Patrick Stevedores Operations No. 2 Pty Ltd v McConnell Dowell Constructors
[2014] NSWSC 1413
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2014-10-16
Before
Ball J
Source
Original judgment source is linked above.
Judgment (8 paragraphs)
Introduction 1By a summons filed on 17 September 2014, which was amended on 29 September 2014, the plaintiff, Patrick Stevedores Operations No. 2 Pty Ltd (Patrick), seeks declarations that a determination made by the third defendant, Mr Nixon (the First Adjudicator), under s 22 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Security of Payment Act) in respect of a payment claim made by the first defendant, McConnell Dowell Constructors (Aust) Pty Ltd (McConnell Dowell), on 30 June 2014 is void and that a determination made by the second defendant, Mr Sullivan (the Second Adjudicator), in respect of the same payment claim is also void. Patrick also seeks other ancillary relief in respect of both determinations.
Background 2On 13 March 2013, Patrick and McConnell Dowell entered into a contract for the construction, testing and commissioning of certain civil works known as the Knuckle Civil Works, which formed part of the Port Botany Redevelopment, for a lump sum price of $75,793,242 (excluding GST). 3Clause 36 of the contract deals with variations. Clause 36.1 relevantly provides: The Contractor shall not vary WUC [work under the contract] except as directed in writing unless the Principal's Representative is of the opinion that the matter is one of such urgency that the Contractor should proceed without waiting for a written direction, in which case the Contractor shall proceed with the work the subject of the variation and the Principal's Representative shall confirm the direction in writing as soon as possible thereafter. 4Clause 36.4 provides: The Principal's Representative shall, as soon as possible, price each variation using the following order of precedence: (a) prior agreement; (b) applicable rates or prices in the Contract; (c) rates or prices in a priced bill of quantities, schedule of rates, schedule of prices or the Summary of Contract Sum, even though not Contract documents, to the extent that it is reasonable to use them (and for the avoidance of doubt, the Summary of Contract Sum is not a Contract document); and (d) reasonable rates or prices, which shall include a reasonable amount for profit and overheads, and any deductions shall include a reasonable amount for profit but not overheads. That price shall be added to or deducted from the contract sum. 5Clause 37 deals with payment. Clause 37.1 relevantly provides: Subject to subclause 37.8, the Contractor shall be entitled to claim payment progressively in accordance with Item 28. Item 28 provides that the time for progress claims is "The last day of each month for WUC done to the second last day of that month". 6Clause 37.2 requires the Principal's Representative, within 10 business days after receiving a progress claim, to issue a progress certificate stating, among other things, the value of WUC completed in accordance with the contract and the amount which the Principal's Representative believes to be then payable. 7Clause 37.4 relevantly provides: Within 28 days after the latter of the expiry of the last defects liability period or the rectification by the Contractor of all defects in accordance with clause 35, the Contractor shall give the Principal's Representative a written final payment claim endorsed 'Final Payment Claim' being a progress claim together with all other claims whatsoever in connection with the subject matter of the Contract. The clause goes on to make provision for the issuing of a final certificate by the Principal's Representative and the payment of the amount stated in the final certificate. 8Clause 37.6 provides for a right of set-off, including a right to set off amounts payable by McConnell Dowell under the Security of Payment Act. Clause 37.6(d) provides: This subclause 37.6 will survive any termination of the Contract. 9Clause 37.7 relevantly provides: (a) The Contractor agrees with the Principal that the date prescribed in subclause 37.1 as the date on which the Contractor must make a progress claim is, for the purposes of section 8 of the SOP Act [Security of Payment Act], the "reference date" (as defined in the SOP Act). (b) For the purposes of section 17(3) of the SOP Act, the Contractor irrevocably chooses the Institute of Arbitrators & Mediators, Australia, as the "authorised nominating authority" (as that term is defined in the SOP Act) for any adjudication application it may make under the SOP Act in respect of the subject matter of the Contract. 10Clause 39A.1 gives Patrick a right to terminate the contract for convenience. Clause 39A.2 relevantly provides: If the Principal terminates the Contract under subclause [39A.1], the Contractor: (a) subject to subclause 37.6, shall be entitled to payment of the following amounts as reasonably determined by the Principal's Representative: (i) for work carried out prior to the date of termination the amount which would have been payable if the Contract had not been terminated and the Contractor submitted a payment claim for work carried out to the date of termination; (ii) the cost of plant or materials reasonably ordered by the Contractor for the Works for which the Contractor is legally bound to pay provided that: A) the value of the plant or materials is not included in the amount payable under subclause [39A.2(a)(i)]; and B) title in the plant and materials shall vest in the Principal upon payment; (iii) the reasonable cost of removing from the site all labour, construction plant and other things used in connection with WUC; and (iv) the amount specified in Item 31A, but in no case shall the total amount payable to the Contractor under this paragraph (a), when added to other amounts already paid and payable to the Contractor, be more than the contract sum as adjusted in accordance with the Contract; and (b) ... This subclause 39A.2 shall survive termination of the Contract by the Principal under subclause 39A.1. The amount specified in Item 31A is an amount of $10. 11Clause 41 relevantly provides: 41.1 Notice of unacknowledged variations If the Contractor considers that a direction by the Principal's Representative constitutes a variation direction under subclause 36.1, but the Principal's Representative has not expressly identified it as a variation direction, the Contractor shall, if it wishes to make a claim against the Principal arising out of, or in any way in connection with, that direction: (a) within 14 days of receiving the direction and before commencing work on the subject matter of the direction, give written notice to the Principal's Representative that the Contractor considers the direction constitutes or involves a variation direction under subclause 36.1; (b) within 14 days of giving the written notice under subclause 41.1(a), submit a written claim to the Principal's Representative which includes the details required by subclause 41.3(b); and (c) continue to carry out WUC in accordance with the Contract and all directions of the Principal's Representative, including any direction in respect of which notice has been given under this subclause 41.1. 41.2 Notice of other claims Except for claims for: (a) ... (c) a variation directed by the Principal's Representative in writing under subclause 36.1 and expressly acknowledged by the Principal's Representative to be a variation under that subclause; or (d) a direction by the Principal's Representative to which subclause 41.1 applies, the Contractor shall give the Principal's Representative the notices required by subclause 41.3 if it wishes to make a claim against the Principal in respect of any direction by the Principal's Representative or any other fact, matter or thing (including a breach of the Contract by the Principal) under, arising out of, or in any way in connection with, WUC or the Contract, including anything in respect of which: (e) the Contractor is otherwise given an express entitlement under the Contract; or (f) the Contract expressly provides that: (i) specified costs or amounts are to be added to the contract sum; or (ii) the contract sum will be otherwise increased or adjusted, as determined by the Principal's Representative. 12Clause 41.3 sets out the form of notice, and cl 41.4 requires the contractor to give periodic notices each month if the matter on which the claim under 41.2 is based is continuing. Clause 41.5 provides: If the Contractor fails to comply with subclauses 41.1, 41.2, 41.3 or 41.4: (a) the Principal will not be liable upon any claim by the Contractor; and (b) the Contractor will be absolutely barred from making any claim against the Principal, arising out of, or in any way in connection with, the relevant direction or fact, matter or thing (as applicable) to which subclause 41.1 or 41.2 applies. 13On 24 April 2014, Patrick terminated the contract for convenience. 14On 30 June 2014, McConnell Dowell served Payment Claim No 13 for $54,320,302.12 plus GST. The payment claim stated that it was made under the Security of Payment Act. 15On 1 July 2014, McConnell Dowell sent Patrick a letter correcting an arithmetic error in its payment claim with the result that its claim became $55,268,634.81 plus GST. 16Patrick provided a payment schedule in respect of the payment claim on 14 July 2014. 17On 28 July 2014, McConnell Dowell made an adjudication application in respect of the payment claim to the Institute of Arbitrators and Mediators Australia (IAMA), which nominated the First Adjudicator as the adjudicator. The First Adjudicator accepted that nomination by letter dated 4 August 2014. 18On 6 August 2014, Patrick responded to McConnell Dowell's adjudication application and, on 18 August 2014, the First Adjudicator notified the parties that he had determined the application. The application was released to the parties on 22 August 2014. The First Adjudicator determined McConnell Dowell's claim at $7,786,770.98 including GST. In reaching that determination, the First Adjudicator determined a number of the claims made by McConnell Dowell as zero on the basis that there was "[n]o agreement by the parties to extend the date for the determination [and there was] [i]nsufficient time within the 10 business days of this Adjudication to address this item". 19Following receipt of the determination, on 25 August 2014, McConnell Dowell withdrew its adjudication application relying on s 26 of the Security of Payment Act. In the same letter, it made a new application to IAMA for the appointment of an adjudicator. IAMA nominated the Second Adjudicator and, on 27 August 2014, the Second Adjudicator notified the parties of his acceptance of the nomination. 20Patrick served a response to the adjudication application on 1 September 2014. In that response, and on other occasions, Patrick took issue with the Second Adjudicator's appointment. 21On 10 September 2014, the Second Adjudicator notified the parties that he had determined the second adjudication application. That determination was released to the parties on 11 September 2014. The Second Adjudicator determined McConnell Dowell's claim at $23,147,562.86 excluding GST.