This Plan sets the zoning, maps and development rules that apply to land in Nambucca: it lists permitted, consent and prohibited uses, technical limits (minimum lot sizes, building heights, floor‑space ratios), exemptions and site‑specific additional uses. It applies to the land on the Land Application Map (cl 1.3) and names the Council as the consent authority (cl 1.6).
It affects landowners, developers and State/local agencies: developers bear compliance costs and must obtain consent where required; the Council decides applications and may use discretion under specific clauses (for example cl 4.6).
This instrument is a local environmental plan (LEP) that establishes the statutory land-use framework for the Nambucca local government area. Mechanically it does the following.
Zones land and makes the Land Use Table operative, specifying what uses are permitted without consent, permitted with development consent and prohibited in each zone (see cl 2.1, cl 2.2, cl 2.3 and the Land Use Table in Part 2). The Land Zoning Map, Lot Size Map, Height of Buildings Map, Floor Space Ratio Map and other maps referenced in the Plan are the spatial instruments that determine applicable controls for individual parcels (cl 1.7; cl 2.2; see multiple provisions that reference the relevant maps such as cll 4.1, 4.3, 4.4).
Confers the consent authority role for this LEP to the Council, subject to the Environmental Planning and Assessment Act (cl 1.6). Development identified as requiring consent cannot lawfully proceed without that consent (see for example cl 2.6 and cl 2.7 which require consent for subdivision and demolition).
Prescribes exempt and complying development regimes (Part 3). Schedule 2 lists additional exempt development, Schedule 3 lists additional complying development and cll 3.1-3.3 set the conditions and exclusions for those categories, including an express prohibition on using exempt or complying pathways in designated environmentally sensitive areas (cl 3.3).
Fixes principal development standards such as minimum lot size for subdivisions (cl 4.1 and related clauses 4.1AA, 4.1B, 4.1C), height limits (cl 4.3), and floor space ratio limits (cl 4.4), and sets rules for calculating site area and FSR (cl 4.5). It also contains an exceptions mechanism allowing consent authorities to permit contraventions of development standards in particular circumstances, subject to specified tests and record‑keeping (cl 4.6).
Current sections
Direct links to the current provisions in Nambucca Local Environmental Plan 2010.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Aquaculture; Cellar door premises; Dual occupancies; Dwelling houses; Eco-tourist facilities; Extractive industries; Farm buildings; Heavy industries; Home industries; Intensive livestock agriculture; Intensive plant agriculture; Landscaping material supplies; Neighbourhood shops; Open cut mining; Plant nurseries; Residential accommodation; Roads; Roadside stalls; Rural supplies; Rural workers’ dwellings; Secondary dwellings; Shop top housing; Tourist and visitor accommodation; Any other development not specified in item 2 or 4
4
Prohibited
4 Prohibited
4 Prohibited
Amusement centres; Attached dwellings; Backpackers’ accommodation; Boarding houses; Camping grounds; Caravan parks; Cemeteries; Centre-based child care facilities; Co-living housing; Commercial premises; Correctional centres; Crematoria; Entertainment facilities; Exhibition homes; Exhibition villages; Function centres; Group homes; Health services facilities; Heavy industrial storage establishments; Heliports; Hostels; Hotel or motel accommodation; Independent living units; Industrial retail outlets; Industrial training facilities; Industries; Mortuaries; Multi dwelling housing; Recreation facilities (indoor); Registered clubs; Residential flat buildings; Respite day care centres; Restricted premises; Semi-detached dwellings; Seniors housing; Service stations; Serviced apartments; Sex services premises; Storage premises; Vehicle body repair workshops; Vehicle repair stations; Warehouse or distribution centres; Wharf or boating facilities; Wholesale supplies
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
Note.
If land, other than land specified in the Table to subclause (2), is required to be acquired under the owner-initiated acquisition provisions, the Minister for Planning is required to take action to enable the designation of the acquiring authority under this clause. Pending the designation of the acquiring authority for that land, the acquiring authority is to be the authority determined by order of the Minister for Planning (see section 21 of the Land Acquisition (Just Terms Compensation) Act 1991).
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Urban release areas
Part 6 Urban release areas
Part 6 Urban release areas
6
Arrangements for designated State public infrastructure
6 Arrangements for designated State public infrastructure
6.1 Arrangements for designated State public infrastructure
(1) The objective of this clause is to require satisfactory arrangements to be made for the provision of designated State public infrastructure before the subdivision of land in an urban release area to satisfy needs that arise from development on the land, but only if the land is developed intensively for urban purposes.
(2) Development consent must not be granted for the subdivision of land in an urban release area if the subdivision would create a lot smaller than the minimum lot size permitted on the land immediately before the land became, or became part of, an urban release area, unless the Director-General has certified in writing to the consent authority that satisfactory arrangements have been made to contribute to the provision of designated State public infrastructure in relation to that lot.
(3) Subclause (2) does not apply to—
(a) any lot identified in the certificate as a residue lot, or
(b) any lot to be created by a subdivision of land that was the subject of a previous development consent granted in accordance with this clause, or
(c) any lot that is proposed in the development application to be reserved or dedicated for public open space, public roads, public utility undertakings, educational facilities or any other public purpose, or
(d) a subdivision for the purpose only of rectifying an encroachment on any existing lot.
(4) This clause does not apply to land in an urban release area if all or any part of the land is in a region within the meaning of the Act, Division 7.1, Subdivision 4.
(1) The objective of this clause is to ensure that development does not disturb, expose or drain acid sulfate soils and cause environmental damage.
(2) Development consent is required for the carrying out of works described in the Table to this subclause on land shown on the Acid Sulfate Soils Map as being of the class specified for those works.
| Class of land | Works |
| 1 | Any works. |
| 2 | Works below the natural ground surface.Works by which the watertable is likely to be lowered. |
| 3 | Works more than 1 metre below the natural ground surface.Works by which the watertable is likely to be lowered more than 1 metre below the natural ground surface. |
| 4 | Works more than 2 metres below the natural ground surface.Works by which the watertable is likely to be lowered more than 2 metres below the natural ground surface. |
| 5 | Works within 500 metres of adjacent Class 1, 2, 3 or 4 land that is below 5 metres Australian Height Datum and by which the watertable is likely to be lowered below 1 metre Australian Height Datum on adjacent Class 1, 2, 3 or 4 land. |
(3) Development consent must not be granted under this clause for the carrying out of works unless an acid sulfate soils management plan has been prepared for the proposed works in accordance with the Acid Sulfate Soils Manual and has been provided to the consent authority.
(4) Despite subclause (2), development consent is not required under this clause for the carrying out of works if—
(a) a preliminary assessment of the proposed works prepared in accordance with the Acid Sulfate Soils Manual indicates that an acid sulfate soils management plan need not be carried out for the works, and
(b) the preliminary assessment has been provided to the consent authority and the consent authority has confirmed the assessment by notice in writing to the person proposing to carry out the works.
(5) Despite subclause (2), development consent is not required under this clause for the carrying out of any of the following works by a public authority (including ancillary work such as excavation, construction of access ways or the supply of power)—
(a) emergency work, being the repair or replacement of the works of the public authority required to be carried out urgently because the works have been damaged, have ceased to function or pose a risk to the environment or to public health and safety,
(b) routine maintenance work, being the periodic inspection, cleaning, repair or replacement of the works of the public authority (other than work that involves the disturbance of more than 1 tonne of soil),
(c) minor work, being work that costs less than $20,000 (other than drainage work).
(6) Despite subclause (2), development consent is not required under this clause to carry out any works if—
(a) the works involve the disturbance of less than 1 tonne of soil, such as occurs in carrying out agriculture, the construction or maintenance of drains, extractive industries, dredging, the construction of artificial water bodies (including canals, dams and detention basins) or foundations or flood mitigation works, and
(b) the works are not likely to lower the watertable.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
Building identification signs and business identification signs
sch.3-sec Building identification signs and business identification signs
Building identification signs and business identification signs
(1) Does not include signs that may be erected as exempt development under Schedule 2.
(2) Must not cover mechanical ventilation inlet or outlet vent.
(3) Must not incorporate flashing or moving components.
(4) If erected on a building, must not project beyond any part of the building on which it is erected.
(5) If erected over a public road (which includes a public footpath), the lowest point of the sign must be at least 2.6m above ground level (existing).
(6) Must not be externally illuminated.
(7) If on a heritage item, heritage conservation area or archaeological site, must comply with the following—
(a) no part may cover windows or architectural projections or other decorative features of the premises upon which it will be displayed,
(b) must be able to be removed without significantly altering or damaging the fabric of the heritage item, heritage conservation area or archaeological site.
(8) Maximum advertising areas as follows—
(a) projecting wall sign—2m2,
(b) above awning sign—3m2,
(c) pole or pylon sign—6m2.
(9) Maximum height of pole or pylon sign—6m above ground level (existing).
(10) Must relate to the lawfully established use and occupation of the land.
(11) Must not be more than 3 signs displayed at the premises or place.
sch.3-sec-oc.2
Industrial development
sch.3-sec-oc.2 Industrial development
Industrial development
(1) Must be external alterations.
(2) Must only be carried out in Zone E4.
(3) Roofing must be of pre-coloured materials.
(4) Must be face brick, pre-coloured metal cladding, textured finish or painted masonry and ‘tilt-slab’ concrete, or a combination of these materials.
(5) Must not be constructed within 1m of any easements or sewer mains.
(6) The floor space ratio (including any mezzanine areas) must not be more than 0.5:1.
(7) Ground level (existing) must not be cut or filled so as to alter by more than 2.0m.
(8) The front setback must be at least 6m.
(9) Awnings or eaves must be at least 1m from the side and rear setbacks required by the Building Code of Australia for the intended use of the building.
(10) A minimum 2m wide landscape area must be provided along all street frontages.
(11) Parking spaces must be provided on the site at the rate of 1 space per 70m2 of gross floor area.
(12) Parking spaces and turning areas must comply with AS 2890.1:2004, Off-street car parking.
(13) Internal driveways must provide access to the building or separate occupancy to accommodate a rigid truck that is at least 11m long, in compliance with AS 2890.1:2004, Off-street car parking, sufficient to allow such trucks to enter and leave the site in a forward direction.
(14) All internal roadways must be constructed to an all-weather bitumen or concrete surface in accordance with Council’s Aus-Spec #1 Design and Construction Specifications.
(15) Storage areas and waste bins must be screened from the street frontage and provided behind the building line.
Industrial development on land below the flood planning level
sch.3-sec-oc.4 Industrial development on land below the flood planning level
Industrial development on land below the flood planning level
(1) A floor level survey plan, prepared by a registered surveyor, must be submitted to the principal certifying authority before the construction of wall frames of a building located on land below the flood planning level.
(2) The plan must show that the floor levels are above the flood planning level.
Schedule 4
Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Nambucca Local Environmental Plan 2010.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Nambucca in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to promote development that is ecologically sustainable,
(b) to encourage growth in a planned and co-ordinated manner which will be economically and ecologically sustainable,
(c) to protect, manage and enhance areas of high quality landscape, natural and scenic resources and environmental values, including water resources, wildlife habitat and corridors,
(d) to protect and promote the use of rural resources for agricultural and primary production and related processing service and value adding industries,
(e) to provide opportunities for rural, residential and hobby farm lifestyles on suitable land that is accessible and provided with adequate infrastructure,
(f) to protect places and buildings of archaeological or heritage significance, including Aboriginal relics and places.
Creates local, use‑specific and site‑specific controls: heritage protections (cl 5.10 and Schedule 5), acid sulfate soils regimes (cl 7.1), aquaculture rules (cl 5.19 and Schedule 6), flood planning controls (cl 5.21), earthworks controls (cl 7.6), public land classification (cl 5.2 and Schedule 4), and others. It also lists a set of additional permitted uses for particular lots in Schedule 1.
