"For buildings which have an occupation certificate but are defective in fire safety, council's only legal recourse is to issue a fire order against the current owners of the building. The owners would need their own legal advice on any issue of obtaining compensation from the original builder or developer".
11 As the court file indicates, and all parties at the bar table have conceded, there were lengthy periods of time when all that happened in relation to the litigation were appearances before the court as the respective parties, slowly but surely as events transpired, managed to work their way into a successful resolution to the problems. Apparently there were no substantive steps taken in the conduct of the proceedings from the Meriton joinder and to use the council's term, "the plaintiff essentially parked the present proceedings against the council from that point in time".
12 The council has contended that the purpose desired by the plaintiffs was achieved solely through the Meriton proceedings. The proposition which has come forward from the council is that the plaintiffs were not justified in commencing the proceedings against the defendant and that it cannot be said that this has become obvious only with the benefit of hindsight. The council's proposition is that no measures were taken by the plaintiffs to determine whether it was reasonably necessary to commence the proceedings against the council. The proposition is that there is no evidence of any communications with Meriton before either these proceedings or Meriton proceedings were commenced. Either the proceedings against the council or the Meriton proceedings were commenced.
13 The council contends that had the issue of defects been raised with Meriton, prior to the commencement of the proceedings, Meriton may well have, and it could reasonably be presumed, would have taken the same approach that it took shortly after the proceedings were commenced against it, ie agreeing without prejudice to its liability to carry out the rectification work.
14 The council's submissions in relation to it having acted reasonably, were that it did act reasonably in denying that it was obliged or able to inspect concealed fire safety works for the purpose of issuing any final occupation certificate. The council's proposition is that it is hardly surprising that the plaintiffs then looked to Meriton to rectify the defects in the building and took no further substantive steps to prosecute the proceedings against the council. The council contends that the plaintiff's only real complaint in relation to the defendant's conduct of the proceedings, is that the defendant is said to have delayed serving the notice under item 6 of s 121B of the EPA Act.
15 The council has contended that its conduct in issuing the notice and order under s 121B constitutes essentially an irrelevant consideration but that in any event it undertook those statutory functions with both care and reasonable haste. The council has contended that the notice and order were issued pursuant to the defendant's statutory functions under the Act and were issued entirely independently of the proceedings.
16 As the council has contended, the proceedings did not seek any relief relating to the issue of any notice or order under s 121B. The council's proposition is that it is not therefore a relevant consideration going to whether or not a defendant acted reasonably in defending the proceedings that it ultimately issued the notice. Further, the council contends that in any event there is no factual basis to the plaintiff's contention because the council asserts that it acted in a timely manner in the issue of the notice and order under s 121B.
17 As the council has indicated in its submissions, the evidence bears out that the issue of such a notice was first raised with the defendant by a letter dated 5 November 2007. A notice of intention to give an order was then issued by the council on or about 28 December 2007. Prior to the issue of the notice, the defendant considered the plaintiff's draft programme for implementation of rectification works and inspected the building.
18 In the circumstances, it does seem to me that the issue of the notice did take place in a reasonably timely fashion. It is important to recognise in that regard that there is the potential for a s 121B order to expose the recipient to significant civil and criminal consequences and to cause undue hardship. (Care v Canterbury City Council (2001) 115 LGERA 252 at [25] per McEwen AJ; Statewide Developments Pty Ltd v Minister for Infrastructure and Planning [2005] NSWLEC 353 at [26] per Lloyd J)
19 In those circumstances, it was obviously incumbent upon a public authority in the position of the council to consider carefully the issue of a s 121B order and any reports and representations made by the plaintiffs in relation to it. In all of the circumstances, notwithstanding the periods of time which elapsed before the 121B order finally emanated, it does seem to me that the defendant cannot be said to have acted more than reasonably and in a timely fashion in ultimately issuing the order under s 121B that it did.
20 After the issue of the notice of intention on or about 28 December 2007, the defendant, whilst still finalising the terms of the final s 121B order, gave permission for Meriton to commence rectification works on or about 15 April 2008. It seems that it was largely due to actions by the plaintiffs that resulted in the defendant's approval not being given earlier than 15 April 2008, which actions included: