Service of the payment schedule
8The defendant's evidence initially was that Mr Sarkis Elia and Mr Sarraf, who were both employees of the defendant, drove to the plaintiff's Double Bay office on 13 May 2010 and served the payment schedule by pushing it part way under the door of the premises at 9.30am on that morning.
9On the plaintiff's part, evidence was given by Mr Hiatt that he was engaged in a meeting with Mr Milgrom between 9am and 10am on 13 May 2010. That meeting was said to have taken place on a couch opposite the entrance to the plaintiff's office. Mr Hiatt gave evidence that no service occurred at that time.
10The plaintiff was in the process of moving to new premises in New South Head Road. In effect, the move was completed by Saturday 15 May 2010. Mr Hiatt's personal assistant, Ms Orlievsky, gave evidence that she observed the payment schedule under the door of the old offices on 20 May 2010.
11It can be seen that the factual circumstances put forward by each party involve a direct conflict between the witnesses, which has to be resolved. The conflict of evidence cannot be resolved by one of the witnesses being mistaken. The conflict is between:
(a) Mr Elia and Mr Sarraf who claimed that they placed the envelope containing the payment schedule under the door to the plaintiff's office at about 9.30 am on 13 May 2010 after having determined that the door to that suite was locked and
(b) Mr Younan who deposed to a conversation he had with Mr Elia, also at 9.30 am on 13 May 2010, when Mr Elia advised that he was at the offices to serve the payment schedule on the plaintiff.
and
(c) Mr Hiatt and Mr Milgrom who said that they had a meeting immediately outside the door to the plaintiff's office during the period 9 am to 10 am on 13 May 2010, and that nothing was delivered during that period and
(d) Ms Orlievsky who confirmed that Mr Hiatt was at that meeting when she arrived at work just prior to 10 am and that no envelope was in the vicinity of the plaintiff's door.
12When evaluating what happened it is also necessary to refer to some matters that occurred on 17 May 2010, the following Monday. On that day, Mr Hiatt asked Ms Orlievsky, his personal assistant, to call the defendant to see whether a payment schedule had been served. He took this step after speaking to his lawyers and receiving advice that he ought to check whether the payment schedule had been served. He also sent an email asking whether the payment schedule had been served, in response to which Mr Elia, the person who was the author of the relevant payment schedule, sent him a copy of an earlier payment schedule from April 2010, but no copy of the payment schedule dated 13 May 2010 was provided.
13The plaintiff suggested that the evidence of Mr Hiatt had been corroborated and supported by documentary evidence:
(a) There was the fact that Mr Hiatt asked his solicitors for advice on 17 May 2010 prior to calling the defendant to check whether a payment schedule had been served. The file notes of the Solicitors support this and lead me to accept that the conversation did, in fact, occur.
(b) The mobile telephone records of Mr Hiatt and Ms Orlievsky which show their whereabouts on the morning of 13 May 2010. The expert evidence concerning the positioning of telephone reception towers supported this. Such evidence shows that Mr Hiatt could have made the calls from the plaintiff's Double Bay office on the morning of 13 May 2010.
(c) The telephone records of Mr Milgrom also show that he could have been in Double Bay on the morning of 13 May 2010, at the relevant times.
14Acceptance of the defendant's evidence would mean, of course, that Mr Hiatt would have removed the payment schedule and embarked on a duplicitous course of conduct. This was put to Mr Hiatt in these terms:
"Q. And the reason that you did that Mr Hiatt I want to suggest is because on 13 May having concluded your meeting with Mr Milgrom shortly after 9am you left your office to travel elsewhere, returned before 10am when your assistant arrived, removed the envelope containing the payment schedule from below the door of suite 303 and decided upon a course of action, namely concealing the payment schedule so as to enable you to seek summary judgment?
