[2015] VCAT 983
Victorian Civil and Administrative Tribunal
2015-07-01
Original judgment source is linked above.
Domestic Building Contracts Act 1995 - architect administered contract - role of architect - tender document - not part of contract - repudiation - conduct amounting to - acceptance of repudiation cannot be withdrawn -s.128 - fixture shown in contract and specification included unless excluded - meaning of "shown" - must be shown with sufficient particularity - standard of work required - uncertain term - whether meaning can be ascertained - approach - extension of time by Tribunal - basis of - when granted
TCM Building Group Pty Ltd v Mercuri (Building and Property) [2015] VCAT 983
Contractual provisions as to price and variations
"I have worked on the claim 13 and the retention but unfortunately I have to verify what's credit to the client and what had to be paid to you before I approve the claim. Furthermore can you please advise us if all defects are rectified."
"I spoke to Vince this morning and he mentioned that they will not release any fund unless all defects and incomplete works are done. They have a list of items that they will send to me by the end of the week to clarify some of the credits that are due to them and items claimed incorrectly."(sic.)
"Repudiation of a contract is a serious matter and is not to be lightly found or inferred: Ross T. Smyth & Co., Ltd. v. T.D. Bailey, Son & Co. (1940) 3 A11 ER 60, at p 71. In considering it, one must look to all the circumstances of the case to see whether the conduct "amounts to a renunciation, to an absolute refusal to perform the contract_": Mersey Steel and Iron Co. v. Naylor, Benzon & Co._ (1884) 9 App Cas 434, at p 439."
"Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way."
"Your failure to meet your obligation under the building contract including in particular, inter alia, (sic.) a failure to pay the progress claim 13 due to our client and in relation to ensuring the proper administration of the contract by your appointed architect..."
Variation 41 - Silver birch stain to floor and sanding and polishing
Variation 43 - Telecommunications from pit to House
Variation 51 - Concrete landing and steps off garage
We should have enough credit for concrete to the front courtyard to compensate for any extra concrete for the steps and landing. Please proceed on this bases" (sic.)
Variation 53 - Repairs to existing timber floor
Item 8.10 - Paint rear lane fence and garage wall
"The cost of any fixture or fitting shown in the plans and specifications included in a domestic building contract is to be taken as having been included in the contract price unless -
(a) the contract states that the fixture or fitting is not included in the contract price; and
(b) the building owner places her, his or its signature or seal next to the statement."
Item 2. The location of the computer internet cable.
Item 4. Flashing above the master bedroom and above bedroom 5.
Item 6. Brickwork at the eastern end of the wall not cleaned
Item 7. Discharge of stormwater drain onto footpath.
Item 12. Brickwork perpends not filled with grout and poor cleaning
Item 13. TV cable installed through exterior of north brickwork.
Item 14. No articulation joint between the low wall and the brick wall at the west end of the building.
Item 15. Front edge of bluestone tread of stairway chipped
Item 17. The kitchen joinery / kicker interface
Item 24 - 30. A number of doors are warped and require replacement.
Item 33. Highlight window in family room ceiling.
"INSPECTING SURFACES FROM A NORMAL VIEWING POSITION", the Guide states:
"Generally, variations in the surface, colour texture and finish of wall, ceilings, floors and roofs, and variations in glass and similar transparent materials are to be viewed where possible from a normal viewing position. A normal viewing position is looking at a distance of 1.5m or greater (600 mm for appliances and fixtures) with the surface or material being illuminated by "non-critical light". Non critical light means the light that strikes the surface is diffused and not glancing or parallel to that surface."
Item 36. External deadlocks incorrectly installed.
Item 38. Water staining to eave above the front door.
"A provisional sum includes labour, materials and all costs and margins"
"Manufactured casework- kitchen allowance will be based on Award Cabinets' or similar Architect approved quote.
