cost and date of sale but did not capture the individual invoices and amounts for courses that were invoiced in instalments.
(c) The new CRM, which ProLearn used from 1 December 2015, captured student name, invoice number, invoice amount and date of sale and recorded the individual invoices and amounts for courses that were invoiced in instalments.
(d) The CRM data summarised in Humunicki's witness statement excludes sales made for students that were subsequently credited.
(e) The question of decrease in income from May to August 2015 is discussed at paragraph 58 of Humunicki's witness statement.
693 While in relation to the assumptions in Smith's expert report which Wright disagreed with, Tutungi referred to the Tutungi First Witness Statement[694] and additionally stated:
(a) Smith does not state that he was instructed to assume ProLearn would have retained all customers.[695]
(b) ProLearn employed one person to deal with the extra administrative burden arising from regulatory changes, and that at the levels of sales referred to in ProLearn's Further and Better Particulars of Loss and Damage dated 20 December 2018, only one person was required to deal with that extra administrative burden.[696]
694 Finally Tutungi states that of the 83 licences ProLearn acquired for use on the NTS, thirteen were for use by administrative staff and 70 were for use by call centre Operators, and when the NTS crashed, the operators were sent home or tried to fill their time with other things such as training and playing games. Tutungi states that she observed that when the NTS did not work as it was designed, this caused Operators frustration, including due to them being abused by people who had been rung more than once, and led to low morale in the call centre.[697] She states that ProLearn undertook five main recruiting drives during the time when the NTS was operating, these being:
(a) on 27 November 2015;
(b) on 14 January 2016, when 33 new Operators commenced;
(c) on 8 February 2016, when ProLearn employed 17 new Operators;
(d) on 14 March 2016, when ProLearn employed another 17 Operators, bringing the total to 71; and
(e) on 14 April 2016, when ProLearn employed 46 new operators.[698]
Paragraphs [28]-[40] of the Tutungi Reply Witness Statement set out data on course enrolments based on the NCVER subpoena documents.
695 Tutungi also provided details of the overall enrolments across 2014, 2015 and 2016 in some of the courses that ProLearn marketed for SWSI in 2015 and 2016, based on the NCVER subpoena documents with the ProLearn enrolment numbers derived from ProLearn's CRM, as follows:
Tutungi states that the NCVER subpoena documents do not contain details for the remaining courses that ProLearn was marketing for SWSI in 2015 and 2016, and that the NCVER subpoena documents contain different information for SWSI than the SWSI subpoena documents.
Quantification of loss and damage upon the Existing System Counterfactual
696 ProLearn identifies two main issues to be resolved in determining the appropriateness of the hypothetical expected level of sales upon which to determine ProLearn's loss and damage on the Existing System Counterfactual, namely:
(a) whether the appropriate comparator is the sales achieved in the last 6 months of the First Period (as opposed to some other comparator such as the last 3 months of sales prior to the Loss Period); and
(b) whether the appropriate comparator is the number of sales ProLearn achieved for all providers for whom ProLearn sold courses during the relevant months of the First Period (Scenario 1), or whether this should be limited to the sales ProLearn achieved during the relevant months of the Loss Period for the providers for which it sold courses for during the Loss Period (Scenario 2).[702]
697 ProLearn primarily submits that upon the Existing System Counterfactual, that is, continuing to use the CommSys system, the appropriate quantification of its loss and damage is $10,812,310.
698 This amount is arrived at on the basis of the hypothetical that ProLearn would have achieved sales during the Loss Period at the same sales rate as it did in the last six months of the First Period in Scenario 1.[703]
699 Alternatively, if the Court were to determine the appropriate comparator was the last 3 months of sales in the First Period on Scenario 1, ProLearn quantifies its loss and damage as being $4,812,505. These above amounts have been calculated by ProLearn's expert Smith and are set out in Table 2.1 of Smith's expert report, which states:[704]
700 Alternatively, if the Court were to consider Scenario 2 more appropriate, ProLearn submits that its loss and damage upon the Existing System Counterfactual should be quantified at $7,324,003 on the basis of the sales achieved by ProLearn in the last six months of the First Period and limited to providers for whom ProLearn sold courses during the Loss Period.[705]
701 ProLearn submits that, if the Court were to consider that the appropriate comparator is the last 3 months of sales in the First Period on Scenario 2 then its loss and damage should be quantified as $2,679,557.[706] These amounts are set out in Table 2.2 of Smith's expert report, which states:[707]
702 ProLearn accepts that regardless of which of the above amounts the Court considers to be an appropriate comparator, on the Existing System Counterfactual, the Court could still arrive at a lesser figure by discounting ProLearn's claim for contingencies, risks and other causes not the fault of the defendants. However, ProLearn did not make submission or point to material to inform such discounts.
703 I consider that if Scenario 2, based on a comparator calculation period of 3 months, is used, there is no need for any additional discounts, including to factor in to this estimate the difficult to quantify factors and circumstances which I have referred to above and accepted were, to a minor extent, negatively impacting ProLearn's sales. This is because:
(a) I have rejected, for reasons I have earlier outlined, Kytec and Telstra's claims that there were other significant and material causes of ProLearn's significant drop in revenue and consequential profits before and after deployment of the Solution;
(b) As the ProLearn calculation of loss and damage under Scenario 2 is based on the Existing System Counterfactual, any unjustified additional revenue generated by ProLearn's use of the Automated Dialler is not applicable; and
(c) In my view, in all the circumstances the calculation of ProLearn's loss, confined to the period of three months prior to the Loss Period and limited to Providers to which ProLearn sold courses in the Loss Period (Scenario 2), is sufficiently and appropriately conservative so as to thereby make appropriate allowance for the factors and circumstances which I have earlier identified and recognised as difficult to quantify but which I nevertheless consider were to some degree impairing ProLearn's revenue in the period prior to deployment by ProLearn of the Solution and after deployment, and which I also consider were likely to gradually but increasingly impair ProLearn's revenue and consequently profits in the Loss Period.
Furthermore, I consider the application of ProLearn's evidence of relevant loss and damage calculated on the conservative basis of a period of three months and on the basis of limited Providers, as referred to above, is in my view likely to be appropriate, just and fair.
This includes because the short duration of three months and its proximity to deployment of the Solution, in my view probably better and more accurately reflects the difficult to quantify factors and circumstances negatively impacting ProLearn's revenue, which it is logical and reasonable to consider were, and would continue to, increasingly negatively impact ProLearn's revenue, in particular the demise of the VET sector market.
Further, by basing the applicable calculation on Providers limited in the manner referred to above, I consider that this component of the estimation of ProLearn's reduced sales and consequent reduced revenue and profit is calculated using an integer which is less hypothetical and which reflects likely actual sales in that period.
(d) Finally, in this assessment process evaluating the large number of relevant factors and circumstances I have referred to, I have done the best I can to estimate the effect of difficult to quantify impairing factors and circumstances on ProLearn's revenue and consequential profits, informed by the very substantial body of data, metrics and other evidence adduced on by the parties on these matters.
704 Further, in this regard I consider that the loss calculation limited to three months prior to the Loss Period is more likely to bring to account the effects of what I accept was an overall decline in the VET market in the First Period and the Loss Period.
705 For the above reasons I am satisfied that ProLearn has sufficiently established, including by its evidence of reduced sales after deployment of the Solution, and in relation to its probable reduction in revenue and losses, that ProLearn's relevant loss and damage has been in the sum of $2,679,553.
706 Sections 236, 237 and 243 of the ACL provide as follows:
236 Actions for damages
(1) If:
(a) a person (the claimant) suffers loss or damage because of the conduct of another person; and
(b) the conduct contravened a provision of Chapter 2 or 3;
the claimant may recover the amount of the loss or damage by action against that other person, or against any person involved in the contravention.
(2) An action under subsection (1) may be commenced at any time within 6 years after the day on which the cause of action that relates to the conduct accrued.
Division 4 -- Compensation orders etc. for injured persons and orders for non-party consumers
Subdivision A--Compensation orders etc. for injured persons
237 Compensation orders etc. on application by an injured person or the regulator
(1) A court may:
(a) on application of a person (the injured person) who has suffered, or is likely to suffer, loss or damage because of the conduct of another person that:
(i) was engaged in a contravention of a provision of Chapter 2, 3 or 4; or
(ii) constitutes applying or relying on, or purporting to apply or rely on, a term of a contract that has been declared under section 250 to be an unfair term; or
(b) on the application of the regulator made on behalf of one or more such injured persons;
make such order or orders as the court thinks appropriate against the person who engaged in the conduct, or a person involved in that conduct.
(2) The order must be an order that the court considers will:
(a) compensate the injured person, or any such injured persons, in whole or in part for the loss or damage; or
(b) prevent or reduce the loss or damage suffered, or likely to be suffered, by the injured person or any such injured persons.
(3) An application under subsection (1) may be made at any time within 6 years after the day on which:
(a) if subsection (1)(a)(i) applies--the cause of action that relates to the conduct referred to in that subsection accrued; or
(b) if subsection (1)(a)(ii) applies - the declaration referred to in that subsection is made.
...
243 Kinds of orders that may be made
Without limiting section 237(1), 238(1) or 239(1), the orders that a court may make under any of those sections against a person (the respondent) include all or any of the following:
(a) an order declaring the whole or any part of a contract made between the respondent and a person (the injured person) who suffered, or is likely to suffer, the loss or damage referred to in that section, or of a collateral arrangement relating to such a contract:
(i) to be void; and
(ii) if the court thinks fit--to have been void ab initio or void at all times on and after such date as is specified in the order (which may be a date that is before the date on which the order is made);
(b) an order:
(i) varying such a contract or arrangement in such manner as is specified in the order; and
(ii) if the court thinks fit--declaring the contract or arrangement to have had effect as so varied on and after such date as is specified in the order (which may be a date that is before the date on which the order is made);
(c) an order refusing to enforce any or all of the provisions of such a contract or arrangement;
(d) an order directing the respondent to refund money or return property to the injured person;
(e) except if the order is to be made under section 239(1)--an order directing the respondent to pay the injured person the amount of the loss or damage;
(f) an order directing the respondent, at his or her own expense, to repair, or provide parts for, goods that had been supplied by the respondent to the injured person;
(g) an order directing the respondent, at his or her own expense, to supply specified services to the injured person;
(h) an order, in relation to an instrument creating or transferring an interest in land, directing the respondent to execute an instrument that:
(i) varies, or has the effect of varying, the first mentioned instrument; or
(ii) terminates or otherwise affects, or has the effect of terminating or otherwise affecting, the operation or effect of the first mentioned instrument.
707 ProLearn seeks damages and compensation pursuant to s 236 of the ACL against both Kytec and against Telstra,[708] and for reasons I have outlined above, total damages in the sum of $2,679,533 will be awarded to ProLearn.
708 ProLearn also, by its Amended Statement of Claim and the ProLearn Closing Submissions, unequivocally seeks to have the Kytec Contract, the Equipment and Services Agreement, the Telephone Contract and the Data Contract set aside from their inception pursuant to s 243 of the ACL.[709]
709 At trial, ProLearn pressed the relief sought in the last preceding paragraph.[710]
710 ProLearn did not seek to reserve its position in that regard in relation to the outcome of its several causes of action, or reserve its election as to remedies and orders, save that it abandoned its claim for refunds of sums paid to Kytec and Telstra, if it succeeded in its damages claims against those parties.[711]
711 ProLearn also, in passing in its oral submissions, appeared to clarify that it ultimately sought the relief which, depending on the outcome of its several causes of action, best advantaged ProLearn.[712]
712 Setting each of the subject contracts aside, as well as ordering damages and compensation to ProLearn pursuant to ss 236 and 237 of the ACL, is I consider just and appropriate in this matter for the reasons I have addressed separately below in relation to s 243 and the effect of rescission of the four subject contracts, including because:
(a) both Kytec and Telstra have each made false and untruthful representations which vitiate each of the subject contracts, including because those false and untrue representations rendered the fundamental contractual precepts, representations and promises made by Kytec and Telstra to ProLearn in late April 2015, illusory;
(b) Kytec and Telstra's contravening conduct has caused very considerable operational, financial and other forms of harm to ProLearn;
(c) all the subject contracts were, in practical terms, inextricably intertwined and interdependent, and all focus in varying ways on the characteristics, delivery and performance of the Solution; and
(d) It is just and appropriate that in the above circumstances, ProLearn be relieved of all the ongoing obligations, liabilities and limitations imposed on it by each of the subject contracts.
713 It is common ground amongst the parties that ProLearn's s 18 ACL claims are apportionable.
714 There is dispute about whether ProLearn's claim under s 29(1)(g) of the ACL is apportionable. ProLearn submits that the claim for damages for contravention of s 29(1)(g) of the ACL is not an apportionable claim within the meaning of s 87CB of the CCA.
715 Telstra also submits that ProLearn's claim for breach of contract and breach of a contractual warranty are apportionable under s 24AE of the Wrongs Act 1958 (Vic) (Wrongs Act), and that ProLearn's consumer protection-related claims are apportionable pursuant to Part VIA of the CCA.
716 Kytec submits that its liability to ProLearn under both s 18 and s 29(1)(g) of the ACL, and in negligence, if established, should be apportioned taking into account ProLearn's conduct in relation to all those causes of action and taking into account Telstra's conduct pursuant to both s 24AH(1) of the Wrongs Act and s 87CB of the CCA.
717 In relation to the Court's apportionment task, with respect to contraventions of s 18 of the ACL, ProLearn submits that in the present circumstances, it is relevant that it was Kytec which formulated the Final Proposal, and was required to deliver the Solution. However, ProLearn submits that it was Telstra with which ProLearn wished to contract, and ultimately contracted, yet it was Telstra which took no responsibility for the content of the Final Proposal or its capacity to deliver that proposal; it was Telstra whose reputation and expertise prompted ProLearn's initial enquiry and it was Telstra which profited from the contracts in relation to the Solution to which it was a party.[713]
718 ProLearn submits that an appropriate apportionment as between Kytec and Telstra on ProLearn's s 18 ACL claims should 'tip' more substantially against Telstra for the above reasons and because it was Telstra, immediately upon ProLearn's enquiry, which referred ProLearn to Kytec.
719 ProLearn also denies that there is any basis for reducing, or apportioning to ProLearn, damages awarded to it based on its own conduct. ProLearn denies any of its conduct was causative of the loss, and says that it is not clear how the matters identified by Kytec, and set out below, require apportionment of damages.[714]
720 Kytec submits that any damages should be reduced or apportioned by reason of ProLearn's own conduct, including:[715]
(a) ProLearn's delays in moving premises;
(b) ProLearn's direction to Kytec to stop working on the Personal Call Back List functionality and instead install the gadget (Call Back Workaround);
(c) ProLearn's failure to manage its business properly, including its failure to hire a dialler manager and other staff required to scale up its business;
(d) ProLearn's failure or inability to purchase sufficient leads, including quality leads, and to employ and retain sufficient operators;
(e) ProLearn's failure to move to a web-based CRM;
(f) ProLearn's business decisions in regard to its contracts and arrangements with SWSI and Cohort; and
(g) ProLearn's planning and management of its own business and staff.
721 Kytec says further that any liability for damages on the part of Kytec should be apportioned equally with Telstra as the supplier of the Solution and carriage services.[716]
722 Telstra submits that ProLearn's claims for breach of contract are apportionable under s 24AE of the Wrongs Act, on the basis that ProLearn's case is in substance that there was a failure by Telstra to exercise reasonable care in respect of the Final Proposal, and that this failure forms the basis of ProLearn's claims for breach of contract.[717]
723 Telstra submits further that whether ProLearn's claim for contravention of s 29(1)(g) of the ACL is apportionable, in circumstances where ProLearn relies on the same conduct to establish its ss 18 and 29(1)(g) claims, it must be doubted that ProLearn can escape the proportionate liability scheme in Part VIA of the CCA.[718]
724 Telstra contends that, in any event, ProLearn has failed to demonstrate how the facts alleged are applicable to a claim for contravention of s 29(1)(g),[719] and says further that the authorities relied on by ProLearn in support of the alleged contravention of s 29(1)(g) of the ACL[720] are not analogous on the facts.[721]
725 Telstra submits that any liability on its part should be reduced to a very small proportion of the amount of loss and damage, in circumstances where the evidence shows that Kytec is primarily responsible for any loss and damage.[722]
726 In my view, I need only consider apportioning liability between Kytec and Telstra, and only in relation to ProLearn's s 18 ACL claims. This is because:
(a) I add that in this matter there is no need to differentiate or deal separately with the apportionment of damages and compensation in respect of contraventions of s 18 of the ACL and contraventions of s 29(1)(g) of the ACL. Here, the whole of ProLearn's loss and damage is as a result of several almost congruous established representations by Kytec and Telstra, contravening both s 18 and s 29(1)(g) of the ACL. Accordingly, in my view, it is not necessary or sensible, nor practically possible, to attempt to adjust the above apportionment on the basis that the wrongful representations which contravened s 29(1)(g) give rise to some separately identifiable loss and damage. Furthermore, as I have observed in this matter, nearly all the established Kytec and Telstra Representations each contravened s 18 of the ACL, giving rise to apportionable liability under that section.
(b) I add for avoidance of any doubt that I do not regard ProLearn as having caused any appreciable part of its own loss or damage. I make this finding in respect of ProLearn's ACL claims and its contractual claims, and its unsuccessful negligence claim.
(c) I have below separately addressed the reasons for concluding that Kytec and Telstra should each bear fifty percent (50%) of the liability for ProLearn's loss and damage.
(d) No s 24AE of the Wrongs Act apportionment is necessary because I have rejected ProLearn's negligence case against Kytec.
I have also rejected Telstra's assertion that ProLearn's claims in contract were in part founded on a breach of contractual duty of care, rather than on unembellished breaches by Telstra of cl 1.1 of the Equipment and Services Agreement and the Warranty in cl 5.3 of Schedule 2 of that same contract;
(e) Although ProLearn has succeeded in its contractual claim against Telstra, ProLearn's pleading and submitted case at trial seeks statutory rescission. ProLearn also pressed to have the Telstra Contracts set aside at trial, more so if, on the outcome of the various ProLearn causes of action in this proceeding, such orders advantaged ProLearn.
Accordingly, ProLearn does not ultimately seek contractual recovery, or an order for contractual damages, and therefore it is at all events unnecessary to decide whether Telstra's apportionment claim asserted as effecting ProLearn's potential contractual entitlements against Telstra should succeed or be rejected.
727 Both Kytec and Telstra counterclaim against ProLearn for amounts owed under the various agreements between the parties relating to the Solution.
728 As against ProLearn, Telstra claims outstanding amounts owed pursuant to the Data Contract, the Telephone Contract and the Equipment and Services Agreement, comprising amounts owing for telephone calls and data ($306,832), and early termination charges under the Data Contract and Equipment and Services Agreement ($209,481).[723]
729 Telstra submits that the early termination charges ($209,481) relate to repayments of pricing discounts provided by Telstra to ProLearn, on the express basis that the Data Contract and Telephone Contract would remain on foot for the agreed time. Accordingly, such charges are not a penalty, and it is fair and reasonable that the amount is repaid.[724]
730 In the event that ProLearn established its claim that Telstra engaged in misleading and deceptive conduct, Telstra submits that the Court should refuse to exercise its discretion in making a declaration that the Data Contract and Telephone Contract are void ab initio, such that the early termination charges do not apply, as submitted by ProLearn.[725]
731 Kytec claims $10,340.00 based on unpaid invoices owing by ProLearn under the Kytec Contract.[726] Kytec submits that ProLearn has pleaded no defence, therefore, to the counterclaim in the event that ProLearn's substantive claims fail, and there should be no set off in relation to Kytec's recovery.[727]
732 ProLearn seeks relief pursuant to s 243 of the ACL in respect of all contractual arrangements between ProLearn and Telstra, and between ProLearn and Kytec, and thereby seeks to have the Court hold that each of the relevant contracts are void ab initio. ProLearn's pleaded position is also that ProLearn requires Telstra and Kytec to repay all moneys paid by ProLearn in accordance with those agreements.[728]
733 Notwithstanding ProLearn's pleaded case referred to in the preceding paragraph, ProLearn's closing submissions at trial were that in the event that the Court orders damages in favour of ProLearn pursuant to s 236 of the ACL, ProLearn no longer seeks the refund of moneys paid under those contracts, but continues to press for those agreements to be set aside.[729]
734 Furthermore, in respect of the contractual arrangements with Telstra, ProLearn accepts that it had the benefit of the data and calls provided by Telstra, pursuant to those contracts, in the amount of $304,172.
735 ProLearn's ultimate position, as submitted at trial, was that subject to recovery of damages for Kytec and Telstra's contravening conduct, ProLearn agrees to pay $304,172 to Telstra.
736 ProLearn also disputes Telstra's claim in relation to early termination charges. ProLearn submits that because those charges arise as a result of the termination by ProLearn of contracts that it would have not entered into, but for the misleading and deceptive conduct of the defendants, Telstra should not be entitled to recover any early termination charges.[730]
737 Because I have decided to accede to the relief sought by ProLearn and set aside the contracts entered into with Telstra, noting that ProLearn has agreed to pay Telstra for data and telephone calls if successful in its s 236 and/or s 237 claims for damages, Telstra's counterclaims against ProLearn have no foundation and will be dismissed.
738 As against Kytec, Telstra seeks indemnity and damages for breach from Kytec, pursuant to the Telstra Dealership Agreement between Kytec and Telstra, for any liability that Telstra has to ProLearn in this proceeding, and in relation to Kytec's conduct which gave rise to Telstra's liability.[731]
739 The Telstra Dealership Agreement specifically provides:
2.15 Indemnity:
You indemnify us and our Representatives from and against any liability, loss, damage, costs or expenses we or our Representatives incur or suffer arising directly or indirectly from or in connection with:
(a) any breach or threatened breach of this agreement by you;
(b) any breach by a Nominated Dealer of its Nominated Dealer Agreement;
(c) any breach by a Linked Dealer of its Linked Dealer Agreement;
(d) any act by or omission of you or your Representatives including negligent or criminal acts or omissions;
(e) the termination of this agreement (or part of this agreement) because of your breach; and
(f) any penalty imposed under any applicable law relating to your performance of this agreement.
Each indemnity in this agreement is a continuing obligation, separate and independent from your other obligations and survives termination of this agreement.
...
4 Informing customers about Products and Services
You must not make any misrepresentations about Products and Services or a Process and, when promoting Products and Service, you must provide accurate information to customers about:
(a) the Service's geographical coverage - especially in any area identified by the customer as an area where the customer intends to use the Service;
(b) the key features and limitations of the Products, Services and associated technologies;
(c) any amounts payable for connection to and supply of the Products and Service; and
(d) any other information about the Products and Services that we give you to provide to customers.
740 It is common ground that the referral by Telstra to Kytec of the ProLearn enquiry, and the subsequent work performed by Kytec in developing the Final Proposal, were undertaken by Kytec within the terms of the Telstra Dealership Agreement.[732]
741 Telstra submits that the above indemnity in the Telstra Dealership Agreement is engaged in respect of ProLearn's claim on the basis that any such liability arising for Telstra in this proceeding arises directly or indirectly from or in connection with the acts or omissions of Kytec, or from the misrepresentations of Kytec in providing the Final Proposal in breach of the Telstra Dealership Agreement.[733]
742 In the alternative, Telstra submits that, in the event that ProLearn establishes its claim, Kytec will have breached the Telstra Dealership Agreement by making a misrepresentation, or misrepresentations, in the Final Proposal, therefore Telstra is entitled to recover and be indemnified by Kytec for Telstra's loss and damage comprising its liability to ProLearn and its legal costs.[734]
743 Telstra also seeks contribution from Kytec, in respect of any liability of Telstra to ProLearn for non-apportionable claims.[735]
744 Kytec denies that the indemnity in the Telstra Dealership Agreement is engaged. Kytec submits that, in the event that Telstra is liable to ProLearn, such liability arises primarily under the contractual arrangements between Telstra and ProLearn, of which the Solution was a part. Any indemnity under the Telstra Dealership Agreement cannot be engaged, as Kytec was not in breach of that agreement.[736]
745 On its terms, Telstra's above identified indemnity and rights to recover damages for breach of the Telstra Dealership Agreement are clear and broad.
746 However, in my view, the clear meaning of the language which Telstra and Kytec employed in the Telstra Dealership Agreement indemnity in cl 2.15, limits the intended enforceable indemnity to liability, loss, damage, costs or expenses Telstra incurs or suffers, directly or indirectly from or in connection with, relevantly, any act or omission by the Dealer (Kytec), or its representatives, including negligent or criminal acts or omissions.
747 In this proceeding, Telstra seeks to apply the terms of the indemnity clause, including in relation to indemnity for breach by Kytec of cl 4 of the Telstra Dealership Agreement, to recover from Kytec whatever sum Telstra may be liable for, including costs (and in addition Telstra's own costs from Kytec).
748 However, here, Telstra is, for reasons I have separately explained, liable to ProLearn for half of the loss and damage suffered by ProLearn in relation to multiple contravening representations by both Kytec and Telstra.
749 I have determined that it is just and appropriate, for the reasons I have also outlined elsewhere, which included that because both Kytec and Telstra's conduct contributed equally to ProLearn's reliance and loss and damage, that Kytec and Telstra are each liable for half of ProLearn's loss and damage.
750 I consider that it follows from the above that Telstra's liability hereunder for ProLearn's loss and damage has not been incurred or suffered by Telstra, directly or indirectly, as a result of Kytec's breach or threatened breach of the Telstra Dealership Agreement or Kytec's acts or omissions.
751 Rather, Telstra's liability hereunder has been incurred and is suffered by Telstra as a direct result of its own acts or omissions.
752 Therefore, I find that cl 2.15 of the Telstra Dealership Agreement is not engaged and does not entitle Telstra to the indemnity it seeks against Kytec.
753 For the same reasons, I also consider that cl 4 of the Telstra Dealership Agreement does not avail Telstra. Telstra seek to recover for breach of cl 4 by means of the indemnity provisions of cl 2.15 of the Telstra Dealership Agreement, which, for reasons I have outlined, does not respond to Telstra's liability hereunder (that is arising from this judgment).
(a) Kytec and Telstra wrongly and in contravention of the ACL represented to ProLearn that:
(i) the Solution would be able to automatically create Personal Call Back Lists (Representation 'A');
(ii) the Solution would be able to be used by 83 agents (Representation 'B');
(iii) the Solution would enhance ProLearn's productivity (Representation 'E');
(iv) the Solution was appropriate for the ProLearn Requirements (Representation 'F'); and
(v) the above representations were based on reasonable grounds (Representation 'G').
(b) In making the Representations identified in the last preceding sub-paragraph, Kytec did so both directly and also as Telstra's agent and with Telstra's consent or agreement within the meaning of both s 84(2)(a) and s 84(2)(b) of the CCA, because those representations were made within the actual or apparent scope of Telstra's authority and were made with Telstra's implied consent and agreement.
(c) Telstra independently wrongly and in contravention of the ACL represented to ProLearn that:
(i) the Solution would be able to automatically create Personal Call Back Lists (Telstra Representation 'TA');
(ii) the Solution would be able to be used by 83 agents (Telstra Representation 'TB');
(iii) the Solution would perform in accordance with the specifications in (i) and (ii) above, for 12 months from the date on which ProLearn completed a customer acceptance certificate (Telstra Representation 'TD'); and
(iv) the above representations were based on reasonable grounds (Telstra Representation 'TE');
(d) The Representations 'A', 'B', 'E' and 'F' referred to above were representations as to future matters, and so also were Telstra Representations 'TA', 'TB' and 'TD' referred to above representations as to future matters.
(e) Each of the above Representations was made in trade and commerce.
(f) Each of Representations 'A', 'B', 'E', 'F' and 'G' and Telstra Representations 'TA', 'TB', 'TD' and 'TE' were false and untrue.
(g) Each of the above Representations constituted conduct that was misleading and deceptive and likely to mislead and deceive in contravention of s 18 of the ACL.
(h) By Representation 'F' as above, Kytec and Telstra made false and misleading representations in respect of the performance characteristics, use and benefits of the Solution in contravention of s 29(1)(g) of the ACL.
(i) By Telstra Representation 'TD', Telstra made false and misleading representations in respect of the performance characteristics, use and benefits of the Solution in contravention of s 29(1)(g) of the ACL.
(j) ProLearn relied on each of the above Representations, and as a result of that reliance ProLearn entered into the Equipment and Services Agreement, the Telephone Contract, the Data Contract and the Kytec Contract, and commenced using the Solution in about late August 2015.
755 I have, for the reasons addressed above, upheld ProLearn's contract claims for breach by Telstra of cl 1.1 of Schedule 2 of the Equipment and Services Agreement and breach of the Warranty in cl 5.3 of Schedule 2 of the Equipment and Services Agreement. Both cl 1.1 and the Warranty in cl 5.3 were breached because of the existence of the problems, defects, deficiencies and incapacities of the Solution.
756 I have also found that the limitation of liabilities clauses at 5.2, 5.3(c) and 5.4 of the Equipment and Services Agreement are effective to limit Telstra's contractual liability as expressly provided in those clauses, in relation to ProLearn's contractual entitlements to damages against Telstra.
757 Accordingly, ProLearn's recovery of damages on either of the two contractual bases it claims (breach of cl 1.1 of Schedule 2 and breach of the Warranty in cl 5.3 of Schedule 2) are subject to the comprehensive and effective liability limitation in cls 5.2, 5.3(c) and 5.4 of the Equipment and Services Agreement.
758 I have also concluded and found that, although not subject to discounts for risks and contingencies, the plaintiff's expectation losses recoverable for breach of the Equipment and Services Agreement are in the same sum also claimed and established by ProLearn as its loss of opportunity damage for the established Kytec and Telstra Representations[737] in the sum of $2,679,553.
759 Assessing all relevant factors in the way outlined above, as best can be done on the evidence, I am satisfied that ProLearn's loss and damage resulting from Telstra's breach of cl 1.1 of Schedule 2 of the Equipment and Services Agreement and Telstra's breach of the Warranty in cl 5.3 of Schedule 2, also equates to the losses of profit ProLearn suffered deploying the defective and deficient NTS Solution, which I have awarded ProLearn pursuant to s 236 and s 273 of the ACL.
760 As I have observed elsewhere, ProLearn seek orders that the Equipment and Services Agreement be set aside and I have acceded to that application and granted the relief which ProLearn seeks, and will make orders including orders setting aside each of the subject contracts.
761 I have concluded for reasons outlined earlier that no relevant duty of care arose between ProLearn and Kytec.
762 Further, for the reasons outlined above, I am also not persuaded that, in any event, Kytec was negligent in relation to the testing of the Solution.
763 For the above outlined reasons, ProLearn is entitled to damages and compensation in the total sum of $2,679,557 against both Kytec and Telstra pursuant to s 236 and s 237 of the ACL.
764 Pursuant to s 87CB of the CCA, I consider that Kytec and Telstra are each fifty percent (50 percent) liable in relation to the damages and compensation awarded to ProLearn in the total sum of $2,679,557.
