[2026] NSWSC 937
Supreme Court of NSW
2026-08-06
Pike J
Original judgment source is linked above.
Source: NSW Caselaw (www.caselaw.nsw.gov.au). Converted to plain text by ZoeLaw. Not the official version.
Medium Neutral Citation: Waterhouse v Rothner [2026] NSWSC 937
Hearing dates: 12, 13, 14, 17, 18 and 19 November 2025, 30 April 2026
Date of orders: 6 August 2026
Decision date: 06 August 2026
Jurisdiction: Equity - Real Property List
Before: Pike J
Decision: (1) The parties are to confer to seek to agree on orders in accordance with these reasons and provide any agreed orders to my Associate by no later than 20 August 2026.
(2) In the event that agreement cannot be reached, the parties are to each provide to my Associate, by no later than 20 August 2026, the orders for which they contend, together with submissions in support of those orders of no more than five pages.
(3) Any submissions in reply, of no more than three pages, are to be provided to my Associate by no later than 27 August 2026, upon which I will determine the remaining issues on the papers.
Catchwords: CONTRACTS — construction — contract for sale of residential property — Spanish style Rose Bay mansion – Villa Biscaya — purchaser granted pre-completion access and exclusive occupation — purchaser permitted to carry out works on property — trees removed from adjoining property — purchaser authorised removal — whether removal breached special condition prohibiting damage, nuisance or inconvenience to adjoining property — clause confined to damage caused by works carried out on subject property
CONTRACTS — termination — notice of default — vendor purported to terminate purchaser’s contractual occupation rights — whether notified non-compliance rectified within contractual period — deed polls offered in response to allegations concerning removal of trees — whether rectification required to address only notified non-compliance — whether purchaser rectified notified non-compliance
CONTRACTS — performance — vendor required to sign applications, plan and consents reasonably required by purchaser — failure to sign construction certificate application — breach of express term and implied duty to cooperate — no loss caused
EQUITY — relief against forfeiture — contractual right of occupation pending completion of sale — vendor’s asserted entitlement to terminate occupation rights — whether relief against forfeiture available
EVIDENCE — witness credibility — conflicting accounts concerning responsibility for removal of trees — contemporaneous communications, including WhatsApp messages and video evidence — failure to call material witness — inference that purchaser authorised removal of trees
DAMAGES — mesne profits — where purchaser remained in occupation after purported termination — vendor claimed market rent or loss of opportunity to lease property — whether vendor would have leased property to third party — vendor unable to prove lost rental income or opportunity — alternative assessment of mesne profits — whether quantum of land tax payable by vendor if property leased should be deducted from mesne profits
DAMAGES — causation — purchaser claimed increased holding costs arising from vendor’s failure to sign construction certificate application — whether purchaser would have commenced main-house works immediately
Waterhouse
Rothner
Legislation Cited: Evidence Act 1995 (NSW), s 140
Cases Cited: 1128CG Pty Ltd v MH Affordable Homes on Kelly Pty Ltd [2025] NSWSC 563
Akici v L R Butlin Ltd [2006] 1 WLR 201
Auburn Shopping Village Pty Ltd v Nelmeer Hoteliers Pty Ltd (2017) 324 FLR 378; [2017] NSWSC 1230
Auburn Shopping Village Pty Ltd v Nelmeer Hoteliers Pty Ltd (2018) 19 BPR 38,569; [2018] NSWCA 114
Ayers Rock SkyShip Pty Ltd v Voyages Indigenous Tourism Australia Pty Ltd (2019) 19 BPR 39,541; [2019] NSWSC 828
Batson v de Carvalho (1948) 48 SR (NSW) 417
Bird v DP (2024) 419 ALR 552; [2024] HCA 41
Briginshaw v Briginshaw (1938) 60 CLR 336; [1938] HCA 34
Bunnings Group Limited v CHEP Australia Limited (2011) 82 NSWLR 420; [2011] NSWCA 342
Butt v M’Donald (1896) 7 QLJ 68
Dexus Capital Investment Services Pty Ltd v Australia Pacific Airports Corp Ltd [2026] NSWSC 600
ET-China.com International Holdings Limited v Cheung (2021) 150 ACSR 461; [2021] NSWCA 24
Goodman Fielder Consumer Foods Pty Ltd v Graincorp Foods Australia Pty Ltd [2020] NSWSC 706
Huang v Waterhouse [2025] NSWLEC 71
ING Bank (Aust) Ltd v O’Shea (2010) 14 BPR 27,317; [2010] NSWCA 71
Inverugie Investments Ltd v Hackett [1995] 1 WLR 713
JPA Finance Pty Ltd v Gordon Nominees Pty Ltd (2019) 58 VR 393; [2019] VSCA 159
Kay v Playup Australia Pty Ltd (2020) 19 BPR 40,037; [2020] NSWCA 33
L Schuler AG v Wickman Machine Tools Sales Ltd [1974] AC 235
Mineralogy Pty Ltd v Sino Iron Pty Ltd [2017] FCAFC 55
Mineralogy Pty Ltd v Sino Iron Pty Ltd (No 6) (2015) 329 ALR 1; [2015] FCA 825
Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17 at 39; [1985] HCA 14
Scandinavian Trading Tanker Co A.B. v Flota Petrolera Ecuatoriana (The Scaptrade) [1983] 2 AC 694
Schellenberg v Tunnel Holdings Pty Ltd (2000) 200 CLR 121; [2000] HCA 18
Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596; [1979] HCA 51
Sydney Local Health District v Macquarie International Health Clinic Pty Ltd (2020) 105 NSWLR 325; [2020] NSWCA 274
The J&P Marlow (No 2) Pty Ltd v Hayes & McCabe (2023) 112 NSWLR 29; [2023] NSWCA 117
The National Insurance Company of New Zealand Limited v Espagne (1961) 105 CLR 569; [1961] HCA 15
Vauxhall Motors Ltd v Manchester Ship Canal Co Ltd [2020] AC 1161; [2019] UKSC 46
Wickland (Holdings) Ltd v Telchadder [2014] 1 WLR 4004; [2014] UKSC 57
Texts Cited: “Salvaging security: The normative basis of Equity’s relief against forfeiture” by A Berriman (2021) 15 Journal of Equity 306
“The Requirement of Property or Possessory Rights for Relief against Forfeiture” by F Di Lizia (2021) 95 ALJ 641
“Themes and Prospects” in Paul Finn (ed), Essays in Equity (Lawbook Co 1985)
Interpretation, Herzfeld and Prince (3rd ed, Thomson Reuters)
N Tiveros [2020] CLJ 17
P Turner [2019] CLJ 276
Category: Principal judgment
Parties: David Waterhouse (Plaintiff)
Michael Rothner (First Defendant)
Lisa Rothner (Second Defendant)
Al Shahwan (Fifth Defendant)
Representation: Counsel:
F M Douglas KC / D Allen (Plaintiff)
S A Lawrance SC / C J Chiam (First Defendant)
Solicitors:
Ad Valorem Law (Plaintiff)
Arnold Bloch Leibler (First Defendant)
File Number(s): 2024/00208021
Publication restriction: Nil
JUDGMENT
1 Overview of the witnesses and their credibility
2 Application to call evidence from Olivia Waterhouse
3 Application to reopen
4 The facts
The purchase of the Property and the terms
Early works by Mr and Mrs Rothner – the beginning of the disputes
Mr Rothner commences occupation – the disputes continue
Requests for Mr Waterhouse to sign forms
The 2 April 2024 cutting of trees on No 8
The first Gibbons Statutory Declaration and statement
The 17 May Notice of Default
The Second Gibbons Statutory Declaration and statement
Resolution of whether Mr Rothner spoke to Mr Gibbons on 2 April 2024
Subsequent Events
5 Issues for determination
Issue 1 – Is Mr Rothner responsible for the removal of the trees on No 8?
Issue 2 – Did Mr Rothner breach clause 49.1(c)(vii)?
Issue 3 – Has Mr Rothner rectified any non-compliance?
Issue 4 – Is Mr Rothner entitled to relief against forfeiture?
Issue 5 – Quantification of Mr Waterhouse’s loss
Issue 6 – Whether Mr Waterhouse breached the contract of sale by failing to sign the application for a construction certificate to carry out approved works under DA 518/2021?
Issue 7 – Quantum of loss caused by Mr Waterhouse’s breach
6 The claims against Mrs Rothner and Al Shahwan
7 Conclusion and orders
These proceedings concern a property located at 6 Tivoli Avenue, Rose Bay (Property). Located on the Property is “Villa Biscaya” – a free standing Spanish style residence comprising four bedrooms, four bathrooms, three car spaces, a pool and a poolside cabana. The land size of the Property is approximately 1,119 square metres.
The Property offers sweeping panoramic views across Rose Bay to Sydney Harbour. It is a trophy home said to exude “Hollywood Charm”! A photograph of the Property and its view, taken from a Sotheby’s marketing brochure is below:
Prior to 17 December 2025, the Property was owned by the plaintiff, David Waterhouse (Mr Waterhouse).
By contract dated 30 June 2023, Mr Waterhouse agreed to sell the Property to the first defendant, Michael Rothner (Mr Rothner) for $25,750,000 (Contract).
The Contract was subject to a number of special conditions, including:
(a) a settlement date of 31 July 2025 subject to special condition 47; (b) for Mr Rothner to access the Property between 9.00 am and 5.00 pm from 31 July 2023 to carry out works to the garage and the garden (special condition 48); (c) for Mr Rothner to exclusively occupy the Property from 5 January 2024 until completion, including permitting Mr Rothner to carry out works to the Property (special condition 49); and (d) requiring Mr Waterhouse to consent to Mr Rothner lodging a Development Application or any application to vary a Development Application (special condition 50).
Mr Rothner availed himself of the right of access and subsequently the right of occupation, commencing work in the garden in about late 2023 and moving into the Property on 5 January 2024. Works were carried out including under the supervision of the second defendant, Lisa Rothner (Mrs Rothner), Mr Rothner’s former wife. That work included work to the garden of the Property.
It is not in dispute that prior to 10 June 2024 a number of trees/plants were removed from 8 Tivoli Avenue, Rose Bay (No 8), being the land immediately to the north of the Property. Those trees/plants were in the line of sight from the Property to the Sydney Harbour Bridge.
Extracted below is a still image from a video shot by Mrs Rothner and sent to Mr Rothner, likely in early 2024, and prior to the removal of trees in early April 2024.
On 17 May 2024, having been told about the removal of trees on No 8, Mr Waterhouse gave a notice of default to Mr Rothner contending that he had breached the special condition granting him the right of occupation by causing damage to an adjoining property, and giving Mr Rothner notice that should he fail to rectify the breach within 14 days, his right of occupation would be terminated.
On 5 June 2024, Mr Waterhouse purported to terminate Mr Rothner’s occupation rights and commenced these proceedings by statement of claim.
Mr Waterhouse relevantly contends, and Mr Rothner disputes, that he validly terminated Mr Rothner’s occupation and seeks damages measured by what he contends he would have leased the Property for during the period from 5 June 2024 until completion. Mr Rothner contends that he had nothing to do with the removal of trees from No. 8.
Mr Rothner has cross-claimed against Mr Waterhouse contending that Mr Waterhouse has breached the special conditions of the Contract by not consenting to Development Applications. Mr Rothner contends that by reason of these breaches he has been delayed in the construction work he was proposing to carry out – he will now not be able to carry out the work until after he has completed on the purchase. As a consequence, he says he will incur increased construction costs and increased holding costs prior to selling the Property which he says was always his intention.
There are, and were, other defendants.
The fifth defendant, Al Shahwan (Mr Shahwan), is alleged to have caused the trees on No. 8 to be cut down. He was represented by a solicitor until the first day of the hearing when the solicitor provided to the Court a communication from Mr Shahwan withdrawing his instructions. I gave the solicitor leave to withdraw and the hearing proceeded in the absence of Mr Shahwan.
Mrs Rothner, the second defendant took an active role in defending the proceedings, including by the appearance of counsel, until the second day of the hearing. On the morning of the second day of the hearing, junior counsel for Mr Waterhouse advised the Court that he was no longer seeking any injunctive relief against Mrs Rothner to the effect that Mr Waterhouse was involved in the removal of the trees and associated relief including damages. Counsel for Mrs Rothner sought, and was granted, leave to file a submitting appearance save as to costs. Mrs Rothner thereafter took no role in the proceedings, although she remained in the public gallery of the Court for a large part of the initial hearing in November 2025.
The third and fourth defendants, Mincong and Minshan Huang (the Huangs) are the owners of No. 8. They brought a cross-summons against Mr Rothner in relation to the removal of trees from No. 8. Shortly prior to the hearing, those proceedings settled and a notice of discontinuance was filed in relation to the claims brought by the Huangs. A copy of the settlement deed entered into between the Huangs, Mr Rothner and Mr Shahwan was tendered in evidence late in the initial hearing.
The only active parties at the hearing were Mr Waterhouse and Mr Rothner. Mr Waterhouse was represented by Mr F M Douglas KC and Mr D A Allen. Mr Rothner was represented by Mr S A Lawrance SC and Mr C J Chiam. The proceedings were initially heard over the period 12 to 19 November 2025.
On the first morning of the hearing, I conducted a view of the Property in the presence of counsel and the legal representatives for the parties, including Mrs Rothner’s representatives. The view included the entirety of the house on the Property and also the front (harbourside) garden and pool area. This enabled me to observe the views presently available from the Property as well as the boundary between the Property and No 8 where the trees were removed.
As set out in a little more detail later in these reasons, both Mr Waterhouse and Mr Rothner made applications to reopen in February 2026. On 30 April 2026, I determined that leave to reopen should be granted but only to permit evidence to be admitted of the objective facts which had occurred since the initial hearing. Each of Mr Waterhouse and Mr Rothner then provided written submissions as to what flowed from these new facts in terms of the issues I had to decide.
As between Mr Waterhouse and Mr Rothner, seven issues arose for determination by the Court. Those issues, and a brief statement of what I have found in relation to each, are as follows:
First, whether Mr Rothner is responsible for the removal of the trees on No. 8? Yes, he authorised Mrs Rothner to carry out the works.
Secondly, and if so, whether Mr Rothner failed to comply with cl 49.1(c)(vii) of the Contract? No, the clause properly construed does not extend to work on a neighbouring property.
Thirdly, if so, whether Mr Rothner rectified that non-compliance? Does not arise, but if it did, Yes.
Fourthly, if Mr Waterhouse is contractually entitled to terminate Mr Rothner’s right of occupancy, whether relief against forfeiture should be granted to prevent him from exercising that right? Does not arise, but if it did, No.
Fifthly, and depending on the resolution of the previous issues, what (if any) compensation is Mr Waterhouse entitled to either as damages for breach of contract, or as indemnity under the Deed Poll? Does not arise, but if it did, he is entitled to $256,430 plus interest.
Sixthly, whether Mr Waterhouse breached the terms of the Contract by failing to sign an application for a construction certificate to carry out works on the Property? Yes.
Seventhly, if Mr Waterhouse breached the Contract by not signing those documents, the measure of Mr Rothner’s loss which was caused by that breach? No loss was caused by the breach because Mr Rothner would not have immediately carried out the work to the main house. If**, contrary to my finding,** loss was caused, I quantify it at $1,313,256.00.
The remaining claims against Mrs Rothner and Mr Shahwan are made out and the declaratory relief sought by Mr Waterhouse against them should be made.
The parties should otherwise confer to seek to agree orders, including as to costs. I will determine any remaining issues on the papers.
On Mr Waterhouse’s side, there were two witnesses – Gary Gibbons (Mr Gibbons) and Mr Waterhouse himself. Each was extensively cross-examined and a credit attack levelled at their evidence in closing submissions.
Dealing first with the evidence of Mr Gibbons, Mr Rothner contended in closing submissions that he was not a reliable witness, who, in his answers in cross-examination was significantly confused about the chronology of events. There is some substance to these contentions. On a number of matters his evidence was just plainly wrong or inconsistent with the contemporaneous documentation. A prime example of the former is the evidence he gave in relation to when he first visited the Property. An example of the latter is his evidence that he was pretty sure that Mr Waterhouse’s daughter, Olivia Waterhouse (Olivia) only typed up one of his statements. The objective evidence is to the contrary. He is also mistaken that one of the statements and associated statutory declarations was made before Mr Whitfield.
These matters do not cause me to reject Mr Gibbons uncorroborated evidence entirely but rather cause me to approach Mr Gibbons’ evidence with caution and to analyse it in the context of the other evidence and inherent likelihoods. I consider each relevant aspect of Mr Gibbons’ evidence as part of my chronological fact finding below. Relevantly, I accept as mostly accurate the contents of Mr Gibbons’ two statements including what he says in his Second Statement about his interaction with Mr Rothner on 2 April 2024.
Whilst Mr Gibbons freely admitted in cross-examination that he was “genuinely grateful” to Mr and Mrs Waterhouse and wanted to help them in this litigation, I do not regard this as providing a reason to further question Mr Gibbons’ evidence. It was not suggested that Mr Gibbons’ was giving deliberately false evidence, just to help Mr Waterhouse. Having observed him in the witness box, I would not have accepted such a contention if made. Mr Gibbons’ affinity for Mr Waterhouse was explained by what Mr Waterhouse had done for Mr Gibbons. The affinity simply reinforces the necessity of a cautious approach to Mr Gibbons’ evidence.
Without wishing to be unkind to Mr Gibbons, he did not appear to me to be overly sophisticated or articulate. He struck me, however, as a person seeking to do his best to assist the Court in giving his evidence. It is the inconsistency of some parts of his evidence with objective material that warrants a cautious approach to it.
In relation to Mr Waterhouse, I also approach his evidence with considerable caution. It was obvious to me throughout the hearing that Mr Waterhouse had a significant hand in the preparation of his case. That role continued to some extent when he entered the witness box. On a number of occasions in cross-examination, particularly early in the cross-examination, Mr Waterhouse did not answer the question asked but rather volunteered information that he no doubt thought would assist his case. I have carefully considered Mr Waterhouse’s oral and affidavit evidence against the objective material and inherent probabilities. In a number of respects, I do not accept his evidence, particularly as to aspects of the preparation of Mr Gibbons’ Second Statement.
For Mr Rothner, the principal witness was Mr Rothner himself. He was extensively cross-examined for about a day.
Mr Waterhouse contended that I should not accept key aspects of Mr Rothner’s evidence, particularly and importantly his denial of any knowledge, or approval of, the removal of trees from No 8. Having closely observed Mr Rothner in the witness box during his cross-examination, I have some difficulty in accepting key aspects of his evidence, particularly his denials on the key issues. They are difficult to reconcile against the objective material and inherent likelihoods.
A considerable number of text and WhatsApp messages were tendered in evidence between Mr and Mrs Rothner. I set out a number of these messages in the chronological sequence below. For some unexplained reason, there are very few messages in April 2024 when some of the tree removal undoubtedly occurred. The messages produced provide a relatively reliable base against which to assess Mr Rothner’s oral evidence: see ET-China.com International Holdings Limited v Cheung (2021) 150 ACSR 461; [2021] NSWCA 24 at [25]-[30] per Bell P (Bathurst CJ and Leeming JA agreeing). The messages show regular communications between Mr and Mrs Rothner in relation to the work being carried out to the garden to open up the view from the Property, with Mr Rothner being engaged in the communications and indeed requesting pictures be sent. The messages include videos and in particular a video showing the view to the Sydney Harbour Bridge being opened up with more work to be done. This material paints a picture somewhat at odds with Mr Rothner’s denials of any knowledge of the tree removal on No 8, and the importance of views from the Property north toward the Harbour Bridge. Again, I approach Mr Rothner’s evidence with considerable caution. As set out below, I do not accept it on some lay aspects.
There was some brief expert evidence at the hearing.
First, concurrent evidence was given by Julia Conlon (Ms Conlon) (for Mr Waterhouse) and Jerome Srot (Mr Srot) (for Mr Rothner) as to what rent the Property would achieve if Mr Rothner’s right of occupation was validly terminated by Mr Waterhouse and the Property rented out prior to completion. There was a significant difference of opinion between the two as to what the Property would likely rent for. Whilst I accept that each was no doubt expressing their honest opinion, there were difficulties with each of their opinions. Mr Srot identified what he regarded as comparable properties, but it emerged reasonably clearly in cross-examination that they were not comparable but rather inferior to the Property. The likely rental in my view would be higher than Mr Srot’s estimate. Ms Conlon did not, however, identify any particular comparable properties so as to enable her opinion to be tested. The fact that she may have listed the Property for rent at $7,000 per week is far from determinative in the absence of some evidence that there would be any takers at this price. In the circumstances there is little alternative other than to adopt a mid-point between the two.
Second, David Madden (Mr Madden), a quantity surveyor called by Mr Rothner, was briefly cross-examined by junior counsel for Mr Waterhouse on day 4 of the hearing. I did not understand any credit attack to be levelled at his evidence.
Finally, Gavin Rubinstein (Mr Rubinstein), a real estate agent called by Mr Rothner was briefly cross-examined in relation to the opinion he expressed as to how long it would take to sell the Property if put on the market. Again, no credit issues arose.
Experts were also retained by Mr Waterhouse and Mr Rothner in relation to the trees that were cut down on No. 8. They ultimately reached agreement and as such neither was required for cross-examination.
It was contended by Mr Waterhouse that Mr Rothner should have called Mrs Rothner to give evidence in his case and that I should draw a Jones v Dunkel inference against Mr Rothner for failing to do so.
The issue is complicated by the fact that Mrs Rothner is a party to the proceedings as the second defendant. She made an affidavit. On the second morning of the hearing, however, she was granted leave to file a submitting appearance save as to costs. Her counsel then withdrew from the hearing. This was consequent upon Mr Waterhouse dropping the claims against Mrs Rothner for injunctive relief and damages, leaving only declaratory relief.
Mrs Rothner remained in the back of the court for most of the rest of the initial hearing, including during the cross-examination of Mr Rothner.
In closing submissions, counsel for Mr Rothner contended that a Jones v Dunkel inference should not be drawn for two reasons.
First, an ex-wife could not be said to be in the camp of her ex-husband. Secondly, while there were allegations being made against Mrs Rothner, one would not expect Mr Rothner to call her.
It was accepted that there were two matters on which it may be expected that Mrs Rothner would give evidence:
(a) whether any authorisation was given by Mr Rothner to Mrs Rothner for the removal of trees on No 8; and (b) on the events of 2 April 2024 given by Mr Gibbons involving Mr Rothner in the presence of Mrs Rothner.
In the circumstances of the present case, I am satisfied that it would be expected or natural for Mr Rothner to call Mrs Rothner as a witness in his case. The evidence established that although Mr and Mrs Rothner separated in 2014 and divorced approximately three years later, they thereafter have continued to enjoy a close relationship. This close relationship went to the heart of the work which led to the allegations in these proceedings – namely the renovation of the Property including the removal of vegetation and trees to improve the view. There was no suggestion in the evidence of a falling out between Mr and Mrs Rothner which may have explained her not being called.
The fact that Mrs Rothner is a defendant in the proceedings facing her own allegations does not, in my view, provide a reason for Mr Rothner not to call Mrs Rothner. There is no suggestion that their respective interests were not aligned. After the injunctive and monetary relief was dropped against Mrs Rothner, she filed a submitting appearance. She no longer had any significant interest in the case.
I am conscious that the significance of Mrs Rothner not being called is to be assessed by reference to the relevant issues on which it may be expected she would have been called.
I am also conscious, as senior counsel for Mr Rothner submitted to me in closing submissions, that the failure to call Mrs Rothner cannot be used to fill gaps in the evidence: see Schellenberg v Tunnel Holdings Pty Ltd (2000) 200 CLR 121; [2000] HCA 18 at [53] per Gleeson CJ and McHugh J.
I address below, where necessary, what flows from the failure to call Mrs Rothner.
On the morning of the fourth day of the hearing, junior counsel for Mr Waterhouse made an application for leave to rely on an affidavit of Olivia (Mr Waterhouse’s daughter) which had been served unsworn on the evening before (Sunday 16 November 2025) and which I was informed would be adopted by Olivia in the witness box if I permitted the evidence to be given.
An application was made earlier in the hearing – on day 2 – for Olivia to be called to give evidence orally and without notice. I refused that application and indicated that if Mr Waterhouse wished to seek leave to rely on evidence from Olivia, an affidavit should be prepared and served before any such application was made. The unsworn affidavit from Olivia was subsequently served on the basis she would adopt it when called.
Mr Rothner opposed the application by Mr Waterhouse to rely on Olivia’s affidavit. Reliance was placed on an affidavit made by Jonathan Milner (Mr Milner), Mr Rothner’s solicitor who set out the steps that he would have taken had he been given earlier notice of the intention to rely on the affidavit of Olivia.
After hearing argument, I refused the application to rely on Olivia’s affidavit. I indicated that I would give reasons in my final judgment for this decision.
In simple terms, I took the view that it would not be in the interests of justice to permit Mr Waterhouse to rely on Olivia’s affidavit. This is because there was no reason why the affidavit could not have been served much earlier than it was, which would have allowed Mr Rothner to take the steps set out by Mr Milner in his affidavit.
The fact that the involvement of Olivia was referred to in the cross-examination of Mr Gibbons does not deal with the fact that Mr Waterhouse was always aware that the statutory declarations made by Mr Gibbons – and more particularly the second statutory declaration made 23 May 2024 – would be called into question and could have served evidence from Olivia as part of Mr Waterhouse’s evidence in chief.
There was no challenge to the evidence given by Mr Milner as to the steps that he says would have been taken had Olivia’s affidavit been served earlier. There was also no suggestion that the hearing could conclude within its allocated time if the steps were now taken. An adjournment would thus have been necessary. Even if that adjournment would only have been for a short period, new dates would need to have been found for the conclusion of the hearing. In the circumstances, including the history of the matter, I formed the view that it would not be in the interests of justice for this to occur.
At the time of the conclusion of the hearing in November 2025, the time for Mr Rothner to complete on the purchase of the Property had not been reached. He was required to complete by 22 December 2025. At least one party foreshadowed at the hearing that there would likely be an application to reopen after completion had occurred, if, as is the case, judgment had not been delivered by this time.
As it transpired, both Mr Waterhouse and Mr Rothner made applications by motion to reopen. The first in time was Mr Waterhouse by motion filed 5 February 2026 by which Mr Waterhouse sought the following orders:
1 The plaintiff have leave to re-open to:
a. Tender the Pexa Settlement Completion Record annexed hereto.
b. To make a submission on Mr Rothner’s lack of credit based on Pexa Settlement Completion Record.
2 The plaintiff be given access to the documents returned on subpoena by Dyson Austen.
3 Further, the plaintiff have leave to make further submissions as to Mr Rothner’s credit upon review of the material provided on return of subpoena by the National Australia Bank, Boskoviz, the Commissioner of State Revenue and Dyson Austen.
4 Costs on an indemnity basis.
1A Leave be granted to the First Defendant to re-open the proceedings to:
a. tender evidence; and
b. make submissions.
as to the quantum of the First Defendant’s loss on his cross-claim.
2 Order pursuant to r 33.4 of the Uniform Civil Procedure Rules 2005 (NSW) that the subpoenas issued by the Plaintiff on:
a. 6 January 2026 to ‘Boskovitz’;
b. 5 January 2026 to ‘Revenue NSW’; and
c. 5 January 2026 to ‘National Australia Bank Limited’,
be set aside.
3 Order that the documents produced in compliance with those subpoenas be returned to the entities that produced those documents.
4 The Plaintiff pay the First Defendant’s costs of and incidental to the notice of motion.
5 Such further or other orders as the Court considers appropriate.
In connection with the applications to reopen, Mr Waterhouse caused to be issued subpoenas to Mr Rothner’s conveyancing solicitor (Boskovitz), Revenue NSW, National Australia Bank Limited, BIDA Design Consultants Pty Ltd as well as a notice to produce to Mr Rothner. Mr Rothner sought to set each of these aside.
Due to various availability reasons of the parties, which do not need to be traversed in these reasons, it was not possible for the motions to reopen and to set aside the subpoenas and notice to produce, to be heard until 30 April 2026.
Mr Waterhouse made a number of affidavits in support of his position. Mr Rothner relied on two affidavits made by Mr Milner. I also had the benefit of written submissions from both sides. Mr Milner was briefly cross-examined. No credit issues arose from this.
It was not in dispute that the purchase completed on 17 December 2025. The PEXA settlement statement stated that the funds to enable Mr Rothner to settle were provided by the National Australia Bank (NAB). During the hearing, Mr Rothner gave evidence that he was borrowing funds from Pallas Capital. There was no mention of the NAB. Evidence led on the applications to reopen was to the effect that the NAB loan was cheaper for Mr Rothner than the proposed facility from Pallas Capital.
Mr Waterhouse’s position on the application was that he should be given leave to reopen to tender only the PEXA settlement statement, and that Mr Rothner’s application to reopen should be dismissed. Further, that if the Court was minded to grant Mr Rothner leave to reopen, it should be on condition that Mr Rothner be made available for further cross-examination and that Mr Waterhouse be given access to the documents produced or to be produced pursuant to the subpoenas and notice to produce. Mr Rothner would then be cross-examined not only as to the circumstances surrounding the change to the NAB, but also as to his intentions to carry out renovation works at the Property and then to resell it. There would also be further cross-examination as to his credit and it was contended that the subpoena to Revenue NSW was relevant to Mr Rothner’s credit, namely whether he paid the correct amount of stamp duty or underpaid it.
Mr Rothner’s principal position, outlined in written submissions served prior to the hearing and clarified at the start of the hearing, was that he should be given leave to reopen to tender the documents evidencing the terms on which Mr Rothner borrowed money from the NAB and then to make submissions as to damages that should be awarded to Mr Rothner on his cross claim in light of that evidence. A fallback position was that leave to reopen should be given on particular topics in which case there was a possibility that Mr Rothner would make a further affidavit and would make himself available for cross-examination on that affidavit.
I ultimately determined that leave to reopen should only be granted in a limited manner to tender:
(a) the PEXA settlement statement; and (b) a document or documents evidencing the terms on which Mr Rothner borrowed funds from the NAB to enable him to settle on the purchase of the Property.
I thus confined the reopening to the objective facts that had occurred since the hearing. I also allowed the parties to make further submissions based on this further material, which they each did.
I was not satisfied that it was in the interests of justice for there to be any broader grant of leave: see Goodman Fielder Consumer Foods Pty Ltd v Graincorp Foods Australia Pty Ltd [2020] NSWSC 706 at [39]-[48].
It was not entirely clear to me what further material would be sought to be tendered. There was a real likelihood of a further delay in the finalisation of the matter whilst the further evidence was prepared and then tested in a further hearing. Each party had already had a more than adequate opportunity to present their cases to the Court.
I set out later in these reasons the documents that were subsequently tendered and their significance.
I set out below the relevant facts, resolving any factual disputes along the way.
Having regard to the issues to be determined, it is necessary to set out the facts in some detail. What follows is largely chronological.
Mr Waterhouse bought the Property in August 2021.
At the time of the sale to Mr Rothner, Mr Waterhouse had a loan from Westpac Banking Corporation (Westpac) secured by a registered first mortgage over the Property. The amount outstanding on that loan at the time was in the order of $14 million.
The Contract with Mr Rothner was entered into on 30 June 2023. As set out above, the purchase price was $25,750,000.
The date for completion stated on the front page of the Contract was 31 July 2025, subject to Special Condition 47, which was in the following terms:
47. Extended Completion
47.1 Notwithstanding the date for completion stipulated on the front page of this Contract, provided the purchaser gives written notice (the “Extension Notice”) to the vendor not less than three (3) months prior to 31 July 2025 and pays and releases to the vendor, at the time of giving such notice the sum as set out below (the “Extension Fees”) the date for completion shall be extended as set out below:
Payments of -
(a) $41,666.67 extends completion to 31 August 2025;
(b) $83,333.34 extends completion to 30 September 2025;
(c) $125,000.00 extends completion to 31 October 2025;
(d) $166,666.67 extends completion to 30 November 2025;
(e) $208,333.34 extends completion to 21 December 2025; and ,
(f) $250,000.00 extends completion to 31 January 2026.
47.2 The purchaser may give only one (1) Extension Notice.
47.3 The Extension Fees referred to in Special Condition 47.1 shall be in addition to the sale price and not credited towards the sale price.
47.4 Notwithstanding anything previously contained herein, should completion take place in 2026, and the vendor is liable for land tax for the 2026 land tax year, then the purchaser shall on completion reimburse the vendor for the amount of the land tax payable by the vendor for the 2026 land tax year, other than due to default on the part of the vendor in circumstances where the purchaser is ready, willing and able to complete.
As events have transpired, completion which was to take place by 22 December 2025, in fact took place on 17 December 2025. The Contract required the 10% deposit to be paid in two instalments – $257,500 (1%) on exchange and $2,317,500 (9%) on or before 31 July 2023. Two additional amounts were also required to be paid and released to Mr Waterhouse – $1,287,500 (5%) on or before 31 January 2024 and a further $1,287,500 (5%) on or before 31 January 2025. All of these payments were made when required.
Mr Rothner contends that at the time that he entered into the Contract he intended to renovate it and, as soon as he had completed on the Contract, to sell the Property.
The first of these contentions was not seriously in dispute although the extent of the renovations was. The second was in dispute with Mr Waterhouse contending that Mr Rothner was purchasing and renovating a family home for Mr Rothner and at least his daughters.
As to the first of these contentions, special conditions 48, 49 and 50 were included in the Contract, in the following terms:
48. Purchaser’s Right of Access
48.1 Subject to clause 43.2 provided the vendor has received the deposit monies equal to 10% of the sale price ($2,575,000.00) by 31 July 2023, the vendor grants a licence to the purchaser to access the property between the hours of 9am and 5pm daily from 31 July 2023 seven (7) days a week on the following terms and conditions:
(b) The right of access shall not permit the purchaser to conduct any commercial activity on the property, with the exception of the purchaser’s entitlement to carry out works as set out hereunder.
(c) The purchaser shall be entitled to carry out works to the garage and the garden (however, no work shall be carried out internally to the house) as may be proved by a Development Consent or work not requiring Council approval, provided: -
(i) all work is carried out in a proper and workmanlike manner;
(ii) all work is carried out by properly qualified and licenced tradespersons holding adequate and appropriate insurances the evidence of which shall be provided to the vendor;
(ii) the purchaser shall ensure, and provide evidence to the vendor, that the builder is properly licensed to carry out the required works and that appropriate insurance under the Home Building Act 1989 has been issued and maintained.
(iv) The purchaser indemnifies, and keeps indemnified, the vendor from any claim made against the vendor for damage to property or persons or whatsoever with regard to the works being carried out.
(v) The purchaser shall accept the property at completion subject to any work that has been carried out by or with the authority of the purchaser and shall make no claim on the vendor with respect to same.
(vi) All work on the property shall be carried out at the risk of the purchaser.
(vii) The purchaser shall cause no damage, nuisance or inconvenience to any adjoining property or occupier of an adjoining property.
48.2 The right of access granted to the purchaser may be terminated at the will of the vendor by giving the purchaser not less than fourteen (14) days notice in writing to that effect PROVIDED ALWAYS that the vendor shall not terminate the right of access unless and until the purchaser has failed to comply in any respect with the terms and conditions of this Special Condition AND has failed to rectify that non-compliance within the said period of fourteen (14) day period the contract is either terminated or rescinded.
48.3 Nothing in this Special Condition is intended to or shall confer in the purchaser any right as tenant of the property or create any relationship of landlord and tenant for the purposes of the Residential Tenancy Act 2010 as amended and any such implication or reference is hereby expressly negatived.
48.4 In the event of the purchaser being required to terminate his access to the property, the property will be returned to the vendor in the same condition and state of repair as at the date of this contract subject to any alterations or additions that have been approved by the Council or the vendor.
48.5 The provisions of clause 18 of this contract shall not apply as the purchaser is not being granted occupation of the property but rights of access as legal possession as his principal place of residence shall remain with the vendor.
48.6 The right of access is granted personally to the purchaser, and to those authorised by the purchaser with regard to the carrying out of any works, and is not capable of assignment by the purchaser, nor shall the purchaser grant any right of access, occupation or licence to a third party.
48.7 The purchaser shall keep the vendor indemnified against any claims or liabilities for damage, loss, or injury which may occur to the property, the improvements to the property or any person or persons who enter upon or near the property in respect of which indemnity the purchaser is required to take out such insurance as the vendor deems reasonable, including but not limited to, public risk insurance for not less than $20,000,000.00. Evidence of the currency of the insurance policies shall be provided to the vendor and such insurances are to be maintained until completion of this contract at the cost of the purchaser.
48.8 The purchaser will, at all times, comply with all relevant legislation and with the requirements of all relevant authorities having jurisdiction over or in respect of the property.
48.9 The purchaser acknowledges that he has not relied on any representation, warranty or other assurance from the vendor concerning his right of access or right to carry out works on the property.
48.10 The vendor shall continue until completion of this contract to be responsible for the payment of all rates, taxes and utilities on the property until completion, being council rates, water rates, electricity and gas. Payment of land tax is in accordance with clause 47.4. All rates, taxes and utility accounts shall remain in the name of the vendor until completion.
49. Purchaser**’s Right of Occupation**
49.1 Subject to clause 43.2 provided the vendor has received the deposit monies equal to 10% of the sale price ($2,575,000.00) by 31 July 2023, the vendor grants occupation of the property to the purchaser to exclusively occupy the property from 5 January 2024 until completion on the following terms and conditions:
(a) On 5 January 2024 the vendor will provide to the purchaser all keys, access cards and security codes necessary to allow the purchaser possession of the property.
(b) The right of occupation shall not permit the purchaser to conduct any commercial activity on the property, with the exception of the purchaser’s entitlement to carry out works as set out hereunder.
(c) The purchaser shall be entitled to carry out any works, by way of alterations or additions to the property, as may be either approved by a Development Consent or work not requiring Council approval, provided:-
(i) all work is carried out in a proper and workmanlike manner;
(ii) all work is carried out by properly qualified and licenced tradespersons holding adequate and appropriate-insurances the evidence of which shall be provided to the vendor;
(ii) the purchaser shall ensure, and provide evidence to the vendor, that the builder is properly licensed to carry out the required works and that appropriate insurance under the Home Building Act 1989 has been issued and maintained.
(iv) The purchaser indemnifies, and keeps indemnified, the vendor from any claim made against the vendor for damage to property or persons or whatsoever with regard to the works being carried out.
(v) The purchaser shall accept the property at completion subject to any work that has been carried out by or with the authority of the purchaser and shall make no claim on the vendor with respect to same.
(vi) All work on the property shall be carried out at the risk of the purchaser.
(vii) The purchaser shall cause no damage, nuisance or inconvenience to any adjoining property or occupier of an adjoining property.
49.2 The right of occupation granted to the purchaser may be terminated at the will of the vendor by giving the purchaser not less than fourteen (14) days notice in writing to that effect PROVIDED ALWAYS that the vendor shall not terminate the right of occupation unless and until the purchaser has failed to comply in any respect with the terms and conditions of this Special Condition AND has failed to rectify that non-compliance within the said fourteen (14) day period OR the contract is either terminated or rescinded.
49.3 Nothing in this Special Condition is intended to or shall confer in the purchaser any right as tenant of the property or create any relationship of landlord and tenant for the purposes of the Residential Tenancy Act 2010 as amended and any such implication or reference is hereby expressly negatived.
49.4 ln the event of the purchaser being required to terminate his occupation of the property, the property will be returned to the vendor in the same condition and state of repair as at the date of this contract, subject to any alterations or additions that have been approved by the Council or the vendor.
49.5 The provisions of clause 18 of this contract shall not apply.
49.6 The right of occupation is granted personally to the purchaser, and to those authorised by the purchaser with regard to the carrying out of any works, and is not capable of assignment by the purchaser, nor shall the purchaser-grant any right of access, occupation or licence to a third party.
49.7 The purchaser shall keep the vendor indemnified against any claims or liabilities for damage, loss, or injury which may occur to the property, the improvements to the property or any person or persons who enter upon or near the property in respect of which indemnity the purchaser is required to take out such insurance as the vendor deems reasonable, including but not limited to, public risk insurance for not less than $20,000,000.00. Evidence of the currency of the insurance policies shall be provided to the vendor and such insurances are to be maintained until completion of this contract at the cost of the purchaser.
49.8 The purchaser will, at all times, comply with all relevant legislation and with the requirements of all relevant authorities having jurisdiction over or in respect of the property.
49.9 The purchaser acknowledges that he has not relied on any representation, warranty or other assurance from the vendor concerning his right of occupation or right to carry out works on the property.
49.10 The vendor shall continue until completion of this contract to be responsible for the payment of all rates, taxes and utilities on the property until completion, being council rates, water rates, electricity and gas. Payment of land tax is in accordance with clause 47.4. All rates, taxes and utility accounts shall remain in the name of the vendor until completion.
50. Development Consent
50.1 The vendor will consent to the lodgement by the purchaser of a Development Application or application to vary a Development Application to the Council and will sign all such applications, plans and consents as may be reasonably required by the purchaser PROVIDED however this contract is in no way subject to the approval or lack of approval of any such Application which may or may not be granted. The costs of any such Application shall be borne by the purchaser and the purchaser shall indemnify the vendor with respect to same.
50.2 The vendor is deemed on the date of this contract to assign to the purchaser the Development Consent held by the vendor from the council in respect of the property and all the vendors rights to the related specifications, plans and documents. Should this contract be validly rescinded or terminated then the purchaser will re-assign the Development Consent back to the vendor. The vendor warrants that the vendor has paid in full all fees and expenses owing and payable to its consultants exchanged in the creation, preparation and lodgement of the Development Application resulting in the Development Consent and the vendor has paid all fees and expenses then due to the Council. The vendor will procure full and unfettered rights and/or an unconditional licence for the purchaser to use or modify the architects plans the subject of the Development Consent. The vendor will give all consents and sign all documents to give effect to this clause.
50.3 The purchaser has relied on his own enquiries and investigations of the Council and any other relevant authority regarding the Development Consent and has not relied on any statement, representation or warranty by or on behalf of the vendor whether expressed or implied in relation to the Development Consent or any matter arising out of or in any way connected with the Development Consent.
The insertion of these special conditions were to facilitate Mr Rothner’s development of the Property.
Prior to entering into the Contract, Mr Rothner sought advice from his architect, Michael Suttie (Mr Suttie), on whether there were any surrounding developments that may impact the view from the Property. In early June 2023, Mr Suttie emailed Mr and Mrs Rothner attaching a document which reviewed “current DA’s” on Woollahra Council’s (Council) planning portal. Mr Suttie identified that the only “project of concern is occurring at 10a” being a reference to 10a Tivoli Gardens. The covering email stated, in part:
..as you will see from our work to date that whilst the proposal is substantial and in the view corridor to the bridge, it is largely within the existing canopy, and as such does not appear to substantially impact on the views of the water or bridge from the proposed new level.
The issue is much bigger then the extension of the top floor alone. It’s a concern from all levels including the garden areas if there is any obstruction of water or city skyline.
At the time of the Contract there were DAs which were thought to be in effect in relation to the Property. The first – referred to as the Garage DA, was obtained in June 2007 by the former owner of the Property (DA 795/06).
The second, referred to as the House DA, was obtained by Mr Waterhouse in 2021 – DA 518/2021. The DA included approval for an extra storey.
A third – DA 67/2025 – was subsequently obtained concerning the construction of a wellness centre on the Property (Wellness Centre DA).
The second contention – that Mr Rothner intended to sell the Property once he had renovated it and completed on the purchase of it – was hotly disputed by Mr Waterhouse. Mr Waterhouse contended that Mr Rothner did not acquire the Property as an investment – to renovate and then sell hopefully at a profit – but rather acquired it as a family home for him, Mrs Rothner and Mr Rothner’s three daughters. It was also in dispute whether Mr Rothner would, had Mr Waterhouse consented, immediately undertaken works to the house once it emerged (as set out below) that the Garage DA was invalid and another DA would need to be submitted, or whether he would have done all renovations at once after a new DA had been obtained. I deal with these issues later in these reasons.
On 31 July 2023, Westpac issued a letter to Mr Rothner in the following terms:
Regarding your purchase of 6 Tivoli Avenue ROSE BAY NSW 2029 from Mr David Richard Charles Waterhouse, we confirm that Mr Waterhouse is a customer of the Bank and that the Bank currently holds a mortgage (the Mortgage) over the above property (the Property). We understand you have or will enter into a contract to purchase the property from Mr Waterhouse.
At the request of Mr Waterhouse, we confirm to you that:
- The outstanding balance of the loan secured by the Mortgage does not currently exceed $14.1m.
- That on receipt of the full 10% deposit of the purchase price ($2.575m), Westpac agrees to reduce the limit of the relevant loan to $12,000,000.
- Westpac consents to you registering a second mortgage behind our first registered mortgage. This will further be supported by an agreed Letter of Priority which will limit our prior interest to $12m (plus fees and interest).
- The Bank undertakes to discharge our first registered mortgage once all monies owing under the mortgage have been paid.
A reminder that all other conditions under the first registered mortgage would otherwise continue to apply.
Mr Rothner sought to immediately exercise his visitation rights under the Contract. It was not in dispute that Mr Rothner authorised Mrs Rothner to carry out the works on the Property. The extent of that authority is in issue.
A dispute arose early in relation to this which involved correspondence between the parties’ respective solicitors. The correspondence states that it was Mr Rothner’s intention to immediately commence external renovation works covering the garage, the structure beneath and all external grounds. No work on the main home would take place prior to possession on 4 January 2024.
As at 9 August 2023, Mr Rothner (or more accurately consultants working for him) were seeking quotes to carry out geotechnical investigations in relation to the Property. By 13 August 2023, quotes were being sought for tree/shrub pruning and removal works. Scott Freeman (Mr Freeman) had been engaged by Mr Rothner as a horticultural expert. Sandra Ongaro (Ms Ongaro), a director and interior designer had also been engaged by Mr Rothner with overall responsibility for the proposed works.
On 14 August 2023, Ms Ongaro sent an Arborists Report to Mr Rothner proposing a staged approach to tree removal on the Property. Section J refers to “clearing the view”. It is clear from this early time that Mrs Rothner was to be involved in relation to the garden work. Ms Ongaro’s communications were addressed to Mr and Mrs Rothner. As set out above, it was not in dispute that Mr Rothner authorised Mrs Rothner to carry out this work.
On 17 August 2023, Michael Drake (Mr Drake) of Westpac telephoned Mr Waterhouse to inform him that he needed Westpac’s approval in order to carry out internal works on the house. Mr Drake did not say that Westpac would not approve the work but that approval was necessary.
On 21 August 2023, Mr Waterhouse’s solicitor wrote to Mr Rothner’s solicitor as part of the correspondence working out the access arrangements, stating, inter alia, that the works being carried out by Mr Rothner would need to be approved by Westpac in accordance with the terms of the existing mortgage.
Mr Waterhouse immediately forwarded the letter to Mr Drake.
Mr Waterhouse was, at this time, engaged in discussions with Westpac (Mr Drake) with a view to changing his loan facility agreement such that the interest he would be paying would be reduced by approximately 1% per annum. At the time of the Contract, he owed Westpac approximately $14 million and was paying interest of 6% per annum. Mr Waterhouse expected to be able to change his loan.
Mr Waterhouse’s dealings with Westpac at this time are relied on by Mr Rothner as bearing on Mr Waterhouse’s motives in his dealings with Mr Rothner, including in relation to Mr Waterhouse signing (or refusing to sign) documents consenting to the work which Mr Rothner was proposing to carry out.
The correspondence between the solicitors continued in relation to the conditions attaching to access including whose responsibility it was to obtain Westpac’s approval and whether Mr Rothner was required to have his own insurance for the work he was proposing to carry out. By email dated 22 August 2023, Mr Rothner’s solicitor contended that it was Mr Waterhouse that was required to obtain the approval.
In about early September 2023, Mr Waterhouse was informed by Westpac that his interest rate would not be reduced as he had expected but in fact it was to be increased to 6.5% per annum. Mr Waterhouse agreed that he was “extremely unhappy” about this. It was shortly after this time that Mr Waterhouse made the first suggestion to Mr Rothner to settle early (by text message sent on 13 September 2023). Mr Waterhouse rejected the suggestion that the only reason he suggested that Mr Rothner settle early was because of Westpac’s decision to increase his interest rate on the loan. He said it was also because he thought that Westpac had reneged on Mr Rothner doing work on the Property.
On 5 September 2023, Mr Rothner and Mr Waterhouse exchanged text messages in relation to the proposed works. Mr Rothner’s texts included:
I am not doing main house at all initially as I said but it will be second half of next year. First stage just garage and grounds.
Tree cutting on the Property appears to have begun in about mid-September 2023. On 21 September 2023 Mr Waterhouse complained to Ms Ongaro that the contractors only had $5 million in insurance, not $20 million as required. Mrs Rothner had earlier texted Mr Rothner on 11 September 2023 telling him that the arborist was to start on Thursday, which would have been 14 September 2023.
On 14 September 2023, Mr and Mrs Rothner exchanged a number of WhatsApp messages which began after Ms Ongaro had told Mr Rothner that the difference from the arborists work already was enormous. Mr Rothner asked Mrs Rothner:
Has it genuinely opened the view that much? We need to take as much as possible out of garden level that is in front of verandah as well. Don’t make it too bare btw but I think there is ample foliage.
In her responses Mrs Rothner told Mr Rothner that her “vision is coming to life”.
There is no suggestion at this early stage that the plants being removed were located on No 8. The significance of the exchange is the considerable interest of Mr Rothner from the very beginning, in the work that Mrs Rothner was doing to open up the view. He was actively involved in understanding what was being done.
On 22 September 2023, Mrs Rothner texted the image below to Mr Rothner, saying “you’re going to be *blown…away”, to which Mr Rothner replied “even looks good in these conditions – phenomenal”:
By at least 1 October 2023, Mr Waterhouse had formalised an offer to Mr Rothner to settle early. The offer was in the following terms and was repeated by Mr Waterhouse on several occasions:
Re early settlement: Property in Michael’s name and taking possession on settlement with green light to do renovations-no interference from Westpac, as property is in owner’s name (not a 10% deposit holder as the position is now-which credit dept. of Westpac don’t like)
First mortgage(FM) of $12m-David to guarantee with WBC
Second mortgage of $11,185,000 interest free for 3 years-saving the final year interest bill
The negative is the cost of interest on FM
The plus is saving interest on the 3rd year second mortgage
The difference-when match is one year of interest $720,000
The windfall is non-payment of $250,000 to extend 6 months
The windfall of $2,575,000(not needed to pay in Jan 2024/25) of extra spare cash over the 2 years to help with the renovations-worth $200,000 in saving in interest and $500,000 in renovation cost -as doing everything at one hit
Michael’s overall cost around is plus for michael of + $230k or if renovation costs no difference then a cost - $270k to Michael-off set with guarantee from David
David’s risk apart from guarantee of FM-cost of taking re-possession of property and paying $1.8m in stamp duty
Smart deal for both parties-as per previous negations-this is full and final offer.
As you know, we act for Michael Rothner.
As you also know, our client exchanged contracts on 30 June 2023 to purchase the above property from your customer David Waterhouse (“contract for sale”). Amongst other things, the contract for sale provides for a delayed settlement, with access and occupation rights to our client and the right for our client to carry out certain building works to the property specified in the contract for sale prior to settlement.
Although not relevant to our client’s entitlement to exercise his rights under the contract for sale, it is our client’s understanding that Westapc [sic] approved the contract for sale.
We are instructed that David Waterhouse has asked our client to provide Westpac with certain information about the building works to the property proposed by our client, including providing to Westpac evidence of insurance, poof [sic] of funds to carry out the works and the name of the builder.
Although our client believes it has no obligation to provide this information to Westpac nor seek the consent of Westpac to the building works to the property proposed by our client, in the interests of co-operation our client has provided us with the attached letter from his project manager Sandra Ongaro detailing the scope of works and other relevant information, which includes the existing development consent which we understand Westpac is already aware of. In this regard, our client notes that he is not a party to the mortgage nor is he buying the property subject to the mortgage.
In addition, we are instructed that:
• Our client is only proceeding at this stage with the garage works which is referred to in the letter from the project manager, not the approved works for the main residence.
• The garage works will be commencing soon.
• Without any obligation to do so, our client will at a later date inform Westpac when the approved works for the main residence will commence and the scope of those works.
The attached letter from Ms Ongaro stated that the “project consists of demolition of an existing garage, followed by the excavation and construction of a new Secondary two storeys dwelling with garage above”.
On 1 November 2023, Mr Waterhouse sent a text message to Mr Rothner as follows:
Re structure work includes knocking a wall down (painting or tile is ok) the Tivoli property – WBC have stated with their mortgage – they will not approve it and if work happens then I’m in default on the conditions of the loan.
So if you are insisting on that – then either i find another lender or you settle earlier as per my written offer
I have informed Sandra – that I (as owner) can not sign anything involving structural work
Mr Waterhouse did not agree that he was exaggerating Westpac’s position in this text message in that Westpac had only said that approval was required, not that they would not approve. I do not accept this evidence. I am satisfied that Mr Waterhouse was seeking to persuade Mr Rothner to settle early by exaggerating Westpac’s position.
On 7 November 2023, Mr and Mrs Rothner exchanged text messages. Mrs Rothner sent Mr Rothner the below photograph to which he responded “Beautiful”:
In a later text that day, Mrs Rothner said to Mr Rothner “once my vision comes to life anyone & everyone is going to be blown away”.
In mid-November 2023, Mr Rothner put Mr Waterhouse in touch with the NAB for the purposes of seeking to refinance from Westpac to NAB pending settlement of Mr Rothner’s purchase. On 14 November 2023, Mr Waterhouse sent an email to an NAB representative and Mr Rothner making an offer to settle early. The email was in the following terms:
Good to talk to you just now.
I think you agree in the unlikely event NAB did gave me the loan (re issue with serviceably) ,then their credit dept.(who would want to see the contract) would have the same constraints as WBC Credit about a non-vender [sic] doing the internal works on the house.
I really think if Michael is hell-bent doing the internal works on the house, then he should consider settling early. If not and he does the work and WBC find out (in the loan doct they can inspect any time) via neighbour complaining to council and even driving pass the property-then I would be in-default on the loan and they could call in my loan forthwith ,which would be terrible for both parties.
Please see attached my offer to settle early.
On a valuation of $26m(I know another buyer had a valuation on the property at $30m)-all he has to find is $9.425m ($12m less $2.575m payable Jan 2024 and Jan 2025) on a FM-36% LVR.
NAB should be nod.
I would give him a second for $11,175m for 3 years interest free.
It’s a win-win for everyone, with no risk of being in default with WBC.
By this time, it appears that Mr Rothner’s position had changed in relation to carrying out the internal works. Mr Waterhouse was seeking to take advantage of that change to get him (Mr Rothner) to settle early.
The offer seemed to be precipitated by an email from Mr Drake of Westpac to Mr Rothner on 10 November 2023 which Mr Rothner forwarded to Mr Waterhouse on 13 November 2023. The Westpac email stated:
Just a quick note to confirm that the Bank has granted formal consent to progress the proposed works the garage, etc, as was previously sought.
I note this was technically approved back on 25/10 but I understand approval was only conveyed verbally.
I spoke briefly with Michael on Wednesday this week and undertook to confirm said approval in writing.
Please don’t hesitate to let me know any issues or questions.
They don’t mention the house.
You need approval re the house-or I will be in default.
Re-conceder early settlement.
It’s a win for you and takes me out of the firing line with the bank
Mr Waterhouse attached to the email the same settlement offer he made on 1 October 2023.
