Greater Hume Shire Council v J & L Cauchi Civil Contracting Pty Ltd
[2006] NSWLEC 738
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2006-10-03
Before
Biscoe J, Mr P
Source
Original judgment source is linked above.
Judgment (43 paragraphs)
BACKGROUND 3 On 22 December 2005 the Greater Hume Shire Council commenced these proceedings against the four respondents seeking a declaration that they had undertaken or caused to be undertaken the use of land for the purposes of an extractive industry without a prior development consent, and an injunction. The land is described as being within the local government area of Hume, Parish of Yambla, County of Goulburn, being Lot 41 in deposited plan 1004275, located at the corner of the Hume Highway and Bells Road, Tabletop.
4 On the same day, an ex parte injunction was granted to the council restraining the respondents from carrying out any further work for the purposes of or related to an extractive industry, upon any part of the land without the prior written consent of the applicant pursuant to the EPA Act and the Hume Local Environmental Plan 2001. The ex parte injunction was expressed to endure until 28 December 2005. On that date the respondents appeared and the injunction was continued until 30 December 2005. Then it was continued until 6 January 2006, subject to a proviso that the respondents could remove material already extracted from its natural state and stockpiled on the site.