2.3 Background and relevant chronology
82 This section of my reasons sets out, in chronological sequence, the key events relevant to this litigation. Later in these reasons, I make reference to some of these events and the evidence concerning them in more detail. This section merely establishes the background and sequence of the most significant events.
83 On 12 December 1990, Exploration Licences 08/117 and 08/118 were transferred to Mineralogy. These exploration licences are within a location described as Bilanoo. They can be seen in Annexure 1 to these reasons.
84 On 28 September 1992, Mining Leases 08/118 to 08/128 were issued to Mineralogy. Their commencement date was 23 June 1993. These mining leases can be seen in Annexures 1 and 2 to these reasons. They are described as the "Balmoral tenements".
85 The Balmoral tenements run in a corridor which is approximately 5km wide and 30km long in a northerly direction. As can be seen in Annexure 1 to these reasons, the Balmoral tenements are divided into Balmoral North, Balmoral Central (including the George Palmer Deposit), and Balmoral South.
86 The Sino Iron Project Area, as it later became, includes the Balmoral Central tenements (08/123 to 08/125) from this corridor. Mineralogy holds a number of nearby tenements including other mining leases in this corridor. Mineralogy also holds General Purposes Leases 08/63 (from 27 August 2009) and 08/74 (from 24 September 2009) and Miscellaneous Licence 08/20 (from 5 March 2004). These leases and licences can be seen in Annexures 1 and 2 to these reasons.
87 23 June 1993 was the commencement date of Exploration Licence 08/636 granted to Mineralogy by the State of Western Australia. The area of Exploration Licence 08/636 can be seen in Annexure 3 to these reasons. The importance of this area of Exploration Licence 08/636 is that it includes the area of the port terminal facilities (which are part of the Sino Iron Project) which are at the heart of this dispute. In the Facilities Deeds, the area of Exploration Licence 08/636 is defined as the Preston Area. Clause 33(h) of the Facilities Deeds requires that on termination of the Facilities Deeds, Sino Iron and Korean Steel (in each case) "shall vacate the Preston Area".
88 On 14 February 2001, Mineralogy obtained Mining Leases 08/264, 08/265, and 08/266. As can be seen from Annexure 2 to these reasons, these later formed part of the Sino Iron Project Area.
89 On 25 October 2001, Mineralogy entered into Sublease Agreements with (i) Sino Iron (by its former name, Bellswater), and (ii) Korean Steel. The Sublease Agreements recited that Mineralogy was the holder of Mining Leases 08/118 to 08/130 and Exploration Licence 08/636, and that each of Sino Iron and Korean Steel wished to acquire a right to mine in the Project Area, which is part of the mining leases, to enable the company to mine iron ore.
90 On 26 October 2001, Mineralogy entered into Facilities Deeds with six companies:
(1) Bellswater Pty Ltd (subsequently Sino Iron);
(2) Korean Steel Pty Ltd;
(3) Brunei Steel Pty Ltd;
(4) International Minerals Pty Ltd;
(5) Austeel Pty Ltd; and
(6) Balmoral Iron Pty Ltd.
91 The terms of the Facilities Deeds are considered at length later in these reasons. In very broad terms, and as amended, they relate to the construction, operation, maintenance, and use of facilities for the extraction, processing, transport, and export operations in a project for the export of magnetite ore.
92 On 26 October 2001, Mineralogy, Korean Steel, Sino Iron, and others entered into the Fortescue Projects Consolidation Agreement.
93 On 5 December 2001, Mineralogy entered into the Iron Ore Processing (Mineralogy Pty Ltd) Agreement (the State Agreement) with companies including Korean Steel, Sino Iron, and the State of Western Australia.
94 The recitals to the State Agreement, in broad terms, described how Mineralogy is the holder of mining tenements in the Pilbara region and has granted various rights in relation to certain of the mining tenements to the Co-Proponents (including Sino Iron and Korean Steel) and that Mineralogy (by itself or with a Co-Proponent) wishes to develop projects incorporating the mining, processing, transport and shipping of iron ore, including the establishment of new port facilities in the Pilbara region.