At this time, Mr Waterhouse was being pressed by Mr Rothner to sign a consent to Woollahra Council for amended plans for the Garage DA to be submitted. Ms Ongaro had sent the “Replacement Application” form to Mr Waterhouse for his signature on 6 November 2023. At 2.19pm on 14 November 2023, Mr Waterhouse emailed Ms Ongaro in the following terms:
Gary Kosmin wants an inclusion that any work done in the house by Michael and causing my loan with WBC to be in default -then the settlement is brought forward forthwith.
WBC are giving me major grief re this provision-they just suggested I should move banks, as they will default me if work is done inside the house.
I think I must switch lenders-so I cannot sign anything until this is sorted.
I think the smartest and best idea is to settle early.
It appears that Mr Waterhouse signed the form later that afternoon. His email was again, overstating Westpac’s position in an effort to persuade Mr Rothner to settle early.
On 15 November 2023, Ms Ongaro sent an email to Mr Waterhouse, copied to Mr Rothner, confirming that no construction works would take place at the Property without all relevant insurances being submitted to Mr Waterhouse for his approval prior to any works taking place.
At about this time, Mr Waterhouse was exploring refinancing with the Bank of Singapore. On 15 November 2023, he texted Mr Rothner asking if he (Mr Rothner) could bring forward one of the part payments under the Contract as this would help with the transfer to the Bank of Singapore. Mr Rothner asked if Mr Waterhouse, in return, was able to provide earlier access to Mr Rothner. Mr Waterhouse replied that this was impossible because the Property was rented until 3 January. Mr Waterhouse admitted this “was a fib”. His ex-wife and her sick partner were staying there at the time.
The expert arborists agreed that the first tree cutting event on No 8 occurred between 3 October 2023 and 7 December 2023, with a Native Daphne, five metres in height, removed. A text message from Mr Shahwan to Mrs Rothner dated 10 December 2023 or shortly thereafter states:
Hi Lisa, I came back just to tidy up a few things, the guys cutting down the tree next door. I’ll be sure to clean the front and Jetski once they leave and before I leave this afternoon.
(Emphasis added.)
We refer to the above and note that pursuant to clause 43.4 of the Contract, the Purchaser is required to pay the Vendor an amount of $1,287,500.00 (5% of the price) on or before 31 January 2024. We are instructed that our respective clients have agreed that the amount due be paid on 5 January 2024, prior to the Purchaser taking occupation, pursuant to clause 49 of the Contract. In consideration, the Vendor offers a reduction in the amount payable by $4,500.00 to compensate the Purchaser for lost interest. Please confirm your client’s instructions.
In the meantime, we refer to clauses 48.7 (relating to the current access period) and clause 49.7 (the occupation period) and request copies of the insurance policy held by the Purchaser as our client is concerned that the policy currently held may not contain sufficient coverage.
Further, we refer to clause 49.1(c)(ii) and request that evidence of the builders licence and appropriate insurance under the Home Building Act 1989 be provided.
We are instructed that your client has agreed to sign off that he accepts the property (inside and outside including the pool) in its state of repair and condition prior to taking occupation.
We are also instructed that our respective clients have had discussions concerning our client’s consideration of changing his mortgagee bank from Westpac Bank to Bank of Singapore. The Westpac Bank, due to the existence of the Contract, are charging at bridging loan rates and are not necessarily being cooperative concerning the Purchasers proposed building works.
We respectfully submit that the Vendor does not require the Purchaser’s consent to change banks, however, in the spirit of cooperation, should the Vendor decide to proceed with the Bank of Singapore it shall be appropriate for the change to be documented between our clients. The Vendor is of the opinion that the Bank of Singapore shall be less stringent in granting approval for the carrying out of works by the Purchaser.
We thank you for your assistance and await your reply.
Reference is made to your letter of 6 December 2023 and we respond as follows using the numbers set out against each paragraph as shown in the attached letter:
- Subject to agreement being reached on all other matters our client agrees to pay $1,287,500 on 5 January 2024 subject also to occupation being given to our client on or before that date. Our client would pay the amount into our Trust Account prior to that date with instructions to pay upon occupation being given to our client. Our client does not wish to receive interest. He merely wishes the next instalment to be extended by 26 days.
- We sent the policy to you some time ago with no comment from you. What is sufficient coverage? Please provide details. When our client takes occupation he will take out full comprehensive insurance when he moves in.
- When our client engages a builder and commences work we will provide this insurance.
- Our client (as is yours) is bound by the conditions of the Contract.
- In principle, our client has no objection to your client changing mortgagees provided that his position is not compromised in any way. Whilst you say your client is not obliged to seek consent, this is obviously not correct. There is no doubt that Bank of Singapore will require documents signed by our client. Where in the Contract does your client have the right to require our client to do so?
In any event, our client reserves his position until he sees the documentation. Our client wishes to co-operate but cannot confirm until he is satisfied he will be no worse off.
We await to hear from you.
I refer to my conversation with you of a few minutes ago. My client is very upset with the contents of his telephone conversation with your client. Your client has threatened that unless our client agrees to the Bank of Singapore taking Westpac over without first looking at the documentation, he will not allow our client to move in on 5 January as prescribed by the Contract.
Such heavy handed behavior [sic] will not be tolerated. In the event that our client is not given possession on 5 January, we have instructions to institute immediate proceedings.
Your client will be in breach of his contractual obligations and our client will be entitled to all damages arising out of such breach including payment of rent that our client is obliged to pay elsewhere whilst he is not allowed to enter into possession.
In any event, our client does not understand your client’s outrage. What is more confusing, is that your client has not spoken to you recently and has not discussed this issue. We understand your client is coming to see you tomorrow.
It should be made abundantly clear to your client that he has picked the wrong target if he thinks he can bully our client into a course of action. This will certainly not work in this case.
We have indicated to you in previous correspondence that our client wishes to co-operate with your client in all ways possible. However, your client cannot expect our client to agree to something without seeing the documentation relating to it.
Further to our last conversation, our client has sent us a copy of a text your client has sent him indicating that our client does not have proper insurance in place. That is not correct. Our client has proper insurance covering the current situation. When our client is given possession, he will then look at the insurance situation. In any event, if your client thinks proper insurance is not in place, then your client should immediately identify what insurance our client should have. For example, your client in previous correspondence talked about builder’s insurance. Our client does not have a builder at the moment so there is no builder’s insurance required.
Please ask your client to accept this letter in the most serious spirit in which it is intended.
The writer met with our client this morning and I am instructed that he has never “threatened” your client. He has requested your client to consent to the substitution of the Bank of Singapore instead of the Westpac Bank in the transaction although the terms of a new loan are not likely to be settled until January or February. The reason being that Westpac Bank have increased the interest rate under the facility as a consequence of the building works being carried out by your client. Your client’s co-operation is appreciated.
Our client intends to abide by the Contract in giving occupation of the property, pursuant to the terms of the Contract, on 5 January 2024 and, we note, that your client has agreed (point 1 of your letter of 11 December 2023) to make the payment due of $1,287,500.00 on the day of occupation.
However, our client is concerned that proper and adequate insurance (building and public risk) as required by clause 49.7 be in place prior to your client taking occupation. Accordingly, it is requested that evidence of the insurance policies and copies of the policies be provided.
Your client’s attention to this matter urgently, so that it is not left to the last minute, would be appreciated.
Mr Waterhouse denied in cross-examination that he said what John Landerer (Mr Landerer) had alleged in his letter. There is no need for me to determine whether he did because whatever was said was overtaken by the letter in response from Gary Kosmin (Mr Kosmin) (Mr Waterhouse’s solicitor). I am in no doubt, however, that Mr Waterhouse was seeking to exert as much pressure on Mr Rothner as he could to either consent to Mr Waterhouse refinancing with Bank of Singapore or settle early.
Proceedings were threatened by Mr Rothner prior to Christmas in 2023 to ensure access on 5 January 2024. Mr Waterhouse agreed that by December 2023 his relationship with Mr Rothner had become estranged. During late December 2023, early January 2024, his relationship with Mr Rothner deteriorated and soured.
Mr Rothner’s insurance continued to be a live topic in the correspondence. Mr Waterhouse’s solicitor wrote to Mr Rothner’s solicitor on 20 December 2023, relevantly as follows:
We refer to your email of early this morning. The writer was only advised this morning that our client has been in discussions directly with Francis Douglas KC as we had provided him with a copy of your correspondence of yesterday and he was concerned that counsel would be available if required to attend Court today. If you have briefed counsel, we should be pleased to receive his name, should it be necessary for our client’s counsel to communicate with him.
You state in your email that our client is “disregarding his contractual obligations” whereas it appears that your client is the one disregarding his essential obligation under the Contract (clause 48.7) to provide the required insurances. Your client is required to provide evidence of property and public risk (not less than $20,000,000.00) insurances. Despite numerous requests, your client has not provided same.
However, through a third party, our client has received a Certificate of Currency from Berkley Insurance Australia (copy attached) for “Public and Products Liability”. This, we respectfully submit, is not appropriate insurance as we attach a copy of a page of the Insurer’s website which notes that the policy “protects businesses” with regard to “business activity and manufactured or supplied product”.
Our client requires evidence, from a reputable Insurer, of building insurance for not less than $7,500,000.00 and public liability insurance. We note that failure to provide the insurances is a breach of the Contract, entitling the Vendor to terminate the right of access. We trust that this shall be attended to urgently.
The Contract notes (clause 46) that the right of access was granted personally to the Purchaser and those authorised by the Purchaser “with regard to the carrying out of any works”. We are instructed that your client has completed his required works to the garden area and there is no need for further access. If further works are still required, please provide details and upon receipt of the appropriate insurances, access can continue to be provided.
In the meantime, the risk of access is too great and the Vendor is entitled to deny the Purchaser access.
P.S . We are instructed that Mr Douglas is available today but thereafter is not available until 28 or 29 December 2023.
By letter dated 21 December 2023, Mr Rothner’s solicitors requested that Mr Waterhouse sign an authority in the following terms:
Mr Waterhouse did not sign any such authority.
Mr Rothner moved into the Property on 5 January 2024.
In the week commencing 8 January 2024, there was considerable work in the garden, including the removal of trees. An invoice issued by Al Shahwan’s company, Livello Property Group (Livello) to Mrs Rothner dated 10 January 2024, suggests there was “removal of palm trees” on that day and further tree lopping occurred during the period between Wednesday 10 January to Sunday 14 January 2024.
On 8 January 2024, the following text message exchange occurred between Mrs and Mr Rothner:
| Mrs Rothner: | doing the ferns to open up the bridge | | Mr Rothner: | and trim back big 🌴 | | Mrs Rothner: | bit by bit | | Mrs Rothner: | Wednesday got the big team coming for Palm | | Mrs Rothner: | First one down | | Mrs Rothner: | Second down | | Mrs Rothner: | Removing trees with Al |
Mr Rothner’s response is strongly suggestive that he wanted a view of the bridge. That view was through No 8. In his oral evidence he sought to downplay any such desire.
Interspersed with these texts were videos from Mrs Rothner to Mr Rothner.
In one of his texts on 10 January 2024 to Mrs Rothner, Mr Rothner said:
Send pics – other than the big tree what else has helped the view?
On 10 January 2024, prior to the text I have extracted above, two videos were texted by Mrs Rothner to Mr Rothner. After the second video Mr Rothner asks, “How is that helping view?”.
It is not clear which video this is in response to.
One of the videos likely taken by Mrs Rothner and texted to Mr Rothner shows a view of the corridor from the Property. There is a voiceover by Mrs Rothner which includes:
That’s how it’s going to look on the left, they’re just coming round to the right. It’s opened it right up. Taken away two more there. [This appears to be a reference to trees on the Property]
Obviously we will do more here but we’ve gotta be smart.
Extracted below is a still from the video at the part where Mrs Rothner stated “we will do more here but we’ve gotta be smart”:
Mr Rothner said in cross-examination that he could not recall viewing this video. His evidence was relevantly as follows:
He subsequently said when I asked him whether he denies having seen this video – “I don’t recall having seen it at the time”.
I do not accept this evidence and, indeed, whether or not in the witness box Mr Rothner could recall viewing the video, I am satisfied that he did at the time he received it. The text exchanges between Mr and Mrs Rothner both before and after this indicate Mr Rothner actively sought out visual evidence from Mrs Rothner as to what she was doing in relation to the view. It is thus inherently likely that he viewed what he was sent.
On 11 January 2024, Mrs Rothner texted Mr Shahwan – “Al lets be smart re next door [obviously a reference to No 8] – I don’t think take too much” to which Mr Shahwan replied “Yes, bit by bit.”
On 12 January 2024, Mrs Rothner sent Mr Rothner a photograph of the Sydney Harbour Bridge from the Property:
The photograph was requested by Mr Rothner after the following exchanges. Earlier in the day, Mrs Rothner texted Mr Rothner:
Another 5 bird of paradise down.
This could only be a reference to trees on No 8 as there were no birds of paradise on the Property.
Mr Rothner responded:
Send pic pls
And the palms?
Pls send a pic from deck of corner house looking to water
I’ll go back into house after & take pics in the middle of it.
It is not clear on the evidence whether the reference by Mr Rothner to “the palms” is a reference to the palms on No 8 or some on the Property. In any event, the exchange continues to confirm the importance of the view to Mr Rothner. The removal of the 5 bird of paradise from No 8 and Mr Rothner’s response is strongly suggestive of Mr Rothner being aware of, and encouraging such work. It confirms an active joint endeavour between Mr and Mrs Rothner to open up the view, including by the removal of trees on No 8.
A comparison of the video of 10 January 2024 and the picture sent on 12 January 2024 suggests that there has been a significant reduction in what was below the two palms on No 8.
On 13 January 2024, the texts exchanged between Mr and Mrs Rothner state:
| Mrs Rothner: | Al’s still going…site will be cleared out tomoz. | | Mr Rothner: | Important - do not want anything left. Good to do Sun am when everyone away. |
Absolutely & we can’t have an evidence on site … Mike it’s just amazing.
Needs to be like 100 by Mon as from Mon council Mr Waterhouse etc
No innocent reason was suggested on behalf of Mr Rothner as to why both Mr and Mrs Rothner would be concerned to do the work whilst “everyone away” and that no evidence be left. The obvious inference is that the work was being done surreptitiously.
Amongst the many texts from Mrs Rothner to Mr Rothner on 13 January 2024 were:
We’ve got another huge mother fuker [sic] down.
On 14 January 2024 (Sunday), Mrs Rothner texted a video to Mr Rothner which was not in evidence. In the text exchange Mrs Rothner stated she arrived at the Property at 6.30 am, that there were “5 guys on site” and “Want to clear it out today … so no evidence”.
Mr Rothner responded:
Pls make sure they take ALL rubbish.
No probs r there?
Again, nothing was said on behalf of Mr Rothner to contradict the obvious continued inference that the work was being carried out surreptitiously.
On 17 January 2024, Council granted approval to the amended plans for the garage work.
A Livello invoice dated 24 January 2024 refers to Mr Shahwan cutting “two palms” on 24 January 2024.
On 31 January 2024, Mr Rothner’s solicitor sent an email to Mr Waterhouse’s solicitor attaching “a number of applications and consent forms that need be signed by your client as owner”.
The documents were sent under cover of three emails. The covering email ended:
We are aware your client is overseas but we would accept emailed consent forms with the originals sent to us when he returns. This is most important for our client and your client would be causing our client financial damage if he does not comply with his obligations as above.
The first email concerned the Garage DA. The second concerned a DA for the proposed Wellness Centre. The third email is the relevant one for the purposes of these proceedings. It concerned work to the house. The email included approved plans and an application form for a construction certificate (CC Application Form).
The CC Application Form referred to a DA 518/2021/2. The “Description of Development” stated “Alteration and additions to existing dwelling including enclosure of balcony, two new verandas and an attic room addition”. The value of the work was stated to be $302,488.
On 7 February 2024, Mr Rothner wrote to Mr Drake at Westpac in the following terms:
I hope this email finds you well and you had a pleasant break over Xmas and the new year.
As you may be aware, I released a further $1,287,500 to David Waterhouse the end of last month. I am in the process of moving into 6 Tivoli Avenue Rose Bay. I am getting the CC’s completed so work can commence on the garage in late March/early April. At the same time that I do works on rebuilding the garage, I am intending to extend/upgrade the kitchen, fix the roof and provide insulation, as well as do a cosmetic upgrade to the residence internally. I have asked my interior designer/project manager to outline below the works to be completed in addition to the garage. It is intended that the works will be undertaken simultaneously for efficiency.
Could you please review the below and confirm the Bank’s support to upgrade/extend the kitchen and do the repairs and cosmetic improvements to the residence at the same time as the garage. I am also able to remain at the premises whilst these works are being completed. In addition to the cost of the garage already approved, the costs estimated are going to be around $300K. I will be funding this cost with my own capital.
Also, I spoke to Kimberley before Xmas about opening an account with Westpac and am happy to set up a CMA and have funds on deposit to further cement the relationship at a personal level.
I look forward to your response in due course.
(Emphasis added.)
We have prepared a general Scope of Works to be submitted to Westpac Banking Corporation for the proposed main house works which has been itemised into three sections and they are Floor Plan Modification, Interior Renovation Works and Roof Repair. The Scope of Works for these areas are as follows:
Floor Plan Modification
Ground Floor (Back of House)
• Proposed Works – Ground floor extension of the main kitchen
• Activate (Part DA)
• Woollahra Council (Plans Attached)
• DA 518/2021/1
• Approved 23/12/21
First Floor (Back of House)
• Proposed Works – New verandah to be installed above main kitchen extension and new roof
• Activate (Part DA)
• Woollahra Council
• DA 518/2021/1
• Approved 23/12/21
Cosmetic Interior Renovation Works
Ground Floor
• Design and installation of new kitchen
• Painting
First Floor
• Flooring
• Painting
Roof Repair
• Removal of existing roof tiles (To be reused)
• Repair and installation of new ceiling rafters and joist
• Installation of sarking and insulation
Project Overview
• Estimated Duration of Works – 12-16 weeks from commencement
• Estimated Cost of Works $250,000 - $350,000 (Exclusive of GST)
On 16 February 2024, Mrs Rothner texted a photograph to Mr Rothner of several people standing on the Property with the palm trees on No 8 behind – along with a text stating “planning garden layout. Really productive positive meeting on site – they where [sic] on same page as my vision. V happy.” Mr Rothner responded “Great 👍” with a thumbs up emoji.
On 20 February 2024, Mr Waterhouse’s solicitors wrote to Mr Rothner’s solicitors in response to the 31 January 2024 request for Mr Waterhouse to consent:
We are instructed that our client has now had an opportunity to review your client’s proposed plans for the property.
Our client instructs us to convey the following concerns:
- Prior to entering the Contract, your client was provided with copies of the current approved Council plans for renovations to the property. Your client advised our client that he may wish to seek approval for some minor amendments to the approved plans.
It was never contemplated, as now provided in the plans submitted by your client for our client’s approval, that there would be a major redevelopment which would include substantial changes to the existing building including the removal of walls and a relocation of the pool area.
Our client is not trying to be obstructive as he has already given approval for changes requested by your client with regard to the garage. However, the current request could substantially affect the value of the property which is of real concern to our client when your client has only paid 15% of the purchase price.
Your client’s request is still being considered, taking into account that clause 50.1 of the Contract requires the vendor’s consent “as may be reasonably required by the purchaser”.
- Any application to the Council for consent to carry out alterations or additions to the property shall require the consent of the Westpac Bank as Mortgagee. Again, the Bank is likely to be concerned about the affect on the value of the property. In this regard, the Bank may require, if they grant consent to the lodgement of the plans, that no substantial building works commence until after completion of the Contract.
We shall contact you once we receive our client’s further instructions with regard to the above but should be pleased to receive your comments.
We refer to your letter dated 20 February 2024.
The contract regulates what works our client can carry out, and is in no way restricted in the manner you suggest.
Clause 49.1 (c), opening paragraph, is unequivocal and absolute. It expressly provides that:
The purchaser shall be entitled to carry out any works, by way of alterations or additions to the property, as may either be approved by a Development Consent or work not requiring Council approval ...
The vendor has no discretion in the matter, and provided the proposed works are either approved by a Development Consent or do not require Council approval, our client is entitled to carry out the works.
Clause 50.1 is equally unequivocal and absolute. It expressly provides that:
The vendor will consent to the lodgement by the purchaser of a Development Application or application to vary a Development Application to the council and will sign all such applications, plans and consents as may be reasonably required by the purchaser .. .
You have misunderstood the reference to “as may be reasonably required by the purchaser”**. This is simply a reference to the form of the consent the purchaser requires to be signed, not the substance of the Development Application or application to vary a Development Application.
Nothing in the contract makes our client’s rights to do works or your client’s obligations to provide consent to those works conditional on Westpac’s consent. Westpac’s consent is not relevant to our client’s entitlement to exercise his rights under the contract, nor is it relevant to your client performing his obligations under the contract. Our client has no obligation to provide information about the proposed works to Westpac, nor to seek the consent of Westpac to the proposed works. Our client notes that he is not a party to the Westpac mortgage nor is he buying the property subject to the mortgage. Whether or not our client approaches Westpac is a matter for our client.
Our client has every intention on enforcing his rights under the contract, and will certainly not be delaying his proposed works until after completion.
We refer to our letter of 2 February 2024 where we gave your client until Friday 23 February 2024 to sign the required documentation. We wish to reiterate once again that our client will not be stalled, bullied or in any way delayed by your client. You say your client does not wish to obstruct our client; we regret to advise this is not evident to us or our client. If indeed your client does not wish to obstruct our client why does he not immediately sign all applications other than those dealing with the wellness area all of which he has seen before.
We do not wish to waste money briefing Counsel until we know your client’s attitude. However, your client may rest assured that if he does not sign by the date stated, Counsel will be briefed and Court proceedings will be commenced including a claim for substantial damages.
In this regard, please advise if you have instructions to accept service.
(Emphasis in original.)
On 26 February 2024, Mr Waterhouse’s solicitors sent him a draft response to the letter from Mr Rothner’s solicitors dated 21 February 2024. The draft response proposed attaching a signed consent for the “Garage Extension” but not otherwise.
On 27 February 2024, Mr Rothner chased Westpac for a response to his 7 February 2024 email seeking Westpac’s support for the works to the house. Mr Drake responded on 28 February 2024 as follows:
Thanks for following up. Apologies responding to this earlier had slipped through the cracks!
Just to quickly share some, following a reshuffle in January Kim is no longer in my team. However, as I have been closely involved in this matter previously (and am familiar with the background) I think it makes sense for me to continue to run with this matter.
Let’s quickly recap: generally speaking and where the Bank holds a mortgage over a property, it is the obligation of the borrower to seek our permission before completing material works on the property. In this case we are just working on the basis that either David seeks this from us (effectively on your behalf) or you just seek from us directly (as you are doing here).
We previously considered and approved for the works on the garage to take place. I note from review of the prior DA that this actually involved some substantial work (knocking down and rebuilding the garage which is effectively a 3 storey structure adjoining the main building, which is then also more fully joined to the main building, also requiring work on the main building).
From what you are describing below in terms of additional works, this sounds relatively minor and cosmetic relative to the works already considered and approved. I am therefore inclined to simply give my support for these works to also take place at the same time (as you have outlined).
I have also considered that;
* the amount of debt outstanding against the security is reducing (as further payments take place),
* the works that you are completing should logically add further value to the security property, and
* given our understanding of your financial position, it is also reasonable to conclude that you have the financial capacity to complete the works.
Please note that I am not seeking to comment in any way in terms of any rights or obligations between David and yourself (in terms of your separate agreement). So if you still require David’s approval in terms of that agreement, that would be a separate matter.
I am simply saying that as a representative of the Bank, I acknowledge your advice to us that the works are to be completed, and I do not believe (from your description) that what is now being done is sufficient to warrant an additional formal submission for approval from Credit (in addition to the one already provided). I am therefore comfortable for these works to proceed.
Please let me know any questions or issues.
Just following your voicemail message, I thought it would be best to share with you the exact email interaction (below).
As was done previously in regards to the proposed works on the garage, Michael reached out to see if the Bank would consider for the works to be done.
As I have outlined, based on his description of works, it would not appear to me necessary to undertake a further formal approval beyond that which had already been obtained and provided previously.
However, as I have also clearly outlined in my email, this does not have any impact on any obligations Michael still has to you. As I have expressly stated, if he still requires your approval to undertake works then that would be a separate matter.
Please review and let’s look to discuss further tomorrow AM – I just need to leave now to attend a client function. Hopefully this has not caused any major issues!
Mr Waterhouse did not agree that, at this stage, he had no reason not to sign the application for a construction certificate that he had been sent. Mr Waterhouse said he was not going to sign unless Mr Rothner had proper insurance and he did not.
Mr Waterhouse also denied the suggestion that the reason why he did not sign the application for a construction certificate for the internal house works was because he did not want to lose his pressure point over Mr Rothner to persuade him to settle early or agree to the Bank of Singapore refinance.
This then led to the following email from Mr Waterhouse to Mr Drake at 5.02pm on 28 February 2024:
Please call.
I have just had a call from Gary Kosmin that you have approved Mr Rothner his own future DA, which he is demanding that I as owner lodge with Woollahra Council. I will not, as I don’t support these new huge massive plans for the property.
If this is true and is the case and you have given approval to plans which are new and have not been lodged with Council- without notifying myself, as the owner and client first-then I am shocked and extremely disappointed.
What right do you have to support anything without notifying myself first?
I remind youm [sic] Mr Rothner has only paid 15% of the purchase price, if he is allowed to embark on this massive undertaking of construction and does not complete, I would be in a unnecessary weaker position, which I do not want.
I would like a response asap-as Mr Rothner is threating Supreme Court action against me based on your approval/support for this proposed DA, which is totally different to the previously approved Council DA, which I obtained prior to selling the property to Mr Rothner.
From now on-the only approval Westpac should give or not give is the approved Council DA - not any future DA without obtain [sic] my approval-as client.
If Mr Rothner is not correct and you have not given approval to his proposed future DA-then please tread very carefully with Mr Rothner-until settlement.
I await your response
I have just send [sic] an email to you.
Based on your interaction, we will be most likely be going to the Supreme Court next week, which Mr Rothner is threatening now to do.
I think you should work out who you [sic] client is?
I am extremely annoyed you wrote this, without my approval-what right do you have to give approval for “additional works” on a property, without asking the owner/borrower?
If you have caused me to be [sic] the Supreme Court next week, you will have explain yourself giving this approval for this massive additional works.
I would like your superior to contact me about this email below, asap.
(The email below was Mr Drake’s cover email to Mr Waterhouse and his email to Mr Rothner, as extracted above.)
Reading the email below-Rothner has under played his plans massively -which is no excuse that you didn’t contact me before giving him “carte blanch” approval from Westpac.
This is the first of three emails -the proposed da is that big.
This annexure I have no issues-as the garage been previously approved-the next 2 emails I do.
Please on-send to credit dept. for their take on this
Mr Waterhouse forwarded to Mr Drake the three emails which Mr Rothner’s solicitors had emailed to Mr Waterhouse’s solicitor on 31 January 2024. Mr Waterhouse’s covering email to Mr Drake in relation to the proposed house renovations (the third email from Mr Rothner’s solicitor) referred to Mr Rothner “gutting the house” and said that Mr Waterhouse would not support this.
At 8.23am the following morning, Mr Drake emailed Mr Rothner:
Please refer to my email below from yesterday.
I have discussed with David who has provided me with a copy of the plans, and I can see the proposed works to be completed are materially more substantial than I feel they were described to me in your initial email.
As outlined, the view I initially gave that I did not feel we necessarily needed to go to Credit was based on the understanding that the additional works being undertaken were only “minor and cosmetic”.
Noting now that the actual works to now be undertaken are more substantial, then a formal submission to Credit will definitely be required.
The works outlined in the initial below email are exactly the works that are anticipated.
We have no intention of doing the top floor extension. We are only commencing works to the garage and internal cosmetic upgrades together with the extension to the kitchen as described below. The approval for the extension to the kitchen is part of the same DA to add an additional floor to the residence which is not occurring. We are specifically only activating the extension to the kitchen part of the DA at present.
I will forward you a separate email with attached plans from my project manager confirming this.