765 Kytec and Telstra are each equally liable to ProLearn and should each contribute equally to ProLearn's damages and compensation, including because:
(a) both the established Kytec Representation and the established Telstra Representations were, as earlier explained, made jointly and at the same time by Kytec and Telstra;
(b) In addition to Telstra authorising Kytec to relevantly act as its agent, the established Representations were jointly made by Kytec and Telstra as entities in substance partnering in the endeavour of selling their equipment and services to ProLearn;
(c) ProLearn, I consider, relied equally on each of the Kytec and Telstra Representations in deciding to enter into the Equipment and Services Agreement, the Telephone Contract, the Data Contract and the Kytec Contract and to commence using the Solution.
(d) Both the Kytec and Telstra established Representations were false and untrue in essentially the same respects and essentially to the same degrees;
(e) I consider that both Kytec and Telstra were equally responsible for the way in which, and the extent to which, ProLearn was misled and deceived by their Representations; and
(f) Kytec and Telstra to the same degree caused ProLearn's loss and damage as a result of their equally false and untrue established Representations.
766 In The Law of Misleading or Deceptive Conduct, Lockhart compares and contrasts the award damages under ACL s 236 with orders for compensation under ACL s 237, observing that:[738]
ACL s 236 awards, and ACL ss 237 and 238 orders (prior to 1 January 2011, TPA s 82 awards and s 87 orders) share the common purpose of providing redress for loss or damage flowing from a contravention of the statutes' prohibitions. Consequently, as with claims under s 236, a s 237 or s 238 claimant will need to prove the breach caused the loss or likely loss for which compensation is sought. Upon such proof, however, the victim must be granted compensatory orders that compensate for the whole of the loss, irrespective of the provision pursuant to which the claim is brought. On the other hand, just as s 236 awards may not be made for a non-compensatory purpose, ss 237 and 238 will rarely, if ever, enable the grant of orders that fulfil expectations, such as specific performance, or an account of profits.
767 Lockhart identifies that ACL ss 237 and 238 orders extend the statutory compensatory tools under the ACL in at least the following three ways:[739]
First, if the plaintiff has already suffered damage by a breach, and may therefore claim for that loss under s 236, resort to the wide powers granted by ss 237 and 238 may enable a court 'to do more complete justice than can ... be done merely by an award of damages'. Using those powers, which include the ability to make orders combining monetary and non-monetary elements, the court may effectively place the parties in the position they were in before the impugned conduct occurred, rather than attempt to approximate that result by a purely monetary award, particularly where there are significant difficulties associated with fixing the quantum of damages that might be awarded pursuant to s 236.
Second, ss 237 and 238 provide authority to intervene by 'anticipatory' remedies to prevent loss or damage occurring, or continuing to occur, by misleading conduct. ...
Third, 'loss or damage' may have a broader meaning in ACL ss 237 and 238 than in s 236. The phrase in TPA s 87 was said to encompass reliance by entry into a contract induced by misleading conduct, whether or not the act resulted in damage which was compensable under s 82 of the Act. That approach is, however, not easily reconciled with the High Court's statement in Wardley Aust Ltd v WA that detriment upon entry into an agreement has 'not been universally equated with the legal concept of "loss or damage"'. ...
768 As to the interaction between orders for damages under s 236 and orders for compensation under s 237, Lockhart observes that:[740]
In view of the broader scope of ACL ss 237 and 238, the role of s 236 in the Acts' remedial regimes might be thought to be marginal. There is, however, no entitlement to s 237 and s 238 orders, which are granted at the court's discretion.
Orders pursuant to s 237 or s 238, may be refused if, for example, it is impossible to do 'practical justice' between the parties by avoiding a contract induced by a breach, or if a monetary award under those provisions would avoid a limit imposed on damages available pursuant to s 236, such as for contributory negligence. In such circumstances, s 236 awards, which, if sought, must be granted for proven loss or damage by misleading conduct, may be the only means of redress for that loss. Awards pursuant to s 236 will also be the sole available compensatory remedy where the limitation period for a cause of action under s 237 or s 238 (which may begin to run when loss or damage is likely to be suffered) expires prior to that for a s 236 claim (which commences upon actual loss being first suffered by the plaintiff).
Where relief is available under each provision, whether one form of compensation is to be preferred to another is unclear. It was said that damages are the 'ordinary remedy for a breach of [TPA] s 52', and, as 'the right [to damages under TPA s 82 is] not made subject to s 87', the latter did not provide 'a discretionary remedy to take away, or modify the right conferred by s 82'. Further, the reference in ACL ss 237(2) and 238(2) (before 1 January 2011, TPA s 87(1) and (1A)), to the making of orders that 'will compensate [the victim] in whole or in part for the loss or damage' because of, or by, a contravention does 'not suggest that the combination of orders that a court makes should do less than provide full compensation' for the loss. In that context, 'in whole or in part' refers to the possibility that full compensation pursuant to s 237 or s 238, may be 'unnecessary or inappropriate' due to the grant of compensation under other powers, such as s 236.
769 In relation to the Court's powers and approach to setting aside a contract under s 237 in addition to awarding damages or compensation, Lockhart observes:[741]
[A] further question arises as to whether damages for consequential loss from entry into a contract declared void ab initio pursuant to the statutes may, in any event, be granted pursuant to ACL s 236. Although damages pursuant to TPA s 82 were expressly awarded along with avoidance or variation pursuant to s 87, the courts have generally refrained from specifying the power invoked to grant monetary orders in that setting. At first glance, s 236, which provides for the recovery of damages for the amount of loss or damage suffered by misleading conduct, seem less apt for that purpose than ss 237 and 238, which permit money awards which compensate in whole or in part for such loss.
Once a contract is avoided pursuant to ACL s 237 or s 238, though, it is arguable that the court can then look to s 236 to compensate for the whole of the remaining outstanding loss, which seems to have been the assumption behind the Full Federal Court's decision in ASX Operations Pty Ltd v Pont Data Aust Pty Ltd (No 2) to allow the plaintiff to pursue a remedy under TPA s 82 notwithstanding the grant of an avoidance order pursuant to TPA s 87. As damages pursuant to ACL s 236 will clearly be available where the plaintiff has effectively rescinded the contract in question by virtue of an analogous common law right, the better view is that the exercise of the statutory avoidance power ought not to preclude concomitant s 236 awards.
770 In ASX Operations Pty Ltd v Pont Data Aust Pty Ltd (No 2),[742] referred to in the passage above, the court made a declaration that two agreements were void ab initio but on terms requiring payments by the respondent to the first appellant and that the declaration as to invalidity not commence to operate until the filing of a written undertaking by the respondent.
771 In deciding as to the appropriateness of relief in this matter I have also considered the facts of this particular case and the policy of the empowering legislation.[743]
772 I consider that, given my above conclusions and findings, and in the circumstances, also taking into account that ProLearn seeks orders setting aside all the subject contracts between ProLearn and Telstra and ProLearn and Kytec, such relief under s 237 and s 243 of the ACL in the nature of statutory rescission is justified and appropriate and should be ordered here.
773 Setting each of the subject contracts aside under s 243, as well as ordering damages and compensation to ProLearn pursuant to ss 236 and 237 of the ACL, is just and appropriate in this case for reasons including that:
(a) both Kytec and Telstra have each made the misleading and deceptive Representations which vitiated each of the subject contracts, which if it was not for those misleading and deceptive established Representations, ProLearn would not have entered into;
(b) the established Representations undercut the fundamental contractual precepts, representations and promises made in each of the subject contracts by Kytec and Telstra to ProLearn, and on which ProLearn relied in late April 2015;
(c) all the subject contracts were, in practical terms, inextricably intertwined and interdependent, and all focus in varying respects on the characteristics, delivery and performance of the Solution;
(d) Kytec and Telstra's contravening conduct has caused very considerable operational, financial and other forms of harm to ProLearn; and
(e) it is just and appropriate that in the above circumstances, ProLearn be relieved of, and in relation to, all liabilities (save the liability to Telstra for data and calls invoiced by Telstra which ProLearn has accepted it will pay) and all the ongoing obligations, liabilities and limitations imposed by the subject contracts.
774 As a result of the orders which will be made under ss 237 and 243 of the ACL, each of the Equipment and Services Agreement, the Telephone Contract, the Data Contract and the Kytec Contract will be declared void ab initio and set aside. In the result, the contractual bases for the Kytec and the Telstra counterclaims in this proceeding are removed from the dates of those contracts. Similarly, the limitation provisions and indemnity entitlements asserted by Telstra under the Telstra subject contracts with ProLearn have no foundation.
Kytec's counterclaim pursuant to the Kytec Contract
775 Further, as a result of my conclusion and finding that ProLearn is entitled to succeed on its claim for relief under s 237 and s 243 of the ACL, the Kytec Contract will be declared void ab initio and will be set aside, and cannot found the relief Kytec claims under the terms of that Contract. Accordingly, the Kytec counterclaim in relation to unpaid invoices, in the sum of $10,340.00, is dismissed.
Telstra's counterclaims under the Equipment and Services Agreement, the Data Contract and the Telephone Contract
776 Further, as a result of my conclusions and finding that ProLearn is entitled to succeed on its claim for relief under s 237 and s 243 of the ACL, the Equipment and Services Agreement, the Telephone Contract and the Data Contract will be declared void ab initio and of no effect. The Equipment and Services Agreement, the Telephone Contract and the Data Contract are hereby set aside and cannot found the relief Telstra claims pursuant to those three Contracts. Accordingly, the Telstra counterclaim against ProLearn in the sum of $514,663.98 is dismissed.
777 For the reasons outlined above, Telstra's liability in these proceedings ultimately arises as a result of Telstra's own wrongful conduct in relation to making the Telstra Representations.
778 As earlier found, Telstra's liability does not arise either because of a breach, or threatened breach, of the Telstra Dealership Agreement by Kytec, or Kytec's wrongful conduct causing ProLearn loss and damage.
779 For the above reasons, I have earlier concluded and found that the Telstra Dealership Agreement indemnity is not engaged, including by breach of cl 4 of that Agreement, in relation to Telstra's liability to ProLearn hereunder.
780 Further, I observe and add that it would be an anomalous result, and may offend the public policy enshrined in the ACL and CCA, were it to transpire that even though Telstra, 'hand in hand' with Kytec, made prohibited representations for which it was held to be jointly responsible under s 18 of the ACL, and in respect of the loss and damage caused to ProLearn, Telstra was found to be fifty percent liable, pursuant to the Telstra Dealership Agreement, a contract connected to the impugned contracts (the Equipment and Services Agreement, the Telephone Contract and the Data Contract, and the Kytec Contract) and closely associated with the determinative dealings between the parties, Telstra could avoid the financial consequences of its wrongful conduct through the operation of an indemnity clause in the Telstra Dealership Agreement between it and Kytec.
