Yisheng Construction Pty Ltd v City Garden Australia Pty Ltd
[2022] NSWSC 221
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2022-02-28
Before
Ball J
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
Introduction
- The first defendant, City Garden Australia Pty Ltd (City Garden), is the developer of a residential development consisting of 50 townhouses in North Rocks, Sydney (the Development). City Garden undertook the Development as trustee of the Ming Tian City Garden Unit Trust. The principal shareholders in City Garden and unitholders in the Trust are Jian Wei Liang (also known as Victor Jian Wei) and Meng Dai (also known as Adam Dai). Both were also directors of City Garden, although Meng Dai retired as a director on 27 November 2019. Following the approach adopted by the parties during the course of the hearing, I will refer to the individuals involved in the case by their Anglicised given names.
- The principal contractor for the Development was Ming Tian Real Property Pty Limited (the Builder). At the time the building contract was entered into, Adam was the sole director of the Builder and one of its shareholders. Victor had no interest in the Builder. The plaintiffs, Yisheng Construction Pty Ltd (YSC) and Yisheng Air Con. Pty Ltd (YSA), were engaged by the Builder as subcontractors on the Development. YSC is a construction company that provides general building services. YSA provides air-conditioning and ventilation services. Both are controlled by Fei Biao Ji (Billy). Both companies had done substantial work for Victor through another development company he controlled known as Ronghai Property Pty Ltd. They had also done substantial work for the Builder in the past and were working on another project as subcontractor for the Builder at the time they worked on the Development.
- The issue in this case is whether City Garden agreed, or is estopped from denying that it agreed, that it would take responsibility for the payment of amounts due to YSC and YSA in relation to the Development and if so, the terms of the agreement or arrangement between City Garden on the one hand and YSC and YSA on the other and the amount payable by City Garden in accordance with that agreement or arrangement.