Any exceeded amount on Award Cabinets' quote for the kitchen only or similar cabinet maker's quote for the same item is to be paid by the client however no margin is to be charged by the Builder on the exceeding amount.
As agreed by the Builder & Architect on the 23/6/2010."
"In effect, any overrun on the provisional sum for manufactured casework would result in an adjustment to the contract sum of the net difference between the provisional sum and the net cost of the work."
"Architect may instruct regarding provisional or prime cost sum
.1 The Architect may instruct the Contractor to provide a written quotation for work, the supply or supply and installation of an item or the payment of a fee or charge to an authority for which a provisional sum or prime cost sum has been allowed.
.2 The quotation must be for the direct cost to the contractor of performing the work, supplying or supplying and installation the item or paying the fee or charge, including GST but excluding any margins for overhead or profit.
.3 If the architect agrees with the quotation. The architect may issue an instruction to proceed and the contract price will be adjusted in accordance with clauses K4 or K5, when the next certificate is issued.
.4 If the architect does not agree with the quotation, the architect may instruct the contractor to proceed, in which case the architect must issue a decision in accordance with clause H4."
.1 The contract price is to be adjusted by the architect to take account of any difference between a provisional sum or prime cost summand the cost of the performance of the work or the supply, or supply and installation of the item under clause K2.
.2 If the difference is positive, the extra cost will be adjusted by applying the percentage shown in item 13 of schedule 1 and adding the total amount to the contract price.
.3 If the difference is negative, the net difference will be deducted from the contract price.
,4 Any difference to the contract price is to be shown in the next progress certificate."
".36 The provisions of commercial agreements are to be construed according to what a reasonable person would have understood them to mean, having regard to the surrounding circumstances known to the parties and the purpose and object of the transaction: Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd.
37 This principle is often stated in terms of a necessity to construe commercial agreements so as to accord with 'business commonsense' or 'commercial reality'."
Not removing hard plaster sill to curved window.
"I am now aware as a result of this action that variations 15, 20 and 43 which I certified for payment and which were paid are not in fact variations."
"(iii) Excavate generally as required or as shown on the drawings, including but not necessarily limited to the following:
Removal of footings and unnatural items below grade;
"This project price is based on the buying rate of foreign exchange of 0.693 Euro cents and subject to rise and fall in the event of foreign exchange movement of more than 5 per cent (0.658- 0.727)m - our buying rate is .046 difference in the daily Euro rate."
"We met with the builders over a month ago (David and Tony) where we agreed to an extension of time till early December (5 months to completion) There is enough time to complete the project if sufficient resources are deployed. Could you provide a completion schedule for this project. Unfortunately no extra extensions are possible."
"We chose to be pragmatic and as a gesture of good faith agreed we would not pursue late completion penalties accrued between August and November if TCM achieved completion and handover to enable us to move back by December, a time frame which you indicated was achievable. We have taken you at your word and reasonably expect that our goodwill is appreciated and returned in kind by TCM."
Mr Chamberlain said that, when excavating for the footings in September 2010 the Builder encountered excessive water which caused the excavation to take six weeks instead of two.
Changes to the engineering design made by the Architect on 16 September 2010 which resulted in a variation (VR1) were said to cause a delay of two days.
This was found in the site of the new footing and was the subject of a variation (VR2). Its removal was alleged to have caused a delay of two days.
On 22 February 2011 by another variation (VR6), the timber floor of the southern building was to be replaced by a concrete slab. The Architect and engineer were to provide a design of the slab and this was requested by the Builder from 1 March 2011 and thereafter four further emails throughout March 2011. The information was not received until "about the end of April 2011". As a consequence the slab was not poured until 30 April 2011. A delay of four weeks is claimed.
