[2020] WASAT 57
State Administrative Tribunal (WA)
2020-10-02
Original judgment source is linked above.
CITATION : OWNERS OF STRATA PLAN 65323 and PALAZZO HOMES PTY LTD [2020] WASAT 57
Building service complaint - Meaning of 'carried out' a regulated building service - Nature of building contract - Contract specifications varied - Deficiencies in tiling system - Effect of acoustic mat on tiling system - Form of building remedy order
Building Act 2011 (WA), s 3
Building Regulations 1989 (WA), reg 13(1)(d)
Applicants successful in relation to conceded items, reimbursement items and items the Tribunal identified as unsatisfactory
Diploma Construction (WA) Pty Ltd v South Central WA Pty Ltd [2015] WASC 289
Gemmill v Sanders [2018] WASC 179
Hawke and Ennis [2018] WASAT 118
Jones v Dunkel [1959] HCA 8; (1959) 101 CLR 298
Lewis and Waco Pty Ltd [2016] WASAT 127
Primrose Meadows Pty Ltd v River View Pty Ltd [2019] VSC 263
Shami and Teo [2017] WASAT 73
Shaw v McLeod (unreported, WASC, Library No 4707, 8 November 1982)
The Owners of One Brighton Strata Plan 51948 and Pindan Pty Ltd [No 2] [2020] WASAT 3
(1) did Palazzo Homes carry out a regulated building service?;
(2) if the answer to (1) is in the affirmative, was the building work, the subject of each of the complaint items, faulty or unsatisfactory?; and
(3) if the answer to (1) and (2) is in the affirmative, what is the appropriate form of the building remedy order (if any)?
(a) remedy the building service as specified in the order;
(b) pay to an aggrieved person such costs of remedying the building service as the Tribunal considers reasonable and specifies in the order; and
(c) pay an aggrieved person a sum of money specified in the order to compensate the aggrieved person for the failure to carry out the building service in a proper and proficient manner or for faulty or unsatisfactory building work.
Background to the dispute and remaining complaint items
(1) The Principal engaged an architect, DesignWise Concepts, to design the Moritz and the Prestige (Buildings).
(2) On 27 August 2008, the Principal entered into a contract with Palazzo Homes for the construction of the Prestige. Palazzo Homes completed the forward works for the Prestige.
(3) The Prestige is located at 63 South Perth Esplanade, South Perth. It is a four storey residential apartment complex with four apartments and a roof deck. The City of South Perth (City) issued building licence no. 20.2009.551.1 to Palazzo Homes in respect of the Prestige on 12 August 2011. Practical completion of the Prestige was achieved on or about 4 December 2014.
(4) The Principal entered into a contract with Palazzo Builders Pty Ltd (Palazzo Builders) for the construction of the Moritz on 21 June 2010.
(5) The Moritz is located at 5 Ferry Street, South Perth. It is a five storey residential apartment complex which comprises seven apartments and two two-storey penthouses. The City issued building licence no. 30.2009/550 to Palazzo Homes in respect of the Moritz on 24 May 2010. Practical completion of the Moritz was achieved on or about 29 August 2013.
(6) The Strata Company is not a party to the building contracts (it was not a legal entity at the time the contracts were signed).
(7) The building licences for the Moritz and the Prestige were issued under the s 374 of the Local Government (Miscellaneous Provisions) Act 1960 (WA) and reg 13(1)(d) of the Building Regulations 1989 (WA) (1989 Regulations). These provisions have been repealed and replaced by the Building Act.
(8) The parties do not contest that the Buildings are a strata complex under Strata Plan 65323, the Buildings consist of multiple levels and the Strata Company is responsible for the common property of the Buildings.
(9) Of the 102 items that remain in dispute, 32 relate to the tiling system and waterproofing on the external areas and balconies of the Buildings. There are also a number of complaint items relating to work that the applicants contend was not performed or which varied from the contract specifications. The remainder of the items relate largely to water ingress issues and cracking in the internal render and brickwork of the apartments, and in the basement car park of the Prestige.
(10) Palazzo Homes contends that it did not construct the Buildings and, therefore, did not carry out a regulated building service for the purposes of s 5(1) of the Act. For this reason, Palazzo Homes contends that the Tribunal is unable to make any building remedy order against it under s 36(1) of the Act.
The conduct of the proceedings and expert evidence
(1) The builder is Palazzo Homes because it applied for and was issued the building licences for both the Moritz and the Prestige (Exhibit 1, p 1022). Mr Jujnovich gave evidence that Palazzo Homes collected the building licences from the City and paid for them (ts 361, 13 November 2019).
(2) All building licences for the building works were in the name of Palazzo Homes and no application was made to the City for the building licences to be amended or re-issued in the name of Palazzo Builders.
(3) The building contracts for the construction of the Moritz and the Prestige were between the Principal and Palazzo Builders. The Strata Company was not a party to the building contracts. The Principal received an email on 30 September 2015 in relation to practical completion (document 43, solicitor's letter dated 3 December 2019). The email was sent from Mr Jujnovich at a Palazzo Homes email address.
(4) Mr Jujnovich swore a statutory declaration on 25 October 2019 in which he stated that Palazzo Homes was the registered builder that constructed the residential apartments at 5 Ferry Street, South Perth and 63 South Perth Esplanade, South Perth (Exhibit 1, p 638).
(5) Palazzo Homes did not contest that it carried out a regulated building service in respect of the Moritz and the Prestige at the time the complaints were made to the Building Commissioner in April 2019 or prior to the Tribunal hearing.
(1) Palazzo Homes did not install a tiling system on the balconies of the Moritz and the Prestige that complies with the Building Code of Australia (BCA) and relevant Australian Standards. The water proof membrane does not continue past the edge of the balcony, down the face of the balcony and return back to the drip groove as required by AS 4654.2.
(2) The majority of the balconies have no perimeter expansion joints. This has caused the tiles to delaminate and become 'drummy'. Some tiles have lifted or 'tented'. In the Prestige, where there are compliant intermediate joints but no perimeter joints, there is no tenting and the 'drumminess' is less than at the Moritz where there is a lack of expansion joints.
(3) The sequence of the tiling system used by Palazzo Homes' contractors at the Buildings is not in accordance with the construction drawings. The drawings required the following sequence:
(4) The screed had not been prepared properly. The waterproofing on the roof and balconies had failed and there is water penetration into the building.
(5) There is no continuation of the waterproof membrane around the penetrations of the drain and the penetrations for the fixings of the balcony stirrups.
(d) the waterproofing has not been continued up the walls and has allowed water to enter.
(7) The acoustic mat used by Palazzo Homes is not the one specified in the detailed construction plans (plan 59 of 60, Rev 3, 3 August 2009). Even if a different acoustic mat was used, however, the tiling system would have failed because of the other workmanship deficiencies.
(8) The remediation of the tiling and waterproofing system at the Moritz and the Prestige is complex and warrants the appointment of an expert engineer to supervise the remedial work.
(1) Palazzo Homes contends that it is not the builder because the building contracts for the Moritz and the Prestige were between the Principal and Palazzo Builders, not Palazzo Homes. (The contract for the Prestige was initially between the Principal and Palazzo Homes but was subsequently replaced with a contract with Palazzo Builders).
(2) Mr Jujnovich provided evidence at the hearing that:
(a) Palazzo Homes did not build the Moritz, Palazzo Builders did;
(b) Palazzo Homes carried out the forward works in respect of the Prestige but did not otherwise build the Prestige, Palazzo Builders did; and
(c) Palazzo Homes did not receive any money from the Principal or invoice the Principal (except in relation to the forward works).
(3) Palazzo Homes accepts that it was the party that held the building licences but that does not contribute in any way to answering the question of who carried out the regulated building service within the meaning of s 36(1) of the Act. The holding of a building licence or permit does not equate to carrying out the registered building service.
(4) The only party that carried out a registered building service, by virtue of carrying out building work within the meaning of the Building Act, is Palazzo Builders.
(5) The Principal knew that Palazzo Builders was the builder as substantial correspondence was sent and certain permits were applied for and granted in the name of Palazzo Builders, including applications for occupancy permits and a building permit in respect of work for fire compartments (for example, documents 9 and 11, solicitor's letter of 3 December 2019). Palazzo Homes also provided to the Tribunal numerous examples of correspondence between the Principal and Palazzo Builders, including evidence of payments made by the Principal to Palazzo Builders.