Implements spatial prohibitions and specific use limits. Examples: canal estate development is expressly prohibited (cl 2.9); temporary land uses are permitted only up to 52 days in any 12 month period unless otherwise specified (cl 2.8); and various floor‑area or guest limits are set for uses such as bed and breakfast, home business and neighbourhood shops (cl 5.4).
Preserves continuity and transition for pending applications and prior instruments. The Plan repeals prior local environmental plans applying to the area (cl 1.8) and contains savings for development applications made but not finally determined at the time of commencement (cl 1.8A).
The Plan also states its policy aims (cl 1.2), including ecological sustainability, protection of landscape and water resources, support for arts and cultural activities and the protection of heritage. Those aims are expressed as the instrument’s declared objectives but the operative text implements those aims by controlling uses, requiring management plans and setting locational and design standards (see cl 1.2 and the many operational clauses referenced above).
Practically, the Plan relocates much of the decision rulemaking to the Council as consent authority, while preserving State policy primacy where a State environmental planning policy (SEPP) prevails over this Plan (cl 1.9). The Plan also cross‑references and conditions other approvals under State legislation: for example it requires heritage notifications to the Heritage Council and consultation with Aboriginal communities where relevant (cl 5.10), and it prescribes when public authorities can carry out works without consent under certain SEPP chapters (cl 5.12).
All operative constraints, conditions and definitional matters are contained in the Plan text, the schedules and the referenced maps. A practitioner must read the maps, the Land Use Table and the relevant schedules together with the clauses that set process and standard tests before advising on a specific site.
Main concepts
The Plan rests on a small set of organising legal concepts that determine how land may be used, developed and subdivided within the Nambucca area.
Zoning and the Land Use Table. The Plan’s primary regulatory mechanism is zoning. Clause 2.1 lists the zones; cl 2.2 ties those zones to the Land Zoning Map; and cl 2.3 makes the Land Use Table the operative matrix that pairs each zone with zone objectives and a list of uses that are permitted without consent, permitted with consent and prohibited. The consent authority must have regard to the zone objectives when determining applications (cl 2.3(2)). The schedule regime (Schedule 1) permits specific exceptions for particular lots (cl 2.5).
Maps as legal instruments. Clause 1.7 treats named maps approved by the local plan‑making authority as the authoritative spatial records for the Plan and requires maps to be kept and made available. Clauses throughout the Plan make direct reference to the Lot Size Map, Height of Buildings Map and Floor Space Ratio Map when fixing development standards (for example cll 4.1, 4.3, 4.4, 4.5). Thus the mapping layer is an integrated part of the statutory rule set.
Consent, exempt and complying development. The Plan differentiates development that requires development consent from development permitted without consent. Part 3 identifies exempt development (Schedule 2) and complying development (Schedule 3) and sets tests and exclusions (cll 3.1-3.3). Notably exempt or complying pathways are excluded where a site is an environmentally sensitive area as defined in cl 3.3. The Plan also cross‑references the State SEPP that contains the State‑wide exempt and complying codes (see notes in Schedules and cl 3.1).
Principal development standards and exceptions. Part 4 sets principal standards: minimum subdivision lot size (cl 4.1 and subclauses addressing community titles, split zones and exceptions), height limits (cl 4.3), FSR (cl 4.4) and calculation rules (cl 4.5). Clause 4.6 provides a mechanism to depart from development standards if the applicant satisfies the consent authority of specific tests, while identifying categories that cannot be varied under that clause (cl 4.6(8)).
Site‑specific and nature‑based constraints. The Plan incorporates specialised constraints where particular environmental, heritage or technical risks are present. Examples include acid sulfate soil management (cl 7.1), heritage consent and notification requirements including the ability to require heritage management documents or conservation management plans (cl 5.10(4)-(6)), bush fire hazard reduction permissions (cl 5.11) and detailed flood‑planning tests and considerations for land in the flood planning area (cl 5.21). Aquaculture is regulated by a mix of site selection and operational conditions in cl 5.19 and Schedule 6.
Coordination with other laws and agencies. The Plan frequently cross‑references State legislation and SEPPs, preserves State policy primacy where applicable (cl 1.9), and identifies State acquiring authorities for land reservation/owner‑initiated acquisition purposes (cl 5.1 and the Land Reservation Acquisition Map). Clause 1.9A provides a limited suspension of private covenants and instruments where they would otherwise restrict development permitted by the Plan, subject to enumerated exclusions (cl 1.9A(1)-(3)).
Staging and infrastructure for urban release areas. Part 6 establishes procedural preconditions for major urban release areas, including requiring satisfactory arrangements for designated State public infrastructure before subdivision (cl 6.1), and requiring a development control plan for staged, serviced release (cl 6.2).
Overall, the Plan’s legal logic is to allocate decision‑making to the Council while embedding technical standards, spatial limits and consultation/notification duties into the consent process. The Plan ties many of its policy aims (stated in cl 1.2) to concrete controls and information requirements that an applicant must satisfy before development consent can be granted.
Who it affects
The planning framework reaches multiple categories of actors and assigns different rights, obligations and decision roles.
Landowners and prospective developers. The Plan determines what a landowner can lawfully do on their parcel: whether uses are prohibited, permitted with consent, or permitted without consent in their zone (cl 2.3; see the Land Use Table). Subdivision, demolition and erection of dwellings have particular consent triggers (cl 2.6; cl 2.7; cl 4.2A). Owners of lots covered by Schedule 1 have site‑specific permitted uses. Owners seeking exemptions or complying development must ensure they are not in an environmentally sensitive area (cl 3.3).
Nambucca Council. The Council is the consent authority for transactions under this Plan, subject to the Act (cl 1.6). The Council must apply zone objectives when assessing development applications (cl 2.3(2)), ensure infrastructure availability for proposed developments (cl 7.4), and it has powers to classify or reclassify public land as operational or community land in accordance with the Local Government Act (cl 5.2 and Schedule 4).
State agencies and Ministers. The Plan identifies State agency interests and designated acquiring authorities for particular classes of reserved land (cl 5.1 and Land Reservation Acquisition Map). It also defers to SEPPs where they prevail over the Plan (cl 1.9) and preserves the ability of public authorities to carry out certain infrastructure development under SEPP (cl 5.12). The Governor approved certain clauses under section 3.16 of the Act, as noted in cl 1.9A.
Heritage and Aboriginal communities. The Plan imposes specific obligations where development affects heritage items, heritage conservation areas, archaeological sites or Aboriginal places of heritage significance. The consent authority must consider heritage impacts, can require heritage management documents or conservation plans and must notify the Heritage Council and local Aboriginal communities in particular circumstances (cl 5.10(4)-(9)).
Primary industry and aquaculture operators. The Plan contains an aquaculture regime (cl 5.19 and Schedule 6) that sets minimum siting and operational requirements, including exclusion zones and design/operational rules for pond and tank systems. Intensive livestock agriculture is subject to assessment criteria and, under thresholds, may be permissible without consent only if certain locational criteria are satisfied (cl 5.18).
Event organisers and users of public reserves and roads. Clause 7.8 permits temporary events on public reserves and roads without development consent for up to 52 days in any 12 month period, subject to other approvals under other Acts.
Infrastructure and service providers. The Plan requires the consent authority to be satisfied that essential public utility infrastructure is available or that arrangements are in place to make it available when required (cl 7.4). For urban release areas, designated State public infrastructure must be arranged before certain subdivisions proceed (cl 6.1).
Developers relying on exempt or complying pathways. Those operators must be aware that exempt/compliant paths are not available in environmentally sensitive areas (cl 3.3) and that particular standards, including Building Code compliance and BASIX,related requirements, apply where relevant (cl 3.1(3)-(5); cl 4.6(8)(b)).
Who effectively decides and who bears costs. The primary decision‑maker under the Plan is the Council as consent authority (cl 1.6). Costs fall on applicants and landowners: preparing heritage management documents, acid sulfate soils management plans, flood risk mitigation measures, or satisfying aquaculture operational requirements will be borne by proponents (cl 7.1(3); cl 5.10(5)-(6); cl 5.21). State agencies bear responsibility for providing or certifying certain infrastructure or for taking over acquisition responsibilities under cl 5.1. Aboriginal communities are recipients of notification and consultation duties but the Plan does not set financial compensation mechanisms for impacts.
Concentrated benefits and diffuse costs. Specific parcels gain bespoke rights via Schedule 1 (for example permissive uses at defined lots), which yields concentrated benefits to particular landowners. Costs of compliance for many development types, such as heritage conservation, flood safe design and aquaculture operational standards, diffuse across applicants and increase pre‑application transactional costs for developers.
In short, the Plan allocates rights to use land by zone and attaches a range of procedural and technical obligations to applications, shaping who must act and who bears compliance costs.
Key duties and rights
The Plan sets out discrete duties for consent authorities, applicants and landowners and specific rights pertaining to the carrying out of permitted development.
Consent authority duties and discretions
Apply zone objectives when assessing applications (cl 2.3(2)). That is a statutory consideration rather than a mere aspiration.
Refuse or grant consent for development specified as requiring consent, applying the tests and mandatory preconditions in the Plan. For example, cl 5.21 requires the consent authority to be satisfied that proposed development in the flood planning area is compatible with flood function and will not adversely affect flood behaviour, safe occupation or the environment (cl 5.21(2)).
Keep records of assessments under the exceptions to development standards procedure when an applicant seeks a variation (cl 4.6(4)). The consent authority must also not grant certain subdivision variations in rural and conservation zones that would result in specified outcomes (cl 4.6(6)).
Require heritage management documents or heritage conservation management plans prior to consent for works affecting heritage items or areas, and to notify the Heritage Council or Aboriginal communities as required by cl 5.10(5)-(9).
Applicant and landowner duties
Obtain development consent where the Plan requires it (e.g. subdivision cl 2.6; demolition cl 2.7; many land uses in the Land Use Table). Carrying out development without required consent is inconsistent with the Plan and may attract action under the Act (the Plan establishes the consent regime throughout).
Prepare and provide management plans where mandated: for acid sulfate soils (cl 7.1(3)), heritage management documents (cl 5.10(5)), and in urban release areas the development control plan must be prepared for the land before development consent is granted (cl 6.2).
Ensure exempt or complying development meets the conditions of Part 3 and is not on an environmentally sensitive area identified in cl 3.3.
Meet technical limits on particular uses where the Plan prescribes quantitative controls, for example bed and breakfast guest/room limits, home business and home industry floor area caps, neighbourhood shop floor area caps and neighbourhood supermarket size limit (cl 5.4).
Express rights
Permitted without consent uses. Where the Land Use Table lists a use as permitted without consent, an owner may carry out that development provided it meets the Plan’s requirements for exempt development (see cl 2.3(1)(b), cl 3.1 and Schedule 2 where applicable).
Complying development pathway. Development specified in Schedule 3 that complies with the listed standards may be undertaken as complying development (cl 3.2), subject to relevant building code and local requirements such as certification under the Local Government Act where on‑site effluent is involved (cl 3.2(3)(b)-(c)).
Notification, consultation and referral duties
Heritage: notify the Heritage Council as required for archaeological sites (cl 5.10(7)) and for demolition of nominated State heritage items (cl 5.10(9)). For Aboriginal places, the consent authority must notify local Aboriginal communities and consider responses (cl 5.10(8)).
Flooding and natural hazards: must consider projected changes as a result of climate change and the design and scale of buildings relative to flood behaviour when deciding applications in flood planning areas (cl 5.21(3)).
Limitations on other instruments
Suspension of private covenants and similar instruments. Clause 1.9A provides that private agreements that restrict carrying out development permitted by the Plan do not apply to the extent necessary to enable development under the Plan, but the clause is subject to exclusions including covenants imposed by the Council and conservation agreements under named Acts (cl 1.9A(1)-(2)). This is a specific statutory qualification on private instruments.
