[2013] VCAT 324
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2013-02-21
Original judgment source is linked above.
The purposes of the statutory scheme are to ensure proper standards of building and construction, to protect the public from delinquent and unscrupulous building practices and to maintain the standing of the building industry.
(b) carry out inspections of buildings and building work; and
(c ) issue occupancy permits and temporary approvals.
(1) Subject to Division 4, the relevant building surveyor must not issue a building permit unless he or she is satisfied that -
(a) the building work and the building permit will comply with this Act and the building regulations; and
Despite the terms of an appointment under this section, a private building surveyor, carrying out any functions set out in section 76, must comply with this Act and the regulations.
(a) perform his or her work as a building practitioner in a competent manner and to a professional standard.[15]
The combination of experience, tertiary qualifications and professional liability insurance means that the building surveyor is comparable to other building professionals, such as architects and engineers. The building control legislative scheme is thus designed with the object of ensuring that building surveyors and other registered building practitioners act with a high degree of professionalism and integrity, in order to protect the public.[16]
Save for the term that the service would be rendered with due care and skill, which is sought to be implied in the pleadings, all the other terms which are sought to be implied, appear to fix the building surveyor with the type of duties that one might expect on a trade practices action or a sale of goods action as to quality or as to fitness for purpose. The role of a building surveyor is fixed by the legislation, and is tied to certification in accordance with minimal requirements as set out in the Building Act, the Regulations and the Building Code Australia (BCA). In this particular instance, it must be remembered that the second respondent is not employed either as an architect or designer where some such terms may be implied. In this particular instance, the second respondent is obliged to comply with the BCA and various statutory requirements and to exercise due care and skill.
(i) Neither the building permit, nor a Notice in accordance with BR 317, was ever displayed on the building site;
(ii) He never recorded the names of any registered builder on the building permit, because none had been appointed when it was first issued and the Applicant never changed her status from Owner Builder;
(iii) Furthermore, he did not record any registered builders in his file for the purpose of the occupancy permit, because the Applicant had not advised him to do so;
(iv) At no time during the project did the Respondent advise the Applicant that either Laukert or Terry B should be noted on the building permit and covered by insurance;
(v) He had prepared Inspection Reports in the form of emails sent after an inspection. However, he agreed he did not prepare any formal reports, as he believed he did not have to;
(vi) He made no hand written notes on site during any site inspections, other than some brief notes which appear on the Plans; and
(vii) He made no file notes of any of his telephone conversations, other than as confirmed by subsequent emails.
(b) He assumed that the Applicant would be using registered builders, as disclosed in her application for an Owner Builder's permit. Where builders are not notified to the building surveyor prior to issuing a building permit, then the builder will not be recorded on the permit;
(c) When he issued a building permit to the Applicant, as an Owner Builder, all registered building practitioners become that Owner Builder's subcontractors;
(d) He described the frame which he inspected on 29 (or 30) April 2009 as 'substantially non-compliant'; and later conceded that the frame was 'substantially defective';
(e) He agreed that a builder engaged under a major domestic building contract will be 'A person who is in charge of the carrying out of building work' for the purpose of the BA and BR and not the Owner Builder. However, he did not issue a direction to Laukart to rectify the defective frame, 'because he is not my client';
(f) If he became aware of any breaches of the DBCA, he agreed he had a duty to take action as appropriate, as the relevant building surveyor. For instance, if he was aware of an unregistered builder, he agreed he would have to take action, such as advising the home owner that the builder must be registered. However, he did not consider that he had a duty to enquire of builders on a building site;
(g) Where he had to issue Orders or Notices he was entitled to charge an additional fee;
(h) He agreed with most of the implied terms alleged under paragraph 5 of the Points of Claim, although these had been denied in the corresponding paragraph of the Points of Defence; and
(i) He acknowledged that his function as a relevant building surveyor is an important part of the consumer protection provisions of the BA and the DBCA.
54 In his witness statement he confirmed that, as an Owner Builder, the Applicant was responsible for the works on site, and he did not need to concern himself with her 'subcontractors'. Furthermore, it was for the Applicant to manage her 'subcontractors' and any problems caused by them were her responsibility, not his.
I certainly did not provide any advice or direction to her in relation to becoming an Owner Builder
I do not recall filling out an Owner Builder application form for her and I do not think that I did
(i) He claimed not to be familiar with the requirements under the BA for insurance;
(ii) In his statement he says that his father did have insurance, whereas in oral evidence he did not know his father's insurance arrangements;
(iii) He agreed that he had assisted his father with the letter of demand;
(iv) He agreed there no was written agreement between the Applicant and his father, who was therefore in breach of the DBCA; and
(v) He agreed that he had not found an insurance policy which shows that the building works were covered for 2009.
I understand that Ms Orders now alleges that Steve Maloney and AABP are responsible for the delays and difficulties she encountered on the Project. I cannot see on what grounds she would make this allegation. According to my recollection, Mr Maloney was a capable building surveyor who dealt with Ms Orders patiently. My experience of the Project was that such problems as it did encounter resulted from the fact that Ms Orders made numerous changes to the building's design and that she did so without prior consultation with the building professionals engaged on the Project.
Throughout the course of the Project, my point of contact was Ms Orders herself, as owner-builder. Although she engaged a number of subcontractors, I do not recall that she engaged a builder to oversee the entire Project or parts of it.
I wish you and Steve all the best at VCAT and look forward to hearing of a favourable outcome.
that's okay, just fill in your name and address and I will do the rest.
