[2017] VCAT 129
Victorian Civil and Administrative Tribunal
2017-08-25
Mr J
Original judgment source is linked above.
Building and Property List - claims for variation, extension of time, defects, damages for delay and damages for wrongly cashing security - contract AS 2124-1992 - validity of superintendents' certificates - whether superintendent has acted fairly and reasonably within the contract - ability to review superintendents' determinations - reserve powers of superintendent in relation to extension of time - inconsistent clauses in contract.
5, 8, 9, 12, 13, 14, 15, 16, 19, 20, 21, 22 & 23 September 2016 and 4, 5, 7, 10, 11, 13, 14, 17, 18, 19, 20 & 21 October 2016, 15, 16 & 17 May 2017 and 13, 14 & 15 June 2017
Mackie Pty Ltd v Republic of Turkey (Building and Property) [2017] VCAT 129
Mr R. Andrew of Counsel with Mr N.J. Phillpott of Counsel
Contractual and Statutory Matters Concerning Variations
Tectura's vanguard, Mr Baycan, was less than impressive as a witness. He was unwilling to make the most basic and obvious concessions, he was argumentative, evasive, obstructive and from time to time lacked candour...
Mr Baycan kept no records that the VCAT could scrutinize to understand his decision-making process as Superintendent's representative under the Contract.
Mr Baycan assumed that his decisions were final and he took offence to the suggestion that his decision may be exposed to rational objective criticism...
The Superintendent acting honestly, impartially and fairly, ought reasonably have extended the date for Practical Completion.
Mr Forrest stated that the word "honestly" referred to in the quotation above, was an allegation of dishonesty against the architect/superintendent.
The expert opinion referred to in (a) (competence and skill that is usual among architects...at the exercise of due care and skill), is critical as it would establish an appropriate yardstick or measure against which an architect's conduct can be measured. Without the evidence of the conduct of a reasonable and competent architect being established in the Tribunal, the yardstick or measure critical to the cause of action and against which actual conduct the architect is compared is not available.
PRINCIPLES OF REVIEWING SUPERINTENDENT'S DETERMINATIONS
...Unless there is fraud or dishonesty which is well known and long-standing ground for review or setting aside certificates, that has now been abandoned, it is just not open to the Tribunal to conduct what is now being called a 'merits review standing in the shoes of the Superintendent'.
A builder and an owner entered into a standard form contract in December 2004 in relation to certain building works. Disputes arose between the parties over alleged defects in the works, and in September 2006 the owner exercised its rights under the agreement by taking the whole of the remaining work out of the hands of the builder. The owner engaged another builder to complete the works (including rectifications) and to undertake additional works not part of the original scope of works. Clause 44.6 of the agreement relevantly provided as follows:
When work taken out of the hands of the Contractor under Clause 44.4(a) is completed the Superintendent shall ascertain the cost incurred by the Principal in completing the work and shall issue a certificate to the Principal and the Contractor certifying:
(a) the amount of that cost and setting out the calculations employed to arrive at that cost;
(b) the amount which would otherwise have been paid to the Contractor if the work had been completed by the Contractor;
The superintendent relied on the work of a quantity surveyor in certifying that the relevant difference was $4,457.308, payable by the builder to the owner. Dixon J dismissed the builder's claims, which were based on alleged breaches of the agreement, and gave judgment for the owner on its counterclaim for the amount certified by the superintendent, plus interest. The builder appealed against the judgment on the counterclaim on grounds that the superintendent's processes had not complied with the requirements of cl 44.6 of the agreement. The builder's contention was that for the superintendent to "ascertain" the cost to complete the works required the costs incurred to be known with precision, and did not permit an estimate to be arrived at using experience, judgment or discretionary decision-making...
[28] It is clear from the language of this clause that the parties intended by their use of the word "ascertain" to authorise a process of computation which would, where necessary, involve judgment, estimation and approximation. The determination of what might be "reasonable" is, quintessentially, an exercise involving judgment and experience. Moreover, the language of this clause is entirely consistent with the notion of "a reasonable measure or value", which the parties used in cl 23(a) (above) to define how the Superintendent should carry out functions of this kind.
[29] It is to be presumed that the parties intended the word "ascertain" to have the same meaning in cl 44.6. There is nothing in the language or context of cl 44.6 to suggest otherwise. It follows that they intended to authorise the Superintendent, when carrying out the task of "ascertainment" under cl 44.6, to exercise judgment where necessary. What the Superintendent did (in reliance on the work of Mr Clack) was therefore within the scope of the "ascertainment" function conferred on him by cl 44.6. The parties are therefore bound by the Superintendent's certificate. That conclusion is sufficient to dispose of this ground of appeal.
[13] The respondents have adopted an uncritical and mindless application of Dura to apply the Court of Appeal's reasoning in relation to 44.6 of Capital AS 2124-1992 more broadly to all decisions of Tectura concerning claims for extension of time (Clause 35.5) or variations (Clause 40.5) and the disputes concerning the merits of such claims and assessments dealt with by such decisions of the Superintendent are not justiciable by the VCAT.
[18] Ordinarily, in cases of this kind, where a certified valuation is to be made by reference to fixed, objective criteria (such that there is no discretionary element in the valuation) there will only be one uniquely correct value. If the certifying valuer, in these circumstances, arrives at the incorrect value, the valuation will be in breach of the contract. It is for that reason that an incorrect certificate will also be set aside. The court will then have the jurisdiction to hear the merits of the claim, the clause that gives the arbitrator jurisdiction to hear the merits of the claim, the arbitrator will have the same powers as the court...
[35] I think it would be helpful at this stage to summarise the principles applicable to the review of discretionary valuations by a third party. I shall then refer to the authorities from which they are derived.
[36] First, by the contract, the parties agree to be bound by a valuation made in terms thereof. Therefore, if the valuation complies with the contract, they are bound thereby. Because of the discretionary nature of the valuation, the contract will not require the valuation to be "correct". There will indeed be no uniquely correct valuation. The valuation will merely have to be within the terms of the contract.
[37] Secondly, a court will not set aside a valuer's determination merely on the ground that it is "incorrect" or that it reveals errors. The determination will only be interfered with if it is not made in terms of the contract; a mere mistake in the valuation will ordinarily not be a departure from the terms of the contract.
The question is not whether there is an error in the discretionary judgment of the valuer. It is whether the valuation complies with the terms of the contract.
...The contract requires in relation to an extension of time, both that the superintendent's manner of exercise of the functions must be honest and fair and that the product of her deliberations must be reasonable. It follows that even if the superintendent had acted honestly and reasonably, Walton could not be bound by her determination if the determination did not meet the description "reasonable extension of time". That is because, by definition, it would not have got what it was entitled to received.
What is a reasonable extension of time for a particular cause and in a particular situation is a question of fact to be assessed objectively. Likewise, what is a reasonable sum to be allowed for the cost of executing a variation to work is a question of fact to be assessed objectively. That is so in each case notwithstanding that as I accept, reasonable minds acting on a properly informed basis and in a rational way may differ as to what is, in either case, reasonable...
In relation to both extensions of time and the value of variations, the court is able to look at the product of the superintendent's labours to see whether she has arrived at a reasonable extension of time or a reasonable valuation for a variation...If the superintendent did not do so, then she has not performed her task, and Walton has not received its contractual entitlement. [underlining supplied]
Accordingly, I conclude that it is open to the court to look at the challenged assessments (for extensions of time and the value of variations and the like), to determine whether or not they equated to the contractual standard of reasonableness, and to substitute its own determination for what should reasonably have been allowed if they do not...
