[2021] WASC 45
Supreme Court of WA
2021-02-24
Martin J
Original judgment source is linked above.
The key point presently, however, is that the two MRSLAs entered in 2006, are very obviously long term agreements spanning potentially 30 years' duration, or more. They envisage, objectively assessed of course, a first construction phase of mining infrastructure, to establish an ore processing plant at Area A at Cape Preston prior to the following envisaged production of 'Product' (as defined in MRSLA cl 8.2(a)). The construction phase to establish the processing plant at a greenfields mining location and any delays associated with getting that plant established to the point of readiness to generate Product for offshore shipment, are obviously now all events of the somewhat distant past as regard the ongoing performances of the two MRSLAs.
[For the purposes of the ASOC trial exercise in relation to so‑called 'Purported' September 2010 and December 2017 Notifications mentioned above, no reliance, other than as background, looks to be placed upon par D from a debt liability creation perspective, by Mineralogy. However, as explained earlier, Mineralogy does rely upon its April 2018, further and alternatively on its May 2018, notifications and notices, to ground its debt claim put against the CITIC defendants.]
(a) were not a use of the administrative fund for any of the purposes identified in clause 5 of the Facilities Deeds; and
(b) were made in breach of Mineralogy's obligations in clause 5 of the Facilities Deeds to use the Administrative Fund only for the purposes identified in that clause.
The key text in each MRSLA as to the Site Remediation Fund
...
20.4 Site Remediation Work
(a) As and when required by Legal Requirements, Sino will carry out all Site Remediation Work that may be required as a result of Sino's Activities. All Site Remediation Work must meet Legal Requirements.
(b) Following Mine Closure, Sino will remove and dispose of all Sino's Project Facilities in accordance with Legal Requirements, and will carry out all necessary Site Remediation Work. Sino will comply, and will continue to comply, with all ongoing Legal Requirements relating to Site Remediation Work on areas affected by Sino's Activities.
20.5 Mineralogy may require security
Mineralogy may from time to time require Sino to provide reasonable security for the performance of its obligations under this Clause 20. Such security will be provided in the form of a Site Remediation Fund.
20.6 Site Remediation Fund
(a) In order to make provision and to provide security for payment of future Site Remediation Costs as they become payable, Mineralogy will establish a Site Remediation Fund, and Sino will make payments into the Site Remediation Fund in the manner set out in this clause.
(b) The Site Remediation Fund is intended to provide security and certainty for the benefit of Sino, and for Mineralogy as the holder of the Mining Lease, that sufficient funds will be available at Mine Closure to meet Site Remediation Costs.
(c) The Site Remediation Fund will be maintained in a separate interest-bearing trust account controlled by Mineralogy as trustee, and which will be designated as a trust account. The interest earned on funds in the Site Remediation Fund will be retained in the Site Remediation Fund.
(d) The Site Remediation Fund may be used solely for the purpose of paying Site Remediation Costs as they become payable. The Site Remediation Fund may not be used or accessed for any other purpose.
(e) For each Operating Year, Mineralogy will determine an annual charge on account of future Site Remediation Costs to be made by Sino in that Operating Year. The amount of the annual charge is to be determined by Mineralogy, having regard to:
(i) Mineralogy's best prevailing estimate of the amount of future Site Remediation Costs, and the amount (if any) already contributed by Sino into the Site Remediation Fund; and
(ii) the number of years remaining until Mine Closure.
(f) At least 30 days prior to commencement of each Operating Year, Mineralogy will notify Sino of its annual charge in respect of the forthcoming Operating Year.
The parties' non-expert witnesses at trial Mineralogy
All topsoil that may be removed ahead of pipelaying operations to be stockpiled for replacement in accordance with the directions of the Inspector.
... Mineralogy had granted, through the Subleases described above, rights to mine magnetite iron ore to several of its subsidiaries which were party to the JDA, but the extraction of the ore pursuant to those rights required a single open cut operation. The JDA, accordingly, sought to coordinate the manner in which the mining rights granted under the Subleases were to be exercised, including through the use of a 'Manager' which was initially to be Mineralogy Mine Management Pty Ltd.
Schedule 1 to the JDA included an allocation of 'Mine Costs' among each of the companies participating in the mining operations.
(a) was a variation and restatement of and so, had replaced the Sino sublease of 25 October 2001 (referring to cl 2.1 of the First Sino MRSLA);
(b) that Sino Iron was granted certain rights by Mineralogy with respect to the mining of magnetite iron ore, although such rights were to be 'in accordance with the JDA' (cl 4.2) and subject to the terms and conditions identified, including terms and conditions in the JDA (cl 4.3); and
(c) by cl 18.5 of the First Sino MRSLA, that Mineralogy could require Sino Iron to provide reasonable security for the performance of its obligations to carry out 'Site Remediation Work' in the form of a Site Remediation Fund as provided for in the JDA.
(a) the 2006 MRSLAs were a variation and restatement of and so, effectively replaced the First Sino and First Korean MRSLAs (cl 2.1);
(b) a granting of certain rights to Sino Iron and Korean Steel by Mineralogy was no longer to be in accordance with or subject to the terms of the JDA; and
(c) nonetheless, cl 20.5 and 20.6 in each MRSLA enabled Mineralogy to require a provision of reasonable security for the performance of Sino Iron and Korean Steel's obligations to carry out Site Remediation Work on the basis of such security being provided in the form of a Site Remediation Fund.
... Mineralogy, with effect from 'Completion', conditionally assigned all of its rights, title and interest under the JDA to CITIC, but that if CITIC did not exercise a certain option by a certain time, such right, title and interest was to be reassigned back to Mineralogy.
... agreed that the JDA would be suspended and eventually, subject to certain conditions, terminated, with CITIC or its nominee taking on the responsibility for coordinating the activities of Sino Iron and Korean Steel and each of CITIC, Sino Iron and Korean Steel being solely responsible for all 'Mine Costs' incurred.
A Preliminary Decommissioning and Closure management plan has been approved by the EPA. Progressive rehabilitation in accordance with the WRL and TSF Management Plans will take place on the waste rock landforms and the TSF. The WRL and TSF areas located on Plans B, C and D are rehabilitated footprints allowing for re-working of the gradient and batter angles to produce a final form. The WRL and TSF will be built to include a buffer of approximately 50 m at relevant tenement boundaries.
Given its forensic importance, I will refer specifically to the full content of the 11 April 2014 communication later in the reasons.
