[2026] VSCA 25
General information, not legal advice.
Court of Appeal (Vic)
2026-02-27
Leish JA, Lyons JA
Original judgment source is linked above.
OZZIE HOMES BUILDING & CONSTRUCTION PTY LTD (ACN 130 154 906)
[2024] VCC 1337 (Judge Burchell)
CONTRACT - Major domestic building contract - Claim for progress payment - Contract containing divisible obligations of performance in respect of each construction stage - Relevance of defects to completion of intermediate construction stage - Whether lock‑up stage complete - Plyboard barrier in place of door or temporary door - Lock‑up stage not complete - Builder not entitled to progress payment - Neither party effectively rescinded contract - Mutual abandonment of contract - Builder failed to establish claim for quantum meruit - Appeal against dismissal of counterclaim partly allowed - Owners entitled to liquidated damages - Leave to appeal granted - Appeal allowed.
Cardona v Brown [2012] VSCA 174; (2012) 35 VR 538, considered; Mann v Paterson Constructions Pty Ltd [2019] HCA 32; (2019) 267 CLR 560, Foran v Wright [1989] HCA 51; (1989) 168 CLR 385, Lumbers v W Cook Builders Pty Ltd (in liq) [2008] HCA 27; (2008) 232 CLR 635, Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221, applied.
PRACTICE AND PROCEDURE - Application to adduce further evidence - Leave to adduce further evidence denied but for two documents.
Supreme Court (General Civil Procedure) Rules 2025, r 64.13.
Carroll v Goff [2021] VSCA 267, Foody v Horewood [2007] VSCA 130, applied.
(a) finding that the builder was entitled to payment for the lock‑up stage (ground 1);
(b) finding that the builder validly terminated the contract (ground 2);
(c) finding in the alternative that the parties mutually abandoned the contract or agreed to its termination, or that the builder accepted the owners' offer to terminate the contract (ground 2A(a));
(d) finding that the builder was entitled to payment on a quantum meruit (ground 2A(b));
(e) failing to award damages to the owners (ground 3).
CONSTRUCTION STAGES APPLICABLE TO METHOD 1 PROGRESS PAYMENTS
a) in the case of a home with a timber floor, the stage when the concrete footings for the floor are poured and the base brickwork is built to floor level;
b) in the case of a home with a timber floor with no base brickwork, the stage when the stumps, piers or columns are completed;
c) in the case of a home with a suspended concrete slab floor, the stage when the concrete footings are poured;
d) in the case of a home with a concrete floor, the stage when the floor is completed;
e) in the case of a home for which the exterior walls and roof are constructed before the floor is constructed, the stage when the concrete footings are poured;
the stage when a home's frame is completed and approved by a building surveyor;
the stage when a home's external wall cladding and roof covering is fixed, the flooring is laid and external doors and external windows are fixed (even if those doors or windows are only temporary);
the stage when all internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards of a home are fitted and fixed in position;
the Building Works are complete in accordance with the Contract Documents.
This table is prescribed by Section 40 of the Domestic Building Contracts Act 1995. In the case of a Domestic Building Contract that is not listed in the Table, a Builder must not demand or receive any amount or instalment that is not directly related to the progress of the Building Works being carried out under the Contract.
The owner must pay the amount of a progress payment set out in Schedule 3 within the number of days set out in Item 7 of Schedule 1 after both:
• the stage has been completed; and
• the owner has received a written claim for the progress payment.
[42.2] If the owner is in substantial breach of this contract the builder may give the owner a written notice to remedy the breach:
[42.3] If the owner does not remedy the substantial breach stated in the notice to remedy the breach within 10 days of receiving that notice, the builder may end this contract by giving a further written notice to that effect.
As per the contract Construction period to build this house is 270 days after obtaining the building permit which is ending on 11th November 2021.
Due to Covid 19 there is a shortage of building materials supply specially framing timber that's why construction of this house won't complete by 11/11/2021.
Ozzie Homes Building & Construction Pty Ltd confirms here that any extra time which will be taken to complete this house after 11/11/2021 the builder will compensate the owner by paying their bank loan interest which will arise as an extra expense due to delay in the construction for this house until the completion of this construction. The construction period will end by obtaining the Occupancy permit.
Our client had proposed a split Payment options with 50% of invoice to be paid after they receive all the compensation, completed selection sheet and defects fixed issued in both reports by surveyor and our clients building inspector. Loan repayment Compensation to be paid in advance is average $2550 pm from 11/11/21 until may-22 total =$15300 & + ongoing when the house construction is completed.
Plus Construction delay:
$250 P/week pay in advance as contract a builder compensation from 11/11/21 until May 22 total =$7350 + ongoing when the house construction is completed.
Compensation for our client's ongoing stress $10,000.00
The remaining 50% will be paid after the plaster is completed and our client will monitor the progress for the next 2 weeks after the plaster. In the event, there is no progress then our client will not proceed further.
...
If the above is unacceptable to your client then, we believe that DBDRV has issued the certificate and our client retains their rights in relation to the issues mentioned above. Please reply to our offer by 6/6/22 or else our client may have to employ other builders to finish the construction.[21]
We clearly mentioned to you, Ikbal and Ozcan in our first communication in Feb 2022, we aren't paying the invoice for the incomplete lock up stage to your builder until we will get all the answers, compensation and a guarantor who will take the responsibility of our house completion.
But you all just ignoring us and don't value your customers and have disturbed our mental health & financial lost [scil, loss].
Your client - builder has stopped the site work since Feb and issued an invoice on 02/02/2022 demanding for the lock up stage ... when the lock up stage wasn't finished but our bank repayments hasn't stopped and I don't have any more money to pay our mortgage to Bank. ...
They don't have any workmanship, after I paid them $169750 they will run away, one partner Ikbal is already disappear & shut his office, so I don't have anymore trust left on them and we aren't paying the invoice this time until :
- complete all the works reported in inspection report by our inspector and surveyor's report
- pay us the compensation in advance which is due from 11/11/2021, contracted & provided letter of bank loan interest until now +$2000 for site cleanup +$700 for temporary fence.
- complete all the queries for selection sheet asked in our previous emails,
- provide me the time frame of construction completion on statutory declaration.,
- provide customer service and progress in work (if they want payment from us) then we will think about if we can go ahead with you.
FYI: we are not breaching any clause ( builder) ur clients are breaching the law and Not complying to surveyor's reports 1. Written directions. 2.building notice. 3.building order, they keep ignoring. 4.they claiming for lockup but they leave my property insecure without temporary fence for so many weeks & I arranged from another company. 5.they leave the site so messy with his rubbish since they start work, I cleaned from my pocket. Which is builder responsibility to maintain under the contract.
I am offering them for the last time to arrange a time with me. Otherwise, I don't care if wants to terminate the contract.
Due to all these issues and wrong brick work on my house, I am not progressing the payments and would like to hear from you about (When they want to answer me).
Ground 1 - Failure to complete lock‑up stage
(a) Both of Mr Laycock's reports reproduced a photograph taken from the inside of the house depicting a doorway boarded up with plywood with the description 'Doors (Temporary) Does Not Conform With Plans'. The reports also reproduced a photograph of the front entranceway to the house boarded up with plywood. In oral evidence‑in‑chief, Mr Laycock was shown an unidentified photograph[29] and was asked what problem the photograph revealed. His answer was, 'No front door or no temporary front door'. He said that it was usual practice at lock‑up stage to put in place the 'actual doorframe' with a temporary door. He said that in the photograph no frame was shown. It was not disputed before this Court that the door to which Mr Laycock referred in his evidence was the front door to the house (door 'D01' on the plans).
(b) A photograph in each report showed the main entranceway to the garage at the front of the house without a door in place. The reports did not otherwise describe or refer to the main garage entranceway or door (D02).
(c) An 'alfresco' sliding door was installed incorrectly. In oral evidence, Mr Laycock said that the door was loose and hanging, flapping in the breeze and leaning into the building unsecured.
(d) The laundry door was not the correct size.
(e) The reports stated 'Brickwork Does Not Conform With Plans', meaning relevantly that the 'stepdown on the North elevation' was not in accordance with the plans and that the wrong bricks were used on the garage and north elevation. The photos showed various gaps and chips in brickwork.
(f) It was put to Mr Laycock in cross‑examination that 'the floors were there'. He agreed, adding, 'The stuff that was there, that was meant to be there was defective, a lot of it'.
(a) He acknowledged the contractual definition of lock‑up stage. He said that lock‑up works typically include the installation of all claddings, external doors and windows (permanent or temporary) 'excluding the garage door but including the garage pedestrian door/s' and the completion of roofing. He did not elaborate on why the garage door was to be excluded from the external doors required to be fixed as part of the lock‑up stage. He was not instructed to assume that the garage was not part of the house.[31] The report did not otherwise mention the main garage door (DO2).
(b) Mr Wood then described and made observations about the items said in each of the primary materials to have been incomplete or deficient.
(c) By reference to the March Laycock Report[32] Mr Wood identified seven items that were 'incomplete works from the lock‑up stage', namely: brickwork that did not conform with plans; incomplete flashings; missing bricks to brick piers; temporary door not in accordance with plans; missing roof tiles; walls not straightened, plumbed and wall junctions not nailed; and noggings missing.[33]
(d) Mr Wood also listed several groups of items from that report that he said were defective or incomplete but not part of lock‑up stage works.
(e) By way of conclusion, he said that the March Laycock Report was accurate in that the lock‑up stage works remained incomplete in October 2022 and it followed that 'the comments in the Jim's report would be incorrect'.
(f) By way of summary, Mr Wood said that the primary materials identified that 'the works had progressed to approximately 95% through the lock‑up stage with some roofing, masonry cladding, and doors to be completed'. He concluded, 'The lock‑up stage was not achieved, but was approximately 95% completed'.
From my experience, if the works have been completed, but been completed incorrectly, they'd be considered completed ... and defects would be rectified throughout the course of building work. I don't know ...
...
I'm not quite sure whether or how to answer this, because my opinion on this is that if the works are completed and completed incorrectly, they're completed nonetheless, and if they need to be rectified, then they would be rectified and brought back into compliance. When that happens, I'm - I'm not too sure how that impacts a contract or - and I don't know, your Honour, if I'm the right person to answer that question.
(a) In late January 2022, he formed the opinion that lock‑up stage had been reached. External cladding had been installed, the roof covering was installed, the flooring was laid and external doors and windows had been supplied and fixed, with the exception of the front door and garage roller door.
(b) The garage roller door was impossible to install until after the plaster had been done, which occurred at lock‑up stage. There was no elaboration on this statement.
(c) It was not practical to install the front doors which were a solid timber system, expensive, heavy and liable to be damaged if fixed into position before fixing stage had been completed. Installing the door jamb prior to fixing would leave it exposed to being damaged by workers coming and going, and the door's hinges would be at risk of being damaged. The 'final doors' needed to be levelled, which is a time‑consuming process. When the plastering is done, the lock‑up fixer levels the jamb and fixes it in place permanently, then puts on architraves and skirting around the doors. Therefore, instead of fixing the permanent doors at the end of lock‑up stage, a piece of plyboard was fixed to the entryway by nails to the timber from the house from the inside. It is more secure than a temporary swinging door in a door jamb. To gain entry from the outside, it would need to be destroyed. To remove it without damaging the plyboard, it would need to be removed from the inside. All other entries to the house were locked by either fixed doors or fixed windows. Entry into the building for the purposes of the fixing stage was via a sliding door to the alfresco area.
(a) By 2 February 2022 (when the first lock‑up stage invoice was issued) the windows were in, the cladding was done and the roof was in, but 'we did not have a front door because it was not practical to install it (which was to be a large solid timber double‑door system); it would only have been damaged if it had been installed'.
(b) As to the render on the garage wall, during the construction of that wall Sukhvinder called Ikbal to say some of the bricks were facing the wrong way. Ikbal called the bricklayer and told him to stop. He inspected the site when Sukhvinder was present. The bricklayer agreed he had made a mistake. Ikbal asked him to remove the bricks and start again. Sukhvinder asked if the wall could be rendered instead of fixing the issue. Ikbal then had the garage wall rendered. He did not ask or cause the builder to issue a variation for the render.
(c) The building notice stated that the brickwork on the north elevation 'had a step down in lieu of being straight'. This occurred because of an error in the drawings. The only way to make the brickwork match the height of the parapet wall was to add two or three courses of bricks to the ground floor brickwork, which continued in a straight line until it met the study window after which it had a 'step down' to go underneath the window.[35]
(a) Whether lock‑up stage has been completed turns on the facts and requires consideration of the language of s 40(1) of the Act.[36]
(b) Defective works are not a relevant consideration in determining whether works have reached lock‑up stage.[37] For this conclusion, the judge relied on the opinion of Mr Wood, whose evidence as summarised by the judge was that 'in lock up stage if it is defective work, [the work is] considered completed and defects are rectified during the course of the work'.[38]
(c) The owners accepted in closing submissions that 'defective works are not part of lock up items'.[39] The owners pleaded and opened their case relying on the March and June Laycock Reports but in closing submissions confined their case to the seven matters set out in the SJE Report.[40]
(d) The items identified in the March and June Laycock reports were 'trivial in nature and do not constitute a breach, and do not disentitle the Builder from issuing the invoice for lock‑up stage'.[41]
(e) The judge then addressed several items said to be incomplete or defective by reference to the SJE Report:
(i) As to the front door, the judge accepted the evidence of Ozcan and Ikbal that 'the front doors were a solid timber double‑door system' that were 'expensive, heavy and liable to be damaged if fixed into position before fixing stage'. Instead of fixing the permanent doors at the end of lock‑up stage a piece of plywood was fixed to the entryway by way of nails to the timber frame, which is 'more secure than a temporary swinging door'.[42] The judge concluded that the front door entry system was not installed because it was impractical to do so. The judge concluded that instead the front door 'had plywood in situ which gives the effect that the house is locked up which is the statutory purpose of that stage'.[43] The judge referred to this Court's observation in Cardona v Brown[44] that the reference in the definition of lock‑up stage in s 40 of the Act to 'temporary doors or windows' suggests that there may be a need for interim works to ensure the house is completely closed.
(ii) As to the garage door, the judge accepted the unchallenged evidence of Ozcan that it was 'not possible to install the garage door until the plaster had been done'.[45] As with the front door, the judge found that the garage door had plywood in situ which satisfied the statutory purpose of the stage.[46]
(iii) The issue of whether the frame stage was completed was irrelevant on the owners' amended pleadings.[47]
In any event, I accept the Builder's position that even at its highest, Mr Wood maintained that, taken altogether, the incomplete items amounted to 5% of lock‑up stage. In my view, 5% is a trivial amount and it does not preclude effective and satisfactory completion of the stage.[48]
(i) the garage external doors had not been installed;
(ii) parts of the external brick veneer walls had been constructed using the wrong bricks, which the builder failed to rectify despite the relevant building surveyor issuing a Building Notice and a Building Order;
(iii) the brickwork on the north elevation was incorrectly constructed, which the builder failed to rectify despite the relevant building surveyor issuing a Building Notice and a Building Order;
(iv) the brickwork had various defects including cracks, chips and poorly laid bricks, and gaps;
(v) the external laundry door was only 1400 mm wide, instead of 1500 mm wide, which the builder failed to rectify despite the relevant building surveyor issuing a Building Notice and a Building Order;
(vi) the Court ordered Single Joint Expert, Mr Wood, concluded in his report that the lock‑up stage was not achieved;
(vii) the front door had not been installed;
(viii) the alfresco door was loose and hanging, the door frame had not been installed correctly and the door was flapping in the breeze, it was not fixed in place, and it was leaning into the building unsecured and could have been easily pushed in; and
(ix) the previous stage, Frame Stage, had not been effectively and satisfactorily completed and was the subject of a Building Notice and Building Order which the builder failed to comply with.
(a) The garage external doors were not installed.[49] That suffices to establish that lock‑up stage was not complete. The garage was part of the house and external doors had to be fixed to complete lock‑up. The contractual definition of lock‑up stage at least required a temporary door. The evidence of Ozcan Oztas, that it was not possible to install the garage roller door until after the plastering was done, did not address the absence of a temporary door. The fact that the evidence was not challenged was irrelevant. The builder bore the onus of establishing lock‑up; it was not for the owner to prove what the builder ought to have done. The judge's finding that the garage roller door had 'plywood in situ' was erroneous.[50] In closing submissions the owners' counsel referred to a photograph of the boarded‑up front door, mistakenly saying it was the garage. That he did so is of no moment because it was for the builder to discharge the onus of proving that a door (whether temporary or permanent) was fixed. The mistaken reference was corrected by the builder's counsel in closing. The missing garage doors were the front roller (panel) door (D02 on the plans) and the door from the garage to the garden (D03 on the plans).
(b) Neither a permanent nor a temporary front door was installed where door D01 was shown on the plans. The front doorway was boarded up with plywood, and no door frame was installed. Plywood is not a temporary door. The single joint expert concluded that this item was an incomplete work required for lock‑up.
(c) The alfresco door was not fixed in place, and it was leaning into the building, loose and flapping in the breeze, according to the evidence of Mr Laycock which was based on his inspection and was not challenged. It was not 'fixed', as required by the contractual definition. The single joint expert estimated a cost of $2,000 for rectification.
(d) The fact that part of the external walls were constructed with the wrong brick was raised in the 9 April 2022 building notice, with which the builder did not comply.
(e) The brickwork on the north elevation was incorrectly constructed as raised in the 9 April 2022 building notice, with which the builder did not comply. The single joint expert estimated a cost of $11,152.57 for rectification.
(f) The single joint expert reported on numerous defects in the brickwork including gaps due to the windows having been incorrectly placed without reasonable care. The effective and satisfactory completion of the brick walls was required to complete lock‑up stage.
(g) The external laundry door was specified as 1500 mm wide but was constructed at 1400 mm. The single joint expert opined that this arose because an incorrect window was placed without reasonable care and estimated a cost of $6,056.05 for rectification.
(h) The owners relied on the frame defects in the building order of 7 June 2022 as evidence that the frame stage was not completed.
(a) Most of the matters raised by the owners were not raised or pressed before the judge. A party is bound by the conduct of its case[51] and except in the most exceptional circumstances will not be allowed to raise a new argument that it failed to put to the lower court after a case has been decided against it.[52] The owners relied on matters in the March and June Laycock Reports in their pleadings and opening,[53] but in closing confined their argument to seven matters set out in the single joint expert.
(b) The owners accepted that defects were not part of lock‑up items and accepted the evidence of the single joint expert that milestone stages of works do not need to be defect‑free.[54] They should not be permitted to resile from this concession.
(c) Furthermore, for completion of a stage 'the items must be there'; lock‑up is an interim stage and works comprising the stage need not be defect‑free. For lock‑up stage, items must be 'fixed' in order to fulfil the statutory purpose of the stage discussed in Cardona, which is to afford some security to the dwelling.
(d) In any event, each of the matters relied on by the owners were trivial failures or minor failures caused by impracticalities that do not preclude the completion of lock‑up stage.
(a) The installation of the garage roller (panel) door was in issue below. In closing, the owners submitted that the garage door did not comply with the definition of lock‑up stage, but the owners' counsel mistakenly described the front door that was boarded up with plywood, rather than the garage door. It was not put to the builder's witnesses that it may be possible or practical to install plyboard as a temporary garage roller door. The unchallenged evidence of Ozcan was that it was impossible to install the garage roller door before plastering that occurred at fixing stage. According to Cardona, failures borne of impracticality do not prevent completion of a stage.
(b) The door between the garage and the garden (D03) was not raised below in any submissions or expert report. No witness or expert identified that this door was missing. The evidence to which the owners referred on this appeal does not clearly show a missing door.
(c) As to the front door (D01 of the plans), the judge accepted the evidence of Ozcan and Ikbal that the doors (a double‑door system) were liable to be damaged if fixed into position before the fixing stage, and that instead of fixing permanent doors, a piece of plywood was fixed to the entryway by way of nails to the timber frame, which was more secure than a temporary swinging door.[55] Those findings were not challenged. That temporary work enclosed the home and does not preclude the completion of lock‑up stage.
(d) The fixing of the alfresco door could have been rectified by repositioning the windows and that work would have required two carpenters for a day. This item is a triviality or is irrelevant to the question of completion.
(e) The construction of the garage wall with the wrong bricks was not one of the seven items relied upon at trial. In any event, the evidence was that Sukhvinder requested that the wall be rendered instead of re‑building it with the correct bricks. The owners do not challenge the finding to that effect.[56]
(f) Incorrect construction on the north elevation was not one of the seven items relied upon at trial. The 'step down in lieu of being straight' was a result of an error in inconsistent drawings,[57] which the single joint expert concluded was a discrepancy in the contract documents.
(g) Defects in the brickwork, such as gaps and chips, were not within the seven items relied upon at trial. It is unknown how many bricks were cracked and only one brick was identified as chipped. According to the single joint expert, rectification would have required a bricklayer for a small project call‑out. Rectification of gaps in the brickwork would have taken two carpenters a day to fix. These were trivial items.
(h) The construction of the laundry door at 1400 mm instead of 1500 mm wide was not one of the seven items relied upon at trial. There is no suggestion that the wrong dimensions meant that the external doors to the house were not fixed.
(i) The owners conceded the frame issue and amended their pleadings accordingly prior to trial, as the judge recorded.[58] The issue was not relevant on the pleadings and the judge did not determine it. The owners cannot rely upon it on appeal.
(j) Whether lock‑up stage was complete was a legal and factual matter for the judge to determine. The judge considered each of the uncompleted works and determined that they did not preclude completion of lock‑up stage. That the single joint expert concluded that the works were only 95 per cent complete did not preclude the judge from reaching her own view.
It is necessary for there to be 'effective and satisfactory completion of the required stage ... [as] a condition of any instalment payment' and while trivial failures, or failures borne of impracticalities, do not preclude effective and satisfactory completion, it is noteworthy that the dispute in relation to the trusses was not resolved until the first day of the hearing before VCAT. That resolution involved work being done on the trusses to strengthen them in accordance with the recommendations of the consultant engineer.[61]
(a) The builder was an innocent party who was entitled to terminate the contract and was entitled, as an alternative to damages, to claim a quantum meruit for work done for an incomplete stage, applying the principles discussed in Mann v Paterson.[82]
(b) The builder was entitled to terminate the contract 'on the grounds of the owners' repudiation of the contract'. By their 2 August 2022 email, the owners unequivocally evinced an intention to no longer be bound by the contract. They made plain that they were not willing to perform the contract in accordance with its terms by stating that they would not pay the builder's invoice until each of the other terms they imposed would be met.[83] There was no contractual basis for that position. In cross‑examination, Sukhvinder 'doubled down on his position', saying that even if the builder had satisfied all the items in the March and June Laycock Reports, the owners would still not pay the invoice.[84] The builders were entitled to terminate on grounds different to those advanced in their notice of termination.[85]
(c) Quantum meruit is available 'independently of the basis of termination' and has its genesis in restitution based on the concept of unjust enrichment. The owners have obtained a benefit in the builder conducting works to construct a partly built house for the owners. The cost of the building works was for the goods supplied as set out in the invoices for the sum claimed. There was nothing to suggest that that sum did not represent a fair and reasonable price.[86]
(d) The builder relied in the alternative on the contention that it may be inferred that the parties abandoned the contract or agreed to its termination. The inference may be drawn from the builder's legally ineffective termination (assuming its notice of termination of 8 August 2022 was invalid) and the absence of any termination by the owners. In effect, the builders said that they would not do any further work and the owners did not say anything in response. Alternatively, Sukhvinder offered in the 2 August 2022 email that the builder could either meet the owners' demands or accept their offer to terminate the contract. The builder accepted that offer by its notice of termination of 8 August 2022.[87] The judge did not address what implications flowed from the parties abandoning the contract but concluded by saying that there had been substantial performance of the lock‑up stage and the contract price may be recovered by the builder for the work done.[88]
(a) Because the builder did not reach lock‑up stage, its purported termination under cl 42 of the contract was ineffective.
(b) The builder had suspended works on the site for months without ever serving a notice of termination as required by cl 35 of the contract, which amounted to a substantial breach of the contract under cl 43.1 and a repudiation of the contract, entitling the owners to terminate the contract at common law. Furthermore, the builder threatened to stop work on 2 February 2022 and 4 March 2022 but did not give notice of its suspension of works, as required by cl 35.1 of the contract. Suspending the works without serving a notice under cl 35 was itself a substantial breach of the contract.[89] The builder was not entitled to terminate the contract under cl 42, being in substantial breach itself. The owners accepted the builder's repudiation and terminated the contract at common law when they engaged a new builder to complete the works.
(c) The owners did not repudiate the contract by seeking to resolve their dispute with the builder on terms that went beyond the contract. The parties had been in conciliation, which had failed. Then, having received a notice of intention to terminate, the owners offered to resolve the dispute by their 2 August 2022 email to the builder. The email, written by a layperson, is a desperate attempt by the owners to engage with the builder to resolve the matter as an alternative to paying the lock‑up invoice in full, where the owners did not accept that the work was complete.
(d) The builder is not entitled to quantum meruit; there is no basis for restitution. The builder was not entitled to a contractual payment and was not an innocent party who accepted the repudiation of the other party as the only available course of action.
(e) The parties did not abandon the contract or agree to its termination. Alternatively, if they did, no agreement that the builder was entitled to payment for partly completed works can be implied in circumstances where the owners made clear that they were refusing to pay the disputed lock‑up stage invoice. Unjust enrichment is not itself a cause of action; a basis for payment in quantum meruit has not been established.
(a) The evidence did not establish that the builder suspended the works.
(b) In characterising the end of the parties' contractual relationship, there were only four possibilities: the owners terminated the contract; the builder terminated it; the parties abandoned it; or it remained on foot until the issue of proceedings by counterclaim.
(c) The owners did not terminate the contract by accepting the builder's repudiation. A contract is on foot until terminated even where one party has engaged in repudiatory conduct. A party must communicate that it accepts the other party's repudiation. The owners have not established that they communicated their acceptance of the builder's repudiation. To the contrary, the owners repudiated the contract by evincing an intention not to be bound by it. Their intention was expressed in their 2 August 2022 email. Sukhvinder maintained when cross‑examined that he would not have paid even if the work was completed.
(d) The builder was entitled to accept the owners' repudiation and terminate the contract. The builder accepted the owners' termination by serving its notice of termination on 8 August 2022. The builder had served a notice of intention to terminate on the grounds of non‑payment of the lock‑up stage invoice. However, a termination that is invalid on one ground (non‑payment of a progress claim that was not in fact due for payment) may be supported by another ground (accepting the other party's repudiation), whether or not the terminating party had knowledge of it.[90] In those circumstances, where the owners were the defaulting party (having repudiated the contract) the builder was entitled to payment on a quantum meruit. The builder accepted that if, contrary to its submission, it was properly to be regarded as the defaulting party and the contract was terminated on the basis of that default, quantum meruit was precluded.
(e) It is not tenable to regard the contract as having been on foot until the owners issued a counterclaim. The owners plainly regarded the contract as being 'completely off' at least when they appointed a new builder.
(f) If neither party validly terminated the contract, it must have been abandoned. It is open to characterise the parties' communications in this way: the builder conveyed to the owners that it was not going to perform any more work, which meant that the builder could not do the remaining work to accrue its entitlement to payment at the conclusion of the lock‑up stage. The owners communicated in response that they were not going to insist on the builder finishing that stage. In those circumstances the builder could recover payment on one of two bases. First, the parties ought be regarded as having tacitly agreed to mutually discharge one another from their prospective obligations and to have agreed that the owners would pay the builder a reasonable amount for the work in fact performed. Alternatively, the builder was entitled to payment in restitution on a quantum meruit on the basis that the work was done for and at the request of the owners and it would be unjust or unreasonable for the owners to retain the benefit of the work without paying for it.
Consideration: ground 2 - termination by the builder
The suspension of building works is a significant step for a builder to take. A suspension carried out other than in conformity with cl 35 is treated by the contract as having the same level of seriousness as the cancellation or suspension of a builder's licence.
...
So too, cl 43.1 treats as significant the requirement to issue a notice of suspension of works immediately. The notice has several important functions, one of which is to trigger the commencement of a time period of seven days during which the owner has an opportunity, and an obligation, to remedy the breach that prompted the suspension of the works.[93]
Consideration: ground 2A(a) - mutual abandonment
(a) They reiterated that the builder had stopped work on site and had demanded payment for lock‑up stage when the works were not complete.
(b) They said that they would not pay the lock‑up stage invoice until several conditions were met: completion of all works reported in the owners' inspection report (which we take to mean the March and June Laycock Reports); payment of 'compensation', which we infer relied upon the builder's email of 3 August 2021, plus payment of $2,000 for site cleanup and $700 for the provision of a temporary fence; the completion of 'all the queries for the selection sheets asked in our previous emails'; a statutory declaration from the builder stating the time for completion; 'provide customer service and progress in work' and 'a guarantor who will take responsibility for our house completion'.
(c) On the subject of the contract they said:
.... provide customer service and progress in work (if they want payment from us) then we will think about if we can go ahead with you.
...
FYI: we are not breaching any clause ( builder) ur (scil your) clients are breaching the law and Not complying to surveyor's reports
...
I am offering them for the last time to arrange a time with me. Otherwise, I don't care if wants to terminate the contract.[98]
... unjust enrichment was identified [in Pavey & Matthews] as a legal concept unifying 'a variety of distinct categories of case'. It was not identified as a principle which can be taken as a sufficient premise for direct application in particular cases. Rather, as Deane J emphasised in Pavey & Matthews, it is necessary to proceed by 'the ordinary processes of legal reasoning' and by reference to existing categories of cases in which an obligation to pay compensation has been imposed. 'To identify the basis of such actions as restitution and not genuine agreement is not to assert a judicial discretion to do whatever idiosyncratic notions of what is fair and just might dictate'. On the contrary, what the recognition of the unifying concept does is to assist in the determination, by ordinary processes of legal reasoning, of the question whether the law should, in justice, recognise such an obligation in a new or developing category of case'.[117]
In Steele v Tardiani, ... Dixon J explained the problems of identifying, for the purpose of a quantum meruit claim not based on the contract, a 'benefit' conferred on a building owner by the performance of work otherwise than in accordance with the contract. He accepted that, where building work is done outside the contract, and the benefit of the work is taken, there may arise an obligation to pay for the work. He went on to refer, however, to 'the dilemma in which a building owner is placed'. He quoted Collins LJ who said, in Sumpter v Hedges:
- Where, as in the case of work done on land, the circumstances are such as to give the defendant no option whether he will take the benefit of the work or not, then one must look to other facts than the mere taking the benefit of the work in order to ground the inference of a new contract ... The mere fact that a defendant is in possession of what he cannot help keeping, or even has done work upon it, affords no ground for such an inference.
The reference to an 'inference of a new contract' may reflect an approach since overtaken by Pavey & Matthews Pty Ltd v Paul, but the problem involved in identifying a conferring or accepting of a benefit remains.[119]
Where a contractor is only entitled to receive remuneration if the contract is wholly carried into effect, and the other party's wrongful repudiation of the contract has the effect of preventing the contractor from becoming entitled to receive remuneration for services already rendered, the contractor may, after electing to treat the contract as at an end, maintain an action to recover restitution as upon a quantum meruit for those services, instead of suing for damages.
(a) In light of the finding that the builder completed lock‑up stage and effectively terminated the contract, the counterclaim must fail.[131]
(b) In any event, the owners failed to prove their loss. As to delay damages, the owners led no evidence of the start date of construction (although they referred to the date of 18 February 2021 in their particulars and in opening submissions). Without evidence of that date, loss cannot be quantified.
(c) As to the mortgage interest claim, the owners did not plead or prove a separate agreement. As to the alleged agreement, they did not establish why the amount claimed over and above contractual delay damages ought be granted, noting that delay damages are intended to be a genuine pre‑estimate of the costs the owner will incur if the project is not completed by the date for practical completion.[132] They did not prove that they were obliged to pay interest under a loan agreement. There was no evidence that they paid interest on their mortgage repayments in the sum claimed ($67,542.25).
(a) The judge's finding that the counterclaim must fail because the builder terminated the claim was in error because accrued contractual rights survive termination.
(b) They were entitled to 55 weeks of liquidated damages for delay from 11 November 2021 to 17 December 2022 when they terminated the contract, amounting to $13,750. The claim was squarely pleaded.
(c) As to the date of commencement of construction, a letter 'to whom it may concern' from Ozzie Homes signed by Ozcan dated 19 February 2021 stated 'we confirm through this letter that the construction work is started on 18 February 2021'. A letter from Emperial Homes to the owners dated 21 February 2021 stated 'construction ... is started'. Those letters were in the court book at trial but by oversight were not tendered. No relevant prejudice arises from their being allowed in evidence on this appeal. That evidence is consistent with the inference available from the builder's letter to the owners of 3 August 2021, which was in evidence. The 3 August letter states that, under the contract, the construction period is 270 days after obtaining the building permit which period ends on 11 November 2021. Working back from the end dates produces a start date of 15 February 2021. The judge's finding that no evidence was led as to the actual date of commencement was in error.
(d) Pursuant to the builder's letter of 3 August 2021, the builder agreed to pay the owners for their bank interest. The judge was wrong to conclude that no separate agreement was pleaded or proved by the owners and no evidence was before the court on which to calculate the loss.[133] The owners alleged the agreement, and advanced that claim by its counter‑claim, and tendered bank statements showing the interest paid on 'home loan transactions'. The owners had been very critical of the builder since at least October 2020. It may be inferred that the builder's promise to pay bank interest was given in exchange for the owners forbearing from exercising their rights against the builder in relation to their complaints about delays. The payment by the owners of interest to their bank for the loan in respect of the property was evidenced by their bank statements that were in evidence.
(a) As to the claim for delay damages, the owners did not plead the commencement date. That had the result that no evidence was led to prove the date of commencement of construction. Without that evidence, the loss could not be quantified. Had that date been alleged, the builder in turn would have pleaded delays due to COVID‑related restrictions and that time would have been extended under cl 34 of the contract for delays beyond the builder's control.
(b) As to the bank loan interest claim: there was no loan agreement before the court to establish interest charges; the owners did not establish how any additional interest charges arose from a breach of contract; the agreement was not supported by consideration and any claim for delay‑related damages is precluded by the express provision under the contract for liquidated damages.[134]
(c) The owners did not counterclaim for defects at trial. The claim should not be allowed on appeal. In any event, the obligation for the work to be free of defects had not yet arrived.
(d) To the extent that the owners succeed and are entitled to damages they must give credit for the value of the builder's work.
If the building works have not reached Completion by the end of the building period the owner is entitled to agreed damages in the sum set out in item 9 of schedule 1 for each week after the end of the building period to and including the earlier of:
• the date the building works reach Completion;
• the date this contract is ended; and
• the date the owner takes possession of the land or any part of the land.
The plaintiffs are entitled to be compensated a total of $22,500 in delay damages in accordance with clause 40 of the contract.
(i) Clause 40 of the Contract states that if the building works have not reached completion by the end of the building period, the owner is entitled to agreed damages in the sum set out in Item 9 of Schedule 1 for each week after the end of the building period to and including the earlier of the date of the building works reach completion, the date the contract is ended, and the date the owner takes possession of the land or any part of the land. A copy of the Building Contract is included in the Court Book (pages 447- 493).
(ii) The building work commenced on 18 February 2021. And according to Clause 1 in Schedule 1 of the Contract, the building work should have reached full completion by 15 November 2021. A copy of the commencement letter dated 19 February 2021 is included in the Court Book (page 533).
(iii) Due to the fact that the Defendant unlawfully terminated the Contract Defendant's repudiation of the Contract which the Plaintiffs accepted it, it took the Plaintiffs four months to find another builder who was willing to complete the building works. A copy of the new builder's letter confirming the taking over of the building project is included in the Court Book (page 1059).
(iv) On 17 December 2022, the Plaintiffs signed a new building contract with Kotam Projects Pty Ltd to complete the Lock‑Up stage and finalise the building project. The building works commenced in about mid January 2023. A copy of the new building contract is included in the Court Book (pages 1062-1119).
(v) On 7 August 2023, the occupancy permit was issued. A copy of the occupancy permit is included in the Court Book (pages 1128-1129).
(vi) Between 15 November 2021 and 7 August 2023, there were 90 weeks which is the delay period. $250 x 90 weeks = $22,500.
The plaintiffs are entitled to be compensated a total of $67,542.25 for the interest charges they incurred on their mortgage repayments during the delay period as agreed between the plaintiffs and the defendant.
Particulars
On 3 August 2021, it was agreed by the Defendant that any extra time which will be taken to complete the property after 11 November 2021, the Defendant will compensate the Plaintiffs by paying their bank loan interests which will arise as extra expenses due to delay in the construction for this property until completion of the construction. And that the construction period will end by obtaining the occupancy permit. A copy of the agreement letter is included in the Court Book (page 611).
(a) a construction quote from Emperial Homes received by the owners in May 2020, which was referred to at [88] of the Reasons, but not tendered at trial;
(b) a post‑trial online search of the Building and Plumbing Commission website;
(c) an article entitled, 'Industry Alert: Concerning increase in license lending' dated 9 June 2022;
(d) a deposit invoice from the builder, which was in the Court Book but not tendered at trial;
(e) a photo of the site fence taken on or about 8 February 2022 which listed Emperial Homes as the builder, which was in the Court Book but not tendered;
(f) a letter from the liquidator of Emperial Homes dated 21 September 2022, demanding payment of lock‑up stage;
(g) three reports filed with ASIC regarding Emperial Homes' liquidation which pre‑dated the trial (initial report to creditors dated 26 August 2022, statutory report by a liquidator to creditors dated 3 November 2022, third report to creditors dated 22 March 2023);
(h) three reports filed with ASIC regarding Emperial Home's liquidation and subsequent deregistration which post‑dated the trial (annual administration return dated 4 November 2024, deregistration request dated 18 June 2025, current and historical company extract for Emperial Homes);
(i) post‑trial correspondence between the parties' solicitors and between the owners' solicitors and the liquidator of Emperial Homes concerning the ASIC reports.
[E]ven if that remedy [quantum meruit] were available the facts of this case disentitle the builder from claiming restitution for unjust enrichment. Relevant to that submission is the fact that the builder in this case acted unconscionably in lending its licence to Emperial Homes, a company which was unregistered and insolvent from 2019. That is what caused the dispute.
[1] Under s 40(4) of the Act, contracting parties may agree that ss 40(2) and (3) do not apply, but the parties in this case did not do so.
[3] The date of commencement was in dispute. It is considered below in the context of ground 3.
[18] Other building notices and orders were issued but they are not material to the determination of this application.
[26] The notice referred to cl 43 but it is clear that cl 42 was intended.
[27] The particulars are set out below. They comprise eight items of work and reliance on the opinion of the single joint expert that lock‑up stage was not reached.
[28] The March and June Laycock Reports were substantially the same but not identical.
[29] It was not possible to tell from the transcript of evidence what he was being shown.
[30] The VBA building notices were dated 13 January 2022, 9 April 2022 and 5 May 2022; and the VBA building orders were dated 31 May 2022 and 7 June 2022.
[31] It was not contended that the garage did not form part of the house.
[32] Which was noted to have drawn the same conclusions as the June Laycock Report.
[33] Four of the items taken from the Laycock Reports were also the subject of the 9 April 2022 building notice, including 'brick work at north elevation has a step down in lieu of straight'; 'Front Brick Piers is at finished floor level of the balcony in lieu of above baluster height'; 'laundry door is 1400mm in lieu of 1500mm'; and garage wall rendered in lieu of brick.
[35] The 9 April 2022 building notice also addressed the laundry door and brick piers.
[38] Reasons, [148]. Mr Wood's evidence was further that defects need to be completed 'at some stage' but he did not know when.
[44] [2012] VSCA 174; (2012) 35 VR 538 ('Cardona').
[47] Reasons, [247]. The judge also dealt with flashings, missing roof tiles and incomplete construction of brickwork on the pillars supporting the balcony, concluding they were not incomplete works for the purpose of lock‑up stage. Those findings were not challenged.
[49] It was not contested that the garage roller panel door was not installed. Ozcan accepted that fact in his evidence.
[51] Citing Abedini v Commissioner of Australian Federal Police [2024] VSCA 230, [75] (McLeish, Lyons and Kaye JJA).
[52] Citing University of Wollongong v Metwally [No 2] (1985) 60 ALR 68, 71 (Gibbs CJ, Mason, Wilson, Brennan, Deane and Dawson JJ); Coulton v Holcombe [1986] HCA 33; (1986) 162 CLR 1, 7-8 (Gibbs CJ, Wilson, Brennan and Dawson JJ); Geelong Building Society v Encel [1996] VicRp 44; [1996] 1 VR 594, 595 (Tadgell J, Ormiston J agreeing at 609, Ashley J agreeing at 613).
[59] Cardona [2012] VSCA 174; (2012) 35 VR 538, 539 [7], 559-8 [82] (Tate JA, Bongiorno JA agreeing at 540 [1], R Osborn JA agreeing at 562 [102]).
[60] Tate JA said at [72] that the regime for progress payments in s 40 of the Act (and adopted by the contract) was premised on an expectation that lock‑up stage would not occur before the frame stage had been completed.
[61] Cardona [2012] VSCA 174; (2012) 35 VR 538, 556 [74] (citations omitted). The reference to 'effective and satisfactory completion' in that passage of the Court's reasons was a quotation from Wallace, Hudson's Building and Engineering Contracts, 12th ed, (2010), [3-076].
[62] Cardona [2012] VSCA 174; (2012) 35 VR 538, 556 [73]-[75].
[64] See AMO Rifat Holdings Pty Ltd v Dib (Building and Property) [2024] VCAT 419, [38]-[41] (Woodward P).
[70] Cardona [2012] VSCA 174; (2012) 35 VR 538, 559 [85].
[71] Cardona [2012] VSCA 174; (2012) 35 VR 538, 558-9 [82]-[85].
[72] Macquarie Dictionary (online at 19 December 2025) 'door'.
[74] GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd [2003] FCA 50; (2003) 128 FCR 1, 164-165 [702]-[706]; Tan Hung Nguyen v Luxury Design Homes Pty Ltd (2005) 21 BCL 46, 50 [24]; 52 [39] (McColl JA); 57 [73] (Einstein J), Hodgson JA agreeing, 47 [1].
[75] [2019] HCA 32; (2019) 267 CLR 560 ('Mann v Paterson').
[76] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 630-1 [176] (Nettle, Gordon and Edelman JJ).
[77] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 629-30 [174] (Nettle, Gordon and Edelman JJ). See also Maples Winterview Pty Ltd v Liu [2015] ACTSC 58, [82] in which Mossop AsJ construed a similar but not identical contract as requiring the completion of each stage as a condition precedent to an entitlement to progress payments.
[79] Reasons, [64], [322]. The Reasons refer to 9 August 2022 but the parties agreed that the date of issue of the notice of termination was 8 August 2022.
[80] The issues were dealt with by the judge under the heading 'Issue 2 - is the builder entitled to payment of some other sum assessed as on a quantum meruit?', at Reasons, [296]-[326].
[89] Citing Cardona [2012] VSCA 174; (2012) 35 VR 538, 559 [87], 561 [98].
[90] Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR 359, 370-1 (Rich J).
[91] The owners also relied in a submission put in general terms, on the builder's delays and 'defective work'. It is unnecessary, in light of the conclusions we have otherwise reached, to address that submission.
[92] The parties agreed that the builder 'threatened to stop work' in an email covering the first issue of its lock‑up stage claim on 2 February 2022. They were in dispute about whether there was evidence of a subsequent demand on 4 March 2022 that if payment was not received by 11 March 2022, the builder would suspend works in accordance with its contractual rights; the builder contended that the 4 March 2022 demand was not in evidence at trial. The builder did not contend that it had complied with cl 35.1 of the contract.
[93] Cardona [2012] VSCA 174; (2012) 35 VR 538, 560 [90]-[91].
[94] Clause 42.4 provided that 'the builder is not entitled to end this contract under this clause when the builder is in substantial breach of this contract'. Clause 42.0 preserved the builder's exercise of 'any other right or remedy' available to it if the owner breached the contract including by repudiation.
[95] Foran v Wright [1989] HCA 51; (1989) 168 CLR 385, 397 (Mason CJ), 424 (Brennan J), 451 (Dawson J).
[96] See Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115, 138 [48] (Gleeson CJ, Gummow, Heydon, Crennan JJ).
[97] Reasons, [64], [322]. The parties agreed that the date of issue of the notice of termination was 8 August 2022.
[99] See Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115, 135-8 [44]-[48] (Gleeson CJ, Gummow, Heydon, Crennan JJ).
[101] See the emails of 17 May 2022 and 25 May 2022 in the chronology above.
[102] Sopov v Kane Constructions [2007] VSCA 257; (2007) 20 VR 127, 130 [10]-[11] (Maxwell P and Kellam JA).
[103] There was no evidence of the date on which that occurred.
[104] Foran v Wight [1989] HCA 51; (1989) 168 CLR 385, 395 (Mason CJ), 416-17 (Brennan J), 442 (Dawson J).
[105] Poort v Development Underwriting (Vic) Pty Ltd (No. 2) [1977] VicRp 52; [1977] VR 454, 459 [20] (Starke, Lush and Kaye JJ).
[106] Sargent v ASL Developments Ltd; Turnbull v ASL Developments Ltd [1974] HCA 40; (1974) 131 CLR 634, 655-6 (Mason J) (citations omitted).
[107] Poort v Development Underwriting (Vic) Pty Ltd (No. 2) [1977] VicRp 52; [1977] VR 454, 459 [20] (Starke, Lush and Kaye JJ); Actrol Parts Pty Ltd v Coppi (No 2) [2015] VSC 694, [51] (Bell J), and the cases there cited.
[108] Sargent v ASL Developments Ltd; Turnbull v ASL Developments Ltd [1974] HCA 40; (1974) 131 CLR 634, 656 (Mason J).
[110] DTR Nominees v Mona Homes Pty Ltd [1978] HCA 12; (1978) 138 CLR 423, 434 (Stephen, Mason, Jacobs JJ, Aickin J agreeing at 437, Murphy J dissenting at 435-7).
[111] Jafari v 23 Developments Pty Ltd [2019] VSCA 201, [192] (Whelan and Niall JJA and Sifris AJA); Técnicas Reunidas SA v Andrew [2018] NSWCA 192, [51] (Leeming JA, Bathurst CJ agreeing at [1], White JA agreeing at [86]); Woolworths Group Ltd v Gazcorp Pty Ltd [2022] NSWCA 19, [93] (Bell P, Bathurst CJ agreeing at [1], Meagher JA agreeing at [231]).