He then forwarded to Mr Drake an email from Ms Ongaro to Mr Rothner confirming Mr Rothner would not be activating the Attic Part of the DA.
Mr Drake then emailed Mr Waterhouse at 2.02pm on 29 February 2024:
Just to reaffirm per our discussion this morning, I will not be further communicating with Michael around these matters without your express confirmation.
I also understand from our discussion earlier today that you do not want us to commence a formal submission to seek approval from Credit for whatever works are now being sought (beyond the works previously considered which I would just refer to as “the garage”), which I have also advised Kim. So we will not commence any such process until confirmed.
I assume that at some point in future, Michael will again follow up to enquire about progress? It would be good to get your thoughts as to how you would like us to respond at that point?
Let us know what you think.
We refer to your “without prejudice” letter of 21 February 2024 and our telephone conversation this morning.
You previously provided Council Applications and Plans concerning three (3) proposed applications:-
1. Kitchen Balcony Enclosure
2. Garage Extension
3. Wellness Centre
Please find attach the Vendors signed consents on the Replacement Application (Section 4.55 Modifications to the approved Garage and Studio Structure) and on the Council’s Owners Consent Form. These consents are in respect of the Plans referred to by you as “Garage Extension” only.
We are advised that, so far as the Vendor is aware, the Westpac Bank as mortgagee has consented to the Garage Extension plans only.
We are instructed that the Westpac Bank will not agree to the other works being carried out as they could detrimentally affect the value of the property and their security, as substantial demolition works would be required and the currently approved DA, which extends the height of the building, may be in jeopardy.
Our client has obtained Senior Counsels advice concerning your interpretation of clauses 49.1(c) and 50.1 of the Contract. The advice is that the entitlement to carry out “any works” is to be read in the context of the whole Contract and the negotiations prior to the entering of the Contract. In this regard, the intention was always that the Purchaser would be entitled to vary the existing Development Application to a reasonable extent only. In this regard, we refer you to the email from David Voet of your office, dated 15 June 2023, wherein he states:-
Development Consent: Our client would submit particulars of any proposed DA modifications to the vendor for approval, such approval not to be unreasonably withheld. The vendor would then consent to any such applications to Council and allow our client to carry out those works once approved by Council. The agreement is for “DA modifications” only.
Further, with respect, your interpretation of clause 50.1 that the issue of “as may be reasonably required by the purchaser” only relates to the “form of consent” is strongly disputed. There is no question of reasonableness with the ‘‘form of consent” as the form of consent is a standard Woollahra Council form. The reasonableness relates to the applications and the plans as “reasonably required by the purchaser”. The applications and plans are to be “reasonable”.
However, as your client is aware, the Vendor is currently negotiating a refinance of the loan facility secured over the property by discharging the Westpac Bank and granting security to the Bank of Singapore. Without admission, this may require the Purchaser’s consent as we note the Purchaser holds a second mortgage over the property. The Vendor is of the view that the Bank of Singapore is likely to be less stringent concerning works being carried out on the property and, accordingly, it is requested whether your client might consent (if required) to the granting of the mortgage to the Bank of Singapore if requested by the Vendor.
In any event, should your client still feel a need to approach the Court for orders we are instructed to accept service, however, we cannot see how this can best serve either of our clients’ interests.
The letter again overstates Westpac’s position, a matter which Mr Rothner’s solicitor immediately picked up on.
Mr Rothner’s solicitor responded on 29 February 2024:
We refer to your letter of 28 February 2024.
In particular we refer to the paragraph beginning “We are advised that so far as the Vendor is aware ...” and the following paragraph “We are instructed that Westpac will not agree”. Please note this could not be further from the truth. We enclose herewith letter from Westpac clearly saying as at yesterday they consent to those works.
Our client is now sick and tired of your client’s procrastination and in fact misleading statements as contained in your letter.
Today our client received a letter from the Bank referring to a conversation with your client today. It is obvious your client has done his best to change the Bank’s mind. This is rather strange. Why is your client raising obstacles at every turn of events? We surely do not need to remind you that under the Contract your client is obliged to sign the various consents. The mortgage is your client’s mortgage and not our client’s. It is incumbent on your client to obtain his mortgagee’s consent and not our client’s. It seems your client is doing his best to cause difficulty for our client. No doubt this will be an important factor in any court proceedings.
It appears the DA in question covers the kitchen work and the upstairs work. Your client knows this because the plans were prepared at your client’s instructions.
We are telling you our client does only wish to proceed with the kitchen work at present and not with the upstairs work.
We request that the consent form be signed and returned to us immediately because as your client knows the Bank has approved the kitchen work.
As for the various interpretations of the Contract, we will leave this for the Court to determine if necessary and not you.
Our client sees no reason why he cannot communicate with the Bank and obviously the Bank is happy with this as well.
Further to my previous emails and requests, confirming that you refrain from any further communications with Mr Rothner unless I request re proposed internal works on Council approved works. If Mr Rothner or his advisers contact you, please refer the correspondence to myself or my solicitor, Mr Kosmin. Your repeated correspondence to Mr Rothner, without including me or seeking my approval to correspond directly to Mr Rothner, who is not party to the loan with Westpac, have made a difficult situation worse and could constitute a breach of the Code of Banking Practice, hopefully Mr Rothner [sic] threat of Supreme Court does not eventuate and this dies a natural death.
Re already Council approved works-Garage has the green light from Westpac Credit Dept. Which I appreciate and thank you.
The Main House if Westpac Credit Dept.. give a green light ,which is a matter for them. However the internal approved works of an extra storie [sic] is now moot, as Mr Rothner has decided not to add the addition stories.
He may want to do work approved in the December 2021 Council DA - which is to do with extending a kitchen veranda, however you suggested a good idea that WBC holds the funds in an escrow account to builders draw from this account, but this is a matter for WBC to decide. Westpac should not get involved in any proposed Council DA Plans, as it’s not approved and is no concern to Westpac unless approved.
Whilst we work through the legal issues with this matter, I would respectively [sic] request that Westpac reduce the interest rate to the previously agreed in June 2023-this was prior to the exchanging of the contract with Mr Rothner. The Bullet Loan Rate or a maximum rate of 6.49% (variable interest only rate) was offered by yourself at that time. Noting the rates quoted from Bank of Singapore at 6.05% and rates quoted from CBA/Bendigo are 6.29%.
I would appreciate your response in writing by close of business 8 March.
On 1 March 2024, Mr Rothner emailed Mr Drake asking him to “reconfirm your support to undertake the cosmetic and kitchen works to be completed concurrently with the garage.” This continues to suggest that, at least at this time, Mr Rothner was proposing to carry out the internal works at the same time as the garage works.
Shortly thereafter, Mr Drake forwarded Mr Rothner’s email to Mr Waterhouse asking Mr Waterhouse to let him “know how you would like me to reply?”
Mr Waterhouse responded to Mr Drake that evening:
The garage is separate to the house-whatever happens there-it cannot be worse than it is now.
A different story re main house-I would think Westpac need to see accepted quotes for the house re (BS) “cosmetic and kitchen works”-once this happened, I would think Westpac Credit would like to escrow these funds(from the purchaser) to insure completion.
Also, Westpac Credit would need someone to check on the site every few week-either someone from the credit team or the actual owner (I am barred-at the present from the site by Mr Rothner).
Lastly -this was a 24 month settlement-we have gone a terrible 8 months (caused by Mr Rothner) into it and the conditions are getting worse-so 16 months to go. I do not want to be in default with Westpac, because of Mr Rothner aggression or misinformation!
We confirm receipt of your email of 29 February 2024.
It is interesting that you refer to our client making “misleading statements” when your client clearly misled the Bank by claiming the works being undertaken were only “minor and cosmetic” (email from Michael Drake to Michael Rothner 29 February 2024 at 5:23AM).
Further, you have conveniently omitted that the Bank’s approval was subsequently withdrawn.
Our client is not “doing his best to cause difficulty for your client”, however, as previously submitted our client is only required to provide consent to reasonable building works and not substantial demolition works likely to affect the value of the property. Having said the above, it would appear that there has been a certain amount of cross purposes.
Both our client and the Bank have agreed to your client carrying out the works which were approved in 2021 by the Council which includes extension of the kitchen/veranda. If this is still what your client is seeking the vendor’s consent, then there is no issue in the vendor signing the consent forms. However, if your client’s request is for a major restructure of the kitchen, which may include potential structural issues, then the vendor and the Banks so far as the vendor is aware, will not agree. The current consent form as submitted by you, would appear to cover both the kitchen and the upstairs work which is not acceptable.
On the issue of your client communicating directly with our client’s Bank we respectfully submit that there are reasons why he should not do so, particularly as it may jeopardise our clients ongoing relationship with the Bank, particularly if misleading information is provided to the Bank.
We trust that your client shall refrain from doing so without our client’s consent.
On 7 March 2024, Mr Rothner’s solicitor responded to the effect that the nominated certifier was unable to carry out the work, and a new certifier had been appointed. New forms were attached for Mr Waterhouse to sign – for the garage works and kitchen and additions to the balcony.
On 8 March 2024, Mr Waterhouse’s solicitors responded to Mr Rothner’s solicitors:
With reference to your email yesterday when you provided the new Application forms requesting our client’s consent:
- The first form specifically states that it is for “Alterations and addition to existing garage”. Mr Waterhouse has no issue with that form as the works are DA approved and, so far as our client is aware, are approved by his Bank.
- The second form states in general terms “Alteration and addition to existing dwelling house” and is not specific to the enclosure of the Balcony, which Mr Waterhouse understood was being requested. Again, so far as our client is aware, the Bank has approved the enclosure of the Balcony (off the kitchen) and not the construction of additional Balconies or other work under DA 518/2021/1 the subject of the form. The form should be limited to the enclosure of the Balcony only.
- The carrying out of work on the property was always subject to the consent of the Bank, as otherwise Mr Waterhouse would be in default under his Mortgage entitling the Bank to foreclose. Mr Rothner was aware of the Mortgage to the Bank prior to entering the Contract.
- We are instructed that the Bank, because they feel that they may have been misled into previously granting approval (which was subsequently withdrawn) are now saying that they need to see builder’s quotations and may need funds held in an escrow account before granting approval.
- Mr Waterhouse’s relationship with the Westpac Bank is becoming strained due to Mr Rothner’s direct communications (without Mr Waterhouse’ consent) and this is one of the reasons that he is actively seeking to refinance with the Bank of Singapore. We are instructed that the Bank of Singapore have given verbal approval and a formal approval is likely shortly.
- Mr Waterhouse believes that the Bank of Singapore shall be far less stringent on giving ongoing approvals for the proposed building work. Accordingly, without admitting that it is required, Mr Rothner’s approval to refinance is requested. The Bank of Singapore have been advised of the sale Contract and Mr Rothner will still be entitled to a second Mortgage.
Please obtain your client’s instructions and reply.
- The consent by the owner is only for the carrying out of work to the garage and the creation of living areas below the garage.
- No work whatsoever is to be caried out on the actual house including there is to be no opening of the wall between the house and the garage.
- In accordance with the requirement advised to our client by Westpac Bank, no work is to commence until a quotation for the building works has been accepted by the Bank and payment for the works are to be held in an escrow bank account (this may be your Trust Account).
- Evidence of the builder’s insurance to be provided prior to any work commencing.
- That a Bank representative and David Waterhouse be entitled to inspect the works fortnightly if requested.
Mr Rothner did not accept conditions 2, 3 and 5 and contended, by letter dated 5 April 2024, that Mr Waterhouse was in breach of cl 50.1 of the Contract and asked Mr Waterhouse’s solicitor whether they had instructions to accept service.
Mr Rothner’s proposed garage renovation plans took a twist in late March 2024. On 25 March 2024, solicitors for the Huangs wrote to Mr Waterhouse contending that the original consent for the garage works granted by Council on 26 June 2007, had lapsed because there had been no commencement of works prior to the lapsing date of 26 June 2012.
Proceedings were subsequently commenced by the Huangs in the Land and Environment Court (on 10 April 2024). The proceedings were defended by Mr Waterhouse. The Huangs ultimately prevailed with the Court determining on 4 July 2025 that the consent had lapsed: see Huang v Waterhouse [2025] NSWLEC 71.
Mr Rothner obviously did not immediately become aware of the Huang’s position because on 5 April 2024 his solicitor wrote to the Westpac seeking confirmation that, subject to the provision of evidence of the builder’s insurance, Westpac consents to the carrying out of the works to the garage without the imposition of further conditions.
Mr Drake forwarded the letter to Mr Waterhouse’s solicitor and Mr Waterhouse. Westpac told Mr Rothner’s solicitor that their letter had been forwarded to Mr Waterhouse’s lawyer.
At the conclusion of evidence of day 5 of the hearing, Mr Rothner, through his senior counsel, conceded that Mrs Rothner asked Mr Shahwan and Mr Gibbons to cut down the trees on No 8, that were cut down on 2 April 2024, and that she asked them to do that knowing that the owners of No 8 had not consented to the cutting, and that she did it with the intention of improving the views from the Property.
That concession obviously only relates to Mr Rothner and not Mrs Rothner or Mr Shahwan – the remaining parties. As regards the cutting, no one seriously challenged Mr Gibbons on his evidence. It may relevantly be summarised as follows:
(a) he was asked by Mr Shahwan to meet him at the Property on 29 March 2024 for the purposes of cutting down trees; (b) when he arrived at the Property on 29 March 2024, Mr Shahwan had already put a ladder down into No 8. He also had a chainsaw; (c) Mrs Rothner said to them both – “I want the trees removed for a better view of the harbour.” Mr Gibbons said to Mr Shahwan he would need a bigger chainsaw. Mr Gibbons asked Mrs Rothner whether she had permission to cut the trees down to which Mrs Rothner responded that they would blame it on Mr Waterhouse; (d) Mrs Rothner gave Mr Gibbons $300 which he apparently lost and she gave him another $300. Mr Gibbons said he had second thoughts about being involved but was pressured to return by Mr Shahwan; and (e) in his affidavit made in December 2024, Mr Gibbons said that it was on 3 April 2024 that Mr Shahwan and he entered No 8 from the Property and “cut down roughly four to six palms including the largest”. The 3 April 2024 date was also included in his Second Statement. The same mistake was made by Mr Waterhouse. This date of 3 April 2024 was no doubt based on a document which Mr Waterhouse obtained from Kennards Hire Waverley (Kennards) in May 2024. There was ultimately no dispute that the trees were cut down on 2 April 2024. I address below the significance of Mr Gibbons and Mr Waterhouse making the same mistake of 3 April 2024.
There was also evidence that Mrs Rothner hired a chainsaw from Kennards on 2 April 2024 and returned it on 3 April 2024. Mr Waterhouse ascertained this when he went to Kennards on 20 May 2024.
The experts retained by the parties reached agreement in relation to the trees removed from No 8. They agreed that there were three relevant periods:
3 October to 7 December 2023:
1 x Native daphne 5m high.
3 April 2024 (though the evidence reveals it was 2 April):
1 x Mexican fan palm of 8m high;
11 x Scaly tree-ferns of 4 – 6m high (including a triple-stemmed specimen); and
15 x Giant white bird of paradise stems to 4-6m high.
7 April to 10 June 2024:
1 x Kentia palm to 4 - 5m trunk (6 - 7m high with fronds);
1 x Illawarra flame tree 7m high; and
1 x Blueberry ash 5m high.
The last date referred to above – 10 June 2024 – is taken from aerial photography. Aerial photographs were not available for each day, but rather selectively. Other evidence suggests that the last trees were cut on 14 April 2024. On that day Mrs Rothner sent a WhatsApp message to Mr Rothner stating, “Another 3 🌴 fown, *down”. This must be a reference to trees on No 8 as there was no suggestion in the evidence that three palm trees were removed from the Property at or about this time.
The joint report of the experts also stated:
The experts agree the cutting down of trees on the Site was a very selective process and confined only to those trees between heights of approximately 4-8 metres in the Site. This tree cutting opened a relatively unobstructed west/southwest, oblique view corridor from No 8, across the rear of the Site, to the Sydney Harbour Bridge and city skyline. Taller trees, notably a tall Mexican fan palm and four Bungalow palms, and shorter Scaly tree ferns, were left untouched.
It appears that in or about early May 2024, Mr Gibbons told Mr Waterhouse about the trees removed from No 8. Mr Waterhouse said this was of great concern to him and he asked Mr Gibbons to prepare a statement setting out what occurred. Mr Gibbons agreed.
On 10 May 2024, Mr Waterhouse told the barrister retained by the Huang’s in the Land and Environment Court proceedings, about the removal of the trees from No 8.
Mr Gibbons made a statutory declaration on 10 May 2024 before Gary Kosmin (Mr Waterhouse’s solicitor) (Mr Kosmin) attesting to the truth of a statement he had signed the same day in the following terms:
I, Gary John Gibbons of sound mind live at unit X, X street Five Dock NSW 2046 and my mobile number is X. I do casual ground and gardening work for David and Janette Waterhouse, they also have another bloke that works for them whose name is Al Shahwan. On the 28/3/2024 Al called me up and asked me if I had cut trees down before. I said yes and he told me to meet him at 6A Tivoli Avenue Rose Bay on the 29/3/2024 8:30am as we will be doing some work for Lisa Rothner of the above address. I arrive at 6A Tivoli Avenue and went down the front, where Al had put a ladder into the next door’s property (8 Tivoli Avenue) which is on the right-hand side of Lisa’s place. Al and I both climb over the wall to take a look at the Palms that Lisa wanted removed for a better view of the harbour. At this time, I thought she had permission to do this and to be on the property. Because of this, Al and I were going to cut down the palms (one of which was well over 30 feet tall) but were not able to because the chainsaw was not good enough. So, I said to Al ‘you’re going to have to get a better chainsaw’ to which they went and hired one. This took place on the 29/3/2024. We then had a group conversation about what was the best way to remove the palms from the property next door. I asked Lisa and Al if they had gotten permission to remove these palms to which she responded that they would blame it on David Waterhouse. Al interjected by saying not to worry we will make a ‘bodgy’ company and this company can be said to be doing the work on behalf of David Waterhouse. I was in shock in what they said, I told them both that ‘I couldn’t do that, I don’t want to be involved and it is not right.’ They both said I would be fine, but I was worried about this so Al said he would see me on the 30/3/2024 which I never turned up. I didn’t want to go back but I had to as Lisa paid me $300 cash on 29/3/2024 and dropped me at Edgecliff station where I somehow had misplaced that money. I believe I had dropped it in her car as that was the only place I had been between receiving it and realising it was lost although she stated I did not. She then gave me another $300 so I was then obligated to come back and do that work which was supposed to be on 30/3/2024 but as previously stated I never turned up. Al rang me up on the 31/3/2024 stating that I was obligated to do this work for Lisa as ‘she has paid you’ and has ‘been very good to you’. I stated to Al that “I don’t want to do this, I can give her the $300 back as what she is asking of me is illegal.” I did decide after this conversation to go back to the Tivoli Address on 1/4/2024 but I still protested on doing the work knowing that it was wrong although I was the one that was left to cut down the palms. After cutting down several palms (roughly four) we moved all the rubbish down to the Lefthand side, bottom of the property and jumped back over the fence onto Lisa’s property. I then finished up a bit more work for Lisa on XX Tivoli Avenue. Nothing else was said until Al called me to help at XX Elizabeth Bay Road (Mr Waterhouse’s’ address) on 6/5/2024 which I turned up to. Al stated that he had more work for me, and I asked what it was. He stated that we were to do a break and enter at the property to the right of XX Tivoli Avenue being number 8 (same place as previous stated, where we had cut down the palms) because Lisa and Al believed there was money in the place, and it would be shared 3 ways. I was shocked and told Al via text that I don’t want to be involved with anything illegal and I found it already bad enough he had gotten me to cut down the Palms. I then got in contact with David and Janette via text and asked to have a sit-down meeting with them. I spoke with Janette Mr Waterhouse for three hours about the situation and was willing to come in to make a full statement on what had been said and done against the Waterhouse’s by Al Shahwan and Lisa Rothner.
There was cross-examination of both Mr Gibbons and Mr Waterhouse as to the circumstances in which the statement and statutory declaration were prepared.
Mr Gibbons prepared a handwritten statement that was then typed up by Olivia. Mr Waterhouse then took Mr Gibbons to Mr Kosmin and he made the statutory declaration on 10 May 2024.
Mr Gibbons sent Mr Waterhouse a text message at 6.17pm on 9 May 2024 asking Mr Waterhouse the address of the Property for inclusion in his statement.
Mr Waterhouse sent a message to Francis Douglas KC on 10 May 2024 which stated the “gardener [Mr Gibbons] has written a four page statement, which Gary Kosmin will put in a statement”.
Mr Waterhouse was not sure whether he ever saw the handwritten statement.
It was not in dispute that Olivia typed up the handwritten statement and emailed it to Mr Kosmin. Mr Gibbons then attended on Mr Kosmin and made the statutory declaration. There was some suggestion that Mr Waterhouse provided the handwritten statement to Olivia before Mr Gibbons arrived at Mr Waterhouse’s property on 10 May 2024. This suggestion was based on the time the file was created by Olivia and a later exchange of messages between Mr Waterhouse and his ex-wife to the effect that Mr Gibbons was waiting outside the property. Both Mr Waterhouse and Mr Gibbons did not agree with this contention. I am satisfied that Mr Gibbons arrived at the Elizabeth Bay property and gave the handwritten statement to Olivia for typing. The contention advanced by Mr Rothner is speculation.
At 2.18pm on 10 May 2024, Olivia sent an email to Mr Kosmin, copied to Mr Gibbons and Mr Waterhouse stating:
Please find attached Gary Gibbons statement which was dictated to me. Mr Gibbons is coming down to our address to sign it now.
1 We refer to the above proceedings.
2 We are instructed that at approximately 3:00pm on 9 May 2024 a commercial skip bin was delivered to No. 6 Tivoli Avenue (No. 6).
3 We are also instructed that on the afternoon of 10 May 2024 demolition works appear to have commenced on the Property. Provided at Annexure A are photographs of the activities observed which appear to include the removal of a tree on No. 6 and demolition of elements of the building.
4 The skip bin has now been filled with vegetation and other materials as shown in the photograph at Annexure B.
5 The presence of the skip bin and the materials placed in it, raises significant concerns as it indicates that your client may be progressing works on No. 6 notwithstanding:
(a) the nature of the orders sought by our client in the proceedings; and
(b) that your client has been aware of these proceedings and the orders sought since 17 April 2024, being the date on which the First Respondent’s solicitors sent Landerer & Company Solicitors (your client’s previous solicitor) a letter enclosing a copy of the Summons.
6 Orders 2 and 3(b) of the Summons specifically seek to restrain the carrying out of any development on No. 6 in purported reliance on development consent 795/2006/1 (Consent).
7 Secondly, we have received evidence in the form of a statutory declaration declaring that employees and/or contractors of Mr Rothner have trespassed onto no. 8 Tivoli Avenue, Rose Bay **(**No.8) and removed at least four large trees on No .8 without Mr Huang’s consent, apparently to improve the views of the harbour enjoyed by No. 6. As far as Mr Huang is aware, no approvals have been granted by Woollahra Municipal Council **(**Council) or any other authority for any tree removal on No.8.
8 The photos at Annexure C show the trees that have been cut down and discarded on No. 6. The photos at Annexure D show the stumps of the trees on No. 8.
9 The issues raised in this letter are concerning given the proceedings that are on foot and the serious implications of unauthorised tree removal.
10 In the circumstances, our client requests a written undertaking from your client that he will not (by his servants, agents, contractors or subcontractors or otherwise) carry out any works pursuant to the Consent until the proceedings have been determined or otherwise resolved. We request that this undertaking is provided no later than 5pm on Wednesday, 15 May 2024.
11 Shound [sic] your client (by its servants, agents, contractors or subcontractors) refuse or fail to provide the undertaking, we are instructed to file a notice of motion seeking:
(a) an urgent injunction to restrain your client from carrying out any works on No. 6 in reliance of the Consent; and
(b) that the hearing of the proceedings be expedited.
12 We are instructed to seek costs against your client in relation to any such application(s) required.
13 Our client reserves all his rights in relation to the unauthorised tree removal including but not limited to amendment to the Summons to address the serious breach of the Environmental Planning and Assessment Act 1979 and separate civil proceedings to address the trespass. Our client also intends to notify the police and the Council about this matter.
(Underlined added.)
To whom it may concern,
I, Gary John Gibbons of sound mind live at unit X, X Street Five Dock NSW 2046 and my mobile number is X. I refer to my previous statue [sic] of declaration dated 10th May 2024. I first met Michael Rothner on the South Coast at their beach house in Bundeena on the 3rd of February. This was because I was requested by Al Shahwan to come to their property to do some gardening work. I previously stated in my statement that the date of the actual removal of the 4 or 5 large palm trees (8 Tivoli Avenue) was the 29th of March. Upon checking my phone records and other independent information this is not correct. Easter weekend finished on Monday 1st of April. The actual date I attended was Wednesday 3rd April. On that day Mrs Rothner hired an 18-inch chainsaw which she hired herself from Kennards. I note, I had tended the property previous to this, where I was instructed to use a smaller chainsaw which was too small to cut down these large palm trees. This is how the confusion happened over the actual exact date of removal.
I have been told by David Waterhouse that Michael Rothner denies any knowledge of the trees being cut next door- this is false. After cutting the 4 or 5 large palm trees down, Al helped me move all the dead wood to the bottom left-hand side of the property, at which point Al and I climbed back into number 6 Tivoli Avenue via a portable ladder we brought over from 6 Tivoli Avenue. I believe on the same afternoon, Mrs Rothner brought her husband Michael Rothner out of the house and showed him the results of the work Al and I had done on the neighbouring property (being 8 Tivoli Avenue) and said, “Look at what we have done, we have cleared the view”. At this point, Michael said to me “Hello Gary, how are you?”. He was friendly but non-committal on commenting on the drastic change to the view line of the neighbouring property. This is the last time I believed I visited the property.
After this Lisa Rothner asked me if I knew anyone tree loppers for a very tall tree in front of her property which is on waterworks land. She mentioned she wanted the canopy chopped off this tree (the tree being 40 or 50 feet tall). I suggested an old employer who had employed me in the past and his name is Hank and works at Sydney Arbor works. I gave her the contact details for him (his number is X). A couple of weeks later I had a conversation with Hank in which he told me that Mrs Rothner had asked him to cut a tree which is on waterworks land which he refused to do without permission from the council.
Lastly, Al Shahwan told me that he was living in the pool cabana at 6 Tivoli Avenue, rent free as he was doing work since mid-February. After the statement was given to David Waterhouse, I have received numerous threatening text messages which caused me to block his number. Last Sunday, 19th May at 1:02pm I received an email from Mr Shahwan. Attached to this statement are copies of his previous texts and emails.
The genesis for this Second Statement appears to be what occurred at the meeting between Mr Waterhouse and Mr Rothner and their respective solicitors on 17 May 2024 at which point Mr Rothner denied any knowledge of the trees being cut down, or having ever met Mr Gibbons. Mr Waterhouse asked Mr Gibbons whether this was correct. He was told it was not.
Mr Waterhouse then asked Mr Gibbons to provide the Second Statement detailing Mr Rothner’s involvement. Mr Waterhouse agreed that he wanted a statement from Mr Gibbons that implicated Mr Rothner in the cutting down of the trees on No 8. He also agreed that this was the main change to Mr Gibbons’ evidence introduced by the Second Statement.
Consistent with the content of both of his statements, Mr Gibbons also made an affidavit in the proceedings, dated 4 December 2024 in which he relevantly deposed:
7 The next day, 29 March 2024, I arrived at No 6 and went to where Al had put a ladder down into the next door property (8 Tivoli Avenue) which is on the right-hand side of No 6 as you look from the street towards the harbour and the city. Al had a chainsaw.
8 Al and I both climbed down and took a look at some Palms growing on No 8, one of which was well over 30 feet tall.
9 Lisa Rothner was on No 6 at the time looking down into No 8. She said,
“I want the trees removed for a better view of the harbour.”
