Total Construction Pty Ltd v Kennedy Civil Contracting Pty Ltd
[2023] NSWCA 306
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2023-12-07
Before
Meagher JA, Mitchelmore JA, Adamson JA
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] On 22 February 2022, the respondent, Kennedy Civil Contracting Pty Ltd (subject to a Deed of Company Arrangement) (Kennedy), entered into a contract with the appellant, Total Construction Pty Ltd (Total), for Kennedy to carry out construction works for a project in Arndell Park. Kennedy carried out those works between February 2022 and August 2022. Between 25 February 2022 and 28 June 2022, Kennedy served four payment claims on Total, using the system stipulated in the contract for service of claims, being the PayApps system. In response, Total served payment schedules on Kennedy, and made payments in accordance with the amount specified in each payment schedule. On 1 August 2022, Kennedy was placed into administration. On 4 August 2022, Kennedy served a further payment claim. In response, Total served a payment schedule with a negative amount, which meant that it would not make any payment. On 25 October 2022, the solicitors for Kennedy's administrators sent a letter and attachments to Total. The letter stated that Total was indebted to the company in the amount of $545,353.18 and demanded payment of that sum into the solicitor's trust account by a deadline, being 5 business days. The letter also stated, inter alia, that if Total failed to pay, Kennedy anticipated commencing proceedings to recover the outstanding amount by way of statutory debt pursuant to ss 15 or 16 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act), and urged a commercial resolution without the need for further recovery action. A number of tax invoices were attached, which were created on or about the date of the letter, by the amending and updating of earlier tax invoices submitted with earlier payment claims. Total did not serve a payment schedule within 10 business days of receiving the letter. On 23 November 2022, Kennedy commenced proceedings against Total in the District Court, claiming $545,353.18. Abadee DCJ held that the 25 October 2022 letter and attachments satisfied the requirements for a payment claim in s 13 of the Act and, in the absence of serving a payment schedule, Total was liable for the claimed amount. The issue on appeal was whether the 25 October 2022 letter and attachments constituted a payment claim within the meaning of s 13(1) of the Act. Total contended that, objectively, the letter was a demand for payment in respect of a pre-existing debt, supported by the attached documents. Total also contended that the 25 October 2022 letter and attachments did not comply with s 13(2) of the Act, or with s 13(6)(b). The Court (Mitchelmore JA, Meagher and Adamson JJA agreeing), allowing the appeal, held: (1) The 25 October 2022 letter was, objectively, a letter of demand for payment of an outstanding indebtedness by the stipulated deadline, failing which the solicitors would likely be instructed to commence recovery proceedings. The following features of the letter inform that conclusion: it was drafted on the letterhead of, and was signed by, solicitors acting for the administrators appointed to Kennedy; it asserted that Total was "indebted" to Kennedy; it was reasonable to infer that the attachments supported the assertion of current indebtedness; the deadline for payment was less than that permitted under the Act for service of a payment schedule; unlike previous payment claims, Total was instructed to make payment into the solicitors' trust account; the "outstanding amount" was not to be paid to satisfy any third party debts; it foreshadowed proceedings "to recover the outstanding [amount] as well as seek costs and interest"; and the solicitors urged Total to consider the benefits of early resolution and referred to "further recovery action": at [29]-[31]. Brookhollow Pty Ltd v R & R Consultants Pty Ltd [2006] NSWSC 1, considered. (2) The invoices that were attached to the letter served only to support its objective characterisation as a letter of demand. They were dated well before 25 October 2022; four out of the five invoices referred to an amount already paid and gave the balance as the amount due; only one of the invoices contained any detailed description of the relevant construction work; there was nothing on the face of one of the invoices to indicate the construction work to which it related; and the specified payment method was outdated by the directions in the letter. The statement in each invoice that each was a payment claim made under the Act was of no more than historical significance, when read with the terms of the letter: at [32]-[37]. Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Ltd (2004) 61 NSWLR 515; [2004] NSWCA 393; Coordinated Construction Company Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229; Fernandes Constructions v Tahmoor Coal (trading as Centennial Coal) [2007] NSWSC 381; Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391; Joye Group Pty Ltd v Cemco Projects Pty Ltd [2021] NSWCA 211; Piety Constructions Pty Ltd v Megacrane Holdings Pty Ltd [2023] NSWSC 309, considered; Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (In Liq) (2005) 64 NSWLR 462; [2005] NSWCA 409, distinguished.