781 For the reasons outlined earlier and those outlined immediately above, I also dismiss Telstra's claims for contribution against Kytec.
782 For the above reasons I declare and propose to order:
1. In relation to the ProLearn claims against Kytec
(a) a declaration that in contravention of s 18 of Schedule 2 of the Competition and Consumer Law 2010 (Australian Consumer Law), Kytec made Representations 'A', 'B', 'E', 'F' and 'G' to ProLearn;
(b) a declaration that in contravention of s 29(1)(g) of the Australian Consumer Law, Kytec made Representation 'F' to ProLearn;
(c) that Kytec pay ProLearn damages pursuant to s 236(1) and s 237(1) of the Australian Consumer Law in the total sum of $1,339,776;
(d) a declaration pursuant to s 237(1) and s 243(a)(ii) of the Australian Consumer Law, that the Kytec Contract is wholly void ab initio and of no effect, and is hereby set aside.
That Kytec's counterclaim against ProLearn, in the sum of $10,340.00, is dismissed.
3. In relation to the ProLearn claims against Telstra
(a) a declaration that in contravention of s 18 of the Australian Consumer Law, Telstra made Telstra Representations 'TA', 'TB', 'TD' and 'TE' to ProLearn;
(b) a declaration that in contravention of s 29(1)(g) of the Australian Consumer Law, Telstra made Representations 'F' and 'TD' to ProLearn;
(c) Telstra pay ProLearn damages pursuant to ss 236(1) and 237(1) of the Australian Consumer Law in the total sum of $1,339,776;
(d) a declaration that pursuant to s 237(1) and s 243(a)(ii) of the Australian Consumer Law, that each of the Equipment and Services Agreement, the Telephone Contract and the Data Contract are wholly void and of no effect and are hereby set aside;
(e) ProLearn pay Telstra the sum of $304,172 in relation to unpaid Telstra invoices.
The Telstra counterclaims and claims against ProLearn and against Kytec are dismissed.
Pursuant to Rule 47.04 of the Supreme Court (General Civil Procedure) Rules 2015, and the Court's inherent discretion, any unresolved questions of costs, interest entitlements, or the form of the above orders, be heard and determined by a Judge to be nominated.
[7] T111.7-16; ProLearn relied on incorrect transcript references in written and oral submissions: I note that ProLearn's transcript references in its written and oral submissions (in many instances) appear to be between four and six pages (4-6) behind the record of Transcript.
[22] Okulicz's statement 25 November 2016, [125] and [150]; T724.19-31, T725.6-13.
[38] Order of Riordan J (Supreme Court of Victoria, S CI 2017 2377, 30 November 2019), [5], as amended by Order of Digby J (Supreme Court of Victoria, S CI 2017 2377, 30 November 2019), [2].
[40] (2012) 247 CLR 345, 432 [232]-[234], 441-5 [250]-[259].
[41] Kytec Reply Closing Submissions, [17] quoting (2012) 247 CLR 345, 442 [250].
[42] Kytec Reply Closing Submissions, [18(a)] citing T179.5-22.
[43] Kytec Closing Submissions, [69]; Kytec's Reply Closing Submissions, [18(b)], citing T535.11-15.
[44] Kytec Reply Closing Submissions, [18(c)].
[45] Kytec Closing Submissions, [131]-[132].
[46] Telstra Reply Closing Submissions, [74].
[47] ProLearn Reply Closing Submissions, [38].
[48] ProLearn Reply Closing Submissions, [38].
[49] Jones v Multiple Sclerosis Society of Victoria 3 VR 499 [506]; Winham v Tabro Meats [2012] VSC 491 [127]-[128].
[50] ProLearn Closing Submissions, [55].
[52] Kytec Reply Closing Submissions, Annexure [55], citing CB236-266, [65].
[54] Kytec Reply Closing Submissions, Annexure, [55].
[55] ProLearn Closing Submissions, [28].
[56] Kytec Reply Closing Submissions, [19].
[57] Kytec Reply Closing Submissions, [20].
[58] ProLearn Opening Submissions, [5].
[59] See, for example, ProLearn Opening Submissions, [63].
[60] CB106-CB184, [16]; CB185-CB210, [7].
[61] CB106-CB184, [16]; CB185-CB210, [7].
[67] ProLearn Opening Submissions, [7]-[9]; CB106-184, [20].
[68] ProLearn Opening Submissions, [8]; CB106-184, [20].
[69] ProLearn Closing Submissions, [5].
[71] ProLearn Closing Submissions, [5].
[72] ProLearn Closing Submissions, [5].
[73] ProLearn Closing Submissions, [5].
[80] ProLearn Opening Submissions, [14]. CB106-184, [29].
[83] CB106-184, [30]; CB236-CB266, [43].
[86] CB1219. This statement is repeated in the Final Proposal: CB1771.
[91] CB1488-1525; CB1537.1-1537.11 and CB1526-1528.
[96] CB1739; ProLearn Closing Submissions, [11].
[97] ProLearn Closing Submissions, [11]; CB1739; CB1747.
[98] CB120, [38]; ProLearn Closing Submissions, [12].
[99] Tutungi [38] (CB1 [120]). Neither Kytec nor Telstra objected to ProLearn's reliance on this evidence in ProLearn Closing Submissions; see also Tutungi's evidence at T400-401.
[102] CB1752; ProLearn Closing Submissions, [15].
[103] CB1752-1822; ProLearn Closing Submissions, [15].
[106] ProLearn Closing Submissions, [19].
[107] ProLearn Closing Submissions, [19].
[108] CB1755; ProLearn Closing Submissions, [16].
[116] ProLearn Closing Submissions, [20]; CB106-184, [66].
[117] T808.21-T810.27. See Kytec Reply Submissions, [11(d)].
[118] ProLearn Closing Submissions, [21].
[127] ProLearn Closing Submissions, [22].
[135] ProLearn Closing Submissions, [23]-[24].
[137] ProLearn Closing Submissions, [79]; CB106-184, [197]. The Audit Report was the subject of a Court Ruling on Day 2 of trial that the extracted passages at [197] of the first Tutungi Witness Statement would not be admitted as expert opinion evidence nor as proof of the facts which are referred to in those passages: T128-132.
[139] ProLearn Closing Submissions, [82]; CB4626-4630.
[142] CB185-210, [44]-[46]; CB236-266, [209].
[143] ProLearn Closing Submissions, [57].
[145] In its Amended Statement of Claim dated 12 September 2018, [8(c) and (d)] (CB0001), ProLearn pleads that Kytec represented that 'the Solution would have the capacity to be used in the future by approximately 200 Operators in accordance with ProLearn's expansion plans, with the only additional requirement being that ProLearn would be required to pay for additional licences' [8(c)] and that 'the Solution would integrate with ProLearn's CRM for customer information' [8(d)]; such representations also being representations of Telstra, in accordance with s 84(2) of the CCA. ProLearn Closing Submissions, 18 June 2019 [50]. These additional representations are not however relied on by ProLearn in its Closing Submissions. Further, ProLearn stated during submissions that ProLearn no longer presses the claim for misrepresentation against Telstra for failure to integrate with the CRM (T1199.14-16).
[146] ProLearn Closing Submissions, [57].
[147] ProLearn no longer presses the claim for misrepresentation against Telstra that 'the Solution would integrate with ProLearn's web-based CRM for customer information'; cf ProLearn's Amended Statement of Claim [11(c)], CB0001: T1199.14-16.
[148] Kytec Closing Submissions, [89].
[149] Kytec Closing Submissions, [92(b)]; T180.21-25; T182.23-28. While ProLearn's CRM was migrated to one written in SQL, in November 2015, it is accepted that this new system was not 'web-based'.
[150] Kytec Closing Submissions, [94].
[151] Kytec Closing Submissions, [95].
[152] Kytec Closing Submissions, [96]; CB236-266, [3]-[25]. See also Kytec Reply Submissions, [6].
[153] See City of Botany Bay Council v Jazabas Pty Ltd [2001] NSWCA 94; [2002] ANZ Conv R 300, [83]; Auswest Timbers Pty Ltd v Secretary to Department of Sustainability and Environment [2010] VSC 389; (2010) 241 FLR 360, 385 [48].
[155] Kytec Closing Submissions, [97]-[98].
[156] Kytec Closing Submissions, [100].
[157] CB236-266, [185]; CB458-548, [17], [106].
[158] CB236-266, [185]; CB458-548, [17], [106].
[160] CB236-266, [62]-[63]; CB458-548, [17], [22], [106].
[161] In its Amended Statement of Claim dated 12 September 2018, [8(c) and (d)] (CB0001), ProLearn pleads that Kytec also represented that 'the Solution would have the capacity to be used in the future by approximately 200 Operators in accordance with ProLearn's expansion plans, with the only additional requirement being that ProLearn would be required to pay for additional licences', and that 'the Solution would integrate with ProLearn's CRM for customer information'; such representations also being representations of Telstra in accordance with s 84(2) of the CCA. However, these additional representations are not relied on by ProLearn in its Closing Submissions.
[163] Telstra Closing Submissions, [70].
[164] Technology Leasing Ltd v Lennmar Pty Ltd [2012] FCA 709, [144].
[165] Tonto Home Loans Australia Pty Ltd v Tavares [2011] NSWCA 389, [194]. Telstra Closing Submissions, [62]-[63]. See also, Telstra Reply Submissions, [41]-[42].
[166] Telstra Closing Submissions, [65].
[167] Telstra Reply Submissions, [45].
[169] CB224-235, [20]-[27]; Telstra Closing Submissions, [66], [74].
[172] Telstra Closing Submissions, [67].
[173] Telstra Closing Submissions, [68].
[174] Telstra Closing Submissions, [69].
[176] Telstra Closing Submissions, [72].
[177] Telstra Closing Submissions, [73]; Telstra Reply Submissions, [46].
[178] Telstra Closing Submissions, [74].
[179] Telstra Closing Submissions, [75].
[180] Telstra Closing Submissions, [76].
[183] Telstra Closing Submissions, [79].
[184] Telstra Reply Submissions, [48].
[185] Telstra Reply Submissions, [48].
[186] Telstra Reply Submissions, [52]-[53].
[187] Telstra Closing Submissions, [80].
[188] Telstra Reply Submissions, [55(a)-(b)].