95 On 14 December 2007, the parties agreed on certain variations to the State Agreement.
96 On 24 September 2002, the Iron Ore Processing (Mineralogy Pty Ltd) Agreement Act 2002 (WA) (Agreement Act) came into operation with Royal Assent. This had the effect of bringing the State Agreement into force.
97 On 20 October 2003, Ministerial Statement 635 issued to Mineralogy, under the Environment Protection Act 1986 (WA). In that Ministerial Statement, Mineralogy was the Proponent, with responsibility "for the implementation of the proposal" which was described in Schedule 1 as being "to establish and operate an iron ore mine, process plant (pelletising, direct reduced iron and hot-briquetted iron), accommodation and port facility in the Cape Preston area". The Proposal was described as including "stockpiling, seawater desalination plant and port facilities at Cape Preston and off Preston Island".
98 10 December 2003 was the commencement date for General Purpose Lease 08/52. As I have explained, this is the general purpose lease which covers the area of the port facilities which are in dispute.
99 Mineralogy pleads, and the CITIC parties admit, that the Facilities that Sino Iron and Korean Steel have constructed are located within General Purpose Lease 08/52 and are in the area comprising the Preston Area (as defined in the Facilities Deeds).
100 In April 2004, ARH submitted its first Project Proposal under the State Agreement.
101 30 April 2004 was the commencement date for General Purpose Lease 08/51. As can be seen in Annexure 2 to these reasons, this is the general purpose lease which covers the area of water seaward of the port facilities which are in dispute.
102 On 12 March 2005, Mineralogy and Mineralogy Mine Management Pty Ltd entered into a Joint Development Agreement with three Co-Proponents, including Sino Iron but not Korean Steel.
103 On 21 March 2006, Mineralogy and Sino Iron, and Mineralogy and Korean Steel, varied and re-stated the terms of their respective (amended) Subleases. The new agreements became the Sino Iron MRSLA and Korean Steel MRSLA. Mineralogy also entered into MRSLAs with Brunei Steel, Balmoral Iron, and International Minerals.
104 The Sino Iron MRSLA and the Korean Steel MRSLA were both concerned with matters arising from the Balmoral Central tenements (Mining Leases 08/123 to 08/125). They provided for a total extraction limit of 1 billion tonnes and an annual extraction limit sufficient to produce 12 mtpa.
105 On 8 January 2008, Mineralogy and Sino Iron entered into a deed amending the Sino Iron MRSLA.
106 On 21 March 2006, Mineralogy and Sino Iron, and Mineralogy and Korean Steel amended the terms of their Facilities Deeds.
107 On 31 March 2006, Mineralogy, Sino Iron, Sino Iron Holdings Pty Ltd, and CITIC Pacific Ltd entered into a Takeover Agreement by which Sino Iron Holdings Pty Ltd (a company controlled by CITIC Pacific Ltd) agreed to acquire all of the issued share capital of Sino Iron for US $215 million.
108 On 8 May 2006, CITIC Pacific Ltd became the ultimate holding company of Sino Iron.
109 On 6 July 2006, Sino Iron Holdings completed the acquisition of Sino Iron pursuant to the terms of the Sino Iron Takeover Agreement.
110 In November 2007, Mineralogy and Sino Iron prepared the February 2008 Sino Iron Pellet Project Proposal for the Balmoral Central tenements (Mining Leases 08/123, 08/124, and 08/125).
111 On 1 November 2007, Mr Palmer, Mineralogy, Balmoral Iron Holdings Pty Ltd, Korean Steel, CITIC Pacific Ltd, and Sino Iron entered into a Takeover Agreement pursuant to which Balmoral Iron Holdings agreed to acquire all of the issued share capital of Korean Steel for a consideration of US $200 million, subject to certain adjustments.
112 On 19 November 2007, Sino Iron and Mineralogy as Co-Proponents submitted a compliant Proposal to the State under cl 6(1) and cl 6(2) of the State Agreement.