It is not my role to provide basic regulatory advice about Owner Builders.[49]
Help you to achieve compliance within the regulations[61]
refers to the building surveyor's duties to obtain all requisite information required for the issue of a building permit;
(e) As an Owner Builder, the Applicant had undertaken to supervise building work not carried out by her and it was not his responsibility to ensure or enquire whether she was able to do this;
(f) When he issued the building permit to the Applicant he considered that he had a sound knowledge of the BA and BR; and the DBCA and the regulatory requirements;
(g) He never agreed to provide additional consultancy services to her, outside his obligations as the relevant building surveyor;
(h) He issued the building permit prior to the Applicant engaging any builder;
(i) The Applicant, as Owner Builder, is then obliged to notify the relevant building surveyor of the appointment of any subsequent builder so they can be noted on the Occupancy Permit;
(j) He first learnt that a builder was on site when he was called to a slab inspection, but agreed he made no enquiries as to what builder/s had been engaged;
(k) He regarded the Applicant as the Owner Builder, throughout the building project, even after she engaged registered builders;
(l) As the Owner Builder, the Applicant was responsible for what happened on site, including overseeing the works;
(m) He agreed that the Applicant would not be performing the work herself, but he did not know what knowledge she had of building; and he did not know what work she would be doing;
(n) It was the Applicant's obligation to advise the building surveyor that she no longer wished to be an Owner Builder, which would give rise to the issue of an amended permit recording a registered builder;
(o) It was not his responsibility to advise her about major domestic building contracts or requisite insurance as he was dealing with her as an Owner Builder. He was not thinking in terms of an owner who might be 'duped' by an unscrupulous builder;
(p) It was not his responsibility to monitor dubious or unscrupulous builders; and
(q) He agreed that the role of an Owner Builder was not easy and not one he would take on himself.
First Mandatory (Slab) Inspection - 12 & 13 March 2009
...the frame actually wobbles when you are standing on the first floor.
It appears that all the bracing specified on your drawings has been installed.[81]
The frame appeared to have been constructed largely in accordance with the building permit documentation. However, I had a number of queries for the structural engineer...[87]
(l) Notwithstanding other concessions made, the Respondent continued to endorse the above statement and still believed he approached the inspection in the right way;
(m) He confirmed that the form of Inspection Report which he was using in 2011 was not set up in his system at the relevant time;
(n) After conducting the frame inspection, the Respondent did not issue an Order[88] but rather an oral approval of the frame to Laukert, subject to engineer's sign off. He did not record this instruction to Laukert but confirmed this in writing to the Applicant days later;
(o) He did not think about the costs to the Applicant involved in further amended drawings, engineer inspections and amended building permit;
(p) He agreed that the defects with this frame were not standard industry practice, as advised in his email to the Applicant; and
(q) He agreed that he tried to convey to the Applicant not to be too concerned. He believed at the time that the outstanding matters could be resolved by the engineers.
Please see reply from builder (Civic Home Improvement).
My understanding is that the framework structure is unstable. Have you passed the frameworks inspection?
If necessary, I may have to get another company engineer to check on BGE's drawings. Please advise.[89]
Who says the framework is unstable? All I have stated is that there is a wobble to the frame, which is unusual.
I carried out a frame inspection with Heino on site and a number of minor issues were resolved by his carpenter whilst I was on site.[90] There were other items that I raised at the time of the inspection and even though Heino and his truss manufacturer offered assurances on the installation, it did not fully comply with the structural documentation and I sought the comments of your structural engineer (standard industry practice).
Therefore the inspection was Approved subject to the engineer signing off on my queries, as there were a number of elements not strictly in accordance with the structural design documentation (this is not unusual).
[the Respondent then sets out what he notified the structural engineer]
This is standard industry practice within the industry when alterations occur on site. If your engineer inspects the frame and is OK with its construction then the frame will be approved.
My professional advice to you is to get the frame inspected by BGE and then take whatever action you feel necessary after receiving the engineer's report - otherwise we will just go around in a circle issuing emails to no avail.[91]
a complete set of documentation will be required for review.
The defects were so numerous ...I recommend that the building be demolished and re erected correctly.
I should not worry about it and that in his 38 years of building experience, not one frame that was not built in accordance with the drawings had been ordered to be demolished by the building commission.
(b) She then saw Phyland at his office and was told everything is okay; and that she should amend the working drawings to reflect the 'as-built' frame so that they could be submitted to the Council;
(c) She was told to arrange a site meeting with the Respondent and Terry B;
(d) She was told that Terry B had made some changes; and
(e) She was told that Terry B would instruct her as to what changes to make to the drawings.
Respondent: has this drawing been amended by Roy Hodgson?
Applicant: No, I made the changes as that is what Terence Phyland told me to do.
Phyland: she can update the working drawings to reflect the as built, as she is the Owner Builder - just strike out Roy Hodgson's title block.
(c) The Applicant said that the Respondent then took out his pen and struck out Hodgson Design's Title block [this is denied by the Respondent]. After further discussion, the Respondent agreed to destroy the drawings provided to him and that any further amended drawings would not make any reference to 'Roy Hodgson Design';
(d) Phyland told the Applicant to attend the Boroondara Council, to have the planning permit updated to reflect the changes he had discussed and made with Terry B. Phyland further advised the Applicant and the Respondent that BGE's computations were still applicable; and
(e) The Respondent, at the conclusion of the meeting, stated that he would issue a Stop Work Order and Building Notice, despite Phyland's objection, by reason that he could not inspect the frame, owing to the brick work that had been put up by Terry B; and because the frame was not being built in accordance with plans.
we have also been contacted by Peter Stewart who is assisting you with your project and provided us with some information. Can you please confirm if the attached invoice has been settled and confirm how payment was made.[133]
5. The design (attached) was created by me; therefore you also do not own it.
(b) the Respondent had still not commented upon the amended planning permit or working and engineering drawings provided to him.[150]
[from the Applicant to the Respondent][155]
I had sent you the building permit on 18 November 2009 (see attached)
You have delayed the project since 4 November 2009; do you need another three months?