[189] Telstra Reply Submissions, [55(c)].
[193] CB236-266, [34]. Telstra Closing Submissions, [84].
[196] Telstra Closing Submissions, [84].
[197] Telstra Closing Submissions, [85(a)].
[198] Telstra Closing Submissions, [85(b)].
[199] Telstra Closing Submissions, [91].
[201] CB211-223, [21]-[24]. Telstra Closing Submissions, [93].
[203] Telstra Closing Submissions, [97].
[204] Telstra Closing Submissions, [95].
[205] Telstra Closing Submissions, [86]-[89].
[206] ProLearn Reply Submissions, [1], [11]-[16].
[207] ProLearn Reply Submissions, [1], [11]-[16].
[208] T250.10-15; T251.11-17. ProLearn Reply Submissions, [8].
[209] ProLearn Reply Submissions, [2], [17]-[18].
[210] ProLearn Reply Submissions, [20].
[211] ProLearn Reply Submissions, [27].
[212] CB106-184, [91]-[92]; ProLearn Reply Submissions, [29].
[214] ProLearn Reply Submissions, [32].
[216] ProLearn Reply Submissions, [49].
[217] ProLearn Reply Submissions, [50].
[218] Lisciandro v Official Trustee in Bankruptcy [1995] FCA 1527; (1995) ATPR 41-436; NMFM Property Pty Ltd v Citibank Ltd (No 10) [2000] FCA 1558; (2000) 107 FCR 270.
[219] ProLearn Reply Submissions, [52].
[220] ProLearn Reply Submissions, [54]-[55].
[221] Australian Competition and Consumer Commission v TPG Internet Pty Ltd [2013] HCA 54; (2013) 250 CLR 640, 651 [39].
[222] See Global Sportsman Pty Ltd v Mirror Newspapers Pty Ltd (1984) 2 FCR 82, 87-88.
[223] Butcher v Lachlan Elder Realty Pty Ltd; [2004] HCA 60; (2004) 218 CLR 592, 625 [109]; Parkdale Custom Built Furniture Pty Ltd v Puxu Pty Ltd. [1982] HCA 44; (1982) 149 CLR 191, 199.
[224] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304.
[225] Global Sportsman Pty Ltd v Mirror Newspapers Pty Ltd (1984) 2 FCR 82, 87.
[226] Global Sportsman Pty Ltd v Mirror Newspapers Pty Ltd (1984) 2 FCR 82, 87.
[227] Australian Competition and Consumer Commission v Dukemaster Pty Ltd [2009] FCA 682, [14]-[15].
[228] Universal Telecasters (Qld) Ltd v Guthrie [1978] FCA 9; (1978) 18 ALR 531.
[229] Cassidy v Saatchi & Saatchi Australia Pty Ltd [2004] FCAFC 34; (2004) 134 FCR 585; Gardam v George Wills & Co Ltd (No 1) [1988] FCA 289; (1988) 82 ALR 415.
[230] Accounting Systems 2000 (Developments) Pty Ltd v CCH Australia Ltd (1993) 42 FCR 470.
[231] Gardam v George Wills & Co Ltd (No 1) [1988] FCA 289; (1988) 82 ALR 415.
[232] [2012] FCAFC 1; (2012) 285 ALR 217, 224, [30].
[233] Sykes v Reserve Bank of Australia [1998] FCA 1405; (1998) 88 FCR 511.
[234] Cummings v Lewis [1993] FCA 190; (1993) 41 FCR 559.
[236] [2004] HCA 54; (2004) 217 CLR 640, 649 [13].
[238] In its Amended Statement of Claim dated 12 September 2018, [8(c) and (d)] (CB0001) ProLearn pleads that Kytec represented that 'the Solution would have the capacity to be used in the future by approximately 200 Operators in accordance with ProLearn's expansion plans, with the only additional requirement being that ProLearn would be required to pay for additional licences' and that 'the Solution would integrate with ProLearn's CRM for customer information'. These representations are also alleged to be representations by Telstra in breach of s 84(2) of the CCA. These additional representations did not appear to be relied on by ProLearn in its Closing Submissions and further, ProLearn no longer presses the claim for misrepresentation against Telstra for failure to integrate with the CRM (T1199.14-16).
[241] CB106-184, [38]. See also, ProLearn Closing Submissions, [12].
[242] As to Asimakidis, CB224-235, [34]; T917.10-T918.9. Re Okulicz, CB236-266, [59]; T692.14-23, T695.6-9.
[244] CB1751. See also, ProLearn Closing Submissions, [13].
[251] CB1751. See also, ProLearn Closing Submissions, [13].
[254] CB1-24, [8(b)]. See for example, CB1435.
[258] CB106-184, [48]. See also, [122].
[259] In its Amended Statement of Claim dated 12 September 2018, [8(c) and (d)] (CB0001) ProLearn pleads that Kytec represented that 'the Solution would have the capacity to be used in the future by approximately 200 Operators in accordance with ProLearn's expansion plans, with the only additional requirement being that ProLearn would be required to pay for additional licences' and also pleads that 'the Solution would integrate with ProLearn's CRM for customer information'. The latter representation was also asserted against Telstra in breach of s 84(2) of the CCA. It is to be noted, however, that these representations are not relied on by ProLearn in its Closing Submissions.
[263] See also, ProLearn Closing Submissions, [50].
[272] ProLearn Closing Submissions, [61].
[273] ProLearn Closing Submissions, [66].
[275] ProLearn no longer presses the claim for misrepresentation against Telstra that 'the Solution would integrate with ProLearn's web-based CRM for customer information', cf ProLearn's Amended Statement of Claim [11(c)], CB0001: T1199.14-16.
[280] ProLearn Closing Submissions in Reply, [47] and [51]. See [10].
[283] ProLearn Reply Submissions, [10]
[284] Kytec Closing Submissions, [4].
[285] Tutungi, 17 August 2015 [65] to [221].
[286] Tutungi, 17 August 2015, including at [49].
[287] Tutungi, 17 August 2018, [48] and [49].
[289] Kytec Closing Submissions, [42].
[290] Kytec Closing Submissions, [43].
[291] Kytec Closing Submissions, [53].
[292] Kytec Closing Submissions, [52]; CB7293-7299.
[293] T188-190; T409-410; T176-178, T228-230; Humunicki, T574-575; Tutungi First Witness Statement, [65]-[221].
[294] Tutungi First Witness Statement, [99], [122]; T869.
[295] ProLearn's Closing Submissions, [21] referring to CB106-CB184, [76]-[92].
[296] ProLearn's Closing Submissions, [21] referring to CB106-CB184, [92]-[134], [162]-[166].
[303] CB106-184, [110]; T232.30-T233.1.
[304] ProLearn's Reply Closing Submissions, [45].
[306] ProLearn Reply Submissions, [45].
[308] CB4972-CB4974; CB106-CB184, [163].
[311] Okulicz witness statement at [57], CB245; Green report at [17], CB463 and [119], CB492.
[312] Green report at [17], CB 463 and [77]; Okulicz witness statement at [171], CB260.
[313] Telstra Closing Submissions, [80].
[315] CB132, [66]; CB135, [77]; CB188-189, [17].
[316] CB135, [76]; CB188-189, [21].
[318] CB255, [125], cf CB258-259, [150].
[320] ProLearn Closing Submissions, [69].
[321] ProLearn Closing Submissions, [70].
[322] ProLearn Closing Submissions, [93].
[323] Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540, 550; ProLearn Closing Submissions, [93].
[324] ProLearn Closing Submissions, [93].
[325] ProLearn Closing Submissions, [77].
[326] ProLearn Closing Submissions, [78].
[327] ProLearn Closing Submissions, [80].
[328] Telstra Closing Submissions, [7], [14].
[329] Telstra Closing Submissions, [24].
[330] Telstra Reply Submissions, [13]-[19].
[333] Telstra Closing Submissions, [24].
[334] Telstra Closing Submissions, [27]-[30].
[335] Garden City Transport v National Manufactured Products No 2 Ltd (1995) 65 SASR 109, 115; Doggett v Commonwealth Bank of Australia [2015] VSCA 351, [122]; Telstra Closing Submissions, [13].
[336] Telstra Reply Submissions, [5]-[7], [21].
[337] Telstra Closing Submissions, [37].
[338] Telstra Reply Submissions, [23]-[24].
[339] Telstra Reply Submissions, [25].
[341] CB106-184, [110]; T232.30-T233.1.
[343] T182-5. Telstra Reply Submissions, [26].
[344] ProLearn Reply Submissions, [43].
[345] ProLearn Reply Submissions, [43] citing Walker v Citigroup Global Markets Australia Pty Ltd [2006] FCAFC 101; (2006) 233 ALR 687, 706 [77]; T1167.7-12; T1169.6-18.
[346] ProLearn Reply Submissions, [43].
[347] ProLearn Reply Submissions, [45].
[348] ProLearn Reply Submissions, [45].
[349] ProLearn Reply Submissions, [47].
[350] ProLearn Reply Submissions, [48].
[351] [2015] HCA 37; (2015) 256 CLR 104, 116-117 [46]-[52] (citations omitted).
[357] Walker v Citygroup Global Markets Australia Pty Ltd [2006] FCAFC 101; (2006) 233 ALR 687, 706 [77] (Gyles, Edmonds and Greenwood JJ).
[358] ProLearn Closing Submissions, [21], referring to CB106-CB184, [76]-[92].
[359] ProLearn Closing Submissions, [21], referring to CB106-CB184, [92]-[134], [162]-[166]; CB106-CB184, [76]-[77]; CB185-CB210, [21]-[23]; CB236-CB266, [150].
[361] CB106-184, [110]; T232.30-T233.1.
[362] ProLearn Reply Submissions, [45].
[364] ProLearn Reply Submissions, [45].
[366] CB4972-CB4974; CB106-CB184, [163].
[369] Okulicz Witness Statement, [57], (CB245); Green Report, [17] (CB463), [119], (CB492).
[370] Green Report, [17] (CB 463), [77]; Okulicz Witness Statement, [171] (CB260).
[371] ProLearn Closing Submissions, [21(b)].
[372] ProLearn Reply Submissions, [44]; ProLearn Closing Submissions, [21(b)] referring to CB106-CB184, [135]-[161].
[373] See Tutungi First Witness Statement, CB106-CB184, [135]-[161].
[375] ProLearn Reply Submissions, [44].
[377] Telstra Reply Submissions, [25].
[378] Telstra Reply Submissions, [25] referring to CB236-CB266, [170].
