[2025] QSC 286
General information, not legal advice.
Supreme Court of Queensland
2025-11-04
Wilson J
Original judgment source is linked above.
BUILDING, ENGINEERING AND RELATED CONTRACTS - ADJUDICATION DECISION - where the applicant is the principal under a contract - where the first respondent is a contractor who undertook to carry out works for a building development - where the first respondent terminated the contract - where the first respondent lodged an adjudication application with an adjudicator - whether the existence of a reference date is an objective or subjective jurisdictional fact - whether the applicant was denied procedural fairness - whether the adjudicator's decision was affected by jurisdictional error and void
Building Industry Fairness (Security of Payment) Act 2017 (Qld) s 67, 70, 71, 75, , (2)
Uniform Civil Procedure Rules 1999 (Qld) r 483(1)
ABC Glass & Aluminium Pty Ltd v Nik Nominees Pty Ltd [2019] QSC 171
A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7
Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410
Allianz Australia Limited v Delor Vue Apartments CTS 39788 [2022] HCA 38; (2022) 277 CLR 445
Bhusal v Catholic Health Care [2017] NSWSC 838
Brolton Group Pty Ltd v Hanson Construction Materials Pty Ltd [2020] NSWCA 63
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393
Chevron Park Pty Ltd v Groupline Constructions Pty Ltd [2024] QSC 202
City of Enfield v Development Assessment Commission [2000] HCA 5; (2000) 199 CLR 135
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228
Demex Pty Ltd v McNab Building Services Pty Ltd [2023] NSWCA 261; (2023) 113 NSWLR 282
Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99
EQ Constructions Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1604
Forme Two Pty Ltd v McNab Developments (Qld) Pty Ltd [2025] QSC 96
Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd [2018] NSWCA 339
JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty Ltd [2018] NTCA 6; (2018) 334 FLR 314
John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd (2006) 66 NSWLR 707
John Holland Pty Ltd v TAC Pacific Pty Ltd [2009] QSC 205; [2010] 1 Qd R 302
Kioa v West [1985] HCA 81; (1985) 159 CLR 550
Lendlease Building Pty Ltd v BCF Airport Systems Pty Ltd [2024] QSC 164
Low v MCC Pty Ltd [2018] QSC 6s
LPDT v Minister for Immigration, Citizenship, Migrant Services, and Multicultural Affairs [2024] HCA 12; (2024) 418 ALR 152
Martinus Rail Pty Ltd v Qube RE Services (No 2) Pty Ltd [2025] NSWCA 49
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Musico v Davenport [2003] NSWSC 977
National Management Group Pty Ltd v Biriel Industries Pty Ltd (t/a Master Steel) [2019] QSC 219
Patrick Stevedores Operations (No 2) Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [2014] NSWSC 1413
Procon Developments (Australia) Pty Ltd v Hi-Cal Bricklaying [2025] QSC 67
Rhomberg Rail Australia Pty Ltd v Concrete Evidence Pty Ltd [2019] NSWSC 755
Saville (T/as China Sourcing Services) v Hallmarc Construction Pty Ltd [2015] VSCA 318; (2015) 47 VR 177
SHA Premier Constructions Pty Ltd v Niclin Constructions Pty Ltd [2020] QSC 307
Southern Han Breakfast Point Pty Ltd (in liquidation) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340
TWT Property Group Pty Ltd v Cenric Group Pty Ltd [2020] NSWSC 72
Watkins Contracting Pty Ltd v Hyatt Ground Engineering Pty Ltd [2018] QSC 065
Westbourne Grammar School v Gemcan Constructions Pty Ltd [2017] VSC 645
York Property Holdings Pty Ltd v Tomkins [2025] QSC 44
D Piggott KC, and J Menzies, for the First Respondent
(a) whether the existence of a reference date is an objective or subjective jurisdictional fact. If the jurisdictional fact is:
(i) objective, the Court must decide whether the reference date of 10 September 2024 existed. This question is determined by the Court upon the evidence before it, without being limited to the probative material before the adjudicator; or
(ii) subjective, the Court must decide whether the adjudicator arrived at the required state of mind in the way contemplated by the legislature.
(b) in relation to the adjudicator's finding about waiver, whether York was denied procedural fairness in respect of the adjudicator's alleged reliance upon Allianz Australia Insurance Limited v Delor Vue Apartments CTS 39788 [2022] HCA 38; (2022) 277 CLR 445 ("Allianz").
(c) in relation to Tomkins' entitlement to claim for unfixed materials, whether York was denied procedural fairness in relation to a so-called finding that its letter of 30 August 2024 was a variation under the Contract.
(d) in relation to termination costs, whether the adjudicator made a jurisdictional error in finding that Tomkins was entitled to certain termination costs.
(a) Separate question 1: Is the applicant entitled to the relief claimed in paragraph 2 of the Originating Application?
(b) Separate question 2: Was the existence of a reference date for Payment Claim 36 by reason of the operation of s 67(2) of the BIF Act a "subjective jurisdictional fact" or an "objective jurisdictional fact"?
(c) Separate question 3: If the answer to separate question 2 is a "subjective jurisdictional fact", is the applicant entitled to the relief claimed in paragraph 1 of the Originating Application?
(d) Separate question 4: Did the adjudicator's reference to Allianz deny the applicant procedural fairness?
(e) Separate question 5: If the answer to separate question 4 is "yes", was it a material denial of procedural fairness?
(a) Separate Question 4
(b) Separate Question 5
(c) Separate Question 1
(d) Separate Question 2
(e) Separate Question 3.
Separate Question 4: Did the adjudicator's reference to Allianz deny the applicant procedural fairness?
If the Principal commits a substantial breach of the Contract, the Contractor may, by hand or by certified post, give the Principal a written notice to show cause....
d) the date and time by which the Principal must show cause (which will not be less than 7 day clear days after the notice is received by the Principal); ...
If the Principal fails to show reasonable cause by the stated date and time, the Contractor may, by written notice to the Principal suspend the whole or any part of the WUC.
The Contractor may, by written notice to the Principal, terminate the Contract, if within 7 days of the date of suspension under this subclause, the Principal fails to:
b) if the breach is not capable of remedy, to make other arrangements to the reasonable satisfaction of the Contractor.
Damages suffered by the Contractor by reason of the suspension will be assessed by the Superintendent, who will certify them as moneys due and payable to the Contractor (emphasis added)."