[112] Realestate.com.au Pty Ltd v Hardingham (2022) 277 CLR 115 ('Hardingham').
[113] Hardingham (2022) 277 CLR 115, 126 [15] (Kiefel CJ and Gageler J). See also Gordon J at 133 [45]; Edelman and Steward JJ at 147 [83]; 156 [117], 158 [123].
[114] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 629-30 [174] (Nettle, Gordon and Edelman JJ).
[115] [2008] HCA 27; (2008) 232 CLR 635 ('Lumbers').
[116] Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221, 227 (Mason and Wilson JJ), 256-7 (Deane J) ('Pavey & Matthews').
[117] Lumbers [2008] HCA 27; (2008) 232 CLR 635, 665 [85] (Gummow, Hayne, Crennan and Kiefel JJ) emphasis in original, citations omitted.
[118] Lumbers [2008] HCA 27; (2008) 232 CLR 635, 656 [51]-[52] (Gleeson CJ), 663 [80] (Gummow, Hayne, Crennan and Kiefel JJ); Steele v Tardiani [1946] HCA 21; (1946) 72 CLR 386, 402 (Dixon J, McTiernan J agreeing at 408).
[119] Lumbers [2008] HCA 27; (2008) 232 CLR 635, 656 [51]-[52] (citations omitted).
[120] Lumbers [2008] HCA 27; (2008) 232 CLR 635, 661 [75] (Gummow, Hayne, Crennan and Kiefel JJ).
[121] Lumbers [2008] HCA 27; (2008) 232 CLR 635, 663 [79] (Gummow, Hayne, Crennan and Kiefel JJ) (citations omitted); cf Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 599 [83] (Gageler J).
[122] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 607 [109] (Nettle, Gordon and Edelman JJ, Gageler J agreeing at 607 [108], Kiefel CJ, Bell and Keane JJ dissenting).
[123] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 626 [166] (Nettle, Gordon and Edelman JJ, Gageler J agreeing at 591-2 [61], Kiefel CJ, Bell and Keane JJ dissenting). The dissentients would not have allowed recovery in restitution at all.
[124] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 628 [170] (Nettle, Gordon and Edelman JJ).
[125] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 627 [168] (Nettle, Gordon and Edelman JJ). That point was elaborated at 630-1 [176], Nettle, Gordon and Edelman saying that 'if there are any uncompleted stages, there will be a total failure of consideration in respect of those stages due to the failure of the builder's right to complete the performance and earn the price. In that event there will be nothing due under the contract in relation to those stages, and restitution upon a quantum meruit will lie in respect of work and labour done towards those uncompleted stages'.
[126] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 591-2 [61], 597 [76] (Gageler J).
[127] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 596-7 [75] (Gageler J).
[128] Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 598-9 [81] (Gageler J).
[129] Pavey & Matthews [1987] HCA 5; (1987) 162 CLR 221, 256 (Deane J).
[130] Cf Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 599 [83] (Gageler J).
[134] Citing Hacer Group Pty Ltd v Euro Façade Tech Export Sdn Bhd [2022] VSC 373 (Stynes J), [179].
[135] McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 CLR 457, 476-7 (Dixon J, McTiernan J agreeing at 486); Mann v Paterson [2019] HCA 32; (2019) 267 CLR 560, 625 [165] (Nettle, Gordon and Edelman JJ).
[136] See Agtrack (NT) Pty Ltd v Hatfield [2003] VSCA 6; (2003) 7 VR 63, 73 [14] (Ormiston JA, Chernov JA and O'Bryan AJA agreeing at 105 [85]-[87]); affirmed in Agtrack (NT) Pty Ltd v Hatfield [2005] HCA 38; (2005) 223 CLR 251 (Gleeson CJ, McHugh, Gummow, Hayne and Heydon JJ, Kirby J at 276 [87], Callinan J at 282 [109]).
[137] The owners referred to a start date of 18 February 2021 in their particulars, and if that is accepted, then the 270‑day building period would have concluded on 15 November 2021, which accords with the pleaded end date. The 3 August 2021 letter referred to an end date of 11 November 2021 which was adopted in the owners' written case. If the building period concluded on 11 November 2021, then the start date would have been 14 February 2021. We adopt the pleaded start date which is founded on the 19 February 2021 letter.
[139] See Hacer Group Pty Ltd v Euro Façade Tech Export Sdn Bhd [2022] VSC 373, [177]-[180] (Stynes J) and the case cited there.
[141] Carroll v Goff [2021] VSCA 267, [54] (Maxwell P, Kennedy and Walker JJA).
[142] Foody v Horewood [2007] VSCA 130, [61] (Chernov, Ashley and Neave JJA).
[143] Foody v Horewood [2007] VSCA 130, [61], citing Commonwealth Bank of Australia v Quade (1991) 178 CLR 134, 141 (Mason CJ, Deane, Dawson, Toohey and Gaudron JJ) (citations omitted).
[144] Carroll v Goff [2021] VSCA 267, [56], citing Apostolidis v Kalenik [2011] VSCA 307; (2011) 35 VR 563, 581-2 [56] (Nettle, Ashley and Tate JJA) (citations omitted).
[145] See Alphington Developments Pty Ltd v Amcor Pty Ltd [2025] VSCA 48, [439] (Walker and Whelan JJA) (citations omitted).
[146] See University of Wollongong v Metwally (No 2) (1985) 60 ALR 68, 71 (Gibbs CJ, Mason, Wilson, Brennan, Deane and Dawson JJ).
[147] ASIC search, which contained historical information regarding Emperial Homes, and the search of the Building and Plumbing Commission website.
[148] Article entitled, 'Industry Alert: Concerning increase in license lending' dated 9 June 2022.
[149] Initial Report to Creditors dated 26 August 2022; Statutory Report by a Liquidator to Creditors dated 3 November 2022, and Third Report to Creditors dated 22 March 2023.
Singh
Ozzie Homes Building & Construction Pty Ltd [2026] VSCA 25
(1989) 168 CLR 385
(2003) 128 FCR 1
(2007) 233 CLR 115
(1974) 131 CLR 634
(1946) 72 CLR 386
(2003) 7 VR 63
(2005) 223 CLR 251
(2008) 232 CLR 635
(1985) 60 ALR 68
(1986) 162 CLR 1
(1931) 45 CLR 359
(1978) 138 CLR 423
(2022) 277 CLR 115
(1933) 48 CLR 457
(2012) 35 VR 538
(2019) 267 CLR 560
(1987) 162 CLR 221
(2007) 20 VR 127
(1991) 178 CLR 134
(2011) 35 VR 563