· Fourthly, where the adjudication determination was procured by fraud in which the adjudicator was complicit.
11 Where any of those circumstances apply, an adjudicator's determination is not a "determination" within the meaning of the Act at all, and is not merely voidable, but void [Brodyn, [52]]. In Holmwood v Halkat [2005] NSWSC 1129, I expressed the view that Brodyn was correctly to be understood as saying that mere error of fact or law, including in the interpretation of the Act or contract, does not invalidate an adjudicator's determination, and endeavoured to explain that although Hodgson JA eschewed the terminology of jurisdictional error - at least in the context of when non-compliance with what his Honour called the "more detailed requirements", as distinct from the "basic and essential requirements", would result in invalidity - the concept of jurisdictional error remains a useful one in identifying which requirements were intended to be essential pre-conditions to a valid determination, since traditionally jurisdictional error results in the decision being void, and, although the Act contains no privative clause, Brodyn limits the availability of judicial review to decisions which are void [Holmwood v Halkat, [45]-[51]].
Inclusion of allowance for lost income
12 Section 27(2A) of the Act relevantly provides:
If the claimant, in exercising the right to suspend the carrying out of construction work … incurs any loss or expenses as a result of the removal by the respondent from the contract of any part of the work or supply, the respondent is liable to pay the claimant the amount of any such loss or expenses.
13 Section 13 (Payment claims) relevantly provides:
(1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the claimant ) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount ), and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount:
(a) that the respondent is liable to pay the claimant under section 27 (2A), or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
14 Parkview submitted that a claim for damages in the nature of the loss of income claim as advanced by Sydney Civil in its payment claim is impermissible under the Act, as it was a claim for damages for repudiation of the contract and not a claim for a progress payment for construction work. Parkview submitted that the adjudicator determined that the loss of income claim by Sydney Civil was a claim "for loss of income following termination of the contract by the Respondent", which (it said) was "a pure damages claim for loss of profit"; that there was no basis under the Act to make an award of damages of that kind; and that by awarding damages for loss of profit, the adjudicator breached the basic and essential requirement to take into consideration all provisions of the Act, by failing to take into account the proper definition of a progress payment relating to construction work and not relating to pure damages for breach of contract.
15 However, the Act does not say that an amount for damages cannot in any circumstances be included in an award, as the passage cited by Parkview from the judgment of Hodgson JA in Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63 NSWLR 385 shows:
[41] In my opinion, the circumstance that a particular amount may be characterised by a contract as "damages" or "interest" cannot be conclusive as to whether or not such an amount is for construction work carried out or for related goods and services supplied. Rather, any amount that a construction contract requires to be paid as part of the total price of construction work is generally, in my opinion, an amount due for that construction work, even if the contract labels it as "damages" or "interest"; while on the other hand, any amount which is truly payable as damages for breach of contract is generally not an amount due for that construction work
16 The principle for which the cases stand is not that an award can never under any guise include an amount which is in substance in the nature of damages, but that damages for breach of contract are usually not within the concept of a progress payment for construction work. Thus, in Quasar Constructions v Demtech Pty Ltd [2004] NSWSC 116, Barrett J said:
[32] There has been some discussion in earlier cases of the question whether inclusion in a payment claim of an element for extension of time, delay or disruption invalidates the payment claim because the subject matter of such items does not bear the relationship to construction work envisaged by the word "for" in s 13(2). The decision has been that, because of the nature of a payment claim as a statement of the claimant's demands and contentions, it would not be correct to regard it as invalid because of the inclusion of matter arguably beyond its permitted scope: see, in particular, Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd [2003] NSWSC 266 and Paynter Dixon Constructions Pty Ltd v J F & C G Tilston Pty Ltd [2003] NSWSC 869.
[33] As Bergin J pointed out in the last-mentioned case, however, it is quite another thing to say that an element on account of extension of time, delay, disruption or any other perceived wrong can properly be taken into account in an adjudication, as distinct from a payment claim. Referring specifically to the matter of damages for repudiation, her Honour said:
I am not satisfied that Nicholas J's judgment [in Walter v CPL ] is authority for the proposition for which the defendant also contends that the claim for damages for wrongful repudiation of the contract is a matter that the adjudicator can determine. His Honour was considering a claim in respect of services provided under a construction contract that specifically dealt with an entitlement in the subcontractor to an amount for such costs. That is a very different matter to a claim for damages for wrongful repudiation of a contract. The adjudicator will decide what amount, if any, the plaintiff is to pay the defendant having regard to the matters he is obliged to consider pursuant to s 22 of the Act.