[From the Respondent to the Applicant][156]
thanks for your colourful e-mail - trust the litigation is going well
as you should be aware, it is your builder's fault that you are in this situation - YOU are the builder.
I lifted the Stop Work Notice on your property sometime ago and advised you that you could continue working in accordance with the APPROVED DOCUMENTATION ONLY. Obviously you wanted to proceed with your amended design and that takes time to review.
In regards to the application form, if you wish me to use the outdated application form, then I can do so, just provide me with written confirmation from Roy, Barry and Alan that they are the respective designers for their elements of the project.
Otherwise provide an updated application form or this could drag on for another three months.
I'm sure we would all like to get this project completed.
the invoices stand as they are and I will not be providing any further breakdown... If the above is not to your liking, then you may contact the building commission or your solicitor.[162]
I intend to carry out the work as an Owner Builder [Yes/No]
Yes, after frame construction; No, before frame construction
Your statement 'Yes, after frame construction; No, before frame construction' is not acceptable. You were listed as the 'Owner Builder' for all the works and remain so as far as we are aware.
I found that Ms Orders had completed the second story of the frame and had covered the roof and clad the walls. The building was largely finished, but there had still been no approved frame inspection and an amended building permit reflecting the as built structure had still not been issued (nor indeed had an application for the amended building permit yet been made). I told Ms Orders that I would therefore have two issue another Building Notice and Stop Work Order.[167]
(a) She gave her evidence in a clear and unreserved manner;
(b) She had a comprehensive recollection of conversations and correspondence;
(c) Her evidence was consistent and her explanations plausible; and
(d) Her evidence was not contradicted or materially undermined under cross-examination.
(1) A person must not carry out building work unless a building permit in respect of the work has been issued and is in force under this Act and the work is carried out in accordance with this Act, the building regulations and the permit.
500 penalty units, in the case of a natural person.
2500 penalty units, in the case of a body corporate.
(2) Subsection (1) does not apply to building work exempted by or under this Act or the regulations.
The main purpose of the Building Legislation (Amendment ) Bill is to amend the Building Act 1993 to prevent speculative builders avoiding insurance and registration requirements by falsely claiming to be Owner Builders. The bill also enables a home owner to make more fully informed decisions about carrying out domestic building work as an Owner Builder.
The bill provides that a prospective Owner Builder must obtain a certificate of consent from the Building Practitioners Board before applying for a building permit for domestic building works where the cost of the work is more than $12000.
When applying for a certificate of consent, the bill requires an Owner Builder to confirm that they have read an information statement published by the Building Commission on their rights and responsibilities as an Owner Builder.
The bill ensures that genuine Owner Builders and registered builders can continue to operate. Its provisions will help to protect consumers from exposure to unregistered builders who seek to bypass the existing domestic builder registration system by operating as, or through, Owner Builders...
Home owners are often unaware of the extent of the risks and liabilities they are exposed to when choosing to take out, or being 'duped' into taking out, a building permit as an Owner Builder...
An Owner Builder is a person who carries out building work on his or her own land. This generally does not include registered builders...
Owner builders take on many of the responsibilities of a builder. Depending on the circumstances, these may include:
Supervising building work and/or carrying out the work themselves
Ensuring the work meets relevant building regulations, standards and other laws
Arranging for building inspections as required by law at particular stages of the building work
Obtaining an occupancy permit or certificate of final inspection from the relevant building surveyor on completion of work.
If you engage a builder for the entire project then you are not an owner-builder. The builder needs to be registered if the work costs over $5,000 and provide domestic warranty insurance if the work is valued over $12,000.
If you engage a number of builders to construct various parts of the work and also do some small components yourself, you can be an Owner Builder.
If you enter into a contract with a person to complete any building work and the contract price is more than $5,000 the person must be a Registered Building Practitioner and must enter into a written domestic building contract [which] must include certain minimum terms...[and where]...the contract price is more than $12,000, that person must ensure that the work is covered by domestic building insurance.
If you engage this person before the building permit is issued, you must notify the relevant building surveyor when you make the application for the building permit. If you engage this person after a building permit has been issued, you must give the relevant building surveyor written notice of the engagement within 14 days, including the building practitioner's registration details.
If you do not comply with this requirement, you may be prosecuted by the Building Commission.
Tradespeople carrying out the following domestic building work as a single trade only do not need to offer you a major domestic building contract for work over $5,000: [following is a list of relevant works]
24A Further limitations on issue of building permit
(2) The relevant building surveyor may consider an application for a building permit for domestic building work that is to be carried out under a major domestic building contract but must not issue the permit unless he or she is satisfied that -
(a) the work is to be carried out by a builder who is registered under Part 11 in the appropriate class of domestic builder and is covered by the required insurance; and
(b) each architect to be engaged in the building work is an insured architect.
(3) The relevant building surveyor may consider an application for a building permit for domestic building work where the cost of the work (estimated in accordance with section 201) is more than $12,000 and the work is not to be carried out under a major domestic building contract but must not issue the permit unless he or she is satisfied that -
(i) a builder who is registered under Part 11; or
(ii) an architect who is registered under the Architects Act 1991; or
(b) the Applicant has been issued with a certificate of consent for the work; or
(c) the Applicant is the Director of Housing within the meaning of the Housing Act 1983.
An owner of land or a building must not carry out domestic building work as builder on that land or in respect of that building if the cost of the work (estimated in accordance with section 201) is more than $12,000 unless the owner -
(a) has been issued with a certificate of consent for the work; or
(b) is a builder who is registered under Part 11; or
(c) is an architect who is registered under the Architects Act 1991; or
(e) is carrying out the work in accordance with an emergency order, a building notice or a building order made under Part 8.
25C Application for owner-builder certificate of consent
(1) A natural person may apply to the Building Practitioners Board for the issue of a certificate of consent to carry out domestic building work on land_._
(i) a statutory declaration by the Applicant stating that the Applicant has read the information statement published under section 25I; and
Was the Respondent in breach of his duty in issuing the building permit?
(ii) building a domestic residence or dealing with builders;
(iii) the significance of the distinction between a registered building practitioner and a subcontractor;
(iv) the role and responsibilities of an Owner Builder;
(v) the distinction between obtaining a builder permit as an Owner Builder and a registered builder for the building work being recorded on such permit; or
(vi) the significance of a major domestic building contract and requisite insurance for the benefit of the building owner.
(b) She was 'duped' by Terry B into applying for a Certificate of Consent and applying for a building permit as Owner Builder;
(c) The application for a Certificate of Consent was completed in her presence by George B and signed by the Applicant;
(d) She either did not receive or did not in fact read the Information Statement;
(e) Neither Terry nor George B gave her any advice or read any document to her in relation to her application for a Certificate of Consent;
(f) She relied upon and trusted the advice of Terry and/or George B to the effect that an application for a Certificate of Consent was appropriate for her and would facilitate the obtaining of a building permit;
(g) In their initial telephone contact, the Applicant advised the Respondent that she had or was proposing to use a builder;
(h) In their initial meeting, the Applicant advised the Respondent that:
(i) she had never previously been involved in a building project and did not know how to complete an application for a building permit; and
(ii) the slab and frame would be constructed by a registered builder.
(ii) the Applicant's competencies as an Owner Builder;
(iii) registered builders or requisite insurance;
(iv) what building work was being constructed under a major domestic building contract.
(i) the relevant regulatory requirements and the risks pertaining to being an Owner Builder; or
(ii) the requirements for builder registration, insurance and engaging builders, where appropriate under a major domestic building contract.
I can start work on 1st March 2009, please give me the building permit asap...[206]
[I]t is clear that the duty of a building surveyor and inspector is to act in conformity with the requirements of the Act and Regulations and this is his sole function. Thus, in my view, it would be wrong to burden a surveyor or inspector with issues in relation to design, supervision, or workmanship except insofar as those issues relate to the Act and Regulations. The issues of design, supervision and workmanship are for an architect or supervising builder, not for a surveyor or inspector who is exercising a statutory function.
There is a great danger, particularly in professional negligence matters, of applying an unrealistic hindsight judgment. Any fool can be wise after the event. That is not the test. The Court must be careful to judge the conduct of a defendant, where negligent failure to warn is asserted, by reference to what the defendant reasonably knew at the relevant time. Not after the loss has been suffered.
[the case] raises an issue concerning liability in negligence for pure economic loss caused by the collapse of part of the foundations of a house (and for other consequential damage). The property had been purchased by ... ("the Taitapanuis"). They claimed that the loss resulted from breaches of duty owed to them as subsequent purchasers in respect of the careless and incompetent performance by the ... "the surveyor"), of his functions as a building surveyor engaged by the builder of the house on behalf of the property owners some three years earlier...[213]
It was accepted at the tribunal that the plans and other documents submitted to [the building surveyor] with the application for the building permit were inadequate in a considerable number of respects, in particular because the footings as specified were of stump and pad design. The tribunal held that [the building surveyor] had been in substantial default by issuing the permit. That default arose in the first place because, contrary to the regulations, no specifications had been provided describing the materials and methods to be used. Moreover, the plans did not identify the particular external wall material, although it did show a wall thickness of 250 mm which ought to have alerted [the building surveyor] to the likelihood that masonry product would be used. So the tribunal held that [the building surveyor] had failed in his basic functions of ensuring that the application contained sufficient information to ensure compliance with the regulations. It described his conduct as amounting to "gross carelessness and incompetence. The learned judge in the Trial Division said the tribunal was clearly justified in saying that the plans were "completely inadequate and [appeared] in effect to have been done by a thumbnail dipped in tar". The tribunal also noted that some 20 other construction defects had been identified, most of which [the building surveyor] should have picked up in the course of his inspection - in particular, subfloor defects in the bearers and joists, defects in the roof framing, clear shortcomings in the flashings and a failure to provide the correct safety glass for certain window and door panels.[214] [footnotes omitted]
Quite apart from the surveyors role in inspecting buildings which are under construction ... the surveyor must not issue a permit unless he or she is satisfied, inter alia, that the building work will comply with the Act and the regulations - into the latter of which is incorporated the Building Code of Australia. No doubt it is with that responsibility in mind that the regulations prescribe, as we have said, the documents which must be provided with an application for a permit, and which empower the surveyor to require additional information. A permit, when granted under the hand of the surveyor, is a written certification which both authorises building work and declares that the building work as described in the application will comply with the Act and the regulations.
[98] In the present case, the permit should never have been issued. [the building surveyor], as the tribunal found, failed his basic statutory function "to the extent of gross carelessness and incompetence". He issued the permit when the material provided by the application was, as he must have known, much lacking. Because he issued the permit in those circumstances, the critical design flaw - which must have required refusal of the permit - went unrecognized.[215] [footnotes omitted]
... by both the known, inevitable, dependence of each subsequent owner upon the proper performance of the surveyors function, and the assumption of responsibility by the surveyor, in accordance with his statutory duties, to ensure that the house as constructed complied with the building regulations.
...the surveyor - like the builder and the engineer - has a responsibility to the first owner to take reasonable care to ensure that the house as constructed complies with all applicable building regulations.[216]
...the vulnerability of the plaintiff has emerged as an important requirement in cases where a duty of care to avoid economic loss has been held to have been owed. 'Vulnerability', in this context, is not to be understood as meaning only that the plaintiff was likely to suffer damage if reasonable care was not taken. Rather, 'vulnerability' is to be understood as a reference to the plaintiff's inability to protect itself from the consequences of a defendant's want of reasonable care, either entirely or at least in a way which would cast the consequences of loss on the defendant.[217]
... [has] complete control over the discharge of the statutory functions of granting the necessary permits. Like the first owner, the subsequent owner is completely powerless to influence that process;[220] and
(d) The owners (first and subsequent) of the house will rely - or will necessarily be dependent - on the building inspections having been done with reasonable care. Each owner is vulnerable to any failure on the part of the defendant to take such care.[221]
...I told Laukart, as I subsequently told Ms Orders, that if the engineers were satisfied with the frame from a structural point of view, the frame would be unconditionally approved. However, as I explain below and as Ms Orders was very well aware, BGE would not confirm that the frame met the intent of their structural design.
As per your request, please find attached the photos of building works at the 6 Croydon Road, Surrey Hills property.[230]
then responsibility for rectifying defective and non-complying building works would have been placed fairly upon the responsible builder.
Delay in Issuing Stop Work Order ['SWO'] and Building Notice ['BN']
It is well-established that, in contract as in tort, the intervening act, sufficient to constitute a novus actus interveniens and break the chain of causation, can be the act of a third party: Pounder v North Eastern Railway Co [1892] 1 QB 385; Cobb v Great Western Railway Co [1894] AC 419 and Weld-Blundell v Stephens [1920] AC 956. However, the intervening act of a third party will not operate as a novus actus interveniens if the contractual duty of which the defendant is in breach was to guard against the very act of the intervener or that class of act: London Joint Stock Bank v Macmillan & Arthur [1918] AC 777; De La Bere v Pearson Ltd [1908] 1 KB 280; Stansbie v Troman [1948] 2 KB 48 and Schilling v Kidd Garrett Ltd [1977] 1 NZLR 243. Further, an abnormal intervening event, which combines with the defendant's breach of contract to cause damage to the plaintiff, will generally break the chain of causation unless the intervening act was of a kind which was to be reasonably anticipated: The Wilhelm (1866) 14 LT 636 and Monarch Steamship Co Ltd v Karlshamns Oljefabriker.
Assessment of Damages for Second Frame and Alleged Delays
(i) failing to reply to enquiries of the Applicant and/or her solicitor;
(ii) delay in issuing a SWO and BN following the second frame inspection;
(iii) increasingly unprofessional and obstructive behaviour;
(iv) confusing instruction or lack of instruction of the Respondent in his dealing with the Applicant and other building practitioners; and
(v) issuing a further SWO and BN, ostensibly for the same reasons as the previously cancelled Order and Notice.
(b) the malicious damage caused to the building work in January 2010; and the time taken for rectification works;
(c) on the part of the Applicant, extensive changes made to the permit documentation, which appear to have been directed at both complying with the 'as-built' structure; and providing for additional features desired by the Applicant.[260]
454 In turn, these factors have all contributed to the delay in issuing an Occupancy Permit and the need for the Applicant to rely upon rental accommodation.
Restriction on recovery of damages for non-economic loss
A person is not entitled to recover damages for non-economic loss in any proceeding in a court in respect of an injury to a person caused by the fault of another person unless the person injured has suffered significant injury.
injury means personal or bodily injury and includes -
non-economic loss means any one or more of the following -
It follows from this excursus that a claim for damages that involves any component of mental distress, anxiety or stress is caught by the definition of injury and therefore Part VBA of the Wrongs Act applies. So claims in the past that have been allowed as being for "mental distress or anxiety" as part of a claim for inconvenience must be put to one side.
The question remains then whether a claim can be made for inconvenience alone where no mental harm is alleged as a consequence of that inconvenience.
In my opinion, notwithstanding the difficulties associated with identification of what constitutes physical inconvenience and also ensuring that no allowance is made for any element of mental distress, this category of damage remains claimable in tort ...[264]
The end result is, I think, that if a claim is to be made for inconvenience there needs to be a strong evidentiary foundation that the tortious act led to a genuine inconvenience of some significance (be that in terms of impact or duration).[265]
(ii) he dealt directly with a number of building practitioners, often without reference to the Applicant;
(iii) he failed to take any notes at his inspections, save for some notations on the building plans;
(iv) he failed to prepare a report following such inspections;
(v) he failed to make any record of telephone conversations relating to his dealings with the Applicant and other building practitioners;
(vi) he failed to identify defects, including substantial defects; and
(vii) he gave inadequate, misleading and confusing advice to the Applicant in relation to the result of inspections and what was required of her;
(c) purporting to approve the first frame, subject to engineers sign off, which neither constituted a meaningful 'conditional' approval nor gave adequate direction and instruction to the Applicant or other relevant building practitioners, as to what was required;
(d) determining to issue a Stop Work Order and Building Notice in relation to the second frame, and then failing to do so for two weeks;
(e) issuing a Stop Work Order and Building Notice in relation to the second frame without specifying the nature of the non-complying and/or defective work;
(f) issuing a further Stop Work Order and Building Notice ostensibly on the same basis, after the earlier Order and Notice had been cancelled; and
(g) otherwise causing unjustifiable obstruction and delay.
476 The Applicant suffered financial loss as a direct and foreseeable consequence of the Respondent's breach of statutory duties and negligence.
DOMESTIC BUILDING CONTRACTS ACT 1995 (THE 'DBCA')
Section 5 of the DBCA provides, in part:
(a) the erection or construction of a home, including - ...
(23) A reference to a home in subsection (1) includes a reference to any part of a home.
Section 53 of the DBCA, provides, so far as it is relevant to this Application:
(1) The Tribunal may make any order it considers fair to resolve a domestic building dispute.
(2) Without limiting this power, the Tribunal may do one or more of the following -
(a) refer a dispute to a mediator appointed by the Tribunal;
(i) found to be owing by one party to another party;
(ii) by way of damages (including exemplary damages and damages in the nature of interest);
(ba) order the payment of a sum of money representing a part payment under a major domestic building contract if -
(i) the requirement in paragraph (b) of section 42 has been met but the requirement in paragraph (a) of that section has not; and
(ii) the Tribunal is satisfied that the work required to complete the contract (including rectifying any defects) is minor in nature and not such as would prevent the owner from occupation and quiet enjoyment of the building;
(bb) order payment of a sum of money representing the amount of any money in dispute (including an amount on account of costs) to be paid into the Domestic Builders Fund pending the resolution of the dispute;
(bc) order payment of a sum of money to be paid out of the Domestic Builders Fund representing the amount of any sum paid into the Domestic Builders Fund in accordance with an order under paragraph (bb);
(c) vary any term of a domestic building contract (including the completion date, the contract price, a provisional sum or the amount to be paid for any prime cost item);
(d) declare that a term of a domestic building contract is, or is not, void under section 132;
(e) declare void any unjust term of a domestic building contract, or otherwise vary a domestic building contract to avoid injustice;
(f) order the refund of any money paid under a domestic building contract or under a void domestic building contract;
(g) order rectification of defective building work;
(3) In awarding damages in the nature of interest, the Tribunal may base the amount awarded on the interest rate fixed from time to time under section 2 of the Penalty Interest Rates Act 1983 or on any lesser rate it thinks appropriate.
(4) In determining whether a term of a contract is unjust under subsection (2)(e), the Tribunal may have regard to -
(a) the intelligibility of the contract generally, and of the term in particular;
(b) the extent to which the term, and its legal and practical effect, was accurately explained to the building owner before the term was agreed to and the extent to which the building owner understood the term and its effect;
(c) the relative bargaining power of the parties to the contract;
(d) the consequences to the parties to the contract if the term is complied with or not complied with and the relative hardship of those consequences to each party;
(e) whether or not it was reasonably practicable for the building owner to reject, or negotiate for a change in, the term before it was agreed to;
(f) the relationship of the term to the other terms of the contract;
(g) whether the building owner obtained independent legal or other expert advice before agreeing to the term;
(h) whether unfair pressure, undue influence or unfair tactics were used to obtain the building owner's consent to the contract or the term;
(i) whether at the time the term was agreed to the builder knew, or could probably have found out by asking, that the term would cause the building owner hardship;
(j) the conduct of the parties to the contract after the term was agreed to;
(k) whether the term is usually found in domestic building contracts;
(m) whether the term is unconscionable, harsh or oppressive;
(n) any other factor the Tribunal thinks is relevant.
(5) Despite anything to the contrary in this section, in determining whether a term of a contract is unjust, the Tribunal is not to have regard to any injustice arising from circumstances that were not reasonably foreseeable when the term was agreed to.
Section 54 of the DBCA defines a 'domestic building dispute' so far as it is relevant to this Application, as follows:
(1) A domestic building dispute is a dispute or claim arising -
(ii) a building practitioner (as defined in the Building Act 1993); or
in relation to a domestic building contract or the carrying out of domestic building work; or
(2) For the purposes of subsection (1), a dispute or claim includes any dispute or claim in negligence, nuisance or trespass but does not include a dispute or claim related to a personal injury.
(3) A reference to a building owner in this section includes a reference to any person who is the owner for the time being of the building or land in respect of which a domestic building contract was made or domestic building work was carried out.
Under s 3 of the BA, the term 'domestic building work' is defined as having the same meaning as it has in the DBCA.
SECTION 108 FAIR TRADING ACT 1999
Section 108 of the Fair Trading Act 1999 was substantially re enacted in Section 184 of the Australian Consumer Law and Fair Trading Act 2012, with effect from 1 July 2012, as follows:
184 Settlement of consumer and trader disputes or small claims
(1) VCAT may hear and determine a consumer and trader dispute.
(2) VCAT may do one or more of the following in relation to a consumer and trader dispute -
(a) refer a dispute to a mediator appointed by VCAT;
(i) found to be owing by one party to another party;
(ii) by way of damages (including exemplary damages and damages in the nature of interest);
(d) declare that a term of a contract is, or is not, void;
(e) order the refund of any money paid under a contract or under a void contract;
(f) make an order in the nature of an order for specific performance of a contract;
(k) order a party to do or refrain from doing something;
If the supplier has default listed the purchaser with a credit reference agency in relation to a perceived debt owing, VCAT, in addition to declaring that there is no debt owing, may order the supplier to contact the credit reference agency and have the default listing removed from the purchaser's credit record.
(3) The power to make an order under subsection (2)(j) may only be exercised by a judicial member of VCAT.
(4) In awarding damages in the nature of interest, VCAT may base the amount awarded on the interest rate fixed from time to time under section 2 of the Penalty Interest Rates Act 1983 or on any lesser rate it thinks appropriate.
317 Provision and display of permit information
(1) A person who is in charge of the carrying out of building work on an allotment must take all reasonable steps to ensure that a copy of the building permit and one set of any approved plans, specifications and documents relating to that permit are available for inspection at the allotment concerned while the building work for which the building permit was issued is in progress.
(2) A person who is in charge of the carrying out of building work on an allotment must -
(i) the registration numbers and contact details of the builder and building surveyor; and
(ii) the number of the relevant building permit and the date of issue of the permit -
are displayed on the allotment in a conspicuous position accessible to the public prior to the commencement of building work (including demolition or removal of a building on the allotment); and
(b) take all reasonable steps to ensure that a copy of that information continues to be so displayed and remains visible and legible for the duration of the building work to which the permit applies.
(a) perform his or her work as a building practitioner in a competent manner and to a professional standard; and
(b) immediately inform the client in writing if a conflict of interest arises or appears likely to arise between his or her interest as a building practitioner and that of his or her client; and
(c) receive remuneration for his or her services as a building practitioner solely by the professional fee or other benefits specified in the contract of engagement or by the salary and other benefits payable by the building practitioner's employer.
A building practitioner who contravenes the requirements of regulation 1502 may be the subject of an inquiry under section 179 of the Act.
[4] TB 2.278, Tab 42: also refer to Respondent's email 27 May 2010 at TB 2.280, Tab 43.
[5] [2010] VSC 295 at [44] This passage was adopted with approval by His Honour Judge Shelton in the County Court Building Cases Division in Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd [2011] VCC 294 at [99].
[7] Which deals with the requirement for building surveyors to carry out inspections at mandatory notification stages as defined in Regulation 7.1.
[8] Which deals with the power of a building surveyor to cause an inspection of building work at any time.
[9] Which deals with the power of a building surveyor in the conduct of inspections.
[10] Which deals with directions by the building surveyor to a person in charge of carrying out the building work and the issue of a building notice.
[11] Which deals with the obligation upon a building surveyor to issue a certificate of final inspection.
[12] Which deals with the circumstances in which a building notice may be issued.
[13] Which deals with the circumstances in which a stop work building order may be issued.
[14] Which deals with matters which the building surveyor must refer to the BC.
[17] As set out in POC 5 and 6 respectively.
[18] [2004] VCAT 547 at [39].
[20] Which encompassed: slab and frame, with windows.
[24] Witness Statement signed on 7 May 2012, as amended and adopted on 8 June 2012.
[25] Witness statement signed on 17 May 2012.
[26] Witness statement signed on 2 May 2012.
[27] Witness statement signed on 30 May 2012.
[28] Refer ss 170(1)(b)(ii) and 170(5) of the BA.
[33] Ex 11: Witness statement confirmed 15 June 2012 minus paragraphs 9 and 10.
[34] TB Vol 2 Tab 10 photo 33 shows the collapsed brick wall.
[36] Preliminary drawings had been prepared by Terry B's godson, who could not afford the time to complete.
[38] The Applicant gave evidence that she relied on the advice of the plumber and concreter, in this regard.
[40] Exhibit U: email of 9 December 2008; and Exhibit Y: letter dated 28 November 2008.
[41] Exhibit RH-2 to Hodgson's witness statement: TB 3.326.
[42] Under cover of email dated 24 November 2009, which otherwise makes no reference to the circumstances of the amended drawings, as explained in the Applicant's evidence.
[43] Exhibit RH-2 to Hodgson witness statement: TB 3.326; 3.327 and 3.328.
[47] TB 2.4, Applicant's Witness Statement paragraph 15.
[48] Ex N; Page 5 of the statement lists questions identifying the requisite knowledge of an Owner Builder, with which the Respondent agreed.
[49] The Respondent under cross-examination.
[50] Refer also Respondent's witness statement at paragraph 7; TB 3.3.
[52] Between 19 and 25 February 2009: TB 4.174, 4.175, 4.179, 4.182, 4.184, 4.187.
[53] All of whom are noted on the Application for Building Permit dated 24/01/09: TB 3.38.
[57] Refer also, Points of Defence filed 18 August 201: especially paras 14(b)(ii); 16(a); para 18 - particulars para (vii); 20(b)(iii); 22(b)(i); 25((b)(vi) and (vii); 31(b)(ii); para 55 - particulars).
[59] Refer also to Exhibit 9: Amended witness statement of Respondent.
[60] TB 4.599: Application Kit for an Owner Builder summarises the responsibilities assumed as a builder.
[62] In his evidence Hodgson agreed he gave the Applicant Laukart's details.
[64] Exhibit 4 to affidavit; and TB 2.32.
[65] A description given in the witness statement of Vincent Urbano, which he could not substantiate in his oral evidence: TB 3.333, paragraph 3.
[68] Urbano denied receiving such cash.
[73] TB3.55. Those drawings are at TB4.204A-E.
[75] Respondent's witness statement at [19].
[76] Refer photos taken by the Applicant behind tab 10, with the numbers 13, 14, and 15.
[78] Cf evidence of the Applicant that she advised the Respondent upon signing a contract with CHI.
[79] Exhibit 6 to affidavit. The Applicant said that she only saw this email during Discovery process in an earlier proceeding against CHI.
[80] TB Vol 3, 3.74 email from the Respondent to BGE.
[81] Cf Phyland report which says that: "vi. Bracing incorrectly applied".
[83] Including the arrow endorsed on 4.47 Plan S7A.
[85] The Respondent was referred to photos taken by the Applicant's daughter on 25 April and 2 May 2009.
[88] He agreed he could have issued a Building Notice and a Stop Work Order.
[97] Exhibit 13 to affidavit; TB Vol 2 Tab 13.
[99] Exhibits 15, 16 and 17 to affidavit.
[102] Exhibit 19 to affidavit; TB Vol 3, Ex 21, 3.100.
[104] TB Vol 4B, 4.249 email dated 15 June 2009.
[107] Vol 2 Tab 26 2.196 and 2,197 & 2.199
[108] Vol 2 Tab 26 2.196 & 2,197 and 2.199.
[114] Exhibit 24 to affidavit; TB Vol 2, 2.191.
[116] Exhibits 26 and 27 to affidavit.
[117] TB Vol4, 4.370-4.374; report dated 26 October 2009.
[120] Ex SM 26 to Respondent's witness statement; TB 3.8.
[123] TB 3.326: Email dated 24 November 2009 from Hodgson to the Applicant alleging unauthorised amendments to and use of his plans.
[124] Being drawings which the Applicant says the Respondent put a strike through Hodgson's stamp.
[137] In which she copied names from previous permit; together with copies again of Compliance Frame & Steel and Roof Truss manual.
