© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2006] NSWSC 1
Supreme Court of NSW
2005-12-12
Palmer J, Young J, Grant Constructions P, Ms J
Original judgment source is linked above.
CITATION : Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor [2006] NSWSC 1
HEARING DATE(S) : 21 & 22 November, and 12 December 2005
JURISDICTION : Equity Division Technology & Construction List
CATCHWORDS : BUILDING AND CONSTRUCTION INDUSTRY - When is a payment claim invalid for purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) - authorities and principles discussed - what are the requirements of s.22(2) - what must an adjudicator show in reasons for determination when adjudication process is undefended.
LEGISLATION CITED : Building and Construction Industry Security of Payment Act 1999 (NSW) - s.11, s.13, s.14, s.15, s.17, s.20, s.22, s.23, s.24, s.25, s.32.
Brookhollow Pty Ltd (formerly Grant Constructions P/L) - Plaintiff PARTIES : R&R Consultants Pty Ltd - First Defendant Philip Davenport - Second Defendant
COUNSEL : R. Harper SC - Plaintiff Ms J. Oakley - Defendants
SOLICITORS : Home Wilkinson Lowry - Plaintiff McMahons National Lawyers - Defendants
1 The Plaintiff ("Brookhollow") seeks a declaration that an adjudication determination made by the Second Defendant, Mr Davenport, under s.22 of the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act") is void. The Plaintiff seeks a permanent injunction restraining the First Defendant ("R&R") from taking any action to enforce the determination. 2 The validity of the determination depends essentially on whether:
3 The relevant facts are in short compass and are not in dispute. 4 On or about 9 July 2002, Brookhollow entered into a sub-contract with R&R whereby R&R would perform certain demolition and excavation work ("the Contract"). 5 On 29 September 2003, R&R left the site and did no further under the Contract. 6 On or about 2 December 2003, R&R served on Brookhollow a payment claim under the Act. The claim was entitled "Final Claim" and was for contractual work up to 31 August 2003. After adjustments for variations and other allowances, the amount claimed was $169,494.25. For convenience, I will call this "Claim No 8". 7 It is clear that the parties were in dispute at the time of the delivery of Claim No 8. However, no proceedings to enforce this payment claim were instituted by R&R at that time. 8 About eleven months later, on 9 November 2004, R&R served on Brookhollow a further payment claim under the Act. It has been called "Claim No 9" and I will refer to it by that description. 9 Claim No 9 claimed payment of exactly the same amount as was claimed in Claim No 8, namely, $169,494.25. R&R concedes that it did no further work on the site after 29 September 2003 and that the work for which payment is claimed in Claim No 9 is the same work which is the subject of Claim No 8. 10 However, between the delivery of Claim No 8 and Claim No 9, Brookhollow carried out certain remedial work which it said should have been done by R&R. Brookhollow claimed to be entitled to deduct the cost of this work from the amount to which R&R was entitled. R&R denied that entitlement. 11 In Claim No 9, R&R set out the work for which it claimed payment, by reference to Claim No 8 which was attached. Also attached was the Contract. A covering letter, referred to in the payment claim, stated: " A. PAYMENT CLAIM
Please find attached our Payment Claim No.9 for November 2004 dated the 8th November 2004.
Our current Payment Claim is based on and relies on "The Building and Construction Security of Payment Act (as amended) Clause 13(6)" .
"(6) However, Subsection (5) does not prevent the claimant from including in a Payment Claim an amount that has been the subject of a previous Claim."
We advise that our current Payment Claim includes an amount that has been the subject of a previous claim.
Our current Payment Claim is also based on and relies on Clause 13(4)(b) of the Act referred to above.
"(4)(b) the period of 12 months after the Construction work to which the Claim relates was last carried out."
We note that Grant Construction unilaterally and without prior agreement - undertook certain work allegedly on behalf of R&R Consultants Pty Ltd in March 2004. Grant Construction subsequently purported to back-charge us an amount of $3,633.67 for that work. A copy of your advice is attached.
