Consideration
65 It was common ground that whether the parties intended immediately to be contractually bound was to be determined objectively, according to the intention disclosed by their words and conduct. It is sufficient to refer to Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540 at 548-9 per Gleeson CJ, with whom Hope and Mahoney JA agreed, and the cases there cited.
66 It must be remembered, however, that the intention in question in the present case was not a general intention at some time to enter into a contract, but an intention to make an immediately binding contract. Parties may enter into a binding contract upon terms and conditions necessary for their contractual relationship, in the expectation that at a later time the formal contract will be executed consistently with those terms and conditions or perhaps with additional terms and conditions. Conversely, parties may agree upon quite detailed terms and conditions for a contractual relationship but not intend immediately to be contractually bound on those terms and conditions; this may be pending negotiations on other matters or until execution of a formal contract. Unsurprisingly, a conclusion must be reached in the circumstances of the particular case, although judges are wont to formulate guiding "principles" or "propositions". While I will refer to some "principles", they are subservient to the fact-specific objective finding of the parties' intention. .
67 As I have indicated, Sagacious submitted that the trial judge should not have looked beyond the April letter. It submitted that what it described as "extra-contractual evidence" had no significance, because the April letter was sent as a "proposal" which "merges all the terms and conditions which have been negotiated and agreed to" and "supersedes all previous correspondence in relation to our contract renegotiation to date", and was signed on behalf of Mayne to "acknowledge and accept the terms and conditions outlined above". It drew attention to the reference by Gleeson CJ in Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd at 549-50 to a case where the parties had signed a single document containing an expression such as "subject to contract" where the outcome "will ordinarily turn on the construction of the single document". It referred to the significance of signature of a document as a commitment to its terms, even if the terms were not known or understood, as explained in Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 210 CLR 165 at [40]-[45] per Gleeson CJ and Gummow, Hayne, Callinan and Heydon JJ. It said that the parties' contractual intention should therefore be found only by regard to the April letter.
68 Where the question is whether a document constitutes a legally binding contract, McHugh JA said in G R Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd at 634 that "the decisive issue is the intention of the parties which must be objectively ascertained from the terms of the document when read in the light of the surrounding circumstances". However, there is the prior question whether the document is the sole repository of the parties' contractual intention. A formal document expressed to be "subject to contract", for example, may provide that starting-point, but it may nonetheless be shown that a legally binding contract was not intended. McHugh JA gave examples in Air Great Lakes Pty Ltd v K S Easter (Holdings) Pty Ltd (1985) 2 NSWLR 309 at 336-7, and said that a party may prove that before signing an agreement the signatories agreed that it did not constitute a binding contract and that "the intention to be bound is a jural act separate and distinct from the terms of their bargain".
69 The answer to what can generally be described as a Masters v Cameron question is not necessarily found in a single document. The intention of the parties may be found in a series of communications, or it may be shown that the signed document is only part of their putative contractual relationship. Further, in ascertaining the intention of the parties, whether from a series of communications or from a single document, regard can be had to the commercial circumstances in which the parties exchanged their communications or arrived at the document and to the subject-matter of the putative contract. The objective intention of the parties is fact-based, found in all the circumstances including "by drawing inferences from their words and their conduct in the making of [their] agreement": Allen v Carbone (1975) 132 CLR 528 at 532 per Stephen, Mason and Murphy JJ; see also Australian Broadcasting Corporation v XIV Commonwealth Games Ltd at 548 per Gleeson CJ. Regard can also be had to the conduct of the parties after the occasion of the putative contract, to cast light on the meaning of the communications in question and otherwise on whether they intended immediately to be contractually bound, of which I say more later in these reasons.
70 Even in construing the April letter as a contract, regard could be had to evidence of surrounding circumstances. Putting that aside, I do not think the signature of the April letter closed off regard to the circumstances in which the letter was sent and signed and to the conduct of the parties thereafter. The prior question remained. Although Mr Dalton signified Mayne's acknowledgment and acceptance of "the terms and conditions outlined above", where there is a Masters v Cameron question it must still be asked whether what was thereby signified was with the intention that the parties be immediately contractually bound on those the terms and conditions. The parties may have agreed, but what had they agreed? To confine attention to the terms of the April letter begs the question.