Dear Colleagues
Further to paragraph 3(d)(i) of our letter of yesterday, 10 April 2014, we advise that the account details for the Site Remediation Fund established by our client are as follows:
Name of Account: Mineralogy Pty Ltd - Remediation
Institution: NAB
Account Number: [REDACTED] 6708
BSB Number [REDACTED]
Regards
Joel Borgeaud
The only organisations, such as law firms and real estate agents, that are required by statute to have a statutory trust account are capable of having a 'statutory trust account' with the bank. For accounts for private trusts, being every other trust that is not an express statutory trust account, the trust just holds as regular account with the bank.
Hello Michael and thanks for your time on the telephone this afternoon.
Here are the details of the account
Account name: MINERALOGY PTY LTD REMEDIATION ACCOUNT
Account BSB & number: [REDACTED] 6708
Credit Interest Rate structure:
Tiered (Interest paid on whole balance over threshold) calculated on daily balance, paid monthly
From $1 to $1,000,000 RBA Cash Rate less 0.50% - currently 1.00%
From $1,000,001 to $2,000,000 - RBA Cash Rate less 0.25% - currently 1.25%
From 2,000,001 and over - RBA Cash Rate less 0.00% - currently 1.50%
Account Fees:
Base account fee of $20 per month (waived when minimum credit balance is maintained above $5,000)
Transaction Fees: $0.30 per transaction (first 50 transactions per month are free)
Account opening date: 11 April 2014
Account operating authority (unconfirmed): Clive Frederick Palmer solely to sign (I cannot locate the original account authority which should have been obtained at establishment. Please arrange for attached Account Authority Card to be signed.)
Account status: Stopped to Debit Operations (Stop will be removed on receipt of signed Account Authority Card).
Please let me know if you have any further questions.
Regards,
Philip Ingle
Transaction Solutions, Corporations & Institutional Banking
National Australia Bank Limited
And do you understand that part of its task is to manage that relationship with Mineralogy?---Yes. That's correct.
And do you understand that part of its task is also to try and alter the existing contractual arrangements with Mineralogy?---Yes.
All right. And that's because CITIC - or Sino and Korean - consider that the present contractual arrangements they have don't suit them.
Objection was taken to the question, inter alia, upon the basis of legal professional privilege. After some arguments on each side, I did not uphold the objection (ts 321).
And the reason that Sino and Korean wanted the contractual arrangements changed with Mineralogy was because they did not consider that those contracts suited them?---I'm not sure that's entirely correct. I think there are - our client considers there were a number of problems with the documents and that's - - -
Sure. But they're not the difficulties you're talking about. The difficulties you're talking about is the commercial terms are ones that Sino and Korean consider are unsatisfactory. That's correct, isn't it?---Yes.
Legal Dispute Prevention Mechanism Risk
Civil or criminal suit to deal with the risk Business Partners Debt Transfer Risks (row 89)
Risks are currently being adequately managed. CPM has a dedicated Special Projects Team to manage the major litigations with Mineralogy.
In my view, it follows that the Administrative Fund contributions made to the bank account were not held on trust by Mineralogy, because the contractual obligations of Mineralogy did not extend to an obligation not to deposit into and thereby mix other moneys in the bank account.
Only if I find that the challenged payments were made from funds held on trust, the defendants made three other concessions ...
His Honour, of course, found that the funds were not held on trust.
In view of those findings, it is unnecessary for me to go further. It is not necessary to make a specific finding of dishonest or fraudulent design by Mineralogy, through the first defendant [ie, Mr Palmer], or of dishonest assistance with knowledge by the first defendant. There are reasons why, in my view, I should not do so. First, such findings could cause significant reputational damage to the first defendant, but they are not necessary in order to resolve the liability of the first or second defendants as a matter of fact and law. Second, the way in which this case has been conducted does admit of the possibility that the plaintiffs seek not only to obtain the relief claimed in the proceeding, but also to embarrass the first defendant at the same time.
Construction of Commercial Contracts - Principles
It is trite law that the primary duty of a court in construing a written contract is to endeavour to discover the intention of the parties from the words of the instrument in which the contract is embodied. Of course the whole of the instrument has to be considered, since the meaning of any one part of it may be revealed by other parts, and the words of every clause must if possible be construed so as to render them all harmonious one with another. If the words used are unambiguous the court must give effect to them, notwithstanding that the result may appear capricious or unreasonable, and notwithstanding that it may be guessed or suspected that the parties intended something different. The court has no power to remake or amend a contract for the purpose of avoiding a result which is considered to be inconvenient or unjust. On the other hand, if the language is open to two constructions, that will be preferred which will avoid consequence which appear to be capricious, unreasonable, inconvenient or unjust, 'even though the construction adopted is not the most obvious, or the most grammatically accurate', to use the words from an earlier authority cited in Locke v Dunlop (1888) 39 Ch 387, 393, which, although spoken in relation to a will, are applicable to the construction of written instruments generally; see also Bottomley's Case [1880] UKLawRpCh 258; (1880) 16 Ch D 681, 686. Further, it will be permissible to depart from the ordinary meaning of the words of one provision so far as is necessary to avoid an inconsistency between that provision and the rest of the instrument. Finally, the statement of Lord Wright in Hillas & Co Ltd v Arcos Ltd [1932] UKHL 2; (1932) 147 LT 503, 514, that the court should construe commercial contracts 'fairly and broadly, without being too astute or subtle in finding defects', should not, in my opinion, be understood as limited to documents drawn by businessmen for themselves and without legal assistance (cf Upper Hunger County District Council v Australian Chilling and Freezing Co Ltd [1968] HCA 8; (1968) 118 CLR 429, 327).
Early interpretive observations concerning the text of MRSLA cl 20.4, 20.5 and 20.6
[E]ach period of 12 months commencing 1 July. The first Operating Year will be the period commencing on the date of this Agreement [which was 21 March 2006] and ending on the next 30 June.
The parties' submissions on the construction of cl 20.6(e) The dispute
Valuations may involve making decisions where no fixed or readily available standard criteria exist. There may be several possible methods of assessing value, each giving widely different results, but each being reasonable. Many subsidiary factors relevant to the valuation may be uncertain, many contingencies may have to be taken into account, wide ranges of legitimate decisions may apply, and opinions may legitimately differ as to virtually all of the relevant issues.
(a) the different levels of remediation cost estimates as were received between 2016 - 2018 from various experts as to the disturbance levels - including AECOM's 2016 estimate,[70] Mr Slight's 2018 estimate,[71] AECOM's revised 2018 estimate (taking into account Liberty Industrial's estimate)[72] and then, Mr Cramer's estimate;
(b) the inability even for the rival experts at the trial to identify a common formula to be used; and
(c) the fact cl 20.6 does not fall for reference under the MRSLA provision for the resolution of disputes by an expert under MRSLA cl 33.
(a) the amount of time Mr Slight initially claimed he would need to produce the report (80 hours).[80] However, they suggest that the evidence shows that whilst preparing his report, Mr Slight was also engaged in other work concerning other projects or activities, such as driving across Australia. Further, they appear to suggest that Mr Slight was asked to sign off on a report in a quick manner, so as to satisfy Mineralogy and Mr Palmer's needs. Mr Slight had informed Mineralogy that he had spent 52 hours on the report;[81]
(b) the inclusion of the cost of removing the port and causeway by Mr Slight, after being requested to add that cost assessment by Mineralogy and Mr Palmer;[82]
(c) a failed non‑visit to site in March 2018. Although a visit had been requested to be arranged by Mineralogy, in order for Mr Slight to physically view the site, after those visit arrangements were made, Mineralogy representatives and Mr Slight had then failed to attend the site.[83] Mr Slight did later on attend the site in 2019. However, this meant he had not physically seen the site when he had earlier submitted his April 2018 report; and
(d) there being no meeting between CITIC representatives and Mr Slight. Whilst arrangements were attempted to be made, as things eventuated, Mr Slight did not meet with any CITIC representatives prior to his first report being submitted. The CITIC defendants identify this as important, as Mr Slight had himself later identified that there was a deficiency in the information he required to complete his report which he would have been able to obtain through a meeting with CITIC representatives.[84]
(a) area photos of the mine site showing the mine features and infrastructure;
(d) the Preliminary Decommissioning and Closure Plan; and
(e) a wealth of knowledge and experience from his previous estimates.
Clause 20.6(e) The reviewability of determination by Mineralogy
EXPERT CONCLAVE - CIV 2840 of 2018 | Mineralogy Pty Ltd v Sino Iron Pty Ltd & Ors
Joint Memorandum of Mr Slight and Mr Cramer
15 November 2020
This joint memorandum has been prepared by Mr Slight and Mr Cramer following an expert conclave held on 13 November 2020. The memorandum draws upon the information contained in the April 2018 Slight Report, the August 2020 Slight Report, the October 2020 Cramer Report and the October 2020 Slight Report (see Schedule 1). Our original instructions and qualifications are set out in those documents.
The memorandum has been prepared following the expert conclave to narrow the issues in respect of which we agree, partly agree or disagree.
2.1 Most applicable type of remediation cost estimate
Two key terms are used in this memorandum to describe different types of remediation (or closure) cost estimates. These terms are defined as follows based on International Council on Mining and Metals (ICMM) definitions:
A summary of these two types of closure cost estimates along with other common estimate types is provided in Schedule 2, taken from ICMM.
Mr Slight's view is that the remediation fund should ensure security and certainty to all parties and that sufficient funds will be available to meet the site remediation costs at all times and is best met by a financial assurance cost estimation method. This is because:
In Mr Cramer's opinion, the most appropriate basis for developing a 'best prevailing estimate' of remediation costs, as required under Clause 20 of the MRSLAs, is a financial liability closure cost estimate. This is because:
2.2 Whether contingency should be included
Mr Slight considers that the remediation estimate must include a contingency (as required for a financial assurance) to allow for those items not already accounted for in the estimate, such as those not known about when preparing the estimate (and therefore not included) and other cost impacts still to be determined and due to other unknown influencing facts (eg environmental, physical, chemical, regulatory etc). Mr Slight has suggested the following potential additional factors that will impact on the estimate and assumed to be allowed for in the contingency.
Mr Cramer considers that contingency should be excluded from the remediation estimate as:
2.3 Whether discounting should be included
Mr Slight's view is that the remediation estimate should not be discounted to a net present value due to the following:
Mr Cramer considers that discounting should be included in the remediation cost estimate as:
2.4 Whether marine and port facilities should be included
The following provides the reasons why Mr Slight has included the cost for remediation of the marine and port facilities:
The following provides the reasons why Mr Cramer has excluded the cost for remediation of the marine and port facilities:
2.5 Basis for post‑closure monitoring and maintenance costs
Mr Slight and Mr Cramer have used different approaches to estimate post‑closure monitoring and maintenance costs. However, as Mr Slight's most recent (October 2020) estimate of monitoring and maintenance costs ($12,185,968) and Mr Cramer's April 2018 and October 2018 estimates ($11,473,267 and $12,452,818, respectively) are broadly consistent, these differences in approach are not discussed further in this memorandum.
Mr Slight and Mr Cramer reached agreement through the process of reviewing each other's reports (and prior to the expert conclave) on the following aspects of the remediation costs which had been initially misaligned.
In addition, both parties have consistently agreed that salvage costs for ferrous and non ferrous materials (such as estimated by Liberty Industrial) should be excluded from the cost estimate.
A summary of the cost estimates by Mr Slight and Mr Cramer are presented in Table 1. The differences in the cost estimates are predominantly a result of the following factors:
2020 (2020 Slight Report, cost updated October 2020)
*Note that in his 2018 and 2019 estimates, Mr Slight included landform maintenance costs under the landform category.
The cost estimate totals in Table 1 do not include discounting. Mr Cramer has estimated that if NPV adjustments are applied to his April and October 2018 cost estimates based on the assumptions outline in the 2020 Cramer Report, then a reduction in the order of 20% would result. As discussed in Section 2.3, above, Mr Slight does not consider that discounting should be applied to the cost estimates.
Mineralogy's primary debt claim - 16 April 2018
CPM considers that Mineralogy's request for payment of AUD200 million in respect of the current Operating Year is clearly excessive and does not represent a fair estimate by Mineralogy of 'the amount of future Site Remediation Costs', nor the 'number of years remaining until Mine Closure'.
As you are aware, both Sino Iron Pty Ltd and Korean Steel Pty Ltd have not contributed to the [S]ite [R]emediation [F]und as required by cl 20.6 of the MRSLA in the amounts previously requested by Mineralogy as Trustee of the fund. They have an obligation to do so. Their obligation is not optional.
Mineralogy requires a contribution of $1,300,000,000 to be made within 14 days. ...
Mineralogy's receipt of Mr Slight's remediation estimate report of 16 April 2018
Mineralogy Pty Ltd has requested Mike Slight & Associates to undertake a remediation works cost estimate for Cape Preston Sino Steel Project as per their current agreement under Clauses 20.4, 20.5, and 20.6 with CITIC PACIFIC MINING PTY LTD (CPM). The review has been undertaken as a desktop 'Order of Magnitude' (OoM) costing exercise due to the inability to visit the site or source all relevant remediation plans and documents from CPM. The estimate has considered all likely remediation requirements (as per legal obligations and standards within WA) including remediation of all waste rock dumps (WRL) and tailings storage facility (TSF), removal of the port causeway, decommissioning and demolition of all industrial, processing and support infrastructure required to be removed from the various locations across the site, and all footprint remediation and revegetation ...
Unit costs and production schedules have been developed based on earthmoving 'bottom-up first' principles and have been calibrated against actual remediation and mining activities, to ensure currency and consistency with expected contractor rates for the type of closure activities likely to be undertaken in the estimates. All demolition cost estimates have been based on estimates undertaken for similar processing infrastructure and support facilities within WA[.]
Processing plant, port and causeway, stockyard, administration, camp
Management, supervision, FIFO and camp costs, and consulting services
Moreover, Sino Iron and Korean Steel are in breach of their obligations to make contributions to the Site Remediation Fund as required by clause 20.5 and 20.6 of the MRSLA. The account details have previously been provided to you. Mineralogy is trustee of the Site Remediation Fund which CITIC companies have refused to contribute to for over 5 years. The Site Remediation Fund was agreed at a time when the EPA did not impose bonds. The requirements of clause 20.5 and 20[.6] was to ensure inter alia the CITIC Parties did not leave Australia without attending to the environmental damage they have caused. Mineralogy currently assesses Sino and Korean's outstanding obligations to contribute to the Fund in respect of the current areas for the project is over $529,378,207. These contributions are for the security of the people of Western Australia. The requirements of clause 20.5 and 20.6 were submitted to the Western Australian Cabinet just before the State Agreement was signed, and as you are aware the MRSLA is listed on the schedule to the State Agreement ...
...
That is all the more reason why Mineralogy must require the payment into the Site Remediation Fund for good order and does not consent to any further submissions of proposals by your company under the [S]tate Agreement at this time.
Mineralogy has retained an expert and flown aerial photography to delineate precisely the requirements of Sino and Korean to contribute to the Site Remediation Fund.
If Sino and Korean are not honouring their environmental obligations in respect of the areas under their control there can be no justification for Mineralogy providing Sino and Korean with additional land to degrade.
...
Please find enclosed a [sic] independent report by M Slight in April 2018 confirming the amount required to meet Sino and Korean obligations to date. I note the good faith provisions of the MRSLA and trust this matter can be attended to without further conflict. Mineralogy will then be in a position to consider your company's request.
As set out in our previous correspondence (including most recently Allens' letter of 10 January 2018), we consider that Mineralogy's purported determination under clause 20.6(e) of the MRSLAs is invalid and of no effect. Accordingly, CITIC will not be making a payment in response to the demand made on 29 January 2018 or the implied demand in your letter of 16 April 2018 ...
For the avoidance of doubt, we reject your assertion that CITIC has determined to abandon the Project. Our contribution to the Site Remediation Fund should be determined based on the current estimated duration until Mine Closure.
Before any amount is deposited into the Site Remediation Fund, a properly constituted trust account must be established in conformity with clause 20.6. This will require an agreement to govern how the fund is to be administered. Our lawyers are ready to commence work with your lawyers to achieve that.
Mineralogy has not yet determined, as it is required to do, the 'annual charges' that Sino Iron and Korean Steel are reasonably required to deposit into the fund on account of future site remediation costs: see clause 20.6(e) of each MRSLA. The references to remarks by CITIC that it may be forced to temporarily suspend the operations under force majeure provisions do not affect an assessment of what is a reasonable annual contribution now.
Accordingly, Sino Iron and Korean Steel do not have any outstanding obligation to contribute to the fund.
Nevertheless, by way of good faith indication only, our view is that a reasonable annual charge should be calculated by dividing the total estimated cost of meeting rehabilitation Legal Requirements (as defined in the MRSLAs) by the number of years remaining in the estimated life of the Project (taking into account CITIC's exercise of the First Option). As I foreshadowed in my previous letter, I would welcome the opportunity to discuss with you or your representatives the assessment of our contribution once Mr Slight has updated his report ...
Mineralogy's alternate debt claim - 21 May 2018
21 May 2018
NOTICE
To:
Sino Iron Pty Ltd
Level 7, 45 St Georges Terrace
Perth WA 6000
Attention: Chen Zeng - Director & Fei Xu, CITIC Pacific Mining Management Pty Ltd
Timothy Knowles - Company Secretary, Sino Iron Pty Ltd
Copy:
Korean Steel Pty Ltd
Level 7, 45 St Georges Terrace
Perth WA 6000
Attention: Chen Zeng - Director & Fei Xu, CITIC Pacific Mining Management Pty Ltd
Timothy Knowles - Company Secretary, Sino Iron Pty Ltd
Copy:
CITIC Limited
32nd Floor, CITIC Tower
1 Tim Mei Avenue
Central, Hong Kong
Attention: Ricky Choy - Company Secretary, CITIC Limited
Dear Sirs
RE: Notice of Demand under Mining Right Site Lease Agreement__
(a) the Mining Right and Site Lease Agreement between Mineralogy Pty Ltd (Mineralogy) and Sino Iron Pty Ltd (Sino Iron) dated 21 March 2006, as amended by the Deed of Variation dated 31 March 2006 and the Deed of Amendment dated 8 January 2008 (MRSLA); and
(b) the Mining Right and Site Lease Agreement between Mineralogy and Korean Steel Pty Ltd (Korean Steel) dated 21 March 2006, as amended by the Deed of Amendment dated 22 October 2008 (Korean MRSLA).
(a) as and when required by Legal Requirements, Sino Iron is to carry out all Site Remediation Works that may be required as a result of Sino's Activities, as defined; and
(b) following Mine Closure, Sino Iron is to carry out all necessary Site Remediation Work, including complying with any ongoing Legal Requirements relating to Site Remediation Work on areas affected by Sino's Activities.
(a) Mineralogy is to establish a Site Remediation Fund as defined.
(b) The Site Remediation Fund is to provide security and certainty, for the benefit of Sino Iron and Mineralogy, that sufficient funds will be available at Mine Closure to meet Site Remediation Costs.
(c) The Site Remediation Fund is an interest-bearing trust account controlled by Mineralogy as trustee, with interest earned on funds to be retained in the Fund.
(d) For each Operating Year, Mineralogy may determine an annual charge to be paid into the Site Remediation Fund by Sino Iron.
Failure to Comply with the Site Remediation Obligations
(a) determined an annual charge of $200 million to be paid by Korean Steel and Sino Iron into the Site Remediation Fund for the Operating Year commencing 1 July 2011; and
(b) by way of a letter to the Executive Chairman of CITIC Pacific Mining Management Pty Ltd (CPM), required payment of that amount by Korean Steel and Sino Iron into the Site Remediation Fund by 8 October 2010 (2011 Fund Payment).
(a) determined an annual charge of $1.3 billion to be paid by Korean Steel and is into the Site Remediation Fund for the Operating Year commencing 1 July 2018; and
(b) by way of letter to Mr Zeng of CPM, required payment of that amount by Korean Steel and Sino Iron into the Site Remediation Fund by 10 January 2018.
(a) revised its determination of an annual charge to $529,738,207 to be paid by Korean Steel and Sino Iron into the Site Remediation Fund for the Operating Year commencing 1 July 2018; and
(b) by way of letter to Mr Zeng of CPM, with an attached report of Mr Slight providing part of the basis for the determination, required payment of that amount by Korean Steel and Sino Iron into the Site Remediation Fund (2018 Fund Payment).
(a) Sino Iron has not paid any amounts into the Site Remediation Fund for any Operating Years; and
(b) on 18 April 2018, by way of a letter from Mr Zeng of CPM to Mr Palmer of Mineralogy, Mr Zeng confirmed that payment would not be made into the Site Remediation Fund.
(a) gives further notice that it has determined for the Operating Year commencing 1 July 2018 an annual charge of $529,738,207 to be paid by Korean Steel and Sino Iron into the Site Remediation Fund; and
(b) demands that Sino Iron, pursuant to clauses 20.5 and 20.6 of the MRSLA, pay $264,869,103.50 into the Site Remediation Fund, being its share of the annual charge so determined (but without prejudice to any of Mineralogy's rights under the MRSLA and FC Deed, including clause 25 of the FC Deed), and with the payment details for the Site Remediation Fund being as follows:
Bank: National Australia Bank
Name: Mineralogy Pty Ltd Remediation Fund
BSB: [REDACTED]
Account: [REDACTED]-6708
(c) demands that the payments referred to in this paragraph 21 be made within 14 days of the date of this notice.
Yours sincerely,
[Signed]
Sarah Mole | Executive Assistant to the Chairman
Mineralogy Pty Ltd
(a) gives further notice that it has determined for the Operating Year commencing 1 July 2018 an annual charge of $529,738,207 to be paid by Korean Steel and Sino Iron into the Site Remediation Fund; and
(b) demands that Sino Iron, pursuant to clauses 20.5 and 20.6 of the MRSLA, pay $264,869,103.50 into the Site Remediation Fund, being its share of the annual charge so determined (but without prejudice to any of Mineralogy's rights under the MRSLA and FC Deed, including clause 25 of the FC Deed), and with payment details for the Site Remediation Fund being as follows:
Bank: National Australia Bank
Name: Mineralogy Pty Ltd Remediation Account
BSB: [REDACTED]
Account: [REDACTED]-6708
(c) demands that the payments referred to in this paragraph 21 be made within 14 days of the date of this notice.
Set out below are textual extracts from the Sino Iron MRSLA. Exactly the same provisions are found in the Korean Steel MRSLA.
Included below are a number of the key MRSLA definitions for many words and phrases commonly used in the two agreements.
Also set out in full, taken from each MRSLA is all of the pivotal cl 20, so that the key subclauses therein, namely subcl 20.4 ‑ 20.6 and which address the subject of a Site Remediation Fund, can be seen and assessed in proper surrounding MRSLA cl 20 context.
1.1 Definitions
In this Agreement, unless the context otherwise requires:
Access Area means an area made available by Mineralogy to Sino in accordance with Clause 12.
Claim means any legal proceedings, claims, actions, fines, penalties, judgments, liabilities or demands arising under any statute or in equity or at common law.
Environmental Approval means any Government Approval obtained under the EP Act [Environmental Protection Act 1986 (WA)] or otherwise relating to environmental obligations.
Facilities Deed means the agreement between the parties hereto and listed in a schedule by that name in the State Agreement, as amended or replaced from time to time.
Government Approvals means all approvals, permits, licences and authorisations required from Government Authorities in respect of Sino's Activities.
Government Authority means any local, State or Federal Governmental agency, body or authority, including the responsible Minister under the State Agreement.
Legal Requirements means present or future obligations arising under:
(a) legislation regulations by-laws;
(b) the orders and requirements of any Government Authority, including notices requiring the carrying out of any repair[s], alterations or works;
(c) the terms and conditions of the proposals, as submitted to and approved by the Minister under the State Agreement, in respect of Sino's Project; and
(d) the terms and conditions of the Mining Leases, and of all Government Approvals relating to Sino's Project, Sino's Project Facilities, and Sino's Activities.
Magnetite Ore means ore mined from the Mine Area and containing a magnetite content of at least 17% magnetite Fe. Magnetite Ore also includes any Low-Grade Material used by Sino to produce Iron Ore Concentrates.
Mine means the open-cut mine to be developed within the Mine Area by Sino and/or other Mine Participants for the Mining and extraction of Magnetite Ore.
Mine Area means the area, within the Mining Leases, within which Mining Operations are to be conducted, as described in Clause 3.1, and as may be amended from time to time under this Agreement.
Mine Closure means the permanent cessation of operation at the Mine.
Mine Facilities means facilities established within the Mine Area for the purpose of Sino exploiting its Mining Right in accordance with this Agreement.
Mining Act means the Mining Act 1978 of Western Australia as amended from time to time and includes the Regulations for the time being in force thereunder.
Mining Leases means Mining Leases 08/123 to 08/125 inclusive granted under the Mining Act and any renewals, modifications, variations and substitutions thereof held by Mineralogy as at the date of this Agreement which contains the Mine Area.
Mining Operations means all activities in connection with:
(a) development of one or more Mines within the Mine Area in accordance with the Mine Plan;
(b) mining of Magnetite Ore from the Mine and delivery of the Magnetite Ore to the Processing Facilities;
(c) establishment and operation of Mine Facilities as necessary to support Mining Operations;
(d) creation and operation of all necessary stockpiles and waste dumps;
(e) applying for and obtaining necessary Government Approvals associated with Mining Operations;
(f) acquiring power, water and other services and utilities as required for Mining Operations; and
(g) all activities incidental to the foregoing.
Operating Year means each period of 12 months commencing 1 July. The first Operating Year will be the period commencing on the date of this Agreement and ending on the next 30 June.
Processing Facilities means the processing facilities required by Sino for the processing of Magnetite Ore into products.
Products means up to a combined aggregate total of 12,000,000 (twelve million) tonnes per year of a combination of Iron Ore Concentrate, and/or Pellets and/or HBI for sale or export in such ratio as Sino may decide from time to time and no more.
