[2023] NSWLEC 40
Land and Environment Court (NSW)
2023-03-17
Pritchard J, Property Group P, Kindimindi Investments P
Original judgment source is linked above.
Rossi v Living Choice Australia Ltd [2015] NSWCA 244 Russian Commercial and Industrial Bank v British Bank for Foreign Trade Ltd [1921] 2 AC 438 Zaymill Pty Limited and Maksim Holdings Pty Limited v Ryde City Council [2009] NSWLEC 86 Zaymill Pty Ltd and Maksim Holdings Pty Ltd v Ryde City Council [2009] NSWLEC 142 Marshall Rural Pty Ltd v Basscave (No 3) [2018] NSWLEC 62 Great Lakes Council v Lani [2007] NSWLEC 681; (2007) 158 LGERA 1 Hill Top Residents Action Group Inc v Minister Administering the Sporting Venues Authorities Act 2008 (No 4) [2011] NSWLEC 6 Inner West Council v Balmain Rentals Pty Ltd [2019] NSWLEC 24 Texts Cited: P Herzfeld and T Prince, Interpretation (2nd ed, 2020) JD Heydon, M J Leeming, P G Turner, Meagher, Gummow and Lehane's Equity Doctrines and Remedies (5th ed, 2014) D Pearce, Statutory Interpretation in Australia (9th ed, 2019) Category: Principal judgment Parties: PAG Services Pty Ltd (First Applicant) Murray Curtis (Second Applicant) Byron Shire Council (Respondent) Representation: Counsel: P Tomasetti SC (First and Second Applicants) Submitting appearance (Respondent) Solicitors: McCartney Young Lawyers (First and Second Applicants) Marsdens Law Group (Respondent) File Number(s): 2022/321273 Publication restriction: Nil
Background and outcome
The evidence relied on by the applicants in the Class 4 proceedings
The Class 1 proceedings and development consent granted by Commissioner Murrell on 24 March 2004
The removal of the coastal cypress, the banksia and "various pruning"
Correspondence with Council about whether the 24 March 2004 development consent had lapsed
Legislation in relation to the lapsing of consent
Issues for determination in relation to whether the development consent granted by the Court on 24 March 2004 has lapsed
The applicants' submissions in relation to whether the development consent has lapsed
Was the work relied on building, engineering or construction work?
Did the construction work relate to the approved development?
Was the construction work physically commenced on the land to which the consent applied prior to the lapsing date?
Power of the Court to make the declaration sought by the applicants
The Court's correspondence with Council
Declaratory relief where there is no proper contradictor
Costs of the Class 4 proceedings
Whether costs should follow the event
Orders
Endnotes
PAG Services Pty Ltd
Byron Shire Council
[1998] NSWLEC 194
[1972] HCA 61
(2003) 127 LGERA 413
(2006) 147 LGERA 330
(1972) 127 CLR 421
(1977) 52 ALJR 180
(2005) 63 NSWLR 124
(1992) 81 LGERA 132
(2006) 143 LGERA 268
(1990) 170 CLR 534
(2019) 101 NSWLR 606
(2010) 177 LGERA 261
(1990) 169 CLR 356
(1998) 193 CLR 72
(2012) 188 LGERA 252
(2007) 158 LGERA 1
(2012) 201 FCR 378
(1993) 178 CLR 643
(2004) 211 ALR 231
(1981) 36 ALR 257
[1990] HCA 59
[1998] HCA 11