[379] Telstra Reply Submissions, [25] referring to CB458-CB548, [17], [119].
[380] ProLearn Closing Submissions, [95].
[382] ProLearn Closing Submissions, [95].
[383] Telstra Closing Submissions, [43]-[44]; Telstra Reply Submissions, [32].
[390] Telstra Closing Submissions, [42]; CB106-184, [42]; Telstra Reply Submissions, [28]-[30].
[394] ProLearn Reply Submissions, [47].
[400] Telstra Closing Submissions, [47].
[401] Telstra Closing Submissions, [48].
[402] Telstra Closing Submissions, [49].
[403] Telstra Closing Submissions, [50].
[404] Telstra Closing Submissions, [51].
[405] Telstra Closing Submissions, [52].
[406] Telstra Closing Submissions, [53].
[407] Telstra Reply Submissions, [34].
[408] Telstra Reply Submissions, [9]-[12], [36]-[37].
[410] Telstra Reply Submissions, [38(b), (c)].
[411] Telstra Closing Submissions, [54].
[412] Telstra Reply Submissions, [39].
[413] ProLearn Closing Submissions, [96].
[415] ProLearn Closing Submissions, [96]; T1191.16-22.
[416] ProLearn Closing Submissions, [96].
[417] ProLearn Closing Submissions, [96].
[418] ProLearn Closing Submissions, [96].
[419] ProLearn Closing Submissions, [96].
[420] ProLearn Closing Submissions, [96], see relevant principles relied upon by ProLearn at [86]-[88] of ProLearn Closing Submissions.
[422] ProLearn Closing Submissions, [89].
[423] Suisse Atlantique Societe d'Armement Maritime SA v Rotterdamsche Kolen Centrale [1967] 1 AC 361, 443.
[424] Sydney City Council v West [1965] HCA 68; (1965) 114 CLR 481.
[425] ProLearn Closing Submissions, [97].
[427] ProLearn Closing Submissions, [98].
[428] Tutungi First Witness Statement, [216] (CB 1/178); ProLearn Closing Submissions, [96]; T1192.28-T1193.3.
[431] ProLearn Closing Submissions, [102] citing Gunston v Lawley [2008] VSC 97; (2008) 20 VR 33.
[432] ProLearn Closing submissions, [102] citing Gunston v Lawley [2008] VSC 97; (2008) 20 VR 33, 41 [27]; Valleyfield Pty Ltd v Primac Ltd [2002] QSC 80, [66].
[435] ProLearn Closing Submissions, [100].
[437] ProLearn Closing Submissions, [101].
[441] ProLearn Closing Submissions, [102].
[442] Kytec Reply Submissions, [14].
[443] Kytec Reply Submissions, [13]-[14].
[444] Kytec Closing Submissions, [46].
[446] Kytec Closing Submissions, [103]; T143.30-T144.3.
[447] Kytec Closing Submissions, [103]; T165.14.
[448] Kytec Closing Submissions, [103], [106]; CB458-548, [28]-[44].
[450] Kytec Closing Submissions, [108].
[451] T859.27-T860.4, T861.7-10; ProLearn Reply Submissions, [19].
[452] ProLearn Reply Submissions, [20].
[453] Final Proposal, pages 14 and 15.
[454] Kytec Closing Submissions, [2].
[456] Oculicz Witness Statement, [96]-[12] 4; CB236-CB266.
[458] Okulicz Witness Statement, [107].
[459] Okulicz Witness Statement, [109].
[461] Okulicz Witness Statement, [117].
[469] ProLearn Reply Submissions, [20].
[470] CB1-24, Prayer for Relief, [I,A], [II,A].
[471] CB1-24, Prayer for Relief, [I,B], [II,B].
[472] ProLearn Closing Submissions, [120]-[123].
[473] ProLearn Closing Submissions, [123]; ProLearn Reply Submissions, [59].
[474] Amended Statement of Claim, [38] and [40].
[475] Amended Statement of Claim, [38] and [40].
[476] ProLearn Closing Submissions, [120].
[477] ProLearn Closing Submissions, [121].
[478] ProLearn Closing Submissions, [122].
[479] ProLearn Closing Submissions, [130].
[480] ProLearn Closing Submissions, [117].
[481] Cf 'global loss cases': Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 350. ProLearn Closing Submissions, [118].
[482] ProLearn Closing Submissions, [130].
[485] ProLearn Closing Submissions, [139].
[486] ProLearn Closing Submissions, [134]-[135].
[487] Smith Expert Report [CB366], [392], [397].
[488] ProLearn Closing Submissions, [139].
[489] CB200-203, [58]-59]; T500.11-.20; T501.3-.15; T449.3-.31; T451.1-.7; T440.8-.31; T441.3-.13; T488.12-.16; T494.1-.7. ProLearn Closing Submissions, [138].
[490] ProLearn Closing Submissions, [134]-[135].
[491] ProLearn Closing Submissions, [140].
[493] ProLearn Closing Submissions, [141].
[494] ProLearn Closing Submissions, [119].
[495] CB106-184, [222]-[226]; CB267-297, [7], [8], [10], [11], [17], [18]-[27]; T451.1-7; T468.10-.13.
[496] CB549-613, [36.6]. ProLearn submits that data produced by SWSI on subpoena in fact showed a total decline in SWSI enrolments of 6.6 percent: CB267-297, [15]; ProLearn Closing Submissions, [148]. ProLearn says that this evidence should be preferred to the evidence in the Wolff Report (see [271(f)]), as Wolff considered decline in enrolments across all divisions of TAFE NSW (SWSI is one of ten divisions), rather than any decline to SWSI enrolments: ProLearn Closing Submissions, [147].
[497] CB267-297, [12]; CB549-613, [34.10]. ProLearn Closing Submissions, [146].
[498] Kytec Closing Submissions, [122].
[499] Kytec Closing Submissions, [126(h)].
[500] Kytec Closing Submissions, [133].
[501] Kytec Closing Submissions, [123]-[125].
[503] Kytec Closing Submissions, [126(g)].
[504] Kytec Closing Submissions, [126(f)].
[505] Kytec Closing Submissions, [136].
[506] Kytec Closing Submissions, [147].
[507] Kytec Closing Submissions, [139].
[508] Kytec Closing Submissions, [131]-[132].
[509] CB1-24, [21(f)], [38]. Telstra Closing Submissions, [100].
[510] Telstra Closing Submissions, [101].
[511] Telstra Closing Submissions, [103].
[512] Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 355, 364; Sensis Pty Ltd v McMaster-Fay [2005] NSWCA 163, [24]. Telstra Closing Submissions, [105].
[513] Telstra Reply Submissions, [64].
[514] Telstra Closing Submissions, [109].
[515] Telstra Closing Submissions, [110]-[116].
[516] Telstra Closing Submissions, [111]; Telstra Reply Submissions, [70]-[71].
[517] Telstra Closing Submissions, [112].
[518] Telstra Closing Submissions, [113].
[519] Telstra Closing Submissions, [114].
[520] Telstra Closing Submissions, [115].
[521] Telstra Closing Submissions, [116]. See further, Telstra Closing Submissions, [117]-[121]. Telstra relies on evidence in the Wolff Report that TAFE NSW suffered VET Fee-Help enrolment reduction of 35 percent between 2015 and 2016, greater than the 31.8 percent decline experienced in the wider market: CB549-613, 34.10; Telstra Closing Submissions, [118]. Telstra submits that Wolff's evidence should be preferred to the evidence of Tutungi (see [265]), as the figures used by her include all enrolments (not just VET Fee-Help enrolments), and the data is unreliable and likely contains duplication: T960.29-T961.18, T951.22-T952-5, T964.20-T965-6; Telstra Closing Submissions, [121].
[523] Telstra Reply Submissions, [74]-[75].
[524] Telstra Closing Submissions, [123].
[525] Telstra Closing Submissions, [123]-[125]; Telstra Reply Submissions, [68].
[526] Telstra Closing Submissions, [124].
[527] Telstra Closing Submissions, [125].
[528] Telstra Closing Submissions, [126].
[529] Telstra Closing Submissions, [132].
[530] Telstra Closing Submissions, [129].
[532] Telstra Reply Submissions, [72].
[533] Telstra Closing Submissions, [135].
[534] ProLearn Reply Submissions, [38].
[535] ProLearn Reply Submissions, [39].
[536] ProLearn Reply Submissions, [61].
[537] ProLearn Reply Submissions, [63].
[538] ProLearn Reply Submissions, [64].
[539] CB185-210, [65 (a) and (b)], cf [67 (a) and (b)]; Annexure B.
[540] T191.23-192.6; 245.20-.30; CB185-210, [60] and [61]. ProLearn Reply Submissions, [66].
[541] ProLearn Reply Submissions, [70].
[542] ProLearn Reply Submissions, [73].
[543] ProLearn Reply Submissions, [74].
[551] See Adelaide Petroleum NL v Poseidon Ltd (1990) 98 ALR 431 (French J).
[552] (1994) 179 CLR 332, 348.
[553] (1994) 179 CLR 332, 349 (citation omitted).
[554] (1994) 179 CLR 332, 355.
[555] (1994) 179 CLR 332, 352.
[556] (1994) 179 CLR 332, 358-359.
[557] (1994) 179 CLR 332, 359.
[558] (1994) 179 CLR 332, 362.
[559] (1994) 179 CLR 332, 364.
[560] (1994) 179 CLR 332, 364-365.
[561] (1994) 179 CLR 332, 368.
[563] (1990) 169 CLR 638, 642-643.
[565] [2016] HCA 18; (2016) 257 CLR 440, 454-455 [40]-[41] (citation omitted).
[567] [2020] HCA 27; (2020) 94 ALJR 715, 730 [36].
[568] Telstra Reply Submissions, [64]. See also, Telstra Closing Submissions, [101]-[103], and Kytec Closing Submissions, [136]. Kytec also adopts Telstra's submissions concerning 'global loss' cases: Kytec Closing Submissions, [147].
[569] Telstra refers to Mainteck Services Pty Ltd v Heurtey & Anor [2014] NSWCA 184; (2014) 89 NSWLR 633, [186]-[205] where Leeming J summarised the principles applying to global loss claims by reference to the decision of Byrne J in John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 8 VR 681. Telstra also refers to the reasons of Beech J in DM Drainage & Constructions Pty Ltd v Karara Mining Ltd [2014] WASC 170, [59], [61].
[570] Telstra Closing Submissions, [103].
[571] John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 8 VR 681, [14]; Laing Management (Scotland) Ltd v John Doyle Construction Ltd [2004] ScotCS 141; [2004] BLR 295; 2014 SC 713.