Undertaking that work referred to above, on our behalf and allegedly at our cost, clearly satisfies Clause 13(4)(b)." 12 Brookhollow concedes that it did not serve a payment schedule in response to Claim No 9 within the time limited by s.14(4) of the Act. Brookhollow did not pay the amount claimed in Claim No 9. 13 On 4 January 2005, R&R notified Brookhollow of its intention to seek adjudication under the Act, in accordance with s.17(2). 14 On 14 January 2005, in accordance with s.15(2)(a)(ii) of the Act, R&R made an adjudication application under s.17(1) and (3) of the Act in relation to Claim No 9. A copy of the adjudication application was delivered to Brookhollow. Brookhollow concedes that it did not serve a payment schedule within the time limited in s.17(2)(b) of the Act. There is no dispute that the procedures for engagement of the adjudication process were properly carried out by R&R in due time. 15 As Brookhollow had not served a payment schedule within the times specified in s.14(4) or s.17(2)(b) of the Act, it was precluded by s.20(2A) from lodging an adjudication response under s.20(1). 16 On 21 January 2005, Mr Davenport delivered an Adjudication Determination. I will come to the reasons given by Mr Davenport for his adjudication later. 17 Mr Davenport determined that the "adjudicated amount", as referred to in s.22(1)(a), was the whole of the amount claimed by R&R, namely, $169,494.25 (including GST). He determined that the due date for payment, as referred to in s.22(1)(b), was 22 November 2004 and that the rate of interest, as referred to in s.22(1)(c), was the Supreme Court Rate. 18 On 31 January 2005, the authorised nominating authority issued an Adjudication Certificate purportedly pursuant s.24(1)(a). R&R concedes that this certificate is void because five business days had not elapsed between the date of service of the Adjudicator's Determination and the application for an adjudication certificate, as required by s.23(1)(a) and s.24(1)(a). 19 The Adjudication Certificate was filed in the District Court as a judgment pursuant to s.25(1) on 25 February 2005. 20 R&R does not submit that the entry of judgment in the District Court precludes Brookhollow from seeking injunctive relief in these proceedings. The fundamental question between the parties is whether or not Mr Davenport's Adjudication Determination was, in law, a nullity.
21 Brookhollow submits that Claim No 9 was not a valid payment claim under the Act; accordingly, there was nothing upon which Mr Davenport could validly adjudicate so that his Determination is a nullity. 22 Mr Harper SC, who appears for Brookhollow, says that Claim No 9 is not a payment claim within s.13 of the Act because:
26 In Brodyn at para 53, Hodgson JA referred to the basic and essential requirements for the existence of an adjudicator's determination as including: "1. The existence of a construction contract between the claimant and the respondent, to which the Act applies (s.7 and s.8).
i) a payment claim which is never served on the respondent under s.13(1) cannot set in motion the machinery of Pt 3 so that any purported adjudication of that payment claim and any other enforcement procedures in Pt 3 founded upon that payment claim must be a nullity;
ii) there are some non-compliances with the requirements of s.13(2) of the Act which will result in the nullity of a payment claim for all purposes under the Act; there are other non-compliances which will not produce that result;
iii) a payment claim which does not, on its face, purport in a reasonable way to: - identify the construction work to which the claim relates; or
fails to comply with an essential and mandatory requirement of s.13(2) so that it is a nullity for the purposes of the Act; iv) a payment claim which, on its face, purports reasonably to comply with the requirements of s.13(2) will not be a nullity for the purposes of engaging the adjudication and enforcement procedures of Pt 3 of the Act;
v) in the case of a payment claim which purports reasonably on its face to comply with s.13(2): - if the respondent wishes to object that it does not in fact comply so that it is a nullity for the purposes of the Act, the respondent must serve a payment schedule under s.14(4) and an adjudication response under s.20, in which that objection is taken;
vi) in the case of a payment claim which was never served on the respondent or which does not purport reasonably on its face to comply with the requirements of s.13(2): - the payment claim is a nullity for the purposes of the Act;
50 Brookhollow does not contend that Claim No 9 did not purport reasonably on its face to comply with the requirements of s.13(2) of the Act. 51 For the reasons which I have given, I conclude that because Claim No 9 complied with the requirements of s.13(2), it was not a nullity under the Act, i.e. it was effective to engage the provisions of Pt 3. If Brookhollow wished to assert that the payment claim was barred by reason of the prohibition in s.13(4) or (5), it had to do so in a timeously served payment schedule. Having failed to serve a payment schedule within time, Brookhollow was not entitled to assert nullity of the payment claim in order to resist the entry of judgment under s.15(4). Likewise, it cannot now rely upon the defence in bar to found an injunction restraining enforcement of the adjudication determination or of the judgment resulting from it. 52 The fact that R&R attempted in Claim No 9 to negative a possible defence of prohibition under s.13(4) or (5) has no consequence in terms of the validity of the payment claim for the purpose of engaging the provisions of Pt 3 of the Act; it does, however, have a consequence in terms of whether Mr Davenport complied with the requirements of s.22, to which I now come.
