© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] NSWCA 26
Court of Appeal (NSW)
2018-10-25
Beazley P, Meagher JA, White JA, Pain J
Original judgment source is linked above.
etti SC with R O'Gorman-Hughes (Appellant) T F Robertson SC with J McKelvey (Respondent)
Solicitors: Swaab Attorneys (Appellant) Sparke Helmore Lawyers (Respondent) File Number(s): 2018/197301 Decision under appeal Court or tribunal: Land and Environment Court Jurisdiction: Class 4 Citation: [2018] NSWLEC 83 Date of Decision: 1 June 2018 Before: Pain J File Number(s): 2016/150312
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the decision] In a challenge to a decision of the Land and Environment Court, the appellant ("Cando") sought declarations that the primary judged erred in finding that Cando's development consent for the development of nine townhouses on a site in Guildford ("the Site") had lapsed, and that the primary judge erred in not making orders under s 124 (now s 9.46) of the Environmental Planning and Assessment Act 1979 (NSW) ("the EPA Act") to the effect that if certain remedial works were performed on the Site and certified by an independent expert, the site could be occupied and put to use by Cando without an occupation certificate. The issues at first instance were in substance the same as those on appeal. These were: (i) whether Cando's development consent had not lapsed because s 95(4) (now 4.53(4)) of the EPA Act prevented it from so doing as construction work relating to the land to which the consent applied had been physically commenced within five years of the grant of consent; and (ii) whether the Land and Environment Court could and should make an order under s 124 (now s 9.46) which would effectively sanction and authorise what would otherwise be a breach of the EPA Act. It was common ground both at first instance and on appeal that Cando's predecessor had performed "construction" work, including demolition, on the Site. This work also included the removal of trees and shrubs. It was also common ground that for such work to "relate to" the land the subject of the consent, the work had to be in accordance with, or at least not prohibited by, the consent. It was common ground that the demolition work was not in accordance with the relevant consent. At first instance, it was held, in relation to the first issue, that the development consent had lapsed as no work has been undertaken by Cando's predecessor on the site that "related to" the commencement of the building the subject of the development consent within five years of the grant of consent. In respect of the second issue, the primary judge held that the relief sought by Cando could not be considered because Cando had unsuccessfully resisted the respondent's case. The Court, allowing the appeal in part, held (per White JA, Beazley P and Meagher JA agreeing): As to issue (i): (a) Cando bore the onus of proof in establishing the matters necessary to prevent the consent from lapsing under s 95(4) (now 4.53(4) of the EPA Act (at [92], [97]). Drummoyne Municipal Council v Lebnan (1974) 131 CLR 350, considered. Vines v Djordjevitch (1955) 91 CLR 512; [1955] HCA 19, referred to. Director of Public Prosecutions v United Telecasters Sydney Ltd (1990) 168 CLR 594; [1990] HCA 5, referred to Chugg v Pacific Dunlop Ltd (1990) 170 CLR 249; [1990] HCA 41, referred to. Iron Gates Developments Pty Ltd v Richmond-Evans Environmental Society Inc (1992) 81 LGERA 132, referred to. Green v Kogarah Municipal Council [2001] NSWCA 123; 115 LGERA 115, referred to. K & M Prodanovski Pty Ltd v Wollongong City Council [2013] NSWCA 202, referred to. (b) The clearing of shrubs was construction work that was not demolition work, and should be distinguished from the clearing of trees. Although the clearing of trees was not shown to have been done in compliance with the consent, the same could not be said of the clearing of shrubs. It would therefore qualify as work "relating to" the land the subject of the consent (at [115]). Accordingly the consent did not lapse (at [118]). Hunter Development Brokerage Pty Ltd v Cessnock City Council (2005) 63 NSWLR 124; [2005] NSWCA 169, referred to. Owendale Pty Ltd v Anthony (1967) 117 CLR 539, referred to. As to issue (ii): The orders sought, if made, would require and authorise Cando to carry out remedial works without a construction certificate or the appointment of a principal certifying authority, and would purportedly authorise occupation of new premises without an occupation certificate, in breach of the EPA Act. Such orders are not authorised by s 124 (now s 9.46) of the EPA Act (at [136], [138]). Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335, referred to. F Hannan Pty Ltd v Electricity Commission of NSW (No 3) (1985) 66 LGRA 306, referred to. Great Lakes Council v Lani [2007] NSWLEC 681; 158 LGERA 1, referred to. Grace v Thomas Street Cafe Pty Ltd [2007] NSWCA 359; 159 LGERA 57, referred to.
Judgment
The Development Consent
Mr Refalo's evidence
Development application for use as a boarding house
Agreed facts
The parties' positions at trial
Primary Judge's reasons
Cando's Notice of Appeal
Grounds of appeal
The Council's Notice of Contention
Disposition
Onus of proof
Application to admit further evidence
Construction work through removal of shrubs
Cando's claim for relief under s 124(1)
Appropriate orders
Costs
Proposed orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 25 February 2019
Cando Management and Maintenance Pty Ltd
Cumberland Council
(1994) 34 NSWLR 155
(1990) 170 CLR 249
(1990) 168 CLR 594
(1974) 131 CLR 350
(1955) 93 CLR 435
(2002) 54 NSWLR 612
(2005) 63 NSWLR 124
(1992) 81 LGERA 132
(1967) 117 CLR 539
(1955) 91 CLR 512
(1987) 10 NSWLR 335
(2001) 115 LGERA 231