55044 of 2007 METRO CHATSWOOD PTY LIMITED v CRI CHATSWOOD PTY LIMITED
JUDGMENT
1 The plaintiff, Metro Chatswood Pty Limited, commenced proceedings against the defendant, CRI Chatswood Pty Limited, by Summons filed on 14 June 2007. The plaintiff sought orders for preliminary discovery of documents in the Schedule to the Summons or alternatively an order that the defendant provide the documents in the Schedule to the Summons pursuant to its contractual obligations to the plaintiff. On 4 October 2007 I granted leave to the plaintiff to discontinue the proceedings and heard the parties' respective applications in relation to costs. Mr J Simpkins SC leading Mr J White appeared for the plaintiff and Mr R Carruthers appeared for the defendant.
2 On 22 September 2005 the plaintiff and the defendant entered into a Retail Development Agreement (the RDA) in respect of the construction of a large commercial complex at Chatswood near the rail line. The plaintiff, referred to in the RDA as the "Retail Purchaser", agreed to take a transfer of the "Retail Complex Lot" and to become the tenant under the "Retail Space Lease". The plaintiff agreed to the purchase pursuant to a Contract for the Sale of Land dated 9 January 2006. Under clause 4.2 of the RDA the defendant was obliged to provide to the plaintiff as soon as reasonably practicable information "relevant" to the "Retail Base Works, the Retail Complex Lot, the Retail Space Lease Lot or any other right or obligation" of the plaintiff under the RDA (cl 4.2(b)).
3 The "information" that the plaintiff claims was relevant related to cabling conduits through foundational slabs of concrete to accommodate Telstra cables. Prior to the commencement of construction a number of Telstra cables ran across the construction site. Discussions between Telstra and the defendant had been ongoing after the plaintiff and the defendant entered into the RDA and it was decided between Telstra and the defendant that one of the larger cables, "T4", would traverse the construction site rather than being relocated around the construction site. On 22 August 2006 at a meeting including representatives of the defendant and Telstra, the defendant's project manager, Lee Wood, is recorded as having "confirmed that easement will be undertaken at later date".
4 On 12 February 2007 the plaintiff wrote to the defendant requesting "full details for a proposal to divert Telstra cables within the Retail Stratum". On 13 February 2007 the defendant provided a "Design Report" to the plaintiff which included a paragraph on Telstra Cable Routes containing information about the Telstra cables that would be "impacted by the [construction] works". This report included the information that for the largest Telstra cable route a "combination of redirection and reinstatement across the site is required".
5 On 28 February 2007 the plaintiff wrote to the defendant requesting once again "details for the proposed Telstra cables traversing the Retail Space". On 19 March 2007 the defendant wrote to the plaintiff enclosing a drawing which the defendant claimed "may assist in your understanding of the route of the Telstra conduits across the site". The defendant advised that if the plaintiff had any queries it should not hesitate to contact the defendant. In response to the provision of this drawing, the plaintiff advised the defendant by letter dated 22 March 2007 that it would not accept "the provision of any major infrastructure services traversing through the Retail Complex" and that it required such facilities to be relocated outside any real estate that the plaintiff was acquiring. On 3 April 2007 the defendant advised the plaintiff by letter that the Telstra "conducts" were currently installed in Stage 1 and were encased into the concrete structure; that the installation of the "conducts" was a "requirement" of Telstra for future cable installation; and that the defendant was complying with the Authority's requirement.
6 On 4 April 2007 the plaintiff requested the defendant to provide all appropriate and relevant correspondence from Telstra indicating that the current specific proposed positioning of the conducts was being instigated as a "requirement of Telstra". On 24 April 2007 the defendant wrote to the plaintiff enclosing what it said it regarded as the "relevant portions" of a contract between it and Telstra relating to the T4 relocation. The Recitals to that contract recorded that the development required the relocation of the "Network Assets" to the relocated site.
7 On 8 May 2007 the plaintiff's solicitors wrote to the defendant advising that regardless of who instigated the "requirement", the defendant had no right to unilaterally require installation of infrastructure or easements over the land that the plaintiff was purchasing. That letter referred to the RDA provisions that set out the circumstances in which the draft section 88B instrument, the draft sub-division plans and the Retail Base Works could be changed. This was a reference to clause 6.2 of the RDA which required the defendant to submit any amendments to the plaintiff for its approval if the amendments related to or affected the plaintiff's rights under the RDA. The letter also included the following:
Our client is very concerned that works in relation to the Telstra conduits which have not been authorised by our client and which adversely affect the property which our client is acquiring are proceeding.
In the circumstances, we require that you confirm to us in writing by not later than 5.00 pm on 10 May 2007 that you will not take any further steps to authorise, permit, suffer or otherwise allow any further easements to be granted or any further conduits or telecommunications infrastructure which has not been expressly authorised by our client to be installed or placed on or within the property which our client is acquiring pursuant to the Retail Development Agreement (namely, the Retail Complex Lot or the Retail Space Lease Lot as defined in the Retail Development Agreement) and that within seven days of today's date you provide to us or to our client all information within your possession, knowledge or control in relation to any Telstra conduits or any other Telstra infrastructure placed or proposed to be placed within the aforesaid Retail Complex Lot or Retail Space Lease Lot other than expressly contemplated by the Retail Base Works (as defined in the Retail Development Agreement) or in the easements noted on the draft sub-division plans or referred to in the draft section 88B instrument.
8 On 14 May 2007 the defendant's solicitors wrote to the plaintiff's solicitors advising that the defendant regarded the Telstra requirement for the routing of the conduits as a requirement of an "Authority Approval". That term was defined in the RDA as any "licence, permit, consent, approval, determination, certificate or permission" from any authority and also referred to requirement made under any Law. There was at this stage of the communications between the plaintiff and the defendant a serious issue as to whether the Telstra "requirement" was firstly a requirement imposed by Telstra and secondly whether it could be characterised appropriately under the RDA as an "Authority Approval". This letter also advised the plaintiff that the drawing that the defendant had sent it on 19 March 2007 was no longer applicable because the conduits were contained wholly within the floor slabs and stairs. The solicitors also advised that the defendant took the view that any affectation from the conduits were only minor or immaterial and did not affect the Retail Base Works, thus preventing the plaintiff from making any claim against the defendant in respect of them. The letter also advised that the defendant had not yet determined whether any amendment was to be made to the Draft Registration Documents and that if, "and only if" the defendant determined that an amendment related to or affected the plaintiff's rights would it be in a position to submit the relevant amendment to the plaintiff. The solicitors said:
However, we note that the application of clause 6 has not yet arisen because no amendment to the Draft Registration Documents has been proposed, nor is the requirement for any amendment to those documents certain at this stage, in relation to this issue.
9 The solicitors advised that the defendant was not prepared to provide an undertaking but that it would continue to communicate with the plaintiff in accordance with the RDA.
10 This letter could hardly have allayed the plaintiff's concerns that the property it had agreed to purchase would be adversely affected by the conduits that were being laid across the construction site. The determination of whether an amendment to the Draft Registration Documents needed to be made depended in part on whether Telstra sought or "required" an easement for the conduits and/or the future access to the conduits. Although it may not have been "certain" at that stage that such an amendment was needed, the defendant had certainly been in communication with Telstra at monthly meetings requesting it to "confirm" whether an easement would be required for the conduits through the site. Also at this time the defendant knew that its project manager, Mr Wood, had advised Telstra that "an easement" would be "undertaken at a later date".
11 On 16 May 2007 the plaintiff's solicitors wrote to the defendant's solicitors claiming that "you have not advised whether Telstra will want an easement relating to the conduits or any ongoing rights of access to them". They advised that because the defendant had failed to provide the undertaking the plaintiff would issue proceedings. Notwithstanding this letter the plaintiff's new solicitors wrote to the defendant's solicitors on 25 May 2007 referring back to their predecessor's request for information in the letter of 8 May 2007. The letter of 25 May 2007 included the following:
Our client wishes to access and inspect the above information pursuant to its rights under the RDA. Our client is entitled to receive those documents pursuant to clause 4.2 of the RDA. To the extent that it becomes relevant for any subsequent proceedings, our client wishes to inspect these documents to form its own view as to the obligation upon your client to seek our client's consent in relation to the relevant work.
Our client repeats its previous request and requires that the following specific documents be provided to our client by 4.00 pm on Wednesday 30 May 2007:
1. Any information or documents concerning:
(a) the current progress of construction or installation of ; and
(b) any proposed future construction or installation of; and
(c) any proposed use of
any cabling conduits constructed, being constructed, or which may be constructed through the Retail Complex, Retail Complex Lots or Retail Base Works on the CTI site…
12 This letter also requested all proposed easement plans and documents identifying parties benefiting and burdened by any proposed relocation of the conduits. By 29 May 2007 the plaintiff's solicitors had not received a response from the defendant's solicitors and once again asked them for the information by letter of that date.
13 On 30 May 2007 the defendant's solicitors wrote to the plaintiff's solicitors providing an analysis of why the defendant claimed the Telstra "requirement" amounted to an Authority Approval under the RDA. It confirmed that the T4 cable conduit was contained wholly within concrete and stated that it "does not enter the retail stratum freehold or leasehold lot". That letter also included the following:
Our client is not aware of any other agreement, works or proposed easements for services provided by Telstra in relation to which an amendment to the Draft Registration Documents is proposed or required at this stage.
14 The letter responded to the plaintiff's solicitors' specific request in paragraph 1 of its letter of 25 May 2007 in the following terms:
1. Based upon its enquiries in the time available and as at the date of this letter, CRI is not aware of any documents or information relevant to this paragraph of your Specific Request other than as provided in this letter.
15 The defendant's solicitors letter of 30 May 2007 also advised that the defendant was not aware of "any proposed easement, plans or documents" relevant to the matters in paragraph 1 of the plaintiff's solicitors letter.
16 From the contents of the defendant's solicitors' letters it would appear that the defendant failed to instruct its solicitors that it had been discussing an easement with Telstra and was awaiting confirmation from Telstra in relation to its requirements for easements for the conduits. Throughout the period February to the end of May 2007 whilst the plaintiff and the defendant were corresponding in relation to the plaintiff's request for information, the defendant had attended a number of meetings with Telstra. A standing item on the agenda for the meetings of 5 February 2007, 20 February 2007, 6 March 2007 and 3 April 2007 was for Telstra to "confirm if any easement/tenure is required for T4 conduits through the site". The Minutes of the meeting of 19 June 2007 record that "Telstra easement requirements sent to CRI". It is fairly clear therefore that some time prior to 19 June 2007 Telstra had advised the defendant of its requirements for easements through the site.
17 On 13 June 2007 the plaintiff's solicitors advised the defendant's solicitors that as the defendant had failed to provide the requested information they had been instructed to commence proceedings for preliminary discovery. On 14 June 2007 the defendant's solicitors wrote to the plaintiff's solicitors in terms that included the following:
CRI has informed Metro on a number of occasions, most recently in our letter dated 30 May 2007, that CRI will continue to communicate with Metro in accordance with the requirements of the Retail Development Agreement (RDA). Our letter of 30 May requested that you let us know should Metro request any further information in relation to matters the subject of our letter.
Your letter dated 13 June 2007 notes your instructions to commence proceedings for preliminary discovery, presumably without making further and reasonable enquiries. Should those proceedings be commenced our client will tender this letter in support of an application that Metro pay CRI's costs of the application.
18 The plaintiff's Technology & Construction List Statement was filed on 14 June 2007 and identified the Nature of the Dispute between the parties as an application for preliminary discovery or alternatively for mandatory production of documents that related to the installation of conduits and associated telecommunications cabling "including but not limited to documents relating to any easements that may be created". That List Statement claimed that in February 2007 the plaintiff became aware that twelve conduits were proposed to be built in an east-west direction through that portion of the land that the plaintiff had agreed to purchase. The correspondence to which I have referred above was then referred to and it was claimed that in breach of the RDA the defendant had failed to provide "any information concerning any rights (including easements) which may be created in respect of the conduits". The plaintiff also claimed an entitlement to preliminary discovery to decide whether or not to commence proceedings against the defendant in respect of any actual or proposed future use of the conduits or the grant or proposed grants of rights in respect of the conduits. It claimed that the defendant may have, or have had, documents or things that could assist the plaintiff in determining whether or not the plaintiff was entitled to make a claim for relief against the defendant.
19 On 26 June 2007 the plaintiff's solicitors wrote to the defendant's solicitors disagreeing with the contention in the defendant's solicitors' letter of 14 June 2007 that the plaintiff had failed to make further and reasonable enquiries and advising that the plaintiff was prepared to finalise the proceedings if the defendant consented to the provision of the documents requested. On 2 July 2007 the defendant's solicitors responded in terms including the following:
Our client is willing to consider a compromise. Indeed, prior to this action being commenced and in an effort to avoid it, our client invited you to let us know what further information your client requested beyond that provided in our letter dated 28 May 2007 in relation to Telstra conduits or other services relevant to the Retail-Base Works, the Retail Complex Lot and the Retail Space Lease Lot. Without responding to that invitation your client commenced these proceedings. Your client's conduct in that regard will be relevant to the question of costs.
20 On 11 July 2007 plaintiff's solicitors wrote to the defendant's solicitors enclosing five colour photographs of the construction site taken on 7 July 2007 showing conduits, the subject of the plaintiff' application, laid across the site. The plaintiff's solicitors advised that they were instructed that work to lay the conduits had been continuing. That letter included the following:
In your letter of 30 May 2007, you advised that the routes of any conduits on the eastern side of the CTI site were "not yet determined and relevant drawings will be supplied once the route is finalised". Our client has relied upon this statement when determining the nature of the proceedings it has commenced to date. Clearly the route is known to your client and it has failed to provide the said drawings or other sufficient information in relation to the route of the conduits to enable our client to properly consider its position.
21 That letter went on to request from the defendant a written undertaking to cease work relating to the laying of the conduits until the proceedings could be determined.