Procedural and evidentiary duties
Demonstrate compliance with development standards or meet the cl 4.6 variation test: applicants seeking to contravene a development standard must demonstrate that compliance is unreasonable or unnecessary and that there are sufficient environmental planning grounds (cl 4.6(3)). The consent authority must keep a record of that assessment (cl 4.6(4)).
Rights not created by the Plan
The Plan does not itself create compensation rights under many circumstances; instead it identifies acquisition authorities where owner‑initiated acquisition might occur and preserves statutory acquisition processes in cl 5.1. Compensation and acquisition processes will follow the Land Acquisition (Just Terms Compensation) Act as referenced.
These duties and rights operate in the statutory environment established by the Environmental Planning and Assessment Act and the various State Acts the Plan cross‑references. Practitioners must read the Plan’s duties alongside the Act’s procedural and enforcement regimes.
Penalties and enforcement
The Plan itself primarily sets land‑use rules and procedural duties; it does not create a separate schedule of criminal penalties within its text. Enforcement arises from the statutory planning regime that the Plan sits within and from specific applicable State Acts that the Plan references.
What the Plan provides as enforcement-relevant mechanisms
Development without required consent is contrary to the Plan. The Plan identifies categories of development that require development consent (for example cl 2.6 subdivision, cl 2.7 demolition and numerous items in the Land Use Table). The Plan therefore creates conditions that, if breached, put the carrying out of the works or use beyond what the LEP authorises.
Consent conditions and covenants. The Plan contemplates that consent authorities can impose conditions on development consent, including covenants to prevent “double dipping” in floor space calculations (cl 4.5(9)-(10)). Such conditions form part of the consent and are enforceable as conditions of approval.
Notifications and referral obligations. The Plan requires statutory notifications and referrals prior to consent in specific circumstances (cl 5.10(7)-(9)). Failure to comply with referral processes would undermine the correctness of any consent decision and could be a ground for review.
Requirements for management plans. The Plan mandates management plans and technical reports in some circumstances, for example acid sulfate soils management plans (cl 7.1(3)), heritage management documents (cl 5.10(5)) and compliance with aquaculture industry development plans (cl 5.19). Non‑provision or inadequate plans may attract refusal of consent or conditions requiring rectification.
What the Plan does not do in express terms
The LEP text does not enumerate monetary fines or criminal sanctions. Those enforcement tools and sanctions are contained in the Environmental Planning and Assessment Act and related regulations, not in the LEP provisions themselves. The Plan therefore relies on the broader statutory enforcement mechanisms available under the Act and other legislation it references.
The Plan does not set out administrative appeal pathways in full. Appeals and legal challenges to decisions made under the Plan would proceed under the Act’s administrative review and merits review provisions and under judicial review principles, though those procedural rules are outside the LEP text.
Interaction with other enforcement regimes
Other Acts may impose penalties. The Plan flags that other approvals under other Acts may be required (for instance Local Government Act approvals for on‑site effluent systems or road use, cl 3.2(3) and cl 7.8 note), and those regimes include their own compliance and enforcement machinery.
Heritage and Aboriginal protections. The Plan requires referral and consultation in heritage contexts (cl 5.10). Non‑compliance with heritage statutory requirements under the Heritage Act or the National Parks and Wildlife Act will attract the enforcement regimes those Acts set out.
Practical inference for practitioners
Non‑compliance with a Plan rule (for example carrying out a prohibited use, failing to obtain consent for subdivision) will expose the landowner or developer to action under the Environmental Planning and Assessment Act and potentially other applicable Acts. The Plan provides the substantive legal basis for determining whether the activity was authorised.
Enforcement remedies and penalties will therefore be drawn from the Act and applicable State statutes, and cannot be read off the LEP text alone. For precise enforcement mechanisms and monetary penalties, practitioners must consult the Environmental Planning and Assessment Act, the relevant SEPPs and other statutory instruments referenced by the Plan.
In short, the Plan sets the rights and obligations; enforcement and penalties are implemented through the wider statutory enforcement framework rather than by explicit penalty clauses within the LEP.
How it interacts with other laws
The Plan contains numerous cross‑references to State legislation and State Environmental Planning Policies. Its operation is deliberately integrated with those instruments.
State policy primacy and SEPP interaction
Clause 1.9 expressly states that the Plan is subject to any SEPP that prevails over it as provided by section 3.28 of the Act. The Plan therefore yields to State policy instruments where they conflict or have express overriding effect. Practitioners must check relevant SEPPs such as the State policies named in the Land Use Table notes which may be relevant to particular proposals (for example SEPP (Housing) 2021 and SEPPs dealing with transport, resources, resilience, industry and primary production are explicitly noted).
Statutory Acts referenced and functional interaction
Heritage law. The Plan relies on the Heritage Act 1977 and the National Parks and Wildlife Act for heritage definitions and some obligations. Clause 5.10 cross‑references the Heritage Act and requires referral and consideration obligations consistent with State heritage law; archaeological disturbance and Aboriginal objects engage the National Parks and Wildlife Act (cl 5.10(1)-(3), (7)-(9) and notes).
Fisheries and aquaculture. Clause 5.19 and Schedule 6 cross‑reference the Fisheries Management Act 1994 and the Fisheries Management (Aquaculture) Regulation 2017 and the NSW Oyster Industry Sustainable Aquaculture Strategy. That means aquaculture development must align with fisheries licensing and biosecurity regimes administered under fisheries legislation and the industry development plans referred to.
Crown land and nature conservation. Clause 1.9A excludes from the suspension of covenants instruments within the meaning of the Crown Land Management Act 2016 and conservation agreements under the National Parks and Wildlife Act 1974. Clause 5.2 and the Schedule 4 classification provisions link to the Local Government Act 1993 for classification of public land and for discharge of trusts (cl 5.2 notes).
Land acquisition. Clause 5.1 invokes the Land Acquisition (Just Terms Compensation) Act 1991 to identify acquiring authorities in relation to the Land Reservation Acquisition Map. The Plan therefore slots into statutory acquisition mechanics for owner‑initiated acquisitions.
Local Government Act and road approvals. Several notes in the Plan indicate approvals under the Local Government Act 1993 and the Roads Act 1993 may be required for particular activities (for example cl 3.2(3)(c) concerning on‑site effluent systems and cl 7.8 note concerning events on roads and public reserves).
Biodiversity and conservation. Clause 3.3 defines environmentally sensitive areas for the exempt/compliant development exclusion and cross‑references the Coastal Management Act 2016, the Biodiversity Conservation Act 2016 and declared Ramsar or World Heritage areas. This imports State biodiversity protection thresholds into the LEP’s exempt/compliant regime.
Procedural overlaps and referral obligations
Heritage referrals to the Heritage Council (cl 5.10(7) and (9)) and notification of local Aboriginal communities (cl 5.10(8)) are procedural obligations that interact with statutory duties under the Heritage Act and Indigenous heritage protocols.
Flood planning references the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual, documents prepared at State level (cl 5.21(4)-(5)), importing their technical methods into decisions under the Plan.
Limitations on private instruments
Clause 1.9A suspends private covenants and agreements to the extent necessary to enable development under the Plan, but it explicitly excludes covenants required by the Council, certain Crown instruments and specified conservation agreements (cl 1.9A(1)-(3)). This interaction creates a limited statutory override of private restrictive instruments while protecting public and conservation interests.
Exemptions and State SEPPs
Where the State SEPP specifies exempt or complying development (for example State Environmental Planning Policy (Exempt and Complying Development Codes) 2008), that SEPP operates alongside the Plan. The Plan’s schedules record additional exempt and complying items and where they apply (Schedules 2 and 3). Practitioners must reconcile State SEPP provisions with Plan schedules and the environmentally sensitive area exclusion in cl 3.3.
In practice, the Plan does not operate in isolation. It imports State technical standards, procedural requirements and referral/notification duties, and it defers to SEPPs where they prevail. Applicants must therefore manage compliance across multiple statutory instruments and approvals.
Amendment history
The Plan text itself records a series of amendments and insertions by year and instrument reference across many clauses and schedules. The instrument’s amendment annotations indicate an active maintenance and update history. Representative, source‑grounded highlights include the following entries that appear in the Plan text.
Early amendments and insertions around 2010-2013: the Land Use Table and many clauses carry amendment annotations such as Am 2011 (363), Sch 15, and Ins 2011 (363), Sch 15. For example clause 1.9A was amended and inserted by instruments recorded as Am 2011 (363), Sch 15 [1] and subsequent amendments (cl 1.9A notes).
Community title and strata adjustments: Clause 4.1AA (minimum lot size for community title schemes) was inserted in 2011 (Ins 2011 (363), Sch 15 [30]) and later amended (2022 annotations in cl 4.1AA). Clause 4.2B (strata subdivisions in certain zones) contains amendment notes referencing 2011 and later years.
Exceptions, rural subdivision and dwelling provisions: Clauses dealing with rural subdivision, replacement dwellings and boundary changes (4.1B, 4.1C, 4.2 and 4.2A) reflect insertions and amendments in 2013, 2014 and 2018 (see cl notes showing Ins 2013 (35), Ins 2014 (105), Am 2018 (101), Sch 1 [9]).
Flood planning and floodplain risk management: Clause 5.21 includes references to a 2021 guideline and the Flood Risk Management Manual (published 2023) and cl 7.7 was inserted in 2021 (Ins 2021 (86), Sch 1[1]) with a subsequent amendment in 2023 (Am 2023 (609), Sch 2.12).
Exempt and complying development updates: Part 3 and Schedules 2 and 3 show amendments in 2011, 2019, 2021 and 2022, with annotations such as Am 2011 (363), Sch 15 [39]; 2019 (199), Sch 1 [4]; 2021 (86), Sch 1[3]-[7]; 2022 (832), Sch 1.17[9] and [10].
Recent repeals and insertions: Clause 7.2 is shown as repealed by 2025 (Rep 2025 (106), Sch 1[1]). Various other clauses contain recent amendment annotations up to 2025, indicating ongoing updates.
Schedule and mapping changes: Several schedules show amendment histories including Schedule 1 Am 2017 (123) and later instruments. Schedule 4 classification entries show multiple amendment notes across 2011-2023.
The Plan’s amendment notes are the source evidence of its modification history. They show incremental changes to operational clauses (for example subdivision rules in cl 4.1 and exceptions in cl 4.6), the introduction of new local provisions (for example aquaculture and floodplain risk management clauses inserted in later years), and updates to the Plan’s schedules and maps. Practitioners should consult the instrument as published on the NSW legislation and Planning Portal for the consolidated, in‑force text and the formal amendment instruments referenced in the marginal notes. The marginal amendment annotations in the Plan text themselves identify the year and legislative instrument number for many changes, providing a direct audit trail to the amending instruments.
Litigation history
The Plan text contains no case law citations and does not record any judicial or tribunal decisions. The Plan’s schedules and clauses do not list litigation or appeal outcomes.
What the Plan does indicate about dispute and review pathways
Notes in the Plan refer to the Environmental Planning and Assessment Act and its divisions (for example the savings provision in cl 1.8A references Division 3.5 of the Act), implying that challenges, merits review and applications for review of decisions will follow the Act’s statutory pathways rather than the LEP documenting case law outcomes.
The instrument anticipates situations that frequently attract litigation or review under the Act, such as requests to vary development standards under cl 4.6 and heritage consents where the Heritage Council is notified under cl 5.10. Those parts of the Plan create factual and legal tests that are commonly the subject of merits review or judicial review in the planning context, but the Plan does not itself narrate any decisions.
Practical note for practitioners
Because the LEP does not include a litigation history, practitioners advising on contested matters must search for decisions under the Environmental Planning and Assessment Act, the Land and Environment Court and relevant administrative review bodies for precedents interpreting cl 4.6 variations, heritage obligations in cl 5.10, flood planning tests in cl 5.21 and other contested provisions. The LEP flags the statutory context but does not substitute for case law research.
Where a development proposal raises novel questions under particular LEP clauses,for example use of the exceptions clause cl 4.6 or the application of cl 1.9A to private covenants,practitioners should check administrative and judicial authorities applying the Act and similar LEPs, and consider whether merits review rights under the Act or appeal routes are available.
In short, the LEP does not provide a litigation record. Any litigation history relevant to its interpretation and application must be sought in court and tribunal decisions, and in decisions under the Act.
Gotchas
The Plan contains numerous traps for the unwary. This section highlights concrete pitfalls grounded in the Plan text and cites the controlling clauses.
Maps and site specific controls are decisive
The operative controls for any parcel are the maps and schedules that accompany the Plan. Clause 1.7 makes named maps approved by the plan‑making authority legally operative. Practitioners must check the Land Zoning Map, Lot Size Map, Height of Buildings Map, Floor Space Ratio Map, Heritage Map and Flood Planning Map before advising. Failing to check the maps may result in mis‑advising on permitted uses, lot sizes, height and FSR limits (see cl 1.7; cl 2.2; cll 4.1, 4.3, 4.4).
Environmentally sensitive areas exclude exempt/compliant pathways
Schedule 2 and cl 3.1 permit exempt development only where the Schedule standards are met, but cl 3.3(1) prohibits exempt or complying development on any environmentally sensitive area as defined in cl 3.3(2). That definition reaches coastal waters, coastal lakes, coastal wetlands, declared aquatic reserves, Ramsar and World Heritage areas, land within 100 metres of those areas, land identified as high Aboriginal cultural significance or biodiversity significance, and listed parks and reserves among others. A development that would otherwise be exempt or complying may therefore require full development consent due to site sensitivity.
Suspension of covenants is limited
Clause 1.9A suspends agreements and covenants to the extent necessary to enable development under the Plan. The caveat is that the clause does not operate where the covenant was imposed by the Council, where the instrument is a “relevant instrument” under the Crown Land Management Act, or where it is a conservation agreement, Trust agreement, property vegetation plan, biobanking agreement or a planning agreement. Practitioners cannot assume private restrictive covenants will be wholly overridden; exemptions apply and rights of public authorities are preserved (cl 1.9A(1)-(3)).
Double dipping and floor space ratio calculations
Clause 4.5(3)-(11) contains detailed rules for calculating site area and gross floor area, and contemplates the use of registered covenants to prevent the creation of floor area on one lot that effectively duplicates floor area already accounted for on another lot. Consent authorities can require a covenant preventing double dipping and may reduce the maximum allowable floor area on consolidated sites accordingly. Failure to account for these rules can produce errors in FSR compliance and consent conditions.
Exceptions to development standards are constrained
Clause 4.6 provides a mechanism to depart from standards but requires applicants to demonstrate the standard is unreasonable or unnecessary and that there are sufficient environmental planning grounds (cl 4.6(3)). The clause expressly excludes certain standards from variation including those that arise for complying development, BASIX commitments (cl 4.6(8)(b)), and particular clauses (cl 4.6(8)(c), (caa), (c1) referencing cl 5.4, 5.5, and clauses 6.1 and 7.4). Also cl 4.6(6) prohibits variations in specified zones where the subdivision would create multiple lots below the minimum or below 90% of the minimum. Attempting to rely on cl 4.6 without meeting its stringent tests is a common procedural pitfall.
Heritage procedural traps
Consent is required for works affecting many heritage items and areas, and the consent authority may require heritage management documents or conservation management plans (cl 5.10(2)-(6)). For archaeological sites and Aboriginal places the consent authority must notify the Heritage Council or local Aboriginal communities and consider responses within 28 days (cl 5.10(7)-(8)). Procuring sufficient heritage documentation late in the process risks consent delays or refusal.
Flood planning duties and climate change
Clause 5.21 requires the consent authority to be satisfied that development in flood planning areas is compatible with flood function and will not adversely affect safe evacuation or flood behaviour. The consent authority must consider projected changes due to climate change and the potential to relocate or modify buildings as required (cl 5.21(2)-(3)). Applicants who fail to incorporate climate projective design or evacuation considerations risk refusal.
Canal estate prohibition and similar absolute bans
Canal estate development is expressly prohibited (cl 2.9(1)), with a definition in cl 2.9(2) that catches fill or excavation combined with dwelling erection in inundated or drainage‑connected waterways. This is an absolute prohibition; proposals that attempt to reframe canal construction as drainage works must satisfy the narrow cl 2.9(3) exception that limits such works to public authority drainage and minimal size.
Exempt quantity limits and local caps
Several use categories have precise numerical limits that affect planning classification. Examples include bed and breakfast accommodation limited to no more than three bedrooms (cl 5.4(1)), home business capped at 30 square metres (cl 5.4(2)), home industries 50 square metres (cl 5.4(3)), and neighbourhood shops capped at 80 square metres (cl 5.4(7)). Neighbourhood supermarkets are capped at 1,000 square metres (cl 5.4(7AA)). Practitioners must check these quantitative limits when advising on small business uses.
Public land classification and trust interests
Schedule 4 lists land to be classified as operational or community land and, for Part 2 entries, notes any trusts that are not discharged. Clause 5.2(5) discharges certain public reserves when land is inserted into Part 2, but only subject to the Governor’s approval as noted. Practitioners working on land reclassification must check Schedule 4 and the specified trust notations.
Interdependencies with other approvals
Several Plan provisions note that approvals under other Acts may be required and that development may be exempt under this LEP but still require licences or approvals under other regimes (for example cl 3.1 note on heritage exclusions, Schedule 2 note and cl 7.8 note on other approvals). Reliance on an exempt pathway without auditing other statutory approvals can produce compliance gaps.
In practice, the “gotchas” are mostly about failing to cross‑check maps, ignoring specific numeric caps and misapplying exemptions or variation tests. Each of those mistakes is anchored to a specific clause in the Plan and can be avoided by careful pre‑application checking and early engagement with the consent authority.
How to comply
This section provides a practical, clause‑based compliance checklist for practitioners advising clients on development within the Nambucca area. All steps reference the Plan provisions underpinning the required actions.