10 I looked at the chainsaw Al had given me and said,
“Al you’re going to have to get a better chainsaw.”
11 I asked Lisa and Al,
“have you permission to remove these palms?”
12 Lisa said.
“We will blame it on David Waterhouse.”
Al said:
“don’t worry we will make a bodgy company and this company can be said to be doing the work on behalf of David Waterhouse.”
I said ,
“I don’t want to be involved.”
Both Lisa and Al said,
“it was fine to cut the palms down.”
We all said that we would see each other on 30 March to cut down the palms.
Lisa then gave $300 in cash and drove me to Edgecliff station. When we arrived I could not find the $300. Lisa gave me another $300.
13 On 30 March 2024 I did not turn up at No 6 to cut down palms.
14 On 31 March 2024, Al telephoned me and said,
“You are obliged to do the work Lisa has paid you to do, she has been very good to you.”
I said, “I don’t want to do it, I can give her the $300 back.”
15 I agreed to go back after a lot of pressure from Al.
Al said “I you gave your word and took Lisa Money, you must go back and finish the Job”.
I was scared of Al, he told he was once in the police force and still had his police badge, but what was more scary was his brother was a high-ranking member a bikies gang.
16 On 3 April 2024, Al and I entered No 8 from No 6 and I cut down roughly four to six palms including the largest. I have been shown page 10 of the report of the arborist tree ferns circled in yellow and the Mexican Fan Palm circled in orange as what I cut down on 8 Tivoli Avenue Rose Bay.
17 We then moved all the rubbish down to the lefthand side, bottom of the property and jumped back over the fence onto Lisa’s property. I then finished up a bit more work for Lisa on No 6.
18 While I was working on No 6, Lisa brought her husband Michael Rothner out of the house and showed him the results of palms being cut down and said,
“Look at what the boys have done.” Referring to where the trees had been removed and pointing towards the direction of the Harbour Bridge.
Michael said to me
“Hello Gary, how are you?’’
Michael did not say anything else to me.
In his affidavit made 27 November 2024, Mr Rothner denied the matters set out in the second paragraph of the Second Statement.
Mr Rothner gave the following evidence in cross-examination in response to what Mr Gibbons contended in his Second Statement occurred involving Mr Rothner:
Both Mr Gibbons and Mr Waterhouse were cross-examined as to the circumstances in which the Second Statement was prepared and in particular what involvement Mr Waterhouse had in the preparation of the statement.
Having attended Kennards and obtained evidence that Mrs Rothner had hired a chainsaw from Kennards, Mr Waterhouse emailed Mr Gibbons on 22 May 2024 stating: “Also I have something totally independent which supports you 100% – I will tell you tomorrow.”
Mr Waterhouse met Mr Gibbons at Mr Waterhouse’s Elizabeth Bay property on 23 May 2024.
I am satisfied that Mr Gibbons arrived before 1pm. He was likely given, by Mr Waterhouse, the photo of the chainsaw and the Kennards screenshot that Mr Waterhouse obtained from Kennards.
I am also satisfied that Mr Waterhouse likely told Mr Gibbons that Mrs Rothner had hired the chainsaw on 3 April 2024.
At 12.58pm on 23 May 2024, Mr Gibbons and Mr Waterhouse exchanged the following text messages:
Mr Gibbons said that he was concerned that Mr Rothner may sue him and that he wanted an indemnity from Mr Waterhouse.
At 1.08pm on 23 May 2024, Olivia emailed Mr Kosmin, copied to Mr Waterhouse:
Gary Gibbons just dictated this statement to me. He will be attending at your office to sign it. He is bringing the annexures of Al Shahwan threatening texts and email which he would like to be attached to his statement.
The first statement states:
- Al called him up on 28/3.
- He arrived at Tivoli on 29/03 and chain saw not big enough – paid $300 in advance and lost it.
- Lisa gave him another $300 same day.
- 31/03 Al called and said he was obligated to come back.
- 01/04 came back and did work.
There is only one mistake it was the 3rd not 1st of April.
Mr Waterhouse said he was sending this text complimenting Mr Gibbons on his memory.
At 1.50pm Olivia sent a further email to Mr Kosmin, copied to Mr Waterhouse:
Gary Gibbons has amended one small typo to his statement. Please see the most updated version attached to this email.
I previously stated in my statement that the date of the actual removal… was the 30th of March.
The 1.50pm draft changed the 30 March date to 1 April. Mr Gibbons agreed in cross-examination that he did not suggest this change to be made.
The statement ultimately signed by Mr Gibbons changed this date by hand to 29 March.
Mr Waterhouse denied that he had any input whatsoever into the Second Statement apart from giving Mr Gibbons the Kennards documents. I do not accept this evidence. Mr Waterhouse was involved at least to the extent of telling Mr Gibbons that the date on which the chainsaw was hired, and thus was used to remove the trees on No 8, was 3 April 2024 and that he (Mr Gibbons) should correct this in his Second Statement.
In his affidavit made on 16 December 2024, Mr Waterhouse deposed “this was hire [sic] on the 3rd of April 2024 the day after Easter Monday for 1 day hire and returned the following day.”
Both Mr Waterhouse and Mr Gibbons made the same mistake as to the date of hire. This is unlikely to have been a coincidence. Whilst it may have been the product of each independently reading the Kennards screenshot obtained by Mr Waterhouse, I think this is unlikely.
Mr Waterhouse was also likely the source of the change that was emailed through by Olivia to Mr Kosmin at 1.50pm on 23 May 2024. That change was not accepted, however, in the version of the statement signed by Mr Gibbons on 23 May 2024. This suggests the issue was discussed between Mr Kosmin and Mr Gibbons before signing and the date of 29 March included.
Whilst perhaps telling against Mr Waterhouse’s credit, I do not regard these matters as leading to the conclusion that Mr Waterhouse told Mr Gibbons what to include in his Second Statement about Mr Rothner and that Mr Gibbons agreed to include this false material.
The 3 April date is understandable from the Kennards screenshot obtained by Mr Waterhouse.
An important issue in the proceedings is whether, as Mr Gibbons contends, Mrs Rothner bought Mr Rothner out on 2 April 2024 to show him the clearing of trees on No 8 and the impact on the view from the Property.
I accept Mr Gibbons’ evidence as to his interaction with Mr Rothner on 2 April 2024. I reject Mr Rothner’s denial.
The fact that Mr Gibbons admitted that he was grateful to both Mr Waterhouse and his ex-wife and wanted to assist Mr Waterhouse in these proceedings, does not, in and of itself, cause me to doubt what Mr Gibbons said in relation to Mr Rothner in his Second Statement and affidavit in these proceedings.
Mr Gibbons was unshaken in cross-examination about what occurred on the day in early April 2024 when the trees were cut down on No 8, including Mrs Rothner bringing Mr Rothner out to show him what had been done.
It is inherently likely, in my view, that Mrs Rothner would have done this.
The objective material, principally the text messages between Mr and Mrs Rothner, paints a strong picture of Mr Rothner taking a keen interest in what Mrs Rothner was doing at the Property, particularly in relation to improving the view from the Property and Mrs Rothner keeping him up to date as to what she was doing. Mr Rothner was sent a number of videos and pictures by Mrs Rothner and was often the person requesting that pictures be sent to him. One can well understand Mr Rothner’s keen interest in this subject given the location of the Property. The 12 January 2024 and 14 April 2024 exchanges were both in the context of the tree removal from No 8, directly implicating Mr Rothner in this work being carried out. As I have set out later in these reasons, there was no need for a message between Mr and Mrs Rothner on 2 April 2024 as they were both at the Property.
I am conscious that some aspects of Mr Gibbons’ evidence were unsatisfactory and unreliable in several respects. I have referred to several of these earlier in these reasons. There is also the fact that I am satisfied that Mr Waterhouse likely had a hand in some aspects of the Second Statement by providing the material he had obtained from Kennards to Mr Gibbons, and by sending an email to Mr Kosmin suggesting a change in the date.
Nonetheless, these matters do not cause me to reject Mr Gibbons’ evidence on this key point in circumstances where it is inherently likely to have occurred.
Opening up the view was an important matter to both Mr and Mrs Rothner. In circumstances where Mr Rothner was at the Property after the tree removal was completed, it makes sense that Mrs Rothner would have shown him the results. There was no need for the usual exchange of texts between the two.
I am also not satisfied that Mr Gibbons simply included the material in his Second Statement to implicate Mr Rothner at the request of Mr Waterhouse, both knowing it was not true.
I reject Mr Rothner’s denial of the account given by Mr Gibbons. In a number of respects his evidence was unsatisfactory.
Mr Rothner admitted that he had returned to Australia on 2 April 2024 and was at the Property on that day.
In my view he sought to deliberately downplay the importance of improving the view from the Property because he knew that any such improvement would be short-lived because of the impending development of the nearby 10a.
Whilst it is clear that Mr Rothner was aware at the time of purchasing the Property of the development application that had been submitted in respect of 10a, and had received advice from Mr Suttie as to the likely impact of this proposed development on the views from the Property, Mrs Rothner was also aware of these matters. Notwithstanding this knowledge, the objective material shows that considerable work was done in improving the view from the Property towards the Harbour Bridge in the area where the residence on 10a was to be constructed. Mr Rothner was being constantly updated by Mrs Rothner as to this work, including through the video in early January 2024 referred to above. There were at least three separate cutting events.
Mrs Rothner was not simply on a frolic of her own.
The text exchanges between Mr and Mrs Rothner on about 13 January 2024 also suggest that work was being done whilst no one else was around and with a consciousness that no evidence should be left behind to suggest that any clearing work had been carried out.
The WhatsApp message on 14 April 2024 from Mrs Rothner to Mr Rothner – “Another 3 🌴fown, *down” is a reference to trees being cut on No 8. Mr Rothner was being told this, yet he repeatedly denied being aware of any trees being removed from No 8 until he received a letter on 13 May 2024. Mr Rothner’s response which stated “we need to do the house – forget the F greenery!”, could only be interpreted as Mr Rothner suggesting that Mrs Rothner prioritise work on the house, and not as Mr Rothner being concerned that Mrs Rothner was causing trees to be removed from the neighbouring property.
On 31 May 2024, Mr Rothner executed a Deed Poll in favour of Mr Waterhouse. I extract the relevant terms later in these reasons. In the Deed Poll, Mr Rothner denied that he caused the removal of the trees from No 8, but nevertheless undertook to ensure that Mr Waterhouse was no worse off as a result of the removal of the trees. Mr Rothner relevantly indemnified Mr Waterhouse against any claims etc as a result of the removal of the trees, undertook not to invite Mr Gibbons onto the Property and instructed those working at the Property not to enter No 8.
On the same day, Mr Rothner executed another Deed Poll, this time in favour of Mr Huang. I set out the relevant terms later in these reasons. Mr Rothner relevantly promised to replant trees on No 8 that as closely as possible replicate the trees removed or, at Mr Huang’s election, compensate him for the removal of the trees (or both to the extent that Mr Huang remained worse off after the replacement of the trees).
Mr Rothner’s solicitors responded to the Notice of Default by email dated 31 May 2024, denying any breach of Special Condition 49.1. The email also contended that Mr Rothner had rectified any non-compliance with Special Condition 49 by executing and delivering the two Deed Polls.
On 5 June 2024, Mr Waterhouse purported to terminate Mr Rothner’s occupation rights under cl 49.2. He commenced these proceedings on the same day.
On 1 July 2024, Mr Rothner’s solicitors emailed to Mr Waterhouse’s solicitors, copies of DA drawings for the Wellness Centre together with Owners Consent and a CDC Application Form for Mr Waterhouse’s consent, execution and return, in accordance with his obligations under the contract for sale of land.
By separate email sent at or about the same time, Mr Rothner’s solicitors also emailed DA drawings for the main house (DA 518/2021/1) together with the Construction Certificate and a CDC Application Form for the interior works for Mr Waterhouse’s consent, execution and return in accordance with his obligations under the Contract.
By separate email sent at or about the same time, a third set of documents was sent for the Garage DA for Mr Waterhouse’s consent, execution and return, in accordance with his obligations under the Contract.
By email dated 16 September 2024, Mr Waterhouse’s solicitors responded to Mr Rothner’s solicitors to the effect that they were instructed Mr Waterhouse would consent to signing the Development Application for the Wellness Centre on certain conditions.
There was then a further email from Mr Rothner’s solicitors to Mr Waterhouse’s solicitors dated 27 September 2024, in relation to Mr Waterhouse’s consent to the various development applications. Mr Waterhouse was again asked to return the duly executed documents by Friday, 4 October 2024.
The correspondence on this topic continued with a letter from Mr Waterhouse’s solicitors to Mr Rothner’s solicitors dated 29 September 2024. The response stated:
I refer to your email of the 27 September 2024 and advise on instructions as follows:-
- The carrying out of work on the property was always subject to the consent of the Bank, (Westpac Credit department) as otherwise Mr Waterhouse would be in default under his Mortgage entitling the Bank to foreclose. Mr Rothner was aware of the Mortgage to the Bank prior to entering the Contract.
- Of the 6 documents attached the first form -CERTEX-specifically states that it is for “Alterations and addition to an existing garage”. Mr Waterhouse has no issue with signing that form as the works are DA approved and, so far as our client is aware, are approved by his Bank. However, Westpac has given their instruction as per Mr. Kosmin letter of 14/03/24. Please provide proof that the requested conditions as requested by Westpac have been undertaken by Mr. Rothner. Once received Mr Waterhouse will provide these documents to Westpac Credit and obtain their approved, which will allow him to sign this one document.
- The second form states in general terms “Alteration and addition to existing dwelling house”. Westpac credit has stated no work whatsoever is to be carried out on the actual house itself. The form cannot be signed as my client will be in default under his mortgagee.
- The third and sixth documents are copy of Plans-that do not need to be signed.
- The fourth document is an open “Owners Consent” with no reference to anything. Mr Waterhouse will not sign a blank consent unless he is advised what this is for.
- The fifth is for a new PCA-this is not necessary -as Westpac will not allow any work to be carried out to the main house.
Mr Waterhouse is contractually liable to sign any documents relating to amending an existing DA but not Certex/ Construction certificates that appear partly to be works carried on the interior of the house.
(Bold in original).
On 1 October 2024, Ms Ongaro sent an email to consultants working on the Wellness Centre asking for all works on the Wellness Centre to be paused until further notice.
The solicitor correspondence in relation to Mr Waterhouse consenting to the relevant development applications continued through November and into December 2024.
On 16 December 2024, Mr Waterhouse, through his solicitor, sent to Mr Rothner’s solicitors a signed owners consent. It appears that the consent related to the proposed pool and Wellness Centre.
On 28 April 2025, Mr Rothner gave notice, under cl 47 of the Contract, extending the date for completion of the Contract to 21 December 2025. Mr Rothner had transferred the required $208,333.34 into Mr Waterhouse’s bank account for this purpose.
Shortly thereafter, on 14 May 2025, Mr Rothner forwarded, by his solicitors, his renewed insurance policy noting the interests of both Mr Waterhouse and Westpac. Thereafter there ensued correspondence in relation to the acceptability of this insurance policy. An updated insurance policy was provided on 17 May 2025.
On 29 July 2025, Mr Waterhouse’s solicitors wrote to Mr Rothner’s solicitors referring to the recent decision of the Land and Environment Court in relation to the validity of the 2004 development consent to the existing garage/studio, in which the Court held that the development application lapsed on 26 June 2012. The letter stated that should Mr Rothner wish to proceed with the lodgement of a new development application with new plans, as submitted to Mr Waterhouse for consent on 1 July 2024, the signed owners consent with a copy of the relevant plans was attached to the letter. The letter stated that the owner’s consent was not previously provided as, on counsel’s advice it was not appropriate whilst the Court proceedings were on foot.
On 2 October 2025, the Council approved the development application in relation to the demolition of the existing cabana and swimming pool and the construction of a new wellness pavilion, swimming pool and associated landscaping.
On 29 October 2025, Mr Rothner executed two further Deed Polls, one in favour of Mr Waterhouse and the other in favour of Mr and Mrs Huang. These two new Deed Polls concerned additional plants that had been identified as having been cut down on No 8 between the period 3 October 2023 and 10 June 2024. Again, the Deed Poll in favour of Mr Waterhouse purported to indemnify him against any claims, loss or expenses incurred by him as a result of the removal of the additional plants. The Deed Poll in favour of Mr Huang was also in favour of his wife, and similarly promised to either plant replacement trees on No 8 that as closely as possible replicated the additional plants, or compensate the Huangs for the removal of the additional plants, at their election.
Completion of the sale of the Property occurred on 17 December 2025. The PEXA Settlement Completion Record was admitted into evidence as a consequence of the application to reopen.
The source of funds provided on completion by Mr Rothner of $20,635,689.49 came from the NAB. Of the sale proceeds, Mr Waterhouse appears to have received $9,777,350.11. Westpac’s loan payout was $10,817,859.07.
Also tendered in evidence were the following documents:
(a) a letter of offer from the NAB to Mr Rothner dated 27 October 2025 (NAB offer letter). The amount of credit offered is $21,450,000 on a loan term of 30 years, with an interest only period of two years; (b) article titled “Change to NAB home loan rate” dated 3 February 2026 advising that NAB’s standard variable home loan interest rate will rise by 0.25% per annum from 13 February 2026; (c) article titled “NAB announce change to home loan interest rates” dated 17 March 2026 advising that NAB will increase its home loan variable interest rates by 0.25% per annum, with the changes to come into effect on 27 March 2016; (d) document titled “INDICATOR RATES FOR NAB HOME LENDING” dated 27 April 2026; and (e) transaction statement in respect of NAB Home Loan Account number XXXXXXXXX for the period 17 December 2025 to 18 December 2025 (NAB Transaction Statement), showing a loan drawdown of $21,449,472.90 on 17 December 2025, the date of completion.
In his closing written submissions dated 18 November 2025, Mr Rothner identified the following issues of substance that the Court is required to determine, as between Mr Waterhouse and Mr Rothner:
First, whether Mr Rothner is responsible for the removal of the trees on No 8?
Secondly, if so, whether Mr Rothner failed to comply with cl 49.1(c)(vii) of the Contract?
Thirdly, if so, whether Mr Rothner rectified that non-compliance?
Fourthly, if Mr Waterhouse is contractually entitled to terminate Mr Rothner’s right of occupancy, whether relief against forfeiture should be granted to prevent him from exercising that right?
Fifthly, and depending on the resolution of the previous issues, what (if any) compensation is Mr Waterhouse entitled to either as damages for breach of contract or as indemnity under the deed polls?
Sixthly, whether Mr Waterhouse breached the terms of the Contract by failing to sign the application for a construction certificate to carry out works on the Property?
Seventhly, if Mr Waterhouse breached the Contract by not signing those documents, the measure of Mr Rothner’s loss which was caused by that breach?
These issues provide a convenient structure to consider the claims as between Mr Waterhouse and Mr Rothner.
Some additional issues arise in relation to the other remaining defendants – Mrs Rothner and Mr Shahwan.
I deal first with the issues as between Mr Waterhouse and Mr Rothner and then deal with the issues concerning the other remaining defendants.
Mr Waterhouse contends that the removal of the trees was authorised by Mr Rothner. It is contended that he was in a joint venture with Mrs Rothner to develop the Property to their taste, including opening up the views of the harbour.
The factual finding Mr Waterhouse asks me to make is that Mr Rothner authorised Mrs Rothner to chop down trees on No 8. Alternatively, a finding that Mr Rothner knew that Mrs Rothner was going to chop down trees and acquiesced in her actions in cutting them down.
The case was also put on the basis that Mrs Rothner authorised the work within the scope of the authority given by Mr Rothner.
Mr Rothner does not dispute that he authorised Mrs Rothner to do work on the Property including the removal of trees on the Property. He denied that he authorised Mrs Rothner to remove trees on No 8. He concedes, however, that Mrs Rothner asked Mr Shahwan and Mr Gibbons to cut down the trees on No 8 that were cut down on 2 April 2024, and that she asked them to do that knowing that the owners of No 8 had not consented to the cutting, and that she did it with the intention of improving the views from the Property. He denied however, that Mrs Rothner was his agent such that he is liable for her authorisation of the cutting down of the trees.
Mr Rothner referred me to what the High Court said in Bird v DP (2024) 419 ALR 552; [2024] HCA 41, concerning when a person will be liable for the acts of another. Gageler CJ, Gordon, Edelman, Steward and Beech-Jones JJ stated (at [31]):
The first area of law where the expression “vicarious liability” has been used is where one person is, in a broad sense, an agent of another. It is a form of primary liability where the acts **of another person are attributed to the defendant on the basis that the acts were done for the defendant with the defendant’s express, implied or apparent authorisation of the acts, or ratification of the acts by the defendant. In other words, the acts were done with the defendant’**s “seal of … approval”****, amounting to an acceptance of the acts as the defendant’s own. For this form of liability, based on vicarious acts or vicarious conduct, the expression “vicarious liability” is inapposite. Thus, in contrast to true vicarious liability, it is not the liability, but the acts of the agent that are attributed to the principal.
(Emphasis added.)
At [32], the joint judgment also stated that the liability of A for the acts of B is not established, if B does no more than “represent” A (in the loose sense of merely acting for the benefit or advantage of A).
I am conscious that the allegation levelled by Mr Waterhouse against Mr Rothner in this regard is a serious one to which the well-known principles apply: s 140 of the Evidence Act 1995 (NSW); Briginshaw v Briginshaw (1938) 60 CLR 336; [1938] HCA 34 at 361-2 per Dixon J.
I am comfortably satisfied that Mr Rothner authorised Mrs Rothner to remove the trees in No 8. The two were part of a joint endeavour to develop the Property to their taste including by improving the view from the Property. An aspect of improving the view was removing the trees from No 8 which were obstructing such view.
It is not in dispute that Mr Rothner authorised Mrs Rothner to renovate the Property including by the removal of trees. The evidence – principally the text messages between Mr and Mrs Rothner – demonstrate that Mr Rothner was not content with taking a back seat as it were, and leaving it to Mrs Rothner to do what she wished, with no apparent interest in the outcome. To the contrary, he was intimately involved in what was being done and its impact on the view. He was actively seeking pictures and videos of the impact on the view, and was receiving regular updates. The messages include messages about what trees were being removed from No 8 (12 January 2024 and 14 April 2024).
The messages between the two also establish that aspects of the work were being carried out surreptitiously whilst people (including Mr Waterhouse and the Huangs) were away. Mr and Mrs Rothner were both concerned that no evidence was left behind.
The overwhelming conclusion is that Mr Rothner was taking a keen interest in what was being done. Mr Rothner’s case seems to be that this only extended to the work that Mrs Rothner was carrying out on the Property. The implicit contention, in light of the belated concession that Mrs Rothner authorised the tree cutting on 2 April 2024, must be that Mrs Rothner was on a frolic of her own. I do not accept this contention. The video sent by Mrs Rothner to Mr Rothner in January 2024 is quite contrary to Mrs Rothner going on a frolic. The messages suggesting a degree of secrecy in the work being carried out are also to the contrary.
The 14 April 2024 WhatsApp text “Another 3 🌴 fown, down” from Mrs Rothner to Mr Rothner is directly updating him on the removal of trees from No 8.
There were at least three separate cutting events, which were targeted. They occurred over several months. Mr Rothner was living at the Property for at least part of that time. The view was important to him. All of these matters further diminish the likelihood that Mrs Rothner was on a frolic of her own.
This material alone satisfies me that Mr Rothner authorised the works.
Added to this is Mr Gibbons’ evidence as to what occurred on 2 April 2024, which I accept and prefer over Mr Rothner’s evidence for the reasons given earlier in these reasons. That evidence of Mr Gibbons establishes Mr Rothner’s awareness of the tree removal on that day.
Added to this is the fact that I found Mr Rothner to be an unsatisfactory witness in several respects.
The overwhelming inference from the material that Mr Rothner authorised the carrying out of the works by Mrs Rothner can be more comfortably drawn in circumstances where Mrs Rothner was not called to give evidence.
The matters referred to by Mr Rothner to refute the suggestion that he authorised the tree removal, are not persuasive. Whether or not a new house was to be built at 10A obstructing part of the view is not overly relevant. The objective material shows how important improving the view was to both Mr and Mrs Rothner. It is not in dispute that the tree removal occurred at the direct request of Mrs Rothner. I do not accept that she was on a frolic of her own.
The fact that Mr Rothner issued the deed polls to both Mr Waterhouse and Mr Huang (denying any knowledge) is not inconsistent with Mr Rothner having authorised Mrs Rothner. Having been caught, it was his attempt to rectify the effects.
The parties were apart on the proper construction of cl 49.1(c)(vii). Mr Rothner contends that cl 49(c)(vii) is only breached if Mr Rothner has caused “damage nuisance or inconvenience” to an adjoining property by carrying out works on the Property. Put another way, Mr Rothner contends that cl 49.1(c)(vii) is not concerned with acts of vandalism to No 8 that are unconnected with the carrying out of works by Mr Rothner on the Property. Further, Mr Rothner contends that in order for cl 49.1(c)(vii) to be breached, there must be an act by him or authorised by him – it is not a form of strict liability.
Mr Waterhouse contended that the sub-clause was not limited to works carried out on the Property but rather should be construed as a comprehensive protection to Mr Waterhouse from any third party liability during the extended pre-completion occupation period. Reliance was placed on the fact that sub-clauses (i) through to (vi) all expressly reference “work” or “works”, whereas sub-clause (vii) makes no mention of “work” or “works”. The deliberate omission is said to evidence an intent to create a broader obligation. Reliance in this regard was placed on the principle of expressio unius est exclusion alterius (expression of one thing excludes another). It is also said that the commercial purpose of cl 49.1(c)(vii) was to comprehensively protect Mr Waterhouse from any third party liability arising during the extended pre-completion occupation period and that the narrow construction propounded by Mr Rothner would defeat this protective purpose entirely. The narrow reading of cl 49.1(c)(vii) propounded by Mr Rothner would render that sub-clause redundant or surplusage because sub-clause (iv) already provides for this.
The relevant principles were, understandably, not in question. I summarised the relevant principles in 1128CG Pty Ltd v MH Affordable Homes on Kelly Pty Ltd [2025] NSWSC 563 at [106]-[111]:
[106] Three core principles emerge from what French CJ, Hayne, Crennan and Kiefel JJ said in Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7 at [35]:
- The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean.
- That requires consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or objects to be secured by the contract. That, in turn, is facilitated by an understanding of the genesis of the transaction, the background, the context and the market in which the parties are operating.
- Unless a contrary intention is indicated, a court is entitled to approach the task of giving a commercial contract a businesslike interpretation on the assumption that the parties intended to produce a commercial result. The contract is to be construed so as to avoid it making commercial nonsense or working commercial inconvenience.
[107] Notwithstanding these three core principles, as French CJ, Nettle and Gordon JJ stated in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37 at [48], “[o]rdinarily this process of construction is possible by reference to the contract alone”.
[108] As Allsop P observed in Onesteel Manufacturing Pty Ltd v Bluescope Steel (AIS) Pty Ltd (2013) 85 NSWLR 1; [2013] NSWCA 27 at [61], the analysis is an objective one that can produce only one true meaning. The process of construction is not a process necessarily concluded by logical reason or a priori analysis. It involves the weighing of differing considerations partly logical and partly intuitive (though rational) leading to a choice. Analysis of competing arguments assists in that process, but the “correct” answer is not arrived at merely by seeing which side has the greater number of “good” points.
[109] As Leeming JA observed in Zhang v ROC Services (NSW) Pty Ltd (2016) 93 NSWLR 561; [2016] NSWCA 370 (Zhang v ROC) at [53], the starting point is to determine the literal or grammatical meaning or meanings of the clause. Second, one determines the legal meaning of the clause. Whereas here, there are several clauses of the agreement to be construed, it is clear that every provision must be read, together and construed with the others, so as to render, as far as possible, the provisions harmonious with each other: see Herzfeld and Prince, Interpretation (3rd ed, 2024, Thomson Reuters) at [22.30] and the cases cited therein. This is with a view to the legal meaning reflecting a measure of internal coherence: see HP Mercantile Pty Ltd v Hartnett [2016] NSWCA 342 (HP Mercantile) at [134] per Leeming JA.