53 Section 22 of the Act relevantly provides: "(1) An adjudicator is to determine:
(a) the amount of the progress payment (if any) to be paid by the respondent to the claimant (the "adjudicated amount"), and
(b) the date on which any such amount became or becomes payable, and
(c) the rate of interest payable on any such amount.
(2) In determining an adjudication application, the adjudicator is to consider the following matters only:
(b) the provisions of the construction contract from which the application arose,
(c) the payment claim to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the claimant in support of the claim,
(d) the payment schedule (if any) to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the respondent in support of the schedule,
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.
(b) include the reasons for the determination (unless the claimant and the respondent have both requested the adjudicator not to include those reasons in the determination)." 54 By his Determination dated 21 January 2005, Mr Davenport gave a determination as to the adjudicated amount, the date upon which it was payable, and the rate of interest payable on the amount, as required by s.22(1) of the Act. Purportedly in accordance with the requirements of s.22(3), he then gave the following reasons for his determination. "The claimant carried out construction work within the meaning of the Act under a construction contract. The claimant has made a payment claim dated 8 November 2004 for $169,494.25. The respondent has not provided a payment schedule despite being given a s.17(2) notice. The respondent has not disputed the claim. The claimant has provided submissions in support of the claim. The submissions demonstrate that the claim is for the construction work carried out by the claimant for the respondent. In the absence of any denial by the respondent of liability for the amount claimed, I am satisfied that the claimant is entitled to a progress payment equal to the amount of the progress claim.
In the absence of any submissions on the due date for payment, I apply s.11(1) of the Act and determine that it is 10 business days after the date of the payment claim. That makes the due date for payment 22 November 2004. Similarly, in the absence of any submissions on the rate of interest, I apply s.11(2) of the Act and determine that it is the rate on unpaid judgments of the Supreme Court.
Since the respondent has provided no payment schedule or adjudication response, I determine that the respondent is liable for 100% of the adjudication fees."
I respectfully agree. 63 In a contested adjudication, the adjudicator need consider only those provisions of the Act and of the contract which are relevant to the issues formulated by the parties in their submissions. In an adjudication in which the respondent does not participate the position of the adjudicator is, in my opinion, analogous to that of the Court when a plaintiff seeks the entry of judgment in default of an appearance by the defendant or where the defendant has failed to file a defence. In such a case, the Court still has a duty to decide the case according to truth and fact and if the plaintiff's case appears on the face of the pleading or on the plaintiff's evidence (or lack of it) to be fatally flawed, then the Court will refuse to enter judgment: Charles v Shepherd [1892] 2 QB 622, at 624, 625; Gramophone Company Ltd v Magazine Holder Company (1911) 28 RPC 221, at 225; Termijtelen v Van Arkel (1974) 1 NSWLR 525, at 529; Bridge Wholesale Acceptance Corporation (Australia) Ltd v Burnard (unrep.) NSWSC Young J, 31 May 1991. 64 In my opinion, where the respondent has not participated in the adjudication process so that the payment claim is undefended, s.22(2) requires the adjudicator to address in good faith such issues arising from the need to conform with the provisions of the Act and of the contract as manifestly appear on the face of the payment claim, the adjudication application and any supporting material. In most cases, the consideration will be confined to:
Whether Mr Davenport's "extra-curial" writings are admissible
69 In a separate ruling, I rejected evidence of various seminar papers delivered by Mr Davenport as going to show what was termed "actual or apprehended bias" on the question whether an adjudicator needs to comply with the requirements of s.22(2) in an "undefended" adjudication. For the sake of convenient reference, I will refer to those writings as "extra-curial" although, of course, Mr Davenport did not constitute a court. 70 The description "apprehended or actual bias" was, I think, inapt. "Bias" usually denotes prejudice against a person or class of persons. Here, what I gather Mr Harper meant was that Mr Davenport's seminar papers proved as a fact that he was committed to a view of the law as to the requirements of s.22(2) which is wrong and that he applied his erroneous view when he came to make his adjudication determination. 71 There are two objections to the use of Mr Davenport's "extra-curial" writings for the purposes of this case. First, let it be assumed that when Mr Davenport came to make his adjudication determination he adhered to the views as to the requirements of s.22(2) which he had expressed in the seminar papers. Even if those views, whatever they are, are wrong in law, there is no reason to suppose that he did not hold those views in good faith. If he applied those views in making his determination, he may have committed an error of law but that is not to say that he failed to address in good faith the requirements of s.22(2) as he believed them to be. 72 The second objection to the use of "extra-curial" writing to prove error in decision making is more fundamental. Judges frequently express opinions, both in their judgments and in extra-curial writings, as to what is the law on some particular point; that does not mean that they are never open to subsequent persuasion about the point, that they will never change their minds over time, or that in any particular case they have reached a decision without fairly considering the point again, even though they have arrived at the same answer. 73 To treat a Judge's previous writings, curial or extra-curial, as evidence of the reasoning process by which he or she has actually decided any particular case is to invite limitless speculation and endless litigation: for sound policy reasons, quite apart from considerations of logic and commonsense, the only reasoning process which may legitimately be reviewed to show error in judicial decision making is the reasoning process, or absence of reasoning process, revealed in the judgment itself. In my view, in the light of the express requirement for written reasons which is imposed on the adjudication decision making process by s.22(2), the same considerations apply to decisions given by adjudicators. 74 In my opinion, if I have to find that Mr Davenport failed to give such consideration in good faith to Claim No 9 as s.22(2) required in this case, I must make that finding on the basis of Mr Davenport's written reasons alone.
