The issues
6 It has been extremely difficult to understand the case that the builder seeks to make out. As I have noted, the list statement advances, with particulars, some fourteen alleged instances of "jurisdictional error". The written submissions that were filed in response to the Court's directions ("response" is a somewhat relative term, because they were filed late) did not address all the matters raised in the list statement; and they did not address at all what is now said to be a fundamental point. The oral submissions in court today appeared to have little in common with either the list statement or the written submissions.
7 To begin at the end: the arguments of Dr Doyle, who appeared for the builder, identified what he said were two key submissions. The first related to s 21(4) of the Act. In essence, Dr Doyle submitted thats 21(4) was to be added to the list of "basic and essential requirements" for validity of an adjudicator's determination that were addressed in Brodyn.
8 The second key submission related to the question of onus of proof. Dr Doyle submitted forcefully and at length that the Adjudicator had misdirected herself by imposing on the builder, as claimant, an onus of proof that was not to be found in the Act. Indeed, Dr Doyle put, the imposition of such an onus of proof was inconsistent with the scheme of the Act: in particular, s 32.
9 The s 21(4) point was raised in the list statement, in particular in the ninth to twelfth of the alleged jurisdictional errors. It was not, however, addressed in the written submissions.
10 By contrast, the onus point was not identified explicitly in the list statement. It was, however, addressed, although somewhat obliquely, in paragraph 9 of the written submissions.
11 An understanding of the builder's position was not assisted by Dr Doyle's failure to identify and address the real issues in dispute as they arise from the "pleadings". This put the proprietors at some disadvantage, and Mr Christie of counsel, who appeared for them, referred to this in his submissions. In particular, in support of the onus point, Dr Doyle produced a document (MFI "A") that identified some 30 instances in the determination "in which the onus question/adjudicator duty appears". Although some of those paragraphs had been identified in the list statement, it is impossible to discern from the list statement that the identification was for the purpose for which they were used in the course of oral submissions. It is unfortunate, and perhaps ironic, that a party claiming to have been deprived of natural Justice treats the other party in a way that is, quite frankly, not at all distinguishable.
12 Further, an understanding of the builder's case was not assisted by the repetitive, oblique and opaque way in which many of the points were addressed. Although I hope to deal with the principal points that were raised, it is possible that I may have overlooked some in the flurry of verbiage.
13 In those circumstances, I think that the safest course is to go to the contentions in the list statement and deal with them to the extent that it is necessary to do so, and then to go to the separate points made in submissions.
First challenge: denial of natural justice
14 The first challenge advanced in the list statement is that the Adjudicator breached the requirements of procedural fairness because, in some five identified ways, she determined the application on a basis for which neither party had contended, without giving them notice of her intention to do so.
15 The first matter particularised under this rubric was a finding as to s7(2) (b) of the Act. The Adjudicator found in substance that the Act applied to the whole of the contract, or the whole of the works carried out under it, notwithstanding that (as appears to be the case) the proprietors may intend to live in one of the dwelling units that is being constructed. Apparently, the proprietors did not raise that in their payment schedule, but it was a matter raised by the builder in its adjudication application. The builder's case was that the contract applied at least to the balance of the works. The Adjudicator concluded (perhaps on an insufficient appreciation of the proper construction of s7(2)(b)) that the Act applied to the whole of the contract and the contract work. Her determination was more favourable than that sought by the builder. She did not refuse any claim on the ground of the application of the Act. Indeed, in oral submissions in reply, I was informed that the point was not pressed because the builder apparently now agrees with the Adjudicator.
16 The second point under this rubric asserts that the Adjudicator made a finding as to the application of the contract without calling for submissions from the parties. Reference was made in particular to paragraphs 44 to 46 of the determination, in which the Adjudicator considered a claimed extra referred to as "Alucobond". The issue between the parties was whether the builder was entitled to be paid for materials supplied. The proprietors said that the builder was not, because none of the materials had been delivered to the site, nor had they been affixed to, so as to become part of, the building (the point as to non-affixation appears to have been common ground).
17 In those circumstances, the Adjudicator turned her mind to the relevant provisions of the contract: cl 37.3. It was not suggested (nor could it be) that cl 37.3 was irrelevant to this dispute.
18 Section 22(2)(b) of the Act requires an Adjudicator to have regard to "the provisions of the construction contract from which the application arose". The Adjudicator recorded at paragraph 45 her view that the builder's entitlement to be paid had to be assessed in accordance with the contract. With the very greatest of respect, she was entirely correct to reach this conclusion. Section 10(1)(a) makes the point in relation to construction work, and s10(2)(a) makes the point in relation to related goods and services. Thus, the Adjudicator had considered the dispute posed by the parties and taken into consideration the relevant provisions of the contract. She may or may not have had the benefit (if that is the correct word) of submissions from the parties on this point, but why that amounts to jurisdictional error is a matter that was never explained in any of the material to which the Court was taken.
19 The third point under this rubric deals with a similar issue (which I will call for convenience, after the relevant provision of the contract, the clause 37.3 issue). Again, it is suggested, the Adjudicator stepped outside the dispute posed by the parties when she considered the relevant matters. She did not. She dealt with the dispute that was posed for her consideration, and in doing so fulfilled the statutory command to consider the relevant terms of the contract. It might be noted that the general conditions of contract were included as an annexure, DHC5, to the adjudication application; and the annexure to those standard terms which set out particular details was likewise included, as DHC4.
20 The fourth matter referred to under this rubric relates to a Liquidated Damages Certificate. The Adjudicator is said to have found that it constituted part of the payment schedule although no party identified it as having that characteristic. There are two answers to this. The first is that on any view the proprietors made it clear through their "proposed payment schedule" that they proposed to set off liquidated damages, which had been assessed by the Superintendent at $77,500. (In this context, I think that the word "proposed" refers to the payment intended to be made and is not a word intended to qualify, or indicate some provisional or diminished status of, the document as a payment schedule.) The second answer is that in any event there was material before the Adjudicator that would have entitled her to conclude that the certificate in question was not merely referred to in, but physically sent with, the payment schedule. It is apparent that the "proposed payment schedule" is one of ten pages that had been faxed to the builder on 5 October 2007. The other nine pages can be identified by the fax transmission notes. They include the certificate as to liquidated damages.
21 The fifth matter referred to under this rubric, likewise, challenges the Adjudicator's finding as to the contents, or constitution, of the payment schedule. For the reasons that I have just given, there was material on which the Adjudicator was entitled to reach the conclusion that the Liquidated Damages Certificate did form part of the material supplied with, or in amplification of, the payment schedule.
22 As to each of the fourth and fifth matters, I have proceeded, without deciding, on the basis on the basis that if the Adjudicator's decision, that the Liquidated Damages Certificate did form part of the payment schedule, were wrong, then there might be a "jurisdictional" or Brodyn error. I should not be taken as assenting to that view.