[138] These drawings were still using the Hodgson's design.
[144] Exhibit 32 to affidavit; TB 2.226, 4.377; 3.172.
[146] TB 3.330. Hodgson explains his position in quite some detail.
[150] Refer exchange of emails 3.240, 3.149, 3.151. Respondent did not reply to building permit application.
[154] Exhibit 36 to affidavit; TB 3.178.
[165] Exhibit 46 to affidavit; TB 3.216.
[172] Exhibit 59 to affidavit; TB 3.242.
[174] TB 3.263 refers to a site meeting on 3/12/2010, the Applicant was not present.
[175] TB 2.331: Exhibit 54 to affidavit.
[176] TB 2.331: Exhibit 54 to affidavit.
[183] TB 2.348, letter dated 6 May 2011.
[185] Ex DD and Ex EE 536, Letter from BC dated 16 June 2011 to Respondent is in identical terms.
[186] Ex FF, Vol 4B 4.538; and Ex GG Vol 4B 4.543 a being relevant correspondence.
[188] Refer in particular to the statements of Urbano, Hodgson and Bartzis.
[189] For instance, timber measurements of 70x30 instead of the specified 60x40.
[190] Exhibit Q: Exchange of emails and faxes between Respondent and CHI and the Applicant.
[192] Sections 24A, 24B and 24C and Division 3A.
[193] Ms Delahunty Minister for Planning Assembly 3 June 2004.
[194] TB 4.596-4.627. refer pages 3, 8 and 10.
[195] All of which are comprehensively covered in the Information Statement which a prospective Owner Builder is required to declare that they have read.
[198] Section 25E(1)(e), subject to (4).
[202] Refer form of declaration required to be made by an applicant for a Certificate of Consent: TB 4.624.
[204] See in particular Respondents' Final Submissions at [24].
[205] Refer exemptions applicable under Regulation 6(b) of the DBCA Regulations.
[207] Refer also National Australia Bank Ltd v Nemur Variety Pty Ltd [2002] VSCA 18; (2002) 4 VR 252 at 274-5 per Batt JA.
[208] [2004] VCAT 547 at [39].
[209] [2003] VCAT 375 (at [39]).
[210] [2006] VCAT 1363 (11 July 2006) at paragraphs 242-244.
[211] [2003] NSWCA 225 per Ipp JA at [30].
[212] [2006] VSCA 30 the 'Taitapanui case'.
[213] At para 47 per Ormiston and Ashley JJA.
[217] At paragraph 10 per Maxwell P quoting from Woolcock Street Investments Pty Ltd v CDG Pty Ltd [2004] HCA 16; (2004) 216 CLR 515 At 530-1, [23].
[219] At paragraph 30(1) referring to Bryan v Moloney (1995) 182 CLR 609 at 627.
[223] Both Phyland and Mitchell reported that the frame could not be rectified and should be demolished.
[224] Refer report of BGE dated 18 May 2009 which identified 13 issues: see TB at 2.128; and report of Landy: Exhibit Z.
[225] Cf evidence of Hodgson who readily identified defects from photographs and said he would have prepared a report with photographs and required rectification and then a further inspection.
[227] TB 2.121, email from James of CHI to the Applicant on 7 May 2009; and TB 4.385.
[228] The Respondent admitted that his current form of Pro forma inspection report does not contain the option of 'approved subject to...; Refer Exhibit P.
[231] Refer email of Respondent TB 3.81.
[235] CHI also claimed 'variations' totalling $15,460.50.
[236] Exhibit 8; and POC 25. Refer also paragraph 15 of CHI POC; TB 2.45; CHI was not permitted to demand any payment from Ms Orders under the contract because Regulation 12 of the DBR Regulations 2007 was not complied with.
[238] Exhibit Z: Refer Attachment D to Phyland's report. It is apparent from the list contained in this attachment that some items, that the accounts for Austral Bricks and Fulton, at least, may need to be excluded.
[239] I note that the sum of $4,807 has been previously claimed for cost of demolition, but it is unclear where this amount comes from: TB 4.459.
[240] TB3.119. When the Respondent subsequently discovered that the frame had been demolished, he emailed the Applicant for an update.
[241] TB3.113 email dated 28 July 2009 in which the Respondent sets out the requirement for amendments to building and planning permits and seeks the Applicant's advice.
[248] 25 November 2009 (TB3.168); and 27 November 2009 (3.172).
[249] National Australia Bank Ltd v Nemur Variety Pty Ltd [2002] VSCA 18; (2002) 4 VR 252 at 274-5 per Batt JA.
[250] Per Phillips and Batt JJA. [1], [2], [41].
[251] Per Callaway and Batt JJA. [9], [45]-[48].
[252] (1987) 9 NSWLR 310 McHugh JA as he then was said at 361-362.
[254] Modbury Triangle Shopping Centre v Anzil at [40], [42], and [152].
[255] [2010] VSCA 247; see especially Neave JA at [86] - [92].
[256] Detailed in the report of the Applicant's insurer's loss adjustor dated 15 February 2011 at TB3.285 and the report of the truss manufacturer Pryda dated 25 November 2010 at TB3.298.
[257] Pursuant to the quote she obtained on 20 January 2010 (EX JJ).
[260] The Applicant made amendments to her plans between the time she obtained her amended planning permit on 5 November 2009 and a further amended planning permit on 7 March 2011.
[261] Baltic Shipping Company v Dillon [1993] HCA 4; (1992) 176 CLR 344 at 365 per Mason CJ.
Orders
Maloney & Anor
(2002) 4 VR 252
(1992) 176 CLR 344
(2004) 216 CLR 515
(1995) 182 CLR 609
(1998) 192 CLR 603
(1987) 9 NSWLR 310
(2000) 205 CLR 254