[572] Laing Management (Scotland) Ltd v John Doyle Construction Ltd [2004] ScotCS 141; [2004] BLR 295; 2014 SC 713, [10].
[573] Telstra Reply Submissions, [64].
[574] Malec v JC Hutton Pty Ltd (1990) 169 CLR 638, 639.
[575] (1990) 169 CLR 638, 638.
[576] (1990) 169 CLR 638, 639-640.
[577] Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 368.
[579] See for example, March v E & MH Stramare Pty Ltd [1991] HCA 12; (1991) 171 CLR 506, 509, 515-516, 522-24, 529, 530-531.
[580] Henville v Walker [2001] HCA 52; (2001) 206 CLR 459, 469 [14], 480 [61], 509 [163].
[581] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304, 341 [102].
[582] ProLearn Closing Submissions, [130]. See, Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 368.
[583] ProLearn Closing Submissions, [130]. See, (1994) 179 CLR 332, 368.
[588] CB106-184, [26]; CB185-210, [10].
[589] CB106-184, [26]; CB185-210, [10]; CB2698-2738.
[590] Telstra Closing Submissions, [87].
[591] See [46] of these reasons. Tutungi refers to the 'provision of the documents set out in paragraph 24', however this reference to paragraph 24 of the Tutungi First Witness Statement appears to be an error.
[596] Humunicki Witness Statement, [47]-[73], [65] and [67]; Humunicki Witness Statement, Annexure B (Record of Sales).
[597] Humunicki Witness Statement, [47]-[73].
[598] Tutungi First Witness Statement, [66]-[233]; Humunicki Witness Statement, [47]-[73].
[599] See for example, Kytec Closing Submissions, [73]-[76]. See also, CB236-266, [164]; CB236-266, [175].
[601] CB185-210, [65(f)], [67(f)].
[602] CB366-457, [7.19], Table 7.19.
[605] Kytec Closing Submissions, [5].
[606] Kytec Closing Submissions, [61].
[607] ProLearn Reply Submissions, [63].
[608] ProLearn Reply Submissions, [64].
[609] Telstra Closing Submissions, [109].
[613] Tutungi Reply Witness Statement, including at [8(c)], [10], [18], [19] and [27].
[614] See for example, Telstra Closing Submissions, [111]; Kytec Closing Submissions, [125].
[616] See T455.8-11; T455.21-31; T456.1-30; T467.19-23; T491.27-31; T492.6-15; T492.26-31; T515.16-26.
[617] CB106-184, [143]; T169.9-28; T260.8-16; T310.29-T311.4.
[619] ProLearn Reply Submissions, [68], referring to CB614-CB711, [5.2.25].
[620] Telstra Closing Submissions, [124]; Telstra Reply Submissions, [68]; Exhibits D21B and D21C, CB7298-7299.
[621] See for example, Gates v City Mutual Life Assurance Society Ltd (1986) 160 CLR 1, 7, 13-14.
[622] (1994) 179 CLR 332, 365.
[623] Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 368.
[632] Kytec Closing Submissions, [138]. See also T1041.2-18; T1043.11-22; T1158.1-5; T1249.15-23.
[633] Kytec Reply Submissions, [23].
[634] Kytec Reply Submissions, [23].
[637] ProLearn Reply Submissions, [61].
[638] Telstra Closing Submissions, [106]; Kytec Closing Submissions, [138].
[641] ProLearn Further and Better Particulars of Loss and Damage, [7].
[642] Humunicki Witness Statement, [56]-[57].
[643] Telstra Closing Submissions, [126]; Kytec Closing Submissions, [126].
[644] Telstra Closing Submissions, [126], citing Tutungi XXN at T322-324.
[645] Telstra Closing Submissions, [126].
[646] Kytec Closing Submissions, [133].
[648] Kytec Closing Submissions, [134].
[649] ProLearn Reply Submissions, [74].
[650] ProLearn Reply Submissions, [74].
[651] ProLearn Reply Submissions, [39].
[652] Telstra Closing Submissions, [123]-[126].
[653] ProLearn Reply Submissions, [74].
[659] CB267-CB297, [7], [19] referring to CB549-CB613, [4.1], [4.2], [22.2.1], [23.2.2], [23.2.3].
[660] CB267-CB297, [8(a)] referring to CB549-CB613, [4.2], [22.2.2].
[661] CB267-CB297, [8(b)] referring to CB549-CB613, [4.2], [22.2.2].
[662] CB267-CB297, [8(c)] referring to CB549-CB613, [4.2], [22.2.2].
[663] CB267-CB297, [9] referring to CB549-CB613, [4.3], [22.3.1.1].
[664] CB267-CB297, [10] referring to CB549-CB613, [4.3], [25], [35.6].
[665] CB267-CB297, [18] referring to CB549-CB613, [23.2.1].
[666] CB267-CB297, [20] referring to CB549-CB613, [23.3].
[672] CB549-CB613, [6.7], [6.8], [34.10], [34.11].
[677] CB267-CB297, [23]. The Tutungi Reply Witness Statement contains a table comparing the courses offered in these periods at CB267-CB297, [24].
[683] CB614-CB711, [5.2.33]-[5.2.36].
[690] CB614-CB711, [5.3.8]-[5.3.9].
[699] Including the Diploma of Community Services Work and the Diploma of Community Services (Case Management).
[700] Tutungi states that the NCVER data for 2014 appears to be incomplete as it discloses only 414 enrolments, whereas ProLearn secured 711 enrolments.
[701] Tutungi states that the data appears to be incomplete as it shows no enrolments in 2016 notwithstanding that ProLearn provided seven enrolments in SWSI in 2016.
[702] See ProLearn Closing Submissions, [136].
[703] See ProLearn Opening Submissions, [60]; ProLearn Further and Better Particulars of Loss and Damage, [2]-[4], [7]-[8]; ProLearn Closing Submissions, [134]; ProLearn Reply Submissions, [72].
[705] See ProLearn Opening Submissions, [60]; ProLearn Further and Better Particulars of Loss and Damage, [2]-[4], [7]-[8]; ProLearn Closing Submissions, [135].
[706] See ProLearn Closing Submissions, [135]; ProLearn Reply Submissions, [72]; Note at CB 370 Smith's figure is $2,679,553.
[708] Amended Statement of Claim 38(b); Prayer for Relief IA and B, and IIA and B.
[709] Amended Statement of Claim 38(a); Prayer for Relief IC and IIC. ProLearn's pleaded claim (and the consequential relief sought to have the relevant Contracts set aside under s 243 of the ACL) were not in the alternative (Amended Statement of Claim [38] (see also [27] and Prayer for Relief IC and IIC)).
[710] ProLearn Closing Submissions, [157], [159]-[163] and [165]-[166].
[711] ProLearn Closing Submissions, [158].
[713] ProLearn Closing Submissions, [156].
[714] ProLearn Reply Submissions, [40].
[715] Kytec Closing Submissions, [149].
[716] Kytec Closing Submissions, [150].
[717] Telstra Closing Submissions, [137].
[718] Telstra Closing Submissions, [138].
[719] Telstra Closing Submissions, [139]-[140].
[720] See ProLearn Closing Submissions, [56].
[721] Telstra Reply Submissions, [76].
[722] Telstra Closing Submissions, [138].
[724] Telstra Closing Submissions, [146].
[725] Telstra Closing Submissions, [147].
[727] Kytec Closing Submissions, [148].
[728] ProLearn Closing Submissions, [157]; CB1-24, [38].
[729] ProLearn Closing Submissions, [158]-[159].
[730] ProLearn Closing Submissions, [162].
[731] CB25-49, [53]-[59]. Telstra Closing Submissions, [148].
[732] Telstra Closing Submissions, [149].
[733] Telstra Reply Submissions, [150]-[151].
[734] CB25-49, [60]; Telstra Closing Submissions, [152].
[735] CB25-49, [61]; Telstra Closing Submissions, [153].
[736] Kytec Closing Submissions, [151]-[153].
[737] ProLearn's pleaded claim for contractual damages in the Amended Statement of Claim 2018 [4], [8] and [10], and the Existing System Counterfactual at paragraph [4] of ProLearn Further and Better Particulars of Loss and Damage were to apply. ProLearn Closing Submissions, [164]; ProLearn Reply Submissions, [72]; T 1245-1246 [39], ProLearn Further and Better Particulars of Loss and Damage: the ProLearn damages flowing from the breach of the Equipment and Services Agreement, and the repudiation of the Equipment and Services Agreement by Telstra are, as put by ProLearn, to be calculated and identified in the same way as the loss of opportunity damages and the compensation sought by ProLearn in relation to its ss 236 and 237 of the ACL claims.
[738] Colin Lockhart, The Law of Misleading or Deceptive Conduct (5th ed, 2019, LexisNexis) 527 [11.52] (citations omitted).
[739] Colin Lockhart, The Law of Misleading or Deceptive Conduct (5th ed, 2019, LexisNexis) 527-9 [11.53] (citations omitted).
[740] Colin Lockhart, The Law of Misleading or Deceptive Conduct (5th ed, 2019, LexisNexis) 530 [11.54] (citations omitted).
[741] Colin Lockhart, The Law of Misleading or Deceptive Conduct (5th ed, 2019, LexisNexis) 540-1 [11.64].
[743] Awad v Twin Creeks Properties Pty Ltd [2012] NSWCA 200.
ProLearn
Kytec and Telstra [2022] VSC 5
(2012) 247 CLR 345
(2010) 241 FLR 360
(2000) 107 FCR 270
(2013) 250 CLR 640
(1984) 2 FCR 82
(2004) 218 CLR 592
(1982) 149 CLR 191
(2009) 238 CLR 304
(1978) 18 ALR 531
(2004) 134 FCR 585
(1988) 82 ALR 415
(1993) 42 FCR 470
(2012) 285 ALR 217
(1998) 88 FCR 511
(1993) 41 FCR 559
(2004) 217 CLR 640
(1988) 18 NSWLR 540
(1995) 65 SASR 109
(2006) 233 ALR 687
(2015) 256 CLR 104
(1965) 114 CLR 481
(2008) 20 VR 33
(1994) 179 CLR 332
(1986) 160 CLR 1
(1990) 98 ALR 431
(1990) 169 CLR 638
(2016) 257 CLR 440
(2020) 94 ALJR 715
(2014) 89 NSWLR 633
(1996) 8 VR 681
(1991) 171 CLR 506
(2001) 206 CLR 459
(1991) 27 FCR 492