71 The terms of the April letter are nonetheless important to finding the parties' contractual intention. Mr Dalton did sign by way of acknowledgment and acceptance of the outlined terms and conditions, and para 7(c) of the letter contained its own acknowledgment that the parties "are bound by these terms and conditions and will act in good faith to expedite the finalisation of the Service Level Agreement which will be provided by Sagacious to Mayne". The April letter referred from time to time to "this agreement", see the first paragraph and paras 1.1(a) and (b), 1.3(h) and 6(a). Paragraphs 1.1(a) and (b) and 6(a) referred to "the term of this agreement", clearly enough the period from 1 May 2002 to December 2004 in para 1.4. If one goes no further, these are strong indicators that the parties intended that the letter should constitute a binding contract, albeit that they were to negotiate in good faith to a formal contract called in the letter a Service Level Agreement.
72 However, on going further there are contra-indicators within the April letter itself, suggesting that the agreement it recorded was upon terms and conditions for a contract in advanced negotiation but yet to be finalised and become binding. As was said by Higgins J in Barrier Wharfs Ltd v W Scott Fell & Co Ltd (1908) 5 CLR 647 at 650 -
"There is no contract unless the two parties mutually consented to be bound one to the other by one agreement. Moreover--though it ought to be superfluous to say it--it is one thing for two parties to settle what are to be the terms of an agreement, if it should be made; and quite another thing to make the agreement."
73 Some of the matters to which I will refer bring into consideration one of the "principles" found in the cases, a formulation by Kirby P in Geebung Investments Pty Ltd v Varga Group Investments No 8 Pty Ltd (1995) 7 BPR 97578 at 14,569 being that "[t]he existence of matters of importance on which the parties have not reached consensus in their informal agreement will render it less likely that they intended immediately to be bound before the execution of a formal document". It is ordinary reasoning: in Australian Broadcasting Corporation v XIV Commonwealth Games Ltd at 548 Gleeson CJ said that "as a matter of fact and commonsense" the more numerous and significant the areas in respect of which the parties had failed to reach agreement, the slower a court will be to conclude that they had the requisite contractual intention. And the ordinary reasoning can extend to where the parties have failed to express their agreement clearly as well as where they have failed to reach agreement; put another way, failure to reach agreement includes where there is obscurity or incompleteness in the agreement. While the courts will endeavour to give effect to a contract made between businessmen notwithstanding that its terms have not been fully or well stated, that the terms have not been fully or well stated is material to whether a contract was made.
74 Paragraph 1.3(h) of the April letter stated an acknowledgment that "this agreement (and the final Service Level Agreement) will include provisions, or similar in intent, to the July 2000 Strategic Alliance Agreement". It said that "such provision will include", followed by a list of provisions purportedly identifiable in the Strategic Alliance Agreement.
75 This underlined that a final Service Level Agreement was yet to come; it was unclear whether this meant an equivalent to the Strategic Alliance Agreement or, by reference to the Service Level Agreement which had accompanied the Strategic Alliance Agreement, an equivalent detailed and necessary part of the contractual relationship, but in any event there was yet to be agreement upon it. But by the words "this agreement … will include", with words of futurity used in relation to "this agreement" as well as in relation to the Service Level Agreement, it also conveyed that acknowledged and accepted in the April letter was of terms and conditions to be part of a contract to which the parties were not yet bound, giving some point to the frequent use of the word "proposal" as a description of the contents of the letter.
76 Further, the provisions to be included were left unclear in two respects. They were to be "similar in intent" to the Strategic Alliance Agreement, and the list was inclusory rather than definitive. These were important provisions for a major contractual relationship, which one would expect the parties to wish to have clear before they were contractually bound. In particular there were significant provisions of the Strategic Alliance Agreement
77 A matter which occupied some time in submissions was the provision "Termination" to be imported from the Strategic Alliance Agreement.
78 Para 1.3(h) of the April letter would, if it constituted a binding contract, incorporate the provision, or a provision similar in intent to, the Strategic Alliance Agreement provision(s) identified as "Termination". Clause 9 of the Strategic Alliance Agreement, under the heading "Termination", provided for termination by Mayne for convenience (cl 9.2), termination by Sagacious for cause (cl 9.2), termination by Mayne for cause (cl 9.3) and an obligation of both parties to act in good faith (cl 9.4). Mayne could terminate for convenience during the Initial Term on one month's notice and with payment of an Early Termination Payment on a sliding scale, and after the Initial Term on three month's notice without that payment. The Initial Term was the two years commencing on 1 August 2000.
79 It will be recalled that as a fall-back Mayne had in its letter of 31 July 2002 purported to terminate on three months notice. Sagacious would have a largely Pyrrhic victory if it established a binding contract which had been validly terminated.
80 Sagacious submitted that as a matter of construction of the April letter it incorporated only cll 9.2 and 9.3 of the Strategic Alliance Agreement. It said that the Initial Term was no longer relevant, that para 1.3(h) separately referred to a provision "Obligation to act in good faith" and so cl 9.4 was not to be imported, and that a limited termination for convenience flowed from para 1.4(b) of the April letter (removal of certain groups of hospitals et cetera) so an inconsistent cl 9.1 could not have been intended.
81 Termination for convenience had been the subject of the 11 April 2002 discussion between Mr O'Shanassy and Mr Dalton, according to Mr O'Shanassy super kitchens expressly being the only occasion for termination for convenience but according to Mr Dalton not so. As I have said, the trial judge did not resolve this conflict in the evidence.
82 It was by no means clear that the construction for which Sagacious contended was the correct one. At the least the residue of the Initial Term could have been relevant, or in the incorporation of cl 9 of the Strategic Alliance Agreement a corresponding Initial Term could have been created. The Strategic Alliance Agreement had another provision imposing an obligation of good faith, cl 1.2, to which para 1.3(h) of the April letter could have been referring. Paragraph 1.4(b) was not a termination provision, but a provision for reduction in scope in certain events. Whatever the discussion between Mr O'Shannassy and Mr Dalton had been, its availability as an aid to construction would be doubtful at best, but if it were available para 1.4(b) was not in terms of super kitchens.
83 I do not decide the correct construction of the April letter in this respect. While it was open to the parties to make an immediately binding contract which was obscure, the obscurity on such an important matter gives point to the futurity in the provisions to be included and to the lack of clarity in "similar in intent". This at least of the listed provisions to be taken up from the Strategic Alliance Agreement needed the clarification which would be expected in the final expression of a binding contract, and the obscurity is an indicator that the parties did not intend immediately to be bound.
84 The penultimate paragraph of the April letter commencing "Notwithstanding the provisions outlined above … " provided for a trial period and review and adjustment of the PPD rates, and that any adjustments "will be incorporated into the contract for services provided by Sagacious to Mayne during a contract period of not less than two and a half years". The adjustment was to be to "the subsequent contractual terms". This was not the language of adjustments within a presently binding contract, but conveyed that a contract was to be made after the trial period and review taking up any adjustments to the proposed PPD rates.
85 The second paragraph of the April letter referred to "our contract renegotiation discussions to date", on one reading meaning that the letter was part of a contract renegotiation yet to be concluded. An important matter on which one would expect further negotiation was the adjustment to which the penultimate paragraph referred, an adjustment "so that Sagacious receives revenue sufficient to meet the Costs of Goods (COGS) purchased for Mayne and a reasonable Sagacious overhead and profit". On Mr O'Shanassy's evidence, this had been introduced in the letter as part of his draft of something "to encapsulate what we see as the intent", without greater clarity in the discussion. Any adjustment was highly important to both Sagacious and Mayne, but the penultimate paragraph was unclear in a number of respects.
86 On one view, an adjustment would be retrospective to 15 January 2002, which would negate the greater part of the savings of $1,300,000 on which Mayne had insisted. But the paragraph also could be understood as providing for adjustment for the future.
