[2016] VCAT 1770
Victorian Civil and Administrative Tribunal
2016-10-20
Mr J
Original judgment source is linked above.
Domestic Building Contracts Act 1995 - ABIC Major Works Contract - documents incorporated into Contract - claims for variations - requirements - power of Architect to certify extension of time before final certificate if no claim made - no claim interpreted to mean no valid claim - Peninsular v. Balmain principle applied - duty of Architect to certify if fair and reasonable to do so - Tribunal to exercise power if fair and reasonable to do so - extension of time - delay in reaching practical completion - evidence - Builder must prove delay to critical path - calculation of delay period - use of works programs - expert evidence - claim for extension of time costs - how calculated - whether off site overheads included
6 - 17 May and 26 May, 26 July 2016. Final submissions received 15 August 2016.
Allmore Constructions Pty Ltd v K7 Property Group Pty Ltd (Building and Property) [2016] VCAT 1770
"draft fire engineering report - Rawfire - Dated 7-12-11,
Sustainability statements - Ark Resources - dated 9-9-11,
"B1.2 The intent of this contract is to construct 37 apartments, car parking and associated works. The contractor has been involved in the documentation process and has provided advice on the construction technique and detailing, as well as reviewing the documentation and budget throughout the process. The contractor assumes the risk of any minor errors and omissions as defined in Clause B1.3 up to a maximum amount of $5,000.00 for minor errors and omissions. The contractor will not be entitled to claim any additional costs in respect of any minor errors and omissions as defined in Clause B1.3, unless the aggregate value of all costs incurred by the contractor in respect of minor errors and omissions exceeds $5,000.00. If the aggregate value of all costs incurred by the contractor in respect of minor errors and omissions exceeds $5,000.00, then the contractor will be entitled to make a claim to adjust the contract for the value of all costs incurred by the contractor in relation to minor errors and omissions to the extent that such costs exceed $5,000.00. For the avoidance of doubt, the contractor will be entitled to claim an extension of time for any delay affecting working days caused by minor errors and omissions as defined in Clause B1.3.
B1.3 The contractor shall perform any works that are necessary to complete minor errors and omissions in the contract documents or the works, provided that the aggregate value of all costs incurred by the contractor in respect of minor errors and omissions does not exceed $5,000.00."
If the Contractor has not made a claim to adjust the Contract in relation to any change which results from complying with any instruction given under Section J for a variation or from causes of delay noted in Clause L1 or L2, the Architect may adjust the Contract at any time up to the issue of the final certificate under Clause N12, or a certificate under clauses Q9 or Q 17."
Variation CV 7 - in-situ or pre-cast blade walls
"Allmore intend replacing insitu concrete columns with pre-cast columns for the entire project."
'Blade wall composition (in situ vs precast) advised by ONG [the Engineer] that needs to be in situ. Allmore to review and advise costs as precast included within the Tender/Head Contract Sum'.
25 mm Kingspan Kooltherm K 10 soffit board to garage soffit shared with habitable spaces above - R1.19."
Under metal roof construction and all units ceilings with roof areas above - R.5"
"Allmore have not made any allowance for revised requirements as part of the 'energy and efficiency report issued' on the 28/3/12."
35mm Kingspan Kooltherm K10 soffit board: slab soffit and basement car park shared with apartments above R1.67.
50 mm ISO Board soffit board: floor areas over open spaces R1.66.
50 mm ISO Board soffit board: underside of concrete ceiling/roof sections shared with terrace above R1.66.
Total R3 .5 value to be achieved with ceiling insulation + starting to underside of metal deck roof R3.5."
"The Contractor further warrants to the Owner that:
................................................................................................... it has satisfied itself as to the correctness and sufficiency of its tender for the works and that the contract price including any additions expressly required to be made under the contract is sufficient to cover the cost of performing all of its obligations under and in connection with this contract and the costs of all matters and things necessary for the due and proper performance and completion of this contract and the works."
"All smoke/fire rated walls are to be extended full height to the underside of the roof tray or floor surface above, all penetrations are to be smoke sealed."
"Please find attached details for the fire rating to top floor corridor walls. These have been agreed to by building surveyor, fire engineer and acoustic engineer."
Variation CV 29 - engineering fee for truss re-design
Variation CV 30 - additional inspection for fire rating top floors
Variation CV 38 - revised fire rating works and truss rectification
"Supply and install Tyco WS Fire Sprinkler Window Drenchers in accordance with Fire Engineer's Report, MFB Regulations and Manufacturers Recommendations".
"The locations, invert levels and sizes of all services shown on the drawings are indicative only. It is the responsibility of the Contractor to verify and confirm all the services prior to commencement of any works or ordering of any materials."
EOT 13 16.09.13 Install additional insulation to soffit areas 10
EOT 15 15.10.13 Delay in provision of Architect's instruction
EOT 16 28.10.13 Delay caused by the performance of work set
EOT 22 21.01.14 Delay in provision of Architect's further instruction
EOT 24 21.01.14 Delay caused by the performance of further work
EOT 20 16.12.13 Delay caused by the performance of works set
out in an instruction by the Architect to construct
EOT 25 28.05.14 Delay in provision of Architect's instruction in
respect of the layout and installation of additional drenchers and amendments to existing drenchers 18
EOT 26 21.07.14 Delay in the issue of the certificate of practical
(f) the owner's consultants failing to promptly provide necessary information which is properly due to the contractor which the contractor has specifically requested in writing;
(i) a material breach of the contract by the owner:
(j) an active prevention by the owner not otherwise covered by that clause;
"L2.1 The Contractor may make a claim for an adjustment to the date for practical completion but not for adjustment of time costs caused by:
a disruptive weather conditions exceeding the allowance shown in item 25 of schedule one
b any other circumstance exceeding the allowance shown in item 26.
L2.2 the requirements for making a claim to adjust the Contract and procedures to be followed are stated in section H."
It is a condition precedent to the Contractor's entitlement to an adjustment of time under this section that the Contractor must:
"673 McAlpine outlines the general approach which should be taken with respect to EOT claims. More specifically, with EOT claims, the burden of proof is on the claimant to establish actual delay. Whilst theoretical calculations, particularly those contained in computer software programs, are useful tools in the building industry, generally further information will be required. Whilst there may be assumptions and calculations, it is necessarily a matter of the claimant proving in the proper way that there has been actual delay such as to substantiate claims for reimbursement.
674 Thus, in this case, it behoved the plaintiff for the purposes of the EOT claims to establish that it had actually been delayed and that damage was actually suffered by reason of that delay. The defendants argued that the plaintiff failed on both counts.
675 As observed, to assist in deciding the point, McAlpine casts the necessary approach as one that requires a builder, in this instance the plaintiff, to present a drawing by drawing, beam by beam, column by column, gutter by gutter factual analysis to show how a particular event had the effect of delaying other identified work."
EOT 15, 16, 22 & 24 Fire rated corridor walls 76 43
Is the Builder out of time to claim an adjustment for delay?
"The referee expressed the view that, of the five extensions contended for before him by Abigroup, four were variations that could be classed as acts of prevention by Peninsula, and one was a "neutral delay"; and that the Superintendent should have granted extensions for the former, and should have granted an extension for the latter since it was reasonable for it to do so. The referee continued:
'Using the power which I believe I have to open up and review the decisions (including non-decisions) of the Superintendent, I therefore find that EOTs should be granted for all the delays listed at the head of this section, and for the times involved.'"
"79 In my opinion, no error is shown regarding the primary judge's acceptance of the referee's conclusion based on the Superintendent's power. In my opinion, this power is one capable of being exercised in the interests both of the owner and the Builder, and in my opinion the Superintendent is obliged to act honestly and impartially in deciding whether to exercise this power. Of course, if a timely claim has not been made, and the ground on which an extension is claimed is one which is difficult to decide because of the time that has elapsed since the time when the claim should have been made, that may be a ground on which the Superintendent can fairly refuse the extension; but there is no suggestion that that is the case here.
