Yisheng Construction Pty Ltd v City Garden Australia Pty Ltd
[2022] NSWCA 269
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2022-12-07
Before
Meagher JA, Mitchelmore JA, Ball J
Source
Original judgment source is linked above.
Judgment (14 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] The appellants, Yisheng Construction Pty Ltd and Yisheng Air Con Pty Ltd, were subcontractors on a residential development at North Rocks. The respondent, City Garden Australia Pty Ltd, was the owner and developer of the site. In 2019, the builder, Ming Tian Real Property Pty Ltd, failed to pay payment claims lodged by subcontractors on the development. On 20 September 2019, a site meeting was convened in response to the subcontractors threatening to suspend work on the site until outstanding payment claims were met. At this meeting, a principal of the respondent represented that the respondent would pay the outstanding claims and for future work conducted under the subcontracts. By April 2020, the appellants had completed work on the site. On 19 May, the appellants sent a letter of demand to the respondent for outstanding payment claims. On 24 June 2020, the appellants commenced proceedings in the Equity Division, Technology and Construction List, seeking damages from the respondent. The primary judge held that the respondent's representation constituted a contractual offer from the respondent to pay the outstanding payment claims and for future work, which was accepted by the appellants by resuming work and incurring further expenses. However, the primary judge dismissed the claim on two bases. First, the judge found that the appellants' case in final submissions was materially different to that pleaded and run at trial. He found that the appellants had originally sought to prove the amount claimed by identifying whether each payment schedule and payment claim had been paid. The appellants' new case was said to rely on the total amount due in the payment schedules, deducting the amounts paid to the appellants as disclosed in their bank statements Secondly, the primary judge held that, on the evidence, the appellants had not established that there were amounts owing under the subcontracts nor that they had incurred loss in relying on the respondent's representation. The primary judge found that the payment schedules, which had been tendered as business records, were not sufficient proof of the amounts owed. On appeal, the primary issues were whether: (i) the primary judge erred in finding that the appellants had substantially changed their case; and (ii) the primary judge erred in finding that the appellants had not proven the amounts owing under the subcontracts or the loss incurred in relying on the respondent's representation. Held by Basten AJA (Meagher and Mitchelmore JJA agreeing), allowing the appeal: As to issue (i) - appellants' changed case at trial (1) There was no substantial difference between the appellants' pleaded case on damages and the appellants' case in final submissions. The total amount that the appellants had received must have been the sum of the payment claims which had been paid: [45]. (2) It was not correct to state that the respondent did not have reason to investigate the total amount that YSC had received until the appellants made their final submissions. On the second day of hearing, the appellants had handed up a summary of the claim (Appendix A) which noted the total amount received. The pleaded claim was the amounts claimed less payments made by the builder or the respondent. The appellants' assistant general manager, Mr Dechao Liu, had assessed the amount owing with respect to each unpaid payment schedule. In response to Mr Liu's affidavit, the respondent's principal, Mr Jian Wei Liang, also calculated the payments made by the respondent to the appellants: [46], [48]. (3) It was not correct to state that the appellants had not sought to prove how much had been paid in respect of each subcontract. Mr Liu's affidavit summarised the amounts claimed, identified by reference to the payment schedules, and the amounts unpaid. Each payment schedule was specific to an identified subcontract: [47]. As to issue (ii) - assessment of damages (4) The primary judge erred in finding that the payment schedules were not definitive proof of the amounts owing to each appellant. The payment schedules were admitted as business records without objection and did not need to be proved extraneously. There was no doubt about the authenticity of the payment schedules, nor their sufficiency for the representations they made. There was no basis to infer that there were possible issues with the execution of the payment schedules. The fact that the last two payment schedules were issued after the appellants' letter of demand did not affect the probity of those payment schedules. The payment schedules did not provide any basis for believing that every amount other than the payment claims referred to in the final payment schedules had been made: [51]-[61]. (5) The amounts owing to the appellants were those assessed by Mr Liu, which were based on records and were not the subject of cross-examination. This evidence was uncontradicted by the respondent: [62]-[63].