87 One description of the adjustment was to bring the guaranteed PPD rate into a relationship with the actual PPD rate. Another, perhaps to apply only prospectively, was to give Sagacious the cost of goods plus a reasonable overhead and profit component. How the two stood together was quite obscure.
88 The reasonable overhead and profit component was itself an uncertain concept. Sagacious submitted that the 4.75 per cent of the original Strategic Alliance Agreement was part of the actual PPD rate and that the overhead and profit component meant the 4.75 per cent. The argument it put produced a Suttor v Gundowda objection by Mayne; I have difficulty in seeing how it could be correct. There was at the least obscurity, and it seems to me likely that the reasonable overhead and profit component was not to be identified with the 4.75 per cent. Testing the significance of the uncertainty against the parties' own conduct, in the negotiations prior to the Strategic Alliance Agreement Sagacious had sought a percentage fee of 20 per cent, Mayne had refused, and the fee struck was 4.75 per cent; there is a graphic illustration of different views of what could be a reasonable overhead and profit component, with eventual agreement between the parties to two percentage points.
89 Again, it is not necessary to resolve the construction of the penultimate paragraph. It is difficult to accept an objectively found intention that these parties, in the historical setting of their relationship, immediately bound themselves to such obscurity and indeterminacy on such an important matter.
90 Paragraphs 7(b) and (c) of the April letter are of some significance. Paragraph 7(b) states the interdependence of the previous paragraphs as components of "the proposal", and that "neither Sagacious nor Mayne can arbitrarily remove any term or condition in the sections outlined above". Paragraph 7(c) refers to the parties being bound by the terms and conditions, but also to acting "in good faith to expedite the finalisation of the Service Level Agreement which will be provided by Sagacious to Mayne". There were to be further negotiations and execution of a formal contract, and the embargo on arbitrary removal of terms or conditions suggested that they could be removed if there were good reason in the future negotiations. That is, the terms and conditions were agreed as the platform for further negotiations, being binding between the parties as the platform (subject to non-arbitrary change) but not as an immediately binding contract for the provision of eProcurement services.
91 The April letter left rather indeterminate a number of other matters. In a multi-million dollar contract, the terms of which had in the Strategic Alliance Agreement and its Service Level Agreement been stated in detail and at length, one would expect the parties to state them definitively before being contractually bound. A contract can, of course, provide for matters to be worked out during the course of the contract. But the April letter left many matters to be worked out, stating -
· that Sagacious and Mayne "are to agree on the following mechanism to alert 'abuse' on expenditure … " (para 1.2(a)), the mechanism being outlined but further agreement being contemplated;
· that extraction of certain amounts involved agreement on a separate arrangement and anticipation of supply of software and hardware, (para 4);
· that in that respect Sagacious had a "preliminary position", it seems only as a preliminary position subject to change (para 4);
· as examples only of language which one would not expect in a major contract of this nature, that Sagacious' responsibility was "to ensure a 24 x 7 seamless hospital operation" (para 1.3(f)) and that Mayne could remove "certain groups of hospitals" if it decided "to substantially change or alter its food service operations which result in making the Sagacious service redundant" (para 2(b));
· that the upgrade of the e-commerce system was contingent on Mayne's agreement to it and its implementation (para 5); and
· that Sagacious had a "first right of offer" on its services to new hospitals or commercial production facilities, without any elaboration or mechanism for giving effect to the first right of offer.
92 For a number of reasons, then, the April letter was equivocal in expressing an intention that the parties would immediately be contractually bound. The agreement signified by the acknowledgment and acceptance of the terms and conditions was by no means plainly that those terms and conditions were the terms and conditions of a binding contract, and it was open to conclude that the agreed terms and conditions were the then stage of the negotiations but the binding contract was yet to be finalised.