75 I am unable to accept Mr Harper's submission that the omission in Mr Davenport's reasons for determination of any reference to the validity of Claim No 9 as a payment claim means that he failed in good faith to consider its validity to the extent that he was required to do so. 76 For the reasons I have given earlier, the validity of Claim No 9 as a payment claim under the Act depended on whether it purported reasonably on its face to comply with s.13(2), not on whether it also complied with the requirements of s.13(4) and (5). Non-compliance with s.13(4) and (5) was a defence which it was open to Brookhollow to raise in a timeously served payment schedule. There being no such payment schedule, Mr Davenport was not bound to consider those defences. 77 There is no suggestion that Claim No 9 did not comply with s.13(2). The fact that Mr Davenport did not refer in his reasons to s.13(2) is capable of indicating merely that he saw no fatal flaw with regard to the requirements of that subsection. 78 However, the covering letter to Claim No 9, which Mr Davenport had, and the adjudication application expressly attempted to negative a possible defence based on non-compliance with s.13(4) and (5). The argument of R&R seems to be founded upon the wording of s.13(4)(b), which requires that a payment claim may be served only within "the period of twelve months after the construction work to which the claim relates was last carried out" . As I apprehend it, R&R was contending that remedial work carried out by Brookhollow within the period of twelve months was "construction work to which the claim relates" because that remedial work was said to result in a deduction from the amount claimed in Claim No 8. Alternatively, Brookhollow seemed to be suggesting that in doing the remedial work, Brookhollow was purporting to act "for or on behalf of R&R" so that the work can be said to have been carried out by Brookhollow as its agent. 79 I do not find those arguments at all convincing. It seems to me that the words in s.13(4)(b) "the construction work to which the claim relates" means "the construction work carried out by the claimant itself" and that such work would not include remedial work carried out by the proprietor or a third party which is said to result in an offsetting deduction against a progress claim. However, it is not necessary for the purposes of this case to decide the question. The issue is whether omission of reference to s.13(4) and (5) in Mr Davenport's reasons for determination demonstrates that he failed to address in good faith the provisions of the Act and of the contract to the extent which was required, bearing in mind that no defence to the payment claim founded on non-compliance with s.13(4) and (5) was raised in a payment schedule. 80 Mr Davenport may have omitted reference to s.13(4) and (5) in his reasons simply because he accepted the argument advanced by R&R as to the construction of s.13(4)(b), saw no fatal flaw in the payment claim in that regard, and saw no reason to mention the matter further as the adjudication process was uncontested. If this is what happened, it may be that Mr Davenport fell into error of law but that does not invalidate his determination. 81 On the other hand, it may be that Mr Davenport did not accept the arguments as to the effect of s.13(4) and (5) but believed that, because no timeously served payment schedule had raised defences founded on those subsections, s.22(2) did not require him to consider them. In other words, he may have held the same views as I have expressed in paragraphs 44 to 48 of this judgment. 82 In short, I cannot infer that Mr Davenport's failure to advert in his reasons to R&R's argument negating a defence to the payment claim is unequivocally the result of a failure to address in good faith the essential question which s.22(2) requires an adjudicator to consider when a payment claim is undefended in the adjudication process by reason of the operation of s.20(2A), namely, does the payment claim or the material adduced in support manifestly demonstrate on its face a fatal flaw in compliance with the provisions of the Act or with the relevant provisions of the contract. 83 Brookhollow submits that Mr Davenport must have failed to consider the relevant provisions of the contract in applying s.11(1)(b) to reach a date for payment for the purposes of s.22(b) and (c) because Clause 42.1 and Part PA of the contract stipulate a date upon which the payment claimed in Claim No 9 becomes due for payment. Brookhollow contends that it should have been clear in the present case that s.11(1)(a) was applicable, not s.11(1)(b). I am unable to accept this submission. 84 Mr Davenport does not say in his reasons that the contract makes no express provision with respect to a date for payment of Claim No 9. Rather, he says that no submission has been made as to the date for payment. This distinction is of some significance. 