[2018] WASAT 113
State Administrative Tribunal (WA)
2018-11-01
Original judgment source is linked above.
Water ingress to basement carpark water ingress to basement carpark and associated basement areas described in the notice of proposed complaint served on builder on 7 March 2012. Remedy sought rectification.
(a) the construction of the basement with relief vents that punctured the vapour barrier, resulting in the basement not complying with the Building Code of Australia (at [311]);
(b) the installation of the vapour barrier, instead of one of the possible types of waterproofing set out under 'Water Proof Membranes Systems' in the specifications of the relevant contract, which amounted to a breach of the contract and constituted a failure to carry out the regulated building service in a proper and proficient manner given that no conventional form of waterproofing had been installed (at [353][356]);
(c) inadequate waterproofing of the basement slab (at [359]); and
(d) the failure to insert an external water stop at the joint between the AFS wall and the basement floor amounting to a failure by Psaros Builders to carry out the regulated building service in a proper and proficient manner in that a vapour barrier was selected as the device to exclude water, thereby rendering additional sealing at the joint necessary and an external water stop was not provided (at [377][391]).
On the application of the parties by Minute of Consent Orders dated 9 April 2015 and following a directions hearing on 9 June 2015, it is by consent of the parties ordered that:
(i) a report to the respondent from BG & E Structural Engineers, dated 11 August 2014; and
(ii) a Certificate of Design Compliance issued by BG & E Structural Engineers to the respondent dated 26 September 2014 and a letter from BG & E Structural Engineers to the respondent dated 28 October 2014.
(b) The remediation terms and conditions agreed between the parties as evidence by:
(i) a letter from Hotchkin Hanly to Squire Patton Boggs of 10 September 2014;
(ii) a letter from Squire Patton Boggs of 3 October 2014;
(iii) a letter from Hotchkin Hanly to Squire Patton Boggs of 27 October 2014;
(iv) an email from Hotchkin Hanly to Squire Patton Boggs of 15 December 2014 and responsive emails from Squire Patton Boggs to Hotchkin Hanly of 19 December 2014 and 13 January 2015 and;
(v) an email from Hotchkin Hanly to Squire Patton Boggs of 2 February 2015 and a responsive email from Squire Patton Boggs to Hotchkin Hanly of 17 February 2015.
Dear Sir
OWNERS OF STRATA PLAN 52843 v PSAROS BUILDERS PTY LTD
...
The Alternative Solution
...
Our client is willing to consider the suitability of the alternative solution your client has now produced however it reserves all its rights as regards the costs it has incurred having its structural engineers liaise with Brown Consulting over the past 12 months.
The alternative solution now proposed has been raised and put forward by your client on the basis that it offers a less intrusive solution which will provide a reasonable and effective means of addressing the concerns of the owners and tenants of Tyne Square, that were ventilated during the course of the SAT hearing in 2012. We note that the alternative solution now posited by your client was not raised during the course of the hearing before the SAT on 8, 9, 11 and 12 October 2012, and 6 and 7 December 2012.
Issues Arising from 18 August 2014 proposal
Our client is currently considering your client's proposal in the most timely and cost effective way to arrange a review of the design now produced by BG & E Engineering. Whilst that process is being undertaken we seek your client's response to the following matters that arise from the proposal made by your client:
...
(a) Please confirm that your client will undertake all remedial works described in its proposed solution at its cost;
(b) Please confirm that no services to the building will be suspended during the course of the remedial works including water, power, gas, telephone, data cabling and sewer;
(c) Item 6.6 refers to waterproofing. Please confirm that the process of waterproofing so as to achieve a fully tanked basement will include all the areas being treated in the last revision of the Airey Taylor/ETEC drawings and up to the same height as is shown in those drawings; and
(d) Please advise who the specialist waterproofing subcontractor is that has developed a design to waterproof the existing joints to the car park basement and who will undertake the work, as referred to at item 6.6 of the construction management plan; and
(e) Please provide a copy of the design document produced by your client's waterproofing subcontractor so our client may review it.
Documenting the arrangement
We note your client's view that a formal legal agreement by deed is unnecessary to regulate the rights of the parties during the remediation process, and your client's preference that the process be agreed by an exchange of correspondence. Our client is willing to consider this suggestion subject to your client entering into an appropriately worded consent order to be filed with the SAT which has the effect of varying the orders made by the SAT on 5 April 2013 such that the remedial work contemplated by Order 2 of the 5 April 2013 orders refers to the BG & E alternative solution as well as the specialist waterproofing works to be undertaken by your client's subcontractor. This is subject to our client firstly agreeing to the alternative solution proposed by BG & E. Please advise whether your client is in principle willing to enter into consent orders to this effect.
...
Yours sincerely
HOTCHKIN HANLY
Dear Andrew
Owners of Strata Plan 52843 and Psaros Building Pty Ltd
We refer to your letter dated 10 September 2014.
...
(a) Our client confirms that the Remedial Works Solution will be undertaken at its own cost.
(b) Our client .confirms that no services to the building will be required to be suspended during the course of undertaking the Remedial Works Solution.
(c) Our client confirms that the areas that require waterproofing to achieve a fully tanked basement will include all areas being treated in the last revision of the Airey Taylor/ETEC drawings and up to the same height as shown in those drawings.
(d) Mr Greg Crocker of Allduro developed the waterproofing design on behalf of the manufacturer of the waterproofing product. Mr Darius Amin of Concrete Coating and Repairs will undertake the waterproofing treatment.
(e) Allduro's design has already been provided with our letter of 18 August 2014. If more detail or further explanation is required, Greg Croker is available to meet with the newly appointed engineer.
Documenting the arrangement
Can you please provide, the wording of your clients proposed consent orders. Our client is unable to agree in principle or otherwise with consent orders before reviewing the orders proposed. Please confirm why your client feels it is necessary to have any further substantive SAT orders when the agreement between our clients will be binding and enforceable.
Squire Patton Boggs (AU)
(Applicant's Bundle)
Dear Sir
OWNERS OF STRATA PLAN 52843 v PSAROS BUILDERS PTY LTD
CC 602 OF 2012
Thank you for your letter of 3 October 2014. Our client has instructed us that it is agreeable to the basement remedial works proceeding in accordance with the BG & E design and on the basis of those matters described in paragraphs 2 - 12 of your 3 October 2014 letter, subject to the following matters:
...
Our client is willing to allow remedial works to commence after the issues described at paragraphs 2, 4 and 5 above have been addressed and we look forward to your early response.
Yours sincerely
HOTCKIN HANLY
Andrew Buchan
Partner
(Applicant's Bundle)
(a) On 13 October 2015 Mr Sutton sent an email to the applicant stating: 'Psaros will then stand by these works for a period of 6 years as per normal obligations under a construction contract'.
(b) On 6 November 2015 Mr Sutton sent the applicant an email stating: 'Psaros confirm that the 6 year period for the SAT rectification works in this room, and all other areas that the SAT scope of works covered, would be honoured'.
(c) On 8 November 2016 Mr Sutton sent the applicant an email in response to an email from Mr Andrew Spain, from the Tyne Square Strata Management Company. Mr Spain's email stated: 'It is the strata Companies understanding that the period for which Psaros is responsible for the defects for all works completed under Building Permit number 6.2015.200.1 as enforced by the SAT Order for a period of 6 years resets from the date of which the current remedial works are completed'.
(d) Andrew Sutton replied: 'Your understanding is correct regarding this' (para 21 of the parties' agreed facts).
Dear Adrian
...
Psaros Pty Ltd, the contractor engaged to carry out the works to the basement will only be responsible for the workmanship of the works performed. In this case, in consultation with our waterproofing supplier, Psaros request access again to determine the extent of any installed waterproofing workmanship issues with the purpose to rectify any workmanship issues discovered.
As communicated previously, Psaros group of companies (Psaros) advises that the builder of Tyne Square was Psaros Builders Pty Ltd which no longer exists and has been deregistered since August 2016.
While Psaros has in good faith and of its own volition attended to some building issues since Psaros Builders Pty Ltd has been deregistered, it feels that the time has come to cease providing ex gratia assistance, particularly given the time that has expired since the building was completed and the completion of certain agreed remedial solutions.
Psaros is not responsible or liable to rectify any defects in the building that became apparent before the date of this email, or will become apparent afterwards, and has not accepted nor assumed, and will not accept or assume, any such responsibility or liability.
...
Regards
Robert Sansalone
Director Construction Administration
(a) Who carried out the regulated building service comprising the relevant remedial work?
Dear Parties
The Tribunal wishes to raise two matters with you for your consideration and submission at the upcoming hearing.
Firstly, as a significant matter, the Tribunal notes that the applicant has as yet failed to identify the specific regulated building service, of which they complain. The complaint at the present time simply refers to the symptom of the complaint, that is of water ingress. It does not identify what the regulated building service is, in respect of which it seeks the Tribunal to determine was carried out in a manner which was not proper and proficient or which is faulty or unsatisfactory.
As a second matter, the Tribunal's view is that the agreed outline of facts is incomplete in that it does not identify the legal basis on which the parties approached the Tribunal in 2015 and on which the Tribunal made the 'Varied Orders'. At the present time the Tribunal cannot identify any legal basis on which that occurred.
The Tribunal would be grateful if these matters could be addressed at the hearing.
(a) On 5 April 2013 the Tribunal made the Original Order compelling Psaros Builders to remedy water ingress to the basement carpark of Tyne Square.