(6) The Strata Company has actual or constructive knowledge that Palazzo Builders was the builder by virtue of the director of the Principal being the owner of a number of the apartments in both the Moritz and the Prestige.
(1) While there may have been minor departures from the BCA, the tiling on the balconies in both the Moritz and the Prestige was done according to the overall nominated design and in a proper and workmanlike manner.
(2) The key failing with respect to the tiling system arises out of the thermal expansion properties of the acoustic mat, the use of which was specified by the Principal and rendered the entire system (as proposed) doomed to fail.
(3) It was the thermal expansion properties of the acoustic mat that resulted in expansion causing water to permeate the moisture barrier into the screed. The screed was satisfactory prior to waterproofing.
(4) Any assertion that Palazzo Homes ought to have inserted control joints at every tile point would be entirely different from that which was required by the building contract and, in any event, would not be guaranteed to remain waterproof.
(5) As the burden rests with the applicants to establish that the work performed by Palazzo Homes on the overall tiling system was defective (including the waterproofing, screed and control joints), based on the evidence before the Tribunal, it is impossible for the applicants to successfully discharge that burden.
Did Palazzo Homes carry out a regulated building service?
For the purposes of s 36(1), s 37(1) and s 38(1) of the BSCRA Act, it is the entirety of the work of the building project which is carried out, not the components of it. What follows from that construction is that a building remedy order can only be made against the person who had the role of ensuring that the entire building project which includes the work which is the subject of a building service complaint was 'carried out', or in other words 'brought to completion'. It does not matter whether the work was done personally by that person or by persons whom they arranged to perform the various components of the overall work.
What is made clear in the decision of Shami is that the entity who has carried out the regulated building service for the purposes of the BSCRA Act is not necessarily the person on site undertaking the mechanics of the work but is that entity which is responsible for the entirety of the building project. It is the entity who has the role of ensuring that the entire project is carried out and brought to a completed state.
... While there are some complaints that I have offered to remedy (such as those relating to water ingress and other miscellaneous complaints that may be describe[d] as building issues), there are a range of complaints that are clearly not the respondent's responsibility. These relate, for example, to complaints which are based on design defects or are the result of fair wear and tear and are maintenance issues.
In relation to these complaints, the Owners and Allset appear to have misunderstood my role as a builder, which is to construct a building according to the design and instructions provided. It is not my role to rectify design defects which are selected by the client and given to me.
Was the building work, the subject of each complaint item faulty or unsatisfactory?
The tiling system, waterproofing and control joints
... it was open to the Tribunal to be satisfied that the construction of the drainage works which the appellant carried out was unsatisfactory because insufficient underground stormwater storage was constructed to comply with the requirements of the [Australian Rainfall and Runoff - A Guide to Flood Estimation] and accommodate a one in 10-year storm event. The Tribunal was not precluded from being so satisfied by the fact that the appellant had received professional engineering advice from a contractor as to the volume of underground water storage which should be constructed.
What is the appropriate building remedy order (if any)?
I do agree that in light of the Tribunal's clear and unambiguous findings made about the method that is to be implemented to make good the cornices and ceilings, to simply state in the order that Gemmill Homes is required to remedy the effect of all cracking is not to specify how the regulated building service is to be remedied. Put another way, an order that simply required Gemmill Homes to remedy the effect of the cracking is not to implement the findings made by the Tribunal as to how the defects in the work were to be remedied.
(a) the items it has agreed to remedy in Annexure A being items 10(a), 16, 17, 23, 24, 32, 33, 34, 35, 39, 43, 49, 50, 51, 54, 55, 58, 61, 62, 64, 65, 66, 69, 70, 72, 74, 77, 78, 82(b)-(e), 84, 85, 86, 92, 93, 118, and 126 of the Scott Schedule; and
(b) the items in Annexure B that the Tribunal has identified as unsatisfactory being items 7, 20, 21, 25, 30, 37, 38(b), 38(c), 41, 47, 48, 53, 63, 71, 76, 82(a), 87, 88, 89, 90, 91, 96, 99, 100, 103 of the Scott Schedule.
(a) the items it has agreed to remedy in Annexure C being items 6, 8, 9, 10, 11, 12, 14, 15, 16, 17, 23, 25, 26, 32, 36, 44, and 49 of the Scott Schedule; and
(b) the items in Annexure D that the Tribunal has identified as unsatisfactory being items 4, 5, 7, 13, 29, 30, 31, 38, 43, 45, and 48 of the Scott Schedule.
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
Annexure A - Items of complaint conceded by Palazzo Homes in CC 888 of 2019 (common property)
Apartment 2 - Uncontrolled condensate in corrosion of louvres and deterioration to tiling
Conceded. Palazzo Homes will connect overflows and direct to drains.
Water coming down cavity. Water damage to sill, wall and skirting.
Horizontal crack along both walls about floor, south west corner. Face of wall either side of crack. Not flush.
Apartment 6 (next to lift well). Air conditioning installation -Uncontrolled condensate from air conditioning unit. Discharges from P.G.I. Tray under and spills down face of louves, adding to spillage at Level 1.
Conceded. Palazzo Homes will connect and discharge into adjacent drain.
Apartment 7 (next to lift well). Air conditioning installation -
Uncontrolled condensate from air conditioning unit. Discharges from P.G.I. Tray under and spills down face of louves, adding to spillage at Level 1
Conceded. Palazzo Homes will connect and discharge into adjacent drain.
Dining Room - Cracks have developed in ceiling flush joins in both directions. Flush joins have not been offset as required by "Gyprock Residential Installation Guide".
Entry - Flush join near kitchen wall is delaminating.
Kitchen - Cracking in bulkhead radiating from window pelmet.
Laundry cupboard - Hole 200 x 8mm in ceiling recess.
Bathroom - Water ingress through ceiling above vanity, resulting in nail ' popping' and staining.
Bedroom 3 - Water ingress resulting in damage left hand end of window pelmet.
Top Landing Stairs - No flexible joint between floor tiles and door frame.
Laundry cupboard - Hole in ceiling recess approximately 200 x 8mm
Living Room (Ceiling) - Water ingress resulting in damage to ceiling adjacent to powder room. The damage is directly below column in east wall of Apartment 8 master suite over.
(Ceiling) - Crack radiating from south east corner of skylight.
Conceded. Palazzo Homes will remedy (ts 158, 12 November 2019).
Entry Hall - Extensive water ingress resulting in damage along north wall.
Balcony #1 - Window head and underside of soffit not parallel. The surfaces vary 20mm over 1.2m, the gap has been roughly filled and is visible.
Mr Harrison gave evidence that the item could be remedied by the installation of new purpose-made pressing (ts 159, 12 November 2019).
Conceded in part. Palazzo Homes will perform the works recommended by Mr Harrison.
The Tribunal accepts the evidence of the Mr Harrison in relation to the manner in which the work is to be remedied.
Apartment 13 (not apartment 4) - Cracking to parapet walls. Cracking in parapet render up to 2mm wide on south elevation and west elevation return.
Powder Room Ceiling (Opposite kitchen) - Water ingress around exhaust fan. Staining and damage to ceiling.
Bedroom 1 Windows - water ingress has caused damage to west window sill, wall from sill to floor right hand end. South window right hand side to ceiling to floor. Plater reveal head west window.
Bedroom 2 Windows - Water ingress along north window head and sill has caused damage.
Outdoor Living (Tiling and drainage) - No perimeter or intermediate control joints to tiles area exit. Door from stairwell has no stepdown onto deck.
BBQ Recess - Tiles delaminating external corner west end
Foyer - Water ingress. Left hand side of doors to stairs damaged set coat and skirting.
Public Lobby - Water ingress external corner left hand side of lift. Set court damages to F.L. up wall 600mm.
Conceded. Palazzo Homes will remedy (ts 163, 12 November 2019).
Carpark - Wall finish blistered top of wall left hand side of carpark #12. Possibly from water ingress.
Common Terrace (Opposite BBQ) - Upstand tiles delaminating. No intermediate movement control.
Stairwell (Ground to Level 1) south wall - Staining from water penetration form plantar box behind, along "V" joint
Parapet construction not in accordance with Fig 2.5 or 2.6. Detail AS 4654.2 waterproofing membranes for external above - Ground use in particular:-
No coping or metal capping to top of parapet and/or
Architectural drawing floor plan - Level 3 and roof plan - notation states - "limestone cladding to wrap over and down to slab".
Whole of complex ie '"The Prestige" fire rating - Service duct and services continuous from ground floor to third floor and access hatches not fire rated.