Project Area means, at the time of this Agreement, the Mining Leases together with the Site Lease Area, Mining Leases 08/264 to 08/266 inclusive, Miscellaneous Licence 08/20 and General Purpose Leases 08/52 to 08/54 inclusive, and as amended from time to time in accordance with this Agreement, the Facilities Deed and the State Agreement.
Sino's Activities means all activities and operations undertaken by Sino pursuant to this Agreement, including without limitation:
(a) all activities and operations within the Site Lease Area; and
(b) all activities and operations associated with Sino's use of Access Areas.
Sino's Project means Sino's Project described in the Schedule, which is to be implemented by Sino under this Agreement.
Sino's Project Facilities means the Mine Facilities constructed or installed within the Mine Area, the Processing Facilities constructed or installed within the Site Lease Area, and any other plant, facilities or infrastructure constructed or installed by Sino pursuant to its rights under this Agreement within the Mine Area, Site Lease Area or under the Facilities Deed in the Access Areas or elsewhere within the Project Area.
Site Lease Area means the area, within the Tenements, described in Clause 4.1, or otherwise agreed in writing between Mineralogy and Sino.
Site Remediation Costs means costs and liabilities incurred in respect of Site Remediation Work.
Site Remediation Fund is defined in Clause 20.6.
Site Remediation Work means all work required in connection with the decommissioning of the Mine, shut-down and cessation of Mining Operations, and rehabilitation or remediation of areas affected by Mining Operations as necessary to meet Legal Requirements and good industry practices. Without limitation, Site Remediation Work may include as appropriate severing and removing structures and facilities, making good damage to the land, re contouring the land, spreading top-soil, re‑establishing vegetation and removing contaminated soil.
State Agreement means the Iron Ore Processing (Mineralogy Pty Ltd) Agreement dated 5 December 2001 between the Honourable Geoffrey Ian Gallop, the Premier of Western Australia, acting for and on behalf of the State of Western Australia and its instrumentalities from time to time, Mineralogy, International Minerals Pty Ltd ABN 86 058341 638, Austeel Pty Ltd ABN 38 058 430 032, Balmoral Iron Pty Ltd ABN 83 058 429 931, Sino (then named Bellswater Pty Ltd), Brunei Steel Pty Ltd ABN 79 058 429 977 and Korean Steel Pty Ltd ABN 20 058 429 600, ratified by the State Agreement Act and as amended from time to time[.]
Tenements means Mining Leases 08[/]123 to 08/125 inclusive any other title held by Mineralogy over these areas.
20. ENVIRONMENTAL OBLIGATIONS
20.1 Environmental Approvals
(a) Unless otherwise determined by Mineralogy, Sino is responsible for obtaining all necessary Environmental Approvals in relation to Sino's Project and Sino's Activities.
(b) Mineralogy may elect to obtain (or may have obtained) Environmental Approvals in respect of Sino's Project as a proponent. In that event, and if Mineralogy wishes to transfer a part of the whole of any Environmental Approval to Sino:
(i) Sino must sign any document or instrument, pay any bond, security or other financial provision and otherwise do anything reasonably necessary to effect the transfer.
(ii) Sino will indemnify Mineralogy for any costs and expenses, including any fines or penalties that Mineralogy incurs or has incurred by virtue of Mineralogy having been the proponent and/or continuing to be a co-proponent for Sino's Project and its associated activities.
20.2 Legal Requirements
(a) In relation to the Site Lease Area and otherwise in relation to all of Sino's Activities, Sino will comply strictly with all Legal Requirements relating to protection of the environment and Site Remediation Work.
(b) Sino acknowledges that Legal Requirements will include:
(i) the conditions of all present or future Environmental Approvals in relation to Sino's Project;
(ii) the undertakings made by Sino or by Mineralogy in relation to Sino's Project as part of Sino's Project Proposals made under the State Agreement in relation to Sino's Project[.]
20.3 Bonds
As between Mineralogy and Sino, Sino will be solely responsible for the provision of all bonds required by Government Authorities in respect of Sino's Activities.
20.4 Site Remediation Work
(a) As and when required by Legal Requirements, Sino will carry out all Site Remediation Work that may be required as a result of Sino's Activities. All Site Remediation Work must meet Legal Requirements.
(b) Following Mine Closure, Sino will remove and dispose of all Sino's Project Facilities in accordance with Legal Requirements, and will carry out all necessary Site Remediation Work. Sino will comply, and will continue to comply, with any ongoing Legal Requirements relating to Site Remediation Work on areas affected by Sino's Activities.
20.5 Mineralogy may require security
Mineralogy may from time to time require Sino to provide reasonable security for the performance of its obligations under this Clause 20. Such security will be provided in the form of a Site Remediation Fund.
20.6 Site Remediation Fund
(a) In order to make provision and to provide security for payment of future Site Remediation Costs as they become payable, Mineralogy will establish a Site Remediation Fund, and Sino will make payments into the Site Remediation Fund in the manner set out in this clause.
(b) The Site Remediation Fund is intended to provide security and certainty for the benefit of Sino, and for Mineralogy as the holder of the Mining Lease, that sufficient funds will be available at Mine Closure to meet Site Remediation Costs.
(c) The Site Remediation Fund will be maintained in a separate interest bearing trust account controlled by Mineralogy as trustee, and which will be designated as a trust account. The interest earned on funds in the Site Remediation Fund will be retained in the Site Remediation Fund.
(d) The Site Remediation Fund may be used solely for the purpose of paying Site Remediation Costs as they become payable. The Site Remediation Fund may not be used or accessed for any other purpose.
(e) For each Operating Year, Mineralogy will determine an annual charge on account of future Site Remediation Costs to be made by Sino in that Operating Year. The amount of the annual charge is to be determined by Mineralogy, having regard to:
(i) Mineralogy's best prevailing estimate of the amount of future Site Remediation Costs, and the amount (if any) already contributed by Sino Iron into the Site Remediation Fund; and
(ii) the number of years remaining until Mine Closure.
(f) At least 30 days prior to the commencement of each Operating Year, Mineralogy will notify Sino of its annual charge in respect of the forthcoming Operating Year.
20.7 Environmental Management Plan
(a) As a condition to Mineralogy's approval of Sino's Development Plan, Sino will prepare for the approval of Mineralogy an environmental management plan setting out the obligations of Sino with regard to environmental management. Sino may from time to time submit changes to the environmental management plan.
(b) The environmental management plan must at a minimum:
(i) be sufficient to ensure compliance by Sino with its obligations under all applicable Legal Requirements, and to meet the requirements of all relevant Government Authorities;
(ii) comply with good and accepted environmental management practices adopted by the mining industry in Australia;
(iii) set out the strategies and management processes that will achieve compliance with those requirements;
(iv) set out the obligations of Sino with regard to, among other things, the reporting of environmental incidents; and
(v) set out the obligations of Sino with regard to periodic review of its environmental management performance.