(a) any subsequent suspension by Tomkins based on the invalid show cause notice would be a wrongful suspension; and
(b) in turn, any subsequent termination would be unlawful.
(a) if York had objected to the allegedly incorrect specified time frame before responding, then Tomkins could have re-served the notice; and
(b) York's failure to do so amounted to a waiver of the same type in Dura.
"119. It is clear that the Show Cause Notice must satisfy clause 39.8(d) of the Contract.
388. Hudson's Building and Engineering Contracts, state the general rule concerning modern contractual determination clauses that require written notice in one form or another at the time of determination of the contract in these terms:
Express notice requirements are often in 'two tier' form ... In every case the clause must be carefully considered and closely followed in all respects, both as to the contents and timing of the notices, but the courts will usually regard the notices as commercial documents, and the modern approach is to interpret notice clauses with regard to their commercial purpose [Mannai Investments Co Ltd v Eagle Star Assurance [1997] UKHL 19; [1997] AC 749].
390. The Court of Appeal of this court, in MLW Technology Pty Ltd v May, in the context of a licensing agreement, considered the principles relevant to interpreting the effect of contractual notices. Gillard AJA emphasised that in construing commercial contracts, and the actions of businessmen, a common sense non-technical approach should be adopted. Gillard AJA approved of the observations of the House of Lords in Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd finding them to accord with authority in this court. A reasonable recipient, in the circumstances of the parties is aware of the terms of the contract, of the correspondence that has passed between the parties, and of the history of the building project. A builder would have had extensive knowledge of the works."
"127. In further support of that conclusion, I refer to Allianz Australia Insurance Limited v Delor Vue Apartments CTS 39788. In that judgment, Kiefel CJ, Gageler, Edelman, Stewart [sic] and Gleeson JJ described a similar form of waiver in the following terms;
128. The Respondent replied to the Claimant's Notice to Show Cause, within the prescribed time, and made clear its position. By that act, the Respondent expressly made clear to the Claimant its position and implicitly invited the Claimant to accept its reply or take the next steps.
129. The Claimant considered the Respondent's reply to the Claimant's Show Cause Notice of 21 August 2024 and determined the Respondent's reply did explain (show cause) as to what the Respondent proposed to do to rectify the breaches in relation to failure to provide design in a timely manner.
130. The Claimant relied and acted on the Respondent's reply of 28 August 2024 and issued its notice of full suspension under clause 39.9 on 29 August 2024.
If the Principal fails to show reasonable cause by the stated date and time, the Contractor may, by written notice to the Principal, suspend the whole or any part of WUC.[2]
The Contractor will remove the suspension if the Principal remedies the breach.
The Contractor may, by written notice to the Principal, terminate the Contract if, within 7 days of the date of suspension under this subclause the Principal fails:
b) if the breach is not capable of remedy, to make other arrangements to the reasonable satisfaction of the Contractor.
Damages suffered by the Contractor by reason of the suspension will be assessed by the Superintendent, who will certify them as moneys due and payable to the Contractor.
132. The Respondent had a further 7 days from the date of the Notice of full suspension of works under Contract to explain how the Respondent would remedy the breaches. The Respondent did not take any such steps in the period following the Claimant's notice of full suspension.
133. On 10 September 2025, 12 days after it had issued its Notice of full suspension of works under Contract to remedy the breaches, the Claimant send [sic] a further written notice terminating the Contract.
134. Notwithstanding the issue of whether the Respondent had committed the notified substantial breaches of Contract, I am satisfied that the Claimant followed the requirements of the Contract, as amended by the conduct of the parties and lawfully terminated contract."
(a) determined the issue of waiver in reliance on Allianz when, in fact, the reasoning in Allianz supported the opposite proposition to that found by the adjudicator; and
(b) relied on Allianz to justify his conclusion that, as a matter of law, York's mere act of replying to Tomkins' Notice within the prescribed time was an act of waiver.
".. But we say the problem about it is that had we been alerted to the fact - had the adjudicator said to us, "Look, I'm concerned about the Allianz. I've heard all about Dura, and I've got some views about that, but I'm concerned about Allianz because I think that supports Tomkins' position." That's what he should have done to give us natural justice. But he didn't do that. Had he done that, we would have said, "Well, Mr Adjudicator, in fact, that decision is squarely against Tomkins because of the part that's extracted in the reasons which says that it must be an unequivocal rejection of rights."
"[41] ... the valid exercise of an adjudicator's jurisdiction is conditioned on the adjudicator having accorded to the parties what White JA described in Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd as "the necessary level of procedural fairness". The juridical basis for this proposition is the same as the preceding propositions. The legislature must be taken to have contemplated that an adjudicator would have accorded the parties the necessary level of procedural fairness, such that failure to do so would be regarded as breach of a condition of the valid exercise of the jurisdiction..."
"[4] The issues in most disputes are familiar, and only rarely will there be scope for an adjudicator to determine them in a way which could not be anticipated thereby amounting to procedural unfairness".
"[107] ... It may readily be accepted that the Act provides for a somewhat rough and ready way of assessing a builder's entitlement to progress claims. It may also be accepted that the procedure is intended not only to be swift, but also to be carried out with the minimum amount of formality and expense. Nonetheless, what an adjudicator is required to do is to decide the dispute between the parties. Under the scheme of the Act, that dispute is advanced by the parties through their adjudication application and adjudication response (which, no doubt, will usually incorporate the antecedent payment claim and payment schedule). If an adjudicator is minded to come to a particular determination on a particular ground for which neither party has contended then, in my opinion, the requirements of natural justice require the adjudicator to give the parties notice of that intention so that they may put submissions on it..."
"[50] In determining whether there has been a substantial denial of natural justice it is not sufficient to simply identify the issue in dispute between the parties, and to determine whether they had an opportunity to make submissions with respect to that issue... The subject of a decision is entitled to have his or her mind directed to "the critical issues or factors on which the decision is likely to turn in order to have an opportunity of dealing with it". In a case such as the present, if the decision is likely to turn on a point of law not contended for by one of the parties, and about which the parties have not been given an opportunity to address, then the requirements of natural justice will not have been observed. It is the issue of law, and not the general issue in dispute, upon which the decision is likely to turn."
Separate question 5: If the answer to separate question 4 is "yes", was it a material denial of procedural fairness?