Services penetrating wall between ground floor foyer and void under stairs to common area Level 1 have non-compliant seal.
Termite Treatment - Unable to locate reticulated system specified on page 2 of 2 of Selection Schedule". Palazzo Homes to provide details of system for maintenance requirements.
Termite Treatment - Unable to locate termite system for servicing.
Undercover carpark - services penetrations not fire rated - Some service pipe penetrations do not have compliant seals through ceiling.
Undercover Carpark- Storeroom 6 - Door into store 6 has no fire rated seals or hardware.
Ensuite - Shower recess ceiling - Water damage to ceiling along north and west walls after shower in Apartment 6 above is used.
The Strata Company is seeking an order to pay in the sum of $6,487.80 as the remedial works have been completed (see Resources Contractors Group invoice 10.01 dated 27 November 2019).
The Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Palazzo Homes is to pay the Strata Company the amount of $6,487.80 (inclusive of GST) for the costs of remedying the building service.
Water Damage south East corner of Master Suite - Evidence of water ingress bottom of right hand window. Window reveal - ie paint peeling.
W.I.R. (master suite) - Staining to ceiling from water ingress north east corner directly under metal roof over.
Annexure B - Items of complaint disputed by Palazzo Homes in CC 888 of 2019 (common property)
Storeroom 6 - Water ingress north west corner of store and around pier in Apartment 6 carpark abutting
Mr Harrison gave evidence that there is water ingress in the corner of the storeroom due to a failing of the waterproofing in that area. In his opinion, it was not connected to the work on the adjoining site (ts 127, 12 November 2019).
Palazzo Homes contends that this is a maintenance issue due to a failure to clean the gutters. A drainpipe immediately adjacent to the corner was blocked with a plastic bag and a pile of leaves (ts 127, 12 November 2019).
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that the Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Apartment 1 - Unable to locate condensate discharge point
Apartment 1 Ensuite/W.C. - Water ingress in ceiling above W.C. ensuite.
Mr Harrison gave evidence that there was water ingress and evidence of staining on ceiling along face of plumbing duct above W.C. ensuite (ts 129, 12 November 2019). The probable source of the damage is water tracking from plumbing associated with ensuite in unit above (in ceiling space); failure of waterproofing to ensuite floor of unit above; water tracking down duct from unidentified source from levels 1&2 (Exhibit 1, p 319).
The statement by Mr Harrison that water ingress from any source is faulty work is unfounded and insufficient to establish liability.
The Tribunal accepts the evidence of Mr Harrison and finds that there is water ingress in the ceiling above the W.C. ensuite which is due to poor workmanship being a failure in the plumbing associated with the ensuite in the unit above and the failure of the waterproofing.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Uncontrolled condensate discharge resulting in corrosion of louvres and deterioration to tiling.
Collection tray under unit continuously holding condensate (health problem)
No waterproof membrane at edge of balcony and edge detail not in accordance with AS 4654.2 Waterproofing Membranes Section.
Non-compliance with AS 3958.1 installation of ceramic tiles clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Air conditioner installation - Same as for Apartment 2, Item 7
Tiling - Many tiles have "drummy" sound when tapped.
There are no perimeter or intermediate control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 waterproofing membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
(off Bedrooms 2 and 3) Tiling - Many tiles have "drummy" sound when tapped.
There are no perimeter or intermediate control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 waterproofing membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Air conditioner installation - Same as for Apartment 2, Item 10
Tiling - Many tiles have "drummy" sound when tapped.
There are no perimeter or intermediate control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 waterproofing membranes Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Note: This balcony adjoins tiled roof area over garages below providing a continuous tiled area and is defined by a glass balustrade i.e. adjoins
"common property'' - Many tiles have "drummy'' sound when tapped.
There are no perimeter or intermediate control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 waterproofing membranes Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Water ingress - Water ingress as window sill damaging wall and skirting
Mr Harrison gave evidence that there is water damage to the window sill and skirting from water ingress (ts 131, 11 November 2019).
Mr Harrison was unable to determine the source of the water ingress (or provide an opinion on the issue) and, therefore, could not attribute any faulty workmanship to Palazzo Homes.
The Tribunal accepts the evidence of Mr Harrison of water ingress at this location and finds that it is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison's evidence is that there is a vertical crack under the window in the lift lobby.
Mr Harrison was unable to determine the cause of the crack (or provide an opinion on the issue) and, therefore, could not attribute any faulty workmanship to the Palazzo Homes.
The Tribunal accepts the evidence of Mr Harrison that the crack was not caused by movement as the building sits on piles (ts 133, 12 November 2019). The Tribunal finds that there is a vertical wall crack in the lift lobby and that it is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Discharges from P.G.I. Tray under and spills down face of louvres, adding to spillage at Level 1.
Water ingress above window - Evidence (staining) of water ingress left hand top corner of window
Mr Harrison gave evidence that there is water damage from water ingress above the window (ts 134, 11 November 2019).
Mr Harrison was unable to determine the source of the water ingress (or provide an opinion on the issue) and, therefore, to attribute any faulty workmanship to Palazzo Homes.
The Tribunal accepts the evidence of water ingress at this location and finds that it is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Level 4 behind stairwell on the roof) - Installation not in accordance with DWG No 5 i.e. 2 units not 1.
Condensate discharges uncontrolled onto the roof area.
Access to units for servicing is via climbing parapet wall or glass safety balustrade.
Tiling - Majority of tiles have "drummy" sound when tapped.
Two tiles easily lifted north east corner adjacent to column
Not waterproof membrane to upstand and membrane stops short of wall.
Cracked tiles under glass balustrade shoes and around drain.
No waterproof membrane to edge of balcony and edge detail not in accordance with AS 4654.2 Waterproofing Membranes Section.
Water ponding around floor drain outside dining room door.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Note: Outdoor Living common. Adjoins tiled roof areas that form the roof for Level 3. Under the Outdoor Living is defined by glass balustrade - Many tiles have "drummy" sound when tapped.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
(West side) - Palazzo Homess repair to "plywood" soffit visible.
Mr Harrison gave evidence that an area of 10 x 50mm has been poorly repaired and is clearly visible from normal viewing position (ts 134, 11 November 2019).
There is no evidence as to when the alleged damage occurred or who carried out the relevant repair work. There is no evidence that Palazzo Homes performed the alleged faulty work.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Walls) - Gyprock lining to staircase walls is "fractured" and there are many horizontal and diagonal cracks.
Mr Harrison gave evidence that the gyprock lining hasn't been fixed in accordance with the gyprock code. The cracking of the gyprock has occurred because there is no clearance and is due to poor installation (ts 135, 136, 11 November 2019).
Mr Harrison acknowledged in cross-examination that the significant crazing and cracking in the gyprock could have been a result of movement in the building.
The Tribunal accepts the evidence of Mr Harrison and finds that the cracking of the gyprock is due to poor installation.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Master Suite - Previous repairs to ceiling clearly visible.
Mr Harrison's evidence is that the poor flushing of repairs in finished work is faulty work (Exhibit 1, p 341).
There is no evidence that Palazzo Homes carried out the repair work. The item was not listed in the defects inspections performed as provided by Palazzo Homes at documents 12-16 and 40-42, solicitor's letter of 3 December 2019.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Bedroom 3 - Previously repaired horizontal crack near air conditioning vent has reappeared.
Mr Harrison gave evidence that a hairline horizontal crack has developed on the left hand side of the AC vent (Exhibit 1, p 344). The crack happened during the construction stage, prior to the building next door being built (ts 137, 11 November 2019).
The statement by Mr Harrison that the majority of the cracks reported on happened during the construction of the building appears to be pure conjecture. The cracking was not identified in construction reports and defects punch lists produced by Palazzo Homes.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Damage to top left hand window reveal and staining on walls down to floor.
Mr Harrison gave evidence that there is water staining on the walls down to the floor from water ingress (ts 139, 11 November 2019).
Mr Harrison was unable to determine the source of the water ingress (or provide an opinion on the issue) and, therefore, to attribute any faulty workmanship to Palazzo Homes.
The Tribunal accepts the evidence of Mr Harrison of water ingress at this location and that it is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Bedroom 3 - Horizontal crack left hand side of window sill.
"Map" cracking visible top of wall between window and corner.
Plaster reveal to sill delaminating from sub-strate.
Mr Harrison gave evidence that the 'map' cracking is caused by workmanship (the application of the plaster) and that moisture is causing delamination of the set coat from the float coat in relation to the reveal. In Mr Harrison's opinion, it is a moisture problem (ts 140, 11 November 2019).
Mr Harrison acknowledged in cross-examination that the horizontal crack to the left hand side of the window sill could have occurred as a result of movement.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate the complaint item in relation to the horizontal crack. However, the Tribunal accepts the evidence of the Strata Company's witness in relation to the 'map' cracking (item 38(b)) and the reveal (item 38(c)) and finds that the observed faults are due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to item 38(b) and item 38(c), Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Bedroom 4 - Horizontal crack left hand side of air conditioning vent.
Mr Harrison gave evidence that the horizontal joint might have been fractured when the hole was formed (ts 142, 11 November 2019). The crack has recently appeared (Exhibit 1, p 344).
The cracking is of a minor nature and as a result of the normal expansion and contraction of building materials (Mr Marocchi's report, Exhibit 1, p 1065). There is no direct attribution by the Strata Company of faulty workmanship.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Entry - Hole in ceiling next to downlight, over size hole for light fitting.
Mr Harrison gave evidence that a hole had been drilled in the ceiling that was too large for the fitting or in the wrong location. The patching has not been successful and is unacceptable workmanship (Exhibit 1, p 347; ts 150, 11 November 2019).
There is no evidence as to when the alleged damage occurred or who carried out the relevant repair work. There is no evidence that Palazzo Homes performed the alleged faulty work.
The Tribunal accepts the evidence of Mr Harrison and finds that the defect in the ceiling is the result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Level 4 behind stairs on roof) - Air conditioning unit not mounted on top AAT section.
Condensate spills uncontrolled across roof top tiles damaging tiles.
Access for servicing unit is via scaling glass safety balustrade and walking around roof or climbing BBQ and walking across lift shaft roof.
Bedroom 3 - Horizontal crack left hand side of air conditioning vent.
Mr Harrison's evidence is that the cracks have recently developed and recommends monitoring the crack (Exhibit 1, p 350).
The cracking is of a minor nature and as a result of the normal expansion and contraction of building materials (Mr Marocchi's report, Exhibit 1, p 1065). There is no direct attribution by the Strata Company of faulty workmanship.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
Bedroom 2 - Horizontal crack left hand end of window sill and vertical crack central below window.
Mr Harrison's evidence is that the cracks have recently developed and recommends monitoring both cracks (Exhibit 1, p 350). The vertical crack is not a step crack so it's not following the brick course and, something is happening behind the crack (ts 153, 11 November 2019).
The cracking is of a minor nature and as a result of the normal expansion and contraction of building materials (Mr Marocchi's report, Exhibit 1, p 1065). There is no direct attribution by the Strata Company of faulty workmanship.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(between Levels 3 and 4) - Many cracks and fracturing of Gyprock lining both sides of stairs.
Mr Harrison gave evidence that the gyprock lining has not been fixed in accordance with the gyprock code. The cracking of the gyprock has occurred because there is no clearance and is due to poor installation (Exhibit 1, p 350).
The cracks and fracturing in the gyprock are the result of the ordinary wear and tear of the building. Mr Harrison acknowledged in cross-examination that the significant crazing and cracking in the gyprock could have been a result of movement in the building.
The Tribunal accepts the evidence of Mr Harrison and finds that the cracking of the gyprock is due to poor installation.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Top landing) - Crack in bulkhead where plaster and gyprock join.
Mr Harrison gave evidence that the crack in the bulkhead was caused by the absence of a v-joint between two different materials. It was not a design error but poor workmanship (ts 154, 12 November 2019).
The Tribunal accepts the evidence of Mr Harrison that the gyprock and plaster set wall move at different ratios and the crack occurred due to the absence of a v-joint (ts, 154, 12 November 2019). The Tribunal finds that the crack in the bulkhead was caused by poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
(North wall) - Vertical crack, top left hand side of north window.
Mr Harrison gave evidence that a vertical crack has developed in this location and should be monitored (Exhibit 1, p 353).
Mr Harrison acknowledged in cross-examination that it is only a hairline crack which should be monitored. There is no allegation of defective work.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(West wall) - Vertical crack in "gyprock" warping 1 mm from left hand end of wall.
Mr Harrison's evidence is that the cracking to the gyprock flush join is faulty work. The crack is in the gyprock cladding of the wall and should be raked out, reflushed and painted (Exhibit 1, p 354).
Mr Harrison was unable to identify a fault and conceded that it may be the result of movement.
The Tribunal accepts the evidence of Mr Harrison that the flush join has moved and has not been done correctly (ts 157, 12 November 2019) and, therefore, the Tribunal finds that the crack in the gyprock is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
(Outside kitchen tiling) - Many tiles have "drummy" sound when tapped.
No waterproof membrane to edge of balcony and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Wall cracks - Cracks in south north and east walls.
Mr Harrison gave evidence that there was drummy render along the east wall track which suggests there is something going on behind the plaster. Cracks greater than 1mm are considered to be faulty work (Exhibit 1, p 359; ts 158, 12 November 2019).
The cracking is minor and as a result of normal movement in the building. Mr Harrison was unclear as to the cause of the cracking.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Tiling - Many tiles have "drummy" sound when tapped.
No waterproof membrane to edge of balcony and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
A channel drain has been installed north/south across balcony with no joint between drain and tiles.
There is a distinct variation in tile colour i.e. 2 visible areas.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
(Level 4, Roof Terrace) - The tiling to outdoor living areas for Apartments 8 and 9 and roof top tiling form the majority of roof cover for Level 3 below with parapet walls, lift shafts and glass balustrade separating the level plane of the roof.
The defects to the tiling across Level 4 are consistent with those described in Item 2 of Apartment 8 "Building Complaint Form" dated 21 March 2019.
The roof top and outdoor living tiling is inseparable.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Mr Harrison stated in evidence that the flush join had not been done very well. The east/west flush join is clearly visible when viewed in accordance with AS/NZS2589. The join was not filled and sanded properly (Exhibit 1, p 387; ts 161, 12 November 2019).
The nature and extent of the alleged defect does not amount to faulty work. The alleged defect was not visible.
The Tribunal accepts the evidence of Mr Harrison that the flush join was not filled and sanded properly. The Tribunal finds that the defect is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Condensate discharges onto tiled floor into floor waste.
It is not containing as recommended by manufacturer.
Condensate should not discharge into sewerage system.
Access for removal of unit if required is only via crane through louvres.
Electrical connections not compliant with manufacturer's instructions.
Mr Harrison gave evidence that the item involves a formed finished panel and you can see where it has dislodged. It's not in line (ts 163, 12 November 2019).
There is insufficient evidence to establish faulty work and liability under the Act.
The Tribunal accepts the evidence of Mr Harrison and finds that the dislodged panel is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that there is a wall crack at the back corner in the car park. There is something causing the crack other than just movement (ts 163, 12 November 2019).
The cracking is minor. Mr Harrison's description of the cause of the crack is insufficient to attribute a finding of faulty work.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Unroofed area) - Cracking along "V" joint between slabs and beam east end of open area.
Mr Harrison gave evidence that there was some cracking 25mm away from the v-joint. Cracking parallel to v joints in not what it's meant to do and there's some water -staining along the crack (ts 164, 11 November 2019).
The cracking is minor and not the result of faulty workmanship. See Mr Marocchi's report, Exhibit 1, p 1065.
The Tribunal accepts the evidence of Mr Harrison and finds that the cracking parallel to the v-joint is the result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
All window and door openings and masonry walls (every level) - No flexible sealant to openings in masonry walls
Mr Harrison gave evidence that he did not detect sealant between any of the openings and the finish aquatex coat (ts 165, 12 November 2019).
The evidence of a third party professional, Mr Shane Winchester of Revaglass, is that the sub framing and angle trims appeared to have fixings and Polyurethane sealant/adhesive to the masonry walls. There have been no complaints or observations of water damage in relation to any of the windows or masonry walls surrounding the windows in the properties (see document 37, solicitor's letter of 3 December 2019).
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, in light of the evidence of Mr Winchester, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Repairs to upstand tiles to moat incomplete. Finish to wall discoloured.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Upstand tiles to rear of service area north east corner delaminating
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
North and west elevation - Horizontal cracking up to 2mm wide along parapet approximately 100mm from top.
Mr Harrison gave evidence that this is similar to the cracking on the parapet walls.
The cracking is minor and not the result of faulty workmanship. See Mr Marocchi's report, Exhibit 1, p 1065.
The Tribunal accepts the evidence of Mr Harrison and finds that the cracking is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
(Level 4) - Architectural drawings A3-53 and 54 notation states:
"Provide waterproofing layer to slab and again to screed prior to laying tiles or as per approved system".
No evidence that a double W.P.M system was installed.
Service duct and services continuous from ground floor to third floor and access hatches not fire rated.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
(a) Ceiling from grid lines 4 to 9, texture coating omitted.
(c) Beams and columns not texture coated grid lines 5 to 9.
Mr Harrison gave evidence that the carpark ceiling grid lines 4 to 9 in the central section has not been texture coated as required by the drawings (ts 167, 12 November 2019). There has been no evidence produced by Palazzo Homes to show that this item was excluded from the specifications of the contract.
This item is excluded from the specifications, despite being on the drawings. Painting and texture coating is only required to the balcony and not the garage. It is not standard practice to texture coat beams and columns in carparks. No issues were raised with this work at completion.
The Tribunal accepts the evidence of Mr Harrison and finds that only part of the car park has been texture coated. (ts, 168, 12 November 2019). The Tribunal finds that the reference to the 'finishes' for the 'garage internal walls' at Exhibit 1, p 655 of the contract specifications for the Moritz does not refer to the precise location of those 'finishes' in the undercover carpark. The Tribunal finds that the failure to complete the texture coating of the carpark in accordance with the drawings is poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Undercover Carpark Exit Door - Clearance under exit door (north elevation) has excessive gap at F.L. and door is delaminating.
Mr Harrison gave evidence that the door has a 30mm gap underneath, that it had not been sealed with a waterproofing strip across the bottom, and that it is delaminating. The doors are to be totally sealed after they have been fitted (ts 170, 12 November 2019).
Palazzo Homes made the decision to raise the door to protect it from water because of the presence of reticulation. This decision does not amount to faulty work. The delamination is not the fault of Palazzo Homes.
The Tribunal accepts the evidence of Mr Harrison and finds that the door is delaminating because the base of the door has not been sealed.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that along the box gutter adjacent to storeroom 6 there is water ingress. The box gutter is leaking at the join (ts 172, 12 November 2019).
The position of Palazzo Homes is that the gutters have not been appropriately cleaned. (The blocked drain is shown in a photograph being document 33, solicitor's letter of 3 December 2019). The box gutters were installed according to design and any issues experienced are the result of a failure of maintenance.
The Tribunal accepts the evidence of Mr Harrison and finds that there is water ingress at the join. The Tribunal further finds that this is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison's evidence is that there is no overflow provision to the box gutters.
The position of Palazzo Homes is that the gutters have not been appropriately cleaned. (The blocked drain is shown in a photograph being document 33, solicitor's letter of 3 December 2019). The box gutters were installed according to design and any issued experienced are the result of a failure of maintenance.
The Tribunal accepts the evidence of Mr Harrison and finds that there is no overflow provision to the box gutters. The Tribunal further finds that this is due to poor workmanship.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Public Lobby - water ingress - Water ingress in bulkhead on gridline 6 -A to B,
Mr Harrison gave evidence that there is water ingress in the bulkhead as you enter the public lobby (ts 173, 12 November 2019).
Palazzo Homes was unable to verify this complaint following inspection. There was no damage or defect sighted.
The Tribunal accepts the evidence of Mr Harrison and finds that there is water ingress in the bulkhead. The Tribunal finds that this is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Undercover Carpark - Additional wall installed between Storeroom 5 and 9 - Additional Wall constructed between storerooms 5 and 9 with non-compliant fire door. Wall is not brick or nominated on floor plan.
Mr Harrison gave evidence that there is an additional wall built in the undercover carpark and that it was not brick. He was not aware whether it had been fire proofed and certified. It was not on the drawings provided to him.
Palazzo Homes has produced the fire door certificate, certificate of design compliance for the car park wall and the occupancy permit (document 9, 10 and 20 respectively, solicitor's letter of 3 December 2019).
The Tribunal accepts the evidence of Palazzo Homes, including that of Mr Jujnovich in relation to reducing the area of the carpark to achieve a certain fire rating (ts 345, 13 November 2019), and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Common Gym - Exit door to pool area - Exit door to pool area non-compliant and safety hazard (door lock).
Mr Harrison gave evidence that this item has been remedied by the Strata Company (ts 176, 12 November 2019). The cost of the work was $1,888.70 (see invoice 10200 from PRM Property Repair and Maintenance dated 14 November 2018).
Palazzo Homes obtained a certificate of occupancy which would not have been granted if there was a non-compliant pool door.
The Tribunal accepts the evidence of Mr Harrison and finds that the common gym door was required to be permanently locked to the outside to prevent access to the pool area in accordance with the City's requirements.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Palazzo Homes did not provide to the Tribunal evidence of its estimated costs of rectifying this item. On the basis of invoice 10200 from PRM Property Repair, Palazzo Homes is to pay the Strata Company the amount of $1888.70 (inclusive of GST) for the costs of remedying the building service.
Pool Surround - Construction joint sealant - Sealant to paving joints in pool area has failed allowing pool water to penetrate paving.
Mr Harrison gave evidence that the construction joints in the paving around the pool area have been filled with a mastic or sealant. The sealant has collapsed (as there is no backing rod underneath) and allows water to penetrate under the paving (ts 179, 12 November 2019).
There was no requirement on Palazzo Homes to install the sealant. Accordingly, the allegation of faulty work is misplaced.
The Tribunal accepts the evidence of the Strata Company's witness, Mr Harrison, and finds that the sealant has collapsed in the construction joints in the paving due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Pool Area - No hot water to BBQ - Hot water not connected to BBQ.
Mr Harrison gave evidence that the hot water connection has not been completed to the barbeque as shown on the architectural drawings (ts 180, 12 November 2019).
The hydraulic drawings show that no hot water was to run to the BBQ, just a hose cock (cold water). Palazzo Homes relies on document 6, solicitor's letter of 3 December 2019.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Pool - Drainage provision - Unable to locate compliant provision for draining of pool and disposal.
Mr Harrison gave evidence that there is a requirement in the BCA to be able to drain the swimming pool. He could not find any return pipes that could drain the pool to external drainage.
The relevant pool installation quote provided for a soak well. There is no requirement for a pool to be drained completely.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Electrical Sub-Station - Non-compliant construction - WPM not continuous down face of slab.
Horizontal cracking all side between slab and top brick course.
Water run-off from roof damaging texture coating and render.
Roof not constructed in accordance with drawing 51.6 electric sub-station i.e. - 20mm roof overhang to wall face omitted.
As constructed there is high risk of water ingress.
Mr Harrison gave evidence that the water proof membrane for the roof does not continue down the face of the slab and there is a horizontal crack through which water could enter. The engineer drawings show a 20mm overhang of the slab to deflect water from getting into the substation (ts 182, 12 November 2019).
The 20mm roof overhang was reduced so that the roof slab finished flush with the wall. This is a design flaw which is not the responsibility of Palazzo Homes. Palazzo Homes relies on document 2, solicitor's letter of 3 December 2019.
The Tribunal accepts the evidence of Mr Harrison and finds that the 20mm overhang required by drawing 51.6 was omitted by Palazzo Homes. The Tribunal does not accept the argument of Palazzo Homes that the complaint item arose from a design flaw. The Tribunal further finds that the water proof membrane does not continue down the face of the slab. The Tribunal finds that these omissions constitute poor workmanship and, as a result, the integrity of the sub-station is at risk of water ingress.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Feature Entry Statement (Levels 1 to 4) - Entry statement cantalevers out over walkway.
Horizontal cracking to both faces 1 c above slab (Level 1).
Water runs out of joint after rain and cascades onto path beneath (continues long after rain ceases).
No written submissions were provided to the Tribunal in relation to this complaint item. The Tribunal has considered the oral evidence given at the hearing.
No written submissions were provided to the Tribunal in relation to this complaint item. The Tribunal has considered the oral evidence given at the hearing.
The Tribunal accepts the evidence of Mr Harrison and finds that water has penetrated the inside of the entry statement, runs out of the building and has discoloured the façade of the building due to poor workmanship (ts 185, 12 November 2019).
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
Undercover Carpark and Driveway - Spoon drains omitted -
Palazzo Homes' specification nominates "spoon drain" to driveway and entrance to garage.
Palazzo Homes has installed a single grated drain inlet centrally near front boundary.
Had Palazzo Homes installed channel drain at entrance the surface water problem between garage and sub-station would not exist.