Reserve Power in relation to Extension of Time
Notwithstanding that the Contractor is not entitled to an extension of time the Superintendent may at any time and from time to time before the issue of the Final Certificate by notice in writing to the Contractor extend the time for Practical Completion for any reason.
I accept that, in the absence of the Superintendent's power to extend time even if a claim had not been made within time, Abigroup would be precluded from the benefit of an extension of time and liable for liquidated damages, even if delay had been caused by variations required by Peninsula and thus within the so-called "prevention principle".
...In my opinion, this power is one capable of being exercised in the interests both of the owner and the builder, and in my opinion the Superintendent is obliged to act honestly and impartially in deciding whether to exercise this power. Of course, if a timely claim has not been made, and the ground on which an extension is claimed is one which is difficult to decide because of the time that has elapsed since the time when the claim should have been made, that may be a ground which the Superintendent can fairly refuse the extension;...
In my opinion also, the power to extend time, including the power to do so even if no claim has been made within time, does not automatically come to an end with the termination of the contract for the builder's breach. Clause 35.6, providing for liquidated damages, expressly operates after the contract has been terminated under cl.44; and in order for it to so operate there must be a date for practical completion on which the clause can operate on which the clause can operate after termination of the contract. If an application had been made within time before termination and not yet determined by the Superintendent at the time of termination, it is plain in my opinion that the Superintendent would have power to determine that claim after termination. If a claim had been made before termination but outside the time provide by cl.35, and the Superintendent had not made a decision in exercise of the Superintendent's power to extend time notwithstanding non-compliance, in my opinion the Superintendent could still do so after termination. In those circumstances, I do not think the Superintendent's power is lost on termination, even if the claim for exercise of the power to extend notwithstanding non-compliance had not been made until after termination.
In my view the Aribtrator was correct in his decision:
(a) The primary mechanism of cl.35.5 gives the contractor an entitlement to an extension of time, subject to compliance with special conditions;
(b) The penultimate paragraph reserves a discretionary power to grant an EOT in other circumstances effectively where it is just and equitable to do so;
(c) Such power is expressly directed to situations where "the contractor is not entitled to or has not claimed an extension of time...";
(d) It is expressed to arise on a separate and distinct basis from the provision for the extension of time pursuant to the primary mechanism;
(e) The grounds for exercise of the reserve power are expressed in the broadest possible terms as "for any reason";
(f) The potential prejudice to the principal flowing from a failure by the contractor to comply with s.35.5 (sic) is a matter going squarely to the equitable exercise of the Arbitrator's discretion.
There is no basis in the objective language of the contract read as a whole to read down these last words by reference to one party alone.
The words are as the Arbitrator observed subject to the obligation of the Superintendent to act "honestly and fairly".
It was open to the parties to modify the contract to give effect to the limitation for which 620 contends, by the use of relatively simple language. They did not do so.
To the contrary, as the Arbitrator observed, the parties adopted a form of condition which emphasised the independence of the Superintendent's discretion, by use of the words "or has not claimed an extension of time".
I commenced the case by saying that the term was merely aspirational and I maintain that position. It is merely an aspiration deposited in the Contract without any clear and evident intention that Mackie would be denied its rights with respect to the recovery of the price for the variation work performed pursuant to the provision that sits below.
Allegation of a 52-Day "Buffer" or "Float" Period
BACKGROUND IN RELATION TO CONSTRUCTION PROGRAMME
Notwithstanding that the contract was not entitled to an extension of time the superintendent may at any time and from time to time before the issue of the Final Certificate by notice in writing to the contractor extend the time for Practical Completion for any reason.
The principal shall ensure that at all times there is a superintendent and that in the exercise of the function of the superintendent over the contract, the superintendent:
(a) Acted impartially, fairly and arrived at a reasonable assessment;
(b) Acts within the time prescribed under the contract or where no time is prescribed within a reasonable time; and
(c) Arrives at a reasonable measure of value of work quantity, quantities or time.
The principal shall ensure that in the exercise of the functions of the superintendent under clause 5.7, 6.2, 8.1, 21.5, 35, 40, 42 of the contract the superintendent acts fairly.
For the purposes of clause 33, a 'construction programme' is a statement in writing showing the dates by which, or the times within which, various stages or parts of the work under the contract are to be executed or completed.
A construction programme should not affect the rights or obligations in clause 33.1.
A contractor may voluntarily furnish to the superintendent a construction programme.
A superintendent may direct the contractor to furnish to the superintendent a construction programme within the time and in the form directed by the superintendent.
The Contractor shall not, without reasonable cause, depart from -
(a) a construction programme included in the contract; or
(b) a construction programme furnished to the superintendent.
The furnishing of a construction programme or of a further construction programme shall not relieve the Contractor of any obligation under the Contract including the obligation to: 'Not, without reasonable cause, depart from an earlier construction programme.'
40.4 Variations for the Convenience of the Contractor
If the contractor requests the superintendent to approve a variation for the convenience of the contractor, the superintendent may do so in writing. The approval may be conditional.
Unless the superintendent otherwise directs in the notice approving the variation, the contractor shall not be entitled to -
(a) An extension of time of practical completion; or
in respect of the variation or anything arising out of the variation which would not have arisen had the variation not been approved.
The superintendent shall not be obliged to approve a variation for the convenience of the contractor.
Where the Contract provides that a valuation shall be made under Clause 40.5, the Principal shall pay or allow the Contractor or the Contractor shall pay or allow the Principal as the case may require, an amount ascertained by the Superintendent as follows -
(a) if the Contract prescribes specific rates or prices to be applied in determining the value, those rates or prices shall be used:
When under Clause 40.3 the Superintendent directs the Contractor to support a variation with measurements and other evidence of cost, the Superintendent shall allow the Contractor the reasonable cost of preparing the measurements or other evidence of cost that has been incurred over and above the reasonable overhead cost.
Andrews considered Mackie's programme were unsuitable for assessing extensions of time claims as they cannot substantiate whether the contractor is or will be delayed in achieving practical completion.
For each delay the baseline programme was updated with recorder progress based on relevant as-built information, rescheduled and subsequently impacted with the delay event; the impact of the delay event on the critical path for the current period and subsequent period was assessed to determine its impact on practical completion. ...
The manner in which the Andrews amended programme was developed is set out in section G1, paragraph 72 of the Andrews report.
Andrews statuses the Andrews amended programme at a number of dates for use in his programme based on as built details extracted from meeting minutes, site photographs and Andrew Frank's diary records. (Andrews at paragraph 6 and Appendix G2 to determine the critical path of the works at the time of each delay considered in his report.)
(Mr Andrews took) the initial programme that was created by Mackie, and is known as the Revision D programme, and developed it into what is described as a baseline programme, and then at a date where an event of delay has been identified he updates the baseline programme and he puts it into information that has been generated from records of doctors (sic) that were produced at the time, and then what he does is to perform his analysis is impact (sic) it with an event to determine whether is that right prevented Mackie from reaching the practical completion.
I have reviewed Mackie's contract programme (construction programme) Rev D04-03-10. I agree with both Degenhart and Andrews that there are deficiencies in this programme and as a result it does not display a critical path.
Because of the constraints of the activities in the programme which are identified and acknowledged by both Degenhart and Andrews, I am not able to identify a critical path from a review of the programme and its current form.
Therefore, I agree with Mr Andrews approach of amending the programme to remove constraints and include logic between activities to create an amended programme determine the critical path of the project.
Andrews Status Programme from 12 April 2010 to 20 December 2010 (ie all Andrews programmes with the exception of the Status Programme of 26 September 2011) are in the period in which the structure is being erected and show the structure is critical.
Therefore the difference in approach in assessing critically does not make the difference between the assessment of Degenhart and Andrews for those delays in 2010 affecting the structure and building envelope (façade and roof). Therefore this is the only a reason for the difference in the respective assessments for the following delays:
Replacement of Sewer Part (EOT18);
Inclement weather delays for September and October 2011 (EOT19); and
Inclement weather delays for November 2011 (EOT20).
I have therefore adopted the statuses of the Andrews Amended Programme as the basis of my analysis for those delays affecting structure, façade and roofing (ie the Andrews Amended Programme Status 12 April 2010 and 20 December 2010).
For those delays occurring in 2011 where Andrews and Degenhart identified different critical paths, as outlined in paragraph 30 above, I discussed the difference in the critical paths in section 3.4 below and my opinion as to the critical path of the works at this stage of the project.
Please ignore previous issues of programme as duration dates are incorrect.
'Works' means the whole of the works to be executed according to the contract, including all variations provided by the contract, which by the contract are to be handed over to the principal.
'Works under the contract' mean the works which the Contract is or may be required to execute under the Contract and includes all variations.
The total sum of all variations shall not exceed 10% in the total contract sum of $4,300,000. (10% variation clause).
(a) Increase, decrease or omit any part of the work under the Contract:
(b) Change character or quality of any material or work:
(c) Change the levels, lines, positions, dimensions of any part of the work under the Contract:
(d) Execute additional work: and/or demolish or remove material or work no longer required by the Principal. The Contractor shall not vary the work of the Contract except as directed by the Superintendent or approved in writing by the Superintendent under clause 40...
If pursuant to a provision of the Contract enabling the Superintendent to give directions, the Superintendent gives a direction, the Contractor shall comply with the direction.
Clause 23 'direction' includes agreement, approval, authorisation, certificate, decision, demand, determination, explanation, instruction, notice, order, permission, rejection, request or requirement except where the Contract otherwise provides, a direction may be given orally but the Superintendent shall as soon as practicable confirm it in writing...
The principal shall ensure that at all times there is a Superintendent and that in the exercise of the function of the Superintendent under the contract, the Superintendent -
(b) acts within the time prescribed under the contract or where no time is prescribed within a reasonable time; and
(c) arrives at a reasonable measure of value of work quantities or time.
The principal shall ensure the exercise of the functions of the Superintendent under clauses 5.7, 6.2, 8.1, 21.5, 35, 40 and 42 of the Contract the Superintendent acts fairly and reasonably.
Variations pursuant to Domestic Buildings Contract Act 1995
38. Variation of plans or specifications - by building owner
(1) A building owner who wishes to vary the plans or
specifications set out in a major domestic building
(2) If the builder reasonably believes the variation
will not require a variation to any permit and will
(b) a notice that states that the builder refuses, or
(5) A builder must not give effect to any variation
(6) A builder is not entitled to recover any money in
(7) If sub-section (6) applies, the builder is entitled to
recover the cost of carrying out the variation plus
(8) This section does not apply to contractual terms
(For convenience, I have attached Annexure "A" to these Reasons which sets out relevant provisions of the Contract).
The correct amount for the variation should have been $68,860 + GST rather than $63,360 + GST.
(a) The price of the work ($22,502.73) plus labour costs for cleaning up the external to the site (8 hours)($60 per hour) totals $22,982.73 add the builder's margin $2298.27 totals $25,281 + GST.
(b) On 2 July 2010 the Superintendent issued a contract variation NI 018 in the sum of $24,753 (ex GST), thus excluding the cost of clean up.
Cleaning up the site is part of the scope of works under the Contract that Mackie was obliged to perform. Page [12] of Part 1 of the Specifications requires Mackie to take full responsibility for ensuring the health, welfare and safety of all persons on, leaving or entering the site at which the works were carried out.
Credit Variation to the Owner in Relationship to Compact and Fill X26D
Variation X41D Increased Price of Structural Steel
The question is - was the superintendent required to approve shop drawings within a reasonable period? If so, did the superintendent do so? If so, can Mackie recover the cost of the increased steel as it was not permitted to commence the work until the drawings were approved and the cost of the steel increased within the period approval was delayed.
The contractor shall not stockpile, manufacture, assemble or supply anything affected by the shop drawings until he has obtained copies of the drawings endorsed with the approval of the engineer.
Allow for all work, including minor and ancillary work, to ensure no omissions of necessary work and allow for appropriate interfaces between the various trades, as necessary, for the complete and satisfactory installation, commissioning, operation and maintenance of the services in accordance with the intent of the drawings and the Specifications.
The architectural drawings show the services required and are intended to depict the installation in a diagram and/or schematic manner.
The Contract Core shall allow for the complete design, supply and installation.
When an item system or any aspect of the services is not indicated on the drawings and/or included in the Specification, but is obviously required, provide such work within the Contract sum.
Lodge all necessary applications to authorities and pay all fees and charges.
The work shall include, but not be limited to the design, supply, installation and commissioning of the following...(see 3831 of TB).
Installation of additional sewer for pool backwash and AC units for which the builder has claimed $2,040 + margin + GST.
This claim has been rejected by the superintendent.
The architectural drawings show the services requirements and are intended to depict the installation in a diagrammatic and/or schematic manner.
The contractors shall allow for completed design, supply and installation.
Where an item, system or any aspect of the services are not indicated on the drawings and/or included in the specifications, but it is obviously required, provide such works within the contract sum...
The works shall include but not be limited to the design, supply, installation and commissioning of the following... (hydraulic services are included).
Stating the obvious, the words of a Contact are to be construed purposefully and commercially. The words of the Specifications themselves do not impose an obligation to design, and are expressed as an 'allowance' meaning that Mackie should in its price allow for the whole of the works as designed.
Tectura undertook the whole of the design including drawings, a specification and equipment lists...
The design obligation defence belatedly arose in order to deny Mackie an entitlement to be paid for extra work.
Variation X077D Claim for Increased Cost of Supplying and Labour Relating to Stonework for the Building
If contract includes selected Sub-contract Work, the Contractor shall Sub-contract the Selected Sub-contract Work to a Selected Sub-Contractor. If the tender documents specify the terms and conditions upon which the Sub-contract is to be entered into, the Sub-contract shall include those terms and conditions.
(a) provide services described in this agreement with the skill and professionalism of a reasonably competent architect (see [TB4492] Clause J(A)).
Within 28 days after the expiration of the defects liability period, or where there is more than one, the last to expire, the contractors shall lodge with the superintendent a final payment claim and endorse it 'final payment claim... after the expiration of the period for lodging a final payment claim, any claim which the contractor could have made against the principal, and has not been made shall be barred.'
The evidence of this conversation (at the meeting of 26 November 2009) and the note from Mr Gebbie is parole evidence, and it is not admissible to contract him. Further these negotiations reflect the subjective intent of the parties and do not provide the matrix of facts against which the contract is to be construed.
The angle brackets were supplied because Mackie had failed to manufacture the external panels for the roof with cast in plates as originally drawn or in accordance with the alternative design as it had been requested in its email correspondence in October 2010...
Variation X119D Three Flues to the Basement for Hot Water Service
Variation X139D (Angle Brackets for Suspended Slab)
Variation X140D Stone Cladding to the Wall around the Reflection Pool
(e) The builder engaged Fota Constructions Pty Ltd for the sub-contract sum of $301,760 (TB2443);
(f) When the builder substituted the Reckli moulds with the form moulds it enquired from Chris Fota of Fota Constructions as to whether there was a cost saving. Christ Fota advised Terry Cross, from the builder, that there was no cost saving (TB2405).
