5 In order to determine whether in the present case the underlying presumption should be displaced, it is necessary to have regard to the circumstances of this particular case, which may be best summarised by reference to the following chronology of events.
6 On 24 June 2004, the Land and Environment Court granted development consent for the erection of 11 interconnected residential buildings, a café/mixed business, basement car parking, associated site works, demolition of all remnant structures and remediation of contamination at Nos. 10-16 Marque Street, Rhodes (the "site").
7 On 10 March 2005, the Minister issued Emergency Order No.15 (the "order") under s 121B of the Environmental Planning and Assessment Act 1979 (NSW) (the "EP&A Act") to restrain Statewide from carrying out works contrary to the conditions of the consent
8 On 18 March 2005, Ms Elisabeth Wild, on behalf of Statewide, wrote to the Minister stating that the applicant had satisfied the terms of the order in full. She further stated that Statewide was incurring daily holding costs of approximately $27,000 due to the order, and as such, Statewide reserved the right to appeal against the order and seek compensation under s 121ZL of the EP&A Act if the order was not lifted.
9 On 22 March 2005, at the request of Ms Susan Budd, acting for the Minister, Ms Wild again wrote to the Minister formally stating that Statewide had complied with the order and attaching documents in support of this contention.
10 On 24 March 2005, following an inspection of the works by Mr John Sparkes, on behalf of the Minister, Ms Budd telephoned Ms Wild, and confirmed that the Minister was satisfied that the terms of the order had been satisfied. Ms Budd prepared a file note in relation to this telephone conversation which states that she informed Ms Wild that the Minister would agree to lift the emergency order on an undertaking that no further works be carried out until an application for modification of the development consent under s 96 of the EP&A Act was approved. The Minister did not, however, take any further steps to formally revoke the order.
11 On 5 April 2005, Mr Mark Beaufoy, acting for Statewide, informed the Minister that he was instructed to file an appeal against the order pursuant to s 121ZK of the EP&A Act and seek compensation under s 121ZL of that Act, for expenses incurred by Statewide as a consequence of the refusal of the Minister to lift the order.
12 On 6 April 2005, pursuant to s 121ZK of the EP&A Act, Statewide commenced the foreshadowed Class 1 appeal the subject of this costs application.
13 On Friday 8 April, Statewide filed a notice of motion requesting that the hearing of the appeal be expedited. The motion was subsequently listed for hearing on 14 April 2005.
14 In response, at approximately 5pm on the same day, Ms Budd faxed a letter to Statewide stating that, notwithstanding that no undertaking had been given by Statewide, the Minister was satisfied that the terms of the order had been satisfied and agreed that the order should be lifted. In addition, however, the Minister required Statewide to give an undertaking by 5pm Monday 11 April 2005:
(1) that Statewide will ensure future Stage 2 remediation works comply with the conditions of consent DA-298-08-2002-I; and
(2) that Statewide Developments agrees not to undertake any further remediation work unless and until:
a. All conditions of development consent which require fulfilment prior to the commencement of remediation works have been complied with to the satisfaction of the Department; and
b. Where the conditions of development consent cannot be complied with because of the manner in which excavation and remediation works have been conducted to date, the development consent is modified under s 96 of the EP&A Act so as to ensure future works are in accordance with the consent.
15 On 11 April 2005, in response to a request from Statewide, the Minister extended the time for giving the undertakings until 5pm Tuesday 12 April 2005 given that the applicant: