[2018] WASC 179
Supreme Court of WA
2018-07-24
Smith AJ
Original judgment source is linked above.
A Activity room/Family room
The respondent is to effect the following works to the cornices affixed to all walls of the activity room and the north wall and east return of the family room:
(a) Cut line to underside of cornice.
(b) Make good any damage to set coat.
(c) Apply fibreglass/plaster grout to backs of cornice against wall plate and top of wall.
(d) Make good all affected areas.
(a) Repair 4 x cracked corners to coffered ceiling.
(b) Make good all affected areas.
(a) item 20 of the home building work contract specification provided that cornices shall be affixed in accordance with the manufacturer's specifications; and
(b) the cornices are gyprock and that the CSR specification was applicable.
2.0 Exercise of original jurisdiction of the Tribunal - first hearing of the building service complaint (heard together with the contract complaint)
(b) dismissing the cornice complaint insofar as it was based in contract; and
(c) concluding that there was fault with the cracking and plaster shear that should be rectified.
(a) The evidence given on behalf of Gemmill Homes by witnesses Mr Harrison and Dr Zurhar is preferred to the evidence of that of Mr Mogg (Sanders' witness) where there is a difference of view.
(b) It is not accepted that Gemmill Homes is in breach of contract by reason of having affixed the cornices to the set coat.
(c) It is accepted that the cracking in plaster shear present in Sanders' home is a result of movement and settlement in the house during and after the building period. Such cracks are to be expected as part of the building process. Given the evidence of Mr Harrison, the cracking may have been exacerbated by expansions and contractions within the building by reason of the extremes of heat that had been present in the roof space for reasons raised in dealing with the cold water issue.
(d) It is not possible for the Tribunal to determine the extent to which the choices made, or not made, by Sanders in relation to the roof space heat issue may have contributed to the plaster issue. Gemmill Homes has always been prepared to make good the plaster issue matters as part of its contractual obligations to Sanders, including its defects period obligations, or similar, and the Tribunal takes a view that it should do so.
(e) It is not reasonable for Sanders to be left with a house that is affected by cracking and plaster shear in the way that the house is. These are faults and they should be rectified.
(f) The argument made on behalf of Gemmill Homes that an order to pay should be made is accepted. In view of the evidence from both sides, there has been a significant breakdown in the relationship between the parties, such that it would be impossible now for Gemmill Homes to be able to satisfy Sanders' expectations on any remedial works.
(g) A third party should undertake the remedial works at Gemmill Homes' cost.
(h) Sanders' request for a work order is refused. As to work to be performed, the remedial method recommended by Mr Mogg is rejected. All three experts agree that Mr Harrison's proposed scope of works is a satisfactory way of remediating the plaster issues.
3.0 Application for leave to review the payment order made by Member Leslie
(a) failing to take into account and give weight to Sanders' desire 'to elect' a remedial order; and
(b) not giving adequate weight to the fact that the usual order that follows the usual circumstances of a finding of faulty and/or unsatisfactory work is an order requiring the respondent to remedy its own work given the advantages afforded to both parties by a remedial (work) order are not afforded to them by the making of a monetary order.
(c) giving weight to the fact that Sanders did not agree with Gemmill Homes' proposed remedial approach.
4.0 Earlier decisions of tribunals in Western Australia on building remedy orders
(a) remedy the fault to be faulty or unsatisfactory building work; or
(b) pay to the owner of the building such costs as remedying the building work that is faulty or unsatisfactory as the Building Disputes Tribunal considers reasonable.
It is helpful to examine the nature of the maintenance or defects obligation. In Cassidy v Engwirda Construction Company (No 2) [1968] Qd R 159 at 166, Hoare J adopted as correct a proposition advanced in Hudson's Building and Engineering Contracts (9th ed 1965) pp 285-288 that in the absence of express provision in the contract, the remedies under maintenance or defects liability clauses are in addition to and not in substitution for common law rights and that even where the defects have appeared within the defects liability period, the employer may sue for damages rather than call on the contractor to do the work subject to the damages being limited to the cost to the contractor doing the work at that time, rather than the possibly greater cost of bringing in another contractor either then or at a later date.
Cassidy's case has been followed in various decisions of the Queensland Building Tribunal, for example: see Jaremus Peter v Raffaele Renato and Sharon, C 430-96/12 May 1997. In the 9th and 10th editions of Hudson the above principle was restated ((10th ed 1970) p 394, (11th ed) par 5-050 ff). In both editions, the learned author recognised that the effect of the clause is to confer a right both on the owner and the builder, but in the later edition, the learned author criticised a conclusion reached in P & M Kaye Ltd v Hosier & Dickinson [1972] 1 WLR 146 at 166 to the effect that it is a necessary implication from the particular clause under consideration that the employer cannot, as he otherwise could, recover as damages from the contractor the difference between the value of the works if they had been constructed in conformity with the contract and their value in their defective condition, without first giving the contractor the opportunity of making good the defects.