[110] Where there is more than one available legal meaning, a court looks at the text, context and purpose with a view to determining which potential meaning best accords with those considerations. An iterative process is called for – checking each of the rival meanings against the other provisions of the document and investigating its commercial consequences.
[111] As Leeming JA further observed in HP Mercantile at [134]:
…The process of working through the consequences of the competing literal or grammatical meanings enables a court to assess whether either party’s preferred legal meaning gives rise to a result that is more or less internally consistent and avoids commercial absurdity.
In the context of the present submissions, I would add, as Bell CJ observed in The J&P Marlow *(*No 2) Pty Ltd v Hayes & McCabe (2023) 112 NSWLR 29; [2023] NSWCA 117 (J&P Marlow) at [76]-[80] that caution should be exercised by courts in attributing a particular commercial intent or understanding of commercial common sense to parties. Commercial purpose is to be determined objectively with the contract itself supplying the best source for the ascertainment of that objectively determined purpose: J&P Marlow at [75] per Bell CJ. It is not for a court to impute purposes to contractual parties where that purpose is not found in the text or context: J&P Marlow at [91] per Meagher and Kirk JJA.
Clause 49.1(c) provides:
…
(c) The purchaser shall be entitled to carry out any works, by way of alterations or additions to the property, as may be either approved by a Development consent or work not requiring Council approval, provided:-
(i) all work is carried out in a proper and workmanlike manner;
(ii) all work is carried out by properly qualified and licenced tradespersons holding adequate and appropriate-insurances the evidence of which shall be provided to the vendor;
(ii) the purchaser shall ensure, and provide evidence to the vendor, that the builder is properly licensed to carry out the required works and that appropriate insurance under the Home Building Act 1989 has been issued and maintained.
(iv) The purchaser indemnifies, and keeps indemnified, the vendor from any claim made against the vendor for damage to property or persons or whatsoever with regard to the works being carried out.
(v) The purchaser shall accept the property at completion subject to any work that has been carried out by or with the authority of the purchaser and shall make no claim on the vendor with respect to same.
(vi) All work on the property shall be carried out at the risk of the purchaser.
(vii) The purchaser shall cause no damage, nuisance or inconvenience to any adjoining property or occupier of an adjoining property.
In my view, cl 49.1(c)(vii), properly construed, only applies where the damage, nuisance or inconvenience is connected to the carrying out of the works on the Property. It is not a free standing obligation unconnected to the works. This emerges from the words used by the parties, construed in context.
First, the structure of cl 49.1 is important. It grants Mr Rothner a right of occupation from 5 January 2024 until completion “on the following terms and conditions”. One of the terms and conditions is contained in subclause (c), which permits Mr Rothner to carry out any works.
The relevant subclause – 49.1(c)(vii) – forms part, obviously enough, of cl 49.1(c). It is not expressed to be a free standing term and condition of the right of occupation – in which case it would be expressed as its own subparagraph of cl 49.1, and not as part of subclause 49.1(c). This would be the more natural grammatical expression of the clause on the construction propounded by Mr Waterhouse.
Turning now to the words of subclause 49.1(c) – it grants permission to Mr Rothner to carry out works “provided”, and then follows (i) to (vii). The natural reading of these words are that (i) to (vii) are directed at the terms on which Mr Rothner can carry out works to the Property. Subclause (vii) must be construed in this context. It is only enlivened if Mr Rothner causes “damage, nuisance or inconvenience” to an adjoining property by the carrying out of works on the Property.
Such a construction serves a sensible commercial purpose. By cl 49.1, Mr Waterhouse authorised or permitted Mr Rothner to carry out works on the Property. By giving that authority or permission it may be alleged that Mr Waterhouse is liable for the consequences of those works.
Conversely, the references by Mr Waterhouse to a broad commercial purpose being flouted do not assist. The contention is circular. As set out above in J&P Marlow, the purpose of a clause normally emerges from the words the parties have used. Mr Waterhouse’s contention simply assumes a broad purpose and then impermissibly uses that alleged purpose to force a construction onto the words that their plain meaning, in context, does not permit.
I do not accept Mr Waterhouse’s contention that the construction of sub-clause 49.1(c)(vii) which I prefer would render the indemnity contained in sub-clause 49.1(c)(iv) superfluous or vice versa. The two paragraphs are directed at different matters. Sub-clause (iv) gives Mr Waterhouse the benefit of an indemnity from Mr Rothner in respect of any claims made against Mr Waterhouse with regards to the works being carried out. Sub-clause (vii) is a prohibition on causing “damage, nuisance or inconvenience” to any adjoining property or occupier.
Mr Waterhouse’s reliance on the expressio unius principle also does not assist. The presumption (and hence the maxim) only applies when it is consistent with the intention discoverable from the face of the instrument and is thus one that must be applied with caution. “It is often a valuable servant, but a dangerous master to follow”: see Interpretation, Herzfeld and Prince (3rd ed, Thomson Reuters) at [24.50] and the cases there cited.
I accept Mr Rothner’s submission that there is a sound textual reason for why subclause (vii) does not expressly refer to “work”. It is the only one of the subclauses which prohibits Mr Rothner from acting in a certain way – a negative promise. Such a promise did not need to specify that it only applied in respect of the works because the word “provided” at the end of the chapeau provides that. By contrast, subclauses (i) to (vi) impose positive obligations and it is more natural to express those positive obligations by reference to the carrying out of the works.
Further, I accept Mr Rothner’s contention that subclause (vii) requires some act attributable to the purchaser (Mr Rothner) for it to be breached. It is not a free standing indemnity. (This point goes nowhere given that I have found the relevant authorisation in Issue 1.)
For these reasons I reject the construction of subclause 49.1(c)(vii) propounded by Mr Waterhouse and accept that contended for by Mr Rothner.
On this construction there must be a link between the works authorised by Mr Waterhouse on the Property and the damage etc caused. On the facts of this case, there was no such link. The fact that the tree removal was carried out by the same people (principally Mrs Rothner and Mr Shahwan) who were carrying out works on the Property, and that Mr Rothner authorised the removal, does not provide the necessary link. The tree removal on No 8 was an act of vandalism unconnected with the carrying out of authorised works on the Property.
The answer to this issue is therefore No.
The right of occupation granted to the purchaser may be terminated at the will of the vendor by giving the purchaser not less than (14) days notice in writing to that effect PROVIDED ALWAYS that the vendor shall not terminate the right of occupation unless and until the purchaser has failed to comply in any respect with the terms and conditions of this Special Condition AND has failed to rectify that non-compliance within the said fourteen (14) day period OR the contract is either terminated or rescinded.
On or about 1 April 2024, the Purchaser, through his agent, or agents, caused damage to the adjoining property at 8 Tivoli Avenue, Rose Bay NSW 2029 (the “Adjoining Property”) by removing several palm trees from the Adjoining Property without the approval of the owner of the Adjoining Property.
The Notice went on to state that should Mr Rothner fail to rectify the breach within 14 days, his right of occupation shall be terminated.
In response, on 31 May 2024, Mr Rothner provided a Deed Poll to each of Mr Huang and Mr Waterhouse. The Deed Poll in favour of Mr Waterhouse contained the following recitals:
A. The Grantor occupies the property at 6 Tivoli Avenue, Rose Bay pursuant to a Contract for Sale and Purchase dated 30 June 2023 between the Grantor as purchaser and the Beneficiary as vendor (Contract).
B. The Beneficiary has alleged in a Notice of Default dated 17 May 2024 that the Grantor caused damage to the adjoining property at 8 Tivoli Avenue, Rose Bay by removing several palm trees (Removed Trees) from the adjoining property without the approval of the owner of the adjoining property.
C. The Grantor denies breach of the Contract and denies that he caused the Removed Trees to be removed and denies that the Removed Trees were removed in the course of works by way of alteration or addition to the property at 6 Tivoli Avenue, Rose Bay.
D. Nevertheless, the Grantor wishes to ensure that the Beneficiary is no worse off as a result of the removal of the Removed Trees.
(Bold in original.)
2. INDEMNITY
2.1 Subject to clause 2.2, the Grantor indemnifies the Beneficiary against claims, loss, expense or costs incurred by the Beneficiary as a result of the removal of the Removed Trees, including in any proceedings commenced by the Local Council or other authority in respect of the removal of the Removed Trees. (save that this indemnity shall not apply if the Beneficiary himself requested, encouraged or procured the removal of the Removed Trees).
For the avoidance of doubt, if the proceedings currently on foot in the Land and Environment Court between Mr Huang and the Beneficiary (proceedings 2024/132772) are amended to include claims in respect of the Removed Trees, this indemnity, subject to clause 2.2, shall apply to the costs or increased costs incurred by or awarded against the Beneficiary in those proceedings as a result of allegations concerning the Removed Trees, but is not an indemnity in respect of other costs incurred by or awarded against the Beneficiary in those proceedings.
2.2 The indemnity in this clause 2 shall not apply if the Beneficiary himself requested, encouraged or procured the removal of the Removed Trees.
3. UNDERTAKINGS
3.1 The Grantor will not invite onto 6 Tivoli Avenue, Rose Bay Mr Gary Gibbons (being the person who the Grantor believes removed the Removed Trees).
3.2 The Grantor will instruct employees and contractors working in the grounds at 6 Tivoli Avenue, Rose Bay that they are not to enter the grounds of 8 Tivoli Avenue, Rose Bay.
2. PROMISE TO REPLANT OR COMPENSATE OR BOTH
2.1 The Grantor will (at the Beneficiary’s election) either plant replacement trees on 8 Tivoli Avenue, Rose Bay that as closely as possible replicate the Removed Trees or compensate the Beneficiary for the removal of the Removed Trees (or both, to the extent, if any, that the Beneficiary remains worse off after planting of the replacement trees).
2.2 The Grantor indemnifies the Beneficiary against claims, loss, expense or costs incurred by the Beneficiary as a result of the removal of the Removed Trees, including in any proceedings commenced by the Local Council or other authority in respect of the removal of the Removed Trees.
3. UNDERTAKINGS
3.1 The Grantor will not invite onto 6 Tivoli Avenue, Rose Bay Mr Gary Gibbons (being the person who the Granter believes removed the Removed Trees).
3.2 The Grantor will instruct employees and contractors working in the grounds at 6 Tivoli Avenue, Rose Bay that they are not to enter the grounds of 8 Tivoli Avenue, Rose Bay.
Mr Waterhouse did not accept that the breach had been rectified and purported to terminate the right of occupation on 5 June 2024.
The parties were at odds as to what was meant by rectify in the present circumstances and whether it was possible for the alleged breach to be rectified. Mr Rothner contended that rectify simply meant cease the alleged conduct. Alternatively, it was contended that any breach was rectified by the two Deed Polls issued in favour of Mr Waterhouse and Mr Huang dated 31 May 2024.
Both parties referred to L Schuler AG v Wickman Machine Tools Sales Ltd [1974] AC 235 (Wickman), which permitted a party to forthwith determine an agreement if “the other party shall have committed a material breach of its obligations hereunder and shall have failed to remedy the same within 60 days of being required in writing so to do”. At 249-250 Lord Reid stated:
It appears to me that clause 11(a)(i) is intended to apply to all material breaches of the agreement which are capable of being remedied. The question then is what is meant in this context by the word “remedy.” It could mean obviate or nullify the effect of a breach so that any damage already done is in some way made good. Or it could mean cure so that matters a****re put right for the future. I think that the latter is the more natural meaning. The word is commonly used in connection with diseases or ailments and they would normally be said to be remedied if they were cured although no cure can remove the past effect or result of the disease before the cure took place. And in general it can only be in a rare case that any remedy of something that has gone wrong in the performance of a continuing positive obligation will, in addition to putting it right for the future, remove or nullify damage already incurred before the remedy was applied. To restrict the meaning of remedy to cases where all damage past and future can be put right would leave hardly any scope at all for this clause. On the other hand, there are cases where it would seem a misuse of language to say that a breach can be remedied. For example, a breach of clause 14 by disclosure of confidential information could not be said to be remedied by a promise not to do it again.
(Emphasis added.)
To ‘remedy’ a breach is not to perform the impossible task of wiping it out - of producing the same condition of affairs as if the breach had never occurred. It is to set things right for the future, and that may be done even though they have for some period not been right, and even though that may have caused some damage to the lessor. … A breach may be remedied … even though the time for doing the thing under the covenant may have passed …
(Emphasis added.)
In Wickland *(*Holdings) Ltd v Telchadder [2014] 1 WLR 4004; [2014] UKSC 57 (Telchadder), Lord Wilson JSC, in considering whether a breach of a covenant not to disturb or annoy other residents of a mobile home park, could be remedied and, if so, how, stated at [31] that the answer is to be found by a practical inquiry whether, and if so, how the mischief resulting from the breach could be redressed.
Lord Toulson JSC at [51] agreed with Lord Wilson JSC in this regard – a practical approach is called for, that is whether and how the mischief caused by the breach can be redressed.
In Dexus Capital Investment Services Pty Ltd v Australia Pacific Airports Corp Ltd [2026] NSWSC 600 (Dexus), Hammerschlag CJ in Eq recently stated at [246]-[248]:
[246] A breach is Irremediable if it cannot be remedied (it is so defined in cl 1.1). It can be remedied if matters can be put right for the future. Each case will turn on its own circumstances. It is not desirable to lay down categories of breach which are, or are not, capable of remedy (Batson v de Carvalho (1948) 48 SR (NSW) 417 per Sugarman J).
[247] The test for materiality focuses not on the materiality of the obligation which has been breached but on the quality of the breach of the obligation, whereas the test for irremediability focuses on its effect (into the future) and not on the historical fact of its occurrence (Tricontinental Corp Ltd v HDFI Ltd (1990) 21 NSWLR 689).
[248] Determining whether a breach is, at the same time, material and Irremediable requires an evaluative judgment.
I do not accept Mr Rothner’s argument that the Court should find that Mr Rothner rectified the failure to comply with cl 49.1(c)(vii) because the breach ceased to occur following the issue of the notice of default on 17 May 2024.
I accept, in this regard, the factual predicate of the argument, namely that none of the trees cut down from No 8 were cut down after 17 May 2024. Although the expert arborists agreed that the final of the three cutting events – being the removal of three trees – occurred between 7 April and 10 June 2024. This is evidenced by the aerial photographs, and there were not daily aerial photographs. I accept that the last three trees were removed around 14 April 2024, being the date Mrs Rothner sent a WhatsApp message to Mr Rothner which stated “Another 3 🌴 fown *down”.
In no sense could it properly be said that merely ceasing the offending conduct is “rectifying” the breach. The authorities set out above make clear that in considering whether a breach is capable of rectification (which I treat as synonymous with remedy in this respect), and if so, how, the focus is on the effect of the breach and how that effect can be redressed into the future.
In the present case, the effect of the breach is not redressed by simply ceasing to engage in the conduct. The effect of the conduct continues into the future.
Reference to the outcome in Wickman and Telchadder in this regard does not assist. As Hammerschlag CJ in Eq recently stated in Dexus, what is required is an evaluative judgment (at [248]) and that “each case will turn on its own circumstances” (at [249]).
I turn now to consider whether the hypothesised breach of cl 49.1(c)(vii) is capable of being rectified and, if so, whether the provision of a Deed Poll to each of Mr Waterhouse and Mr Huang did rectify the breach.
I did not understand Mr Waterhouse to advance a contention that the breach in the present case was not capable of rectification. Rather, the contention was that the two Deed Polls did not rectify the breach.
In Akici v L R Butlin Ltd [2006] 1 WLR 201, Neuberger LJ (with whom Mummery LJ agreed) observed (at [65]) that “the great majority of breaches of covenant should be capable of remedy”.
The Notice of Default alleged a breach of cl 49.1(c)(vii) which provided that Mr Rothner “shall cause no damage, nuisance or inconvenience to any adjoining property or occupier of any adjoining property”. The conduct amounting to the breach was “by removing several palm trees from” No 8 without the approval of the Huangs.
As a matter of substance, the breach was causing damage by the removal of “several palm trees”. The effect of the breach is obvious – the palm trees have gone. The Huangs have lost the palm trees that were once on their property.
Looked at from the perspective of the Huangs that effect can only be redressed by replacing the removed trees and compensating the Huangs for any other loss suffered as a result of their removal.
It may be contended that the breach had an effect on Mr Waterhouse in the sense that he may be exposed to a claim by the Huangs by reason of the fact that Mr Rothner was occupying the Property and carrying out work on it with the permission of Mr Waterhouse. That effect could be redressed by Mr Rothner indemnifying Mr Waterhouse against any such claim.
Viewed through this prism, the two Deed Polls do, in my view, rectify the breach. Practically speaking, they redress the harm suffered by, or effect of, the breach.
I do not accept that, looked at from the perspective of the Huangs, in order to rectify the breach, Mr Rothner was required, within the 14 day period after the service of the Notice of Default, to have in fact replanted the removed trees. This is not at all practicable in circumstances where Mr Rothner had no right of access to the Huang’s property. The effect of, or harm caused by, the breach could be compensated for in money terms, rather than the replacement of the trees. This was a matter for the Huangs to elect under the terms of the Deed Poll.
There was no suggestion in the present case that Mr Rothner’s indemnity to Mr Waterhouse or his promise to compensate Mr Huang for the removal of the trees was worthless in the sense that he did not have the financial resources to fulfill the promises he made in the respective Deed Polls if called on to do so.
Mr Waterhouse also mounted a number of arguments particularly directed at the deficiency in offering a Deed Poll to Mr Waterhouse and Mr Huang.
The first was to point out that a Deed Poll is a unilateral promise to pay which is distinct from a bilateral contract. A deed poll, whilst binding on the grantor, does not need to be accepted by the grantee and as such cannot unilaterally discharge contractual obligations or extinguish secured rights held by another party.
So much may be accepted.
None of this means, in my view, that the offering of the respective Deed Polls does not rectify the breach in the sense of setting things right for the future. There is nothing more that Mr Rothner can do, or needs to do, to redress the effect of, or harm caused by, the breach. It is to be remembered that Mr Rothner cannot force any particular outcome on the Huangs. What is offered will, however, once accepted, set things right for the future.
The second and related contention was to point out that an existing contractual obligation can only be discharged by accord and satisfaction, and in the present case there was no agreed substituted performance. The contents of the Deed Poll could not be forced on the Huangs.
Again, these contentions do not address the relevant issue which is whether Mr Rothner has redressed the effect of, or the harm caused by, the breach. The focus is on making things right for the future. In my view the Deed Polls had this effect.
Finally, Mr Waterhouse contended, as I understood the submission, that his right to terminate had occurred by the time of delivery of the Deed Poll and no unilateral act thereafter by Mr Rothner could extinguish Mr Waterhouse’s accrued right.
The relevant chronology was said to be:
(a) notice on 17 May 2024 specifying the breach; (b) 14 day rectification period expired on 31 May 2024; (c) Waterhouse’s right to terminate accrued upon expiry of that period; and (d) Rothner then executed a Deed Poll on 31 May 2024 (the last day).
I do not accept this argument.
If, as I have found above, the delivery of the two Deed Polls rectified the breach, and the two Deed Polls were delivered within the required 14 day rectification period, Mr Waterhouse no longer had a right to terminate the right of occupation.
Clause 49.2 expressly provides that the right of occupation shall not be terminated unless and until Mr Rothner has failed to comply with cl 49 and has failed to rectify that non-compliance within the 14 day notice period.
The final argument to be addressed in relation to this issue is Mr Waterhouse’s contention that the Deed Polls were grossly inadequate because they only covered four trees even though at the time, and to the knowledge of Mr Rothner, 31 trees had been systematically destroyed over eight months. It was contended that Mr Rothner deliberately limited the first Deed Poll to only four trees and that this was calculated bad faith conduct designed to:
(a) minimise indemnity exposure while maintaining façade of “rectification”; (b) avoid termination of valuable occupation rights (worth millions in renovation time); and (c) shift ultimate liability onto the Huangs (by covering only what they specifically identified).
It was thus said that this was not a genuine attempt to rectify the breach.
No submissions were advanced by Mr Waterhouse in this regard by reference to the contractual framework.
Clause 49.2 clearly requires, before the right of occupation can be terminated:
(a) the purchaser having failed to comply in any respect with the terms and conditions of cl 49; (b) the giving of 14 days’ notice of the proposed termination; and (c) the purchaser having failed to rectify that non-compliance within the said 14 day period.
The obvious intent of this regime is to give the purchaser (Mr Rothner) an opportunity of 14 days to rectify the non-compliance after having been given notice of that non-compliance and having been put on notice that if that non-compliance is not rectified within the 14 day period, the right of occupation will be terminated.
The regime requires notice of the non-compliance to be given. I did not understand any party to contend to the contrary. It is the notified non-compliance that must be rectified.
The obvious intent of cl 49.2 would be flouted if notice of the non-compliance was not required to be given.
The Notice of Default dated 17 May 2024 referred to “removing several palm trees”. The earlier letter from Mr Huang’s solicitors to Mr Rothner’s solicitors dated 13 May 2024 referred to “at least four large trees” having been removed from No 8.
The Deed Poll delivered in favour of Mr Waterhouse was by reference to the Removed Trees which were defined by reference to the Notice of Default – “several palm trees”.
The Deed Poll delivered in favour of Mr Huang defined the Removed Trees by reference to the 13 May 2024 letter as “at least four large trees”.
The Deed Polls were thus directly responsive to what Mr Rothner had then been given notice of – he was seeking to rectify the non-compliances of which he had been given notice and was thus required to rectify.
The fact that it is now known that by that time a larger number of trees had been removed does not make the offered rectification inadequate or indeed grossly inadequate.
The contractually agreed termination regime does not require the purchaser to seek to rectify all breaches or non-compliances of which the purchaser may be aware, but only those with which notice of non-compliance has been given by the vendor.
This issue only arises for consideration if, contrary to what I have found above, Mr Waterhouse is contractually entitled to terminate Mr Rothner’s right of occupancy. I address it against the possibility that I am wrong on the second and third issues above.
Mr Rothner contends that if Mr Waterhouse is contractually entitled to terminate Mr Rothner’s right of occupancy, he (Mr Rothner) is entitled to equity’s intervention to restrain the exercise of that contractual right by the grant of relief against forfeiture.
The parties were apart on two issues:
(a) whether the right possessed by Mr Rothner was one to which the doctrine applied; and (b) if jurisdiction exists to grant relief against forfeiture, whether relief should be granted in the circumstances of the present case.
On the first issue, Mr Rothner placed reliance on two decisions – the judgment of Brereton JA in Kay v Playup Australia Pty Ltd (2020) 19 BPR 40,037; [2020] NSWCA 33 at [100]-[123] (Playup), and the judgment of Edelman J in Mineralogy Pty Ltd v Sino Iron Pty Ltd *(*No 6) (2015) 329 ALR 1; [2015] FCA 825 (Mineralogy) at [981]ff which was approved on appeal, see Mineralogy Pty Ltd v Sino Iron Pty Ltd [2017] FCAFC 55 at 421 per Besanko, McKerracher and Beach JJ.
In Playup, Brereton JA reviewed the authorities, including Mineralogy and stated, at [122]:
[122] As it seems to me, there is no decided case in which relief against forfeiture has been granted in respect of a mere contractual right, accrued or not. All the cases that suggest that it might be available in that context assume its availability in the context that relief is otherwise refused. None of them purport categorically to determine the question. On the other hand, the decisions of the House of Lords in The Scaptrade, and in Sport International Bussum; of the United Kingdom Supreme Court in Vauxhall Motors v Manchester Ship Canal; of the Privy Council in Çukurova Finance International Ltd v Alfa Telecom Turkey; of the Court of Appeal of England and Wales in BICC Plc v Burndy Corporation; of the Full Court of the Supreme Court of Western Australia in Westminster Properties Pty Ltd v Comco Constructions Pty Ltd, and of this Court in Milton v Proctor, support the view, which in my judgment represents the current state of the law, that the doctrine is confined to proprietary or possessory rights, and does not extend to mere contractual rights.
The other two members of the court – Macfarlan JA and Simpson AJA – both expressly did not express a view as to whether the doctrine of forfeiture is confined to proprietary or possessory rights and does not extend to mere contractual rights.
At [102] of his reasons, Brereton JA referred to the fact that in light of the conclusion that he had reached on the question of penalty, it was unnecessary to resolve whether relief against forfeiture should be granted. The statements made by Brereton JA thus do not reflect the views of a majority of the Court.
In Mineralogy, Edelman J stated at [980] - [990]:
[980] Mineralogy’s primary submission for why relief against forfeiture was said to be unavailable was that relief against forfeiture was said only to be available where the subject matter over which relief is sought is a proprietary right.
[981] On the one hand, there are authorities which have suggested that the doctrine might not be so limited and might apply, for instance, to a contractual licence: Chaka Holdings Pty Ltd v Sunsim Pty Ltd (1987) 10 BPR 18,171 at 18,182 (Young J); Milton v Proctor (1988) 4 BPR 9654 at 9659–9660 (McHugh JA); Rossiter CJ, Penalties and Forfeiture: Judicial Review of Contractual Penalties and Relief Against Forfeiture (Law Book Co., 1992) p 201.
[982] On the other hand, there are authorities that can be read as supporting the proposition that relief against forfeiture is only available to protect a proprietary right: Scandanavian Trading Tanker Co AB v Flota Petrolera Ecuatoriana (The Scraptrade) [1983] 2 AC 694; [1983] 2 All ER 763; Sport International Bussum BV v Inter-Footwear Ltd [1984] 1 WLR 776; [1984] 2 All ER 321. In Shiloh Spinners Ltd v Harding [1973] AC 691 at 722; [1973] 1 All ER 90 at 100, Lord Wilberforce spoke of the jurisdiction to “relieve against the forfeiture of property”.
[983] One difficulty with the insistence that relief against forfeiture operates only to relieve from forfeiture of proprietary rights is the issue of the principle. Why should the doctrine be confined to property rights? None of the cases addresses this point.
[984] As a matter of principle, there might be very fine distinctions between relieving from forfeiture of a proprietary right and relieving from forfeiture of a non-proprietary right. For instance, as Professor McFarlane insightfully observes, it is consistent with the decision of the Privy Council in Cukurova Finance International Ltd v Alfa Telecom Turkey Ltd (British Virgin Islands) [2015] 2 WLR 875; [2013] UKPC 2 that if “B has a purely contractual right against X, and then mortgages that right to A as security for a loan … there is no reason in principle why B could not seek relief from forfeiture if A attempted to retain that contractual right”: McFarlane B, “Penalties and Forfeiture” in McGhee J (ed), *Snell’*s Equity (33rd ed, Sweet & Maxwell, 2015) at [13-023].
[985] A second difficulty concerns the meaning of a “proprietary right”. A blind adherence to older authority that suggests that relief against forfeiture is unavailable for non-proprietary rights simply shifts the enquiry into the meaning of a proprietary right. Are patent rights “proprietary” (see BICC Plc v Burndy Corporation [1985] Ch 232; [1985] 1 All ER 417? Should a contractual right fall within this category to the extent that it can be characterised as “quasi-proprietary” (see Zhu v Treasurer of New South Wales (2004) 218 CLR 530; 211 ALR 159; [2004] HCA 56 at [126] (the Court))?
[986] A third difficulty concerns the line of cases involving termination of contracts for the purchase of land where relief against forfeiture is allowed, or considered, without any suggestion that such cases are beyond the scope of relief against forfeiture: eg Legione v Hateley (1983) 152 CLR 406; 46 ALR 1; Ciavarella v Balmer (1983) 153 CLR 438; 48 ALR 407 .