Mechanical works were to be by a subcontractor nominated by the Architect. (Section 16351). The works were not detailed in the Contract documents and were the subject of a provisional sum allowance. According to Mr Chamberlain, between 21 February 2011 and 5 July 2011 he sent 15 emails to Mr Mani requesting the Architect to nominate a subcontractor but the subcontractor was not nominated until 5 July 2011. The nominated subcontractor was engaged by the Builder that same day. Although the emails extended over 134 days, a delay of 6 ½ weeks was suggested.
The joinery and kitchen were to be by nominated subcontractors. In April and May 2011 the Builder requested that the subcontractors be nominated but it was not until 8 June that the Architect issued instructions to the Builder to engage the kitchen supplier, Rogerseller, which it did. The kitchen cabinetry was manufactured in Italy.
Thereafter schedules of finishes had to be agreed to by the Owner with Rogerseller The contract for the supply of the kitchen was entered into by the Builder on 20 June 2011 with an anticipated delivery date of 20 September 2011, which was after the date fixed by the Contract for practical completion.
Communications concerning the kitchen occurred between Rogerseller and the Owner and the Architect as well as the Builder. Installation of the kitchen was not completed until March 2012, having not been commenced until the second half of October 2011.
On 18 May 2011 the Builder asked the Architect to nominate the subcontractor for the joinery and to provide details of the joinery. Between then and July 2011 there were twelve emails from the Builder repeating the request.
On 26 May 2011 the Architect advised that the joinery details had been changed. Amended joinery drawings were not provided to the Builder by the Architect until 28 July 2011 at which time the joinery subcontractor was nominated.
The Architect had dealt with the nominated joinery subcontractor before but the Builder had not. The subcontractor told Mr Chamberlain that because he had not worked for him before he was "down the list". Thereafter Mr Mani appears to have dealt with the joinery subcontractor and advised Mr Chamberlain about progress. In an email of 1 March 2011 Mr Chamberlain sent Mr Mani a list of 17 items for the subcontractor to complete.
The nominated subcontractor was very slow and did not complete the work until 27 March 2012.
The Owner was to supply door hardware. The Builder requested details in fifteen emails between 14 April 2011 and August 2011. On 15 September 2011 the Owner advised Mr Chamberlain that the door hardware was able to be collected from a store in Richmond.
On 8 June 2011 the Builder asked the Architect and the Owner to select the tiles. The interior tiles were not supplied until 13 October 2011 and the tiles for the balcony were not supplied until 24 November 2011. The tiles for the external tiling were not supplied until 17 January 2012. The Architect's nominated tiler did not begin tiling until March 2012 and the set out plan was not confirmed by the Architect until 8 March 2012.
From 4 July 2011 Mr Chamberlain requested information as to the type of bench top the Owner wanted and made several subsequent requests. Three subcontractors were nominated on 28 September 2011, 18 November 2011 and 22 September 2011 respectively.
The design of the front fence was not provided by the Architect until 8 and 9 November 2011 although Mr Chamberlain had requested it on 24 September and in subsequent emails. The design was then changed a number of times and it was not until 12 December 2011 that the plans for the front courtyard and fence were provided.
Mr Chamberlain said that the front paving could not be carried out until such time as the design of the front courtyard had been provided. The design of the letterbox and front gate was also delayed and these works were ultimately carried out by the Owner using another contractor after they took possession.
Although requested on 23 September 2011 and in subsequent emails the paint and render colours were not selected until January and February 2012 and even then were not provided all at once.
According to Mr Chamberlain, the final inspection by the Building Surveyor was arranged for late February 2012 but it did not occur because the Owner had not paid an earlier invoice from the Building Surveyor. The inspection did not take place until 21 March 2012.
Because the power was being relocated to a box in the front fence the delay in regard to the design of the front fence held up the installation of the power. As a result the permanent power supply was not connected until the second half of February 2012.
Mr Chamberlain said that, in February 2012, the Owner changed the floor paint from lacquer to a particular wood wash that was applied by a specialist contractor who could not do it until March 2012, which is when the work was done. Also during that month, the termite affected floorboards were replaced pursuant to Variation request 53 and that was not completed until 22 March 2012.