(c) The environmental management plan submitted by Sino shall be subject to the approval of Mineralogy, approval not to be unreasonably withheld.
(d) Mineralogy may from time to time require Sino to modify or add to the environmental management plan if Mineralogy can demonstrate that the amendment is necessary to meet the standards required under paragraph (b).
(e) Sino will at all times comply with the approved environmental management plan and will ensure that Sino's employees and contractors comply with the approved environmental management plan.
(f) Sino will on an annual basis following commencement of the development review its environmental management performance against the environmental management plan and will provide a report to Mineralogy on the effectiveness of the plan in achieving compliance, the reasons for non-compliance and the changes required to the plan to achieve compliance.
(g) If Mineralogy has approved an environmental management plan under a Project Agreement which contains the same content as the environment management plan to be approved by Mineralogy under this Agreement, Mineralogy will be deemed to have approved the environmental management plan.
(h) If Mineralogy approves the environmental management plan and Mineralogy's approval is also required under a Project Agreement for an environmental management plan which contains the same content as the environmental management plan, Mineralogy will be deemed to have approved that environmental management plan. Sino and Mineralogy hereby agree to vary the terms of such Project Agreement to the extent required to give effect to this paragraph (h).
20.8 Claims in respect of Environmental incidents
Sino will indemnify Mineralogy against all Claims in respect of:
(a) any Site Remediation Work required as a result of Sino's Activities;
(b) any contamination of land resulting from Sino's Activities;
(c) pollution (which includes all discharges and emissions in excess of or in contravention of relevant Legal Requirements) resulting from Sino's Activities;
(d) dangerous, hazardous or toxic substances brought onto the Mining Lease by Sino.
SCHEDULE B Chronology of mostly agreed facts found at the trial (see [73])
Mining Leases 08/123, 08/124 and 08/125 granted to Mineralogy.
Mining Leases 08/264, 08/265 and 08/266 granted to Mineralogy.
Various parties enter into the Iron Ore Processing (Mineralogy Pty Ltd) Agreement Act 2002 (State Agreement), including Mineralogy, Korean Steel and Balmoral Iron Pty Ltd.
The Minister for the Environment issues Ministerial Statement No 635.
General Purpose Leases 08/52, 08/53 and 08/54 granted to Mineralogy.
Mineralogy and Sino Iron and Mineralogy and Korean Steel respectively enter into Mining Right and Site Lease Agreements (MRSLAs)
[NOTE: The Sino Iron MRSLA was amended and varied on 31 March 2006 and later again, on 8 January 2008. The Korean Steel MRSLA was amended and varied on 22 October 2008.]
Mineralogy submits the Preliminary Decommissioning and Closure Plan for the Sino Iron Project.
Mineralogy, Sino Iron, Korean Steel and CITIC Pacific Ltd enter into the Fortescue Coordination Deed.
Mineralogy relinquishes certain land ('Area D') to the State and the State Agreement is varied accordingly
Mineralogy sends a letter to CPM regarding the Site Remediation Fund (SRF). Amongst other things, the letter states that 'there is currently no Site Remediation Fund ... established for CPM's Project ...' Mineralogy requests information from CPM relating to the SRF.
Mineralogy letter to CPM requiring CPM to deposit $200 million into a 'separate interest bearing trust account controlled by Mineralogy Pty Ltd as trustee' within '30 days from the date of this letter'.
CPM letter to Mineralogy requesting that it 'withdraw its notification dated 8 September and re‑submit notification of the annual charge to be made to the Site Remediation Fund in accordance with the terms of the [MRSLAs]'.
Mineralogy requests further information for the purposes of calculating the Site Remediation Costs and the parties exchange correspondence regarding the information requests.
CITIC and Mineralogy hold various meetings and exchanges correspondence regarding (amongst other things) the SRF.
Sino Iron and Korean Steel transfer ownership of Camp 123 back to Mineralogy and vacate the accommodation facilities at Camp 123.
Mineralogy opens a bank account with the National Australia Bank styled 'Mineralogy Pty Ltd Remediation Account' with account number [REDACTED]‑6708 (NAB account)
Mineralogy emails CITIC (Allens) providing details of the NAB account.
Mineralogy emails National Australia Bank attaching a completed NAB Connect Additions/Amendments Request Form.
CITIC submits Mine Continuation Proposals to the State, which attach a copy of CITIC's Conceptual Closure Plan dated January 2017 (January 2017 Conceptual Closure Plan).
CITIC submits its Annual Environmental Report for the 2017/18 financial year to the Department of Jobs, Tourism, Science and Innovation, and provides a copy to Mineralogy.
The Minister for the Environment issues Ministerial Statement No 1066.
CITIC provides Mineralogy with a copy of the January 2017 Conceptual Closure Plan as part of the Mine Continuation Proposals.
Mineralogy sends a letter to CPM requiring that CITIC deposit $1.3 billion into the NAB account within 14 days. See full terms of letter.
Mineralogy and CITIC (Allens) exchange correspondence regarding the 27 December 2017 notification.
Mineralogy engages remediation expert Mr Mike Slight to assess the cost of Site Remediation Works.
Mineralogy notifies CITIC that it has engaged Mr Slight.
Mineralogy requests a site visit for Mineralogy and for Mr Slight on 26 to 28 March 2018 and then Mineralogy and CITIC exchange correspondence about arrangements for the site visit which is scheduled.
Scheduled site visit does not proceed by Mineralogy and Mr Slight.
CITIC and Mineralogy exchange correspondence to schedule a meeting between Mr Slight and CITIC personnel to occur on 16 May 2018 in Perth.
Mr Slight assess the cost of Site Remediation Works to be $529,378,207.
Mineralogy sends a letter to CPM requesting that $529,378,207 be deposited into the NAB account, attaching a copy of Mr Slight's assessment.
CPM responds to the 16 April 2018 communication. Amongst other things, CPM states 'Mineralogy's purported determination ... is invalid and of no effect. Accordingly, CITIC will not be making a payment in response to the demand ...'.
Mineralogy issues written notices of demand to each of Sino Iron and Korean Steel, demanding payment of $264,869,103.50 by each of Sino Iron and Korean Steel into the NAB account (ie $529,378,207 in total).
Meeting at CPM's office in Perth, Western Australia attended by Mr Slight, Mr Chris Spielvogel (Mineralogy) with Mr Horton, Mr Watson and Mr Northey of CPM.
Mineralogy and CITIC exchange correspondence to schedule a site visit for Mr Slight on 6 June 2018.