93 Sagacious submitted that the circumstances in which the letter was sent by it and signed on behalf of Mayne supported an intention to make a concluded contract. It said that, with the Strategic Alliance Agreement as varied by the letter of 18 January 2002 due to expire on 30 July 2002 -
· Sagacious had a strong commercial interest, known to Mayne, in securing a binding long-term contract, both in order to allow Sagacious to recoup losses since January 2002 on the $11.50 PPD rate and in order to use a contract with Mayne as a key customer to obtain contracts with hospitals or other businesses outside Mayne's business; and
· Mayne had a strong commercial interest, impliedly known to Sagacious, in binding Sagacious to long-term provision of eProcurement services on the PPD basis with a view to security of supply and a favourable PPD rate.
94 Sagacious submitted that Mayne could not be confident even that Sagacious could be kept to the $11.50 PPD rate until the end of July 2002, since under the letter of 18 January 2002 there could be reversion to the management fee under the Strategic Alliance Agreement in the event of dispute. Thus, it submitted, it made commercial sense for the parties to replace their existing contractual relationship and provide for a new long-term contractual relationship, with immediate effect; even if the replacement was by a contract on the "basic parameters" of the new contractual relationship, but later to be replaced by a formal contract taking up Mayne's detailed terms and conditions.
95 Sagacious' interest in achieving a long-term contract may be accepted, but less readily Mayne's interest in making a new contract with immediate effect. The courts should be cautious in placing themselves in businessmen's shoes, and for a number of reasons it would be rash to see reciprocal commercial imperatives.
96 In the past Mayne had placed considerable pressure on Sagacious, effectively forcing variation of the Strategic Alliance Agreement to its advantage, and Sagacious had knuckled under. It is plain that Sagacious would go to considerable lengths to accommodate Mayne, including by continuing to provide services with a view to a future long-term contract. Mayne's commercial dominance over Sagacious was such that there was no pressure on Mayne to enter a binding long-term contract, and the proof that it had no need to do so might be thought to be that it declined to proceed with Sagacious at the end of July 2002. Albeit perhaps as a small point, it may be observed that reversion to the management fee under the Strategic Alliance Agreement could not be at Sagacious' will, since it depended on dispute which could not be resolved. It was not particularly likely that Sagacious would cease providing eProcurement services after 31 July 2002 pending execution of a formal contract.
97 Of particular significance, adjustments in accordance with the penultimate paragraph of the April letter ("Notwithstanding the provisions outlined above … ) would negate the inroads Mayne had made by insistence on the savings of $1,300,000 and then on reduction of the $11.50 as provided in the steps down in para 3 of the letter. Possibly a significant part of the $1,300,000 would be lost retrospectively, but certainly savings for the future would be compromised. Mayne would pay according to cost of goods plus a reasonable overhead and profit. It is far from evident that Mayne should be taken to have seen that as to its advantage, particularly with the indeterminancy of "a reasonable overhead and profit component".
98 The Strategic Alliance Agreement had followed the Heads of Agreement, putting what the parties had agreed upon into a detailed formal contract. The presentation on 28 March 2002 had in the last slide referred to first, "Agreement to Proposal" and secondly, "Sign off new contract". In early April 2002 Messrs Dalton and Kyne had both envisaged drafting a new agreement, referred to by Mr Kyne as a full and final agreement. This provides some support for the April letter being intended as the agreement on the parameters of the new contract, on the way to being bound by "signing off" the formal contract.
99 Regard to the parties' subsequent communications is of some importance in this case. That regard may be had to their subsequent communications is undoubted. In Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd Gleeson CJ said at 547-8
"There is ample authority for the proposition that reference may be made to the correspondence between the parties subsequent to 13 June 1986 for the purpose of showing that 'it was not in the contemplation of either party that they were to be bound until all the essential preliminaries had been agreed to, nor until a formal contract had been drawn up embodying all the matters incidental to a transaction of such a nature': Barrier Wharfs Ltd v W Scott Fell & Co Ltd (1908) 5 CLR 647 at 669 per Griffiths CJ; see also Howard Smith and Co Ltd v Varawa (1907) 5 CLR 68; Hussey v Horne-Payne (1879) 4 App Cas 311; B Seppelt and Sons Ltd v Commissioner for Main Roads (1975) 1 BPR 9147 and Film Bars Pty Ltd v Pacific Film Laboratories Pty Ltd (1979) 1 BPR 9251."