"[40] The adjective "substantial" has been used in the relevant authorities to capture the principle that the opportunity denied was material, namely that the matter about which the adjudicator did not provide an opportunity to be heard was a point upon which the adjudicator based his or her decision and was significant to the Payment Actual determination. In addition, the Court's concern is with the practical effect of the alleged denial of natural justice. Reference to the High Court's decisions in Stead v State Government Insurance Commission and Ex parte Aala supports the proposition that even if the Court is satisfied that there has been a denial of natural justice, relief may be denied if it can be shown that compliance with the requirements of natural justice could have made no difference to the outcome. It is probably sufficient in this regard for the applicant for relief to show that there were substantial submissions that, as a matter of reality and not mere speculation, might have persuaded the adjudicator to change his or her mind."
(a) had they been given an opportunity to address the conduct that the adjudicator found constituted a waiver, they could have submitted that this conduct could not ground such a finding because it was not an unequivocal acceptance of the show cause notice;
(b) contrary to the adjudicator's view, Allianz did not support the waiver finding;
(c) had submissions been made, there was a realistic possibility of a different outcome, including that Tomkins' termination was unlawful, no reference date had arisen, and the adjudicator had no jurisdiction;
(d) no other basis was identified by the adjudicator for his finding as to the reference date;
(e) the parties did not advance any other basis for the existence of the reference date and were not given an opportunity to be heard in relation to any other basis;
(f) further, to the extent that any other basis might hypothetically exist, it was not determined by the adjudicator in a way contemplated by the Act (that is rationally and having regard to the Contract).
"[32] Consistently with the effect of what was said in Brodyn, and with the arguments put by the appellant in this case, it should be understood that only if there has been a substantial denial of procedural fairness by an adjudicator in determining an adjudication application will there be jurisdictional error under the Act. Put another way, the content of the requisite procedural fairness is reduced: note Cardinal at [60]. What this means in practice will turn on the particular circumstances of cases. But generally a conclusion of invalidity would only be reached if there was a significant departure from what would ordinarily be the requirements of procedural fairness for a person exercising a statutory power, and where that departure could be characterised as leading to substantial practical injustice in all the circumstances. This approach reflects the fact that the Act provides for a "rough and ready" process (Chase Oyster Bar at [208]), not intended readily to be held invalid on judicial review.
[33] McNab referred the court to the decision of Doyle J in Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd. As his Honour noted at [61] in that decision, "it is not always clear whether an adjudicator has determined a matter on a basis which was not contended for by the parties, or which had not otherwise been put in issue", saying that "[w]hether this is so will often depend upon the level of abstraction or specificity at which one articulates the issues in dispute". He added at [62] that beyond the extremes, "it is difficult to generalise as to the level of abstraction or specificity at which the obligation to afford procedural fairness must be addressed in a particular case". Even so, consistently with the approach just stated, a reviewing court should view sceptically arguments involving high degrees of specificity in this regard.
[34] The primary judge stated at [9] that it "was common ground between the parties that a denial of procedural fairness in an adjudication, if material or substantial, would require an adjudication determination to be set aside" (citation omitted). Insofar as what is set out above is different from the standard the primary judge applied, it is first one of emphasis in relation to what is meant by substantial. That notion has practical significance. Further, there is a difference between considering whether there has been a departure (substantial or otherwise) from the standard of procedural fairness required and whether or not any such departure is material in the sense recently emphasised by the High Court. Whilst both involve issues of relative significance, which may overlap, conceptually the former looks to whether or not there has been a departure from the type of fairness that the Act requires. The latter involves asking a (hypothetical) factual question, looking to what would have occurred but for that departure in the sense of asking whether it deprived the challenger of a realistic possibility of a different outcome: MZAPC v Minister for Immigration and Border Protection at [2], [85]".[16]
Separate Question 1: Is the Applicant entitled to the relief claimed in paragraph 2 of the Originating Application?
(a) the adjudicator's decision that Tomkins was entitled to be paid for "unfixed materials"; and
(b) the adjudicator's decision that Tomkins was entitled to be paid for certain "termination costs", namely, demobilisation costs, staff costs, items left on site, and overheads on each of those costs.
Separation Question (1)(a): unfixed materials
(a) cl 20 provided (relevantly) that the "Superintendent may give a direction orally but will as soon as practicable confirm it in writing";
(b) cl 24 was headed "Site" and addressed a range of matters including possession of, and access to, the site;
(c) cl 28 provided (relevantly) that the "Superintendent may give the Contractor a written direction not to remove materials or construction plant from the site. Thereafter the Contractor will not remove them without the Superintendent's prior written approval (which will not be unreasonably withheld)."
"2. The Contractor is not entitled to suspend the whole or any part of the WUC under the Contract. The notified suspension of the whole of the WUC is a substantial breach of the Contract. We intend to write to you further on this subject shortly.
(a) Tomkins maintained its entitlement to payment for unfixed material in the payment claim; and,
(b) York opposed such a claim based on cl 37.3 of the contract. (the cl. 37.3 issue).
"The Principal will not be liable to pay for unfixed plant and materials unless they are listed in Item 29 and the Contractor:
a) Provides the additional security in Item 13(e); and
b) Satisfies the Superintendent that the subject plant and materials have been paid for, properly stored and protected, and labelled the property of the Principal."
"307. Read in isolation, clause 37.3 prima facie disqualifies claims for unfixed plant and materials. However, when clause 37.3 is considered in the broader context of the Contract and against the mandatory provisions of the BIF Act, it becomes apparent that York's reliance on clause 37.3 as a means for withholding payment is unsustainable in the particular factual matrix that applies to the subject Payment Claim and to this Adjudication Application.
310. Second, the contractual exclusion of Tomkins' entitlement to be paid for unfixed materials under clause 37.3 directly contradicts, and has the effect of excluding, Tomkins' statutory right to payment for 'related goods' under section 70 of the BIF Act. Accordingly, by operation of section 200(2) of the BIF Act, clause 37.3 is of no effect.
"263. In the normal course of events, the Respondent had no claim over the unfixed materials because nothing in the Contract provided the Respondent any possessory or ownership rights over the unfixed materials nor did it have any obligation to pay for the unfixed materials pursuant to Item 29 of Part A of the Annexure and clause 37.3 of the Contract. Similarly, the Claimant had no entitlement to claim payment for unfixed materials pursuant to clause 37.3 of the Contract.
The Contractor will not vary WUC except as directed in writing under this clause 36.
The Superintendent, before the date of practical completion, may direct the Contractor to vary WUC by any one or more of the following which is nevertheless of a character and extent contemplated by, and capable of being carried out under, the provisions of the Contract (including being within the warranties in clause 2A):
(c) change the levels, lines, positions or dimensions
If the Contractor considers that a direction constitutes a
variation, it must, as a condition precedent to any entitlement, give the superintendent notice within 10 business days of the direction, and in any event before commencing any work, the subject of the direction."
"The jurisdictional error alleged, your Honour, is a material denial of procedural fairness. This arose from the adjudicator's failure to put York on notice of his intention to find that a letter that had been sent by York to Tomkins was, in fact, a variation direction under clause 36 of the contract.
A point that's made by Tomkins is that it was not, in fact, a letter from York, but rather an instruction from the superintendent on the same day that was the focus of the adjudicator's decision. The reasons do refer to both correspondence, but it really makes no difference, your Honour. The finding that either letter amounted to a variation direction under 36 was a decision on a basis that no-one had advanced, and with respect, could not have been anticipated by the parties or, for that matter, York. In reality, the adjudicator, off his own bat, made the variation finding, and his characterisation of the correspondence in that respect was incorrect."
(a) York was aware of the issue in dispute;
(b) the adjudicator did not determine the issue in a way that could not be anticipated by York; and
(c) the adjudicator's finding is consistent with submissions made by the parties to the adjudicator.
(a) York had a contractual obligation to pay Tomkins for any unfixed materials that had become part of the works under Contract;
(b) ss 66 and 70 of the BIF Act entitled Tomkins to a progress payment for supplying to York unfixed materials in connection with the works under Contract;
(c) York had "refused to allow Tomkins to retake possession of the unfixed material", the corollary of which is that York had possession of the unfixed material.
"583. The existence of the two provisions - the FIA's general entitlement to payment for materials and the specific exclusion in clause 37.3 for unfixed materials - does not create an ambiguity or inconsistency. Rather, it reflects the ordinary practice in construction contracts. Clause 37.3 acts as a specific restriction on the broader entitlement in the FIA, clarifying that the Contractor is not entitled to payment for materials that have not been fixed to the works unless agreed otherwise.
(a) Tomkins reproduced York's letter, which had referred to the Superintendent's Instruction and identified its consequence that Tomkins was not allowed to retake possession of unfixed materials;
(b) Tomkins argued that, by leaving unfixed materials on site, it had supplied materials for which Tomkins had a statutory right to a progress payment;
(c) York had argued that cl 37.3 of the Contract would apply to restrict Tomkins' entitlement to payment for unfixed materials "unless agreed otherwise";
(d) York identified that cl 2.1 of the General Conditions of Contract required York to pay Tomkins for the work, including provision of materials, thus directing attention to cl 2.1, which provided that York would pay Tomkins "for work ... adjusted by any additions or deductions made pursuant to the Contract";
(e) York submitted that the adjudicator would be required to value the unfixed materials under ss 72(2)(b) and 72(3) of the BIF Act if certain other findings were made. A matter identified by York as relevant to that valuation process was any variation agreed to by the parties.
(a) York's letter involved a variation to the WUC; and
(b) the Variation direction had the effect of increasing the WUC to include the unfixed materials which put the materials within the scope of cl 3(b), namely "completed WUC".
"280. ... In other words, the Respondent was required to value the unfixed materials at the time it directed the Claimant to leave the unfixed reinforcement on site."
"287. ...The distinguishing fact that leads to a different conclusion is that on 30 August 2024, the Respondent instructed the Claimant to leave all unfixed materials on site."
"341. On 30 August 2024, the Respondent instructed to leave the unfixed materials on the site, which was a variation to increase the WUC under clause 36.1. The Superintendent should have, as soon as possible, valued that variation pursuant to clause 36.4 of the Contract.
"Now, the effect of Tomkins' submission seems to be that the mere mention of this clause would have directed the adjudicator's attention to the terms of the provision which included, amongst other things, an acknowledgment that York would pay Tomkins a lump sum contract price that could be adjusted by additions or deductions made pursuant to the contract. That, it says, is the invitation or the gateway by which the adjudicator was then entitled to make the finding that York's letter amounted to a variation direction under clause 36. That submission is incorrect, your Honour.
The mere reference to the general payment clause in contract, in the context of responding to a particular submission, did not give the adjudicator licence to make a finding that York's letter was a variation direction, that no one had made that submission to me. Not wishing to use too many metaphors, but if he did that, your Honour, the adjudicator would have gone off on a frolic of his own."
(a) whether York's letter involved a variation, i.e., 'relinquishing' unfixed materials did not vary the WUC;
(b) that neither York's letter nor the instruction from the Superintendent identified the subject as relating to a variation;
(c) whether Tomkins' conduct in seeking to remove unfixed materials from the site involved it doing more work than what was otherwise required under the Contract; and
(d) the way in which the notice requirement in cl 36.1 operated pursuant to the BIF Act.
Separate Question 1(b) - the termination claim
"If the Contract is terminated pursuant to subclause 39.4(b) or 39.9, the parties' remedies, rights and liabilities will be the same as they would have been under the law governing the Contract had the defaulting party repudiated the Contract and the other party elected to treat the Contract as at an end and recover damages."
(a) $313,609.89 for demobilisation costs;
(b) $615,084.86 for staff costs;
(c) $174,799 for items that Tomkins left on site; and
(d) $110,349.49 for the cost of overheads on the items above.
"1597 York asserts that clause 39.10 bars Tomkins from recovering any amount by way of progress payment. York argues that the only remedy available to Tomkins post termination is a claim for damages which, it asserts, cannot be brought under the BIF Act. On page 206 of the Payment Schedule York states that:
Clause 39.10 of the Contract provides that if the Contractor terminates the Contract pursuant to clause 39.9 (which is denied), the parties remedies, rights and liabilities will be the same as they would have been under the law governing the Contract had the defaulting party repudiated the Contract and the other party elected to treat the Contract as at an end and recover damages. As the Contractor is claiming costs due to its unlawful termination, clause 39.9 confirms under the Contract this is a claim for damages for repudiation and therefore not claimable under the Act."
"1603 Emphasis is placed upon the fact that clause 39.10 provides a contractual entitlement to a party who terminates under clause 39.4(b) or 39.9 (as the case may be). That entitlement is equal to, and derived from, the amount of damages the party would have been entitled to had it accepted the defaulting party's repudiation. It is not a claim for damages in the true sense - because damages are a remedy awarded by operation of law for breach of contract. Rather, it reflects a contractual mechanism that incorporates the measure of damages as determined under the governing law, treating the entitlement as a contractual right rather than a purely legal remedy (emphasis in original).