(g) The builder relies on an email dated 16 September 2010 from Chris Fota of Fota Constructions Pty Ltd to Terry Cross - no cost saving replacing Reckli 'Columbia' Mould (TB2405).
Discussions between Ben De Clemente and John Joveski from Rekkli on 29/1/2014:
John advised 'foam' lines cost 30% of the price of Rekkli Rubber Moulds
John advised 'Columbia' cost $1,160/m2 today cost $900 in 2011
Within 28 days after the expiration of the defects liability period, where there is more than one, the last to expire the Contractor shall lodge with the Superintendent a final payment claim and endorse it 'final payment claim'.
Delays to Demolition and Excavation and Foundation Works EOT 13, EOT 4 & EOT 14)
(a) On 8 September 2010 the Superintendent provided revised structural drawings to the precast lift panels showing revised reinforcing details;
(b) Shop Drawings for Lift Panels LP1 to LP5 Revision 0 were submitted for review on 17 September 2010 and approved under SI 53 on 24 September 2010;
(c) Shop Drawings for Lift Panels LP1 and LP4 Revision 1 showing cast in plates for connections to the structural steel at Levels 1 and 2 were approved on 27 September 2010 under SI 55;
(d) External Precast Panels to the back of the lift and dumb waiter, PT51 and PT53 were approved on 27 September 2010 under SI 55, but the colour of the panels was not approved at this time, or by the time the lift panels were erected on about 26 and 27 October 2010;
The superintendent laid the design for the change of the Lift shaft and dumbwaiter to in situ concrete construction in lieu from precast concrete;
The superintendent delayed completing its design of the panels, including provision for rebates to the panels, window size etc; and
The superintendent delayed in the design of the "Colombia" panels form work.
The lift and dumbwaiter shafts at basement level were changed to in situ concrete in lieu of precast concrete at the specific request of the contractor construction sequences purposes, as the letting of the precast subcontract was late (see EOT No. 6TB4882).
(g) The contracts for the preparation of shop drawings and the manufacture of the panels were not finalised by the builder until late May/June 2010.
(h) An email from the builder to the engineer (Mr Spencer), for his approval referred to a design change of 1 July 2010. Approval was given indicating that it will require a change to precast panel connections which will incur additional design fee to builder.
(i) Thereafter a new design was produced on 3 August 2010 (not on 8 December 2010 as Mr Watson has stated in his report).
(j) Mr Baycan and Mr Spencer gave evidence that the new engineering design was limited to provide reinforced concrete in situ walls in the basement only, terminating at the ground floor. However, it is noted, that necessarily the design provided for new connection details of the in situ walls with the reinforced concrete panels which would have been installed at ground floor level of the building for the lift and dumbwaiter.
(k) Apart from Mr Mackie suggesting that the design of the walls for the lift and dumbwaiter in the basement was inadequate and caused the design change, no other evidence was led in this regard.
During cross examination by Counsel for Mackie, Mr Baycan made baseless allegations concerning, the incompetence of the panel detailer. Mr Baycan alleged that the reasons for the request from the panel detailer was a 'simple case of them not understanding the requirements'(transcript 1840).
This allegation was made despite the fact revised drawings were subsequently required from the structural engineer in response to the panel detailer's requests.
Further, despite the fact both the steel detailer and the panel detailer required clarification on this connection detail, and the engineer provided revised engineering drawings in response to these requests, Tectura alleged that the need for clarification regarding the connection detail was due to the detailers lack of experience (TB2328.28 at [26])
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any of the events referred to in Clause 35.5 above, the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any other event for which payment of extra costs for delay or disruption is provided for in the Annexure or elsewhere in the Contract, the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
(a) Oblige the Principal to pay extra costs for delay or disruption which have already been included in the value of a variation or any other payment under the Contract; or
(b) Limit the Principal's liability for damages for breach of contract.
For the purpose of clause 36, an event referred to in clause 35.5(b)(i) shall be an event which relates solely to the contract.
The Contractor shall be entitled to any payment from the Principal (other than payment which may become due by reason of other provisions of the Contract), including payment by way of damages for breach of contract or other obligations whether payment relates to any delay or disruption which the contractor may have encountered, irrespective of the cause of the delay or disruption, and including delay or disruption caused by the events referred in clause 35.5(b)(i) or clause 35.5(b)(x).
(I have attached Annexure "B" to the Reasons setting out a relevant chronology).
Of the 190 defects on S1244, sixty-seven (67) were accepted by the architect leaving 128 outstanding defects.
Tab (TB0385) of this expert report shows that the outstanding 128 alleged listed defects, 78 defects have been rectified, leaving a balance of 50 defects. In my opinion, most of the remaining defects are minor.
The most significant defects in dispute in my opinion is the reflection pool and the planter boxes outside the front entry. The reflection pool and planter box structures have been varied from the original contract words. The Republic of Turkey ('owners') have also altered the reflection pool structures since the builder ceased work, and it is no longer resembles either the plan or the contract variation. Notwithstanding, the defect is simple to rectify. Further while the defect is the most significant defect in dispute, it is not significant in terms of rectification procedure(s).
My calculations reveal that the total cost to rectify the defective work irrespective of whether or not it is the builder's responsibility is $25,000 including profits and GST.
The cost quotation obtained on behalf of the owners to rectify the alleged defective works are in part conditionalized, inaccurate, undefined, and do not cost each of the individual items listed in SI 244. In my opinion, there is no basis to rely on the costs contained on the various quotations.
(d) Paint cracking in the door jambs and architraves;
(n) Membrane to the planter boxes and the reflection pool.
If the superintendent discovers material or work provided by the Contractor which is not in accordance with the Contract, the Superintendent may direct the contractor to...
(c) Reconstruct, replace or correct material or work...
The superintendent may direct the times within which the contractor must commence and complete the removal, demolition, replacement or correction.
If the contractor fails to comply with the direction issued by the superintendent, pursuant to clause 30.3 within the time specified by the superintendent, in the direction provided and the superintendent has given the contractor notice in writing after the expiry of the seven days from which the contractor receives the notice the principal intends to have the work carried out by other persons, the principal may have the work of removal, demolition, replacement or correction carried out by other persons at the cost incurred by the principal if the works are carried out shall be a debt due from the contractor to the principal.
At any time prior to the 14th day after the expiration of the Defects Liability Period, the Superintendent may direct the Contractor to rectify any omission or defect in the work under the Contract existing at the Date of Practical Completion or which becomes apparent prior to the expiration of the Defects Liability Period. The direction shall identify the omission or defect and state a date by which the Contractor shall complete the work of rectification and may state a date by which the work of rectification shall commence...
If the work of rectification is not commenced or completed by the stated dates, the Principal may have the work of rectification carried out at the Contractor's expense, but without prejudice to any other rights that the Principal may have against the Contractor with respect to such omission or defect and the cost of the work of rectification incurred by the Principal shall be a debt due from the Contractor.
Each of the superintendent instructions issued to Mackie during the defect liability period was a direction in accordance with clause 37 of the contract. Such directions required Tectura to make discretionary assessments using its judgement and experience. As such, the parties by entering into the contract agreed to be bound by the directions and instructions issued by Tectura in accordance with the contract, without review or challenge. In the circumstances, Techtura's Superintendent's Instructions relating to defective work are unable to be challenged and reagitated in this proceeding. To this extent the evidence of Mr George Cross (the expert employed by the builder who made a report and gave oral evidence) is of little to no utility in this proceeding. Further Mr Cross in his evidence does not cost many of the items. Where he does do so, that is merely his opinion. The actual cost paid by the Republic are what is relevant.