Mr Harrison gave evidence that there was a problem with water accumulating and causing damage to the sliding door track. Specifications show that there was a spoon drain to the driveway and to the entrance of the garage that has not been installed (ts 187, 12 November 2019).
The work performed goes beyond the design drawing. Additional drains have been placed over and above what was in the hydraulic design to address drainage issues (Mr Jujnovich, ts 348, 13 November 2019).
The Tribunal accepts the evidence of Palazzo Homes and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Garage Sliding Gate Track - Track rusting and water flows into garage - Floor track for gate badly rusted.
Surface water from roof flows over edge and into garage.
Surface water from roof over discharges over roof edge resulting in damage to building elements.
Track should be heavy duty galvanised in this location.
Mr Harrison gave evidence that this complaint item arises because there are no spoon drains and the track is not a heavy duty galvanised track (ts 188, 12 November 2019).
The galvanisation of the track has worn off due to continual use. Palazzo Homes is not responsible for general wear and tear.
The design at the top of the roof allows water to flow over and down the side of the building. This is a design issue and not the responsibility of Palazzo Homes.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Ground Level Paving - No insolation joints with adjoining surfaces - No "insolation joints' provided to external walls of sub-station and paving.
Mr Harrison gave evidence that the paving around the substation had no isolation joints, and that there are some hairline cracks developing from the corners (ts 201, 13 November 2019).
There is no allegation of cracking to pavement or walls. No physical damage can be observed. It would have manifested by now being approximately six years after completion.
The Tribunal accepts the evidence of Mr Harrison and finds there is a lack of isolation joints. The Tribunal finds that the absence of isolation joints and the development of cracks is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Holes drilled in face of aluminium window frames (Apartments 2 and 4) - Since inspection on 20/07/2018 holes have been drilled in Apt 2 bed 2 and Apt 4 bed 3 windows presumably to disperse water from inside of window.
This attempt to rectify leaking windows is totalling unacceptable and will impact on the lifespan of window frames.
It appears holes were drilled to rectify previously reported water ingress.
Drilling holes in frames is not an acceptable solution to water ingress.
Mr Harrison gave evidence that he does not know how the holes were drilled and could only assume it was Palazzo Homes in order to deal with the water issues in apartments 2 and 4 (ts 206, 13 November 2019).
There is no evidence that Palazzo Homes carried out this work. Without any evidence that is was carried out by Palazzo Homes it cannot be faulty or unsatisfactory building work attributed to Palazzo Homes.
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Carpark roof is part slab/ceramic tile and colorbond sheeting.
Tiles and metal strip along edge of slab (gridline 9) have delaminated and can be peeled off.
Construction of upstand between garage metal roof and tiled roof deck
(Level 1) is non complaint with AS 4654.2 Clause 2.8.2.1 Roofs and Balconies.
Palazzo Homes has been aware of tile delamination for at least 2 years.
Tile delamination has increased since last inspection 20/07/2018.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Air Conditioning Units - Discharge from Apartments 2, 3, 4, 5, 6, and 7 onto Level 1 roof - Condensate.
Units is uncontrolled and spills onto metal louvres and roof deck.
Rusting to louvres and roof flashing has commenced and clearly visible.
Condensate catchment trays holding water which will lead to rusting of units.
Roof Extension - (outside living and kitchen balcony) - No perimeter or intermediate movement control joints
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membranes Section 2.
Non-compliance with AS 3957.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension - (outside master suite balcony) - As for Item 109
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension - (outside master suite balcony) - As for Item 109 Apartment 2
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension (outside living between grids H1) - As for Item 109 Apartment 2
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Tiles are lifting along edge and fall away from drain outlets.
No perimeter or intermediate movement control joints.
No waterproof membrane of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Balcony (outside living) - Many tiles have "drummy" sound when tapped.
No perimeter or intermediate movement control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membranes Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Efflorescence forming where surface water is ponding.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension (outside master suite balcony) - As for Item 109.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension (outside master suite) - No perimeter or intermediate movement control joints.
No waterproofing membrane to edge of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membranes Section 2.
Non-compliance with AS 3958. 1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Balcony (outside beds 2 and 3) - Some tiles have "drummy'' sounds when tapped.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Balcony (outside dining/living) - A east/west crack has developed along tile joint mid span of balcony.
No perimeter or intermediate movement control joints.
slab and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Balcony and Roof Extension (outside master suite) - As for Item 122 Apartment 6
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Roof Extension (outside living/home theatre) - No perimeter or intermediate movement control joints.
No waterproof membrane to edge of slab and edge detail not in accordance with AS 4654.2 Waterproofing Membrane Section 2.
Non-compliance with AS 3958.1 installation of ceramic tiles Clauses 5.4.5 and 5.6.
Extensive efflorescence forming around drain outlets.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Mr Harrison gave evidence that on the drawings the two skylights for apartment 8 and 9 show that there is a diffuser to be installed at ceiling level and it is not there (ts 209, 13 November 2019).
Palazzo Homes relies on a statement by the architect that he gave an instruction not to install the diffuser (document 2, solicitor's letter of 3 December 2019).
The Tribunal accepts the evidence of Palazzo Homes, including that of Mr Jujnovich regarding instructions Palazzo Homes received from the architect to delete the diffusers (ts 349, 13 November 2019) and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
Skylight (in study) - Diffuser omitted from skylight
Mr Harrison gave evidence that on the drawings the two skylights for apartment 8 and 9 show that there is a diffuser to be installed at ceiling level and it is not there (ts 209, 13 November 2019).
Palazzo Homes relies on a statement by the architect that he gave an instruction not to install the diffuser (document 2, solicitor's letter of 3 December 2019).
The Tribunal accepts the evidence of Palazzo Homes, including that of Mr Jujnovich regarding instructions Palazzo Homes received from the architect to delete the diffusers (ts 349, 13 November 2019) and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Window and Door Frame Manufacturer/Installer (all frames all levels) -
There are no manufacturer identification labels on aluminium window and door frames or performance labels.
Mr Harrison gave evidence that there is a requirement under the BCA for the manufacturer to attach a label to the windows for identification and certifying they have been tested. He could not find the labels. The windows are a possible source of water ingress. (ts 209, 13 November 2019).
The absence of labels is not faulty work. Palazzo Homes has produced a compliance certificate for the windows used at the Prestige, from Shelley glass, which includes certification that the windows and doors are provided in accordance with Australian Standards (document 19, solicitor's letter of 3 December 2019).
The Tribunal accepts the evidence of Palazzo Homes, including the evidence of Mr Jujnovich that he has never seen labels on windows that arrive at his building sites (ts 344, 13 November 2019), and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
C-Bus System not working throughout complex - System not working.
Mr Harrison gave evidence that the C-Bus system is not working throughout the units (ts 214, 13 November 2019).
No issues with the C-Bus system have been identified in any punch lists produced by Palazzo Homes. The C-Bus systems were working during walk throughs conducted at defects liability period and handover.
The Tribunal accepts Palazzo Homes' evidence, including the evidence of Mr Jujnovich that all electrical systems were working at the time of handover and in working order at the end of the defects period (ts 349, 13 November 2019), and finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Compliance throughout complex - Unable to confirm acoustic installation is compliant throughout complex.
Note: Acoustic report called for milestone inspections and/or testing.
Mr Harrison gave evidence that there is no acoustic material wrapped around the soil pipes or the water pipes. The acoustic requirements for the building would require them to be wrapped as part of the acoustic compliance certificate. The pipes that he viewed were normal PVC pipes and were not covered by an appropriate acoustic material as required by the BCA (ts 224, 13 November 2019).
There is no evidence from the Strata Company as to defective acoustic properties. There is evidence before the Tribunal of photographs taken during construction which shows the use of acoustic wrapping (document 44, solicitor's letter of 3 December 2019).
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Lift Shaft (water present in lift well) - Water discovered in lift well causing serious damage to lift equipment.
The evidence of Mr Harrison is that the source of water ingress at the top of the lift shaft from a crack line between the concrete slab and brick upstand (ts 224, 13 November 2019). The source of the water has been rectified. If the water table did rise, the lift well is supposed to be waterproofed (ts 226, 13 November 2019).
The entry of water into the lift shaft was the direct result of the construction work on the neighbouring property and the raising of the water table. See Mr Marocchi's report, Exhibit 1, p 1066.