85 Clause 42.1 of the contract provides that a claim for payment is payable within thirty-five days after receipt by Brookhollow's "Representative" of a claim for payment or within fourteen days of the issue by the Representative of a payment certificate, whichever is the earlier. The date upon which Claim No 9 became due for payment under the contract therefore depends on the ascertainment of certain facts, namely, the date of receipt of the claim by Brookhollow's Representative and the date of issue of a payment certificate, if one was issued at all. 86 Neither Claim No 9 nor the adjudication application made a submission about either of these dates. Claim No 9 is dated 8 November 2004 and the copy provided to Mr Davenport bears a stamp "faxed 9/11/04". But nothing is said about whether Brookhollow had a "Representative" for the purposes of Clause 42.1 and, if so, when that Representative received Claim No 9. Nothing is said about whether the Representative had issued a "payment certificate" in respect of that claim. 87 In the absence of information about facts and circumstances necessary to calculate the date for payment of Claim No 9 under the contract, Mr Davenport may well have taken the view that s.11(1)(b) was applicable to fix the date for payment for the purposes of s.22(1)(b). He may or may not have been in error in that view. Whatever be the case, I am far from being persuaded that Mr Davenport's reasons for determination demonstrate clearly that he made no attempt in good faith to consider the terms of the contract in arriving at a date for payment under s.11(1)(b).
88 Brookhollow fails in its substantive claim that Mr Davenport's adjudication determination is void and that enforcement of it should be restrained. 89 As I have noted, R&R concedes that the adjudication certificate issued on 31 January 2005 is invalid because it was requested and issued prematurely. On 9 May 2005 R&R obtained a second adjudication certificate from the authorised nominating authority. Mr Harper submits that the authorised nominating authority, having once issued a certificate purportedly pursuant to s.24(1)(a), was functus officio even though the certificate was a nullity. The consequence would be that the judgment obtained in the District Court on the basis of the first certificate would be set aside, the second certificate would be a nullity and R&R would now have no means of enforcing the adjudication determination which Mr Davenport had validly made. 90 I am unable to accept these submissions. If the adjudication certificate issued on 31 January 2005 was a nullity then the authorised nominating authority was exercising its power under s.24(1)(a) validly for the first time when it issued the second adjudication certificate in May 2005. 91 The District Court judgment is valid unless and until it is set aside. This Court cannot itself set aside a judgment of the District Court except on appeal. However, this Court, acting in personam, could in a proper case restrain the judgment creditor from enforcing the judgment. 92 As the judgment in the District Court is in aid of a valid adjudication determination and there is now in existence a valid adjudication certificate which could be filed as a judgement under s.25(1), I do not see the utility in restraining R&R from enforcing the judgment which it already has. Leaving Brookhollow to set aside the present judgment and requiring R&R to obtain another judgment upon the filing of the second adjudication certificate would simply produce delay in R&R obtaining payment of Claim No 9 and would involve both parties in needlessly duplicated expense. 93 In the exercise of discretion, I decline to restrain R&R from seeking to enforce the District Court judgment. This does not, of course, prevent Brookhollow from applying to the District Court to set that judgment aside but one would hope that some commonsense will prevail and that unnecessary legal expenditure will be avoided. The issue of Brookhollow's ultimate liability should be decided in civil proceedings, as envisaged in s.32.
94 I refuse the declarations and orders sought in paragraphs 1, 2, 5, 6, 7, 9 and 10 of the Plaintiff's Amended Summons. In view of the concession by R&R that the first adjudication certificate is invalid, I see no utility in the declarations and orders sought in paragraphs 3, 4 and 8 of the Amended Summons. 95 Accordingly, the Plaintiff's Amended Summons is dismissed. 96 As to costs, my present tentative view is that, as the First Defendant has succeeded on the substantive issue of the validity of Mr Davenport's determination, the Plaintiff should pay the Defendants' costs. However, I will hear the parties further on costs, if they wish.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Brookhollow Pty Ltd
R&R Consultants Pty Ltd & Anor
(2004) 61 NSWLR 421
(1974) 1 NSWLR 525