[987] Although the vendor of a contract for the sale of land has sometimes been described as a “trustee” for the purchaser, in the joint judgment in the High Court in Tanwar Enterprises Pty Ltd v Cauchi (2003) 217 CLR 315; 201 ALR 359; [2003] HCA 57 at [53] (Tanwar), their Honours said that “the description of the vendor as a trustee tends to conceal the essentially contractual relationship which, rather than the relationship of trustee and beneficiary, governs the rights and duties of the respective parties” (quoting Chang v Registrar of Titles (1976) 137 CLR 177 at 190; 8 ALR 285 at 295 (per Jacobs J)). Even if the purchaser under a contract for the sale of land is described as the beneficiary of a trust, this still begs the question of whether a trust interest should be characterised as “proprietary”. At the very least, it could only be “proprietary” if that word is used in a very different sense from that which describes an estate in land or possession or ownership of goods.
[988] A fourth difficulty with the proprietary restriction is that at least one foundational reason for relief against forfeiture is not tied to the existence of a proprietary right. As I explained in Hampton v BHP Billiton Minerals Pty Ltd (No 2) [2012] WASC 285 at [239]–[240], a plea of relief against forfeiture acts as a constraint upon the exercise of a contractual power. In the words of Professor Getzler, equity does not “act in order to protect an estate contract from being unconscionably cancelled by the vendor, but rather scrutinised the vendor’s resort to a contractual power”: Getzler J, “Forfeiture for Breach of a Time Condition” (2004) 120 Law Quarterly Review 203, 205. For that reason, courts have denied the availability of relief against forfeiture where the termination occurs independently of the exercise of a power by the other party, such as after the failure of a condition subsequent: Kayserian Nominees (No 1) Pty Ltd v J R Garner Pty Ltd [2008] NSWSC 803 at [50]–[51] (Brereton J); Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 372 at [66] (per McMurdo J).
[989] One suggestion which might assist the view that relief against forfeiture requires forfeiture of a proprietary right is that a doctrine of relief against forfeiture can be separated from a different doctrine which relieves against the unconscientious exercise of a contractual power: Heydon JD, Leeming MJ and Turner PG, Meagher, Gummow and Lehane’s Equity Doctrines and Remedies (5th ed, LexisNexis Butterworths, 2015) 601 at [18-340] relying upon an interpretation of Tanwar. It may be that if this deconstruction exercise were undertaken then relief against forfeiture might be divided into different restraints on the exercise of different types of contractual power. On such an approach, the ultimate conclusion may be that there is nothing left of relief against forfeiture: Worthington S “What is Left of Equity’s Relief Against Forfeiture” in E Bant and M Harding, Exploring Private Law (Cambridge University Press, 2010) 249.
[990] It is sufficient for the purposes of this case to proceed on the basis that, however characterised, the relief that the CITIC parties were seeking was not precluded merely because they did not seek relief from the forfeiture of a proprietary right.
On appeal from Edelman J, the full court stated at [421] that “for the reasons set out by the primary judge at [978] to [988], relief against forfeiture may be taken to be available in principle”.
There are several first instance decisions where the Court has proceeded, like Edelman J, on the assumption that relief against forfeiture could apply to non-proprietary rights but then determined that relief should not be granted on the facts: see Auburn Shopping Village Pty Ltd v Nelmeer Hoteliers Pty Ltd (2017) 324 FLR 378; [2017] NSWSC 1230 at [211]ff per Ward CJ in Eq (upheld on appeal in Auburn Shopping Village Pty Ltd v Nelmeer Hoteliers Pty Ltd (2018) 19 BPR 38,569; [2018] NSWCA 114) and Ayers Rock SkyShip Pty Ltd v Voyages Indigenous Tourism Australia Pty Ltd (2019) 19 BPR 39,541; [2019] NSWSC 828 at [106]-[107] per Darke J. The Victorian Court of Appeal in JPA Finance (defined below) took a similar approach (at [82]).
The distinction between, on the one hand proprietary or possessory rights, and on the other contractual rights, stems from what was said by Lord Diplock in Scandinavian Trad**ing Tanker Co A.B. v Flota Petrolera Ecuatoriana *(*The Scaptrade) [1983] 2 AC 694 at 702.
Whatever may be said to be the position in Australia, the distinction remains the law in the United Kingdom: see Vauxhall Motors Ltd v Manchester Ship Canal Co Ltd [2020] AC 1161; [2019] UKSC 46 (Vauxhall). For a discussion of the differences between Australia and the United Kingdom see N Tiveros [2020] CLJ 17, “Salvaging security: The normative basis of Equity’s relief against forfeiture” by A Berriman (2021) 15 Journal of Equity 306, and “The Requirement of Property or Possessory Rights for Relief against Forfeiture” by F Di Lizia (2021) 95 ALJ 641. For a powerful criticism of the distinction see P Turner [2019] CLJ 276. As far back as 1985, Sir Anthony Mason, writing extra judicially, said that the distinction was “difficult to define and defend”: “Themes and Prospects” in Paul Finn (ed), Essays in Equity (Lawbook Co 1985) p 248.
In Vauxhall, Lord Briggs JSC (with whom Lord Carnwath, Lady Black and Lord Kitchin JJSC agreed) clarified what was meant by a possessory right in this context. At [42], Lord Briggs JSC approved the following statement of Lewison LJ in the Court of Appeal:
“There are two elements to the concept of possession: (1) a sufficient degree of physical custody and control (‘factual possession’); (2) an intention to exercise such custody and control on one’s own behalf and for one’s own benefit (‘intention to possess’). What amounts to a sufficient degree of physical custody and control will depend on the nature of the relevant subject matter and the manner in which that subject matter is commonly enjoyed. The existence of the intention to possess is to be objectively ascertained and will usually be deduced from the acts carried out by the putative possessor …”
Although Brereton JA in Playup referred to Vauxhall in other respects, Brereton JA did not refer to the above passage.
Adopting this test from Vauxhall, I am comfortably satisfied that Mr Rothner’s right of occupation pursuant to cl 49 of the Contract is a possessory right for the purposes of the doctrine. Under cl 49.1 of the Contract, Mr Waterhouse “grants occupation of the [Property] to [Mr Rothner] to exclusively occupy the [Property] from 5 January 2024 until completion”. Pursuant to cl 49.1(a) Mr Waterhouse was required to provide Mr Rothner on 5 January 2024 “all keys, access cards and security codes necessary to allow [Mr Rothner] possession of the [Property].”
I am thus satisfied that there is jurisdiction to grant relief against forfeiture in the present case. I now turn to consider whether that jurisdiction should be exercised.
In JPA Finance Pty Ltd v Gordon Nominees Pty Ltd (2019) 58 VR 393; [2019] VSCA 159 (JPA Finance), McLeish JA (with whom Beach and Niall JJA agreed) stated at [98]-[101]:
[98] The following principles, relevant for present purposes, emerge from these authorities. First, equitable relief against forfeiture may be available in two kinds of situation. The first situation is where there is a contractual stipulation for forfeiture which is directed at securing an object of the transaction, where that object can be attained by means other than forfeiture, such that insistence on forfeiture would constitute a penalty. The second situation is where a party is entitled at law to terminate a contract and forfeit the relevant interest but it would be unconscientious to do so, whether because of fraud, mistake, accident or surprise or because of other unconscientious conduct such as taking advantage of a special vulnerability in order to derive an unjust enrichment. Both kinds of case may be characterised as “unconscientious”, on the basis that it is unconscientious to take advantage of a penal forfeiture, but the two are often treated separately, keeping the label “unconscientious” for the latter situation.
[99] Secondly, the Court should not intervene so as to interfere with the contractual rights of the parties merely because it thinks it would be fair or reasonable to do so because subsequent events have rendered one party’s situation more favourable.
[100] Thirdly, equity will not intervene if forfeiture has resulted simply from one party’s inadvertence, or that party’s wilful default.
[101] Fourthly, the question of unconscientious conduct may be addressed by reference to the five “subsidiary questions” identified by Mason and Deane JJ in Legione and set out at [80] above.
Mason and Deane JJ later identified five “subsidiary questions” relevant to the identification of unconscionable conduct in this context:
“In the ultimate analysis the result in a given case will depend upon the resolution of subsidiary questions which inevitably arise. The more important of these are: (1) Did the conduct of the vendor contribute to the purchaser’s breach? (2) Was the purchaser’s breach (a) trivial or slight, and (b) inadvertent and not wilful? (3) What damage or other adverse consequences did the vendor suffer by reason of the purchaser’s breach? (4) What is the magnitude of the purchaser’s loss and the vendor’s gain if the forfeiture is to stand? (5) Is specific performance with or without compensation an adequate safeguard for the vendor?”
In ING Bank *(Aust) Ltd v O’*Shea (2010) 14 BPR 27,317; [2010] NSWCA 71, the NSW Court of Appeal unanimously held that it is necessary in all cases that there be unconscionable or unconscientious behaviour on the part of the party against whom relief is sought. The Court rejected an argument that there was no such requirement in the first category listed above – where a promise was given as security to achieve a stated result.
It must be kept firmly in mind that the claim for relief against forfeiture would only fall to be considered if I was satisfied that Mr Waterhouse was entitled to terminate the right of occupation. I thus would have found, at least:
(a) that Mr Rothner authorised the removal of the trees from No 8; (b) that removal was a breach of cl 49.1(c)(vii) of the Contract; (c) Mr Waterhouse, acting bona fide, gave Mr Rothner notice of that breach and the required 14 days to rectify the breach; and (d) Mr Rothner has not rectified that breach.
Somewhat similar to what Edelman J said in Mineralogy at [991]-[992], it is difficult to see how there could be any basis to grant relief against forfeiture.
Mr Rothner’s authorisation of Mrs Rothner causing the trespass onto No 8 and the removal of trees could properly be described as a wilful or deliberate act. There is also, in my view, nothing unconscionable in Mr Waterhouse seeking to exercise his contractual rights in the circumstances.
Whilst the rights of occupation are undoubtedly valuable rights to Mr Rothner, this is only one matter to be taken into account. It is not determinative. The matters referred to above are more relevant in my view.
The parties were at odds as to whether the clause in the present case falls within the first kind discussed in JPA Finance – whether it is directed at securing an object of the transaction. I do not need to reach a final view on this question because even if I was satisfied that it could be so characterised, I would not, in the exercise of my discretion, grant relief against forfeiture for the reasons set out above.
It does seem to me, however, that the clause does more than simply secure an object of the transaction. It is materially different to a clause securing an obligation to pay rent. Mr Waterhouse would no doubt be concerned about an occupant (Mr Rothner) causing damage at a time when Mr Rothner does not own the Property and may never own the Property if he does not complete on the Contract. He would be entitled in these circumstances to protect his position and terminate the right of occupation, thus removing his exposure going forward until he ceases to own the Property.
A further relevant matter is that, as set out above, in having to deal with relief against forfeiture I will already have found that the breach has not been remedied by Mr Rothner. I will thus have rejected that the Deed Polls in favour of Mr Waterhouse and Mr Huang rectified the breach. This is another reason why relief would not be granted.
Having regard to my conclusions above, it is not strictly necessary that I consider this issue. I address it against the possibility that I am wrong on the issues set out above and Mr Waterhouse was entitled to terminate Mr Rothner’s right of occupation.
Mr Waterhouse purported to terminate the right of occupation on 5 June 2024.
By his second further amended statement of claim, Mr Waterhouse alleges that by reason of Mr Rothner’s breach of the Contract, he is entitled to damages. The loss alleged is the rent he would have received for the Property, or the loss of opportunity to receive that rent.
The first issue that arises is one of causation – whether Mr Waterhouse would have rented the Property to a third party or whether, consistent with well understood principles, Mr Waterhouse has proved he lost the opportunity to rent it out. Mr Rothner contended that Mr Waterhouse would have moved back in.
Mr Waterhouse accepted in cross-examination that if he was receiving rent for the Property, he “would be up for land tax”. The land tax would have been in an amount of approximately $150,000 per annum.
Mr Waterhouse gave the following additional evidence on the topic:
Added to this is the fact that the expert called by Mr Waterhouse on the question of what the Property would have been rented for – Ms Conlon – stated that she would have listed the Property for rent at $7,000 per week. One difficulty with Ms Conlon’s opinion in this regard is that it was not supported by any real comparables. Although she made some general reference in her report to comparables, no detail was provided as to those comparables. It also appears that some of the “comparables” were in fact listings currently available online, suggesting they were not in fact properties that had been leased. No business records were included to suggest that the “comparables” were concluded transactions. Ms Conlon also did not take into account that Mr Rothner still had his rights to access the Property daily to carry out works.
The competing expert qualified by Mr Rothner – Mr Srot – expressed the view that the weekly rental was in the order of $2,750 to $3,000 per week if, as appears to be agreed, the Property was let on an unfurnished basis. The difficulty with Mr Srot’s opinion is that, although he offered what he said were comparable properties, they in fact appear to be inferior properties to the Property. There is also nothing to indicate that he took account of the fact that Mr Rothner continued to have rights to access the Property daily to carry out works.
On the state of the expert evidence, I am left with little alternative but to adopt a position between the two opinions of the experts. One major difficulty with the exercise is whether I need to assess the impact on market rent of Mr Rothner’s continued right to access the Property daily to carry out works to the garden and the garage (cl 48.1).
I assume that the right would have been exercised. There is perhaps a question of construction as to whether the right of occupation in cl 49.1, being a larger right than the right of access in cl 48.1, and coming into effect at a later point in time – 5 January 2024 as opposed to 31 July 2023 – overtakes, in a sense, the right of access such that it ceases to exist. If Mr Rothner is in occupation, he no longer needs or has a right of access.
This issue was not really ventilated before me.
I proceed on the basis that Mr Rothner would have sought to exercise his cl 48.1 right of access if he was removed from occupation.
It is likely that, in this situation, Mr Waterhouse would have sought to terminate the right of access under cl 48.1. Its terms, with respect to termination, are relevantly the same as the terms attached to the right of occupation.
The question of damages that I am presently considering arises if I have found that Mr Waterhouse had validly brought the right of occupation to an end. It is reasonable to assume that if Mr Rothner had still sought to avail himself of his rights under cl 48.1, Mr Waterhouse would have validly terminated that right of access as well. I am in no doubt, given the poor state of their relationship at the time, that Mr Waterhouse would have sought to exercise his right to terminate.
As a result, the exercise should be approached on the basis that Mr Rothner would not have retained his cl 48.1 right of access.
Doing the best I can, I estimate the weekly rental to be $5,000 per week being a figure between Mr Srot and Ms Conlon’s estimates.
On this basis there is no real prospect, taking Mr Waterhouse’s evidence at its most favourable to him, that he would have rented the Property. At $5,000 he said he would probably reject the offer and live in the Property himself. At best his evidence was equivocal at $7,000 per week. His affidavit evidence was $10,000 per week. There is no evidence to support this.
This is all against the background of his initial answer in cross-examination when it was put to him that he would have stayed there himself – “I think so, yes”.
I am not satisfied that Mr Waterhouse would have rented the Property out. Nor am I satisfied that Mr Waterhouse has lost a valuable opportunity to rent the Property out.
Perhaps conscious of this evidentiary difficulty, Mr Waterhouse’s claim in this regard was ultimately put, as I understand it, as a claim for mesne profits. I have addressed the traditional damages claim above in case I have misunderstood Mr Waterhouse’s position. If it is a damages claim on the basis he would have rented the Property out, it fails.
As the Court of Appeal explained in Sydney Local Health District v Macquarie International Health Clinic Pty Ltd (2020) 105 NSWLR 325; [2020] NSWCA 274 (Macquarie International), mesne profits is a monetary remedy for the use of the plaintiff’s land by the defendant during the period of trespass. Typically this measure of damages will be sought where the plaintiff with the right to exclusive possession has in fact suffered no loss or less loss than is represented by a “rent” or “hiring charge” for the land on which the trespass has occurred (at [79]). Further, such a remedy, where available, is in the strict alternative to a claim for damages for loss of profits or loss of opportunity to use the land. This is because the calculation of damages for claims of this latter character is predicated on the plaintiff being in and remaining in possession; the plaintiff could not generate a profit from possession of the property while simultaneously renting it out. The claims are mutually exclusive (see [80]).
As the Court of Appeal made clear at [81], one particular feature of the award of damages by way of mesne profits is that a plaintiff does not need to establish on the balance of probabilities that he, she or it would have rented or licenced the land trespassed upon to the defendant trespasser.
In Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17 at 39; [1985] HCA 14, Brennan J stated:
A lessor who, under a proviso for re-entry, serves the lessee with process for recovery of possession is entitled to mesne profits for the period during which the lessee remains in possession after service…the lessor may thereby recover an amount equal to the rent in respect of that period. Mesne profits are damages for trespass; mesne profits are not rent, nor are they damages for breach of a covenant to pay rent.
[134] Fourthly, the usual measure of damages for or by way of mesne profits will be the market rent for the premises or for the hire of the goods in their state during the period of the trespass. The calculation of that market rent must have regard to the particular context of the case and characteristics of the property or goods in question, as the variable rent calculated in Inverugie by reference to the holiday season illustrates.
[135] Fifth, whilst the usual measure of damages for or by way of mesne profits will be the market rent for the premises in their state during the period of the trespass, there may be special circumstances associated with the defendant which warrant a departure from this yardstick. Any departure from this yardstick is not, however, at large, but again is tied or limited by the defendant’s actual usage of the property in question.
Mr Waterhouse sought mesne profits for a period of 82 weeks at $7,000 per week, being the market rent that he contends the Property would have fetched. The 82 week period runs from 5 June 2024 to 22 December 2025 being the date completion was to occur by. As it happened, completion occurred five days earlier.
As set out above, I have not accepted that a market rent of $7,000 would have been achieved and, doing the best I can, I assess the market rent at $5,000 per week.
The only additional substantive issue raised by Mr Rothner in his closing written submissions in response to the claim for mesne profits, is that the amount awarded to Mr Waterhouse should be reduced by approximately $150,000 to reflect the effect of land tax.
As set out above, Mr Waterhouse did not dispute that if he was living in the house as at 31 December 2024, he would be “up for land tax” and that the amount would be approximately $150,000 per annum.
In his closing written submissions, Mr Rothner submitted:
As for mesne profits, it is accepted that while they are ordinarily calculated with reference to market rent, there may be special circumstances associated with the defendant which warrant a departure from that yardstick: Macquarie International at [135]. The special circumstances of Mr Rother are that by reason of s 26(3) of the [Land Tax Management Act 1956 (NSW)], he is the only person (other than Mr Waterhouse) who could have occupied Number 6 without causing Mr Waterhouse to pay land tax. If a third party tenant occupied Number 6, then s 26(1) of the LTMA would apply and accordingly Mr Waterhouse would be taken to be the owner of the land and accordingly liable to pay land tax. As such mesne profits should be reduced to reflect the reality that Mr Waterhouse could not have enjoyed occupation of Number 6 without paying land tax. That liability would either arise because by renting out Number 6 it would not be his principal place of residence, or in the alternative if he lived at Number 6 then he would have been liable to pay land tax on whatever other property was taken to be his principal place of residence for that land tax year.
The written submissions on mesne profits provided by Mr Waterhouse prior to the conclusion of the initial hearing in November 2025, similarly did not address this point. Mr Douglas KC briefly addressed the point in his closing submissions in reply.
As I understood the submission advanced by Mr Douglas KC, it was to the effect that because mesne profits are awarded on a restitutionary basis, the $150,000 should not be deducted. Mr Waterhouse receives the full amount, and it is a matter between him and Revenue NSW as to whether land tax is payable.
Reference in this regard was made to what was said to be a similar situation considered by the High Court in The National Insurance Company of New Zealand Limited v Espagne (1961) 105 CLR 569; [1961] HCA 15.
I have extracted [135] from Macquarie International (the passage relied on by Mr Rothner) above.
Earlier in the reasons for judgment, the Court in Macquarie International when discussing the seminal decision in Inverugie Investments Ltd v Hackett [1995] 1 WLR 713, stated at [117]:
…. The approach endorsed by the Privy Council may be seen to represent something of a hybrid or compromised result. It was in effect a “market rent” for tour operators booking a block of apartments as opposed to the market rent for individual holidaymakers. **From this amount it was also accepted that there should be deducted the rent the plaintiff needed to pay under his long-term lease together with the plaintiff’**s obligation to contribute to the maintenance and refurbishment of common areas. As such, the damages by way of mesne profits awarded reflected at least the individual circumstances of the property and the defendant (as a tour operator) and, no doubt, an assessment that it was reasonable or just to use what was in effect a wholesale rate to calculate a notional or surrogate rent.
(Emphasis added.)
In the circumstances of the present case, it seems to me to be appropriate in assessing mesne profits to deduct the land tax that Mr Waterhouse would have had to pay had the Property been rented out to a third party. To fail to take this amount into account would risk overcompensation of Mr Waterhouse: see Bunnings Group Limited v CHEP Australia Limited (2011) 82 NSWLR 420; [2011] NSWCA 342 at [185] per Allsop P – (with whom Giles and Macfarlan JJA agreed) referred to in Macquarie International at [121].
Mr Waterhouse is thus entitled to 81 weeks and two days at $5,000 per week, less $150,000. The hypothetical award of damages by way of mesne profits is thus $256,430. To this amount, interest at Court rates should be added.
The objective facts were not in dispute.
First, cl 50.1 of the Contract provided:
50.1 The vendor will consent to the lodgement by the purchaser of a Development Application or application to vary a Development Application to the Council and will sign all such applications, plans and consents as may be reasonably required by the purchaser PROVIDED however this contract is in no way subject to the approval or lack of approval of any such Application which may or may not be granted. The costs of any such Application shall be borne by the purchaser and the purchaser shall indemnify the vendor with respect to same.
Despite the capitalisation, the words “Development Application” are not defined in the Contract.
It is not in dispute that on 31 January 2024, Mr Rothner (by his solicitor at the time) sent an email to Mr Waterhouse’s solicitor which requested that “Applications and consent forms” be signed by Mr Waterhouse. Those forms were sent under the cover of three separate emails. In one of those emails, Mr Rothner asked Mr Waterhouse to sign an application for a construction certificate to carry out the work the subject of DA 518/2021 (the CC Application Form). The CC Application Form described the proposed works as “alterations and additions to existing dwelling including enclosure of balcony, two new verandahs and an attic room addition.”
On the same date, Mr Rothner also sent documents for signing in relation to the garage and wellness centre, but those aspects no longer form part of Mr Rothner’s cross-claim.
On 7 March 2024, Mr Rothner sent a further email to Mr Waterhouse’s solicitor advising him that the original certifier was no longer available and therefore requested that he sign a substitute form to apply for a construction certificate for the works in the house (DA 518/2021). The request that Mr Waterhouse sign an application for a construction certificate in respect of the works for DA 518/2021 was repeated on 1 July 2024, and again on 27 September 2024.
Mr Waterhouse has not signed the CC Application Form for the works on the main house.
Mr Rothner contends that Mr Waterhouse’s failure to do so was a breach of cl 50.1. That clause, properly construed, required him to sign the CC Application Form. Mr Rothner further contended that a term should also be implied into the Contract requiring Mr Waterhouse to do all things necessary to enable Mr Rothner to obtain the benefit of the Contract. The failure was a breach of this implied term.
Under the Contract, Mr Rothner was entitled to carry out works pursuant to cl 49.1(c). That right could only be exercised if Mr Waterhouse, as registered proprietor of the Property, signed the applications for a construction certificate.
Mr Rothner contends that his intention was to renovate the Property during the period that he was in occupation prior to settlement and then sell the Property once he has completed on the purchase. By reason of Mr Waterhouse’s breach, Mr Rothner contends that he has been delayed in carrying out the works to the Property. This has allegedly had two major consequences. First, increased holding costs that Mr Rothner will incur up to the sale of the Property – said to be a delay of 18 months. Second, Mr Rothner contends that he will incur increased construction costs. These two alleged consequences are dealt with in the seventh issue below. This issue is concerned solely with the issue of breach.
Mr Waterhouse raised a number of matters in defence of the claim:
(a) the cross claim accepts that any requirement made of Mr Waterhouse had to be reasonable; (b) the special condition did not require Mr Waterhouse to sign the documents provided to him. The clause only dealt with development applications, not with signing any document required to commence development; (c) it was reasonable for Mr Waterhouse not to sign the documents submitted. Mr Rothner agreed with Mr Waterhouse and Westpac that he would not cause Mr Waterhouse to breach the terms of the first mortgage. Alternatively, it was reasonable for Mr Waterhouse not to consent to any work that had not been approved by Westpac. Westpac did not approve the work; and (d) Mr Rothner failed to obtain insurance in the terms required by cl 49.7, indemnifying Mr Waterhouse as a named beneficiary from any damage caused by building work, and Mr Waterhouse was entitled to withhold consent until he was provided with such a policy.
The first issue to consider is the proper construction of cl 50.1 and, in particular, where the requirement of “reasonable” fits. The usual principles of construction apply. I have set them out above in relation to issue 2.
I have set out cl 50.1 above.
Before considering the text of cl 50.1, it is useful to remember the context in which the clause appears.
As set out above, the clause forms part of a suite of special conditions inserted into the Contract for purchase of the Property in connection with the works which Mr Rothner was proposing to carry out.
In the period from 31 July 2023, Mr Rothner was entitled to carry out works to the garage and the garden which were approved by a Development Consent or work not requiring Council approval, subject to the conditions set out in cl 48.1(c).
From 5 January 2024, Mr Rothner was entitled to carry out any works, by way of alterations or additions to the Property, as were either approved by a Development Consent or work not requiring Council approval, subject to the conditions in cl 49.1(c).
Turning now to the text of cl 50.1, a reasonable person in the position of the parties would regard the clause as firstly imposing an obligation on Mr Waterhouse to consent to the lodgement by Mr Rothner of a development application or application to vary a development application to Council. Second, Mr Waterhouse must sign all such applications, plans and consents as may be reasonably required by Mr Rothner.
The obvious grammatical meaning of the words used is that it is the requirement of Mr Rothner to obtain Mr Waterhouse’s signature on the relevant documents, which must also be reasonable. The clause does not direct attention to Mr Waterhouse’s position. It invites attention to whether Mr Rothner’s requirement for Mr Waterhouse to sign, is reasonable.
The critical issue is what is meant by the words “and will sign all such applications plans and consents”. The ordinary grammatical meaning of those words in context is to impose a separate obligation on Mr Waterhouse to sign all such applications, plans and consents as may be reasonably required by Mr Rothner in connection with a Development Application. The obligation is separate from simply consenting to the lodgement of a Development Application or application to vary a Development Application. This is made clear by the word “and”. It is also clear when construed against the agreed background of some development approvals already having been granted at the time of the Contract.
The CC Application Form would, in my view, clearly fall within that separate aspect of the clause. To contend, as I understood Mr Waterhouse to contend, that cl 50.1 only required consent to lodgement of a Development Application or an application to vary a Development Application, would rob those additional words of any work to do. Those additional words clearly have work to do in circumstances where, at the time of Contract, development approval had already been granted for some works and Mr Rothner was clearly permitted to do those approved works.
In any event, cl 50.1 is only part of the contractual picture. The Contract imposed an implied obligation on each party to do all that was reasonably necessary to secure performance of the Contract: see Secured Income Real Estate *(Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596; [1979] HCA 51 at 607 per Mason J. As Griffith CJ said in Butt v M’*Donald (1896) 7 QLJ 68 at 70-71:
It is a general rule applicable to every contract that each party agrees, by implication, to do all such things as are necessary on his part to enable the other party to have the benefit of the contract.
The Contract permits, post 5 January 2024, Mr Rothner to carry out works to the Property as are approved by a Development Consent. If, in order to do this, Mr Rothner requires Mr Waterhouse’s consent as the owner of the Property, then, at the very least, the implied obligation would require Mr Waterhouse to give his consent. This requirement would perhaps be qualified by an element of reasonableness in the sense that he would not be required to consent if, it would be unreasonable to require him to do so. There was no suggestion, and nor could there be, that an owner of land such as Mr Waterhouse, would not, post the grant of development consent, be required to give any further consent to working being carried out on their land. Put another way, there was no suggestion that the parties should be taken to have contracted on the basis that Mr Waterhouse had no further role, post the grant of development consent, to Mr Rothner doing the works that Mr Waterhouse contractually agreed he could do. (These observations are also equally relevant, in my view, to the construction of cl. 50.1 addressed above.)