(b) The Original Order was incapable of compliance and thus over a number of months during 2014 and 2015 the applicant and Psaros Builders negotiated an alternative remedial solution evidenced by correspondence and reports exchanged between them and ultimately formalised in the Varied Order made by the Tribunal on 9 June 2015. Psaros Builders was actively involved in the negotiations and ultimately reached a binding agreement with the applicant.
(c) Although the building permit was initially applied for by Psaros Builders, it was ultimately obtained by the respondent. The respondent was engaged by Psaros Builders to perform the works required by the Varied Order on the basis that the builder's registration of Psaros Builders had lapsed and it could not retain the building permit in the circumstances.
(d) Psaros Builders engaged the respondent pursuant to a financial arrangement to perform the works that it had negotiated and agreed to perform for the applicant. The cost of the works was not insignificant totalling $496,268.88 (document 8 of the parties' agreed bundle).
(e) When the notice of completion was filed in respect of the remedial works, Psaros Builders was deregistered three months later. The company did not seek deregistration whilst the remedial works were on foot.
(f) As per Shami at [48], it is not the elements of work itself which is the building project, but the entire project on a global basis. In applying the principles identified in Shami, the building project in the present case is the work the subject of the Varied Order. The remedial work was carried out in order to satisfy the Varied Order.
(g) A large part of the building project as evidenced by the Varied Order was the detailed negotiation, development, agreement and implementation of an overall design and construction program in respect to the alternative remediation solution. All of those elements were negotiated and agreed in detail by Psaros Builders. The respondent had no involvement in any of those crucial elements and merely had to perform them.
(h) Psaros Builders was the entity against whom the Varied Order was made and was therefore responsible for ensuring that the building project was carried out and completed. But for the Original Order and the Varied Order the respondent would not have been retained by Psaros Builders to perform the remedial works.
(i) Adopting the reasoning from Shami that the phrase 'carried out' means 'the completion of the entirety of the building work', Psaros Builders 'carried out' the whole of the 'building project', from when the Original Order was made in 2013 until it was deregistered in August 2016.
(j) But for the deregistration of Psaros Builders, the applicant would have made an application pursuant to s 51 of the BSCRA Act on the basis that Psaros Builders carried out the regulated building service. It is disingenuous of it now to contend that the respondent carried out the remedial works simply because the opportunity to initiate an application against Psaros Builders is no longer available.
Who carried out the regulated building service in respect to the remedial works?
... a builder is responsible to the building owner for faulty workmanship carried out by subcontractors ... I agree with what Pidgeon J had to say thereon in Shaw v McLeod. (citation omitted)
... It would, in my view, be an erosion of what the legislature intended by s 12A for a builder to escape the jurisdiction of the Board by submitting that the work complained of was not within the builder's specialty and had been done by a specialized subcontractor. ...
[The Magistrate] considered the charge was validly brought against the accused and gave the following as his reasons:
'I consider that in referring to the person who "carried out the building work" s12A(1) of the [Builders' Registration Act] is referring specifically to the person responsible for the building of the edifice whatever it may be. I do not consider that it is the specific bricklayer, carpenter, plumber or such other tradesmen as actually did the work who is that person ...
My reading of the [Builders' Registration Act] as a whole leads me to the same conclusion as the learned Magistrate and that the person referred to as being the person 'who carried out the building work' would not be the subcontractors engaged. The person who physically carries out the work may not even be the subcontractors and could well be a bricklayer on wages or a builder's labourer. It could not have been the intention of the [Builders' Registration Act] that the [order] goes to such person. I consider that the words 'building work' in s.12A is the whole work the subject of the contract which normally would be the work in respect of which the permit issues or what his Worship describes as 'the edifice'[.]
... a person who, in effect, has the role of ensuring that the necessary building work is performed normally to its completion either by himself or by his servants or agents. It does not ... mean that every person who is actually performing any of the building work in question 'carries out' such building work[.]
When one turns to the meaning given the phrase 'carry out' in the Shorter Oxford Dictionary one finds that the relevant meaning is 'to conduct to conclusion'. This meaning may not, of course, be entirely applicable in respect of a partly completed building, but obviously in completing such a building the person concerned with the building work is carrying out the necessary building work from the beginning of the works upon which he is engaged.
Given your client's view that it is unnecessary for a formal deed of agreement to be entered into between the parties to regulate the remediation process, then the attached consent orders will provide our client with the necessary security that it can seek recourse in the SAT in the event that the remedial works do not proceed as agreed.
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
Abigroup Ltd v Abignano [1992] FCA 567; (1992) 112 ALR 497
Owners of Strata Plan 52843 and Psaros Builders Pty Ltd [2013] WASAT 46
Psaros Builders Pty Ltd v Owners of Strata Plan 52843 [2014] WASC 34
Shami and Teo [2017] WASAT 73
Tulloh v Chief Executive Officer of the Department of Corrective Services [2018] WASC 105
(1992) 112 ALR 497