Verify zoning and map layers first
Check the Land Zoning Map, Lot Size Map, Height of Buildings Map, Floor Space Ratio Map, Flood Planning Map and Heritage Map referenced in cl 1.7 and cl 2.2. Zoning determines permitted uses under the Land Use Table (cl 2.3) and maps determine key development standards (cll 4.1, 4.3, 4.4).
Determine whether the proposed use is permitted, permitted with consent or prohibited
Use the Land Use Table at the end of Part 2 to classify the proposed use in the relevant zone (cl 2.3(1)). If the use is prohibited in the zone, do not proceed without considering an LEP amendment or rezoning.
Check exempt and complying development pathways
See Part 3 and Schedules 2 and 3. Confirm the site is not an environmentally sensitive area as defined in cl 3.3(2) because cl 3.3(1) precludes exempt or complying development in those areas. If seeking complying development under Schedule 3, ensure compliance with the listed standards and any relevant Building Code or Local Government Act requirements (cl 3.2(2)-(3)).
For development requiring consent, identify applicable standards and tests
For subdivisions consult cl 4.1 and its subclauses including community title (4.1AA), split zones (4.1B) and boundary change provisions (4.1C). For strata subdivision limits in certain zones refer to cl 4.2B. For dwelling erection on rural and conservation land follow cl 4.2A.
Check height and FSR maps (cll 4.3-4.4) and apply the floor space calculation rules in cl 4.5, including potential covenants to prevent double counting under cl 4.5(9)-(10).
Consider whether a variation to a development standard is needed and eligible
If a standard would be contravened, prepare the variation justification in accordance with cl 4.6(3): demonstrate that compliance is unreasonable or unnecessary and set out sufficient environmental planning grounds. Remember the consent authority must record the assessment (cl 4.6(4)) and some standards cannot be varied under cl 4.6(8).
Address heritage, Aboriginal and archaeological obligations early
If the site is listed in Schedule 5 or within a heritage conservation area, anticipate that development consent is required for demolition or alteration and that the consent authority may require a heritage management document or conservation plan (cl 5.10(2)-(6)). For archaeological sites, the consent authority must notify the Heritage Council and consider any response (cl 5.10(7)). For Aboriginal places, notify local Aboriginal communities and allow 28 days for response (cl 5.10(8)).
Flood and natural hazard compliance
If the site is in the flood planning area, ensure the proposal satisfies cl 5.21(2): compatibility with flood function, no adverse effects on flood behaviour or evacuation routes, measures to manage risk to life, and environmental protections. Consider the Considering Flooding guideline and the Flood Risk Management Manual referenced in cl 5.21(4)-(5).
Prepare required technical and management plans
Acid sulfate soils: where cl 7.1 applies, provide an acid sulfate soils management plan prepared in accordance with the Acid Sulfate Soils Manual (cl 7.1(3)). If a preliminary assessment indicates no management plan is required, obtain written confirmation from the consent authority (cl 7.1(4)).
Heritage management documents: the consent authority may require these under cl 5.10(5).
Aquaculture proposals: meet the site location and operational requirements in cl 5.19 and Schedule 6 and consult relevant aquaculture industry development plans where required (cl 5.19(2)-(6)).
Infrastructure and service availability
Ensure public utility infrastructure is available or that arrangements exist to provide it when required, as a precondition for consent under cl 7.4(1). For urban release areas ensure development control plans and arrangements for designated State public infrastructure are in place per cll 6.1-6.2.
Pay attention to numeric and local caps
Observe local quantitative controls in cl 5.4 (for example bed and breakfast room caps, home business floor area caps, neighbourhood shop area limits). Non‑compliance may change the development classification from permitted without consent to requiring full development consent.
Anticipate other approvals
Confirm other statutory approvals that may be required under other Acts, for example Local Government Act approvals for on‑site effluent (cl 3.2(3)(c)), Roads Act approvals for works on roads and public reserves (cl 7.8 note), fisheries licences for aquaculture and approvals under the Heritage Act where applicable (cl 5.19(5); cl 5.10 notes).
Early engagement with Council and relevant State agencies
Given the Plan’s frequent referral and notification requirements (for example cl 5.10 and cl 5.1), engage early with Council and with State agencies where the Plan identifies acquiring authorities, flood or environmental matters. Early liaison can reduce approval timing risk and avoid surprises concerning required studies or referral responses.
Document variation and site assessment work
Keep records of how the cl 4.6 variation test is addressed because the consent authority must keep a record of its assessment (cl 4.6(4)). Provide clear environmental planning grounds and technical evidence to support any requested departures.
Check Schedule 1 for site‑specific permitted uses
Confirm whether the lot is subject to an additional permitted use under Schedule 1 (for example specified lots with permitted vehicle sales, crematoriums, caravan parks, agritourism) and note that Schedule 1 operates despite other provisions of the Plan (cl 2.5(2)).
Maintain compliance post‑consent
Ensure conditions of consent, including covenants imposed pursuant to cl 4.5(9), are complied with. Conditions form part of the consent and may restrict further subdivision or floor area creation.
This checklist flows directly from the Plan’s operative clauses. It is not exhaustive for every project type, but it identifies the mandatory checks and documentary requirements that the Plan itself prescribes. For complex proposals, coordinate legal, heritage, hydrological and engineering advice and verify all information against the current consolidated LEP and the maps published on the NSW Planning Portal as referenced in cl 1.7 and cl 1.3.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Nambucca Local Environmental Plan 1995
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provisions relating to development applications
1 Savings provisions relating to development applications
1.8A Savings provisions relating to development applications
(1) If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
(2) If a development application has been made before the commencement of Nambucca Local Environmental Plan 2010 (Amendment No 32) in relation to land to which that plan applies and the application has not been finally determined before that commencement, the application must be determined as if that plan had not commenced.
(3) A development application made, but not finally determined, before the commencement of State Environmental Planning Policy Amendment (Flood Planning) 2023 must be determined as if that policy had not commenced.
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
cl 1.9: Am 2016 (310), Sch 4.16.
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoi
This is an opening excerpt, not the complete document.