I now turn to consider whether Mr Waterhouse’s failure to sign the construction certificate form was a breach of contract – either cl 50.1 or the implied duty to cooperate.
As set out above, the requirement of reasonableness in cl 50.1 is whether it was reasonable for Mr Rothner to require the document to be signed. This is the focus of the inquiry. The inquiry under cl 50.1 is not whether it was reasonable for Mr Waterhouse to sign the documents provided to him. That is not the ordinary meaning of the words used by the parties in the clause.
Further, I accept Mr Rothner’s contention that the question of compliance with cl 50.1 is to be assessed at the time that the relevant request is made by Mr Rothner. It is not to be assessed by subsequent events.
Mr Waterhouse contends that it was reasonable for him not to sign the documents submitted because Mr Rothner had agreed with Mr Waterhouse and Westpac that he would not cause Mr Waterhouse to breach the terms of the first mortgage.
It is clear that the Contract contemplated Mr Rothner taking a second registered mortgage over the Property. The Contract included the terms of a proposed Second Mortgage. The Contract also included a proposed letter from Westpac to Mr Rothner in the following terms:
The provision of a letter in substantially these terms was a condition of Mr Waterhouse obtaining a release of the deposit monies paid by Mr Rothner under the Contract (see cl 43.2).
Clause 10 of the proposed Second Mortgage, which was in the same terms in the Second Mortgage as executed and registered on title, was in the following terms:
The parties acknowledge that the within Mortgage shall be a second Mortgage security as a first Mortgage security has been granted by the Mortgagor to Westpac Banking Corporation securing an amount not exceeding $12,000,000.00 (the “First Mortgage”). The Mortgagor agrees that a default in the observance or performance by the Mortgagor under the First Mortgage shall be deemed to constitute a default under the within Mortgage and shall entitle the Mortgagee to exercise its rights, powers and remedies herein provided for, in the event of a default. The Mortgagor covenants with the Mortgagee that the Mortgagor shall not increase the sum secured by the First Mortgage without the written consent of the Mortgagee hereunder, which consent may be granted or refused in the absolute discretion of the Mortgagee.
The clause provides that a breach of the mortgage with Westpac would also be a breach of the Second Mortgage, entitling Mr Rothner to exercise his rights as mortgagee under the Second Mortgage.
As set out earlier in these reasons, Westpac issued a letter to Mr Rothner dated 31 July 2023 in the following terms:
Regarding your purchase of 6 Tivoli Avenue ROSE BAY NSW 2029 from Mr David Richard Charles Waterhouse, we confirm that Mr Waterhouse is a customer of the Bank and that the Bank currently holds a mortgage (the Mortgage) over the above property (the Property). We understand you have or will enter into a contract to purchase the property from Mr Waterhouse.
At the request of Mr Waterhouse, we confirm to you that:
- The outstanding balance of the loan secured by the Mortgage does not currently exceed $14.1m.
- That on receipt of the full 10% deposit of the purchase price ($2.575m), Westpac agrees to reduce the limit of the relevant loan to $12,000,000.
- Westpac consents to you registering a second mortgage behind our first registered mortgage. This will further be supported by an agreed Letter of Priority which will limit our prior interest to $12m (plus fees and interest).
- The Bank undertakes to discharge our first registered mortgage once all monies owing under the mortgage have been paid.
A reminder that all other conditions under the first registered mortgage would otherwise continue to apply.
In my view, it is impossible to tease out of this material, a tripartite agreement between Mr Waterhouse, Mr Rothner and Westpac whereby Mr Rothner agreed that he would not cause Mr Waterhouse to breach the terms of the mortgage with Westpac. There was also no agreement to this effect between Mr Waterhouse and Mr Rothner. There was no such promise by Mr Rothner to either.
I accept, however, that the matters set out above, are matters that may, depending on the circumstances, be relevant to a determination of whether any requirement of Mr Rothner for Mr Waterhouse to sign a document was a reasonable one.
The first request to sign the CC Application Form was made by letter dated 31 January 2024. I have traced what occurred thereafter in the chronological factual section of these reasons above. The salient points may be summarised as follows:
(a) correspondence between the solicitors for Mr Waterhouse and Mr Rothner ensued; (b) Mr Rothner wrote to Mr Drake at Westpac, seeking Westpac’s support for the work. He set out the details of what he proposed to do; (c) Mr Drake wrote to Mr Rothner on 27 February 2024 saying he was comfortable for those works to proceed. Mr Drake forwarded his response to Mr Waterhouse by separate email; (d) Mr Waterhouse did not react positively to this development and sent a series of emails to Mr Drake contending that the works were far greater than Mr Rothner proposed and that Westpac had no right to approve them; (e) Mr Drake told Mr Rothner that he had discussed the matter with Mr Waterhouse who had provided him with a copy of the plans and that the work seemed greater than that set out in Mr Rothner’s email such that a formal submission to credit would definitely be required. Mr Rothner responded to the effect as was set out in his original email – he would not be activating the Attic part of the DA; (f) Mr Drake then told Mr Waterhouse he would not be communicating with Mr Rothner without Mr Waterhouse’s express confirmation; (g) solicitor correspondence was then exchanged with Mr Waterhouse’s solicitor referring to the fact that Westpac was not consenting, but that Mr Waterhouse was in the process of refinancing with Bank of Singapore who may be less stringent than Westpac; (h) a further request was then made by letter dated 7 March 2024 because a new certifier had to be appointed. Mr Waterhouse’s solicitors immediately responded, not giving consent and continuing to refer to a proposed refinance with the Bank of Singapore who Mr Waterhouse believed would be far less stringent on giving ongoing approvals for the proposed building work; and (i) on 1 July 2024, a further request was made and again on 27 September 2024. Mr Waterhouse’s solicitors responded on 29 September 2024, relevantly to the effect that Mr Waterhouse could not consent as he would be in default under his mortgage with Westpac.
Mr Waterhouse’s refusal to sign the CC Application Form was, in my view, a breach of both cl 50.1 and the implied duty to cooperate.
It may be accepted that Mr Rothner could only reasonably require Mr Waterhouse to sign a document relevant to work which Westpac had approved. Mr Rothner appears to have been proceeding on that basis in writing to Mr Drake in early February (immediately after Mr Rothner had provided the CC Application Form to Mr Waterhouse) seeking Westpac’s support for the work being carried out. (He had also written to Westpac post Contract seeking Westpac’s approval to work.)
Westpac then provided its support. True it is that this was on the basis of what Mr Rothner had told them was the work he was planning to carry out to the house. I am satisfied, however, that this is what Mr Rothner was in fact planning to do at the time. I accept that he did not intend to activate the Attic part of the Main House DA.
Mr Waterhouse should have signed the CC Application Form at this time. Instead, he persuaded Westpac to withdraw its support on the basis that the work was for greater work than what Mr Rothner was intending. He then refused to provide consent to Mr Rothner and brought into the equation Mr Rothner consenting to Mr Waterhouse refinancing with Bank of Singapore on the basis that they would be less stringent than Westpac in terms of approving building works. This was all to achieve a better financial outcome for Mr Waterhouse in the form of a lower interest rate on his substantial debt. Another alternative, again to Mr Waterhouse’s financial advantage, was for Mr Rothner to settle early.
None of this conduct assists Mr Waterhouse. If, contrary to what I have held above, cl 50.1 does involve an inquiry into the reasonableness of Mr Waterhouse’s conduct in refusing consent, I am comfortably satisfied that his refusal was unreasonable when looked at from Mr Waterhouse’s perspective. He was motivated by seeking to exert pressure to bring about a better financial outcome for himself. He overstated Westpac’s position. None of this was reasonable.
I also do not accept Mr Waterhouse’s contentions concerning the lack of any insurance required under cl 49.7 as providing a basis for him to refuse to provide consent.
The correspondence set out earlier in these reasons does not reveal Mr Waterhouse relying on the lack of insurance as a reason for refusing consent at the time. In fact, in relation to the consent provided for the garage works, Mr Waterhouse’s solicitor in his covering letter dated 15 March 2024, purported to include as one of the conditions of consent that evidence of the builders insurance is to be provided prior to any work commencing.
Clause 49.7 provides:
The purchaser shall keep the vendor indemnified against any claims or liabilities for damage, loss, or injury which may occur to the property, the improvements to the property or any person or persons who enter upon or near the property in respect of which indemnity the purchaser is required to take out such insurance as the vendor deems reasonable, including but not limited to, public risk insurance for not less than $20,000,000.00. Evidence of the currency of the insurance policies shall be provided to the vendor and such insurances are to be maintained until completion of this contract at the cost of the purchaser.
I am not satisfied that the obtaining of insurance as required under cl 49.7 is a condition precedent to Mr Waterhouse being required to consent or sign a document under cl 50.1. There is nothing in the text, context or purpose of these provisions that commands such an outcome.
Mr Rothner gave evidence that he had been advised by his broker not to waste time or money getting insurance in relation to the building works until he commenced construction. I accept this evidence and accept that Mr Rothner would have obtained the necessary insurance prior to the work commencing. There is nothing unreasonable in adopting such an approach. It is precisely the approach which Mr Waterhouse sought to impose as a condition of his consent to the Garage Works being carried out.
A suggestion was also made by Mr Waterhouse in oral closing address that insurance was required before the CC Application Form could be lodged with Council. Whether that was in fact correct was not, in my view, proved by Mr Waterhouse. In any event, if it was required, that was a matter for Mr Rothner to satisfy. It was not a matter which, in my view, entitled Mr Waterhouse not to sign the CC Application Form.
For these reasons, I am satisfied that Mr Waterhouse breached both cl 50.1 and the implied duty to cooperate.
Mr Rothner contends that if Mr Waterhouse had signed the CC Application Form in respect of the main house, he would have commenced works on the main house immediately. His claim is for increased holding costs because he has not been able to carry out the work until after he has completed on the purchase, and for increased construction costs.
The first issue to consider is one of causation – whether I am satisfied that if Mr Waterhouse had signed the CC Application Form, Mr Rothner would have commenced works on the main house almost immediately. A second aspect of the causation inquiry is whether I am satisfied that Mr Rothner still intends to carry out the works to the house and then to sell the Property.
For the reasons set out below, I do not accept that had Mr Waterhouse signed the CC Application Form, Mr Rothner would have immediately commenced works on the main house.
The starting point is the evidence given by Mr Rothner in support of this aspect of the claim. In his affidavit made 27 November 2024, Mr Rothner gave the following evidence:
54 I intend to finance the purchase of the Property through a secured loan. As at the time of making this affidavit, I have not arranged a facility to borrow this money. However, I anticipate that I will be able to borrow the necessary funds at an interest rate of around 10%. I hold that belief based on my professional experience. I have worked at Ashe Morgan for over 35 years, which is a commercial real estate investment management firm. I am currently a Principal of that firm. In that role I lead investor relations, funds management and joint ventures. As part of those roles I have extensive experience and knowledge in the operation of debt markets, and in particular the cost of obtaining finance for real estate purchases.
55 As at the date of making this affidavit, the following DAs have been approved in respect of the Property:
a. Main house: DA518/2021/1, approved on 23 December 2021, in respect of the main house. A copy of these approved plans is at Tab 19 of Exhibit MCR-1.
b. Garage and studio: DA795/2006/5, in respect of the garage and studio. An amendment to these plans was approved on 16 January 2024. A copy of these approved plans, as amended, is at Tab 2 of Exhibit MCR-1. This consent is the subject of the LEC Proceedings.
56 The relevant DAs which I have sent to Mr Waterhouse for him to sign the corresponding application form so that I can seek consent are as follows:
a. Garage and studio: Plans for a further proposed modification to DA795/2006/5 in respect of the garage and studio. I have sent two sets of these plans to Mr Waterhouse. The first were sent to him on 31 January 2024. Those plans are dated 17 October 2023 and are at Tab 2 of Exhibit MCR-1 **(**October 2023 Garage/Studio Plans). The second set were sent to him in July 2024. Those planed are dated 25 June 2024 and are at Tab 17 of Exhibit MCR-1 (June 2024 Garage/Studio Plans).
b. Pool and wellness centre: I have also relevantly sent Mr Waterhouse three sets of plans for a proposed pool and wellness centre. The full set of plans were sent to Mr Waterhouse in September 2024 and are stamped with issue date 23 September 2024, revision B (September 2024 Wellness Centre Plans). A copy of these plans is at Tab 33 of Exhibit MCR-2. These plans superseded the ones I sent to him in July 2024. I had previously sent to Mr Waterhouse a more confined set of plans for the wellness centre in January 2024. These plans were dated 21 November 2023, and a copy of these plans is at Tab 2 of Exhibit MCR-1 (November 2023 Wellness Centre Plans).
57 If Mr Waterhouse had signed the proposed DAs and application forms when I sent them to him, and those applications were approved, I would have taken the following course of action:
a. If the proposed plans for the garage/studio were approved, I would have commenced those works immediately. At the same time, I would have commenced the works on the main house which had already been approved. My preference was to renovate the garage/studio in accordance with the October 2023 Garage/Studio Plans. However if the LEC Proceedings found that the existing garage/studio DA was invalid, then I would have instead submitted the June 2024 Garage/Studio Plans for approval and carried out the works in accordance with those plans.
b. My preference is, and always has been, to renovate the main house and the garage/studio at the same time. I understood that the garage/studio works would have taken about six months to complete from commencement. I would have performed as much of the preparatory works on the main house as possible while the garage/studio works were being undertaken, and then started the substantive works on the main house as the garage/studio works neared completion. I planned to perform the works in this manner because I considered it was likely to be cheaper than performing those works separately.
c. As I have explained above at paragraph 14, I was concerned that in respect of the approved DA for the main house, the plans for the roof were compromised because the top floor living spaces were too small. For that reason my intention was that if I got permission to carry out the approved works in respect of the main house, I would have carried out those works except for the part of the approved works which would result in changes to the roof space. I also would have carried out the works to change the interior design of the house in accordance with the plans I have referred to at paragraph 40.
d. If the proposed amendments to the garage/studio were not approved by the Council, then I would have proceeded with the works on the main house on their own (other than the changes to the roof).
e. If the proposed plans and works for the wellness centre were approved, I then would have considered whether to proceed with its construction. I would have considered the cost of the wellness centre works before deciding whether to proceed with them. If Mr Waterhouse signed the September 2024 Wellness Centre Plans, I would have submitted those plans for approval. If those plans were not accepted, then as a fallback I would have submitted and sought to rely on the November 2023 Wellness Centre Plans.
58 Once the works were done, I would have considered selling the Property. One of the principal reasons why I wanted an extended settlement period under the Contract was so that I could complete the works before the completion date. I then would have had the optionality of either settling or selling the Property at completion.
However if it was not possible to perform the garage/studio works, or if there was a delay in getting approval to carry out the works on the garage/studio, then I would have carried out the works on the main house on their own.
In a subsequent paragraph of this affidavit, he referenced the Land and Environment Court proceedings commenced by the Huangs and said that if those proceedings meant that he was not able to carry out the works on the garage/studio, or delayed him in being able to carry out those works, then he would have carried out the works on the main house on their own.
It is to be remembered that until shortly prior to the commencement of the hearing in November 2025, Mr Rothner’s cross-claim involved not only the works to the main house, but also the garage works and the pool and wellness centre.
Shortly prior to the hearing, the claims in relation to the garage works and the pool and wellness centre were dropped.
Mr Rothner’s evidence (at least in his November 2024 affidavit) was prepared in the context of the expanded claim. That affidavit evidence did not directly address the claim ultimately run – confined only to whether Mr Rothner would have immediately commenced works to the main house if Mr Waterhouse signed the CC Application Form.
Mr Rothner’s affidavit evidence expressly states that it was his preference to renovate the main house and the garage/studio at the same time. That evidence is consistent with the objective contemporaneous documents. Mr Rothner told Mr Drake of Westpac on several occasions in early 2024 that this was his intention.
The difficulty with this aspect of Mr Rothner’s claim is that progressing the garage works got derailed with the Land and Environment Court proceedings commenced by the Huangs on 10 April 2024. This derailment obviously cannot be laid at the feet of Mr Waterhouse. Mr Rothner became aware of these proceedings shortly after they were commenced. He was obviously aware that this would significantly delay his ability to do the works to the garage.
There is then no reliable material placed before the Court by Mr Rothner to persuade me that, once the garage works became stalled by the Land and Environment Court proceedings, it was Mr Rothner’s plan to proceed with the works to the main house. I accept that while Mr Rothner gave quite general evidence in cross-examination that Ms Ongaro was speaking to builders and obtaining quotes, no objective material was put before the Court to give content and substance to the general statements made by Mr Rothner.
This is a matter on which Mr Rothner bears the onus and, the evidence to prove these matters is clearly within his power to produce. I have also found Mr Rothner to be an unsatisfactory witness in a number of respects. This cautions me against simply accepting his uncorroborated general evidence in the witness box.
There is no evidence that any builder had been retained, or even a short list of builders or any evidence of any quotes for the work to be carried out. Similarly, there is no evidence as to how Mr Rothner was going to pay for the works. Whilst he told Mr Drake that he was paying for it out of his own funds, there is no evidence that he had the funds available to carry out the works at the time.
Consistent with what he said in his 27 November 2024 affidavit, Mr Rothner was likely waiting for the position to become clear in relation to the Garage DA, before proceeding with any works.
I turn now to consider the second aspect of the causation inquiry, namely whether I am satisfied that Mr Rothner still intends to carry out the works to the main house and then sell the Property. In light of my conclusion on the first aspect of the causation inquiry, it is strictly not necessary to move to the second part, but I address it against the possibility that I am wrong on the first aspect.
The position in this regard has some factual complexity to it, including by reason of the documents tendered by Mr Rothner on the application to reopen.
The evidence adduced by Mr Rothner during the hearing in November 2025 was that on 8 September 2025 he accepted a letter of offer dated 28 August 2025 from Pallas Capital in respect of a First Mortgage Investment Facility with a limit of $24,700,000 which is repayable over a period of 18 months at an interest rate of 8.5% per annum (Pallas Capital Facility). He anticipated drawing down on that facility in the amount of $20,600,000 being the balance payable to Mr Waterhouse on the completion of the Contract.
Mr Rothner also admitted that he would have to pay stamp duty of around $2 million prior to completion. This was also apparently to be funded from the Pallas Capital Facility. Mr Rothner said in cross examination that he would use the remaining funds from the Pallas Capital Facility for the works to the main house.
Post completion of the Contract, both sides applied to reopen. Having heard argument on the application I determined to permit the following documents to be tendered:
(a) the PEXA settlement statement; and (b) a document or documents evidencing the terms on which Mr Rothner borrowed funds from the NAB to enable him to settle on the purchase of the Property.
(a) The NAB offer letter. The amount of credit offered is $21,450,000 on a loan term of 30 years, with an interest only period of two years; (b) article titled “Change to NAB home loan rate” dated 3 February 2026 advising that NAB’s standard variable home loan interest rate will rise by 0.25% per annum from 13 February 2026; (c) article entitled “NAB announce change to home loan interest rates” dated 17 March 2026 advising that NAB will increase its home loan variable interest rates by 0.25% per annum, with the changes to come into effect on 27 March 2016; (d) document titled “INDICATOR RATES FOR NAB HOME LENDING” dated 27 April 2026; and (e) the NAB Transaction Statement, showing a loan drawdown of $21,449,472.90 on 17 December 2025, the date of completion.
The PEXA statement revealed that the funds to enable Mr Rothner to complete were provided by the NAB, not Pallas Capital. The additional documents tendered included the NAB offer letter to Mr Rothner for a 30 year loan for $21,450,000 dated 27 October 2025. The NAB Transaction Statement showed that the full amount of the loan was drawn down on 17 December 2025, being the date on which completion occurred.
Two further observations should be made.
First, Mr Rothner referred to the Pallas Capital Facility in an affidavit made 7 November 2025 and was cross-examined on 17 and 18 November 2025 in relation to it. He gave evidence that the conditions precedent in the Pallas Capital Facility had already been satisfied, at least implicitly suggesting the offer had been accepted. The NAB offer letter is dated 27 October 2025. No reference was made to the NAB offer letter prior to the application to reopen.
Second, during argument on the application to reopen, senior counsel for Mr Rothner accepted that what should be tendered was the loan agreement between Mr Rothner and the NAB which was a different and later document than the NAB offer letter. (Mr Rothner also opposed Mr Waterhouse’s contention that the NAB offer letter should be tendered as it went to Mr Rothner’s credit.) No such loan agreement was tendered, and no real explanation was provided as to why not. The NAB offer letter tendered is not signed by Mr Rothner so as to accept the offer.
On the material presently before me, I am not satisfied that Mr Rothner proposes to carry out the works to the house. This is for the simple reason that there is no evidence as to how he is going to pay for the works. The works are expected to cost at least several hundred thousand dollars. Mr Rothner has just drawn down on a loan of $21,450,000 to pay the entirety of the balance due on completion. There is no evidence of what financial resources, if any, he has available to pay for the works. The previously identified source – the remaining funds under the Pallas Capital Facility – are no longer available.
Again, this is a matter on which Mr Rothner bears the onus and has the capacity to adduce evidence to prove it.
The 30 year term of the NAB loan also casts some doubt on whether it remains Mr Rothner’s intention to sell the Property in the near future having renovated it, or whether he intends to hold it long term as a family home.
The 18 month term of the Pallas Capital Facility together with part of that facility being available to be used to pay for the works to the main house, was consistent with Mr Rothner having some intention to renovate and sell, but that facility was not taken up.
In my view, Mr Rothner will likely sell the Property when he considers it to his financial advantage to do so.
I turn now to quantification. I address it against the prospect that I am wrong on causation.
There are two aspects – holding costs and increased construction costs.
Mr Rothner called Mr Madden, a quantity surveyor to prove the time that it would take for the works to the main house to be completed and what the increased construction costs would be. His evidence was that the work would take nine months. The likely increase in construction costs was estimated to be $68,225, being the difference between $1,181,719 and $1,249,944.
Mr Madden was cross-examined. He was shown the CC Application Form sent on 31 January 2024. He accepted that this form was referring to a later version of the development application than he had been instructed in relation to. He also agreed he had not been provided with the application or the detail of the work described in it.
He was also shown the email from Ms Ongaro (on behalf of Mr Rothner) to Mr Drake on 7 February 2024 setting out the work that Mr Rothner proposed to do to the main house and the estimated cost of $250,000 to $350,000. He agreed he had not seen that document before. The position was the same in relation to the CC Application Form sent on 6 March 2024.
Finally, he agreed in cross-examination that he was not aware of whether Mr Rothner intended to carry out the works that he had costed in his report.
Having regard to the totality of Mr Madden’s evidence, I am not satisfied that the work that he has costed and estimated as to time, bears even a close resemblance to what Mr Rothner was or is planning on doing such that I can place any real reliance on Mr Madden’s evidence.
There are significant differences between the contemporaneous documents and Mr Madden’s estimates, both as to cost and time to complete. No real explanation was provided to explain the discrepancies. Mr Madden offered the explanation that there may have been work being done that was not being done under a DA. That was pure speculation on his part. I cannot reliably estimate any likely increase in construction costs on the evidence.
In terms of time to do the work to the main house, the task is complicated by the lack of clarity as to the work that will be done. The most reliable estimate is from Ms Ongaro’s email to Mr Drake, being 12 to 16 weeks, say 14 weeks.
Another aspect of the holding cost claim is the time to sell the Property. Mr Rothner called expert evidence from Mr Rubinstein a well-known real estate agent in the eastern suburbs. His opinion was that for a home of this nature he expects there would be a period of 9 to 12 months between him being engaged to market and sell the Property and completion. In cross-examination, Mr Rubinstein gave evidence that for a property in the eastern suburbs in the $20 to $40 million range, it may, on average, take six months to sell. The question was not asked, however, as a direct challenge to Mr Rubinstein’s opinion of 9 to 12 months for the Property in his report.
I adopt the period of 9 months.
When this period is added to the 12 to 16 week construction period – say 14 weeks – the delay period would be one year and two weeks, say one year.
In terms of the rate of interest being paid by Mr Rothner, I am satisfied that the NAB offer letter sets out the terms on which Mr Rothner has borrowed funds for the purchase and the subsequent documents tendered prove the increases in rates.
The evidence is, however, far from satisfactory. On the application to reopen it was accepted by senior counsel for Mr Rothner that the NAB offer letter would have been superseded by a loan agreement between the NAB and Mr Rothner and that it was the loan agreement that should be, and would be, tendered. The loan agreement was not tendered and no explanation was proffered or sought to be proffered as to why not.
Mr Waterhouse contended that the failure of Mr Rothner to meet the expectation that he would tender the loan agreement has resulted in a catastrophic denial of natural justice to Mr Waterhouse because he ought to have been entitled to test Mr Rothner’s case by reference to Mr Rothner’s contract with the NAB. I do not accept this contention. The issue is whether Mr Rothner has proved the terms on which he borrowed the funds. He has sought to do this by tendering only the offer and a transaction history showing the funds drawn down, together with two documents showing an increase in the rates.
The NAB offer letter is consistent with the transaction history, as to the amount of the loan. The offer letter is, obviously enough, an offer capable of acceptance. The transaction history and PEXA statement evidence NAB providing the funds – the inference being the NAB offer letter was accepted by Mr Rothner.
The NAB Home Loan Rate Announcements indicate the increases in the interest rate being paid.
It follows from this material that Mr Rothner made interest payments at 5.99% in December 2025 and January 2026 at a rate of 6.24% in February and March 2026, and at a rate of 6.49% from April 2026 onwards.
For the 12 month period I have determined above, the holding cost would be $1,313,256.08.
The uncontradicted evidence of Mr Gibbons as to the circumstances concerning the removal of the trees in early April 2024 clearly establishes that Mrs Rothner and Mr Shahwan were responsible for the removal of those trees. There is also the further evidence of communications between Mrs Rothner and Mr Shahwan concerning the cutting of trees.
The evidence comfortably satisfies me that Mrs Rothner was the architect of the removal of the trees on No 8 and Mr Shahwan was the person who actually carried out the removal of those trees.
It is appropriate to make the declarations sought by Mr Waterhouse in this respect – being paragraphs 4,5,8 and 9 of the relief set out in the second further amended statement of claim.
Neither of the chief protagonists – Mr Waterhouse and Mr Rothner – have fared well in this litigation. Neither has come out a real winner, and I have made adverse credit findings in relation to each.
I will give the parties an opportunity to consider these reasons and seek to agree orders to give effect to them, including as to costs.
Given the terms of her submitting appearance, Mrs Rothner’s legal representatives should be part of the conferral as to costs. Mr Shahwan should also be part of the conferral if he wishes to participate, or at least he should be provided with the orders sought against him and invited to indicate his position in relation to those orders.
If agreement cannot be reached, I will receive submissions and determine any remaining issues on the papers.
The Court makes the following orders:
The parties are to confer to seek to agree on orders in accordance with these reasons and provide any agreed orders to my Associate by no later than 20 August 2026.
In the event that agreement cannot be reached, the parties are to each provide to my Associate, by no later than 20 August 2026, the orders for which they contend, together with submissions in support of those orders of no more than five pages.
Any submissions in reply, of no more than three pages, are to be provided to my Associate by no later than 27 August 2026, upon which I will determine the remaining issues on the papers.
**********
Correction to front sheet
[1938] HCA 34
[2026] NSWSC 600
[2012] WASC 285
(2017) 324 FLR 378
(2024) 419 ALR 552
(1938) 60 CLR 336
(2011) 82 NSWLR 420
(2019) 58 VR 393
(2015) 329 ALR 1
(1985) 157 CLR 17
(2000) 200 CLR 121
(1979) 144 CLR 596
(2020) 105 NSWLR 325
(2023) 112 NSWLR 29
(1961) 105 CLR 569
(2014) 251 CLR 640
(2015) 256 CLR 104
(2013) 85 NSWLR 1
(2016) 93 NSWLR 561
(1990) 21 NSWLR 689
(2004) 218 CLR 530
(1983) 152 CLR 406
(1983) 153 CLR 438
(2003) 217 CLR 315
(1976) 137 CLR 177