100 So also in Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153 at [25] Heydon JA said succinctly, referring to the same cases, that "post-contractual conduct is admissible on the question of whether a contract is formed".
101 In Barrier Wharfs Ltd v W Scott Fell & Co Ltd at 669 Griffiths CJ had considered that subsequent correspondence between the parties showing that they continued in negotiation "negatives the idea of an existing concluded contract". In Howard Smith and Co Ltd v Varawa (1907) 5 CLR 68 his Honour had said at 78 that "the question being whether the parties had in fact concluded an agreement on 1st December, any statements or conduct on their part after that date inconsistent with the existence of a concluded contract are relevant for this purpose". In B Seppelt and Sons Ltd v Commissioner for Main Roads (1975) 1 BPR 9147 regard was had to subsequent communications showing that the parties contemplated the execution of a formal contract, and Mahoney JA said at 9155, with reference to Barrier Wharfs Ltd v W Scott Fell & Co Ltd and Howard Smith and Co Ltd v Varawa, that although it was not conclusive on whether a binding contract had previously been made, the regard -
" … does provide support in the present case for the view that, as the parties understood it, whether the contract was to proceed was affected by matters to be agreed concerning settlement, and that in relation to that agreement, it was proposed to exchange contracts and proceed in the normal course of conveyancing".
102 The juridical basis on which the subsequent communications bear upon contractual intention may not be settled.
103 In Film Bars Pty Ltd v Pacific Film Laboratories Pty Ltd (1979) 1 BPR 9251 McLelland J suggested at 9255-6 that the probative value of subsequent communications lay in the light they shed on "the proper interpretation of the earlier communications alleged to constitute the contract", such as by showing continued negotiations whereby the alleged contractual dealings could not properly be interpreted as mutual assents to be bound; his Honour said they could also be admissions by conduct of the existence or non-existence of a subsisting contract, with the probative force "vary[ing] inversely with the strength of the available direct evidence of the matters in question".
104 Interpretation of the earlier communications may not be an ideal description of the use of the subsequent communications on the first basis to which his Honour referred. It has been put a little differently in other cases. In Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd at 548 Gleeson CJ spoke of "interpretation and understanding of the earlier communications in that it constitutes an important source of information as to what are matters incidental, or for that matter essential, to a transaction of the nature in question". In Geebung Investments Pty Ltd v Varga Group Investments No 8 Pty Ltd one of Kirby P's "principles" was -
"4. In order to determine in what areas the parties were, and were not, in agreement, and what matters they considered necessary in order for an agreement to exist, it is legitimate to examine their subsequent conduct. Where correspondence between the parties after an informal agreement refers to important terms and conditions not mentioned during that informal discussion, it may more readily be inferred that the earlier discussion was simply a preliminary negotiation and not a binding agreement;"
105 I respectfully suggest that subsequent communications are not simply aids to interpretation, or a source of information as to matters with which a concluded contract should deal. Their probative value may be more direct. To repeat, the objective intention of the parties is fact-based, and found in all the circumstances. That in their subsequent communications the parties have continued in negotiations, or have expressed the common understanding that they are not legally bound unless and until a formal contract is executed, is of itself probative as to their contractual intention: see Howard Smith and Co Ltd v Varawa, stating simply that any statements or conduct inconsistent with the existence of a concluded contract are relevant.