A. That's incorrect, it's ridiculous."
15It was submitted that such a suggestion involved Mr Hiatt taking, at least, the following steps:
(a) keeping the payment schedule after 13 May 2010 but removing it from the plaintiff's office [noting that Ms Mergelian and Ms Orlievsky did not see any such document prior to 20 May 2010 so therefore he had to have removed it];
(b) having Ms Orlievsky contact the Defendant by telephone and ask about the missing payment schedule, despite actually having the payment schedule [noting that it was suggested to Ms Orlievsky by an officer of the defendant that there was to be no payment schedule issued];
(c) emailing the defendant on 17 May 2010, asking it to " confirm whether or not Nahas will be issueing [sic] a payment schedule to sand excavation for its claim for Spring Street Bondi Junction works for the month of April 2010 ", despite already having the fortune of the defendant denying the existence of a payment schedule;
(d) receiving, even more fortuitously, from Mr Elia of the defendant a payment schedule which was sent on 15 April 2010, not being the payment schedule which he had already taken on 13 May 2010;
(e) returning the payment schedule to the plaintiff's office on 20 May 2010 for no apparent reason, despite his previous good fortune in the defendant's consistent failure to produce any evidence of a payment schedule being created, dated, finalised or served on the plaintiff on 13 May 2010 during the correspondence on 17 May 2010;
(f) waiting for Mr Younan to discover that there was mail at the door of the plaintiff's office on 20 May 2010 [noting that the plaintiff was no longer using that office space at that time]; and
(g) being fortunate that Mr Younan did not simply ignore this mail which was not his and apparently had nothing to do with him, but instead chose to tell Mr Milgrom that he should contact his sister, Ms Orlievsky, because there was some mail at the door of the plaintiff's office which she should collect.
16Quite apart from suggesting the inherent unlikelihood of such a scenario, the plaintiff puts that clearly the defendant did not serve any payment schedule on 13 May 2010 and that in some misconceived attempt to belatedly serve the payment schedule it was placed at the plaintiff's office by some representative or agent of the defendant on 20 May 2010. Ms Orlievsky's reaction upon finding this document in the company of Mr Younan is said to be instructive; according to Mr Younan, who was called by the defendant, she said, " It's too late Peter ."
17It should also be noted that there is additional unchallenged evidence that at other times after the morning of 13 May 2010 there was no delivery to the plaintiff's office. That evidence is as follows:
(a) Mr Hiatt's evidence that he attended the plaintiff's office on 14 and 15 May 2010, and that there was no payment schedule at the plaintiff's office on these dates;
(b) the evidence of Ms Mergelian, who worked in an office next door to that of the plaintiff, that she did not observe any payment schedule at, or being delivered to, the plaintiff's office on 17 and 18 May 2010, this being after the date on which the plaintiff vacated the office.
18The other matters which the plaintiff suggests support its case are:
(a) the building where the plaintiff's office was located was familiar to the defendant, as it had weekly meetings at that building;
(b) a meeting was actually held by representatives of the defendant at the building where the plaintiff's office was located on 20 May 2010;
(c) the first time that the payment schedule was ever provided to the plaintiff by email was on 20 May 2010 by Mr Elia, despite express requests by Mr Hiatt that the document to be provided on 17 May 2010. The defendant admits that it sent the wrong payment schedule to the plaintiff on 17 May 2010. Both Mr Gary Cory and the General Counsel of the Defendant, Ms Maria Kavaratzis, were copied in on Mr Elia's email of 17 May 2010, whereby the wrong payment schedule was sent. The Defendant has not satisfactorily explained why the alleged correct document was not then sent on 18 or 19 May 2010, despite three of the defendant's employees being party to correspondence sending the wrong payment schedule; and
(d) the fact that the defendant could send the payment schedule by email to the Plaintiff on 20 May 2010 but did not send it by email on 13 May 2010 is also not explained. Clearly the document was capable of being sent by email. It was suggested by the plaintiff that the only rational explanation for the failure to email the payment schedule on 13 May 2010, despite emailing it on 20 May 2010, is that the payment schedule had not been completed by 13 May 2010. However, that suggestion ignores the expert evidence that the relevant file was first created on Mr Elia's computer on 12 May 2010.
19The defendant, for its part, suggested that there were a number of reasons, particularly those related to the financial situation of the plaintiff, which support their version of events and the necessary hypothesis that Mr Hiatt hid the document and planned a course of deception, for the purpose of bringing the present proceedings.
20Before turning to consider the credibility of the various witnesses, it is worth noting the objective facts which the defendant puts in support of its version of events.
21Those objective matters were as follows:
(a) t hat the plaintiff was in financial difficulties;
(b) that the relevant payment claim was clearly an inflated payment claim, which the plaintiff did not want to be subject to scrutiny; and
(c) that there was personal motivation involved, resulting from what was said to be the heated predicament between the plaintiff and the defendant.
22Turning firstly to the financial matters, the following is said to be illustrative:
"Sand Excavation failed to pay rent for the Cross Street address for March and April 2010 (Hiatt, T182.9-11 and T.183-20-34); and the Time Telecom records (tab 15, exhibit 7) which show:
(a) consistent default in the period February to May 2010;
(b) Sand Excavation was unable to pay its accounts, initially in the sum of $483.38 (26 February 2010) and subsequently in the sum of $1,135.44 (28 April 2010);
(c) weekly enquiries and repeated warnings of the impending disconnection of services; and
(d) various promises being made by "Inna" of impending payment of part of the amounts due to maintain services (see comments for 22 April that "they are having trouble getting money through the door..." and for 11 May that "she's waiting for money to come in from some clients")."
23This summary accurately reflects the evidence. That evidence indicates that the plaintiff experienced some difficulty in paying some suppliers. However, without any detailed evidence as to their financial circumstances it is not possible to conclude that the plaintiff was in substantial financial distress.
24In respect of the claim that the payment claim was inflated, the defendant's relevant submissions were as follows:
"73. The payment claim the subject of these proceedings was for an amount of $1,198,789.39. This was issued on 30 April 2010 at a time when, two weeks earlier:
a. Nahas Construction indicated that "$Nil" was due and payable by its payment schedule dated 15 April 2010 (Elia affidavit 24 August 2010, tab 7 of exhibit SE-1) in reply to Sand Excavation's payment claim (claim 4) dated 30 March 2010 which was in the amount of $704,000; and
b. Sand Excavation' s remaining works under the contract were taken out of its hands by Nahas Construction by written notice dated 14 April 2010 (Elia affidavit 24 August, paragraphs 13 and 14, tab 3 of exhibit SE-1).
73. Accordingly, Robert Hiatt was angry at Nahas Construction and he was in financial distress as at 30 April 2010.
74. Sand Excavation did not proceed to adjudication on either the 28 February 2010 payment claim or the 30 March 2010 payment claim after receiving Nahas Construction's payment schedules. The reasonable inference to be drawn in this circumstance is that Sand Excavation did not want any scrutiny of the merits of its claims.
75. It is readily apparent that the 30 April 2010 payment claim is an inflated claim as:
a. the Subcontract sum was $800,000 (see clause 3(a) of the contract, Elia affidavit 24 August 2010, tab 1 of exhibit SE-1) whereas the claim is for $1,198,789.39
b. the previous claim dated 30 March 2010 was for $740,000 (Nahas, T57.40-45);
c. Sand Excavation was only on site for two weeks after the 30 March payment claim before the works were taken out of its hands on 14 April 2010, and no works were carried out by Sand Excavation after 14 April 2010 (Elia affidavit 24 August 2010, paragraphs 13 and 14; tab 3 of exhibit SE-1);
76. it is inconceivable that Sand Excavation could have performed works to a value of $494,789.39 (being the difference in the amount claimed by the 30 March payment claim and the 30 April payment claim) in two weeks."
25The critical matter is of course what was said in paragraph 76 above, namely, whether there is any possibility that the relevant works could have been performed. It is clearly a very substantial claim but, in the absence of any detailed evidence about the extent of the works, it is difficult to draw a conclusion on that possibility.
26In so far as the personal motivation is concerned, it is abundantly clear that there was deep division between the plaintiff and the defendant, as the plaintiff had been removed from the work and the personal difficulties had reached a stage where Mr Hiatt had to ask Ms Orlievsky, his personal assistant, to ring the defendant, rather than make the call himself.
27I turn to the question of the credit of the various witnesses.