113 On 29 February 2008, an amended version of this Proposal was submitted (the February 2008 Sino Iron Pellet Proposal).
114 On 2 May 2008, the February 2008 Sino Iron Pellet Proposal was approved. In a later publication by the CITIC parties, this was described as a "major milestone" [tb 10223].
115 In August 2008, CPMM mobilised its construction team to commence work at Cape Preston.
116 It is also admitted on the pleadings that the CITIC parties have constructed at least the following facilities in the Preston Area with the exception of the facilities at (q), (r), and (bb) which the CITIC parties deny having completely built at the time these proceedings were commenced and which I do not accept to have been proved to have been entirely completed at the time of these proceedings:
(a) Causeway;
(b) Breakwater;
(c) Causeway Conveyor;
(d) Barge Loader;
(e) Iron Ore Wharves;
(f) Materials Offloading Facility (MOF) Wharf;
(g) Service Wharf;
(h) Laydown Area (including any materials or stock piles to be used to construct further Facilities at the Port);
(i) Boat Ramps;
(j) Tug pens;
(k) Navigational Aid;
(l) Can buoys for vessel mooring;
(m) Port Workshop and Site Offices;
(n) Security Gate and Fencing;
(o) Security Office located adjacent to the Security Gate;
(p) Lighting System;
(q) CCTV System;
(r) Site Offices located next to the MOF used for Port Communications and Scheduling;
(s) Communications Tower;
(t) Fibre optic communications cable network (underground);
(u) Power Distribution System (underground transmission lines and surface transmission lines running along the Causeway Conveyor);
(v) Corrosion Protection System, made up of: Cathodic protection systems for the Service Wharf, MOF Wharf and Desalination Plant Outfall Pipe; andAnodic protection system for the stiff leg and to stop dolphins at the Iron Ore Wharves;
(w) Potable Water System (underground);
(x) Raw Water System (underground);
(y) Fire Water System (underground pipes and above ground pipes running along length of the Breakwater and hydrants on the Causeway and the access ramps to the Service Wharf and MOF Wharf);
(z) Waste Water/Sewage System (underground);
(aa) Desalination Plant Inlet Pump and Outfall Pipe (and all associated underground pipelines within the Circled Area); and
(bb) Roads within the Circled Area (being the roads running along the Causeway on either side of the Causeway Conveyor, the access road to the MOF Wharf, the access road to the Service Wharf and the road along the Breakwater).
117 On 6 March 2008, Exploration Licence 08/1414 commenced.
118 On 22 April 2008, Exploration Licence 08/1451 commenced.
119 On 22 July 2008, Mineralogy, Sino Iron, Korean Steel, and the State agreed to amendments to the State Agreement.
120 On 23 September 2008, the Minister declared the Port of Cape Preston was subject to the Occupational Safety and Health Act 1984 (WA).
121 On 22 October 2008, completion of the acquisition of Korean Steel by Balmoral Iron Holdings pursuant to the Korean Takeover Agreement. CITIC Pacific Ltd became the ultimate holding company of Korean Steel. On the same day Mineralogy and Korean Steel entered into a deed amending the Korean Steel MRSLA.
122 On 22 October 2008, Mineralogy, CITIC Pacific Ltd, Sino Iron, and Korean Steel entered into the Fortescue Coordination Deed.
123 The Fortescue Coordination Deed included provisions requiring the transfer of Mineralogy's status as Proponent under Ministerial Statement 635. The Fortescue Coordination Deed also provided that unless the Joint Development Agreement is reinstated as a result of the CITIC Option lapsing, "CITIC or its nominee will be solely responsible for the planning and conduct of Mining Operations by each of the Mining Right Holders": cl 2.4(c).
124 On 14 November 2008, Mineralogy, Korean Steel, Sino Iron, and the State executed an amendment to the State Agreement. That amendment took effect when legislated on 10 December 2008 in the Iron Ore Processing (Mineralogy Pty Ltd) Agreement Amendment Act 2008 (WA).
125 In February 2009, CPMM commenced construction of the causeway at Cape Preston.
126 On 30 March 2009, Mineralogy and Korean Steel submitted the Korean Steel Concentrate Project Proposal for Mining Leases M08/123, M08/124, and M08/125.
127 On 22 April 2009, the Sino Iron Concentrate Proposal submitted to the State under cl 8(1) of the State Agreement.
128 On 22 April 2009, Korean Steel Concentrate Proposal submitted to the State under cl 6 of the State Agreement.
129 On 20 May 2009, the Minister for State Development consented for the Korean Steel Project to use facilities constructed as part of the Sino Iron Project in the conduct of its proposed project.
130 In June 2009, CPMM commended construction of the breakwater at Cape Preston.
131 On 11 June 2009, the Korean Steel Concentrate Proposal was approved by the State (the April 2009 Korean Steel Concentrate Project Proposal). As explained, as part of the Korean Steel Concentrate Proposal, Korean Steel had obtained consent to use Sino Iron's facilities.
132 On 22 June 2009, the Minister for State Development approved the Sino Iron Concentrate Project - Additional Project Proposal (the April 2009 Sino Iron Concentrate Proposal), regarding production and export overseas of iron ore concentrates.
133 On 3 July 2009, State environmental approval was granted permitting the production of iron ore concentrate to be increased from 19.6 mtpa to 27.6 mtpa.
134 This approval was significant to the CITIC parties. In the CITIC annual report for 2009 [tb 4403] it was said:
All major approvals for the construction and operation of the project have now been received. In 2009, we obtained approval under the Western Australian Government's Environmental Protection Act and Iron Ore Processing (Mineralogy Pty Ltd) Agreement Act to build our port and expand the project to export 28 mtpa of concentrate product.
135 The 2009 CITIC annual report also explained that once "the project goes into operation, product ready for export will be moved from land to vessels berthed at sea via transshipment. Transshippers, barges and tugs are now under construction in China" [tb 4406].
136 In July 2009, Sino Iron submitted a development proposal to Mineralogy under the Sino Iron Facilities Deed. The proposal was for the "construction of a port" for the Sino Iron Pellet Project.
137 In October 2009, a further Amended Port Construction Proposal was submitted by Sino Iron and Korean Steel to Mineralogy.
138 In November 2009, construction of a barge loader for the Project commenced in China.
139 On 10 November 2009, the Second Sino Iron Concentrate Proposal submitted to the State under cl 8(1) of the State Agreement.
140 On 10 November 2009, the Second Korean Steel Concentrate Proposal submitted to the State under cl 8(1) of the State Agreement.
141 In December 2009, a Further Amended Port Construction Proposal was submitted by Sino Iron and Korean Steel to Mineralogy. The construction of the permanent causeway at Cape Preston was completed.
142 On 15 December 2009, ProMet Engineers advised Mineralogy on quality of amended Port Proposal.
143 On 17 December 2009, Commonwealth Environmental Approval EPBC 2008/4236 decision.
144 On 23 December 2009, Ministerial Statement 822 was published 23 December 2009 (varying Ministerial Statement 635). Ministerial Statement 823 was published in relation to the Balmoral South Project.
145 On 6 January 2010, the Second Sino Iron Concentrate Proposal (the November 2009 Second Sino Iron Concentrate Proposal) and the Second Korean Steel Concentrate Proposal (the November 2009 Second Korean Steel Concentrate Proposal) were approved by the State.
146 These additional Project Proposal approvals authorised the expansion of the Sino Iron Project and the Korean Steel Project to support production and export of 27.6 mtpa of iron ore concentrate in addition to the 6 mtpa of pellets for the Sino Iron project, with Sino Iron and Korean Steel each being permitted to produce and export 13.8 mtpa of iron ore concentrates.
147 On or about 1 March 2010, Mineralogy established an Administration Fund under the Facilities Deeds.
148 In March 2010, the first ball mill was installed at the processing plant.
149 On 9 March 2010, Ministerial Statement 827 was published (varying Ministerial Statement 823).
150 On 23 March 2010, Mineralogy and the CITIC parties entered into the Port Terminal Operator Agreement.
151 In May 2010, the first autogenous grinding mill was installed at the processing plant.
152 In June 2010, construction of the barge loader was completed in China and construction of the barge loading facility commenced at Cape Preston.
153 In August 2010, construction of the barge loading facility at Cape Preston was completed.
154 On 2 November 2010, the Minister declared the Port was subject to the Mining Act 1978 (WA).
155 In January 2011, the construction of the breakwater at Cape Preston was completed.
156 In March 2011, installation of the barge loader was completed and installation of conveyors along the breakwater commenced.
157 In September 2011, the barges and transshipper were delivered to the Port area.
158 On 22 November 2011, the Minister declared the Port was subject to the Mining Safety and Inspection Regulations 1995 (WA).
159 On 23 November 2011, the last version of Port Construction Proposal was submitted by Sino Iron and Korean Steel to Mineralogy.
160 On 22 March 2012, Mineralogy was granted a non-exclusive Jetty Licence by the Manager, Property Services Coastal Facilities of the Western Australian Department of Transport.
161 On 11 May 2012, Mr Sharma, the Managing Director for Mineralogy in Western Australia, wrote to the CITIC parties, asserting Mineralogy's ownership of "our port facilities" and saying that Mineralogy needed time to recruit operating personnel for equipment including the dewatering plant, the stackers and reclaimers, all pumping equipment in the Port area, all conveyors in the Port area, the barge loader, the water intake and outlet for the desalination plant, and all other equipment installed in the Port area. Mr Sharma also urgently sought information for the operation of the port terminal facilities and stressed the urgency of obtaining that information "prior to taking over operation".
162 In June 2012, dry commissioning of the barge loader, conveyor and transshipment fleet for the Project was in progress.
163 In November 2012, Sino Iron and Korean Steel commenced trial production.
164 On 31 January 2013, the Commonwealth Department of Infrastructure and Regional Development Office of Transport Security declared the Port of Cape Preston to be a security regulated port and designated Mineralogy as Port Operator under the MTOFS Act.
165 On 27 February 2013, the CITIC parties sent a three page letter to Mineralogy saying that the "by-laws" attached to the Facilities Deeds were not approved by the relevant government agencies of the State of Western Australia (as was correct).
166 Mineralogy later relied on this letter as the basis for termination notices which it purported to issue under the Facilities Deeds.
167 On 18 March 2013, Mineralogy commenced Federal Court of Australia Proceeding WAD 83 of 2013.
168 On 2 April 2013, HopgoodGanim, the solicitors for Mineralogy, sent a letter to Allens, solicitors for the CITIC parties, demanding handover of, and control of, the Port Facilities.
169 On 5 April 2013, Mineralogy served a notice of demand on CITIC Pacific Ltd, Sino Iron, and Korean Steel requesting that they hand over possession of the Port.
170 On 12 April 2013, the solicitors for the CITIC parties sent a five page letter to the solicitors for Mineralogy responding to various allegations made by Mineralogy including allegations concerning the Port.
171 Mineralogy later relied on this letter as a basis for Termination Notices which they purported to issue under the Facilities Deeds.
172 On 15 April 2013, Mineralogy withdrew Federal Court of Australia Proceeding WAD 83 of 2013.
173 On 16 April 2013, Mineralogy commenced this proceeding.
174 On 19 April 2013, CITIC Pacific announced that the first shipment of iron ore concentrate was expected to be in the second half of May 2013.
175 On 22 April 2013, Mineralogy wrote to Sino Iron and Korean Steel referring to CITIC Pacific Ltd's recent announcement stating that the first shipment of iron ore concentrate is expected to be in the second half of May 2013, and alleging that cl 25 of the Facilities Deeds says that Mineralogy is responsible for all scheduling and that Sino and Korean shall advise Mineralogy of all proposed shipping schedules. Mineralogy said that it looked "forward to receiving your schedules without further delay" [tb 9653].