106 The basis of subsequent communications as admissions is very different. It does not depend on communication between the parties, and that basis gives scope for evidence of, for example, a party's internal memoranda saying or less directly conveying that there is or is not a concluded contract. Admissions bearing upon contractual intention present difficulties. As Gleeson CJ said in Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd at 550, "it will often be necessary to identify with some care the fact which is said to have been admitted". What is said to be admitted may be a relatively straightforward fact, for example that A discussed with B the price for goods. But if a matter of mixed law and fact is involved, or the application of a legal standard, admissibility may be more contentious. It is considered in Grey v Australian Motorists & General Insurance Co Pty Ltd (1976) 1 NSWLR 669 at 675 per Glass JA and 684-5 per Mahoney JA; Jones v Sutherland Shire Council (1979) 2 NSWLR 206 at 231 per Mahoney JA; and Pitcher v Langford (1991) 23 NSWLR 142 at 147 per Kirby P and 160 per Handley JA, but see the reservations, with reference to other cases, in Cross on Evidence, Aust ed, at [33465]. An admission by conduct in a case such as the present may bring its own difficulties. And a statement that there is or is not a concluded contract, for example, may if admissible, carry significant weight or little weight depending on the circumstances, and the weight of any admission will depend on the source of knowledge of the person making the admission: cf Lustre Hosiery Ltd v York (1936) 54 CLR 134 at138-9 per Rich, Dixon, Evatt and McTiernan JJ.
107 Subject to a qualification, neither Sagacious nor Mayne relied in the appeal on conduct other than communications between the parties, understanding communications in the wide sense of conduct between them extending to (for example) the billing and payment two months in advance (Sagacious) and the presentation of 25 June 2002 and submission of the discussion paper (Mayne). I refer to the qualification later in these reasons.
108 Sagacious submitted that the intention to make a binding contract was supported by the communications whereby, in accordance with the April letter -
· from 1 May 2002 Sagacious billed Mayne two months in advance and Mayne paid Sagacious two months in advance;
· the regional hospitals were included in Sagacious' eProcurement services and its billing; and
· new national menus were introduced from 6 May 2002.
109 These are valid considerations, except perhaps the introduction of new national menus as that seems to have been in train since much earlier in the year. But they are only part of the picture. Other communications after the April letter quite strongly indicated that the parties had not intended to make an immediately binding contract.
110 The provision by Mayne to Sagacious of the draft Product Supply Agreement and the letter of intent, and their acceptance by Sagacious as the next steps in coming to a binding contract, conveyed that there was at that point no binding contract. Particularly is that so when the letter of intent was amended at Sagacious' request to state that "this agreement", being an agreement for which the terms and conditions of the draft Product Supply Agreement were to be accepted, was "based on your proposal on 16 April 2002" and the contractual relationship was explicitly subject to execution of a formal contract.
111 Sagacious' submissions included that this was a "parallel proposal for a replacement contract", one which was postponed because of difficulty in drafting, and that the reference to "proposal" was in the circumstances of little moment. I do not think that can be accepted. In the letter of intent the Product Supply Agreement was not treated as the replacement for a currently binding contract found in the April letter.
112 Not until later did Sagacious assert that the April letter represented a binding agreement between Mayne and Sagacious. Other than in the billing and payment consistent with the April letter, it did not in important communications between itself and Mayne treat the April letter as the embodiment of a present contractual relationship. On the contrary, it made the presentation of 25 June 2002 and submitted the discussion paper, proposing a very different contractual relationship to operate from July 2002 and in the discussion paper putting the detailed proposal for the provision of eProcurement services on a management fee basis as the fulfilment of what para I in the Background had said was the negotiation and finalisation of a long-term agreement "[a]s contemplated in the proposal of 16 April 2002". The long-term agreement proposed was not even the terms and conditions of the April letter with refinements - it was quite different.
113 Of course, if a binding contract had been made subsequent negotiations not resulting in a new contract would not affect it: Lemon v Scarlet & Co (1921) 29 CLR 499 at 409, referring to Perry v Suffields Ltd (1916) 2 Ch 187. But on whether a contract had been made, and adopting the words of Griffiths CJ in Barrier Wharfs Ltd v W Scott Fell & Co Ltd, these matters negative the idea of an existing concluded contract.
114 Sagacious submitted that the explanation lay in changed personnel in Mayne, giving Sagacious reason to "tread carefully". The trial judge had said at [56] that "Sagacious being a small start-up company, was very conscious at all times of the huge significance of the Mayne connection to its prospects", and that it "had no desire to raise the litigation gun against Mayne" and "[i]ts approach to contractual/logistic problems was 'softly softly'." However, it is not evident that treading carefully meant failing to assert that there was a binding contract in place.