80 In my opinion also, the power to extend time, including the power to do so even if no claim has been made within time, does not automatically come to an end with the termination of the Contract for the Builder's breach. Clause 35.6, providing for liquidated damages, expressly operates after the Contract has been terminated under cl.44; and in order for it to so operate there must be a date for practical completion on which the clause can operate after termination of the Contract. If an application had been made within time before termination and not yet determined by the Superintendent at the time of termination, it is plain in my opinion that the Superintendent would have power to determine that claim after termination. If a claim had been made before termination but outside the time provided by cl.35, and the Superintendent had not made a decision in exercise of the Superintendent's power to extend time notwithstanding non-compliance, in my opinion the Superintendent could still do so after termination. In those circumstances, I do not think the Superintendent's power is lost on termination, even if the claim for exercise of the power to extend notwithstanding non-compliance had not been made until after termination.
81 For those reasons, it was in my opinion open to the referee to do what he considered the Superintendent should have done in response to the claims made to the referee; and it was open to the referee to conclude that the Superintendent, acting fairly, would have granted the extensions which the referee found to be justified. This view may have some further support from the referee's finding that Peninsula was itself in breach of cl.23 in failing to ensure that the Superintendent arrive at a reasonable measure of time in respect of delays caused by Peninsula and the Superintendent."
'Notwithstanding that the Contractor is not entitled to an extension of time the superintendent may at any time and from time to time before the issue of the final certificate by notice in writing to the Contract to extend the time for practical completion for any reason.'
'a claim made to the Architect to adjust the Contract price including adjustment of time costs or the date for practical completion or both'.
'540. In general, an owner cannot recover liquidated damages for delay in the completion of works by a builder where that delay has been caused by an act or omission of the owner in breach of the contract. This prevention principle does not apply where the building contract, as here, contains a provision giving to the builder a right to an extension of time for delays caused by the owner's breach of contract but the person having power to extend time must exercise it honestly and fairly and the owner will be in breach of contract if he does not do so, even though the builder has no absolute entitlement to an extension of time ...........................................
"CV 028 - Fire Rating Works and CV 029 - Re-design of trusses
CV 028 - Fire Rating Works and CV 029 - Re-design of trusses
As per our letter sent by David Carabott dated 16 November 2013, we maintain that in our opinion the cost involved with the fire engineering to the top floor of the truss redesign are the responsibility of Allmore constructions i.e. CV 028 and CV 029.
Proceed forthwith without adjustments of cost or time for completion".
"Awaiting an Architect instruction (Requirements changed for approval of fire rating to upper levels - contrary to previous instructions)".
It claimed the commencement of delay to be 15 November 2013 with no specified end.
He said that that was not a prescribed cause of delay under the Contract and that the subsequent articulation of the cause of delay in Schedule 3 of the Points of Claim namely, that it was a delay caused by the performance of work set out in an instruction by the Architect to construct Blade walls using in situ concrete columns in lieu of precast concrete columns, was a new claim. He pointed out that, on 19 December 2013 the Architect rejected the claim on the basis that the Builder was not instructed by the Architect to change the Blade walls from precast to in situ.
'The structural Contract drawings show precast Blade walls in the basement and in situ to the floors above. In our opinion there is no claim as it was Allmore Construction's choice to modify the basement to build in situ Blade walls and the columns above basement were built in accordance with the Contract documents. We retract this variation.'
The Builder's monetary claim for an extension of time
CV 22 EOT 13 Install additional insulation to soffit $21,600
CV 25 EOT 15 Delay costs to preliminaries for awaiting
CV 26 EOT 16 Delay costs to preliminaries for fire engineering
CV 31 EOT 22 Delay costs to preliminaries for awaiting
CV 32 EOT 20 Delay caused by constructing Blade walls using
CV 59 EOT 25 Delay in the provision of Architect's instruction
for layout and installation of additional drenchers
CV 64 EOT 26 Delay in the issue of the certificate of practical
Less liquidated damages claimed by the Developer $ 259,000.01
Amount paid to the Builder by the Developer $9,037,523.42
Amount payable by the Builder to the Developer $ 214,750.30
Allmore Constructions Pty Ltd
K7 Property Group Pty Ltd