44.2 Default by the Contractor
If the Contractor commits a substantial breach of contract the Principal may give the Contractor a written notice to show cause.
Substantial breaches include but are not limited to-
(a) suspension of work, in breach of Clause 33.1;
(b) failing to proceed with due expedition and without delay, in breach of Clause 33.1;
(c) failing to lodge security in breach of Clause 5;
(d) failing to use the standard of materials or provide the standards of workmanship required by the Contract, in breach of Clause 30.1;
(e) failing to comply with a direction of the Superintendent under Clause 30.3, in breach of Clause 23;
(f) failing to provide evidence of insurance, in breach of Clause 21.1; and/or
(g) in respect of Clause 43, knowingly providing a statutory declaration or documentary evidence which contains a statement that is untrue.
44.3 Requirements of a Notice by the Principal to Show Cause
A notice under Clause 44.2 shall-
(a) state that it is a notice under Clause 44 of the General Conditions of Contract;
(b) specify the alleged substantial breach;
(c) require the Contractor to show cause in writing why the Principal should not exercise a right referred to in Clause 44.4;
(d) specify the time and date by which the Contractor must show cause (which time shall not be less than 7 clear days after the notice is given to the Contractor); and
(e) specify the place at which cause must be shown.
44.4 Rights of the Principal
If by the time specified in a notice under Clause 44.2 the Contractor fails to show reasonable cause why the Principal should not exercise a right referred to in Clause 44.4, the Principal may by notice in writing to the Contractor-
(a) take out of the hands of the Contractor the whole or part of the work remaining to be completed; or
(b) terminate the Contract.
Upon giving a notice under Clause 44.2, the Principal may suspend payments to the Contractor until the earlier of-
(i) the date upon which the Contractor shows reasonable cause;
(ii) the date upon which the Principal takes action under Clause 44.4(a) or (b); or
(iii) the date which is 7 days after the last day for showing cause in the notice under Clause 44.2.
If the Principal exercises the right under Clause 44.4(a), the Contractor shall not be entitled to any further payment in respect of the work taken out of the hands of the Contractor unless a payment becomes due to the Contractor under Clause 44.6.
44.5 Procedure when the Principal Takes Over Work
If the Principal takes work out of the hands of the Contractor under Clause 44.4(a) the Principal shall complete that work and the Principal may without payment of compensation take possession of such of the Constructional Plant and other things on or in the vicinity of the Site as are owned by the Contractor and are reasonably required by the Principal to facilitate completion of the work.
The Contractor must, if required by the Principal, assign to the Principal, without payment, the benefit of any agreement for the manufacture or supply or goods and equipment for the performance of any work for the purposes of the Contract. For the purposes of effecting such assignment, the Contractor irrevocably appoints the Principal to be the true and lawful attorney of the Contractor with full power and authority to execute such assignment on behalf of Contractor and to bind the Contractor accordingly. The assignment will be on terms under which the relevant manufacturer, supplier or subcontractor will be entitled to make any reasonable objection to any further assignment by the Principal.
The Principal may pay any manufacturer, supplier or subcontractor for any goods and equipment delivered or work performed (including design work) for the purposes of the Contract (whether before or after the date the Principal takes over the work) if the price has not already been paid by the Contractor. Payments made under this Clause 44.5 may be deducted from any sum due or to become due to the Contractor. The Principal's rights under this Clause 44.5 are in addition to its rights to pay suppliers, manufacturers or sub-contractors as provide elsewhere in the Contract.
The Contractor will, when required in writing by the Superintendent (and not before), remove from the Site any Constructional Plant, Temporary Works and goods. If, within a reasonable time after receipt of such request, the Contractor does not comply, then the Principal may remove or sell any such property of the Contractor.
The Contractor will execute all documents required by the Principal to enable the Principal to obtain the benefit of any approval, consent or permit issued by any relevant authority. For the purposes of obtaining such benefit, the Contractor irrevocably appoints the Principal to be the true and lawful attorney of the Contractor with full power and authority to execute such documents on behalf of the Contractor and to bind the Contractor accordingly.
If the Principal takes possession of Constructional Plant or other things, the Principal shall maintain the Constructional Plant and, subject to Clause 44.6, on completion of the work the Principal shall return to the Contractor the Constructional Plant and any things taken under this Clause which are surplus.
44.6 Adjustment on Completion of the Work Taken Out of Hands of Contractor
When work taken out of the hands of the Contractor under Clause 44.4(a) is completed the Superintendent shall ascertain the cost incurred by the Principal in completing the work and shall issue a certificate to the Principal and the Contractor certifying:
(a) the amount of that cost and setting out the calculations employed to arrive at that cost;
(b) the amount which would otherwise have been paid to the Contractor if the work had been completed by the Contractor;
(c) the difference between (a) and (b).
If the cost incurred by the Principal is greater than the amount which would have been paid to the Contractor if the work had been completed by the Contractor, the difference shall be a debt due from the Contractor to the Principal. If the cost incurred by the Principal is less than the amount that would have been paid to the Contractor if the work had been completed by the Contractor, the difference shall be a debt due to the Contractor from the Principal.
If the Contractor is indebted to the Principal, the Principal may retain Constructional Plant or other things taken under Clause 44.5 until the debt is satisfied. If after reasonable notice, the Contractor fails to pay the debt, the Principal may sell the Constructional Plant or other things and apply the proceeds to the satisfaction of the debt and the costs of sale. Any excess shall be paid to the Contractor.