Of the 50 remaining defects, Mr Cross categorised those as minor.
There is, in my view, no room for a wider common law right in the Proprietor to treat non-compliance with the contractual obligation with the Builder as a separate basis for claiming damages being the cost of having a third party rectifying or completing defective or omitted works. This is because the contract specifies and confirms upon the Proprietor its right flowing from such breach; that is, the parties have, by contract agreed upon the consequences for each of the Proprietor and the Builder, both as to rights and powers flowing from and the consequences of, such breach... It also follows, in my view, that the Proprietor has no entitlement to recover the costs of works performed by others at the request of the Proprietor unless prior to such work being performed the Architect has given the notice required by cl 5.06.1 prior to the date of practical completion or pursuant to cl 5.06.01 as incorporated by cl 6.11.05 after the date of practical completion.
If on the proper construction of the contract as a whole, it can be said that a party has surrendered its common law rights to damages, that construction must be given effect to, notwithstanding the absence of express words to render the common law right to damages.
Total allowance to builder for extension of time:
DAMAGES FOR WRONGLY CASHING SECURITY RELATING TO DEFECTS
Reimbursement to owner by architect superintendent
Total amount to be reimbursed by Architect/ Superintendent to owner
The Principal shall ensure that at all times there is a Superintendent and that in the exercise of the functions of the Superintendent under the Contract, the Superintendent -
(b) acts within the time prescribed under the Contract or where no time is prescribed, within a reasonable time; and
(c) arrives at a reasonable measure or value of work, quantities or time.
If, pursuant to a provision of the Contract enabling the Superintendent to give directions, the Superintendent gives a direction, the Contractor shall comply with the direction.
In Clause 23 'direction' includes agreement, approval, authorization, certificate, decision, demand, determination, explanation, instruction, notice, order, permission, rejection, request or requirement.
Except where the Contract otherwise provides, a direction may be given orally but the Superintendent shall as soon as practicable confirm it in writing.
If the Contractor in writing requests the Superintendent to confirm an oral direction, the Contractor shall not be bound to comply with the direction until the Superintendent confirms it in writing.
For the purposes of Clause 33, a 'construction program' is a statement in writing showing the dates by which, or the times within which, the various stages or parts of the work under the Contract are to be executed or completed.
A construction program shall not affect rights or obligations in Clause 33.1.
The Contractor may voluntarily furnish to the Superintendent a construction program.
The superintendent may direct the Contractor to furnish to the Superintendent a construction program with the time and in the form directed by the Superintendent.
The Contractor shall not, without reasonable cause, depart from -
(a) a construction program included in the Contract; or
(b) a construction program furnished to the Superintendent.
The furnishing of a construction program or of a further construction program shall not relieve the Contractor of any obligations under the Contract including the obligation to not, without reasonable cause, depart from an earlier construction program.
If the Superintendent considers that the suspension of the whole or part of the work under the Contract is necessary -
(i) the Principal, the Superintendent or an employee, consultant or agent of the Principal; or
(ii) the Contractor, a subcontractor or an employee or agent of either;
(b) for the protection or safety of any person or property; or
The Superintendent shall direct the Contractor to suspend the progress of the whole or or part of the work under the Contract for such time as the Superintendent thinks fit.
If the Contractor wishes to suspend the whole or part of the work under the Contract, otherwise than under Clause 44.9, the Contractor shall obtain the prior written approval of the Superintendent. The Superintendent may approve of the suspension and may impose conditions of approval.
As soon as the Superintendent becomes aware that the reason for any suspension no longer exists, the Superintendent shall direct the Contractor to recommence work on the whole or on the relevant part of the work under the Contract.
If work is suspended pursuant to Clause 34.2 or 44.9, the Contractor may recommence work at any time after reasonable advance notice to the Superintendent.
Any cost incurred by the Contractor by reason of a suspension under Clause 34.1 or Clause 34.2 shall be borne by the Contractor but if the suspension is due to an act or omission of the Principal, the Superintendent or an employee, consultant or agent of the Principal and the suspension causes the Contractor to incur more or less cost than otherwise would have been incurred but for the suspension, the difference shall be valued under Clause 40.5.
Suspension shall not affect the Date for Practical Completion but the cause of suspension may be a ground for extension of time under Clause 35.5.
**_35 TIMES FOR COMMENCEMENT AND PRACTICAL COMPLETION
The Contractor shall give the Superintendent 7 days' notice of the date upon which the Contractor proposes to commence work on the Site.
The Superintendent may reduce the period of notice required.
The Contractor shall commence work on the Site within 14 days after the Principal has given the Contractor possession of sufficient of the Site to enable the Contractor to commence work.
The Contractor shall execute the work under the Contract to Practical Completion by the Date for Practical Completion.
Upon the date of Practical Completion the Contractor shall give possession of the Site and the Works to the Principal.
and Clauses 5, 7, 16, 35, 37, 38, 42.3 and 42.5 shall apply separately to each Separable Portion and references therein to the Works and to work under the Contract shall mean so much of the Works and the work under the Contract as is comprised in the relevant Separable Portion.
If the Contract does not make provision for the amount of security, retention moneys, liquidated damages or bonus applicable to a Separable Portion, the respective amounts applicable shall be such proportion of the security, retention moneys, liquidated damages or bonus applicable to the whole of the work under the Contract as the value of the Separable Portion bears to the value of the whole of the work under the Contract.
If a part of the Works has reached a stage equivalent to that of Practical Completion but another part of the Works has not reached such a stage and the parties cannot agree upon the creation of Separable Portions, the Superintendent may determine that the respective parts shall be Separable Portions.
In using the Separable Portion that has reached Practical Completion, the Principal shall not hinder the Contractor in the performance of the work under the Contract.
35.5 Extension of Time for Practical Completion
When it becomes evident to the Contractor that anything, including an act or omission of the Principal, the Superintendent or the Principal's employees, consultants, other contractors or agents, may delay the work under the Contract, the Contractor shall promptly notify the Superintendent in writing with details of the possible delay and the cause.
When it becomes evident to the Principal that anything which the Principal is obliged to do or provide under the Contract may be delayed, the Principal shall give notice to the Superintendent who shall notify the Contractor in writing of the extent of the likely delay.
If the Contractor is or will be delayed in reaching Practical Completion by a cause described in the next paragraph and within 28 days after the delay occurs the Contractor gives the Superintendent a written claim for an extension of time for Practical Completion setting out the facts on which the claim is based, the Contractor shall be entitled to an extension of time for Practical Completion.
(a) events occurring on or before the Date for Practical Completion which are beyond the reasonable control of the Contractor including but not limited to -
(b) any of the following events whether occurring before, on or after the Date for Practical Completion -
- delays caused by -
- - the Principal;
- - the Superintendent;
- - the Principal's employees, consultants, other contractors or agents;
- actual quantities of work being greater than the quantities in the Bill of Quantities or the quantities determined by reference to the upper limit of accuracy stated in the Annexure (otherwise than by reason of a variation directed under Clause 40);
- latent conditions;
- variations directed under Clause 40;
- repudiation or abandonment by a Nominated Subcontractor;
- changes in the law;
- directions by municipal, public or statutory authorities but not where the direction arose from the failure of the Contractor to comply with a requirement referred to in Clause 14.1;
- delays by municipal, public or statutory authorities not caused by the Contractor;
- claims referred to in Clause 17.1(v);
- any breach of the Contract by the Principal;
- any other cause which is expressly stated in the Contract to be a cause for extension of time for Practical Completion.
Where more than one event causes concurrent delays and the cause of at least one of those events, but not all of them, is not a cause referred to in the preceding paragraph, then to the extent that the delays are concurrent, the Contractor shall not be entitled to an extension of time for Practical Completion.
In determining whether the Contractor is or will be delayed in reaching Practical Completion regard shall not be had to -
whether the Contractor can reach Practical Completion by the Date for Practical Completion without an extension of time;
whether the Contractor can, by committing extra resources or incurring extra expenditure, make up the time lost.
With any claim for an extension of time for Practical Completion, or as soon as practicable thereafter, the Contractor shall give the Superintendent written notice of the number of days extension claimed.
If the Contractor is entitled to an extension of time for Practical Completion the Superintendent shall, within 28 days after receipt of the notice of the number of days extension claimed, grant a reasonable extension of time. If within the 28 days the Superintendent does not grant the full extension of time claimed, the Superintendent shall before the expiration of the 28 days give the Contractor notice in writing of the reason.
In determining a reasonable extension of time for an event causing delay, the Superintendent shall have regard to whether the Contractor has taken all reasonable steps to preclude the occurrence of the cause and minimise the consequences of the delay.
Notwithstanding that the Contractor is not entitled to an extension of time the Superintendent may at any time and from time to time before the issue of the Final Certificate by notice in writing to the Contractor extend the time for Practical Completion for any reason.
A delay by the Principal or the failure of the Superintendent to grant a reasonable extension of time or to grant an extension of time within 28 days shall not cause the Date for practical Completion to be set at large but nothing in this paragraph shall prejudice any right of the Contractor to damages.
35.6 Liquidated Damages for Delay in Reaching Practical Completion
If the Contractor fails to reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal for liquidated damages at the rate stated in the Annexure for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated under Clause 44, whichever first occurs.
If after the Contractor has paid or the Principal has deducted liquidated damages, the time for Practical Completion is extended, the Principal shall forthwith repay to the Contractor any liquidated damages paid or deducted in respect of the period up to and including the new Date for Practical Completion.
The Contractor's liability under Clause 35.6 is limited to the amount stated in the Annexure.
If the Date of Practical Completion is earlier than the Date for Practical Completion the Principal shall pay the Contractor the bonus stated in the Annexure for every day after the Date of Practical Completion and including the Date for Practical Completion.
The total of the bonus shall not exceed the limited stated in the Annexure.
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any of the events referred to in Clause 35.5 above, the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any other event for which payment of extra costs for delay or disruption is provided for in the Annexure or elsewhere in the Contract, the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
(a) Oblige the Principal to pay extra costs for delay or disruption which have already been included in the value of a variation or any other payment under the Contract; or
(b) Limit the Principal's liability for damages for breach of contract.
The Defects Liability Period stated in the Annexure shall commence on the Date of Practical Completion.
As soon as possible after the Date of Practical Completion, the Contractor shall rectify any defects or omissions in the work under the Contract existing at Practical Completion.
At any time prior to the 14th day after the expiration of the Defects Liability Period, the Superintendent may direct the Contractor to rectify any omission or defect in the work under the Contract existing at the Date of Practical Completion or which becomes apparent prior to the expiration of the Defects Liability Period. The direction shall identify the omission or defect and state a date by which the Contractor shall complete the work of rectification and may state a date by which the work of rectification shall commence. The direction may provide that in respect of the work of rectification there shall be a separate Defects Liability Period of a stated duration not exceeding the period stated in the Annexure. The separate Defects Liability Period shall commence on the date the Contractor completes the work of rectification. Clause 37 shall apply in respect of the work of rectification and the Defects Liability Period for that work of rectification.
If the work of rectification is not commenced or completed by the stated dates, the Principal may have the work of rectification carried out at the Contractor's expense, but without prejudice to any other rights that the Principal may have against the Contractor with respect to such omission or defect and the cost of the work of rectification incurred by the Principal shall be a debt due from the Contractor.
If it is necessary for the Contractor to carry out work of rectification, the Contractor shall do so at times and in a manner which cause as little inconvenience to the occupants or users of the Works as is reasonably possible.
The Contractor shall keep the Site and the work clean and tidy. The Contractor shall regularly remove rubbish and surplus material.
Within 14 days after the Date of Practical Completion the Contractor shall remove Temporary Works and Constructional Plant.
The Superintendent may extend the time for removal of Temporary Works or Constructional Plant necessary to enable the Contractor to perform remaining obligations.
(a) increase, decrease or omit any part of the work under the Contract;
(b) change the character or quality of any material or work;
(c) change the levels, lines, positions or dimensions of any part of the work under the Contract;
(d) execute additional work; and/or
(e) demolish or remove material or work no longer required by the Principal.
The Contractor shall not vary the work under the Contract except as directed by the Superintendent or approved in writing by the Superintendent under Clause 40.
The Contractor is bound only to execute a variation which is within the general scope of the Contract.
The Contractor shall not be bound to execute a variation directed after Practical Completion unless the variation is in respect of rectification work referred to in Clause 37.
The total sum of all Variations shall not exceed 10% of the total Contract sum of $4,300,000 + GST.
Unless the Superintendent and the Contractor agree upon the price for a variation, the variation directed or approved by the Superintendent under Clause 40.1 shall be valued under Clause 40.5.
The Superintendent may direct the Contractor to provide a detailed quotation for the work of a variation supported by measurements or other evidence of cost.
40.4 Variations for the Convenience of the Contractor
If the Contractor requests the Superintendent to approve a variation for the convenience of the Contractor, the Superintendent may do so in writing. The approval may be conditional.
Unless the Superintendent otherwise directs in the notice approving the variation, the Contractor shall not be entitled to -
(a) an extension of time for Practical Completion; or
(b) extra payment,
in respect of the variation or anything arising out of the variation which would not have arisen had the variation not been approved.
The Superintendent shall not be obliged to approve a variation for the convenience of the Contractor.
Where the Contract provides that a valuation shall be made under Clause 40.5, the Principal shall pay or allow the Contractor or the Contractor shall pay or allow the Principal as the case may require, an amount ascertained by the Superintendent as follows -
(a) if the Contract prescribes specific rates or prices to be applied in determining the value, those rates or prices shall be used:
- if Clause 40.5(a) does not apply, the rates or prices in a Priced Bill of Quantities or Schedule or Rates shall be used to the extent that it is reasonable to use them;
- to the extent that neither Clause 40.5(a) or 40.5(b) apply, reasonable rates or prices shall be used in any valuation made by the Superintendent;
- in determining the deduction to be made for work which is taken out of the Contract, the deduction shall include a reasonable amount for profit and overheads;
- if the valuation is of an increase or decrease in a fee or charge or is a new fee or charge under Clause 14.3, the value shall be the actual increase or decrease or the actual amount of the new fee or charge without regard to overheads or profit;
- if the valuation relates to extra costs incurred by the Contractor for delay or disruption, the valuation shall include a reasonable amount for overheads but shall not include profit or loss of profit;
- if Clause 11(b) applies, the percentage referred to in Clause 11(b) shall be used for valuing the Contractor's profit and attendance; and
- daywork shall be valued in accordance with Clause 41.
When under Clause 40.3 the Superintendent directs the Contractor to support a variation with measurements and other evidence of cost, the Superintendent shall allow the Contractor the reasonable cost of preparing the measurements or other evidence of cost that has been incurred over and above the reasonable overhead cost.
44.6 Adjustment on Completion of the Work Taken Out of the Hands of the Contractor
When work taken out of the hands of the Contractor under Clause 44.4(a) is completed the Superintendent shall ascertain the cost incurred by the Principal in completing the work and shall issue a certificate to the Principal and the Contractor certifying the amount of that cost.