The Tribunal accepts the evidence of Mr Harrison and finds that the water in the lift well entered through a crack at the top of the lift shaft as a result of poor workmanship. The Tribunal further finds that the item has been remedied by the Strata Company because the repair work was required as a matter of some urgency to avoid damage to the mechanics of the lift (ts 224, 13 November 2019).
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Palazzo Homes did not provide evidence to the Tribunal of its estimated costs of rectifying this item. Palazzo Homes is to pay the Strata Company the amount of $8,462.30 (inclusive of GST) for the costs of remedying the building service comprising $5,035.80 for Industrial Building Services invoice 05950 dated 10 September 2019 and $3,426.50 for Schindlers Lifts Australia invoice 468661355 dated 30 October 2019.
There are no manufacturer identification on aluminium window and door frames or performance labels.
Mr Harrison gave evidence that there is a requirement under the BCA for the manufacturer to attach a label to the windows for identification and certifying they have been tested. He could not find the labels. The windows are a possible source of water ingress. (ts 209, 13 November 2019).
The absence of labels is not faulty work. Palazzo Homes has produced a certificate of compliance for the windows used at the Prestige, from Shelley glass, which includes certification that the windows and doors are provided in accordance with Australian Standards (document 19, solicitor's letter of 3 December 2019).
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Unable to confirm acoustic installation is compliant.
Acoustic report called for milestone inspections and/or testing during construction.
Mr Harrison gave evidence that there is no acoustic material wrapped around the soil pipes or the water pipes. The acoustic requirements for the building would require them to be wrapped as part of the acoustic compliance certificate. The pipes that he viewed were normal PVC pipes and were not covered by an appropriate acoustic material as required by the BCA (ts 224, 240, 13 November 2019).
There is no evidence from the Strata Company as to defective acoustic properties. There is evidence before the Tribunal of photographs taken during construction which shows the use of acoustic wrapping (document 44, solicitor's letter of 3 December 2019).
The Tribunal finds that the Strata Company has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Annexure C - Items of complaint conceded by Palazzo Homes in CC 889 of 2019 (non-common property)
Staircase window - Black protection tape still on window frame.
Kitchen - Colour variations in laminate facing to drawer bank and end panels.
Kitchen - Glazing bead to aluminium door not fitting and too short
Kitchen - colour variations in laminate facing to drawer bank and end panels.
Bedroom 1 - Water ingress west wall right hand side of window, skirting and wall damage.
Living - Water ingress west wall right hand side of window skirting and wall damage.
Services Duct - Services duct is continuous from Ground Floor to Level 4 and access hatch is not fire rated or sound proofed. Services penetrations not sealed and non-compliant.
Bathroom 2/W.C - Water ingress around exhaust grill aboce W.C. suite.
Services Duct (Internal - between Hall and Bedroom 1 entry)- Services duct is continuous from Ground Floor to Level 4 and access hatch is not fire rated or sound proofed. Services penetrations not sealed and non-compliant.
Private Terrace - North/east corner of southern plantar box tiles delaminating. Intermediate and perimeter movement control joints non-compliant.
Balcony (off bedroom 2) - Upstand tiles in north/south west corners non-compliant.
Services Duct (Internal - between Hall and Bedroom 1 entry) - Services duct is continuous from Ground Floor to Level 4 and access hatch is not fire rated or sound proofed. Services penetrations not sealed and non-compliant.
Terrace - Glass louvre blade installed by Palazzo Homes exploded and disintegrated - possible safety issue.
Services Duct (Internal - between Hall and Bedroom 1 entry) - Services duct is continuous from Ground Floor to Level 4 and access hatch is not fire rated or sound proofed. Services penetrations not sealed and non-compliant.
Lift Shaft - Upstairs tile to north east corner of shaft delaminated (tile fallen off wall).
Annexure D - Items of complaint disputed by Palazzo Homes in CC 889 of 2019 (non-common property)
Outdoor Living. Glass balustrade shoes and drain outlets not water proofed - Glass balustrade shoes and drain outlets not waterproofed in accordance with AS 4652.2 Waterproofing Membrane Section 2.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Mr Harrison gave evidence that the whole box in the outdoor living area of Apartment 8 is loose and the power point screw has not been attached in the wall. The box itself has not been secured in the wall (ts 249, 13 November 2019).
This is an example of fair wear and tear that is expected of a property of this age. The cause of the alleged defect is pure speculation on the part of Mr Harrison which cannot support a finding of faulty or unsatisfactory building work.
The Tribunal finds that the Principal has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
Outdoor Living - Recessed lights in deck not working, rusting and full of water after rain.
Mr Harrison gave evidence that the recessed lights are not working and have rusted. These are outdoor lights and should not have any water in them. If the lights are waterproof then they are not fit for purpose (ts 205, 13 November 2019).
No complaint was raised in relation to this issue at completion. The cause of the alleged defect is pure speculation on the part of Mr Harrison.
The Tribunal accepts the evidence of Mr Harrison and finds that the exterior lights have rusted and are not working, which is a result of poor workmanship either from the manner in which they were installed or because the lights are not fit for purpose.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Outdoor Living - Full height vertical crack centrally in BBQ west wall.
Mr Harrison gave evidence that the crack in the outdoor living area of Apartment 8 goes from the floor to the ceiling which is about 2 metres high. It is not stepped and has been caused by more than just movement (Exhibit 1, p 339; ts 251, 13 November 2019).
The cracking is minor and part of the natural wear and tear and movement of the buildings. It is not the result of faulty workmanship. See Mr Marocchi's report, Exhibit 1, p 1062).
The Tribunal accepts the evidence of Mr Harrison that this is a vertical crack (and not stepped) and finds that the crack is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Staircase Landing - Large gap internal corner of skirting.
Mr Harrison gave evidence that, in his opinion, the skirting has been poorly fitted. There are no other cracks to suggest that the wall has parted. This just relates to the skirting and is a workmanship issue (ts 253, 13 November 2019).
No complaint was raised in relation to this item at completion. It is a matter of fair wear and tear.
The Tribunal accepts the evidence of Mr Harrison and finds that the gap in the corner of the skirting is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Severe staining/damage has occurred on handrail, glass and tiles.
Edge details of tiled roof over does not conform to AS 4654.2 Waterproofing Membrane Section 2 resulting in the staining.
Mr Harrison gave evidence that the glass on the balcony has been severely stained and cannot be cleaned. The staining is caused by water that comes over the balcony above that is contaminated with a cement based product due to a lack of waterproofing.
This item is the result of the cantilever design of the balcony.
The Tribunal accepts the evidence of Mr Harrison and finds that lack of waterproofing on the balcony above Balcony #2 has contributed to the staining of the glass balustrade. This finding is supported by the evidence of Mr Holland who stated that waterproofing had not continued over the exposed edge of the balconies in both the Moritz and the Prestige (ts 330, 13 November 2019).
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
(Off bedroom 2) - Upstand tiles in north and south west corners delaminating.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Bedroom 1 , Lounge, Study, Bedroom 2, Master Bedroom -
Mr Harrison gave evidence that in the contract specifications it calls for the windows in these locations to have custom wood sills (ts 251, 13 November 2019). There is no documentation in the form of variations and/or instructions from the architect or superintendent to establish that this item was excluded from the contract.
This item was deleted from the scope of work and was not required to be installed (see statutory declaration of Mr Jujnovich, Exhibit 1, p 650). Mr Harrison had no knowledge of the contract negotiation process.
The Tribunal accepts the evidence of Mr Jujnovich in his statutory declaration at Exhibit 1, p 650 and at the hearing (ts 351, 13 November 2019) and finds that the bullnose custom sills system did not form part of the scope of work.
The Principal has not provided sufficient evidence to substantiate this complaint item. No evidence was called by the Principal in relation to the negotiations that took place with Palazzo Homes at the time the contract was entered into.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that when he turned on the exhaust fan the exhaust fan rattled. The fan should not deteriorate and become noisy if it has not been used (ts 253, 13 November 2019).
This item is not a proper allegation of faulty work. Mr Harrison acknowledged that the fans have not been used for an extended period of time.
The Tribunal finds that the Principal has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that the construction documents stated that the vacuum system was to be installed and no variation had been provided by Palazzo Homes to prove that it had been deleted from the contract (ts 253, 13 November 2019).
This item was deleted from the scope of work and was not required to be installed. Mr Harrison had no knowledge of the contract negotiation process. Electrical plans provided as document 32 of the letter of 3 December 2019 do not detail ducted vacuum.
There is no provisional sum allocated for a ducted vacuum system in the contract for the Prestige.
The Tribunal accepts the evidence of Mr Jujnovich in his statutory declaration at Exhibit 1, p 640 and finds that the vacuum system did not form part of the scope of work.
The Principal has not provided sufficient evidence to substantiate this complaint item. No evidence was called by the Principal in relation to the negotiations that took place with Palazzo Homes at the time the contract was entered into.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Exhaust fan not working. All circuit breakers were on.
Mr Harrison gave evidence that the exhaust fans were not working. There was power to the exhaust fan as all circuit breakers were on (ts 254, 13 November 2019).
There is no explanation as to why the fans do not work. This is an example of fair wear and tear and is to be expected of a building of this age. It is not a proper allegation of faulty work.
Mr Harrison acknowledged that the fans have not been used for an extended period of time
The Tribunal accepts the evidence of Mr Harrison and finds that the exhaust fans are not working and that this is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Bathroom 1 - Exhaust fan not working. All circuit breakers were on.
Mr Harrison gave evidence that the exhaust fans were not working. There was power to the exhaust fan as all circuit breakers were on (ts 254, 13 November 2019).
There is no explanation as to why the fans do not work. This is an example of fair wear and tear and is to be expected of a building of this age. It is not a proper allegation of faulty work.
Mr Harrison acknowledged that the fans have not been used for an extended period of time.
The Tribunal accepts the evidence of Mr Harrison and finds that the exhaust fans are not working and that this is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Bathroom 2 - Exhaust fan not working. All circuit breakers were on.
Mr Harrison gave evidence that the exhaust fans were not working. There was power to the exhaust fan as all circuit breakers were on (ts 254, 13 November 2019).
There is no explanation as to why the fans do not work. This is an example of fair wear and tear and is to be expected of a building of this age. It is not a proper allegation of faulty work.
Mr Harrison acknowledged that the fans have not been used for an extended period of time.
The Tribunal accepts the evidence of Mr Harrison and finds that the exhaust fans are not working and that this is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Terrace Tiling - No intermediate movement control joints in tiling.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Mr Harrison gave evidence that the construction documents stated that the vacuum system was to be installed and no variation had been provided by Palazzo Homes to prove that it had been deleted from the contract (ts 253, 13 November 2019).
This item was deleted from the scope of work and was not required to be installed. Mr Harrison had no knowledge of the contract negotiation process. Electrical plans provided as document 32 of the letter of 3 December 2019 do not detail ducted vacuum. There is no provision sum allocation for a ducted vacuum system in the contract for the Prestige.
The Tribunal accepts the evidence of Mr Jujnovich in his statutory declaration at Exhibit 1, p 640 and at hearing (ts 353, 13 November 2019) and finds that the building contract was varied to exclude the installation of the ducted vacuum system.
The Principal has provided insufficient evidence to substantiate this complaint item. No evidence was called by the Principal in relation to the negotiations that took place with Palazzo Homes at the time the contract was entered into.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Design and installation of glass balustrade traps debris against wall.
Cleaning of glass and removal of debris is not possible without removing glass.
Mr Harrison gave evidence that there is a gap about 40mm and the gap continues around but as the tiling slopes up, the glass line does not change. The consequence is that there is no gap behind the glass so the glass cannot be cleaned (ts 260, 13 November 2019).
The design for this item followed the specification. It is incorrect to say that the cleaning of the glass and the removal of the debris is not possible.
The Tribunal accepts the evidence of Mr Harrison and finds that the manner in which the balustrade was installed constitutes poor workmanship.
The Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that when he turned on the exhaust fan the exhaust fan rattled. The fan should not deteriorate and become noisy if it has not been used (ts 262, 13 November 2019).
This item is not a proper allegation of faulty work. Mr Harrison acknowledged that the fans have not been used for an extended period of time
The Tribunal finds that the Principal has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that when he turned on the exhaust fan the exhaust fan rattled. The fan should not deteriorate and become noisy if it has not been used (ts 262, 13 November 2019).
This item is not a proper allegation of faulty work. Mr Harrison acknowledged that the fans have not been used for an extended period of time
The Tribunal finds that the Principal has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that when he turned on the exhaust fan the exhaust fan rattled. The fan should not deteriorate and become noisy if it has not been used (ts 262, 13 November 2019).
This item is not a proper allegation of faulty work. Mr Harrison acknowledged that the fans have not been used for an extended period of time
The Tribunal finds that the Principal has not provided sufficient evidence to substantiate this complaint item.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that the exhaust fans were not working. There was power to the exhaust fan as all circuit breakers were on (ts 262, 13 November 2019).
There is no explanation as to why the fans do not work. This is an example of fair wear and tear and is to be expected of a building of this age. It is not a proper allegation of faulty work.
Mr Harrison acknowledged that the fans have not been used for an extended period of time.
The Tribunal accepts the evidence of Mr Harrison and finds that the exhaust fans are not working and that this is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that the ceiling panel access was poorly fitted. It is not equal in its margins around the opening and looks badly finished. In Mr Harrison's opinion, this is a workmanship item (ts 262, 13 November 2019).
The ceiling access could have been used since the defects liability period. The panel could have been moved.
The Tribunal accepts the evidence of Mr Harrison and finds that the poorly fitted ceiling panel is due to poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory
Terrace (Tiling) - No intermediate movement control joints in tiling.
Palazzo Homes to remedy for the reasons provided in the main body of the Tribunal's decision.
Mr Harrison gave evidence that at the top of the stair landing as you step out onto the balcony there is water ingress. There should have been a spoon drain across the face of the door to prevent the water coming into the building. The water is accumulating and causing damage to the right hand side of the door. It is a workmanship issue (ts 270, 13 November 2019).
In conjunction with the architect, the builder built up areas on a slope to avoid an identified trip issue or risk. It is not a workmanship issue.
The Tribunal accepts the evidence of Mr Harrison and finds that the water ingress in this location is a result of poor workmanship.
Accordingly, the Tribunal finds that, in relation to this item, Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
Mr Harrison gave evidence that the construction documents stated that the vacuum system was to be installed and no variation had been provided by Palazzo Homes to prove that it had been deleted from the contract (ts 253, 13 November 2019).
This item was deleted from the scope of work and was not required to be installed. Mr Harrison had no knowledge of the contract negotiation process. Electrical plans provided as document 32 of the letter of 3 December 2019 do not detail ducted vacuum.
There is no provision sum allocation for a ducted vacuum system in the contract for the Prestige.
The Tribunal accepts the evidence of Mr Jujnovich in his statutory declaration at Exhibit 1, p 640 and at hearing (ts 353, 13 November 2019) and finds that the building contract was varied to exclude the installation of the ducted vacuum system.
The Principal has provided insufficient evidence to substantiate this complaint item. No evidence was called by the Principal in relation to the negotiations that took place with Palazzo Homes at the time the contract was entered into.
Accordingly, the Tribunal is not satisfied that Palazzo Homes has carried out a regulated building service in a manner that is faulty or unsatisfactory.
CITATION : OWNERS OF STRATA PLAN 65323 and PALAZZO HOMES PTY LTD [2020] WASAT 57 (S)
Legal Profession (State Administrative Tribunal) Determination 2020 (WA), Table A, cl 6
Barnett and Barrier Reef Pools (WA) Pty Ltd [2016] WASAT 50
Medical Board of Western Australia and Kyi [2009] WASAT 22
Owners of Strata Plan 65323 and Palazzo Homes Pty Ltd [2020] WASAT 57
Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41 (S)
Summerville and Department of Education and Training [2006] WASAT 368 (S)
Western Australian Planning Commission v Questdale Holdings Pty Ltd [2016] WASCA 32
(1) Subject to this section, the Building Commissioner or the State Administrative Tribunal may make such orders for costs as they think fit in relation to proceedings arising from a building service complaint or a HBWC complaint.
(5) In determining costs to be paid the Building Commissioner or State Administrative Tribunal may take into account any refusal or failure by a party to comply with an order or direction of the Building Commissioner or Tribunal.
(7) This section does not limit the powers of the State Administrative Tribunal under the State Administrative Tribunal Act 2004 Part 4 Division 5.
... If a party has conducted itself in such a way as to unnecessarily prolong the hearing, has acted unreasonably or inappropriately in its conduct of the proceedings, has been capricious, or the proceedings in some other way constitute an abuse of process, then this may give rise to an exercise of the discretion to award costs[.]
The Tribunal makes the following orders in CC 888 of 2019 and CC 889 of 2019:
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.