The landscaping was the responsibility of the Owner. Her contractor did not complete it until February 2012. Mr Hellyer submitted that I should find that the House could not be considered to have been completed until that was done. However the question is, when was the Builder's scope of works complete? Whether the overall work was completed and whether the House could or could not have been occupied without the landscaping are separate questions.
Mr Hellyer submitted that the delay in the selection of sanitary fittings caused further delay.
"Note only when items that are delaying the critical path of construction are confirmed can a completion date be set."
"Please be advised that TCM cannot set a completion date until items affecting the critical path of construction are answered. Only once this information is received can a completion date be set."
"Dear Gabby, attached are all the lists of requests for this project. If the information critical to the flow of this project is not received, TCM has no choice but to put this project on hold until all information is received. Once TCM receives the information a completion date will be set and made contractual. Please let me know when you intend to forward the relevant information."
"Hi Teata, Please find attached list of questions. Please note that some of these items have held the project up for some time now.
Note: only when items that are delaying the critical path of construction are confirmed can a completion date be set."
"Hi Teata, Please find list of items to be confirmed. Please note if some of these items are not answered immediately the job program will be affected."
"Hi Teata/Gabby, Please find attached list. Please note if some of these items are not confirmed asap, the job timetable will be affected."
"When will I receive the plans for the front fence. If the fence is not built now I won't be able to bring the services into the property before Christmas."
"Hi Teata/Gabby, Please find attached list. This list needs confirmation asap for this project to move forward. So many items needing confirmation at this point in time is delaying the project. Please respond asap."
"Teata, the Porters wood wash colour needs to be selected before the floor sander can estimate the additional costs. Apparently the lighter colour may need two coats of stain. As you know he is sanding on Monday so this needs to be finalized tomorrow or we may lose him to another job."
"3 days to go before handover and there are still outstanding items -
"If the contractor has not made a claim to adjust the contract in relation to any change which results from complying with any instruction given under section J4 for a variation of the works or from causes of delay noted in clauses L1 or L2, the architect may adjust the contract at any time up to the issue of the final certificate under clause N11 or a certificate under clause Q9 or Q17".
"79. In my opinion, this power is one capable of being exercised in the interests both of the owner and the builder, and in my opinion the Superintendent is obliged to act honestly and impartially in deciding whether to exercise this power. Of course, if a timely claim has not been made, and the ground on which an extension is claimed is one which is difficult to decide because of the time that has elapsed since the time when the claim should have been made, that may be a ground on which the Superintendent can fairly refuse the extension; but there is no suggestion that that is the case here.
80 In my opinion also, the power to extend time, including the power to do so even if no claim has been made within time, does not automatically come to an end with the termination of the contract for the builder's breach. Clause 35.6, providing for liquidated damages, expressly operates after the contract has been terminated under cl.44; and in order for it to so operate there must be a date for practical completion on which the clause can operate after termination of the contract. If an application had been made within time before termination and not yet determined by the Superintendent at the time of termination, it is plain in my opinion that the Superintendent would have power to determine that claim after termination. If a claim had been made before termination but outside the time provided by cl.35, and the Superintendent had not made a decision in exercise of the Superintendent's power to extend time notwithstanding non-compliance, in my opinion the Superintendent could still do so after termination. In those circumstances, I do not think the Superintendent's power is lost on termination, even if the claim for exercise of the power to extend notwithstanding non-compliance had not been made until after termination.
81 For those reasons, it was in my opinion open to the referee to do what he considered the Superintendent should have done in response to the claims made to the referee; and it was open to the referee to conclude that the Superintendent, acting fairly, would have granted the extensions which the referee found to be justified."
Adjustments for Provisional sums and prime costs
Permits, Council's fees etc $ 2,200.00_________________
TCM Building Group Pty Ltd
Mercuri