The learned author (at 5-051) stated that the above confirmed a submission made in the 10th ed based on either the failure to mitigate, or on the view taken up in Kaye's case that the failure to give the contractor the opportunity to remedy would be a breach of contract. Then in respect of the breach of contract approach said:
'It is suggested however, that this latter view fails to take account of the not uncommon case of an owner who, by reason of a past history of unsatisfactory work or dilatoriness, may have reasonably lost confidence in the contractor's willingness or ability to remedy the defects satisfactorily, and who therefore reasonably prefers to bring in another contractor. The needs of that situation would be better met, it is submitted, by founding any contractor's entitlement to seek a reduction of damages on the owner's unreasonable failure to mitigate damage, if that could be shown, rather than upon a right to damages of the contractor in such a case. Since explicit language is rarely used in the clauses on this particular point, it is submitted that the courts should, notwithstanding Lord Diplock's dictum, be slow to imply a term that the contractor will in all cases have an unqualified right to re-enter and remedy defects himself for breach of which damages would be recoverable from the owner.'
(a) The general practice has been to grant an order to remedy in preference to an order to pay on the basis that the more appropriate remedy is that which puts the innocent party in the position it would have been in had the contract been properly performed without unnecessarily burdening the party in breach.
(b) There is good reason to adhere to that practice, subject to some qualifications. If it is accepted that the builder should not be in a different position during the defects liability period, why should that also not be the case in relation to a defect which arises only after the defects liability period has expired, whether raised by an issue or a subsequent owner?
(c) If, as suggested in Hudson's Building and Engineering Contracts (11th ed) the better jurisprudential basis for concluding that an owner's claim for damages for defects arising during the defects liability period could be reduced where the builder has not had the opportunity to carry out the work is founded on the duty to mitigate, that is a duty which applies at any time.
(d) There is authority for the principle (in the law of contract) that if the party in breach either offers or evinces a willingness to provide substituted performance, the innocent party must act reasonably. In the law of contract, the duty to mitigate may not extend this far as a party is entitled to exercise his right to performance of a contract, despite the other repudiation.
(e) Where an application is brought for a building remedial order under s 12A of the Builders' Registration Act 1939 (WA), the owners are entitled to enforce statutory remedies and do not have to enter into a contract. Consequently, whether the duty to mitigate extends to acting reasonably does not arise. It is therefore not necessary to go any further than to accept the proposition that an owner is under a duty to mitigate his damages by reason that the owner has the right under the statute to seek an order to remedy but has elected not to do so and has thereby failed to mitigate the damages.
In our view the following principles should be applied in determining whether or not to grant an order to remedy or an order to pay under s 12A.
(a) At the heart of the issue as to what order is appropriate is the question as to whether the relationship between the parties has irretrievably broken down. The fact that it is the builder asserting that the relationship has broken down does not matter. The principles equally apply whether it is a builder or an owner making the assertion. This is an important consideration for a number of obvious reasons, including the primary one, namely, to ensure some finality in litigation. If the Tribunal were to order remedial work in circumstances where the relationship between the parties has irretrievably broken down, it is likely not to result in finality of the disputes arising between those parties.
(b) The Tribunal looks to the relationship between the parties and whether the owner has lost confidence in the builder, the willingness or otherwise of the builder to perform remedial works, whether it has performed remedial works which have been unsatisfactory, whether the builder has been refused access, and whether, for example, the extent of the remedial work itself evidences perhaps a lack of competence or ability on the part of the builder which justifies the owner losing confidence in the builder's ability.
This remedial method was described by the Tribunal as:[28]
to provide a cut line along the cornice joint of all cracked cornices and plaster to completely isolate the cornice from the set coat, fill the bottom edge of the cornice with a bead of flexible and paintable sealant, and install scrim behind the cornices, at 450 mm centres and at all joints, and to cut out and reflush ceiling cracks, backblock joiners, and paint affected walls and ceilings.
5.2 Issue 2 appropriate form of building remedy order and Issue 4 the effect of the mediation orders
(a) Usually the applicant (complainant) is entitled to elect whether to claim a remedial work order or monetary order (in lieu of the builder carrying out the remedial work). If the latter applies, the amount to be ordered is the cost of a thirdparty contractor carrying out the work, unless the applicant is considered to be acting unreasonably in insisting on this remedy. In that event, the amount to be awarded will be limited to the cost the builder would incur had the builder been permitted to carry out the work. This is because the applicant is considered not to have mitigated his loss. The rationale for this approach, and the factors generally considered to be relevant, are set out in Nelson.[31]
(b) The Tribunal nevertheless retains a discretion in determining the appropriate remedy, so that there may be circumstances when the general principles expressed in Nelson may give way. Such cases are rare. Trengove was such a case. There the Tribunal found that the grant of a remedial order was appropriate, because the relationship between the parties had irretrievably broken down.
(c) The respondent submits in this case that the relationship between the parties has irretrievably broken down and that it is best to break that relationship by making a payment order. The grounds on which Gemmill Homes rely on to put this point are that Sanders:
(i) refused entry to enable the trial repairs to be carried out;
(ii) criticised the competency of trades used by Gemmill Homes;
(iii) has no confidence in Gemmill Homes' competence to remedy the complaint;
(iv) has gone to such extraordinary lengths in attempting to support his case, to the point of it becoming an obsession, which demonstrates as unreasonableness; and
(v) that if there is any further cracking he will simply continue to litigate.
(a) The evidence establishes that Sanders was correct in identifying why the trial remedial work could not be carried out.
(b) Sanders had been critical at different times to tradespersons and representatives of Gemmill Homes. Sanders' evidence was that these persons had lied to him, in respect of a number of issues.
(c) Sanders referred to lies given about the state of preparation of the house plans. He had been told that they were almost finalised but in fact the plans had already been submitted to the local authorities for their approval without Sanders having sighted them. This caused some weeks of delay because the house had not been located and the position specified by Sanders.
(d) Sanders gave other examples of unsatisfactory work relating to:
(i) the unsightly placing of a conduit for electrical wiring, which should have been put through the cavity within a brick pier;
(ii) he was assured that a cooktop isolation switch could be installed within a cupboard; and
(iii) when an electrician installing airconditioning for Sanders advised the installation was noncompliant, a representative of Gemmill Homes advised him that Western Power had inspected and approved the installation. Sanders stated that Western Power later contradicted this advice.
(e) Sanders was not crossexamined in relation to any of this evidence, which the Tribunal accepted.
(f) Notwithstanding these difficulties, Sanders informed the Tribunal that Gemmill Homes was able to perform its obligations to construct the dwelling and he saw no reason why they could not carry out work which Gemmill Homes acknowledged fell within their maintenance obligations.
(g) Sanders denied making any critical comments about Gemmill Homes on any public forum, format or social media.
(h) Sanders' view as to the reason for the cornice cracking and appropriate remedial method had been based on a report and evidence of his expert witness, Mr Mogg. Whilst Sanders had gone further than Mr Mogg by claiming all the ceilings would need to be replaced, whereas Mr Mogg had stated that they all be repainted, Sanders readily accepted, when questioned by the Tribunal, that there was no contractual basis on insisting on the remedial method advised by Mr Mogg, and he would have to accept the remedial method proposed by Gemmill Homes.
(i) Sanders accepted he had gone to great lengths to support his case because he did not have confidence in Gemmill Homes' experts. Sanders pointed out that Mr Harrison in his initial report had accepted an incorrect method of fixing the cornices might be a cause of failure, but in his second report had retracted that opinion based on what he regarded as unpersuasive grounds, incorrectly construing Australian standards and manufacturers' requirements. Sanders also considered that this was contradicted by Dr Zurhaar, who in evidence accepted the cracking would have been reduced if the cornices had been fixed to the flat coat. Sanders also considered that Gemmill Homes' experts had failed to attribute any cause of failure, and had expressed the opinion that unless the cause of the cracking of the cornices was established, the effectiveness of any remedy could not be properly evaluated. This evidence adequately explained Sanders' persistence.
(a) whilst Gemmill Homes now professes an irretrievable breakdown in its relationship with Sanders, it offered by a letter from its solicitors, dated 13 June 2017, to carry out other remedial work identified as being necessary to the roof framing, which is not the subject of these proceedings;
(b) Gemmill Homes has included in its costings an amount which it now wishes to pay Sanders, in lieu of carrying out the roof repairs. There is nothing identified which might have happened, after this date, which would justify such a change in position; and
(c) as at 13 June 2017, the relationship was not thought by Gemmill Homes to be so bad that it could not carry out the roof repair.
(a) At least one of the advantages favouring such an order, as mentioned in Nelson, also exists in this matter. Namely, that a remedial work order will avoid potential confusion as to liability if significant further cracking occurs after the necessary remedial work has been completed. This is because Mr Harrison reflected in his first report that cornice cracking could be caused by any combination of nine causes, including deflection and movement, or uplift of the roof structure, large variances in temperature within the roof space, incorrect installation of Gyprock ceilings and cornices, and expansion and contraction of brickwork or internal walls.
(b) Whilst in the original decision, the complaints in relation to cornices and ceilings were found to be faulty, there were no express findings as to any particular cause or factors which resulted in that conclusion.
(c) Subsequent to the original hearing, Sanders commissioned a further building inspection report from a Mr Brent Wyatt, a registered builder, dated 6 December 2016. The report, amongst other matters, raised noncompliance issues with regard to the roof framing, including that roof tie down straps were not correctly installed. Gemmill Homes responded by having the roof structure inspected by Mr Shane Just of the consulting engineering firm Structerre. Mr Just found various deficiencies with the roof framing, including the tie down straps, but concluded that the deficiencies had not contributed to the cornice cracking which was attributed to growth of the clay masonry and minor movement in the timber members forming the ceiling structures.
