[2025] VSC 751
General information, not legal advice.
Supreme Court of Victoria
2025-12-04
Daly AsJ
Original judgment source is linked above.
[2025] VSC 751 (revised 5 December 2025)
REAL PROPERTY - Restrictive covenants - Application to modify restrictive covenant under s 84(1)(b) and (c) of the Property Law Act 1958 (Vic) - Covenant not to build dwelling above a certain height - Covenant breached - Whether acquiescence constitutes agreement under s 84(1)(b) of the Property Law Act 1958 (Vic) - Whether inaction by beneficiaries constitutes agreement to modification of the covenant - Whether modification would not cause substantial injury - Re Clearwater Properties Ltd [2013] ] UKUT 210 (LC) applied - No discretionary matters warranting refusal of application - Application granted pursuant to s 84(1)(b) of the (Vic).
STATUTORY INTERPRETATION - Meaning of 'agreement' under s 84(1)(b) of the Property Law Act 1958 (Vic) - Natural and ordinary meaning - Interpretation to give effect to harmonious goals - Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 35; (1998) 194 CLR 355 applied.
CREATION OF RESTRICTION 'B'
The registered proprietors of the burdened land covenant with the registered proprietors of the benefited land as set out in the restriction with the intent that the burden of the restriction runs with and binds the burdened land and the benefit of the restriction is annexed to and runs with the benefited land.
Burdened land: LOTS 9 & 10 ON THIS PLAN.
Benefited land: LOTS 9, 10 &A ON THIS PLAN.
DESCRIPTION OF RESTRICTION:
NO BUILDING GREATER THAN SINGLE STOREY IN HEIGHT MAY BE CONSTRUCTED ON THE BURDENED LAND.
(a) is greater than single storey in height;
(b) has a roof pitch in excess of 25 degrees; and
(c) exceeds the maximum ridge height of 139.3 based on The Australian Height Datum 1971 (AHD 71).[5]
(a) in the week commencing 13 May 2024 the Perrys spoke with the site cut manager about the height restriction and their concerns. The site cut manager said that he was aware of the height restriction, and that the site cut was correct;
(b) the following week, Mrs Perry telephoned the site cut manager and repeated her concerns that the site cut was not deep enough. The site cut manager repeated his assurance that the site cut was correct, and that the plumbers would also check the heights; and
(c) sometime before 4 June 2024, the Perrys spoke to the Jayasinghes outside their home, and told the Jayasinghes about their discussions with the site cut manager. Mr Jayasinghe said that he knew of these discussions, and that the Perrys had questioned the depth of the site cut and the issue of the height restriction.
Between 20 and 29 July 2024, I spoke to two people from Live Well Homes about my concerns about the roof height. I know it was between these dates because it was when Grant was away in Darwin and I was at home.
I spoke to a Live Well Homes employee who held a clipboard. We spoke while we were standing in my driveway. I asked him if he was aware of the height restriction. He started to go through his papers and kept saying "yes, yes" as he flicked through the pages on the clipboard.
I invited one of the site managers or inspectors from Live Well Homes into our home to look at the height of the[new dwelling] from our lounge room. I told him there was a covenant on the [Jayasinghes'] land which was a height restriction. I said that the roof of the [new dwelling] looked too tall to me. We both stood in my lounge room, and he agreed it was a very tall roof. He used the words, "A big head on a small body." I asked him to report it back to his manager and to contact me. I never heard back from him.
I also raised the problem of the height with the workers putting the roof trusses up. One of those workers said, "Oh you're just worried you're going to lose your view."
I refer to paragraphs 60 to 90 of [Mrs Perry's] Affidavit and say that at no time during the period May 2024 to July 2024 did the [Perrys] explicitly advise us that they were concerned that the roof of our home breached the [height restriction]. I agree that in or around July 2024 the [Perrys] raised their concerns regarding the height of the building. However, following the conversation referred to in paragraph 23 of My June Affidavit, I understood that the [Perrys'] concerns were resolved.
I confirm that from July 2024, the [Perrys] did not raise any further concerns regarding the height of our home until we received [the 24 February letter] advising us of their view that our home breached the [height restriction].
We would not have continued with the construction of our home had we suspected or known that the [Perrys] remained concerned that the building breached the [height restriction].
The construction of our home is structurally complete and has connections to water, electricity and sewerage.
All that is left is the internal fit out, including installation of appliances, heating, ventilation and air conditioning, door hardware and fit-off, shower screens and mirrors, carpet and the timber deck.
The last payment made to the builder was on 2 January 2025 with respect to the 'Joinery' stage. Below is a table of the payments made to the builder to date.
Our instructions are as follows:
You purchased [the Jayasinghe property] from our clients with settlement taking place on 28 June 2022.
The title to [the Jayasinghe property] purchased by you contained a restrictive covenant regarding roof pitch and roof height restriction on any dwelling subsequently erected by you.
Currently you are erecting a dwelling on [the Jayasinghe property] which unfortunately breachers [sic] the terms of the restrictive covenant.
Enclosed herewith is copy correspondence from our clients surveyors Millar Merrigan. The correspondence clearly addresses the breach of covenant.
We suggest that at this stage you immediately cease construction of the dwelling. At the same time, it would probably be wise for you to consult a lawyers [sic] to consider your position.