176 On 3 May 2013, CPMM responded to Mineralogy's 22 April 2013 letter and said that "once our shipping schedule is firm and we have a vessel committed for first shipment we will provide you a copy of the shipping schedule" [tb 9799A]. CPMM also said that it did "not expect Mineralogy to make any amendments to the shipping schedule when it is issued" because cl 25(b) of the Facilities Deeds permits Mineralogy to amend CITIC's shipping schedules only "for good cause" [tb 9799A]. CPMM asserted that CITIC has priority rights to access and use the Facilities it has constructed and that no scheduling conflicts should arise as CITIC is currently the only authorised user of the Port. CPMM asked Mineralogy to "please let us know if Mineralogy insists on a formal consultation process in relation to the shipping schedule" [tb 9799A].
177 This letter from CPMM later formed the basis for termination notices which Mineralogy purported to issue under the Facilities Deeds.
178 On 17 September 2013, CPMM wrote to the Department of Mines and Petroleum in respect of a notification under s 4(3) of the Mine Safety and Inspection Act 1994 (WA).
179 On 29 September 2013, the Department of Mines and Petroleum, together with the State Mining Engineer, notified CPMM pursuant to s 4(3) of the Mine Safety and Inspection Act.
180 On 11 November 2013, the Commonwealth Department of Infrastructure and Regional Development Office of Transport Security approved CPPC's Maritime Security Plan for a Port Facility Operator pursuant to the MTOFS Act.
181 On 29 November 2013, Mineralogy replied to CPMM's letter of 28 November 2013 advising that as the port owner and operator, the purported proposed shipping schedule was not approved and that CPPC should not undertake any operations at the Port of Cape Preston.
182 On 2 December 2013, CPMM issued a press release announcing that the first shipment of magnetite ore was being loaded before it set sail for China. The press announcement explained that the first concentrator line was operational and that the second was in process. The critical components surrounding the concentrator line were also operational. These are the power plant, slurry pipeline, desalination plant, and Port Facilities [tb 10371].
183 On 13 February 2014, the CITIC parties' Further Amended Defence was filed in these proceedings. Mineralogy later alleged that filing this defence was a serious breach of the Facilities Deeds in a Termination Notice that Mineralogy issued, purportedly under the Facilities Deeds.
184 On 3 June 2014, Mineralogy wrote to Sino Iron and Korean Steel giving notice that it approved the use of the Facilities by ARH. Mineralogy said that it would "determine pursuant to Clause 8.7(a) the amount that [ARH] will pay to your companies, based on tonnage of products to be shipped from time to time prior to [ARH] commencing such shipments" [tb 10859].
185 On 12 June 2014, CPMM wrote to Mineralogy denying the validity of the notice by Mineralogy that ARH had been given approval to use the facilities and saying that ARH "has made no announcement to the market that it has made a decision to mine. In the context of a listed company that has a market capitalisation of less than $10 million dollars, it is inconceivable that such a decision would not require disclosure in accordance with its continuous disclosure obligations" [tb 10920].
186 This response later formed the basis for Termination Notices issued by Mineralogy purportedly under the Facilities Deeds.
187 On 20 August 2014, the Full Court of the Federal Court set aside the decision to designate Mineralogy as Port Operator for Cape Preston.
188 On 26 September 2014, in the Supreme Court of Western Australia, I granted an interim injunction restraining Mineralogy from issuing default notices and termination notices under the MRSLAs.
189 On 25 November 2014, Mineralogy issued Termination Notices to Sino Iron and Korean Steel under the Facilities Deeds. These Termination Notices became the basis for Mineralogy's primary relief in this action.
190 On 6 February 2015, in the Supreme Court of Western Australia, I made a declaration that Mineralogy was obliged by cl 20.1(a) of the Fortescue Coordination Deed to make an application to the Western Australian Minister for the Environment for the transfer to Sino Iron and Korean Steel of the status of proponent under Ministerial Statement 635 (as amended) and Ministerial Statement 822.