[34] The clear message throughout the Act is, in my opinion, that any "progress payment", including one within paragraph (a), (b) or (c) of the definition of "progress payment", can only have that character if it is "for" work done or, where some element of advance payment has been agreed, "for" work undertaken to be done. The relevant concepts do not extend to damages for breach of contract, including damages for the loss of an opportunity to receive in full a contracted lump sum price. Compensation of that kind does not bear to actual work the relationship upon which the "progress payment" concept is founded.
17 None of those observations was directed to the inclusion in a payment claim, pursuant to s 13(3)(a), of the amount of an asserted liability under s 27(2A). Section 13(3)(a) expressly authorises the inclusion in a payment claim of such an amount, in addition to a claim for a progress payment for construction work. It is beside the point that claims for damages do not fall within the concept of progress payments for work done, where the statute specifically authorises the inclusion of claims for loss arising from the removal of work from the scope of the contract. It is equally beside the point that such claims might be characterised as claims for damages for repudiation, where the statute specifically authorises their inclusion.
18 The Adjudicator was satisfied that Sydney Civil had met the requirements of the Act in suspending the Works; that Sydney Civil's entitlements with respect to suspension applied from the date of the suspension notice; and that Parkview's termination was an attempt to avoid the requirements of the Act. Even if the Adjudicator erred in his interpretation of s 27(2A) of the Act, that would not invalidate his determination. As Hodgson JA said in Hargreaves (at [46]):
I would add that in my opinion, if a determination is valid because the basic and essential requirements of the Act are complied with, an error of law by the adjudicator, even in interpreting the Act itself, would not make the determination unlawful and thus liable to restraint by injunction.
19 Accordingly, inclusion in the award of a component in respect of lost income under s 27(2A) does not invalidate the adjudicator's determination. As s 13(3)(a) expressly authorises the inclusion in a payment claim of the respondent's liability under s 27(2A) to pay the amount of any loss incurred by the claimant in exercising the right to suspend the carrying out of construction work as a result of the removal by the respondent from the contract of any part of the work or supply, it matters not that such loss may also be characterised as damages, and the determination is not vitiated by the inclusion of a component in respect of such liability. The first basis of challenge to the determination fails.
Was it open to Sydney Civil to make a claim under s 27(2A) in its adjudication application?
20 The payment claim did not elaborate the basis of the claim for the item in the sum of $149,362.50 described as "Loss of Income - 20% Contract Balance"; all that appeared was that description, and no reference was made to its being founded on any particular provision of the Act. Parkview responded in its payment schedule by refuting that Sydney Civil was entitled to be awarded damages for loss of income. It was only in the Adjudication Application that Sydney Civil first characterised the claim for loss of income by reference to s 27(2A).
21 Parkview contended that Sydney Civil was not entitled to propound in its adjudication application, and the adjudicator was not entitled to take cognisance of, a claim under s 27(2A), because no such claim had been raised in the payment claim. This was founded on the submission that a claimant under the Act is not permitted to propound a claim in an adjudication application unless it has been raised in the payment claim, and that any adjudication determination that takes into account matters raised by the claimant not in the payment claim but only in subsequent documentation is void, either for denial of natural justice, or for breach of a basic and essential requirement of the Act.
22 In my view, what the cases invoked by Parkview establish is that an applicant may not rely on, and an adjudicator may not consider, material that is included in an adjudication application which is outside the scope or ambit of the claim described in the payment claim. Parkview referred to the observations of Einstein J in John Holland Pty Limited v Cardno MBK (NSW) Pty Limited [2004] NSWSC 258, in which His Honour said:
Approaching the question in terms of section 20 (2B)
[22] The primary touchstone it seems to me, is section 20 (2B). Whilst a claimant which provides the most minimal amount of information in its payment claim may even so, be seen to technically comply with section 13, such a claimant will expose itself to an abortive adjudication determination if it be that:
· the respondent is simply unable to discern from the content of the payment claim, sufficient detail of that claim to be in a position to meaningfully verify or reject the claim: hence not then being in a position to do otherwise than to reject the whole of the claim on the basis of its inability to verify any part of the claim;