If the cost incurred by the Principal is greater than the amount which would have been paid to the Contractor if the work had been completed by the Contractor, the difference shall be a debt due from the Contractor to the Principal. If the cost incurred by the Principal is less than the amount that would have been paid to the Contractor if the work had been completed by the Contractor, the difference shall be a debt due to the Contractor from the Principal. The Principal shall keep records of the cost in a similar manner to that prescribed in Clause 41.
If the Contractor is indebted to the Principal, the Principal may retain Constructional Plant or other things taken under Clause 44.5 until the debt is satisfied. If after reasonable notice, the Contractor fails to pay the debt, the Principal may sell the Constructional Plant or other things and apply the proceeds to the satisfaction of the debt and the costs of sale. Any excess shall be paid to the Contractor.
(d) Minutes of Site Meeting No 7 [TB3293-3294] recorded at Item 7.8.7 that
"Change lift shaft and dumb waiter walls in basement to in situ concrete in lieu of pre-cast panels";
(e) On 6 July 2010 Mackie submitted precast panel shop drawings (see SI 57 dated 4 October 2010) [TB3341];
(f) On 15 July 2010 Mackie submitted preliminary precast panel shop drawings;
(g) On 3 August 2010 the Superintendent issued SI 36 with the attached revised Drawings M08504-S02/2, M08504-S04/2, M08504-S09/3 and M08504-S10/2 in relation to the lift shaft walls and provided details of the insitu lift shaft walls at basement level [TB3295-3300];
(h) On 3 August 2010 the Superintendent issued SI 37 referring to a review of precast panel samples on 4 August 2010 and advising that the panels were not approved [TB3301-3314];
(i) On 16 August 2010 the Superintendent issued SI 40 [TB3315-3317]:
(i) Providing a response to Mackie's precast shop detailer) RFI No 4 dated 9 July 2010 which:
(1) Advised that details of chamfer to the corner of Panel Nos PT36 and PT37 were in accordance with revised Construction Detail Drawing No PCA-CD-13-13 /2;
(2) Attached revised Drawing Nos PCA-CD-07-01/7, PCA-CD-07-02/4 and PCA-CD-07-03/4 in which the location of air vents were detailed, and a note was added relating to 110mm allowance for floor finish depth; and
(ii) Confirmed discussions with Fota Constructions (Mackie's precast concrete fabricator) on 16 August 2010 that:
(1) The specified Abilox "Almond" colour sample was to be prepared with grey cement in lieu of the off-white cement for review at an inspection on 20 August 2010; and
(2) The specified Abilox "Almond" colour sample was to be prepared with grey cement in lieu of the off-white cement for review at an inspection on 20 August 2010;
(j) On 17 August 2010 the Superintendent issued SI 41 [TB3318-3319] and confirmed the Superintendent's telephone discussion with Fota Construction on 17 August 2010 regarding revisions to the colours for the Specified Precast Panels as follows:
(i) Specified Wall Finish Type 1 - Provide Abilox "Muscatel" dose rate 8.3% in grey cement in lieu of specified Abilox "Almond" colour;
(ii) Specified Wall Finish Type 2 - Provide Abilox "Cinnamon Buff dose rate 8.3% in grey cement in lieu of the specified Abilox "Riverblend Beige" colour;
(iii) Specified Wall Finish Type 3 - Provide Abilox "Glo Peach" does rate 8.3% in grey cement in lieu of the specified Abilox "Riverblend Beige" colour;
(iv) Specified Wall Finish Type 4 - Provide Abilox "Muscatel" does rate 8.3% in grey cement in lieu of the specified Abilox "Almond" colour;
(k) On 1 September 2010 the Superintendent issued SI 45 [TB3320] referring to Precast Panel Inspections held on 26 August 2010 and 31 August 2010 and confirmed that:
(i) Specified Wall Finish Type 1 - Sample panel with Abilox "Muscatel" dose rate 8.3% in grey cement was approved;
(ii) Specified Wall Finish Type 4 - Sample panel with Abilox "Muscatel" does rate 8.3% in grey cement was approved;
(iii) Specified Wall Finish Type 2 and Type 3 - The final colour selection would be further reviewed and inspected following the polishing of the raised section of Wall Finish Type 2 with Abilox "Cinnamon Buff" dose rate 8.3% in grey cement as polishing had not occurred at the time of the inspection;
(l) Email from Mackie to Tectura dated 8 September 2010 requested confirmation from the structural engineer that there were no amendments to reinforcement details for the lift panels shown on Section 2 of Drawing M08504-S09/4 with the offset to the lift door;
(m) Email from Tectura to Mackie dated 8 September 2010 [TB3321-3322] responded to Mackie email dated 8 September 2010 and attached revised structural drawings M08504-S09/6 and M08504-S11/4 indicating the reinforcing requirements for Lift Panels PC 2;
(n) On 13 September 2010 the Superintendent issued SI 49 attaching revised Drawing Nos PCA-CD-13-09/5, PCA-CD-13-10/4 and Sketch SK1 dated 13 September 2010 in relation to the finish to Precast panels PT34, PT35, PT40, PT41[TB3327];
(o) On 15 September 2010 the Superintendent issued SI 51 [TB3328] referring to Precast Panel Inspections of 26 August 2010, 31 August 2010 and 10 September 2010 and confirmed that:
(i) Specified Wall Finish Type 2 - Sample panel with Abilox "Cinnamon Buff" dose rate 8.3% in grey cement was approved; and
(ii) Specified Wall Finish Type 3 - Sample panel with Abilox "Cinnamon Buff" dose rate 8.3% in grey cement was approved;
(p) On 21 September 2010 the Superintendent issued SI 52 [TB3329] attaching revised Drawing No M08504-S07/4 in relation to the beam at the Roof and External Wall intersection;
(q) On 24 September 2010 the Superintendent issued S 53 [TB3330-3337] attaching revised Drawing No M08504-S07/5 and revised the beam at the Roof and External Wall intersection and attached Consultant's Advice Notice No 23 which approved subject to comments the Lift Panel Shop Drawings LP1-LP5 Revision 0 stamped as received by Brown on 17 September 2010;
(r) On 27 September 2010 the Superintendent issued SI 54 [TB3338] referring to SI 45 dated 1 September 2010 and Mackie Variation Request XO43 dated 22 September 2010 advising of cost for the colour change, and requested 2 samples be provided of:
(i) Specified Wall Finish Type 4 - Abilox "Black CAF-X2" dose rate 2.78% in off-shite cement in lieu of the nominated Abilox "Muscatel" colour dose rate 8.3% in grey cement; and
(ii) Specified Wall Finish Type 4 - Abilox "Black CAF-X2" does rate 2.78% in off-white cement at 60% strength in lieu of the nominated Abilox "Muscatel" colour dose rate 8.3% in grey cement;
(s) On 27 September 2010 the Superintendent issued SI 55 [TB3339]:
(i) Referring to Consultant's Advice Notice No 24 from Brown & Tomkinson dated 24 September 2010 and Lift Panel Shop Drawings LP3 Revision 1 and LP4 Revision 1 from Brown & Tomkinson which were approved subject to comments; and
(ii) Providing approval of Precast Panels PT51 and PT53 shop drawings issued 22 September 2010 subject to comments;
(t) On 1 October 2010 the Superintendent issued SI 56 [TB3340] referring to Precast Sample Panel inspections on 4 August 2010, 26 August 2010, 31 August 2010, 10 September 2010 and 1 October 2010 and confirmed that:
(i) Specified Wall Finish Type 1 - Abilox "Almond" dose rate 4.15% in off- white cement as approved at the sample panel inspection on 1 October 2010;
(ii) Specified Wall Finish Type 4 - Abilox "Almond" dose rate 4.15% in off- white cement as approved at the sample panel inspection on 1 October 2010;
(iii) Specified Wall Finish Type 2 - Sample panel with Abilox "Cinnamon Buff" does rate 8.3% in grey cement was approved; and
(iv) Specified Wall Finish Type 3 - Sample panel with Abilox "Cinnamon Buff" does rate 8.3% in grey cement was approved
(u) On 4 October 2010 the Superintendent issued SI 57 [TB3341] regarding Revisions to Precast Concrete Panels following inspection of the Formwork on 5 October 2010 attached mark-up of the Precast Panel Shop Drawings received on 6 July 2010, including:
(i) Provision of a 150mm high rebate to the base of precast panels that extend to Ground Floor Level;
(ii) Set out of Precast Wall Finish Type 3 from top of 150mm rebate;
(v) On 19 October 2010 the Superintendent issued SI 58 [TB3342] regarding Revisions to Precast Concrete Panels in relation to window heights:
(i) Attached revised Drawings PCA-CD-07-02/5 and PCA-CD-07-03/5;
(ii) Revised Panels PT34, PT35, PT36, PT37, PT38, PT39, PT40, PT41, PT16, PT28 to suit location of downpipe;
(iii) Panel PT07 vent location relocated (confirmation of email dated 22 September 2010);
(iv) Panels PT1, PT4, PT13, PT16, PT17, PT18, PT32, PT49, PT55 window openings revised;
(v) Panel Shop Drawings approved subject to comments for PT33, PT36, PT37, PT38, PT39, PT40, PT41, PT43;
(w) On 19 October 2010 the Superintendent issued SI 59 [TB3343-3345] advising Mackie that Precast Panels PT51 and PT53 shop drawings were approved subject to comments;
(x) On 21 October 2010 the Superintendent issued SI 60 [TB3346]regarding "Review of Precast Panel 200 x 200 Grid Pattern as received by email dated 20 October 2010" required corrections to be made to 2 Precast Panel Shop Drawings for PT31, PT32, PT33, PT43, PT44, PT45, PT46;
(y) On 22 October 2010 the Superintendent issued SI 61 [TB3347]regarding "Review of Precast Panel Shop Drawings as Received via Email from Weitons (stamped received on 19 October 2010)" and advised that corrections were to be made to PT01, PT02, PT04, PT07, PT08, PT11 to PT18, PT20 to PT 22, PT25 to PT32, PT38, PT39, PT45 to PT47, PT49, PT51, PT53, PT55, PT59;
(z) On 3 November 2010 the Superintendent issued SI 63 [TB3348-3349] regarding "Response to Query via Email from Terry Cross dated 28 October 2010 - Cast in Plates on Top of Precast Panels" attached Consultant's Advice Notice No 31 and Sketch SK1 which showed the connection detail for Precast Panels to Roof Beam RB4 as 1-M20 Bolt in Precast Panel Ferrule, minimum 3 per panel;
(aa) On 12 November 2010 the Superintendent issued SI 65 [TB3350-3370] attaching 10 Precast Panel Pattern Type 2 Shop Drawings and advised that they were Approved Subject to Comments;
(bb) Email from Tectura to Industrial Carving Services and Mackie dated 12 November 2010 [TB3371] refers to a request from Fota Constructions and "attached a copy of the proposed Columbia 2/169 Pattern generated from the pattern in the Reckli Form Liner Brochure in AutoCAD format";
(cc) On 19 November 2010 the Superintendent issued SI 66 [TB3372-3374] referring to Consultant's Advice Notice No 36 and attached 37 precast panel shop drawings which were approved subject to comments, and attached 11 precast panel pattern Type 3 shop drawings which were approved subject to comments;
(dd) On 25 November 2010 the Superintendent issued SI 67 [TB3375] confirming verbal advice of 23 November 2010 that 6mm gaps were to be provided at the intersection points of the raised (polished) sections of Precast Concrete Panels Pattern Type 2 and that the pattern to Precast Concrete Panels No 31 and 32 was to be Pattern Type 3 as shown on Drawing No PCA-CD-07-01/8;
(ee) On 29 November 2010 the Superintendent issued SI 68 [TB3376-3385] attaching 9 precast panel Pattern Type 2 shop drawings received on 23 November 2010 were Approved Subject to Comments;
(ff) Email from Industrial Carving Services to Fota Constructions, copied to Mackie and Tectura, dated 6 December 2010 [TB3387] advised that it had produced a pattern which utilised a straight line which followed profile section 01 and 03 and requested advice as to whether this was an acceptable compromise;
(gg) Email from Industrial Carving Services to Fota Constructions dated 6 December 2010 [TB3386-3387] regarding hard coating of the form liner moulds stated that:
(i) The company which undertakes the hard coating must have the panels by 15 December 2010 at the latest, but it was doubtful that Industrial Carving Services could meet this deadline;
(ii) They did not re-open until 17 January 2011;
(iii) They could not hard coat a panel which was 3000mm wide x 3000mm long, so they would have to be provided with panels 1500mm x 3000mm long which meant there would be more joining and filling required at Fota Constructions;
(iv) Industrial Carving Services could not make any guarantees of how many times the patterns could be used to cast concrete panels from
(hh) Email from Industrial Carving Services to Tectura and Mackie dated 9 December 2010 [TB3388-3390] attached a 3D surface model of the proposed pattern;
(ii) Email from Tectura to Industrial Carving Services dated 15 December 2010 [TB3391-3393] requested that Industrial Carving Services extend the angled lines through to the end of the 3 pattern repetitions so that they could eliminate the bumps forming at the 2 intersections of the 3 pattern repetitions as per the attached image of Industrial Carving Services' CAD file received on 9 December 2010;
(jj) On 17 December 2010 the Superintendent issued SI 72 [TB3394-3397] advising that:
(i) In respect of cast in plates within the Level 1 and 2 slab for precast panel connections, Mackie was to organise an independent welding inspection and verification of all full penetration butt welds at the rear of the property (Consultant's Advice Notice 38) and Mackie was to provide calculations and detailed drawings of the proposed precast panel connections and submit them for approval because Mackie did not install cast in plates to the first and second floors; and
(ii) Attached extract of Drawing PCA-CD-07-02/5 increasing the widths of Precast Panels No 1 and No 2 to the South Elevation;
(kk) On 21 December 201 the Superintendent issued SI 73 [TB3398-3402] advising that the Columbia Precast Concrete Panel Pattern Type 1 AutoCAD drawing submitted via email from Industrial Carving Services was approved subject to the Precast Panel being manufactured with a minimum 120mm structural thickness and 30mm thick grooved / fluted pattern with an overall thickness of 150mm as per the Contract Documents;
(ll) Industrial Carving Services Invoice 11012372 [TB3403-3404] to Fota Constructions dated 14 January 2011 provides:
(i) "Please allow Approx. 4 to [sic] weeks for delivery from Confirmation of Deposit"; and
(ii) "NOTES: WE CANNOT GUARANTEE HOW MANY CONCRETE PANELS CAN BE MADE FROM THIS TYPE OF PATTERN";
(mm) Industrial Carving Services Invoice 1103-237 to Fota Constructions dated 3 March 2011 [TB3405]included for the following:
(i) 15 February 2011 - Labour 2 people to join 6 panels; and
(ii) 18 February 2011 - Labour 1 person to finish panels;
Mackie Pty Ltd
Republic of Turkey
(2013) 41 VR 636
(1985) 1 NSWLR 314
(1950) 101 CLR 298