(a) the Contract allows for a particular type of claim to be included within a final payment claim; and
(b) the Act requires the Adjudicator to make a determination on the claimant's entitlement in respect to that claim; but
(c) the Act also precludes the Adjudicator from performing that function, because the assessment of the very claim which the Act requires the Adjudicator to assess is (on York's construction) beyond the Adjudicator's jurisdiction.
1613 The natural interpretation of the express wording of the Contract, when read in conjunction with the Act is that following termination, any claim in the nature of repudiatory damages which would fall within the scope of clause 39.10 may be brought in a final payment claims, and may subsequently also be subject to adjudication procedures under the BIF Act."
"989 I accept the Respondent's argument that where the Contract has been terminated, all subsequent claims are claims for damages for the purposes of contract law.
992 Furthermore, some claims for damages may be made pursuant to the provisions of the Contract that survive termination. For example; clause 39.9 requires the Superintendent and or the Respondent to assess certain damages after termination. Clearly, that is assessment and liability of the Respondent is [sic] an amount for which the Claimant can claim payment.
75. A similar proposition applies in relation to the final payment claim, which the Act authorises to be made when a contract has been terminated, and even though the fact of the termination means that there can never be a final payment claim advanced pursuant to the contract.
In the present case, it does not matter that the amount which represents the retentions withheld under the contract cannot be said to be an amount which has yet accrued due and payable under the contract.
The contractor has a statutory entitlement to a final payment claim, calculated under s 71(b) and valued under s 72(1)(b).
If the adjudicator values that claim in accordance with the provisions of the Act, the effect of that valuation may well be to enable the claimant to be paid an amount of money which includes the value of cash retentions withheld from work already done (and even though under the contract there was no accrued right to the return of cash retentions), but that seems to me to be made permissible by the terms of the Act.
If a party breaches (including repudiates), the Contract, nothing in this clause will prejudice the right of the other party to recover damages or exercise any other right or remedy."
1001 The Contract provides for the assessment of certain types of damages by the Superintendent and payment of those assessed damages by the Respondent. For example, clauses 14, 32, 34.9 and 39.9 identify certain types of damages, which form part of the construction work in certain cases and may be the subject of a payment claim. This conclusion was confirmed in Coordinated Construction Co. Pty. Ltd. v. J.M. Hargreaves (NSW) Pty. Ltd. & Ors. [2005] NSWCA 228. The relevant extract from that case appears at paragraph 1010) below.
1002 The Claimant may similarly claim payment for damages under clauses 14, 32, 34.9 and 39.9 incurred during the course of the Contract after termination.
1003 I decided above at paragraphs 978) to 987), that the Act provides that upon termination of the Contract, the Claimant accrues a reference date being the date of termination and the Claimant is entitled to make a final payment claim under the Act.
1004 In other words, the Claimant was entitled to make the Payment Claim for completed work which includes damages incurred that were referred to in the Contract.
1005 The Claimant was entitled to claim for the damages suffered that were envisaged by the Contract, which were described in Hargreaves as forming a part of the construction work. The Claimant is not, however, entitled to claim for the types of damages that are not expressly permitted to be claimed by the Contract.
1006 Accordingly, I do not accept the Respondent's argument that the Payment Claim is invalid because it is a claim for damages.
1007 I also do not accept the Claimant's argument about the operation of clause 39.10."
"1016 If damages referred to in the Contract form part of the increased costs or price of construction work actually carried out, those damages are clearly for construction work carried out".
"....One is lack of procedural fairness, so the adjudicator just decided it on a basis which wasn't contended for by the parties. Clause 39.10 was what was suggested. He didn't decide on that. We further say, well, there's a lack of reasoning in the adjudicator's decision, because if your Honour looks at each of the four items for which he made awards, it's impossible to tell, we say, what really is the basis upon which he - the contractual or any other basis that he decides that the - that Tomkins is entitled to the amounts claimed, and we also say that in fact, it didn't apply the contract because you can't do that if you apply clause 39.10, because that's only a common law right. That just preserves common law damages rights."
(a) accepted York's argument that, where the Contract has been terminated, all subsequent claims are claims for damages for the purposes of contract law; and
(b) did not accept the claimant's argument about the operation of cl 39.10.
"[107] ...If an adjudicator is minded to come to a particular determination on a particular ground for which neither party has contended then, in my opinion, the requirements of natural justice require the adjudicator to give the parties notice of that intention so that they may put submissions on it..."
"because whatever the reason that's lurking in the mind of the adjudicator - it's not been told to us, but whatever's lurking there, it's not what the parties have argued about, and we know that because he expressly rejected that."
"1045 I am persuaded that the costs of demobilisation were costs that formed a part of the total costs of the construction work under the Contract, that the Claimant is entitled to claim in the Payment Claim pursuant to section 71(b) of the Act."
The amount of a progress payment to which a person is entitled under a construction contract is -
(a) if the contract provides for the matter - the amount calculated in accordance with the contract; or
(b) if the contract does not provide for the matter - the amount calculated on the basis of the value of construction work carried out, or related goods and services supplied, by the person in accordance with the contract."
Separate question 2: was the existence of a reference date for Payment Claim 36 by reason of the operation of section 67(2) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) a "subjective jurisdictional fact" or an "objective jurisdictional fact"?
(1) A reference date, for a construction contract, means -
(a) a date stated in, or worked out under, the contract as the date on which a claim for a progress payment may be made for construction work carried out, or related goods and services supplied, under the contract; or
(b) if the contract does not provide for the matter -
(i) the last day of the month in which the construction work was first carried out, or the related goods and services were first supplied, under the contract; and
(ii) the last day of each later month.
(2) However, if a construction contract is terminated and the contract does not provide for, or purports to prevent, a reference date surviving beyond termination, the final reference date for the contract is the date the contract is terminated."
(1) Subject to the time requirements under section 85, an adjudicator must decide the following as quickly as possible -
(a) an adjudication application;
(b) applications for extensions of time under section 83.
(2) For a proceeding conducted to decide an adjudication application, an adjudicator -
(a) must decide -
(i) whether he or she has jurisdiction to adjudicate the application; and
(ii) whether the application is frivolous or vexatious; and
(b) may ask for further written submissions from either party and must give the other party an opportunity to comment on the submissions; and
(c) may set deadlines for further submissions and comments by the parties; and
(d) may call a conference of the parties; and
(e) may carry out an inspection of any matter to which the claim relates.
(3) If a conference is called, it must be conducted informally, and the parties are not entitled to any legal representation unless allowed by the adjudicator.
(4) The adjudicator's power to decide an adjudication application is not affected by the failure of either or both of the parties to make a submission or comment within time or to comply with the adjudicator's call for a conference of the parties."
(a) as York was in substantial breach of the Contract in at least one of the respects alleged by Tomkins in the Show Cause Notice;
(b) as the Contract required compliance with the time requirements for a Show Cause Notice in clause 39.8(d) of the General Conditions of Contract;
(c) as the reference to "not less than 7 clear days" in clause 39.8(d) of the General Conditions of Contract meant that the calendar day on which a show cause notice was served cannot be included in the day count, and therefore Tomkins' Show Cause Notice did not strictly comply with the requirements of the Contract;
(d) however, by its conduct, York waived the requirement for strict compliance, such that Tomkins had validly terminated the Contract using the show cause procedure.
"[19] The terminology of category 1 and category 2 matters comes from the New South Wales Court of Appeal decision in Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd (Icon) and particularly at [13]-[15] of that decision. In that decision the Court stated (in effect, relevantly for present purposes) that jurisdiction may depend either on an "identified state of affairs" (the first category) or a "state of satisfaction of the decision maker as to an identified state of affairs" (the second category). The first category jurisdiction depends on a finding of a Court as to whether or not the required state of affairs existed, for the second, the Court is only concerned with whether the relevant opinion has been lawfully formed."
"[62] The Court will not always make a determination as to the existence of a jurisdictional fact. If the donee of the power is authorised to decide authoritatively the existence of the jurisdictional fact, the Court enquires into the process adopted by the primary decision-maker's decision in determining that a jurisdictional fact exists, but does not enquire itself into the existence of that jurisdictional fact."
"[167] A jurisdictional fact may be the existence or non-existence of a specified state of affairs. For simplicity, I will talk only in terms of a jurisdictional fact as the existence of a specified state of affairs. The legislature may specify that the existence of that state of affairs - the jurisdictional fact - is essential to the exercise of statutory power. Or it may go further, and specify as well that the donee of the power is authorised to decide, authoritatively, the existence of the jurisdictional fact.
[168] In the former case, if the exercise of power is challenged on the basis that the jurisdictional fact does not exist, the court must itself inquire into the existence of that fact. It may grant relief against the exercise of jurisdiction if it finds that the jurisdictional fact did not exist.
[169] In the latter case, the court inquires into the primary decision-maker's decision that the jurisdictional fact exists, but does not itself inquire into the existence of that jurisdictional fact."
"[25] If the precondition to an exercise of power is the existence of an objective jurisdictional fact, then, if a challenge is brought to the existence of the jurisdictional fact, the Court's function is to determine de novo whether the objective fact existed. The Court determines the question upon the evidence before it, without being limited to the probative material before the repository of power. ...
"[26] On the other hand, if the precondition to the exercise of the power is that the repository of power has formed a particular state of mind, then, if a challenge is brought to the existence of the subjective jurisdictional fact, the Court's function is limited to determining whether the repository of power arrived at the state of mind in the way contemplated by the legislature. In Minister for Immigration and Citizenship v SZMDS, the High Court acknowledged that "the principles applicable where the jurisdictional fact is a state of satisfaction or opinion are traced back to the use by Latham CJ in R v Connell; Ex parte Hetton Bellbird Collieries Ltd of the terms 'arbitrary, capricious, irrational' as well as 'not bona fide' to stigmatise the formation of an opinion upon which a statutory power was enlivened".
"[32] In the event of a challenge to the existence of that subjective jurisdictional fact, the party advancing the challenge will usually have to persuade the Court that the state of mind did not exist because it was not reached in the way contemplated by the legislature. In approaching that question, it is necessary to have at the forefront of one's mind the observations made by White JA in Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd ... (emphasis added):
... the enquiry should focus more on whether the adjudicator has performed the function demanded by [the Act] and less on pursuing elusive synonyms, keeping always in mind that the legislative intent dictates a person with recognised expertise in the area be selected for the task by an informed body and this, necessarily, facilitates the rapid decision making required."
(a) the object and policy of the BIF Act;
(b) the resolution of complex factual and legal issues; and
(c) consistency between the interpretation of s 84(2)(a)(i) and (ii).
(a) the object of the BIF Act is to provide a quick procedure for interim progress payments so as to avoid cashflow interruptions to the business of construction contractors, whilst preserving parties' rights under the construction contract.
(b) the BIF Act provides for a "quick and inexpensive" interim procedure for builders to be paid,[30] it is an important consideration for construing whether provisions of the Act give rise to jurisdictional facts.[31]
(c) it would undermine that object if s 67(2) were construed as rendering an adjudicator's decision open to challenge on the grounds of alleged jurisdictional error in each and every case in which there is a dispute about the validity of the termination of the contract.
"[41] ... it is generally accepted that a requirement stipulated in the Act is more amenable to being construed as a category 1 matter if it 'is readily determined and little inconvenience is generally caused by identifying it as an essential precondition to the exercise of the relevant powers'".[34]
(2) For a proceeding conducted to decide an adjudication application, an adjudicator -
(i) whether he or she has jurisdiction to adjudicate the application; and
(ii) whether the application is frivolous or vexatious."
"[41] There is no dispute between the parties that service of a payment claim under s 13(1) of the Act[36] is an essential precondition to taking subsequent steps in the procedure set out in Pt 3 of the Act. There is accordingly no dispute that, unless a payment claim answering that description is served, there can be no adjudication application and hence no adjudication within the jurisdiction conferred by s 22 of the Act.[37] That shared understanding of the relationship between ss 13(1) and 22 is undoubtedly correct."
"[61] The construction of s 13(1) consonant with the structure of the Act is accordingly that advanced by Southern Han. The description in s 13(1) of a person referred to in s 8(1) is of a person whom s 8(1) makes entitled to a progress payment. Section 8(1) makes a person who has undertaken to carry out construction work or supply related goods and services under a construction contract entitled to a progress payment only on and from each reference date under the construction contract. In that way, the existence of a reference date under a construction contract within the meaning of s 8(1) is a precondition to the making of a valid payment claim under s 13(1).
[62] Section 13(1) correspondingly produces the result that a document purporting to be a payment claim that is not in respect of a reference date is not a payment claim under the Act. The document is ineffective in either case to trigger the procedure established by Pt 3."
"[43] The first part of proposition 1 can be accepted; the existence of a valid reference date is an objective fact to be found by the Court where necessary: Southern Han at [44]. The balance of the propositions should be rejected. The difficulty with these propositions is that they ignore the difference between the task the adjudicator was authorised and required by s 22(1) to undertake, and the task which the adjudicator in fact undertook and performed in this case.
[48] In summary, Southern Han establishes that a payment claim with an available reference date answering the description in s 13(1) of the Act is a precondition which enlivens the exercise of the adjudicator's statutory power to embark upon the adjudication. The available reference date under the construction contract serves to define the payment claim which is the subject of the adjudication application referred. If the adjudicator addresses a differently defined or described payment claim, the adjudicator is not exercising the jurisdiction in s 22(1) to determine the payment claim in respect of which the statutory power of adjudication is conferred on the adjudicator. That is what occurred in the present case. Hence, there was no error by the primary judge in finding that the determination is void on the ground of jurisdictional error."
"[25] If the precondition to an exercise of power is the existence of an objective jurisdictional fact, then, if a challenge is brought to the existence of the jurisdictional fact, the Court's function is to determine de novo whether the objective fact existed. The Court determines the question upon the evidence before it, without being limited to the probative material before the repository of power. This is the course which SHA invited me to take.
[26] On the other hand, if the precondition to the exercise of the power is that the repository of power has formed a particular state of mind, then, if a challenge is brought to the existence of the subjective jurisdictional fact, the Court's function is limited to determining whether the repository of power arrived at the state of mind in the way contemplated by the legislature. In Minister for Immigration and Citizenship v SZMDS , the High Court acknowledged that "the principles applicable where the jurisdictional fact is a state of satisfaction or opinion are traced back to the use by Latham CJ in R v Connell; Ex parte Hetton Bellbird Collieries Ltd of the terms 'arbitrary, capricious, irrational' as well as 'not bona fide' to stigmatise the formation of an opinion upon which a statutory power was enlivened."
"[97] Watkins did not seek to have the Court determine whether as matter of fact the contract had been terminated and therefore that no reference date existed. In the case of a jurisdictional fact, that is one of the rare cases where the Court may determine whether the decision maker is correct in finding that a precondition of its jurisdiction was satisfied. In this regard, although I do not need to determine the matter, I do not consider that the effect of s 25(3)(a) of the Act changes the nature of the Court's power of review in relation to a jurisdictional fact."
"[59] If an issue amounts to a jurisdictional fact it is reviewable by a superior court to determine if the decision maker was correct in finding that the pre-condition of its jurisdiction was satisfied and thus that its statutory power was enlivened. Moreover, it is reviewable, in effect, de novo, that is, by reference to the evidence available to the reviewing court. This was confirmed in Enfield_:_
where the question is whether the decision-maker has erred as to the jurisdictional facts ... that question has to be answered by the court in which it is litigated upon the evidence before that court.
[60] Where the jurisdictional fact is the existence of a fact, the reviewing court can determine on the balance of probabilities whether the fact exists.
[61] An assumption of jurisdiction when the statutory conditions precedent for the exercise of that jurisdiction are not satisfied is a jurisdictional error resulting, relevantly, in the decision becoming a nullity as 'a decision involving jurisdictional error has no legal foundation and is properly to be regarded, in law, as no decision at all."
(a) is more amenable to being construed as an "objective jurisdictional fact" if it "is readily determined and little inconvenience is generally caused by identifying it as an essential precondition to the exercise of the relevant powers";[42]
(b) is more amenable to being construed as a "subjective jurisdictional fact" if it involves consideration of a factual question which might be quite complex; and[43]
(c) is more amenable to being construed as a "subjective jurisdictional fact" if its determination benefits from the specialised knowledge or expertise of an adjudicator.[44]
(a) not easily meet the description of a requirement which "is readily determined and little inconvenience is generally caused by identifying it as an essential precondition to the exercise of the relevant powers"; and
(b) involve consideration of a factual question which might be quite complex, such as whether there has been a breach of the obligations in a building contract (e.g., here, whether there were breaches of the design obligations).
"[76] A payment claim and a payment schedule are, in many cases, given and received by parties who are experienced in the building industry and are familiar with the particular building contract, the history of construction of the project and the broad issues which have produced the dispute as to the claimant's payment claim. a payment claim and a payment schedule must be produced quickly; much that is contained therein in an abbreviated form which would be meaningless to the uninformed reader will be understood readily by the parties themselves. A payment claim and a payment schedule should not, therefore, be required to be as precise and as particularised as a pleading in the Supreme Court. Nevertheless, precision and particularity must be required to a degree reasonably sufficient to apprise the parties of the real issues in the dispute".[48]
Separate question 3: If the answer to separate question 2 is a "subjective jurisdictional fact", is the Applicant entitled to the relief claimed in paragraph 1 of the Originating Application?
[1] Tomkins is the first respondent. The second and third respondents did not participate in the proceedings.
[2] Underlining as contained in the adjudication decision.
[3] Allianz [2022] HCA 38; (2022) 277 CLR 445, 467 at [28] (Kiefel CJ, Edelman, Steward, and Gleeson JJ).
[4] Kioa v West [1985] HCA 81; (1985) 159 CLR 550, at 585 (Mason J).
[5] Demex Pty Ltd v McNab Building Services Pty Ltd [2023] NSWCA 261; (2023) 113 NSWLR 282, 288 at [22] (Kirk JA, Mitchelmore and Adamson JJA agreeing).
[6] JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty Ltd [2018] NTCA 6; (2018) 334 FLR 314, at [41], approved by Ball J in Rhomberg Rail Australia Pty Ltd v Concrete Evidence Pty Limited [2019] NSWSC 755, at [17].
[7] See also Watkins Contracting Pty Ltd v Hyatt Ground Engineering Pty Ltd [2018] QSC 065, at [64] (Brown J, as her Honour then was).
[8] John Holland [2009] QSC 205; [2010] 1 Qd R 302, at 320 [50].
[9] John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd (2006) 66 NSWLR 707, at [42] (McDougall J) ("John Goss"), approved by Applegarth J in John Holland [2009] QSC 205; [2010] 1 Qd R 302, at [35].
[10] ABC Glass & Aluminium Pty Ltd v Nik Nominees Pty Ltd [2019] QSC 171, at [16] (Mullins J, as her Honour then was); Watkins Contracting [2018] QSC 065, at [64] (Brown J, as her Honour then was).
[11] John Goss (2006) 66 NSWLR 707, at [42] (McDougall J), approved by Applegarth J in John Holland [2009] QSC 205; [2010] 1 Qd R 302, at [35].
[12] John Holland [2009] QSC 205; [2010] 1 Qd R 302, at [37].
[13] John Holland [2009] QSC 205; [2010] 1 Qd R 302, at [40].
[14] At [9]-[34] (Kirk JA, Mitchelmore and Adamson JJA agreeing).
[15] Pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW).
[16] Paragraph [32] in Demex [2023] NSWCA 261; (2023) 113 NSWLR 282 has been inter alia:
(a) referred to, and applied, by the New South Wales Court of Appeal in the recent decisions of A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7, at [2] and [4] (Leeming JA) and [36] (Mitchelmore JA, Leeming and White JJA agreeing) and Martinus Rail Pty Ltd v Qube RE Services (No 2) Pty Ltd [2025] NSWCA 49, at [74] and [117] (Payne JA, Gleeson JA and Griffiths AJA agreeing); and
(b) extracted in part and applied by this Court in the context of the BIF Act in Chevron Park Pty Ltd v Groupline Constructions Pty Ltd [2024] QSC 202, at [85] (Treston J).
[17] ABC Glass [2019] QSC 171, at [24] (Mullins J, as her Honour then was).
[18] Supreme Court Proceeding BS11674/24. The injunction was granted by Justice Treston on 4 September 2024 (Court doc 6).
[19] See paragraph 294 and 322 of the adjudicator's decision.
[20] JKC Australia [2018] NTCA 6; (2018) 334 FLR 314, at [41], approved by Ball J in Rhomberg Rail Australia [2019] NSWSC 755, at [17].
[21] LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs [2024] HCA 12; (2024) 418 ALR 152, at [14] (Gageler CJ, Gordon, Edelman, Steward, Gleeson and Jagot JJ).
[22] LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs [2024] HCA 12; (2024) 418 ALR 152, at [15] (Gageler CJ, Gordon, Edelman, Steward, Gleeson and Jagot JJ).
[23] [2005] NSWCA 228, at [41].
[25] Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340, at [61]. See also Low v MCC Pty Ltd [2018] QSC 6, at [11] (Jackson J); Watkins Contracting [2018] QSC 65, at [54] (Brown J); National Management Group Pty Ltd v Biriel Industries Pty Ltd (t/as Master Steel) [2019] QSC 219, at [47] (Wilson J).
[26] See Niclin Constructions [2020] QSC 307, at [25], citing City of Enfield v Development Assessment Commission [2000] HCA 5; (2000) 199 CLR 135, at [38], [50]-[51] and Bhusal v Catholic Health Care [2017] NSWSC 838, at [53]).
[27] Watkins Contracting [2018] QSC 065, at [62] (Brown J).
[28] Niclin Constructions [2020] QSC 307, at [26].
[29] Niclin Constructions [2020] QSC 307 at [23].
[30] Lendlease Building Pty Ltd v BCF Airport Systems Pty Ltd [2024] QSC 164, at [103] (Sullivan J).
[31] York Property Holdings Pty Ltd v Tomkins [2025] QSC 44, at [20] (Treston J).
[32] This submission has been adapted from EQ Constructions Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1604, at [51] per Williams J.
[33] Forme Two [2025] QSC 96, at [42].
[34] Forme Two [2025] QSC 96, at [41], citing Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd [2018] NSWCA 339, at [14] (Basten JA, Meagher and Leeming JJA agreeing).
[35] Niclin Constructions [2020] QSC 307, at [31].
[36] Section 13(1) of the NSW Act in that case is the equivalent of s 75(1) in the BIF Act, providing for the right to make a payment claim.
[37] Section 22 of the NSW Act is the equivalent of s 88 in the BIF Act, providing that the adjudicator is to determine the amount of the payment claim.
[38] Section 8(1) of the NSW Act, which is referred to in s 13(1), provides that "on and from each reference date under a construction contract" a person undertaking to carry out construction work is entitled to a progress payment. The equivalent provision in the BIF Act is s 70, which provides that, from "each reference date under a construction contract", a person is entitled to a progress payment if the person has carried out construction work or supplied related goods or services.
[39] Southern Han [2016] HCA 52; (2016) 260 CLR 340, at [61]-[62].
[40] Niclin Constructions [2020] QSC 307.
[41] Niclin Constructions [2020] QSC 307, at [31].
[42] Forme Two [2025] QSC 96, at [41] (Hindman J); EQ Constructions [2021] NSWSC 1604, at [42] (Williams J).
[43] Forme Two [2025] QSC 96, at [41]-[42] (Hindman J); EQ Constructions [2021] NSWSC 1604, at [45] and [47] (Williams J), citing TWT Property Group Pty Ltd v Cenric Group Pty Ltd [2020] NSWSC 72, at [104]-[106] (Stevenson J).
[44] Forme Two [2025] QSC 96, at [43] (Hindman J); EQ Constructions [2021] NSWSC 1604, at [47]-[48] (Williams J), citing Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140, at [76] (Palmer J).
[46] See, for example, Procon Developments (Australia) Pty Ltd v Hi-Cal Bricklaying [2025] QSC 67, in which the reference date was described by Bowskill CJ at [8] as "an important element of the adjudication procedure".
[47] Southern Han [2016] HCA 52; (2016) 260 CLR 340, at [2] and [61] (Kiefel CJ, Bell, Gageler, Keane and Gordon JJ).
[48] Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140, at [76].
[52] Acciona [2020] QSC 133; (2020) 4 QR 410.
[53] Acciona [2020] QSC 133; (2020) 4 QR 410, at [34].
[54] Acciona [2020] QSC 133; (2020) 4 QR 410, at [34(b)].
[55] Southern Han [2016] HCA 52; (2016) 260 CLR 340, at [62].
York Property Holdings Pty Ltd
Tomkins Commercial & Industrial Builders Pty Ltd & Ors [2025] QSC 286
(2022) 277 CLR 445
(2010) 78 NSWLR 393
(2000) 199 CLR 135
(2023) 113 NSWLR 282
(2018) 334 FLR 314
(2006) 66 NSWLR 707
(1985) 159 CLR 550
(2024) 418 ALR 152
(2015) 47 VR 177
(2016) 260 CLR 340