(d) Neither Mr Wyatt or Mr Just were called to give evidence, and there was, therefore, no opportunity for the parties, or the Tribunal, to test the views expressed.
(e) It would be prudent for the parties to ensure that the necessary remedial work required to the roof structure which was not part of the proceedings be carried out before the remedial work to the cornices and ceilings so that there can be no future issue about whether the roofing structure defects might have contributed to any further significant cracking which might occur.[35]
(a) Carry out and complete all necessary work at the Applicant's dwelling at 24 Tolworth Way, Embleton, Western Australia so as to remedy the cause and effect of all cracking to the cornices and ceilings within the dwelling in a proper and proficient manner so as to achieve an aesthetically acceptable result, save for that cracking which is present in the Activity room, Family room and Theatre room as described in the order of the Tribunal made on 16 September 2014 in matter CC 1141 of 2014;
(b) Make good any damage caused by compliance with (a) above.
(a) Setting out all costs claim supported to the extent possible by vouchers, in sufficient detail to enable the Tribunal to assess and fix such costs;
(b) Setting out his submissions as to the basis upon which it is contended such costs should be awarded.
6.0 The appeal to the court instituted under s 105 of the SAT Act
7.0 Are questions of law raised in the appeal and should leave be granted?
(a) Leave to appeal should be allowed on grounds 6 to 9, as each of those grounds have been made out.
(b) Leave to appeal should allowed on ground 5, as this ground has been made out.
(c) Grounds 1, 2 and 3 have not been made out. Whilst I agree the Tribunal erred in observing that a complainant who makes a building service complaint is entitled to elect a remedy, I am not satisfied that it has been demonstrated this finding is an error of law that is a vitiating error, that is, it is an error that might have affected the Tribunal's decision to make a building service remedy order.
8.0 Grounds 6 to 9 of the grounds of appeal - is the 'trial' order and the order to revoke the 'trial' order valid?
(a) the order was an interim or interlocutory order and not a final order;
(b) as such it was duly rescinded by the order of Member Carey on 27 November 2014;
(c) alternatively, there was no power to make the order and, therefore, it was not valid; and
(d) as the mediation order had been validly rescinded, or was an invalid order, the Tribunal should have disregarded it when making its final order on 25 October 2017.
In Plaintiff S157/2002 v Commonwealth (2003) 211 CLR 476 (Plaintiff S157) a question was whether s 474 of the Migration Act 1958 (Cth), which provided in effect that a 'privative clause decision', a defined term, was not subject to judicial review precluded judicial review of a decision of the Tribunal in breach of the requirements of natural justice. The High Court held that s 474 did not prevent judicial review of decisions that involve jurisdictional error. Decisions of that character were not 'privative clause decisions' because they were not decisions made 'under' the Act. Gaudron, McHugh, Gummow, Kirby and Hayne JJ said:
'This Court has clearly held that an administrative decision which involves jurisdictional error is "regarded, in law, as no decision at all" [76].'
At [76] their Honours referred to Bhardwaj at [51] per Gaudron and Gummow JJ, [63] per McHugh J and [152] per Hayne J.
Bhardwaj was considered by the Full Federal Court in Jadwan Pty Ltd v Secretary, Department of Health and Aged Care (2003) 145 FCR 1 (Jadwan). Gray and Downes JJ concluded:
'Only Gaudron and Gummow JJ, with the agreement of McHugh, as part of the reasoning, relied on the proposition that jurisdictional error on the part of the decision-maker causes an administrative decision to be of no legal effect. Gleeson CJ, Hayne J and Callinan J do not appear to have embraced the proposition. Kirby J in his dissenting judgment clearly did not [40].'
Gray and Downes JJ also analysed the authorities and concluded that a decision that was no decision at all may still have consequences. Their Honours also highlighted that the High Court had not explained in any detail what the consequences were for a decision that had no legal effect:
'Gaudron and Gummow JJ did not explain in detail the consequences of the proposition that the decision has no legal effect. They did not deal with issues such as the status of the first decision of the IRT if the IRT had not chosen to ignore it and make another. Indeed, their Honours did not discuss what might be the factual, as distinct from the legal, consequences attaching to an administrative decision if no challenge to its validity is ever made, or if challenge to its validity is made out of time, or is made in proceedings to which someone bound or otherwise affected by the decision is not a party. Nor did their Honours say anything about the possible effect of an administrative decision after a court proceeding in which a party has made out a case of jurisdictional error on the part of the decision-maker, but the court has declined to grant relief in relation to the decision by reason of discretionary considerations [40].'
After referring to the reasoning of the High Court in Plaintiff S157, Gray and Downes JJ concluded that Bhardwaj had a limited application:
'In our view, Bhardwaj cannot be taken to be authority for a universal proposition that jurisdictional error on the part of a decision-maker will lead to the decision having no consequences whatsoever. All that it shows is that the legal and factual consequences of the decision, if any, will depend upon the particular statute [42].'
Kenny J agreed at [64].
Those statements of Gray and Downes JJ were obiter because the court held that there had not been any jurisdictional error. However, their Honours comments have been approved or followed by intermediate courts of appeal: Minister for Immigration and Border Protection v Hossain [2017] FCAFC 82; Minister for Immigration and Citizenship v Maman [2012] FCAFC 13; (2012) 200 FCR 30; Director of Public Prosecutions (DPP) v Edwards [2012] VSCA 293; Purton v Jackson [2012] TASFC 2.
Aronson, Groves and Weeks in Judicial Review of Administrative Action and Government Liability (6th ed, 2017), after referring to Bhardwaj, Plaintiff S157 and Jadwan offer the following 'interim conclusions':
'For most contexts, the outcome of judicial review is retrospective, in the sense that the jurisdictionally flawed decision is treated as having had no relevantly adverse legal effect. "Nullity" is a useful word to denote that outcome. It is not automatically the case, however, that jurisdictionally flawed decisions fail to produce legal consequences. Nullity is a bundle of legal consequences. Whether a decision has relevantly adverse legal effects, and if so, how many, are questions which will receive different answers in different contexts [10.120].'
In my opinion the effect of the authorities is as follows. First, an administrative decision which involves jurisdictional error is legally invalid. Secondly, an administrative decision which is legally invalid does not necessarily have no legal effect unless and until it is set aside or declared to be invalid. Thirdly, whether a legally invalid decision has any relevant legal effect before it is set aside or declared to be invalid depends upon the statutory framework under which and the context in which the decision is made.
9.0 Grounds 1 to 3 of the grounds of appeal 9.1 The practice of comity
For reasons of comity and consistency, a member of SAT should also generally follow a decision of another member of the Tribunal (or a member of a former Tribunal which SAT has replaced) that is in point, unless satisfied that the earlier decision was clearly in error: Re Scott and Commissioner for Superannuation (1986) 9 ALD 491 at 499. However, as the President is a judicial member and may review a decision of a nonlegally qualified member on a question of law under s 66 of the TPD Act, the Tribunal constituted by or comprising the President may depart from a decision of a non-legally qualified member or indeed a legally qualified member on a question of law. The President may in this way provide appropriate guidance to the Tribunal on questions of law, subject to any further guidance the Court of Appeal may give from time to time.
The practice of judicial comity is, of course, distinct from, but related to, the doctrine of precedent (or stare decisis) which compels each court in a judicial hierarchy to follow and apply decisions of any court higher in that hierarchy on questions of law. The practice of judicial comity applies to augment that doctrine by creating a non-binding practice applicable to decisions of courts of co-ordinate jurisdiction, or as between a court in one judicial hierarchy, and a court at the same or a higher level in another judicial hierarchy, and provides that questions of law should usually (but not always) be determined the same way.
(a) judicial comity is a practice, not a legal principle, the practical application of which will vary depending upon the individual circumstances of the cases in question - so it could never operate to constrain the issues to be litigated as between parties and only arises when all the evidence and argument relevant to the question under consideration has been received;
(b) the practice only applies as between courts of coordinate jurisdiction or to a situation in which a court is being asked to follow a decision of another court at an equivalent level or higher in a comparable judicial hierarchy; and
(c) the practice is limited to questions of law, and has no application to questions of fact.
9.2 Does a complainant have a right to elect a remedy? - The proper construction of the statutory discretion to make a building remedy order
(1) If the Building Commissioner refers a building service complaint to the State Administrative Tribunal, the Tribunal may
(a) if the Tribunal is satisfied that the regulated building service that is the subject of the building service complaint has not been carried out in a proper and proficient manner or is faulty or unsatisfactory, deal with the building service complaint by making a building remedy order; or
(b) otherwise, decline to make a building remedy order.
(1) A building remedy order consists of one of the following
(a) an order that a person who carried out a regulated building service remedy the building service as specified in the order;
(b) an order that a person who carried out a regulated building service pay to an aggrieved person such costs of remedying the building service as the Building Commissioner or State Administrative Tribunal, as the case requires, considers reasonable and specifies in the order;
(c) an order that a person who carried out a regulated building service pay to an aggrieved person a sum of money specified in the order to compensate the aggrieved person for the failure to carry out the building service in a proper and proficient manner or for faulty or unsatisfactory building work.
(a) a building service carried out by a registered building service provider or an approved owner builder;
(b) home building work that is carried out under a contract or arrangement for gain or reward.
9.3 Did the Tribunal err in referring to a complainant being entitled to elect a remedial work order or a monetary order?
(a) firstly, a complainant is entitled to elect to seek an order to pay; and
(b) secondly, there is an onus on the building service provider to establish that complainants are acting unreasonably in insisting upon an order to pay.
[W]here relevant considerations are not specified, it is largely for the decision-maker, in the light of matters placed before him by the parties, to determine which matters he regards as relevant and the comparative importance to be accorded to matters which he so regards. The ground of failure to take into account a relevant consideration will only be made good if it is shown that the decision-maker has failed to take into account a consideration which he was, in the circumstances, bound to take into account for there to be a valid exercise of the power to decide.
(b) What factors a decision-maker is bound to consider in making the decision is determined by construction of the statute conferring the discretion. If the statute expressly states the considerations to be taken into account, it will often be necessary for the court to decide whether those enumerated factors are exhaustive or merely inclusive. If the relevant factors and in this context I use this expression to refer to the factors which the decision-maker is bound to consider are not expressly stated, they must be determined by implication from the subject matter, scope and purpose of the Act. In the context of judicial review on the ground of taking into account irrelevant considerations, this court has held that, where a statute confers a discretion which in its terms is unconfined, the factors that may be taken into account in the exercise of the discretion are similarly unconfined, except in so far as there may be found in the subject matter, scope and purpose of the statute some implied limitation on the factors to which the decision-maker may legitimately have regard: see Reg v Australian Broadcasting Tribunal; Ex parte 2HD Pty Ltd [1979] HCA 62; (1979) 144 CLR 45 at 49-50 , adopting the earlier formulations of Dixon J in Swan Hill Corp v Bradbury [1937] HCA 15; (1937) 56 CLR 746 at 7578, and Water Conservation and Irrigation Commission (NSW) v Browning [1947] HCA 21; (1947) 74 CLR 492 at 505. By analogy, where the ground of review is that a relevant consideration has not been taken into account and the discretion is unconfined by the terms of the statute, the court will not find that the decision-maker is bound to take a particular matter into account unless an implication that he is bound to do so is to be found in the subjectmatter, scope and purpose of the Act.
(c) Not every consideration that a decision-maker is bound to take into account but fails to take into account will justify the court setting aside the impugned decision and ordering that the discretion be re-exercised according to law. A factor might be so insignificant that the failure to take it into account could not have materially affected the decision: see, eg, the various expressions in Baldwin & Francis Ltd v Patents Appeal Tribunal [1959] AC 663 at 693; Hanks v Minister of Housing and Local Government [1963] 1 QB 999 at 1020; R v Chief Registrar of Friendly Societies; Ex parte New Cross Building Society [1984] QB 227 at 260. A similar principle has been enunciated in cases where regard has been had to irrelevant considerations in the making of an administrative decision: Reg v Bishop of London (1889) 24 QBD 213 at 2267; Reg v Rochdale Metropolitan Borough Council; Ex parte Cromer Ring Mill Ltd [1982] 3 All ER 761 at 76970.
It follows from this definition of the concept that, where action taken in the purported exercise of a statutory power is sought to be impugned for jurisdictional error, the only question will be whether what was done was authorised by the empowering legislation. The answer to that question will turn on the identification of the limits of the authority conferred by the relevant statutory provision, and an analysis of the facts to ascertain whether those limits have been exceeded. The identification of those limits may also be described as identifying the conditions for the valid exercise of the statutory power.
The identification of the conditions for the valid exercise of the relevant statutory power is entirely a question of statutory construction. The proper construction of the relevant statute is 'reached by the application of rules of interpretation accepted by all arms of government in the system of representative democracy'.
Those rules require primary attention to be directed to the text of the relevant provisions. There must be regard to the language of the statute viewed as a whole, considered in its context. An important part of that context will be the purpose of the legislation, ascertained from what the legislation says (rather than any assumption about the desired or desirable reach or operation of the relevant provisions). Once the purpose of the legislation is established, a construction that would promote that purpose shall be preferred to a construction that would not do so.
Some rules of statutory construction relate to assumptions which are to be made in reading legislation. For example, it is presumed that legislation does not overthrow fundamental principles or depart from the general system of law without expressing that intention with irresistible clearness. Where two alternative constructions of legislation are open, that which is consonant with the common law is to be preferred.
(a) to terminate the contract for a breach of an essential condition, or a nonessential term where there is a sufficiently serious breach[63] and if the contract is for building work, sue for damages to be assessed for the cost of necessary work to remedy the defects, together with consequential loss;[64] or
(b) affirm the contract and sue for damages for the breach.
A decision does not 'involve' an error of law unless the error is material to the decision in the sense that it contributes to it so that, but for the error, the decision would have been, or might have been, different. The critical question on this aspect of the case is whether, but for the alleged error of law on which the respondents rely, the decision might have been different by reason of the possibility that the Tribunal would not have made the findings of fact relating to the settlement in the terms in which they were made.
An applicant seeking review by an administrative tribunal may be regarded as having a right to have their review application determined according to law. If a tribunal makes a demonstrable error of law which might have affected the ultimate decision, but which cannot be positively shown to produce an adverse outcome, then the dissatisfied party has not received the kind of review to which they were entitled.
10.0 Ground 4 did the Tribunal take into account an irrelevant consideration?
11.0 Ground 5 did the Tribunal fail to specify in its order how the regulated building service remedy is to be effected?
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
CITATION : GEMMILL HOMES PTY LTD -v- SANDERS [2018] WASC 179 (S)
Citation : GEOFFREY FRANK SANDERS AND GEMMILL HOMES PTY LTD
Practice and procedure - Costs - Departing from general principle - Appeal properly brought - Appeal allowed in part - Both parties successful in part - Each party to bear own costs of appeal - Turns on own facts
Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5(1), s 36(1)(a), s 36(1)(b)
Gemmill Homes Pty Ltd v Sanders [2018] WASC 179
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[2] Complaint Resolution Act, s 11(1)(d) empowers the Building Commissioner to refer a complaint to the Tribunal to deal with under s 38 or s 43 of the Complaint Resolution Act.
[5] ts 15 August 2017, page 5; document book, page 221.
[7] ts 12 July 2016, page 4; document book, page 18.
[8] ts 12 July 2016, page 4; document book, page 18.
[9] ts 12 July 2016, page 22; document book, page 36.
[10] Pursuant to Complaint Resolution Act s 36(1)(b), ts 12 July 2016, page 23; document book, page 37.
[11] Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41.
[12] Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41 [33].
[13] Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41 [33].
[14] Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41 [34].
[15] Sanders and Gemmill Homes Pty Ltd [2017] WASAT 41 [35].
[16] Nelson v Mardesic (1998) 22 SR (WA) 42.
[17] Trengove and Celebration Nominees Pty Ltd [2012] WASAT 65; (2012) 80 SR (WA) 77.
[18] Builders' Registration Act 1939 (WA) s 12A.
[19] Builders' Registration Act 1939 (WA) s 12A.
[20] Nelson v Mardesic (1999) 22 SR (WA) 42, 47.
[21] Nelson v Mardesic (1999) 22 SR (WA) 42, 48 49.
[22] Nelson v Mardesic (1999) 22 SR (WA) 42, 49.
[23] Nelson v Mardesic (1999) 22 SR (WA) 42, 46.
[24] Trengove and Celebration Nominees Pty Ltd [2012] WASAT 65; (2012) 80 SR (WA) 77.
[25] Trengove and Celebration Nominees Pty Ltd [2012] WASAT 65; (2012) 80 SR (WA) 77 [36], [37].
[26] Pursuant to Complaint Resolution Act s 58(2).
[27] ts 15 August 2017, pages 2 3; document book, pages 218 219.
[28] ts 15 August 2017, page 4; document book, page 220.
[29] ts 15 August 2017, page 4; document book, page 220.
[30] ts 15 August 2017, pages 6 7; document book, pages 222 223.
[31] Nelson v Mardesic (1999) 22 SR (WA) 42, 48.
[32] ts 15 August 2017, pages 7 10; document book, pages 223 226.
[33] ts 15 August 2017, page 10; document book, page 226.
[34] ts 15 August 2017, pages 10 - 15; document book, pages 226 231.
[35] In those circumstances the order provided for a longer time than usual for the remedial work to the cornices to be carried out because the roof repairs first needed to be undertaken.
[36] The order by the Tribunal was made on 15 August 2017 and amended on 25 August 2017.
[37] Centrex Australasia Pty Ltd v Commissioner for Consumer Protection [2017] WASCA 79 [106].
[38] Giudice v Legal Profession Complaints Committee [2014] WASCA 115 [71] (Buss JA).
[39] Giudice v Legal Profession Complaints Committee [2014] WASCA 115 [73] (Buss JA); see also TNT Skypak International (Aust) Pty Ltd v Federal Commissioner of Taxation (1988) 82 ALR 175, 178 (Gummow J); and Osland v Secretary, Department of Justice (No 2) [2010] HCA 24; (2010) 241 CLR 320 [21] (French CJ, Gummow & Bell JJ).
[41] See Presiding Member of the Southern Development Assessment Panel v DCSC Pty Ltd [2018] WASC 145 [79] - [98].
[42] Minister for Immigration and Multicultural Affairs v Bhardwaj [2002] HCA 11; (2002) 209 CLR 597 [51].
[43] Tulloh v Chief Executive Officer of the Department of Corrective Services [2018] WASC 105 [21] [28]; see also Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2018] WASCA 28 [131] (Buss P & Murphy JA).
[44] Minister for Immigration and Multicultural Affairs v Bhardwaj [2002] HCA 11; (2002) 209 CLR 597 [52] [53] (Gaudron & Gummow JJ).
[45] The Owners of Strata Plan 18449 and City of Joondalup [2005] WASAT 304 [31].
[46] The Owners of Strata Plan 18449 and City of Joondalup [2005] WASAT 304 [30].
[47] Mustac v Medical Board of Western Australia [2007] WASCA 128 [49] [50] (Martin CJ, Wheeler & Buss JA agreeing).
[48] Mustac v Medical Board of Western Australia [2007] WASCA 128 [38] (Martin CJ, Wheeler & Buss JA agreeing).
[49] Mustac v Medical Board of Western Australia [2007] WASCA 128 [43] (Wheeler & Buss JA agreeing).
[50] Mustac v Medical Board of Western Australia [2007] WASCA 128 [45] (Wheeler & Buss JA agreeing).
[51] Mustac v Medical Board of Western Australia [2007] WASCA 128 [46] (Wheeler & Buss JA agreeing).
[52] Minister for Immigration & Citizenship v Lai (2013) 249 CLR 332 [66]; Jacob v Save Beeliar Wetlands (Inc) [2016] WASCA 126 [68] (McLure P, Buss JA & Newnes JA agreeing).
[53] Kruger v The Commonwealth of Australia [1997] HCA 27; (1997) 190 CLR 1, 36 (Brennan CJ).
[54] Minister for Immigration & Citizenship v Lai (2013) 249 CLR 332 [67]; Jacob v Save Beeliar Wetlands (Inc) [2016] WASCA 126 [68] (McLure P, Buss JA & Newnes JA agreeing).
[56] Dekker v Medical Board of Australia [2014] WASCA 216 [75]; see also Sullivan v Civil Aviation Safety Authority [2014] FCAFC 93 [105] [107], [115] (Flick & Perry JJ) and Erujin Pty Ltd v Jacob [2017] WASC 35 [160] [161].
[57] Yao-Jing v Minister for Immigration & Multicultural Affairs [1997] FCA 289; (1997) 74 FCR 275, 288.
[58] See also Jacob v Save Beeliar Wetlands (Inc) [2016] WASCA 126 [49] (McLure P, Buss JA & Newnes JA agreeing).
[59] Sean Investments Pty Ltd v MacKellar [1981] FCA 191; (1981) 3 ALN N102; (1981) 38 ALR 363, 375.
[60] Minister for Aboriginal Affairs v Peko-Wallsend Ltd [1986] HCA 40; (1986) 162 CLR 24, 39 41.
[61] Laing O'Rourke Australia Construction Pty Ltd v Samsung C&T Corporation [2015] WASC 237 [98] [101].
[62] Saeed v Minister for Immigration and Citizenship [2010] HCA 23; (2010) 241 CLR 252 [13] citing Salemi v MacKellar [No 2] [1977] HCA 26; (1977) 137 CLR 396, 401 (Barwick CJ).
[63] Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61 [47], [49].
[64] Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272; Hughes v Dormley Pty Ltd as Trustee for the Poll Family Trust [2001] WASC 83.
[65] Sargent v ASL Developments Ltd (1974) 131 CLR 634, 641 (Stephen J);.
[66] State of Victoria v Sutton [1998] HCA 56; (1998) 195 CLR 291 [40] (Gaudron, Gummow & Hayne JJ).
[67] Australian Broadcasting Tribunal v Bond [1990] HCA 33; (1990) 170 CLR 321, 353.
[68] Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60 [100].
[69] In closing submissions to the Tribunal, counsel for Gemmill Homes, Mr Monaco, made extensive submissions to the Tribunal as to why a finding of fact should be made that the relationship between the parties had broken down to such an extent that it would be unfair to Gemmill Homes to perform remedial work for Mr Sanders. ts 26 July 2017, pages 20 24.
[70] ts 25, July 2017, page 46; document book, page 106.
[71] Bond Corporation Holdings Ltd v Sulan (1990) 3 WAR 49, 64.
[72] Bond Corporation Holdings Ltd v Sulan (1990) 3 WAR 49, 64.
[75] Rules of the Supreme Court 1971 (WA) O 66 r 1.
[76] Complaint Resolution Act s 36(1)(b).
[77] Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 [136] [143].
[78] Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 [168].
[79] Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 [169].
[80] Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 [75].
[81] Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 [84].
(2003) 145 FCR 1
(2012) 200 FCR 30
(1937) 56 CLR 746
(2002) 209 CLR 597
(2010) 241 CLR 252
(1988) 82 ALR 175
(2010) 241 CLR 320
(1997) 74 FCR 275
(1974) 131 CLR 634
(2003) 211 CLR 476
(1977) 137 CLR 396
(2009) 236 CLR 272
(2013) 249 CLR 332
(1997) 190 CLR 1
(1981) 38 ALR 363
(1954) 90 CLR 613
(1979) 144 CLR 45
(1947) 74 CLR 492
(1986) 162 CLR 24
(1998) 195 CLR 291
(1990) 170 CLR 321
(1990) 3 WAR 49