Our clients are most anxious to bring the current situation to a mutually agreeable solution. To this end we suggest you have your legal representative contact our office.
Power for Court to modify etc. restrictive covenants affecting land
(1) The Court shall have power from time to time on the application of any person interested in any land affected by any restriction arising under covenant or otherwise as to the user thereof or the building thereon by order wholly or partially to discharge or modify any such restriction (subject or not to the payment by the applicant of compensation to any person suffering loss in consequence of the order) upon being satisfied -
(b) that the persons of full age and capacity for the time being or from time to time entitled to the benefit of the restriction whether in respect of estates in fee-simple or any lesser estates or interests in the property to which the benefit of the restriction is annexed have agreed either expressly or by implication by their acts or omissions to the same being discharged or modified; or
(c) that the proposed discharge or modification will not substantially injure the persons entitled to the benefit of the restriction:
Provided that no compensation shall be payable in respect of the discharge or modification of a restriction by reason of any advantage thereby accruing to the owner of the land affected by the restriction unless the person entitled to the benefit of the restriction also suffers loss in consequence of the discharge or modification nor shall any compensation be payable in excess of such loss; but this provision shall not affect any right to compensation where the person claiming the compensation proves that by reason of the imposition of the restriction the amount of consideration paid for the acquisition of the land was reduced.
(emphasis added).
(a) between about 13 May 2024 and 4 June 2024 the Perrys put the Jayasinghes on notice that the site cut may not be deep enough for the new dwelling to comply with the height restriction;
(b) at the July meeting the Perrys demonstrated to the Jayasinghes that the new dwelling would not comply with the height restriction;
(c) the Jayasinghes knew or ought to have known that the new dwelling breached the height restriction;
(d) the Jayasinghes have failed to remedy the breach of the height restriction; and
(e) as a result of the Jayasinghes' breach, the Perrys have suffered loss and damage, namely, the loss of their views, and a loss of the value of their property in an amount yet to be determined.
(a) the coffee table height was about the height of the height restriction,
(b) the [Perrys] were concerned about the height of the' [new] dwelling because it would be higher than the height restriction once the roof went on
(c) and (although he would not admit it during cross examination) given the frame was already up it would have been obvious to Mr Jayasinghe that once the roof went on, the height which the [Perrys] were saying was the height restriction would in fact be breached.
Okay. So they demonstrated, either Grant or Janine demonstrated, to you how to read the height of the dwelling from the height of the coffee table, didn't they? --- They mention[ed] that, yes.
Okay. And their evidence is that Grant bent down and looked upon the - along the ruler?---That's correct, yes.
Did you bend down and look along the ruler?---No, I did not.
Okay. You understood at that time that what they were saying was that the height restriction was about the height of their coffee table, didn't you?--- That's what they mentioned. Yes, correct.
So they told you that the height restriction on your land was about the height of their coffee table, yes?--- That's correct, yes.
Yes. And you looked at your dwelling and you could see that if the roof went on your dwelling, it would exceed the height of that height restriction, didn't you?--- I didn't looked at it, but - and a - and plus, to use a coffee table and the ruler to measure the height I have never heard of, so therefore I didn't take any notice.
You just decided not to take any notice of the concerns they were raising?--- I was more under the impression that for them to confirm their thought, not for me.
They were telling you that the height restriction was about the top of the frame on your dwelling. You understood that that was what they were saying?---They mentioned that. Yes, correct.
And you knew then that if a roof went on your dwelling, you would exceed the height restriction, didn't you? ---I didn't even think of that.
Although you were having a discussion about their concerns, you decided simply not to think about whether or not your dwelling exceeded the height restriction. Is that your evidence?--- So ah actually, it's not correct, the way it is coming through. Because - because of the way it was trying to measure, and plus because my builder, who confirmed their building against the council ah approved document, there was no need for me to check on the coffee table (indistinct).
There was no need for you to check on the coffee table?---No, there was absolutely no need for me to check on that.
Right. So although the Perrys were telling you you were exceeding the AHD restriction, you took your builder's word that the builder was complying with the building contract as ending the matter. Is that right?--- That's correct.
You hadn't told your builder about the height restriction, though, had you?---I didn't know about the height restriction. I only ask[ed] for single-storey house.[15]
(emphasis added).
(a) contrary to the evidence of Mrs Perry, the new dwelling has not caused significant overshadowing of the Perrys' home;
(b) most of the work that the height restriction has to do relates to the part of the Perry land on which the Perry's home is sited; and
(c) the Jayasinghes are unlikely to face significant difficulties in obtaining Council approval for the modification of the new dwelling to enable it to comply with the height restriction.
Have the Jayasinghes established that modification of the height restriction would not cause the Perrys substantial injury?
(a) a substantial injury must be a detriment to the benefitted land that is real and not fanciful. The requirement that the injury must be substantial is intended 'to preclude vexatious opposition cases where there is no genuineness or sincerity or bona fide opposition on any reasonable grounds'. That does not mean, however, that s 84(1)(c) of the [Act] is restricted to dealing with vexatious or frivolous objections. Although the restriction of s 84(1)(c) of the [Act] to 'substantial' injury would enable the weeding out of vexatious objections to the modification or removal of a covenant, the dichotomy in the section is not between vexatious and non-vexatious claims but is between cases involving some genuinely felt but insubstantial injury, on the one hand, and cases where the injury may truly be described as substantial, on the other;
(b) the substantial injury relates to practical benefits, being any real benefits to the person entitled to the benefit of the covenant. It is not sufficient for a plaintiff to merely prove that there will be no appreciable decrease in the value of the property that has the benefit of the covenant;
(c) substantial injury may arise from the order for modification of the covenant being 'used to support further applications resulting in further encroachment and in the long run the object sought when the covenant was imposed [being] completely defeated'. This consideration is referred to as the 'precedent value'; and
(d) whether there will be substantial injury is to be assessed by comparing:
(i) the benefits initially intended to be conferred and actually conferred by the covenant; and
(ii) the benefits, if any, which would remain after the covenant has been discharged or modified;
(e) if the evidence establishes that the difference between the two will not be substantial, the plaintiff has established a case for the exercise of the Court's discretion under s 84(1)(c) of the [Act];
(f) it is relevant to consider evidence of statutory planning provisions to the extent they show what realistically will be the result of the removal or modification of the covenant because 'it would be artificial and wrong to pay no heed at all to the reality of the situation';
(g) in considering whether the plaintiff has satisfied the Court that there will not be substantial injury:
(i) town planning principles and considerations are not relevant;
(ii) the absence of objectors to the discharge or modification of a covenant will not necessarily satisfy the onus of proof; and
(iii) each case must be decided on its own facts, and each covenant should be construed on its own terms and having regard to the particular context in which it was created;
(h) if the plaintiff satisfies the Court that there will be no substantial injury to the relevant persons, the Court has a residual discretion to refuse the application. The Court in exercising its discretion, may consider town planning principles and the precedent value.[17]
(a) the Perrys will retain views from their living room through the sliding door to the outdoor entertaining area, from the entertainment area itself, from the grassed area to the west of the Perrys' home, and from the upper portions of the Perry land;
(b) the evidence shows that the views from large areas of the Perry land are not impacted by the new dwelling;
(c) Mrs Perry's evidence that the construction of the new dwelling has reduced the sunlight reaching her home does not bear scrutiny given the evidence of Mr McIntyre;
(d) given that the purpose of the height restriction as to protect the views from the Perrys' home, not the value of the Perry land, then any potential depreciation in the value of the Perry land is not relevant to the question of substantial injury; and
(e) in any event, there is no admissible evidence of any diminution of value.
Determined objectively, the primary benefit intended to be conferred by the height restriction is the preservation of views across the valley for the purposes of protection of the amenity they provide from the whole of the [Perry] land. Those views are not simply enjoyed from a living room or a deck, but from the whole of the land. They provide for the [Perrys'] enjoyment of their land, they give a sense of openness, they provide a grand vista which is aesthetically pleasing and beneficial to health and wellbeing and they positively contribute to the value of the land.
For the purposes of the substantial injury test, it is irrelevant whether or not the [Perrys] intend to proceed with the second stage of their subdivision. It is irrelevant whether they intend to build a house on the upper part of their lot. It is irrelevant whether or not the [Perrys] intend to demolish their existing dwelling.
The height restriction covenant runs with the land. The benefit of the height restriction adds value to the [Perry] land both in a monetary sense, and in the sense of enjoyment of amenity. Regardless of whether the [Perrys] own the land, live in the existing dwelling, demolish the dwelling or subdivide the lot, the property right they enjoy as beneficiaries of the covenant is valuable, and they will suffer substantial injury if it is disturbed in the way intended by the modification.
Have the Perrys expressly or impliedly agreed to the modification of the height restriction?
In Re Clearwater Properties Ltd [2013] UKUT [210 (LC)], the President of the Upper Tribunal (Lands Chamber) Lindblom P said of the UK provision:
a) there must be clear evidence of consent to the specific outcome for which the applicant contends for a covenant to be discharged or modified under section 84(1)(b):
b) the inclusion of "implication" and "omissions" in section 84(1)(b) indicate that the paragraph does not require a legally binding contract:
c) the power under section 84(1)(b) to discharge or modify a restrictive covenant is widely drawn, and the concept of 'agreement' is a broad one:
d) critically, for present purposes, agreement may be established through acquiescence alone:
e) while all relevant facts must be considered, it is the consent of the beneficiaries to the covenant that must be shown:
f) when construing the beneficiaries' conduct, the test is objective:
[and]
g) the decision maker must be satisfied that agreement has been reached on the particular facts of the case:
(emphasis in original).
Consent may take various forms. These include active encouragement or inducement, participation with or without direct financial benefit, and express consent. Consent may also be inferred from silence and lack of activity with knowledge. The trustee must know of the consent prior to the breach.[30]
Defendant may apply for order
Where any proceedings by action or otherwise are taken to enforce a restrictive covenant any person against whom the proceedings are taken may in such proceedings apply to the Court for an order to be made under [s 84 of the Act].
Where it would be practically unjust to give a remedy, either because the party has, by his conduct, done that which might fairly be regarded as equivalent to a waiver of it, or where by his conduct and neglect he has, though perhaps not waiving that remedy, yet put the other party in a situation in which it would not be reasonable to place him if the remedy were afterwards to be asserted, in either of these cases, lapse of time and delay are most material.[40]
Now, as stated in many authorities, the principle upon which this equitable doctrine rests is that the plaintiffs are not entitled to relief if it would be inequitable to the defendant to grant it. In some of the cases it is said that the plaintiffs by their acts and omissions have impliedly waived performance of the covenants. In other cases it is said that the plaintiffs, having acquiesced in past breaches, cannot now enforce the covenants. It is in all cases a question of degree. It is in many ways analogous to the doctrine of estoppel, and I think it is a fair test to treat it in that way and ask, "Have the plaintiffs by their acts and omissions represented to the defendant that the covenants are no longer enforceable and that he is therefore entitled to use his house as a guest house?"[42]
Acquiescence as a defence to a claim for equitable relief is used in at least two different senses:
A person who is aware that an act is about to be done to his or her prejudice takes no step to object to it.
A person being aware of a violation of his or her rights which has occurred fails to take timely proceedings to obtain equitable relief. This is acquiescence after the event which founds the defence of laches.[44]
(emphasis added).
There remains the defence of acquiescence by Mrs Byrnes in the breach of trust. This, as explained by Deane J in Orr v Ford, is best understood as requiring calculated (that is, deliberate and informed) inaction by her or standing by, which encouraged Mr Kendle reasonably to believe that his omissions were accepted or not opposed by her.[45]
(emphasis added).
The plaintiff knew what his rights were. He never made any complaint or objection to the defendant at the time. His objection to the application for planning permission in respect of the bungalow and his complaints to his solicitors can avail him nothing. He made no complaint to the plaintiff until his solicitors wrote their letter of March 7, 1989, about three years after the acts complained of. He only complained of them then because of the much more serious threat presented by the proposed construction of the riding school. Before that he had effectively treated the conversion of the bungalow and the extension to the barn as incidents which were closed.
For these reasons, I would hold that the plaintiff acquiesced in the conversion of the bungalow and the extension to the barn, his acquiescence being a bar to all relief in respect of those matters.[47]
But oppression must be judged as at the date the court is asked to grant an injunction, and (as Brightman J. recognised in the Wrotham Park case) the court cannot ignore the reality with which it is then confronted.[49]
In the present case, the defendants acted openly and in good faith and in the not unreasonable belief that they were entitled to make use of Ashleigh Avenue for access to the house that they were building. At the same time, they had been warned by the plaintiff and her solicitors that Ashleigh Avenue was a private road, that they were not entitled to use it for access to the new house and that it would be a breach of covenant for them to use the garden of No 5 to gain access to No 5A. They went ahead, not with their eyes open, but at their own risk. On the other hand, the plaintiff did not seek interlocutory relief at a time when she would almost certainly have obtained it. She should not be criticised for that, but it follows that she also took a risk, viz that by the time her case came for trial the court would be presented with a fait accompli. The case was a difficult one, but in an exemplary judgment the judge took into account all the relevant considerations, both those which told in favour of granting an injunction and those which told against, in the exercise of his discretion he decided to refuse it. In my judgment his conclusion cannot be faulted.[50]
[I]t was necessary to make out a special case for the court to exercise its jurisdiction to award damages under Lord Cairns' Act which were not a standard remedy, whereby wrongful acts could routinely be sanctioned by the effective 'purchase' of the landowners' rights. Although the Court of Appeal emphasis that an injunction remained the prima facie remedy for trespass, it approved 'a good working rule articulated by AL Smith LJ in Shelfer v City of London Electric Light Co that provided guidance as to when, exceptionally, damages would be appropriate.
A special case can be made out that the plaintiff should be compensated by an award of damages in lieu of an injunction either when the plaintiff had disentitled himself to an injunction (by conduct such as delay) or where the four conditions of the good working rule were satisfied. The four conditions, which are cumulative, are -
(a) the injury to the plaintiffs legal rights is small;
(b) the injury is capable of being estimated in money;
(c) the injury can be adequately compensated by a small money payment; and
(d) it would be oppressive to the defendant to grant an injunction.
Whether these conditions are found will be fact sensitive in each case. Further, there may also be cases in which, though these four requirements are established, the defendant has, by conduct evidencing disregard for the plaintiffs rights, disentitled himself from asking that damages be assessed in substitution for an injunction.[55]
However, silence may give rise to an estoppel if, having regard to the nature of the relationship, the nature of the assumption, or the circumstances as a whole there is a duty to speak. In Thompson v Palmer, Dixon J observed that an estoppel may be established where a person remains silent, knowing the other person labours under a mistake in circumstances where there is a duty to correct the misunderstanding or identify the true position.
A duty to speak has been found in a number of cases where a person having title or right to property perceives another person as innocently, and in ignorance, conducting itself with reference to the property in a manner that is inconsistent with the existing title or right. In Waltons Stores, Brennan J, speaking of the circumstances in which a defendant induces a plaintiff to adopt an assumption or expectation, said:
For the purposes of the second element, a defendant who has not actively induced the plaintiff to adopt an assumption or expectation will nevertheless be held to have done so if the assumption or expectation can be fulfilled only by a transfer of the defendant's property, a diminution of his rights or an increase in his obligations and he, knowing that the plaintiff's reliance on the assumption or expectation may cause detriment to the plaintiff if it is not fulfilled, fails to deny to the plaintiff the correctness of the assumption or expectation on which the plaintiff is conducting his affairs.
Brennan J held that, once the defendant in Waltons Stores knew that the plaintiff was improving the land in the belief it held a lease, the failure to warn or to countermand that assumption was tantamount to a promise that the defendant would complete the lease.[59]
(a) their failure to take an active interest in the planning permit application, in circumstances where making an objection to the application would have prevented construction of the new dwelling even commencing;
(b) the Perrys learned of the likely breach of the height restriction following Mr Perry's conversation with Mr Grenfell in early June 2024 but took no action to verify their concerns until engaging a surveyor in February 2025;
(c) the Perrys spoke with the Jayasinghes in general terms about compliance with the height restriction, but failed to clearly articulate those concerns until they delivered the 24 February letter; and
(d) the Perrys spent two months in Darwin while the roof on the new dwelling was being constructed, and took no action to enforce the height restriction, even after first being confronted with the scale of the roof in late July 2024.
... when Mrs Perry left for Darwin, the height and the pitch of the roof could clearly be identified. Now, had they done any of these things, the application could almost certainly have been avoided. And as I say, at the time they left for Darwin, both [Mr and Mrs Perry] understood that there would be or there was already a significant breach of the [height] restriction. And, again, the [Jayasinghes] were continuing to spend money on the construction of their new home in reliance - and this is importance [sic] - in reliance on the [Perrys'] evident inaction.
Upon their return to Melbourne a couple of months later with the full extent of the roof form having been constructed, the [Perrys] still showed no interest in enforcing their property rights, and instead travelled to Echuca in Gippsland, again indifferent to the [Jayasinghes'] ongoing program of construction. In my submission, here can be no clearer set of circumstances that comprise acquiescence. If the [Jayasinghes] had not commenced this application themselves soon after receiving the [24 February letter], the [Perrys] might never have sought to enforce their property rights at all.[62]
So we say that a delay of six to 12 months [in] enforcing [their] property rights, while visited with the knowledge that the burdened parties were acting to their detriment, it's not just a regrettable oversight, it's an egregious dereliction of legal responsibility. And given the absence of any discretionary matters that might warrant the court declining to exercise its powers, the application before the court, we say, is one of the clearest contested cases for modification the court is ever likely to encounter.[63]
(a) requesting documents from the Council regarding the planning permit application, noting that the surveyor's report annexed to the 24 February letter did not contain any information which could not have been obtained from the planning permit application;
(b) clearly articulating those concerns to the Jayasinghes, or committing those concerns to writing; or
(c) seeking legal advice and bringing an action to enforce the height restriction.
It follows that by their acts or omissions, the [Perrys] have agreed by implication, to the Covenant being modified to accommodate the dwelling at [the Jayasinghes' property] as it exists today.
It must never be the case that the beneficiary to a restrictive covenant can turn a blind eye to an ongoing process of construction - in this case costing close to half a million dollars - before they act decisively to enforce their rights. A comparable application to cancel a planning permit would be statute barred under the Planning and Environment Act 1987 and there is a case where even a delay of 14 weeks has been sufficient for the Tribunal to refuse to grant relief.
A delay of six to twelve months in enforcing ones' property rights while visited with the knowledge that the burdened parties were acting to their detriment is not just a regrettable oversight, it is an egregious dereliction of legal responsibility.
This dilatory approach to the enforcement of the [height restriction] is curious if not baffling, but the only objective interpretation of the [Perrys'] conduct is that they:
a) were no going to commence proceedings to obtain equitable relief to enforce the [height restriction]; and
b) that they had waived any rights to enforce the [height restriction] and released the [Jayasinghes] from liability.
As far as the [Jayasinghes] were concerned, they were bound by a single storey height restriction, with which they complied, and they had a valid Planning Permit and plans endorsed pursuant to it. They were entitled to believe that, provided they built in accordance with this permission, they were honouring their lawful obligations:
The complexity of these contractual arrangements and the sensitivity of the [Perrys'] views from [the Perrys' home] to construction on [the Jayasinghe property], created a greater responsibility on the [Perrys] to take an active interest in the Planning Permit Application and for the [Perrys] to act quickly the moment they could see a potential breach of the [height restriction].
From July 2024, the [Perrys] understood that they had conveyed their concerns about the height of the dwelling to the [Jayasinghes], the [Jayasinghes] understood their dwelling would exceed the height restriction, and the ball was in the [Jayasinghes] court to do something about that exceedance.
The [Jayasinghes] could not have assumed from July 2024 that the [Perrys'] conduct conveyed agreement to modification of the height restriction covenant. The [Jayasinghes] had unilaterally decided not to act on the [Perrys'] concerns but did not convey the fact to the [Perrys]. Viewed in that context, it is unsurprising that the [Perrys] did not take further action until February 2025.
The [Jayasinghes'] assertion that the [Perrys] did not intend to enforce the covenant, or that they failed to send a solicitor letter earlier than February 2025 is not to point.
From July 2024, the [Jayasinghes] were on notice that their dwelling would exceed the height restriction that the [Perrys] were unhappy about that fact and were concerned for the [Jayasinghes] that their builder would hand over a dwelling which did not comply with the height restriction. This was proof positive to the [Jayasinghes] that the [Perrys] were not agreeing to modify the height restriction covenant.
In July 2024 the [Jayasinghes] knew, and objectively they ought to have known, that the [Perrys] did not agree to the dwelling exceeding the height restriction. In not responding to the [Perrys'] concern, nor taking steps to check for themselves whether the height restriction was complied with, the [Jayasinghes] adopted the risk associated with that decision. That is, that the [Perrys] could, at any time, seek to enforce their rights under the height restriction covenant.
(a) the plain words of the height restriction would indicate to a lay person, without technical knowledge, that there is a restriction on the height of a building which is allowed to be constructed on the [Jayasinghes' property], even if that lay person did not know the precise height of a building which would comply.
(b) it is patently obvious that a single storey dwelling can be a variety of heights and some single storey dwellings will comply with the height restriction, and some will not. It is not necessary to understand AHD, or to know how high the maximum allowable height is to understand this.
(c) it is not reasonable for the [Jayasinghes] to have assumed that the height restriction covenant simply required a single storey dwelling to be constructed on the land
(d) the single storey covenant on the [Jayasinghes' property] supports this view - there is no need for a height restriction and a single storey covenant if all that the height restriction means is that a single storey dwelling must be built
(e) further, if dwelling height on the [Jayasinghes' property] was governed by other regulations (as Mr Jayasinghe stated), there would be no need for a height restriction to be placed on the [Jayasinghe property]. The Regulations would do the work.
The [Jayasinghes'] attitude to the height restriction demonstrated a reckless disregard for the [Perrys'] rights under the height restriction from before the [Jayasinghes] signed the Contract of Sale, then continuing during the process of negotiating with Metricon and Live Well Homes, then during design of the dwelling, in applying for planning permission through their agent, Smart Town Planning, and finally by the [Jayasinghes] declining to alert the [Perrys] to their decision to ignore the [Perrys'] concerns and continue to build because they had obtained a planning permit to do so.
In admitting that he relied on the builder's opinion that there was no problem with the dwelling because of compliance with the Council approval, Mr Jayasinghe has acknowledged he understood that the [Perrys] believed there was a problem, and the [Perrys] did not believe their concerns were resolved. Nothing was said which would have resolved the [Perrys'] concerns.
Mr Jayasinghe also understood that the [Perrys] were not giving up their rights under the covenant, nor agreeing to modify it or not enforce it. Rather, Mr Jayasinghe believed the [Jayasinghes] were in a position to ignore the [Perrys'] concerns because they were complying with the planning permit they had obtained through Smart Town Planning.
From the time of the [July meeting], the [Jayasinghes] were on notice that their dwelling would exceed the height restriction and that the [Perrys] were not agreeing that they could exceed the height restriction and were not agreeing to modify the height restriction.
The [Perrys] put the [Jayasinghes] on notice that they should do something about the impending breach. The [Jayasinghes] chose not to respond to the [Perrys'] concerns, they chose not to check the height of their dwelling against the height restriction, and they chose not to stop the build. In doing so, they adopted the risk associated with their decision.
(a) after the July meeting, it was reasonable for them to believe that they had made it clear to the Jayasinghes that the new dwelling was likely to breach the height restriction, and that the Jayasinghes needed to address this issue;
(b) at no stage had the Perrys indicated that they would be content with a building that breached the height restriction;
(c) objectively speaking, it is highly unlikely that parties in the position of the Perrys would agree to alter the terms of the contract of sale so soon after the imposition of the height restriction;
(d) it was not necessary for the Perrys to object to the planning permit application, because if the Jayasinghes' town planner had referred to the height restriction in the planning permit application, the planning permit would never have been granted;
(e) the (late) evidence of the Jayasinghes regarding the Perrys' now abandoned plans to build a new home on the Perry land did not support the contention that the Perrys had 'run hot and cold on their intentions with respect to the height restriction', and Mrs Jayasinghe's evidence that Mrs Perry said she was not concerned about the views should not be accepted; and
(f) the Perrys submitted as follows:
They imposed the height restriction to protect views from their land. Once construction of the [new dwelling] commenced with the site cut, they started raising their concerns that the dwelling would breach the height restriction. Once the frame went up, in July 2024 they invited the [Jayasinghes] into their home to explain their concerns. Knowing the [Jayasinghes] understood their concerns, the [Perrys] felt the ball was in the [Jayasinghes'] court to do something about the height of their dwelling or the [Jayasinghes] risked being handed a non-compliant dwelling by their builder. When it became clear the [Jayasinghes] were not going to address the issue, the [Perrys] engaged their conveyancing lawyer to write to the [Jayasinghes the 24 February 2025 letter]. It took more than a month for the [Jayasinghes] to provide any substantive response to the 24 February letter.
best understood as requiring calculated that is, deliberate and informed inaction by [the plaintiff] or standing by which encouraged [the defendant] reasonably to believe that [the defendant's] submissions were accepted or not opposed by the plaintiff.[69]
It's not the subjective question of whether or not [the Jayasinghes] understood the height restriction and then took the [Perrys'] actions to be indicating agreement, it is whether it was reasonable for them to take the actions of the [Perrys] as accepting or agreeing to modification of the covenant. So there's an aspect of what a reasonable person, in the [Jayainghes'] situation, would understand was occurring.[70]
It is harder for the [Jayasinghes] to prove their case than if it was an older covenant or these weren't the original parties. A reasonable person in the [Jayasinghes'] shoes would not think that by not sending a solicitor letter earlier that the [Perrys] were agreeing to modify a covenant that they themselves had recently imposed for a particular purpose and have accepted in a contract, for which consideration was paid, and that they would agree to that with no compensation.[73]
And in my submission, the refusal to take any steps to understand the height restriction from the point in time at which the contract of sale was being considered and before it was executed, right through until the February 2025 letter was delivered, is a failure on the part of the [Jayasinghes] to take reasonable care to ensure they were compliant with the height restriction on their title. There's a lot of blame being passed to the [Perrys] for not policing the [Jayasinghes'] actions. There's very little responsibility here being taken by the [Jayasinghes] for the consequences of their actions.
It is my submissions that the transcript and the cross-examination of Mr Jayasinghe shows that he knew where the height restriction was and what it meant in terms of his dwelling breaching the height restriction. Contrary to the evidence affirmed in his affidavit material, he did not consider that the [Perrys'] concerns were resolved. Rather, what he did was ask his builder, 'Are you complying with the planning permit and are you complying with the contract?' When the building said yes, he stayed silent and thought to himself, 'I don't have to worry.'[74]
[The Jayasinghes] didn't tell the [Perrys] that [they were satisfied that they didn't have a problem because they had a planning permit]. They therefore continued to be on notice for the whole period up until because, from the [Perrys'] point of view, we have conveyed what our concerns are. Doesn't need a solicitor letter. It is clear that they are not agreeing to modify the covenant when they've got concerns.
It's kind of running the gauntlet of, well, we know they don't agree because we know they've got concerns, but we're just going to force them into taking more action or we know they don't agree to modify and we know they've got concerns, but we're not worried about it so we're just going to ignore it. The obligations is on the [Jayasinghes] to resolve that issue or to communicate to the [Perrys] that they don't consider they need to resolve that issue.[76]
[T]he only objective interpretation of the [Perry's] conduct is that they were not going to commence proceedings to obtain equitable relief to enforce the [height] restriction and that they had waived any rights to enforce the [height] restriction and release [sic] the [Jayasinghes] from liability.[80]
[T]he sophistication of the controls and the lack of tolerance, given that the Perrys' place was so close to the Jayasinghes' house, means that they should have been more aware of it.[81]
(a) that the Jayasinghes did not understand the Perrys' concern that the new dwelling would breach the height restriction; or
(b) that the Jayasinghes knew about the height restriction and knew that the new dwelling would breach the height restriction, but were pressing ahead regardless, in flagrant breach of the height restriction.
[M]ore commonly, acquiescence is used ... to refer to conduct by a person, with knowledge of the acts of another person, which encourages that other person reasonably to believe that his acts are accepted (if past) or not opposed (if contemporaneous).[86]
Finally I come to the question of exercise of discretion, assuming there was jurisdiction. I do not for myself think that the particular situation of the applicant, as having not very long since struck a bargain inconsistent with this particular outcome, is a factor in the exercise of discretion. I do not think that the personality of the applicant or his past behaviour is relevant to the exercise of the discretion. I refer again to the fact that tomorrow an assign may make the same application. I think that the decision (including the exercise of discretion) must be related to the property and its history as such.[96]
As early as Shelfer v City of London Electric Lighting Co the observation was made that a breaching party is not entitled to ask the court to sanction their wrongful act by purchasing their neighbour's rights through an assessment of damages, leaving the neighbour with the nuisance. In Wakeham v Wood, the court of appeal over-turned a decision to award damages at first instance for breach of a covenant protecting a view and a mandatory injunction was granted on the basis that damages would amount to allowing the breaching party to "buy his way out of his wrong". Here, the [Jayasinghes] seek to change the bargain they struck by regularising their substantial breach with no change to the purchase price they paid for their land.
Equity ought not provide a mechanism for a party to avoid its legal obligations under a common law contract. The [Jayasinghes] freely and voluntarily contracted to purchase land subject to a restriction, and within a matter of months took steps to execute a building contract which would result in a substantial contravention of that restriction.
Many of these criticisms can equally be levelled at the [Jayasinghes] who appear not to have taken any steps to ensure the dwelling proposed under the building contract would comply with the height restriction they had agreed to, did not look at their plans to work out whether the dwelling would breach, when concerns were raised by the [Perrys] they did not make their own enquiries to find out whether they were in breach, they did not arrange to have their own dwelling surveyed until after the [Perrys] had had it surveyed, did not instruct their builder to stop work on their dwelling until about 4 weeks after receiving the February 2025 letter, and did not provide any substantive response to the February 2025 letter for about 4 weeks.
(a) the professionals engaged by the Jayasinghes may well be liable to them for any costs or liabilities incurred by them by reason of the breach of the height restriction; and
(b) the Jayasinghes have overstated the hardship caused to them if they are required to comply with the height restriction, as not all of the costs of the construction of the new building will be thrown away if the application for modification is refused.
(a) the precise form of order to give effect to these reasons;
(b) whether any mortgagee of the Perry land should be notified of the orders made or proposed to be made;
(c) whether liberty to apply should be granted to the Perrys to apply for compensation in this proceeding, or whether this issue should be left to be dealt with in the related proceeding;
(d) the question of costs; and
(e) directions for the future conduct of the related proceeding.
[1] Similar covenants were also placed upon a further lot located on the other side of the Jayasinghe property and sold by the Perrys to another purchaser.
[2] The parent land was 6,200sqm in size, or approximately one and a half acres.
[3] Lots 1 to 5 on the plan of subdivision did not form part of the parent land.
[4] An amended planning permit was issued on 9 December 2020.
[5] Australian Height Datum 1971 (AHD71) is the official vertical datum (height reference system) used for measuring elevations and depths across Australia. Reference Point: AHD71 defines mean sea level as zero elevation. It was established by analyzing tide gauge observations from 30 coastal locations around mainland Australia over several years, with the measurements adjusted to represent mean sea level for the period 1966-1968. Purpose: It provides a consistent reference framework so that heights measured anywhere in Australia can be compared meaningfully. Without a standard datum, elevation measurements from different surveys wouldn't relate properly to each other. Source: Claude AI, Anthropic.
[7] These plans appear to have been prepared by another company, not the builder.
[8] There were three iterations of plans in evidence, dated 29 December 2022, 14 April 2023, and 15 June 2023. The latter set of plans were very detailed, which suggests that planning for the project was well advanced, but the date of these plans was also consistent with the Perrys' evidence that the project was abandoned in late 2023.
[9] However, given the size of the text showing the relevant measurements, and the way in which the height data was presented on the plan, a person inspecting the plans would require excellent eyesight and/or magnification and would need to understand what is meant by 'FFL' (finished floor level) and AHD in order to understand how high the new dwelling would be.
[10] A report prepared by an engineer, Mr Brendon Clark (see paragraph 63 of these reasons), provided examples of how the design of the new dwelling could be modified to comply with the height restriction by constructing a roof with a pitch of two percent.
[12] It is now common ground that the pitch of the roof of the new dwelling does not breach the restrictive covenant.
[13] In their affidavits, the Perrys asserted that the new dwelling was not at lock-up stage in May 2025 as claimed by the Jayasinghes, and that further works have been done at the Jayasinghe property without their consent, but it is not necessary to resolve these disputes for the purpose of the current application.
[14] Although there was no evidence to that effect.
[20] There was no admissible evidence about the impact of the construction of the new dwelling on the value of the Perry land (or on any part of the Perry land), but common sense suggests that there must be some impact.
[21] Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165, 180-1.
[22] I agree with the submission of counsel for the Jayasinghes to the effect that the agreement referred to in s 84(1)(b) of the Act is referable to the outcome of the modification, not any agreement to the amendment of the instrument itself.
[23] See, for example, Re Pivotel Pty Ltd [2000] VSC 264; (2001) V ConvR 54-635; Hillman v Dissayanake [2007] VSC 426; (2008) V ConvR 54-745, [58]; and Re Djurovic [2010] VSC 348, [10] and see also Re University of Westminster (1999) 78 P&CR 82, 90.
[24] See the statement to that effect in Adrian Bradbrook and Susan McCallum Bradbrook and Neave's Easements and Restrictive Covenants (LexisNexis Butterworths, 3rd ed, 2011) [19.126] n 238.
[28] See Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 35; (1998) 194 CLR 355, 384 [78], where the plurality stated as follows: 'Ordinarily ...the legal meaning...will correspond with the grammatical meaning of the provision. But not always. The context of the words, the consequences of a literal or grammatical construction, the purpose of the statute or the canons of construction may require the words of a legislative provision to be read in a way that does not correspond with the literal or grammatical meaning'.
[32] See Averono v Mbuzi [2005] QCA 295, [19].
[33] Here, the concept of acquiescence overlaps with the principles of laches, or delay, which may also deny a party injunctive relief.
[34] Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 35; (1998) 194 CLR 355, 381-2 [70].
[35] Perry Hertzfeld, Thomas Prince and Stephen Tully, Interpretation and Use of Legal Sources: The Laws of Australia (Thomson Reuters, 2013).
[38] Ibid [25.1.1980]. The reference to 'common law' extends to principles of equity.
[55] Manderson v Wright (No 2) [2018] VSC 162, [196]-[198].
[56] [1989] HCA 4; (1989) 167 CLR 316, 337-338.
[60] Byrne v Kendle [2011] HCA 26; (2011) 243 CLR 253, 279-80 [79]. See paragraph 132 of these reasons.
[61] By reason of s 61(4) of the Planning and Environment Act 1987 (Vic), which provides that the Council must refuse to grant a planning permit that would authorise a development that would breach a restrictive covenant.
[64] The Jayasinghes say that any application to cancel the planning permit would fail, as it would be too late, given that the new dwelling is almost complete.
[69] Perpetual Ltd v Myer Pty Ltd [2018] VSC 2, [127].
[82] Byrnes v Kendle [2011] HCA 26; (2011) 243 CLR 253, 280-1 [79].
[83] There is no direct evidence as to when the Perrys engaged their surveyor, but the inference I can draw from Mrs Perry's evidence about their travels is that they did not attend to such matters while they were away from home.
[87] In the title search for the Perry land annexed to the contract of sale for the Jayasinghe property dated 14 May 2025, reference is made to a mortgage in favour of Westpac Banking Corporation registered on 6 July 2016.
[93] However, that submission was only faintly pressed in closing submissions given Mr McIntyre's evidence to the effect that he expected the proposed modification would be approved by the Council.
[94] [2017] VSC 591 [77]-[79].
Jayasinghe
Perry [2025] VSC 751
(1998) 194 CLR 355
(2004) 219 CLR 165
(1992) 26 NSWLR 666
(2011) 243 CLR 253
(2007) 20 VR 311
(1989) 167 CLR 316