Mineralogy issues notices of default to CITIC, Sino Iron and Korean Steel, demanding payment of $529,378,207 into the NAB account.
Allens, on behalf of CITIC, sends a letter to Mineralogy responding to the April 2018 Determination and the notice dated 20 August 2018.
Allens, on behalf of CITIC, puts an open offer to contribute $6 million to the SRF as the annual charge for the Operating Year commencing 1 July 2018, by reference to an estimate prepared by AECOM and Liberty Industrial in September 2018, then estimating future site remediation costs at approximately $180 million.
Mineralogy rejects CITIC's open offer of 5 September 2018.
Mineralogy demands CITIC 'immediately cause Korean Steel and Sino Iron to perform their obligations under clauses 20.5 and 20.6 of the MRSLAs, by paying $529,378,207 in total' into the NAB account.
Mineralogy demands CITIC pay $529,378,207 in total into the NAB account.
CITIC submits a Ramp-up Phase Closure Plan 2018 ‑ 2021 of 4 October 2018 to the State.
CITIC makes a further open offer to contribute $8 million to the SRF as the annual charge for each Operating Year from 2016 to 2021.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] CPM.587.007.0391, exhibit 1.0404 (Sino Iron MRSLA) and MPL.001.002.0180, exhibit 1.0027 (Korean Steel MRSLA). It is not in dispute that the Sino Iron MRSLA and Korean Steel MRSLA are in identical terms, save for a reference to 'Sino' in the former will be a reference to 'Korean' in the latter.
[3] CPM.634.001.4208, exhibit 1.0651 (April 2018 Notice or April 2018 Determination).
[5] MPL.001.001.3222, exhibit 1.0711 (Sino Iron notice); MPL.001.001.3224, exhibit 1.0710 (Korean Steel notice) (May 2018 Notice or May 2018 Determination).
[6] MPL.001.001.3342, exhibit 1.0759. Mineralogy's rejection is at CPM.634.001.5129, exhibit 1.0760.
[8] However, the facts sought to be identified under par 25 of an earlier chronology lodged on behalf of the CITIC defendants (folio document 112) in relation to facts around the CITIC defendants' counterclaim against Mineralogy in relation to an ASIC media release are not received, given an earlier interlocutory ruling of mine concerning the inadmissibility of such matters.
[47] Exhibit 5B, par 7 - CPM.629.018.0032, exhibit 1.0959.
[48] Exhibit 5B, par 8 - CPM.629.019.0054, exhibit 1.0967.
[49] Exhibit 5B, par 9 - CPM.629.019.0056, Confidential exhibit 1.0968.
[51] Exhibit 8, par 4 - CPM.629.014.0060, exhibit 1.0926.
[52] CPM.629.019.0337, exhibit 1.0715. See ts 319 and following.
[55] Mineralogy's opening written submissions dated 2 November 2020 (Mineralogy's opening), par 33.
[56] Mineralogy's closing written submissions dated 23 November 2020 (Mineralogy's closing), par 55.
[58] See the CITIC defendants' closing written submissions dated 23 November 2020 (CITIC defendants' closing), pars 11 - 12.
[59] CITIC defendants' closing, par 23.
[60] CITIC defendants' closing, par 24.
[61] CITIC defendants' closing, par 18.
[64] CITIC defendants' opening submissions (CITIC defendants' opening), par 45.
[65] CITIC defendants' opening, par 47.
[66] CITIC defendants' opening, par 48.
[67] CITIC defendants' opening, par 49.
[68] CITIC defendants' closing, par 54. See also par 38.
[74] See, for example, MPL.001.001.1528, exhibit 1.0538 and CPM.634.001.4040, exhibit 1.0616.
[77] CITIC defendants' opening par 89, referring to Mineralogy's opening par 38.
[78] MPL.001.001.1611, exhibit 1.0492, at page 13 of the document.
[79] Exhibit 10, Cramer Expert Report, pages 63, 65, 78 - 79, 163 - 167.
[84] MPL.001.001.2235, exhibit 1.0617, ts 405, ts 410.
[85] CITIC defendants' opening, pars 94 - 112.
[86] CITIC defendants' opening, pars 95 - 99.
[87] CPM.631.014.2808, exhibit 1.0466, at .2918, .2965, .2911.
[88] CITIC defendants' opening, par 105 and closing, par 144.
[89] See CITIC defendants' closing, par 149.
[90] Exhibit 10, page 41, table 3.4, Cramer Expert Report.
[94] Exhibit 10, Cramer Expert Report; exhibit 9A, August Slight Report, at par 124; Exhibit 9B, October Slight Report, at pars 28 - 33.
[95] CPM.629.026.0118, exhibit 1.1068 at par 0571.
[97] MPL.001.003.0133, exhibit 1.0037, pages 4 and 14 - 15.
[98] CPM.560.002.2778, exhibit 1.0223, page 34.
[99] CPM.639.255.4060, exhibit 1.0773, pages 144 and 156 - 157.
[101] (Footnote from report) 'Termed an "IFRS closure cost" estimate in Cramer 2020. IFRS is an acronym for International Financial Reporting Standards'.
[102] MPL.001.001.0379, exhibit 1.0146.
[103] MPL.001.001.0145, exhibit 1.0150.
[104] MPL.001.001.3464, exhibit 1.0216.
[105] MPL.001.001.1517, exhibit 1.0526.
[106] Exhibit 1.0651 at CPM.634.001.4212.
[107] MPL.001.001.0932, exhibit 1.0662.
[110] MPL.001.001.1976, exhibit 1.0685.
[111] CPM.634.001.4257, exhibit 1.0687.
[112] CPM.629.003.2339, exhibit 1.0708.
[114] MPL.001.001.3982, Confidential exhibit 1.0346.
[115] A reference to the 'CITIC defendants' in this counterclaim context is, of course, exclusively a reference to Sino Iron and Korean Steel.
[116] CITIC defendants' opening, par 133.
[117] CITIC defendants' opening, par 133(iii).
[118] CITIC defendants' closing, pars 157 - 160; and ts 362 - 363.
[119] CITIC defendants' closing, par 172.
[120] SUB.001.001.0277, exhibit 1.1051.
(2015) 256 CLR 104
(2015) 329 ALR 1
(1975) 132 CLR 373
(2007) 230 CLR 89
(1963) 109 CLR 9
(1965) 113 CLR 385
(1973) 129 CLR 99
(2015) 2 Qd R 574
(1968) 118 CLR 429
(1978) 141 CLR 335
(1977) 180 CLR 266
(1990) 20 WAR 489
(2013) 41 VR 636
(1998) 19 WAR 495
(1993) 29 NSWLR 641