RTA v John Holland
[2006] NSWSC 567
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2006-07-03
Before
Macready J
Source
Original judgment source is linked above.
Judgment (24 paragraphs)
Background history 4 The plaintiff's submissions helpfully set out the background history and I will incorporate it with some amendment in this judgement. 5 The plaintiff entered into a contract with the first defendant on or about 8 September 2003 for construction work to create an 8 kilometre dual carriageway and associated bridges in an area to the north of Kiama, NSW. The General Conditions of the contract are based on NPWC3 (1981). 6 The project included an area approximately 300 metres long known as "Cut 4". Cut 4 is located in the vicinity of the town of Bombo and accommodates the dual lane carriageway as well as on-loading and off-loading ramps to the Bombo Interchange Bridge. 7 On 2 February 2006 the first defendant made a payment claim, purportedly both under clause 42.1.1 of the contract and section 13 of the Act for $16,577,648.21 in respect of works up to and including 30 January 2006. 8 The plaintiff, in response to the payment claim dated 2 February 2006, served its payment schedule on 15 February 2006 proposing to pay an amount of $738,033.42. 9 Part of the first defendant's payment claim included a claim for an amount of $7,965,509.13 that the first defendant asserts to be due in relation to alleged instructions given by the Superintendent between November 2003 and March 2004 affecting works in Cut 4 because of the presence of a disused detonator dump. The parties have referred to this claim in short form as the detonator dump claim. On 17 March 2005 the Superintendent, pursuant to clause 45.2(a) of the contract, determined that $1,815,458.61 was payable in respect of the "detonator dump" claim. The plaintiff has paid this amount. 10 The first defendant at paragraph 1.11 of its Adjudication Application requested the Adjudicator to determine the amount of the "detonator dump" claim only, that is, $7,965,509.13 and not the total amount claimed in the payment claim. 11 On 20 March 2006 the Adjudicator determined that the plaintiff was to pay the first defendant the amount of $5,583,794 . The amount of the determination comprises $4,845,760.59 for the detonator dump claim and $738,033.42; being the amount the plaintiff proposed paying the first defendant in its payment schedule. 12 It was pursuant to consent orders made by Bergin J on 28 March 2006 that the first defendant undertook, until further order, not to request an adjudication certificate under s 23 of the Act or to file any such certificate as a judgment debt under s 25. The same orders contain a regime for the plaintiff to provide security for the amount of the determination, plus interest, pending the determination of the summons. The jurisdiction submission 13 The submissions made by the plaintiff to the Adjudicator are contained in the Adjudication Response. In paragraphs 2, 10, 11, and 64-84 of those submissions, the RTA submitted that the Adjudicator had no jurisdiction to determine the Application. The submission was that the Adjudicator did not have jurisdiction because he was being asked to perform a dispute resolution role in relation to an extension of time claim under the contract and not a valuation role in relation to an amount of a progress payment under section 9(a) of the Act. The argument was expressed as follows in paragraph 80 of the plaintiff's Adjudication Response: "An Adjudicator under the Act cannot be an arbiter of a contested EOT claim, which (in the present case) has not only been determined by the Superintendent but has been referred to discussion with the Principal under clause 45.2(b) of the Contract and is now subject to the Expert determination process under clause 45.3. The adjudication of such claims is beyond the object of the Act. The resolution of an EOT claim does not call for the adjudicator to exercise a valuation function, but rather the Adjudicator is being asked to stand in the shoes of the Superintendent in respect of a determination he made under a dispute resolution clause - ie, clause 45.2(a). This is fundamentally different from the situation where an Adjudicator is asked - and is permitted - to stand in the shoes of the Superintendent when the Superintendent is assessing a Payment Claim under the Act." 14 At this stage it is not necessary to go into the full details of the argument that was advanced but merely to see whether the adjudicator considered it. Did the adjudicator consider the jurisdiction submission? 15 A reading of the determination shows that there is no express consideration of the submission. In an early section of the determination dealing with the "procedural history and jurisdiction" the Adjudicator found various facts, such that the work was construction work, which were necessary to give him jurisdiction. Then immediately after making such findings the Adjudicator in clause 5 states that he has "considered" "the Adjudication Response and the documents contained therein". In Timwin Construction Pty Ltd v Façade Innovations Pty Ltd [2005] NSWSC 548 at [38] - [40] McDougall J stated: "A requirement to consider, or take into consideration, is equivalent to a requirement to have regard to something … [a] requirement to "have regard to" something requires the giving of weight to the specified considerations as a fundamental element in the determination, or to take them into account as the focal points by reference to which the relevant decision is to be made". 16 The statement in clause 5 could not, in my view, amount to a consideration of the submission as to jurisdiction, especially in the context of a statutory obligation to give reasons in s 22(3)(b) and coming as it did immediately after the Adjudicator turned his mind to making relevant factual decisions on jurisdiction. 17 In the section of the report that dealt with "Reasons for the determination" and a subheading of "Explanations and Overview" he made the following comments: "6.2 Both parties have provided submissions that are additional to the entitlements provided under the various sections of the Act and were not requested pursuant to section 21(4) (a) of the Act. These additional submissions have not been considered in determining the adjudication application." 18 It is plain that what the Adjudicator was referring to were a series of letters written after the plaintiff had filed its adjudication response. The first defendant had written to the adjudicator pointing out that the submission as to jurisdiction had not been included in the payment schedule and therefore should not be taken into account by the Adjudicator. This short series of correspondence finished with a note from the Adjudicator saying somewhat elliptically that he would only be considering material that was permissible under the Act in the determination. 19 The Adjudicator dealt with the parties' submissions in a detailed and careful manner. On a number of occasions he picked up the point that a matter in the adjudication response had not been dealt with in the payment schedule and accordingly he refused to consider it. However nowhere in his determination does he say this about the jurisdiction submission which was contained in the adjudication response. 20 In my view the Adjudicator has failed to consider the plaintiff's jurisdiction submission. The reason why he did not do so is not apparent from his determination and it is only in this sense that there is an absence of reasons. 21 The first defendant raised the following matters in answer to the plaintiff's claim: