© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2004] HCA 16
respondent. Appeal dismissed with costs. The Court of Appeal's negative answer to the Case Stated stood.
The High Court dismissed a purchaser's claim that engineers owed it a duty to prevent financial loss from defects in a commercial building's foundations. The original owner had refused to pay for proposed soil testing, and the limited facts did not show that the engineers had assumed responsibility to that owner in the way relevant to Bryan v Maloney. The record also did not show that the later purchaser was unable to protect itself from the risk. The Court stressed that foreseeable financial loss alone is not enough. It did not decide that engineers can never owe subsequent purchasers a duty concerning commercial buildings, and it left several broader questions open.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
2,080 words · generated 05/10/2026
Woolcock Street Investments Pty Ltd bought a warehouse and office complex in Townsville in September 1992. The consulting engineer, CDG Pty Ltd, had designed the foundations in 1987. The development proceeded without the proposed geotechnical investigations because the original owner's manager refused to pay for them. CDG had obtained a quotation for the work, but the case does not establish that CDG insisted on the tests or that the owner was contractually obliged to accept them ([25], [41]).
33 cited instruments linked from this judgment.
The sale contract to Woolcock contained no warranty that the building was free of defects, and the vendor did not assign any rights it might have had against third parties for defects ([1], [31]). Structural distress became apparent in 1994, more than a year after Woolcock's purchase. The parties agreed that the distress resulted from settlement of the foundations, material below the foundations, or both ([2]).
Woolcock sued CDG and its employee, alleging negligent design and related failures. The case reached the High Court by way of a Case Stated. The question was whether the agreed facts and Woolcock's pleading disclosed a cause of action in negligence. The Court of Appeal answered no. The High Court dismissed Woolcock's appeal with costs ([3], [8], [36]).
The procedural route mattered. The Court explained that the parties had asked it to decide a substantive legal question using a limited set of agreed facts and pleaded allegations. Courts should be cautious about developing common law principles on an artificially narrow record, and any answer must be understood in light of that limitation ([6]-[7]). The holding therefore addresses the case as presented, not every possible claim by a later owner of commercial premises.
The joint reasons of Gleeson CJ, Gummow, Hayne and Heydon JJ centred on the absence of facts establishing the relationship needed to support a duty for pure economic loss. The Court treated the alleged loss as pure economic loss: the building's defects had been identified, and the claim was not for personal injury or damage to other property ([19]-[20]).
Foreseeability was not enough. The Court said that pure economic loss is not recoverable merely because negligence caused a reasonably foreseeable loss. The law's caution reflects the risks of overly broad liability and interference with commercial activity ([21]). It discussed the development of the law through cases such as Caltex Oil and Perre, including the importance of vulnerability, but did not purport to settle a comprehensive test for every economic-loss claim ([22]-[24]).
A key step was the comparison with Bryan v Maloney. That case concerned a builder and a subsequent purchaser of a dwelling house. The reasoning depended, among other things, on an anterior conclusion that the builder owed the first owner a duty to avoid the relevant economic loss. It also relied on the relationship of responsibility and known reliance between builder and first owner, and on circumstances associated with a permanent dwelling and subsequent purchasers ([10]-[15]).
Here, the facts did not establish that anterior duty. The original owner had refused to fund the soil investigations proposed by the engineers. The majority considered this inconsistent with an inference that the owner had simply entrusted the design to the engineers in a relationship marked by assumption of responsibility and known reliance. The case therefore lacked an important feature that supported the reasoning in Bryan ([25]-[27]).
The majority also found no adequate basis for concluding that Woolcock was vulnerable to the economic consequences of the alleged negligence. Vulnerability was not simply exposure to a risk of loss. The question was whether Woolcock could protect itself from the consequences, or arrange for those consequences to fall on the engineers. The sale's lack of a warranty and assignment described what had happened, but did not establish what protections Woolcock could have negotiated or obtained ([31]). Nor did the stated material establish that the defects could not have been discovered through other investigations. The local-authority certificate concerned a limited statutory inspection, not every investigation that might have been undertaken ([32]). The facts also said nothing about the significance of the purchase to Woolcock ([33]).
The Court did not treat the original contract as irrelevant. It said that the contract defines the task the engineers undertook, and that it would be difficult to impose a duty requiring more or different work than the contract required or permitted. But the Court expressly left open whether a difference between contractual obligations and a proposed duty to a later owner would always defeat a duty. It could dismiss the appeal for other reasons ([28]-[30]).
Before this decision, Bryan v Maloney had recognised that a builder of a dwelling house could owe a duty to a subsequent purchaser to avoid foreseeable economic loss caused by latent defects. The High Court in Woolcock explained that Bryan's reasoning was not simply a rule that foreseeability of loss from defective construction creates a duty. It depended on the particular relationship between the builder and original owner and on the Court's assessment of the relationship with the later owner ([10]-[15]).
The High Court did not overturn Bryan. It observed that later developments had moved away from proximity as the single conceptual determinant of duty, and that Bryan's reasoning could not be transferred mechanically to a commercial-building dispute ([18], [35]). The judgment also recognised that drawing a strict line between dwellings and other buildings could be difficult in mixed-use or similar situations. It did not, however, resolve the claim by creating a categorical distinction based on building type ([17]).
After Woolcock, the result in Bryan remained relevant to its own setting, but did not establish an automatic duty to subsequent purchasers of commercial buildings. The majority's reasoning instead directed attention to features such as vulnerability, known reliance, assumption of responsibility, the original contractual task, and what the particular facts show about the plaintiff's capacity to protect itself ([23]-[31]).
The judgments do not speak with one voice on the broader policy question. McHugh J, agreeing with the result, considered a broader range of factors and concluded that commercial owners and purchasers would ordinarily be able to protect themselves through contractual arrangements and investigations ([74]-[115]). Kirby J dissented, finding the pleaded claim reasonably arguable and emphasising the alleged latent character of the defect and the restricted procedural record ([123]-[124], [168]-[175]). Callinan J agreed that the appeal should be dismissed and questioned both an extension to commercial premises and aspects of Bryan itself ([208]-[215]).
The judgment records statutory protections for purchasers of dwelling houses in various jurisdictions and notes that such protections had overtaken Bryan to a significant extent ([35], [309]). Those statutory provisions are described in the judgment as context; the majority did not decide this appeal by applying them to Woolcock.
At [21], the majority says that pure economic loss is not recoverable merely because a defendant's negligence caused it and it was reasonably foreseeable. In plain English, a foreseeable financial consequence does not, by itself, establish that the defendant owed the plaintiff a legal duty to prevent it.
At [23], the majority explains vulnerability as the plaintiff's inability to protect itself from the consequences of a defendant's lack of care, either entirely or in a way that shifts the loss to the defendant. This is more specific than simply being at risk of financial harm.
At [25]-[27], the Court identifies the missing connection with the original owner. The owner refused to pay for geotechnical investigations, and the facts did not show the relevant assumption of responsibility and known reliance. The majority therefore could not take the same route to a duty as the reasoning in Bryan v Maloney.
At [31], the majority distinguishes between what occurred and what could have been arranged. The fact that Woolcock received no warranty does not, without more, establish that it was unable to seek one, obtain an assignment, or otherwise protect itself. The record did not address those possibilities.
At [7], the Court warns that a legal principle developed on a restricted factual record may be too broad or misleading. The practical meaning is that the outcome must be read in the context of the Case Stated, not as an answer to every factual variation involving a later purchaser and defective building work.
The decision is most directly relevant where a later purchaser seeks damages from engineers, builders, or other construction professionals for financial loss associated with defects in a commercial building, without a direct contract with those professionals. It is particularly relevant where the claim concerns the cost of repairs or a reduction in value, rather than personal injury or damage to other property ([19]-[20], [25]).
The reasoning makes the relationship between the construction professional and the first owner important. A lawyer assessing a different case would likely want to examine what the original contract required, whether investigations were proposed or refused, what work the professional undertook, and whether the facts support responsibility and known reliance ([25]-[30]).
The decision also makes the later purchaser's practical ability to protect itself important. Relevant facts may include what was known about the defect, whether expert inspection was available, what the sale negotiations allowed, and whether contractual warranties or assignments could realistically have been obtained. In Woolcock, the pleadings and agreed facts did not answer those questions ([31]-[33]).
The decision does not establish that a subsequent purchaser can never recover for economic loss from construction professionals, nor that a commercial building can never support a duty. It resolves the pleaded case on the limited material before the Court, while leaving broader questions open ([6]-[7], [35]).
The judgment itself was delivered in 2004 and cannot report how later courts treated Woolcock after that date. It does, however, describe how courts had treated Bryan v Maloney before Woolcock was decided. The reasons note that Bryan had attracted criticism and that intermediate courts had debated whether its reasoning applied only to dwelling houses or extended to other buildings ([8], [16]-[18]).
The Queensland Court of Appeal had answered Woolcock's Case Stated in the negative, reasoning that Bryan did not extend to commercial premises ([8]). The High Court did not adopt a simple rule that commercial buildings are categorically excluded. Instead, the majority held that Bryan's reasoning did not establish a duty on the particular facts and pleading, especially because the necessary relationship with the original owner and the purchaser's vulnerability were not shown ([25]-[27], [31]-[35]).
McHugh J's reasons discuss the different approaches taken in England, Canada, New Zealand and other jurisdictions to defective-premises claims ([49]-[55]). The joint reasons, however, stated that overseas authorities did not need to be discussed in detail because the appellant did not ask the Court to adopt a new or different Australian principle ([34]). Kirby J considered that the overseas trend supported allowing the claim to proceed, but he dissented ([184]-[190]).
The Court did not decide whether a duty of care to a subsequent purchaser is necessarily inconsistent with a construction contract that limits the professional's obligations to the original owner. It stated that the contract is relevant because it defines the task undertaken, but left the broader effect of any disconformity unresolved ([28]-[30]).
The Court also did not formulate a complete test for vulnerability in every pure economic loss case. It explained the concept and applied it to the restricted facts before it, while expressly saying that the appeal could be resolved without stating the breadth of a general proposition about vulnerability ([23]-[24]).
Nor did the Court determine whether Bryan v Maloney would be decided the same way under later negligence principles. The majority said the case could be decided without casting doubt on Bryan's result ([35]). McHugh J likewise said that nothing in his reasons was intended to suggest Bryan would now be decided differently, while identifying the vulnerability of dwelling purchasers as a matter that could bear on the question ([116]).
Finally, the procedural issue remains significant: what a court should do when a developing duty question is presented on a limited Case Stated or pleading. The majority warned about developing law on restricted facts, while Kirby J considered that the incomplete record favoured allowing a trial rather than terminating the claim ([6]-[7], [123]-[124], [137]-[138]).
This is general legal information, not legal advice. Zoe can make mistakes. Before acting on or relying on this analysis, have a qualified Australian lawyer check it.
Source: the High Court of Australia (www.hcourt.gov.au). Converted to plain text by ZoeLaw. Not the official version.
HIGH COURT OF AUSTRALIA
GLEESON CJ,
McHUGH, GUMMOW, KIRBY, HAYNE, CALLINAN AND HEYDON JJ
WOOLCOCK STREET INVESTMENTS PTY LTD APPELLANT
AND
CDG PTY LTD (formerly Cardno & Davies
Australia Pty Ltd) & ANOR RESPONDENTS
Woolcock Street Investments Pty Ltd v CDG Pty Ltd [2004] HCA 16
1 April 2004
B19/2003
ORDER
Appeal dismissed with costs.
On appeal from the Supreme Court of Queensland
Representation:
D F Jackson QC with A M Daubney SC and G D Beacham for the appellant (instructed by Gilshenan & Luton Lawyers)
P A Keane QC with P D T Applegarth SC and M A Hoch for the respondents (instructed by Thynne & Macartney)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
CATCHWORDS
Woolcock Street Investments Pty Ltd v CDG Pty Ltd
Negligence – Duty of care – Where pure economic or financial loss – Whether engineer owed duty of care to subsequent owner of commercial premises – Salient features of relationship giving rise to duty – Vulnerability – Assumption of responsibility – Known reliance (or dependence) – Relevance of latent defects and structural defects.
Negligence – Duty of care – Where pure economic or financial loss – Whether engineer owed duty of care to subsequent owner of commercial premises – Construction of dwellings and construction of other buildings – Relevance of the contract with the original owner – Relevance of statutory protection.
Practice and procedure – Whether cause of action on agreed facts – Sufficiency of pleading – Limitations on determining separate questions.
Words and phrases – "salient features", "vulnerability", "assumption of responsibility", "known reliance (or dependence)", "construction of dwellings and construction of other buildings".
Home Building Act 1989 (NSW), ss 18A-18G, 90-99.
House Contracts Guarantee Act 1987 (Vic), ss 5-8.
Domestic Building Contracts Act 1995 (Vic), ss 8-10.
Building Work Contractors Act 1995 (SA), ss 32-35.
Building Act 1975 (Q), ss 52-53.
Queensland Building Services Authority Act 1991 (Q), ss 68-69, Sched 2.
Home Building Contracts Act 1991 (WA), ss 25A-25D.
Housing Indemnity Act 1992 (Tas), ss 7-9, 11-14.
Building Act 1972 (ACT), ss 62, 64-65.
GLEESON CJ, GUMMOW, HAYNE AND HEYDON JJ.
The issue
In 1987, the first respondent, a company carrying on the business of consulting engineers, designed foundations1 for a warehouse and offices in Townsville. The land on which this building (referred to in the pleadings as "the Complex") was to be built was owned by the trustee of a property trust. Some years after the building was finished it was sold by the then trustee of the property trust to the appellant. The contract for the sale of the land did not include any warranty that the building was free from defect and there was no assignment by the vendor of any rights that the vendor may have had against others in respect of any such defects.
More than a year after the appellant bought the land, it became apparent that the building was suffering substantial structural distress. It is agreed that the distress was and is due to the settlement of the foundations of the building, or the material below the foundations, or both. The appellant alleges that the first respondent and its employee, the second respondent, each owed it a duty to take reasonable care in designing the foundations for the building. The respondents deny that they owed the appellant any duty of care; they deny that they acted in breach of any such duty; they say that despite advising the then owner of the land to allow them to obtain soil tests, the then owner instructed them to proceed without soil tests and to use structural footing sizes provided by the builder. Did the respondents owe the appellant a duty of care?
The procedural context
The appellant commenced proceedings in the Supreme Court of Queensland. After it had delivered a further amended statement of claim and each respondent had filed a defence to that pleading, the parties consented to an order stating a case for the opinion of the Court of Appeal. The question asked in the Case Stated was: "On the agreed facts, does the further amended statement of claim delivered on 11 April 2000 disclose a cause of action in negligence against the defendants?" The Case Stated set out some agreed facts, but those added little to the exiguous allegations of fact made in the pleadings.
The critical paragraphs of the appellant's statement of claim asserted that the respondents had owed it a duty of care but said very little about why that was so. It is as well to set out those paragraphs:
"6(a) The Complex was, at all material times, to be a permanent structure to be used indefinitely.
(b) It was, at all material times, foreseeable that:
(i) failure to design the structure of the Complex properly;
(ii) failure to design the foundations of the Complex properly;
(iii) failure to take any or any proper account of the sub‑soil conditions under the Complex; and/or
(iv) failing to construct the foundations properly,
would result in an owner of the Complex suffering loss and damage of the kind pleaded in paragraphs 3, 4 and 5 herein.
7 The said loss and damage to the Plaintiff has been caused by reason of the negligence of the First Defendant and/or the Second Defendant in discharge of their respective duties to the Plaintiff."
Particulars were given under par 7 of the respects in which it was alleged that there had been a failure to discharge the duties.
The appellant's statement of claim took a form that is common enough in claims for negligence. The allegation of duty was rolled up with the allegation of breach. The pleading did allege that the respondents had been engaged to perform engineering work in connection with the construction of the building, a "permanent" structure, and alleged that the adverse consequences of which the appellant complained were foreseeable but it alleged no other matter bearing upon the existence of the asserted duty of care.
The question reserved for the opinion of the Court of Appeal could have been understood as inviting attention only to the sufficiency of the appellant's pleading. In both the Court of Appeal and this Court, however, the Case Stated has been treated as requiring an answer to a substantive question of law. That is, argument proceeded on the basis that this Court, and the Court of Appeal, were to assume that whether either respondent owed the appellant a duty of care was a question which could be resolved having regard only: first, to the facts set out in the Case Stated; secondly, to any inference that might reasonably be drawn from those facts; and thirdly, to the facts alleged in the appellant's statement of claim.
If a plaintiff is willing to have a point determined by reference only to the facts which that plaintiff chooses to put before the court, and the parties join in seeking determination of the issue, there may appear to be little reason to refuse to decide the point tendered by the parties. It is important, however, to recognise that there may be difficulty in using such procedures in cases in which it is necessary to consider developing, as distinct from applying, common law principles. The dangers of developing common law principle against an artificially constricted body of fact are self‑evident. That is why, in some cases, even if the parties join in asking a court to determine a question separate from trial of the facts, it may be prudent for the court to decline to answer the question presented as being one which it is inappropriate to answer2. Indeed, as Bass v Permanent Trustee Co Ltd illustrates3, in some circumstances to answer a question may be contrary to the judicial process. If the question is answered, it is important to identify any limitations which the procedure adopted may impose on the breadth of any principle that is to be identified as having been established or applied.
The Court of Appeal
The Court of Appeal answered the question reserved: "On the agreed facts, does the further amended statement of claim delivered on 11 April 2000 disclose a cause of action in negligence against the defendants?", "No"4. Both McMurdo P5 and Thomas JA6 (with whose reasons Douglas J7 agreed) concluded that Bryan v Maloney8 established that the builder of a dwelling may owe a duty of care to a remote purchaser. Their Honours concluded9, however, that those who built or designed commercial buildings did not owe any duty of care to subsequent purchasers. As Thomas JA put the matter10, "there is no good reason, in terms of principle or policy, to extend the decision in Bryan v Maloney to cases other than residential dwellings" (footnote omitted). McMurdo P was of the view that in Fangrove Pty Ltd v Tod Group Holdings Pty Ltd11 the Court of Appeal had earlier considered and rejected what her Honour described12 as "[t]he extension of the Bryan v Maloney principle to commercial buildings" and concluded that there was no reason to depart from that earlier decision13.
What did Bryan v Maloney decide?
Bryan v Maloney
In Bryan v Maloney, the Court (Mason CJ, Deane, Toohey and Gaudron JJ, Brennan J dissenting) decided that the builder of a dwelling house owed a subsequent purchaser, Mrs Maloney, of the house a duty to take reasonable care to avoid the economic loss which the subsequent purchaser suffered as a result of the diminution in value of the house when the fabric of the building cracked because the footings were inadequate. Both Mason CJ, Deane and Gaudron JJ in their joint reasons14, and Toohey J in his separate reasons15, noted that there was no direct relationship between the builder and the subsequent purchaser, but concluded16 that the necessary relationship of proximity existed to warrant finding that the builder had owed the subsequent purchaser a duty of care.
It is important to identify the reasoning that underpinned this conclusion. It is convenient to do that by reference to the joint reasons of Mason CJ, Deane and Gaudron JJ. The reasons of Toohey J, although differently expressed, did not depend upon the application of any principles different from those applied in the joint reasons.
The joint reasons began by examining the relationship between the appellant (the builder) and the first owner of the house (Mrs Manion). They, of course, were the parties to the contract in performance of which the builder had built the house. That contract was said17 to be "non‑detailed and [to contain] no exclusion or limitation of liability". Accordingly, the content of the contract was said not to preclude the existence of a duty of care owed by the builder to Mrs Manion, not only to take reasonable care to avoid injury to her person or property18 but also to avoid "mere economic loss by Mrs Manion of the kind ultimately sustained by Mrs Maloney when the inadequacy of the footings became manifest"19. That was because
"the ordinary relationship between a builder of a house and the first owner with respect to that kind of economic loss is characterized by the kind of assumption of responsibility on the one part (i.e. the builder) and known reliance on the other (i.e. the building owner) which commonly exists in the special categories of case in which a relationship of proximity and a consequent duty of care exists in respect of pure economic loss."20
There was said21 to be nothing to suggest that the relationship between the builder and the first owner was not characterised by such an assumption of responsibility and reliance.
Four considerations were then identified as warranting the conclusion that a relationship of proximity also existed with the subsequent owner. First, the house was identified22 as a "connecting link", it being a permanent structure and a significant investment for a subsequent owner like the respondent. Secondly, it was pointed out23 that it was foreseeable that economic loss would likely result from negligent construction of the house. Thirdly, it was said24 that there was no "intervening negligence or other causative event". Finally, the similarities with the relationship between the builder and the first owner as regards the particular kind of economic loss were said25 to be "of much greater significance than the differences to which attention has been drawn, namely, the absence of direct contact or dealing and the possibly extended time in which liability might arise".
It is evident, then, that the conclusion that the builder owed a subsequent owner a duty to take reasonable care to avoid the economic loss which that subsequent owner had suffered depended upon conclusions that were reached about the relationship between the first owner and the builder. In particular, the decision in the case depended upon the anterior step of concluding that the builder owed the first owner a duty of care to avoid economic loss of that kind.
Both this anterior step, and the conclusion drawn from it, were considered in the context of the facts of the particular case – in which the building in question was a dwelling house. The propositions about assumption of responsibility by the builder and known reliance by the building owner were said26 to be characteristics of "the ordinary relationship between a builder of a house and the first owner" (emphasis added). At least in terms, however, the principles that were said to be engaged in Bryan v Maloney did not depend for their operation upon any distinction between particular kinds of, or uses for, buildings. They depended upon considerations of assumption of responsibility, reliance, and proximity. Most importantly, they depended upon equating the responsibilities which the builder owed to the first owner with those owed to a subsequent owner.
Criticisms of Bryan v Maloney
The decision in Bryan v Maloney has not escaped criticism27. Some of those criticisms found reflection in the series of questions posed by Brooking JA in Zumpano v Montagnese28. It is not necessary, in this case, to attempt to deal with all of those criticisms, or to attempt to answer all of the questions posed in Zumpano. Rather, two points should be made.
First, for the reasons given earlier, it may be doubted that the decision in Bryan v Maloney should be understood as depending upon drawing a bright line between cases concerning the construction of dwellings and cases concerning the construction of other buildings. If it were to be understood as attempting to draw such a line, it would turn out to be far from bright, straight, clearly defined, or even clearly definable. As has been pointed out subsequently29, some buildings are used for mixed purposes: shop and dwelling; dwelling and commercial art gallery; general practitioner's surgery and residence. Some high‑rise apartment blocks are built in ways not very different from high‑rise office towers. The original owner of a high‑rise apartment block may be a large commercial enterprise. The list of difficulties in distinguishing between dwellings and other buildings could be extended.
Secondly, the decision in Bryan v Maloney depended upon the view30 that "the overriding requirement of a relationship of proximity represents the conceptual determinant and the unifying theme of the categories of case in which the common law of negligence recognizes the existence of a duty to take reasonable care to avoid a reasonably foreseeable risk of injury to another". It was the application of this "conceptual determinant" of proximity that was seen as both permitting and requiring the equation of the duty owed to the first owner with the duty owed to the subsequent purchaser. Decisions of the Court after Bryan v Maloney31 reveal that proximity is no longer seen as the "conceptual determinant" in this area.
Economic loss
The damage for which the appellant seeks a remedy in this case is the economic loss it alleges it has suffered as a result of buying a building which is defective. Circumstances can be imagined in which, had the defects not been discovered, some damage to person or property might have resulted from those defects. But that is not what has happened. The defects have been identified. Steps can be taken to prevent damage to person or property.
A view was adopted for a time in England32 that, because there was physical damage to the building, a claim of the kind made by the appellant was not solely for economic loss. That view was questioned in Sutherland Shire Council v Heyman33 and rejected in Bryan v Maloney34. It was subsequently also rejected by the House of Lords in Murphy v Brentwood District Council35. There is no reason now to reopen that debate and neither side in the present matter sought to do so. The damage which the appellant alleges it has suffered is pure economic loss.
Claims for damages for pure economic loss present peculiar difficulty. Competition is the hallmark of most forms of commercial activity in Australia. As Brennan J said in Bryan v Maloney36:
"If liability were to be imposed for the doing of anything which caused pure economic loss that was foreseeable, the tort of negligence would destroy commercial competition37, sterilize many contracts and, in the well‑known dictum of Chief Judge Cardozo38, expose defendants to potential liability 'in an indeterminate amount for an indeterminate time to an indeterminate class'."
That is why damages for pure economic loss are not recoverable if all that is shown is that the defendant's negligence was a cause of the loss and the loss was reasonably foreseeable.
In Caltex Oil (Australia) Pty Ltd v The Dredge "Willemstad"39, the Court held that there were circumstances in which damages for economic loss were recoverable. In Caltex Oil, cases for recovery of economic loss were seen as being exceptions to a general rule, said to have been established in Cattle v Stockton Waterworks40, that even if the loss was foreseeable, damages are not recoverable for economic loss which was not consequential upon injury to person or property. In Caltex Oil, Stephen J isolated a number of "salient features" which combined to constitute a sufficiently close relationship to give rise to a duty of care owed to Caltex for breach of which it might recover its purely economic loss41. Chief among those features was the defendant's knowledge that to damage the pipeline which was damaged was inherently likely to produce economic loss42.
Since Caltex Oil, and most notably in Perre v Apand Pty Ltd43, the vulnerability of the plaintiff has emerged as an important requirement in cases where a duty of care to avoid economic loss has been held to have been owed. "Vulnerability", in this context, is not to be understood as meaning only that the plaintiff was likely to suffer damage if reasonable care was not taken. Rather, "vulnerability" is to be understood as a reference to the plaintiff's inability to protect itself from the consequences of a defendant's want of reasonable care, either entirely or at least in a way which would cast the consequences of loss on the defendant44. So, in Perre, the plaintiffs could do nothing to protect themselves from the economic consequences to them of the defendant's negligence in sowing a crop which caused the quarantining of the plaintiffs' land. In Hill v Van Erp45, the intended beneficiary depended entirely upon the solicitor performing the client's retainer properly and the beneficiary could do nothing to ensure that this was done. But in Esanda Finance Corporation Ltd v Peat Marwick Hungerfords, the financier could itself have made inquiries about the financial position of the company to which it was to lend money, rather than depend upon the auditor's certification of the accounts of the company.
The appellant's claim
On the facts set out in the Case Stated and alleged in the pleadings neither respondent owed the appellant a duty to take reasonable care to avoid the appellant suffering the economic loss which it alleges it suffered. As counsel for the respondents submitted, it was not alleged that the respondents breached any obligation to the original owner. Unlike Bryan v Maloney, it cannot be said, in this case, that the respondents owed the original owner of the land a duty to take reasonable care to avoid economic loss of the kind of which the appellant now complains. It was agreed in the Case Stated that, despite the first respondent obtaining a quotation for geotechnical investigations, the original owner of the land, by its manager, refused to pay for such investigations. (The respondents go further in their pleadings and allege that the original owner directed the adoption of particular footing sizes.) The relationship between the respondents and the original owner of the land was, therefore, not one in which the owner entrusted the design of the building to a builder, or in this case the engineer, under a simple, "non‑detailed" contract. It was a relationship in which the original owner asserted control over the investigations which the engineer undertook for the purposes of performing its work.
In its pleading the appellant did not allege that the relationship between the respondents and the original owner was characterised by that assumption of responsibility by the respondents, and known reliance by the original owner on the respondents, which is referred to in the joint reasons in Bryan v Maloney50. Such further facts as are agreed, far from supporting any inference that this was the nature of the relationship between the respondents and the original owner, point firmly in the opposite direction. There was not, therefore, what was referred to in Bryan v Maloney51 as "an identified element of known reliance (or dependence)" or "the assumption of responsibility".
It follows that the appellant's contention that the respondents owed it a duty of care cannot be supported by the reasoning which was adopted in Bryan v Maloney. What we earlier referred to as the anterior step of demonstrating that the respondents owed a duty of care to the original owner is not made out.
The relevance of the contract with the original owner
In this case, as in Bryan v Maloney52, it is not necessary to decide whether disconformity between the obligations owed to the original owner under the contract to build or design a building and the duty of care allegedly owed to a subsequent owner will necessarily deny the existence of that duty of care. However, as Windeyer J said in Voli v Inglewood Shire Council53, the terms of the contract between the original owner and the builder (or, in this case, the respondents) "is not an irrelevant circumstance" in considering what duty a builder or engineer owed others54. At the least, that contract defines the task which the builder or engineer undertook. There would be evident difficulty in holding that the respondents owed the appellant a duty of care to avoid economic loss to a subsequent owner if performance of that duty would have required the respondents to do more or different work than the contract with the original owner required or permitted55.
In Bryan v Maloney, it was found that there was no disconformity between the duty owed to the original owner and the duty owed to the subsequent owner. As Toohey J said56, that case was "uncomplicated by anything arising from the contract between the appellant and Mrs Manion" (the original owner).
This case can be determined without deciding whether disconformity of the kind we have mentioned would always deny the existence of a duty of care to a subsequent owner. There are other reasons for concluding that the respondents owed no duty of care to prevent the economic loss of which the appellant complains.
No vulnerability
Neither the facts alleged in the statement of claim nor those set out in the Case Stated show that the appellant was, in any relevant sense, vulnerable to the economic consequences of any negligence of the respondents in their design of the foundations for the building. Those facts do not show that the appellant could not have protected itself against the economic loss it alleges it has suffered. It is agreed that no warranty of freedom from defect was included in the contract by which the appellant bought the land, and that there was no assignment to the appellant of any rights which the vendor may have had against third parties in respect of any claim for defects in the building. Those facts describe what did happen. They say nothing about what could have been done to cast on the respondents the burden of the economic consequences of any negligence by the respondents. The appellant's pleading and the facts set out in the Case Stated are silent about whether the appellant could have sought and obtained the benefit of terms of that kind in the contract.
It may be accepted that the appellant bought the building not knowing that the foundations were inadequate. It is not alleged or agreed, however, that the defects of which complaint now is made could not have been discovered. The Case Stated records that, before completing its purchase, the appellant sought and obtained from the relevant local authority a certificate that the building complied with the Building Act 1975 (Q) and some subordinate legislation. That the defects now alleged were not discovered by a local authority asked to certify whether the building was "a ruin or so far dilapidated as to be unfit for use or occupation or [was] ... in a structural condition prejudicial to the inhabitants of or to property in the neighbourhood"57 says nothing about what other investigations might have been undertaken or might have revealed.
Finally, if it is relevant to know, as was assumed to be the case in Bryan v Maloney, whether buying the building represented a very significant investment for the appellant58, there is nothing in the Case Stated or the appellant's pleading which bears on that question.
Overseas authorities
Conclusion and orders
The present case arises in a different factual context from that considered in Bryan v Maloney and can be decided without determining whether doubt should now be cast upon the result at which the Court arrived in that case. The actual decision in Bryan v Maloney has now been overtaken, at least to a significant extent, by various statutory forms of protection for those who buy dwelling houses which turn out to be defective. Reference is made to those provisions in the reasons of Callinan J. No doubt, as recognised earlier in these reasons, the principles applicable in cases of negligently inflicted pure economic loss have evolved since Bryan v Maloney was decided. Neither the principles applied in Bryan v Maloney, nor those principles as developed in subsequent cases, support the appellant's contention that on the facts agreed in the Case Stated and alleged in its statement of claim the respondents owed it a duty of care to avoid the economic loss which it alleged it suffered.
The appeal should be dismissed with costs.
McHUGH J. The question in this appeal is whether it is a principle of the Australian law of torts that those involved in the design or construction of commercial premises owe a duty to subsequent purchasers of the premises to take reasonable care to ensure that the building is free from defects so as to prevent pure economic loss to those purchasers. In my opinion, the Australian law of torts imposes no such duty. Moreover, although the point does not arise directly for decision, it must follow that, in the absence of a contract, those involved in the design or construction of commercial premises do not owe such a duty in tort to the first owner of the premises. Where there is a contract between the first owner and those involved in the design or construction of the building, notions of assumption of responsibility and reliance may be sufficient to create a duty in tort as well as obligations in contract. Without re‑introducing the discarded doctrine of proximity, no distinction can be drawn between the case of a first owner and the case of a subsequent purchaser in the absence of a contract with the defendant.
Statement of the case
Woolcock Street Investments Pty Ltd ("Woolcock") brings this appeal against an order of the Court of Appeal of Queensland. The effect of the order was that the respondents, in providing services concerning the construction of a building complex, did not owe Woolcock, as a subsequent purchaser of the building, a duty to take care to protect it from pure economic loss.
The building consists of warehouses and offices and has no dwellings. It was built for a company that was the trustee of a property trust and owned the land on which the building was erected. By late 1987, construction of the building was substantially completed. Woolcock purchased the building in September 1992 from a company that was the successor trustee of the property trust. The contract for sale of the building contained no warranty that it was free of defects. Nor did it assign to the purchaser any rights that the vendor might have against those involved in the design and construction of the building. Before entering into the contract for sale, Woolcock did not retain an expert to inspect the building and did not inquire of the tenants or their agents whether the premises had any structural defects.
Substantial structural distress to the building became apparent in 1994. The distress was caused by the settlement of the foundations or the material below the foundations. Woolcock claims that the damage that it suffered from the subsidence was caused by the negligence of the first and second respondents to the appeal. It claims that it is entitled to damages from the respondents under the principle propounded by this Court in Bryan v Maloney63. In Bryan, the Court held that the builder of a dwelling house owes a duty to a subsequent purchaser of the house to take reasonable care to avoid reasonably foreseeable decreases in its value resulting from latent defects in the house.
The first respondent to the appeal is a company that carries on business as a consulting engineer. It designed the building and provided supervision services in respect of its construction. The second respondent is a qualified civil engineer who was employed by the first respondent and acted as the project manager in respect of the design and construction of the building. In the performance of its services, the first respondent obtained a quotation from another company as to the cost of investigating the sub-soil conditions under the proposed building. Investigation would have required the digging of auger holes at locations on the site and the testing of samples of soil. However, the company undertaking the development of the site for the owner refused to pay for these investigations. Consequently, the construction proceeded without testing the suitability of the sub-soil for the building that was to be constructed.
"On the agreed facts, does the Further Amended Statement of Claim ... disclose a cause of action in negligence against the defendants?"
The Court of Appeal (McMurdo P, Thomas JA and Douglas J) held that that question should be answered "No". Their Honours held that the principle formulated in Bryan v Maloney did not extend and should not be extended to the purchasers of commercial premises. If change in the law is to be made, this Court or the legislature should make it.
Subsequently, this Court gave Woolcock special leave to appeal against the order of the Court of Appeal.
The action in tort for damages for pure economic loss
Since the decision of the House of Lords in Hedley Byrne & Co Ltd v Heller & Partners Ltd64, confusion approaching chaos has reigned in the law of negligence. At all events, it has reigned in that branch of negligence law concerned with a plaintiff suffering economic loss that does not result from injury to the plaintiff's person or property. Hedley Byrne held that a banker might owe a duty to take care to a plaintiff who had requested a credit reference concerning a third party with whom the plaintiff was proposing to deal. On the facts of that case, the House of Lords held that the defendant owed no duty to the plaintiff. But the recognition that, in the absence of a contractual or fiduciary obligation, a person could owe a duty to take reasonable care to prevent pure economic loss to another person has had a dramatic effect on the development of the common law.
Until Hedley Byrne, the accepted rule of the common law was that, absent a contractual, fiduciary or statutory duty, persons such as a banker owed no duty to prevent a plaintiff from suffering economic loss not resulting from injury to their person or property65. This was known as the "exclusionary" rule. The principal reason for the common law's reluctance to impose a duty of care in such cases was the fear that imposing liability on the defendant would result in an indeterminate liability in an indeterminate amount to an indeterminate number of persons66. The common law was particularly fearful of the consequences that might flow from permitting actions to be brought in respect of negligent statements because they were likely to cause economic losses more often than they would cause physical injury. Haunting the corridors of the common law was the spectre of the cartographer being held liable to all the passengers and all the owners of a ship and its cargo that had been sunk by the cartographer's negligence in omitting to mark a reef on a map.
Not only might a defendant be liable to an indeterminate number of persons who directly suffered pure economic loss as the result of the defendant's negligence but in many cases that negligence might have indirect economic consequences for those involved with those directly injured. Were these secondary victims also to be compensated for losses that the defendant had caused and ought reasonably to have foreseen? Fear of this "ripple" effect67 of the defendant's negligence played its part in inducing the common law to hold that, absent a contractual duty, a person owed no common law duty to prevent pure economic loss to others. In some cases, the common law and statute – , for example – allowed a person to recover "pure" economic loss in a derivative action based on a breach of a duty owed to a physically injured person. The action was perhaps the best known example of such a common law cause of action. But otherwise the common law set its face against a claim for pure economic loss that did not arise from a breach of contract or a fiduciary or statutory duty.
United Kingdom case law concerning defective premises
"First one has to ask whether, as between the alleged wrongdoer and the person who has suffered damage there is a sufficient relationship of proximity or neighbourhood such that, in the reasonable contemplation of the former, carelessness on his part may be likely to cause damage to the latter – in which case a prima facie duty of care arises. Secondly, if the first question is answered affirmatively, it is necessary to consider whether there are any considerations which ought to negative, or to reduce or limit the scope of the duty or the class of person to whom it is owed or the damages to which a breach of it may give rise".
His Lordship went on to say that, in the case of buildings, the cause of action "can only arise when the state of the building is such that there is present or imminent danger to the health or safety of persons occupying it"71. Lord Wilberforce classified the defect in that case – cracks in the walls and sloping floors – as "material, physical damage"72. In Pirelli General Cable Works Ltd v Oscar Faber & Partners73, the House of Lords confirmed the proposition that the damage in such cases was physical damage. On this classification of the damage, an action brought in respect of defective premises was a straightforward action for damages for injury to property. Accordingly, such a case fell under the principle formulated by the House of Lords in Donoghue v Stevenson74. Classifying the damage as physical, however, created problems for the purchasers of buildings. Such a claim suffered from the difficulty that the cause of action was complete when the damage occurred. If the defect was not discovered until many years after the plaintiff had acquired the premises, the plaintiff might be met with the defence that the action was statute barred.
In an earlier decision – Junior Books Ltd v Veitchi Co Ltd75 – however, the House of Lords had classified a claim for the cost of replacing defective flooring as one of pure economic loss. This classification was approved in D & F Estates Ltd v Church Commissioners for England76. There, the House of Lords held that, where a claim is based upon the defective condition of the building, the claim is one of pure economic loss. The House held that such a case is distinguishable from an action where the claim is that the defective premises caused physical injury to the plaintiff or damaged other tangible property of the plaintiff. These latter claims fall under the Donoghue v Stevenson principle. In Murphy v Brentwood District Council77, the House of Lords confirmed that a claim based on loss arising out of the discovery that premises were defective was a claim for pure economic loss. In D & F Estates Ltd, the House held that the cost of replacing the defective plaster work of a sub-contractor was not an item of damage for which a builder "could possibly be made liable in negligence under the principle of or any legitimate development of that principle". In , the House held that neither a builder nor a council that had approved the building plans could be liable for the cost of repairing a defect in a building discovered by a subsequent purchaser before the defect had caused any injury to person or other property. Such a claim was one for pure economic loss.
Canadian case law concerning defective premises
"a general rule that a cause of action arises for purposes of a limitation period when the material facts on which it is based have been discovered or ought to have been discovered by the plaintiff by the exercise of reasonable diligence".
New Zealand case law concerning defective premises
New Zealand courts have been the most liberal of the courts in common law jurisdictions in permitting an action in negligence for economic loss caused by defective premises83. In Bowen v Paramount Builders (Hamilton) Ltd84, three members of the Court of Appeal regarded the common law as recognising a cause of action on the part of a purchaser who later discovered a defect in premises. The Court treated the case as one of physical damage. Then in Mount Albert Borough Council v Johnson85, Cooke and Somers JJ held that the purchaser of a defective building was entitled to sue "in tort for economic loss caused by negligence, at least when the loss is associated with physical damage"86. However, their Honours held that the right of action accrued only when the defect became apparent or manifest87.
After a series of cases where plaintiffs successfully sued councils in negligence over the presence of defects in premises, the issue came before the New Zealand courts again in Invercargill City Council v Hamlin88. A majority of the Court of Appeal held that the plaintiff's cause of action arose when the plaintiff (the first owner) first discovered or ought reasonably to have discovered the defect89 and that the plaintiff could recover against the Council, which had inspected the foundations but negligently failed to note that they were not in accordance with the plans. The Court of Appeal held that there was sufficient proximity between the Council and the first owner because the Council had assumed responsibility for the inspection and the plaintiff had relied on the Council. The Judicial Committee of the Privy Council upheld the majority's decision. So far as the nature of the damage was concerned, Lord Lloyd of Berwick said90:
"In other words, the cause of action accrues when the cracks become so bad, or the defects so obvious, that any reasonable homeowner would call in an expert. Since the defects would then be obvious to a potential buyer, or his expert, that marks the moment when the market value of the building is depreciated, and therefore the moment when the economic loss occurs."
His Lordship thought that the Court of Appeal's perception of the prevailing circumstances in New Zealand justified it taking a different view of the law from that taken in Murphy91. The Judicial Committee held, therefore, that in New Zealand a subsequent purchaser could sue a council that had negligently approved a building that was not in accordance with the approved plans.
Australian case law concerning defective premises
Australian courts have long held that a person who suffers physical injury as the result of the defective design or execution of building work may sue in tort for the injury92. In Sutherland Shire Council v Heyman93, however, this Court held that the Council owed no duty to the second owners of a house to take reasonable care to ensure that the house had been constructed in accordance with plans that it had approved so as to prevent them suffering economic loss from defects in the house. After buying the house, the owners were forced to expend money to repair cracking and other problems resulting from faulty foundations. No member of the Court was willing to apply the general principle formulated by Lord Wilberforce in Anns v Merton London Borough Council. Gibbs CJ and Wilson J held that the evidence did not establish that the Council had acted negligently in exercising its discretionary power to inspect the premises. Mason, Brennan and Deane JJ held that the Council owed no relevant duty of care to the plaintiffs because they had not relied on any inquiry of the Council concerning the foundations or inspection. Mason, Wilson and Brennan JJ made no finding as to whether the damage giving rise to the action was physical damage or pure economic loss. However, Gibbs CJ held94 that the damage was physical damage. Deane J held that it was economic, not physical, damage. He held95 that, as a result of the defective foundations, the owners suffered pure economic loss upon the market value of the house falling when the defect was "first known or manifest". By "manifest", Deane J meant "discoverable by reasonable diligence"96. The view of Deane J as to the nature of the damage has prevailed97. It is economic loss, not physical damage.
In Bryan v Maloney98, a majority of this Court reached the opposite conclusion from that reached by the House of Lords in D & F Estates Ltd and Murphy v Brentwood District Council. Expressly or inferentially, the Court approved the decisions – but not necessarily the reasoning – in the Canadian and New Zealand cases to which I have referred. The majority (Mason CJ, Deane, Toohey and Gaudron JJ) held that the builder of a house owed a duty to a subsequent purchaser to take reasonable care to avoid reasonably foreseeable decreases in its value arising from the consequences of latent defects caused by the house's defective construction. Brennan J dissented.
The ratio decidendi of Bryan v Maloney
The first issue in this appeal is whether the ratio decidendi of Bryan v Maloney covers the present case. If it does, Woolcock must succeed. If it does not, a further issue arises as to whether this Court should hold that those involved in the building of commercial premises owe a duty to subsequent purchasers that is similar to the duty owed by a builder to a subsequent purchaser of a dwelling house.
The common law distinguishes between the holding of a case, the rule of the case and its ratio decidendi. The holding of a case is the decision of the court on the precise point in issue – for the plaintiff or the defendant. The rule of the case is the principle for which the case stands – although sometimes judges describe the rule of the case as its holding. The ratio decidendi of the case is the general rule of law that the court propounded as its reason for the decision.
Under the common law system of adjudication, the ratio decidendi of the case binds courts that are lower in the judicial hierarchy than the court deciding the case. Moreover, even courts of co‑ordinate authority or higher in the judicial hierarchy will ordinarily refuse to apply the ratio decidendi of a case only when they are convinced that it is wrong.
Prima facie, the ratio decidendi and the rule of the case are identical. However, if later courts read down the rule of the case, they may treat the proclaimed ratio decidendi as too broad, too narrow or inapplicable99. Later courts may treat the material facts of the case as standing for a narrower or different rule from that formulated by the court that decided the case. Consequently, it may take a series of later cases before the rule of a particular case becomes settled. Thus for many years, courts and commentators debated whether the landmark case of Donoghue v Stevenson100 was confined to manufacturers and consumers and whether the duty formulated in that case was dependent upon the defect being hidden with the lack of any reasonable possibility of intermediate examination101. If later courts take the view that the rule of a case was different from its stated ratio decidendi, they may dismiss the stated ratio as a mere dictum or qualify it to accord with the rule of the case as now perceived.
What then is the ratio decidendi of Bryan v Maloney? That question can be answered only by examining their Honours' reasoning, which I will summarise.
The reasoning in Bryan v Maloney
The starting point of the reasoning in the joint judgment102 in Bryan v Maloney was that the builder, Mr Bryan, had constructed a house for a Mrs Manion on land that she owned. Later, she sold the land and the house to another couple who, seven years after the house was built, sold it to the plaintiff, Mrs Maloney103. The trial judge – who found in the plaintiff's favour – had awarded an amount of damages which "would necessarily be expended in remedying the inadequate footings and the consequential damage to the fabric of the house"104. Thus, the only damage sustained by the plaintiff "was mere economic loss in the sense that it was distinct from, and not consequent upon, ordinary physical injury to person or property"105.
Their Honours said that two policy considerations could militate against recognition of a relationship of proximity in a case involving mere economic loss. First, the law was concerned to avoid the imposition of liability "in an indeterminate amount for an indeterminate time to an indeterminate class"106. Second, the common law feared that a duty to take care to avoid economic loss might be inconsistent with community standards in relation to what was ordinarily legitimate in the pursuit of personal advantage107.
The builder and Mrs Manion were parties to a contract, but the existence of the contract did not preclude a relationship of proximity between them under the law of negligence108. That did not mean that the existence of a contractual relationship was irrelevant to the existence of proximity or the content of a duty of care under the ordinary law of negligence109. However, the contract between the builder and Mrs Manion "was non-detailed and contained no exclusion or limitation of liability"110. Accordingly, neither the existence nor the content of the contract precluded the liability of Mr Bryan to Mrs Manion or Mrs Maloney under the law of negligence.
"In particular, the ordinary relationship between a builder of a house and the first owner with respect to that kind of economic loss is characterized by the kind of assumption of responsibility on the one part (i.e. the builder) and known reliance on the other (i.e. the building owner) which commonly exists in the special categories of case in which a relationship of proximity and a consequent duty of care exists in respect of pure economic loss."
Prima facie, a relationship of proximity also existed between the builder and persons such as Mrs Maloney who might sustain physical injury to person or property as a consequence of inadequate footings of part of the house while they or their property were lawfully in the house or in its vicinity116.
Whether the relationship that existed between the builder and a subsequent owner possessed the relevant degree of proximity to give rise to a duty to take reasonable care to avoid economic loss had to be considered in the context of the relationships of proximity to which their Honours referred117. Although the only connection between the builder and the subsequent owner was likely to be the house itself, their relationship was marked by proximity in a number of respects118:
. the house was a permanent structure which was to be used indefinitely and was likely to represent one of the most significant and possibly the most significant investment which the subsequent owner would ever make;
. it was foreseeable by the builder that the negligent construction of a house with inadequate footings was likely to cause economic loss when the inadequacy became manifest; and
. no intervening negligence or other causative event would occur between the construction and the sustaining of the economic loss.
"Upon analysis, the relationship between builder and subsequent owner with respect to the particular kind of economic loss is, like that between the builder and first owner, marked by the kind of assumption of responsibility and known reliance which is commonly present in the categories of case in which a relationship of proximity exists with respect to pure economic loss. In ordinary circumstances, the builder of a house undertakes the responsibility of erecting a structure on the basis that its footings are adequate to support it for a period during which it is likely that there will be one or more subsequent owners. Such a subsequent owner will ordinarily have no greater, and will often have less, opportunity to inspect and test the footings of the house than the first owner. Such a subsequent owner is likely to be unskilled in building matters and inexperienced in the niceties of real property investment. Any builder should be aware that such a subsequent owner will be likely, if inadequacy of the footings has not become manifest, to assume that the house has been competently built and that the footings are in fact adequate."
I do not think that the ratio decidendi of Bryan v Maloney applies to the case of commercial premises. The ratio can be put no higher than that the builder of a dwelling house owes a duty to a subsequent purchaser to take reasonable care to avoid reasonably foreseeable decreases in its value arising from the consequences of latent defects caused by the house's defective construction. Neither the stated reasons of the Court nor the material facts of the case justify any wider conclusion. Certainly, they do not justify the conclusion that the ratio of the case covers commercial premises. That is not to say that the reasoning in Bryan v Maloney – or by analogy its material facts – may not lead to the conclusion that the common law recognises an identical or similar duty in respect of the builder of commercial premises. That requires further analysis. But it does mean that the ratio decidendi of Bryan v Maloney does not automatically determine the result of this appeal.
Moreover, a conclusive reason for finding that the ratio of Bryan v Maloney does not cover this case is that the Court decided it when the doctrine of proximity governed the Australian law of negligence, and its reasoning is based on that doctrine. Thus, Mason CJ, Deane and Gaudron JJ said120:
"The cases in this Court establish that a duty of care arises under the common law of negligence of this country only where there exists a relationship of proximity between the parties with respect to both the relevant class of act or omission and the relevant kind of damage."
The indicia of a duty to prevent pure economic loss as the result of constructing commercial premises
. reasonable foreseeability of loss,
. indeterminacy of liability,
. autonomy of the individual,
. vulnerability to risk, and
. knowledge of the risk and its magnitude.
Reasonable foreseeability
Indeterminacy of liability
Autonomy of the individual
In Hill v Van Erp125, I pointed out that "Anglo-Australian law has never accepted the proposition that a person owes a duty of care to another person merely because the first person knows that his or her careless act may cause economic loss to the latter person". Speaking generally, a person owes no duty to prevent economic loss to another person even though the first person intends to cause economic loss to that other person. This particular immunity from liability reflects the common law's concern with the autonomy of the individual and its desire to give effect to the choices of the individual by not burdening his or her freedom of action. Thus, as long as a person is legitimately protecting or pursuing his or her commercial interests, the common law does not require that person to be concerned with the effect of his or her conduct on the economic interests of other persons126.
Questions concerning the autonomy of individuals do not seem relevant in the context of claims for damages for pure economic loss arising out of the defective design or construction of a building. Those involved in the building are already under a duty to the first owner to avoid physical injury to the owner's person and property. Consequently, imposing a duty to avoid economic loss to the first or a subsequent owner is not inconsistent with the pursuit of the legitimate interests of those who design or construct the building127.
Vulnerability to risk
Whether or not the plaintiff was vulnerable to the risk of injury from the defendant's conduct is a key issue in determining whether the defendant owed a duty of care to the plaintiff. Indeed, the issue of the purchaser's vulnerability to economic loss is the critical issue in determining whether those involved in the construction of commercial premises owe a duty of care to the purchaser. In this context, vulnerability to risk means not that the plaintiff was exposed to risk but that by reason of ignorance or social, political or economic constraints, the plaintiff was not able to protect him or herself from the risk of injury.
Subject to the express terms of the contract, the first owner or purchaser has extensive contractual remedies open to him or her in respect of the negligent construction of the building. The ordinary building contract contains an implied term that the work will be done in accordance with the contractual stipulation, with proper materials128, in a workmanlike manner and that the building will be reasonably fit for its purpose. Similar terms will be implied in the contracts made with other persons who are involved in the design or construction of the building. These contractual remedies will lie against those involved even in cases where sub-contractors have carried out the work or services. Such remedies usually provide sufficient protection against the problems that are likely to be encountered during the first few years of the building's life.
But extensive as contractual protection may be – it is unlikely to be narrower than in tort – it suffers from one shortcoming. A cause of action in contract arises upon breach. In the case of a defective building, the breach will frequently occur before the loss-causing defect manifests itself. Hence, the first owner of a commercial building may find that his or her claim in contract is outside the relevant limitation period and statute barred. Nevertheless, by insisting that the construction contract be made under seal, the first owner can ordinarily protect him or herself against most problems concerning a defective building that were reasonably foreseeable.
Still, even when the contract is under seal, the first owner may be left with a remedy that is unenforceable. When the defect does not manifest itself for some time, the first owner may find that the builder is insolvent129 or in liquidation, or has gone out of business. If, as is often the case, the defect in the premises results from a sub‑contractor's negligence, holding that there is no duty in tort to guard against economic loss arising from the negligent design or construction of a building deprives the first owner of a valuable remedy against the sub-contractor. No doubt it may be possible in some cases for the first owner to enter into contractual indemnities or warranties with the sub-contractor. In other cases, the first owner may be able to sue the sub-contractor on any warranty given by the sub-contractor to the builder.
The defendant's knowledge of the risk and its magnitude
Other policy factors
Responsibility to control third parties
Outflanking the law of contract
Until the decision of the House of Lords in Hedley Byrne134, the received wisdom was that pure economic loss cases belonged to the law of contract, not tort. Even as late as 1986, the Judicial Committee of the Privy Council and the House of Lords appeared to assume that the contract and not tort was ordinarily the source of the remedy for the recovery of negligently caused economic loss135. Indeed, one reason that the House of Lords gave for denying the owner's claim in D & F Estates Ltd136 was that it would outflank the operation of the law of contract. Lord Bridge of Harwich said137 that to require the builder to owe a duty to a subsequent purchaser "would be to impose upon him for the benefit of those with whom he had no contractual relationship the obligation of one who warranted the quality of the plaster as regards materials, workmanship and fitness for purpose".
But since Hedley Byrne, the argument that economic loss falls within the domain of contract rather than tort cannot be sustained in Australia and probably cannot be sustained even in England. Nor since the decision of the House of Lords in Donoghue v Stevenson138 is it possible to argue that the law of negligence should not be permitted to outflank fundamental contractual doctrines such as consideration and privity. Until the decision of the House of Lords in White v Jones139 and the decision of this Court in Hill v Van Erp140, it was possible to argue that the law of negligence should not be concerned with the loss of expectancies. But those decisions put an end to that argument. They held that a person could bring an action in tort against a solicitor in respect of the loss of an expectancy under a will. In White v Jones141, Lord Goff of Chieveley said that he did not consider that "damages for loss of an expectation are excluded in cases of negligence".
The decisions in , , and , therefore, make it difficult to argue that claims in negligence for pure economic loss should be excluded merely because such claims may outflank or undermine fundamental doctrines of the law of contract. In , this Court rejected the notion that in Australia contract and tort were so neatly compartmentalised that it would be an error to give a remedy in tort for economic loss. So far as the builder and first owner were concerned, Mason CJ, Deane and Gaudron JJ said:
"as a matter of policy, the sanctity of contract or the compartmentalization of the law dictates that liability under the ordinary principles of negligence ... must be excluded as between parties in a contractual relationship notwithstanding the absence of any actual agreement between the parties to that effect".
Once the courts rejected the traditional view that professional persons such as solicitors and architects could only be sued in contract144, it became likely that, in building cases, tortious remedies would extend to third parties affected by the performance of the contract.
The better view in all cases – not merely building cases – is that the capacity of a person to protect him or herself from damage by means of contractual obligations is merely one – although often a decisive – reason for rejecting the existence of a duty of care in tort in cases of pure economic loss.
Whether the securing of an alternative remedy in contract was really open to a plaintiff who has suffered economic loss depends upon current market conditions and conveyancing practices. In Henderson v Merrett Syndicates Ltd145, the House of Lords held that the existence of various contractual arrangements between the plaintiffs and certain managing agents and underwriters did not prevent the plaintiffs from suing in tort. The market conditions were such that the plaintiffs could not bargain for protection against the risks of the agents and others being careless. Similarly, in Smith v Eric S Bush146, the House of Lords held that a purchaser of a house could sue a careless valuer in tort because, having regard to market conditions, the purchaser was not able to protect herself against the valuer's negligence. Likewise in Bryan v Maloney147, the inability of an ordinary purchaser of a dwelling house to realistically protect him or herself against the builder's negligence influenced this Court to allow the purchaser to sue the builder in tort.
As I have pointed out, the Case Stated does not reveal the extent to which, if at all, it is open to the first owner or subsequent purchaser, as a matter of commerce or conveyancing practice, to protect him or herself by contractual remedies against those involved in the negligent design or construction of commercial premises. However, it would be surprising if they could not do so. The first owners and subsequent purchasers of commercial premises are usually sophisticated and often wealthy investors who are advised by competent solicitors, accountants, architects, engineers and valuers. In the absence of evidence, this Court must assume that the first owner of commercial premises is able to bargain for contractual remedies against the builder. It must also assume that a subsequent purchaser is able to bargain for contractual warranties from the vendor of such premises.
The floodgates argument
Disproportionate liability
In some cases concerned with pure economic loss, it may be necessary in determining whether a defendant should owe a duty of care to consider whether any potential liability of the defendant would be disproportionate to its fault. Claims against auditors by investors or creditors are examples of cases where disproportionate liability has played a role in rejecting plaintiffs' claims that the auditors owed them a duty of care149.
However, it is difficult to see how issues of disproportionate liability can be a factor in defective building cases concerned with pure economic loss. First, the loss in value or the cost of repairs to the defective work is likely to bear a proportionate relationship to the contract price for doing or advising in respect of the building work. Second, if the defective building causes physical injury or injury to other property, those involved in the construction will be liable even though the damages payable far exceed the contract price.
Lack of a measurable standard of care
"One man's meat is another man's poison. The scribbling block bought for a few cents at the supermarket might serve very well for the correspondence of the artisan, but it would not have done for the Duke. Price is an important consideration: generally speaking, as the saying goes, you get what you pay for."
Circumventing the policy of limitation legislation
Law is too complex for it to be a seamless web. But, so far as possible, courts should try to make its principles and policies coherent152. Accordingly, it is always relevant in determining whether to create, extend or formulate a duty in tort to consider whether it is consistent with other legal doctrines, principles and policies.
The now accepted doctrine is that, in the case of defective premises, damage does not occur until the defect manifests itself. No cause of action arises in tort until the plaintiff suffers damage. Consequently, those concerned with the design and construction of a building may be required to defend themselves against an action in tort many years after completing the task that now gives rise to the claims against them. On the other hand, a cause of action in contract arises when the contract is breached153. Time runs from the breach, not the sustaining of damage. This creates the paradox that those involved in the design or construction of a building may be sued in tort years after the time has expired for suing on the contract that gave rise to the duty. Of course, since Donoghue v Stevenson154, a similar anomaly arises in the case of goods and chattels. But in that area, the time lag between breach of contract and sustaining damage will ordinarily not be as long as in the case of defective buildings. Goods and chattels are usually consumed or used before the expiration of the contractual limitation period.
Moreover, imposing duties in respect of pure economic loss in building cases creates other problems. As I pointed out in Brisbane South Regional Health Authority v Taylor155, the policy of the law for nearly 400 years has been to fix definite time limits (usually six but often three years) for prosecuting civil claims. These time limitations have been driven by the general perception that "[w]here there is delay the whole quality of justice deteriorates"156. In Taylor157, I went on to say:
"The effect of delay on the quality of justice is no doubt one of the most important influences motivating a legislature to enact limitation periods for commencing actions. But it is not the only one. Courts and commentators have perceived four broad rationales for the enactment of limitation periods. First, as time goes by, relevant evidence is likely to be lost158. Second, it is oppressive, even 'cruel', to a defendant to allow an action to be brought long after the circumstances which gave rise to it have passed159. Third, people should be able to arrange their affairs and utilise their resources on the basis that claims can no longer be made against them160. Insurers, public institutions and businesses, particularly limited liability companies, have a significant interest in knowing that they have no liabilities beyond a definite period161. As the New South Wales Law Reform Commission has pointed out162:
'The potential defendant is thus able to make the most productive use of his or her resources163 and the disruptive effect of unsettled claims on commercial intercourse is thereby avoided164. To that extent the public interest is also served.'
Even where the cause of action relates to personal injuries165, it will be often just as unfair to make the shareholders, ratepayers or taxpayers of today ultimately liable for a wrong of the distant past, as it is to refuse a plaintiff the right to reinstate a spent action arising from that wrong. The final rationale for limitation periods is that the public interest requires that disputes be settled as quickly as possible166.
In enacting limitation periods, legislatures have regard to all these rationales. A limitation period should not be seen therefore as an arbitrary cut off point unrelated to the demands of justice or the general welfare of society. It represents the legislature's judgment that the welfare of society is best served by causes of action being litigated within the limitation period, notwithstanding that the enactment of that period may often result in a good cause of action being defeated."
The respondents owed no duty to Woolcock to protect it from pure economic loss
Whether and in what circumstances the law of torts ought to impose on the builder or other persons involved in designing or constructing commercial premises a duty of care to purchasers to prevent economic loss from defects in the premises are difficult questions. The varying reasons and conclusions of ultimate appellate courts throughout the common law world show that this is unequivocally so. Undoubtedly, the availability of a remedy in tort in respect of such losses strengthens claims by first owners and purchasers for compensation for losses arising from lack of care by those responsible for building defects. Hence, the availability of a remedy in tort would advance the cause of corrective justice, one of the rationales of the law of negligence. Moreover, for the reasons that I have given, the existence of a contractual remedy may not always be a sufficient protection for the first owners and purchasers of commercial premises who suffer economic loss as a result of defective premises. Consequently, the availability of a remedy in tort gives greater protection to the owners and purchasers of commercial premises.
But other factors point against a remedy in tort. Many defects will not manifest themselves for many years after the erection of the building. Given the now accepted doctrine that damage does not occur until the defect manifests itself, those involved in the construction of the building may be required to defend themselves many years after the event. Claims that might have been defended if brought within the normal periods imposed by the statute of limitations may become indefensible in practice. Records may have been destroyed or disappeared; key workers may be untraceable; memories may have long faded. Hence, the capacity of the courts to do justice may be impaired, if not defeated, by the passage of the years. And the capacity of the courts to do justice is impaired rather than improved by the problems to which I have referred in determining an appropriate standard of care.
A further consequence of the doctrine that damage does not occur until the defect manifests itself is that those involved in the construction of a building and their insurers may have to wait many years before they can be sure that they are free of potential claims. As one of the rationales of statutes of limitation indicates, this is an undesirable and unsatisfactory result for any commercial enterprise. To overcome the problems caused by the potential delay in bringing actions, builders in particular may be forced or at all events induced to adopt inefficient commercial practices such as using a series of shell companies to make one-off building contracts for each construction project.
The likelihood that imposing a duty in respect of building premises will have unsatisfactory consequences for the administration of justice and the efficiency of commerce is a powerful reason for not recognising the duty which Woolcock propounds.
But the most powerful reason for rejecting the proposed duty is that the first owners and purchasers of commercial buildings are ordinarily in a position to protect themselves from most losses that are likely to occur from defects in the construction of such buildings. Occasionally, a commercial building may be built or bought for an emotional rather than an economic reason. But in the overwhelming number of cases, commercial buildings are constructed or bought to make money. A commercial building is constructed or bought because it is perceived to be a suitable vehicle for investment. The prudent first owner or purchaser of such a building will compare the likely return on the capital investment with the potential risks including falls in the value of the building that may result from various factors, economic, social and physical. And no prudent purchaser would contemplate buying a building without determining whether it has existing or potential construction defects. Knowledge of its defects, actual or potential, is central to any evaluation of its worth as an investment. In so far as risks are uncertain or unknown, the prudent purchaser will factor the risk into the price or obtain contractual protections or, if necessary, walk away from the negotiations.
"If the plaintiff has taken, or could have taken steps to protect itself from the defendant's conduct and was not induced by the defendant's conduct from taking such steps, there is no reason why the law should step in and impose a duty on the defendant to protect the plaintiff from the risk of pure economic loss."
The respondents did not owe the duty pleaded
Various steps are open to the purchasers of commercial buildings such as Woolcock to protect themselves against pure economic loss that is consequent on the discovery of defects in the construction of those buildings. It is true that Woolcock made no investigation or inquiries concerning defects or potential defects in the building that it bought and obtained no warranties in respect of them. But its failure to take reasonable steps that were open to it is not a ground for holding that the respondents owed it a duty to take care in respect of pure economic losses arising from the defects in the foundations of the building. No doubt if Woolcock had insisted on contractual protection from its vendor, it may have had to pay a higher price for the building. But that only shows that, in this area, contract rather than tort is a better, more just and probably more efficient way of dealing with the problem of pure economic losses arising from defective construction. The price of a commercial building almost invariably reflects the inherent and other risks – including the risk of latent defects – of buying the building.
In my opinion, the law of negligence is best served by leaving it to the market and the law of contract to determine who should bear the economic loss that arises as the result of a fall in the value of a commercial building consequent upon the discovery of latent defects in the building.
Nothing in this judgment is intended to suggest that Bryan v Maloney168 would now be decided differently. Whether a different decision would now be reached under current doctrine almost certainly depends on whether evidence would reveal that the purchasers of dwelling houses are as vulnerable as the Court assumed in that case.
Order
The appeal should be dismissed with costs.
KIRBY J. In Zumpano v Montagnese169, Brooking JA noted the opinion of a commentator170 on this Court's decision in Bryan v Maloney171. The comment suggested that in Bryan the Court had "opened Pandora's Box, visiting on builders all the evils of the world".
Brooking JA remarked that such observations implied that "there is no more agreement about the limits of the decision than there is about what the lidded vase carried by Pandora really contained"172. According to one version of the mythological story, Pandora's box contained all the blessings of the gods which, on its opening, escaped and were lost. The only exception was hope, which was at the bottom173. Now, full of hope, the appellant comes to this Court seeking an extension of the principle in Bryan, to cover its case.
In Zumpano174, Brooking JA went on to observe that:
"On the widest view of its ultimate effect, Bryan v Maloney will impose upon builders who erect or alter any kind of building at least a 'prima facie' duty of care to all those who come to own or even only to use or occupy it and that duty will extend to all defects, whatever their nature and extent, and whether or not they result from the work of a subcontractor, provided only that they are 'latent'."
On the other hand, his Honour accepted175 that Bryan "might be viewed as a determination based upon the particular facts rather than one applicable to a broad category of cases". He predicted that the problem presented in that case would return to this Court in order to resolve these doubts and difficulties176. So, by special leave in this appeal, it has.
The facts and course of the proceedings
The facts and decisional history: The relevant facts are set out in the reasons of the other members of this Court177. The reasons of Gleeson CJ, Gummow, Hayne and Heydon JJ ("the joint reasons") explain the somewhat unsatisfactory way in which an issue of legal importance is now presented in a stated case, supplemented by the parties' pleadings and inferences said to be available from this confined material178.
The other reasons179 also trace the decisional history of this case in the Supreme Court of Queensland, principally in the Court of Appeal180. Those reasons provide an explanation of what was decided by this Court in Bryan181 and some of the criticisms that have been directed at its holding both in judicial opinions and in academic literature182. This material and the outline of the main arguments of the parties allow me to go directly to my analysis. I will not needlessly repeat the facts.
An unsatisfactory procedure: If this case was planned as a vehicle to expand, or confine, the principle in Bryan, it is a somewhat unsuitable one. I can understand the reasons, tactics and hoped-for cost savings that launched the parties upon a contest, effectively over the pleadings. However, the one lesson that has emerged from recent Australian cases about the law of negligence is that the facts and the evidence, taken as a whole, are critical for the resolution of the issues presented by the tort. It is out of the detail of the facts that the "salient features" and pertinent factors will emerge that help the decision-maker to decide whether a duty of care exists, whether it has been breached and, if so, whether that breach caused the plaintiff's damage.
In this appeal, this Court must do its best with the unelaborated facts upon the basis of which we were asked to decide the matter. I cannot but think that this course of events has disadvantaged the party seeking recovery. When the boundaries of liability in negligence are pushed forward it is often because detailed evidence, adduced at trial, appears in its totality to call out for a remedy183 or to indicate that one is not appropriate.
The apparent reasonableness of the appellant's claim
The nature of the claim: The appellant's claim is for economic loss said to be recoverable by a subsequent purchaser of a commercial building for the design of that building by the respondents or their supervision of its construction.
The first respondent is a company of consulting engineers. The second respondent, a qualified civil engineer, was employed by the first respondent. The construction of the building took place between 1987 and 1988. It is at that time that the relevant acts and omissions of negligence were alleged to have occurred. The building contains warehouses and offices, with no residences. It is situated in the city of Townsville. That city abuts the Pacific coast of Queensland. It is a commonplace that buildings erected in the vicinity of water – including an oceanic coastline – are often liable to subsidence. It is elementary that such buildings often need special care in the design and placement of foundations. So it was to prove with the subject building.
The appellant did not acquire the title to the building until September 1992. The substantial structural "distress" did not manifest itself until 1994. A defence based on s 10(1) of the Limitation of Actions Act 1974 (Q) was pleaded by the respondents. However, that plea was raised in the alternative to the more fundamental denial by the respondents that any cause of action against them was available in the circumstances pleaded.
Putting aside any limitation period, and assuming that otherwise the appellant brought its proceedings in time after first becoming aware of the damage suffered by subsidence of the footings of the building, the notion that the respondents, as civil engineers, are liable in law for the ensuing loss to the appellant is not, on the face of things, surprising. At least it is not so in a legal system that provides remedies against those who are negligent and thereby cause damage to others in respect of whom they ought to have exhibited professional care.
A commercial building, such as that in issue, is a large financial investment. Ordinarily, in contemporary Australia, one would expect that it would be built carefully with special attention by supervising engineers to the security and stability of its foundations. Such a building is obviously designed to have a certain life. That life may be described as "permanent" or "indefinite"; but at the least it would usually be envisaged that the building would last for more than 10 years without serious or fundamental defects: earthquakes, tidal waves and other unexpected events of nature aside.
In the present case there was alleged to have been a latent defect, not readily discoverable by the appellant on reasonable inspection. This was alleged to have been caused by the negligent performance by the respondents of their professional duties. The latent character of the defect was a consequence of the very nature of foundations or footings in such a building. The appellant has no contractual relationship with the respondents. Accordingly, its only relevant legal entitlement against them lay in the law of tort – specifically the tort of negligence. The days are past when professional people could claim that their only duty to others was according to their contracts. For duties to a larger range of persons, the other concurrent branch of the law of obligations, namely the law of tort, may be invoked. In this country, as in others, the law has increasingly moved away from accepting immunities from liability in negligence on the part of particular classes of professional people.
"It is difficult to see why, as a matter of principle, policy or common sense, a negligent builder should be liable for ordinary physical injury caused to any person or to other property by reason of the collapse of a building by reason of the inadequacy of the foundations but be not liable to the owner of the building for the cost of remedial work necessary to remedy that inadequacy and to avert such damage."
The appellant must now effect repairs. It seeks to recover the costs of doing so from the respondents whose acts and omissions it alleges were negligent in the circumstances.
To the original developer's instruction not to proceed with soil tests, accepted by the respondents, the appellant has an answer. It says that this might be relevant to any claim in contract between the respondents and the developer or the builder who decided to proceed without the tests, although the respondents' professional experience had caused them to recommend such tests. But, as between the present parties, the appellant says that it is irrelevant to its claim in negligence. The respondents did not owe a duty of care only to the building supervisor, builder and immediate owner and initial occupiers of the building. They owed a duty to those, like the appellant, who within a comparatively short time, and within the reasonable contemplation of the respondents, acquired the building without knowledge of the latent defect. That defect arose from the conduct of the respondents in continuing to act as professional engineers, as they did, in respect of the building although an obviously important test, which they had recommended, had been refused. The acquisition of the building by a later purchaser, such as the appellant, was readily foreseeable. So was the reliance of such a purchaser upon the discharge by the respondents of a duty to observe professional care and skill in the design of the building and supervision of its construction.
If the developer could control, and effectively veto, the conduct of proper structural tests, the appellant, in effect, asked: why bother to have a professional engineer at all? If the law excused the engineer from liability, it would encourage fly-by-night builders and nominee owners. It would relieve professional engineers of the very responsibility for which they were engaged. That responsibility was to ensure the safety of the building and to protect those who might be expected to purchase and use the building during a reasonable period after construction without having to search for, and correct, latent defects for themselves.
Conclusion: an arguable claim: Looked at in this light, the argument of the appellant in support of its claim for recovery against the respondents is not unpersuasive. If upheld, not only would it redress a wrong which arguably arose as a foreseeable consequence of the respondents' acquiescence in the erection of the building without the structural tests that the respondents had proposed. It would also instil proper standards of professional engineering conduct. It would sanction unsafe building practices. It would encourage better building design and supervision. It would protect life, property and investments from the kind of unsafe conduct that allegedly occurred in this case. If the tort of negligence is ultimately concerned with moral issues such as fault and blameworthiness and the protection of those vulnerable from harm done by others who, legally speaking, are their "neighbours"189 – including in business contexts – the provision of a legal remedy to the appellant in its proceedings against the respondents would not, without more, be inconsistent with the purposes of the tort.
The proper approach to a pleading issue
A particular consideration should be taken into account at the threshold. It is one that is enlivened by the way in which the issue comes before this Court. Because the appellant has not yet had a trial, at which all of its evidence might be adduced, and because the respondents assert an entitlement to an immediate termination of the action, the issue in the appeal should be approached in a settled and well established way.
If there is any reasonable prospect that the appellant might be able to make good a cause of action, it is not proper for a court, in effect, to terminate the appellant's action before trial191. Where the law is uncertain, and especially where it is in a state of development, it is inappropriate to put a plaintiff out of court if there is a real issue to be tried192. The proper approach in such cases is one of restraint. Only in a clear case will answers be given, and orders made, that have the effect of denying a party its ordinary civil right to a trial. This is especially so where, as in many actions for negligence, the factual details may help to throw light on the existence of a legal cause of action – specifically a duty of care owed by the defendant to the plaintiff. The parties consented to the course adopted. However, this Court owes its duty to the law. Its decision in this case affects persons other than the parties.
The two foundations of the appellant's action
Analogous reasoning: past authority: It was common ground that no decision of this Court concludes the issue of whether a party in the position of the respondents owed a duty of care to a party in the position of the appellant. It follows that to discover and declare the law applicable to the case, this Court is, and the courts below were, obliged to reach a decision by reference to relevant legal authority and applicable considerations of legal principle and legal policy193.
Neither party pretended in its submissions to this Court that authority alone resolved the appeal. In written and oral submissions, both parties, correctly, addressed the considerations of legal policy without which resolution of the appeal would be a barren and artificial exercise.
To sustain its action against the respondents as conforming to the Australian common law of negligence, the appellant drew particularly upon two lines of this Court's authority concerning the law of negligence and specifically the existence of a duty of care. These were (1) the decision in Bryan194, which concerned the liability of a negligent builder to a subsequent purchaser of a domestic dwelling; and (2) the decision in Perre v Apand Pty Ltd195, which concerned the liability of a neighbour for losses suffered by the growing of prohibited potato seeds on a nearby farm, resulting in economic loss.
The principles in Bryan and Perre: The appellant argued that the principle in Bryan, read in light of Perre, was not as narrow as Australian courts and commentators had sometimes stated. Alternatively, if it was originally so, the appellant argued that the principle should be reformulated in this appeal, in the light of Perre, so as to uphold the existence of a duty of care on the part of the professional engineers to a subsequent purchaser of the subject building, although that building was a non-residential, purely commercial one and although the appellant's loss at this stage was solely economic.
The appellant contested the proposition that an "extension" of the principle in Bryan was really necessary196 or that the holding in that case was limited, in terms, to the liability to subsequent purchasers of builders of domestic dwellings (and by inference other related persons including civil engineers).
The defects of Bryan v Maloney and their repair
Defects of the decision in Bryan: Certain features of the decision in Bryan are obviously unsatisfactory. The attempted expression of the holding in terms of a building of a particular kind is but the first of these. In Zumpano202, Brooking JA collected a long series of problems and uncertainties which such a factual discrimen created for those deciding later cases involving allegedly defective building works of various kinds. As some of his Honour's reasoning is described elsewhere, I will not repeat it203. It is enough to say, if I can be pardoned the expression, that the suggested point of distinction in Bryan presents a very shaky and unstable foundation for a viable legal principle that will answer the many later cases that arise where judges are entitled to expect clear and principled guidance. Unfortunately, in this respect, those judges look in vain to Bryan to show the way.
That is not all. The decision in Bryan can also now be seen as resting on a defective doctrinal basis. The majority reasons are clearly anchored in the consideration of "proximity" as the propounded point of distinction between cases where a duty of care was held to exist and cases where it was missing204. In this, I agree with what is written by the other members of this Court205.
Proximity is not irrelevant as a factor in determining the existence of a duty relationship206. This is especially so if it is used as a synonym for the relationship of legal "neighbours". Indeed, this was the essential defect of the use of proximity as the conceptual determinant of the existence of a duty of care. It was question begging. It did little more than offer a legal fiction designed to state, in shorthand, Lord Atkin's neighbour relationship207. Proximity is not now accepted as a sole criterion for explaining when a duty of care exists at law208, any more than other attempted short verbal formulae can do that job: whether "reasonable foreseeability", "reliance", "assumption of responsibility" or existence of a "special relationship".
(1) That the Court should accept that Bryan constituted a wrong turning in the law of negligence, and should be overruled, and that the principle should be reinstated that there is no duty of care in negligence on the part of a builder or like professional for economic loss to any subsequent purchaser of a building, whether residential, commercial or otherwise209;
(2) That the Court should allow Bryan to remain as authority but effectively confined to its own facts210 or specifically treated as an anomalous exception to the general rule of no liability to subsequent purchasers, absent an express contractual stipulation. This was the primary way in which the respondents eventually argued the appeal. Various contentions of policy were advanced to support this view of authority, including the special vulnerability of residential home owners to latent defects that reasonable care would have prevented or repaired and that allegedly have no equivalent relevance to the investment decisions of purchasers of commercial buildings; and
(3) That the Court should accept the principle stated in Bryan so far as it goes but re-express it in a broader way, more consonant with subsequent decisions of the Court in cases of economic loss, and specifically Perre. Upon this basis, the appellant argued that the "salient features" of the case warranted acceptance of the proposition that the respondents owed a duty of care to the appellant for breach of which they would be held liable in negligence.
Conclusion: need for new principle: Bryan has had its critics211. However, it has also had its defenders212. The latter have viewed Bryan as conformable with other developments of the law of negligence, as elaborated by this Court, including the protection of the vulnerable213. Indeed, the decision in Bryan is one of those described by Professor Stapleton as "fit[ting] well within the Atkinian mould of successful tort law-making [which is] the envy of tort commentators abroad". She has suggested that reversals of such decisions can be left to legislators on the basis of reports of inquiries rather than "judicial activism" instituting what she terms the "dramatic pro-defendant era in tort decisions" in this country in recent times214.
Bryan has stood for nearly a decade. It does not need to be reconsidered and overruled to reach a decision in the present appeal. Its reasoning is available for criticism and confinement or extension as new cases require. I would reject, as unnecessary, the application to overrule it. But, clearly, it does not, in itself, provide a solution to the present case215.
The most that can be said is that Bryan leaves the law in an unsatisfactory state if a later home owner can recover for a latent and undiscoverable defect but a subsequent buyer of a commercial building cannot. This intuitive conclusion stimulates attention to later decisions of this Court to discover whether they provide a more satisfactory conceptual basis for resolving the issues in the appeal. This takes me to the decisions on the recovery of damages for economic loss and particularly to the Court's pronouncements on that subject in Perre and in Cattanach v Melchior216. But first a question is posed, as it was in Cattanach, as to how the appellant's case is to be classified.
Is the present case one of "pure economic loss"?
A contestable concession: In its written submissions, the appellant conceded that its claim was for pure economic loss. That may have been an unnecessary and incorrect concession. There is no doubt that the complaint which the appellant makes involves the demonstration of actual physical damage to its property. This is inherent in the allegation of subsidence and structural "distress" to its building caused by the allegedly inadequate and faulty foundations that the respondents approved and instituted. By inference, there is a risk that, without action on the part of the appellant to repair the specified defects, there will ultimately be physical injury to persons in or near the building, including employees of the owners or tenants and members of the public. Certainly, it can be inferred that physical damage to the foundations of the building itself could be proved.
The "pragmatic"217 basis for the common law's restriction on the recognition of duties of care to prevent pure economic loss to others was a concern that such loss was liable to be open-ended, indeterminate, very substantial and therefore prone to impose an undue burden on economic activity, to the great disadvantage of society218.
Physical damage and indeterminacy: Where physical injury to a person or to property could be shown, much of the sting of indeterminacy is taken out of the common law's reluctance to permit recovery of economic loss. The case would not then be one of "pure" economic loss. This is one explanation of why the plaintiffs recovered economic loss in Perre. It is also an explanation of why the majority in Cattanach219 (decided after the present appeal was argued) rejected a view, expressed by the minority in that case220, that the claim there was unrecoverable as pure economic loss. The happening of the unplanned pregnancy in Cattanach dispelled the contention of indeterminacy. It made concrete the financial loss suffered by the parents who unexpectedly discovered that, despite the sterilisation operation and medical advice, the wife was again pregnant.
In a similar way in this case, the allegation of actual damage to the appellant's building arguably makes its claim one that escapes the common law's resistance to recovery of pure economic loss. Despite its written submissions, the oral arguments of the appellant did not, in the end, as I understood them, disclaim such a contention. I do not accept that earlier decisions bind this Court to a different conclusion. At the least, it should be open to the appellant to argue its case in such a way. It should not be denied the opportunity to do so at trial. and give it support. By the authority of this Court, the respondents would have been liable for damage to persons or property caused by a total collapse of the building. To say the least, the distinction between the damages recoverable in such a case and the damages claimed by the appellant in the present case is not very persuasive.
The developing law on avoidance of economic harm
Developing law on economic loss: A review of recent decisions shows that the law in this country concerning the duty to avoid causing economic loss to others is in a state of development. The original endeavour to confine the tort of negligence to cases which result in "danger to life, danger to limb, or danger to health"224 has given way in recent years to an increasing number of "exceptions" by which the existence of a duty of care and the acceptance of recovery have gradually been treated as separate from the different question of "the nature of the damage"225. The original rule wholly excluding recovery of pure economic loss has increasingly been recognised as capricious and unjust. Only this recognition explains such decisions as Hedley Byrne & Co Ltd v Heller & Partners Ltd226 and Caltex Oil (Australia) Pty Ltd v The Dredge "Willemstad"227.
Nevertheless, as I pointed out in Perre228, crafting a different and convincing substitute rule that is viable and easy to apply has not proved easy. In Perre229 I favoured, as I did in many other cases before and after, the application of the three-fold test expressed by the House of Lords in Caparo Industries Plc v Dickman230 for deciding whether a duty of care existed in a particular factual situation, which the law of negligence would enforce. This approach requires consideration of reasonable foreseeability and proximity (in the sense of "neighbourhood") without attributing to either of these factors the primacy accorded to them in the past and without turning either into a sufficient criterion for acceptance of a duty of care. Caparo also obliges a transparent consideration of the issues of legal policy that tend to favour, or reject, the imposition of a legal duty of care sounding in damages for a negligent breach. Since Perre231, I have been obliged by the holdings of this Court to abandon the approach for the time being. This is so although, in various guises, that approach continues to be applied in the final appellate courts of most Commonwealth countries.
"I cannot help observing that the repeated disavowal in the cases of recourse to public policy is not always convincing … [I]t would be more helpful for the resolution of the controversy if judges frankly acknowledged their debt to their own social values, and the way in which these have in fact moulded or influenced their judgments rather than the application of strict legal principle."
Respectfully, I support these earlier remarks. I regard them as sustaining the transparent approach that Caparo favours for the resolution of the duty of care question. Wherever possible, I favour transparency in the legal process239. If regard is paid to the reasons of the other members of this Court in the present case, most especially those of McHugh J240, they come very close to the transparent weighing of policy considerations that Caparo required.
Nevertheless, until this Court reconsiders its stand, I accept the obligation imposed on me by the authority of Sullivan to approach the issue in the appeal more obliquely, as the other members of this Court favoured in Perre.
The approach in Perre: Two central considerations were identified in Perre as standing against the existence of a legal duty of care in negligence in cases involving economic loss. The first was that such a duty should not be accepted where it would impose liability for an indeterminate amount for an indeterminate time to an indeterminate class. Secondly, it was held that such a duty would not exist where, to impose it, would infringe the rights of others to protect, or pursue, their own legitimate social or business interests241.
This Court in Perre adopted an "incremental approach" in coming to its conclusion that a duty of care was established for the avoidance of the economic loss claimed in that case242. It emphasised the importance of considering all of the facts concerning the relationship between the defendant and the several parties claiming a duty of care243. What does such an approach produce in the present appeal?
The principled application of the tests in Perre v Apand Pty Ltd
Salient features: Various features typical of evidence in cases such as the present were highlighted by different members of the Court in Perre. Thus Gummow J244, in words reminiscent of those used by Stephen J in Caltex Oil245, described certain recurring features and arguments as "the salient features of the matter [which] gave rise to a duty of care". In his reasons, McHugh J identified five factors applicable to cases of economic loss. According to McHugh J, these were the reasonable foreseeability of the loss; the avoidance of indeterminate liability; the protection of the autonomy of individuals; the vulnerability to risk; and the extent, if at all, to which the defendant knew of the risk and of its magnitude246. I do not take the other judges in Perre to have adopted an approach significantly different from these. In this case, McHugh J has knocked the "floodgates" argument on the head247.
Reasonable foreseeability: If the considerations mentioned by McHugh J in Perre are applied to the present case248, there can be no doubt that, at least arguably, the loss allegedly suffered by the appellant was reasonably foreseeable by the respondents. After all, the respondents had suggested expert ground tests, presumably for a purpose. That purpose was arguably to avoid the erection of a building with the problem of subsidence that is now alleged to have transpired. They agreed to, or acquiesced in, the decision of someone else (against which they may have their own legal remedies) not to proceed with the tests. If there is subsidence and instability in the building, it was not only reasonably foreseeable to the respondents. The risk was actually foreseen.
Indeterminate liability: The liability of the respondents propounded in the case is not indeterminate. Nor are the members of the class affected unascertainable. They are members of the class of future owners and users of the building during the period that the building might reasonably be expected to survive who could be damaged by the respondents' failure to insist on the conduct of ground tests against the risk of subsidence evident within a reasonable time. Exposure to liability was not, on the appellant's proposition, open-ended in terms of time. The appellant disclaimed the assertion of a duty of unlimited or indefinite duration. It submitted that all such claims would, as a maximum, be subject to the applicable limitations statute. That statute would, on the face of things, ordinarily be enlivened by the appearance of a defect in the building "so obvious, that any reasonable homeowner would call in an expert".
Other considerations confirm the duty of care
Consumer legislation is irrelevant: In so far as it is relevant to consider issues of legal principle or policy raised in other reasons (as Caparo would certainly require), I will do so briefly for they confirm the conclusion that I have reached by applying the approach taken by this Court in Perre.
It is true that in some, but not all, Australian jurisdictions special legislation has been enacted to provide forms of protection for first purchasers of domestic dwellings but not for other, or later or different, purchasers254. It is natural that, as part of consumer protection, legislatures should enact popular laws of such a kind. However, such laws do not exclude the residual operation of the common law in other instances. Least of all do they do so in a case, such as the present, which is different from Bryan and upon which this Court has not previously pronounced. There is nothing in the legislation mentioned by the respondents that contradicts the application of established common law principles to the facts propounded by the appellant. It is entitled to have its claim decided in the same way as Perre was decided, on its legal merits by the application of the same general principle.
Caveat emptor is irrelevant: The "defence" of caveat emptor is, with respect, irrelevant255. It is, or may be, a defence to any claim that the appellant sought to assert against the vendor from which it purchased the building. However, it is no answer to the appellant's claim in tort against the respondents. The fact that the appellant might have sought a warranty from the vendor is also irrelevant. Why should the appellant reasonably have anticipated a need to obtain such a warranty in a building so recently erected under professional engineering supervision? Would a vendor, and especially a vendor which was itself a later purchaser, have conceivably been willing to give it? What is the usual commercial practice in the purchase of such commercial buildings? Especially where a party is being effectively deprived of its ordinary entitlement to trial of its claims, this Court errs in assuming that the provision of warranties to later purchasers of commercial buildings is either commonly sought or given. Yet substantially on the basis of that possibility, the appellant is put out of court256. The appellant's complaint in law is against the professional civil engineers. It is not against the previous owner or owners.
Local authority tests are irrelevant: The fact that the appellant's solicitors conducted routine enquiries of the local government authority is also irrelevant. Those tests did not, by the terms of the applicable statutes, extend to – nor could they have been expected to include – tests for a latent defect in the foundations of the building. As I have said, the very complaint that the appellant makes against the respondents is that their conduct had the effect of concealing the resulting defect for a time, until objective signs elsewhere in the building began to disclose the subsidence, necessitating repairs.
Overseas authority favours a duty of care
The trend in overseas courts: To the extent that it is relevant in matters such as this to endeavour to uphold similar principles of negligence in Australian law to those observed in other common law countries, the decisions called to notice by the parties evidence the same divisions of judicial opinion as exist in this Court in this appeal.
In England, the House of Lords in Murphy v Brentwood District Council262 adopted an approach supporting some of the propositions of the respondents, essentially for pragmatic reasons. However, as with all arbitrary rulings, the decision, reversing the earlier authority in Anns v Merton London Borough Council263, has not been universally applauded. Recent decisions of the English courts have upheld the assertion of a duty of care to a subsequent purchaser of a building by a design architect, where the claim involved (as here) damage to the building itself rather than only damage to other property264.
The decision in Murphy has not been followed in Canada where the courts have generally adhered to the approach adopted by the House of Lords in Anns265. That case was the progenitor of the Caparo approach. In Winnipeg Condominium Corporation No 36 v Bird Construction Co266, the Supreme Court of Canada unanimously held that this approach resulted in a conclusion that a building professional owed a duty of care to a subsequent purchaser of the building for economic loss caused by the need to repair the building which contained defects posing a "substantial danger to the health and safety of the occupants".
In New Zealand, before the abolition of appeals to the Privy Council, the courts upheld the duty of care by builders to subsequent purchasers. The principle was recognised in Bowen v Paramount Builders (Hamilton) Ltd267. That was a case of a domestic dwelling. It was decided before this Court's decision in Bryan. After the decision of the House of Lords in Murphy, the New Zealand courts continued to apply the approach in Anns, modified in ways similar to the Canadian approach. This was a course of judicial independence in which the Privy Council acquiesced, as appropriate to the different direction that had been taken by the New Zealand common law.
Conclusion and orders
The appellant has established error on the part of the Court of Appeal whose orders have the effect of denying it a trial of its action against the respondents. As a matter of law, such a trial would not be futile.
The appeal should be allowed with costs. The orders of the Supreme Court of Queensland (Court of Appeal) should be set aside. In place thereof, the question set out in the case stated should be answered "yes". The proceedings should be returned for trial. The respondents should pay the appellant's costs in the Supreme Court of proceedings to date.
CALLINAN J. This is a case stated. The principal question that it raises is whether a professional engineer who negligently designed the structure of a building for use as offices and a warehouse is liable for economic loss to a subsequent purchaser of the building.
Facts
The building has no residential component. Its construction was undertaken by two joint venturers. The second respondent was an engineer employed by the first respondent. The first respondent undertook for payment the design and supervision of the complex. No geotechnical inspection of the site was undertaken before the construction began. This was so because one of the joint venturers was unwilling to meet the cost of it although by implication, at the very least, the respondents must have thought it desirable.
The case stated records that,
"[t]he routine civil structural supervision by [the first respondent] included routine civil/structural supervision of the construction of the foundations of the Complex."
Construction started in the middle of 1987 and was completed by about the end of that year.
In September 1992, the appellant, Woolcock Street Investments Pty Ltd, bought the property on which the building stood, from Permanent Trustee Company Limited, a company which had replaced one of the joint venturers, under a contract which contained no warranty that the building was free of defects, and effected no assignment of such rights (if any) as the vendor might have had against third parties, including the respondents, in respect of any structural defects. Before buying, the appellant's solicitors requested the Townsville City Council to make a physical inspection of the building. The Council did so on 18 June 1992 and gave a report to the appellant on 7 July 1992. The Council qualified its report as follows.
"Reference is made to your request dated 12 June 1992 for an inspection of this property. I have treated this request as relating to matters arising under the 'Building Act 1975' and the 'Standard Building Bylaws' and to such matters only. Should you wish the inspection to encompass other matters, it will be necessary for you to specify these matters and to pay the appropriate further inspection fees.
However, matters of, for example, encroachments, or termite infestation are not covered by this inspection. You should consult a licensed surveyor in the case of encroachments, or an appropriately qualified person in the case of termite infestation.
The property has been inspected under the following headings:
Unauthorised structures, alterations or additions. (Section 52)
Unsafe or dilapidated buildings or structures. (Section 53)
Other matters arising under the Act or Bylaws."
The report referred to a number of unauthorized additions and changes to the complex. It did not identify any unsafe or dilapidated structures, or indeed hint at any matters of structural concern. An inspection and report by a plumber in relation to the roof similarly pointed to no serious defects in the building.
By 1994, however, structural distress by way of settlement began to manifest itself.
The appellant sued the respondents in the Supreme Court of Queensland in negligence. The primary judge, Atkinson J ordered that a case be stated. It was in the form that I have summarized, and came on for hearing before the Court of Appeal of Queensland (McMurdo P, Thomas JA and Douglas J) in early 2002. The case was treated, and correctly so, as a case of pure economic loss. There it was argued by the respondents that the principle stated in Bryan v Maloney276 was confined in application to single dwellings. The argument was generally accepted by Thomas JA (who gave the leading judgment) on the basis that Bryan v Maloney rests heavily on notions of vulnerability, of a special vulnerability of members of the public who buy single dwelling houses. This was so, even though, as his Honour said, houses may on occasions be bought by commercial investors. His Honour was influenced by two other factors: that the remedy, if there were any, was available either under current legislation, or, if it were not, should only become available in accordance with specific legislative provision for it because of the underlying economic and social factors relating to an action of this kind and home ownership generally. The other matter which affected the reasoning of Thomas JA was that to enable the appellant to sue here would have the effect of granting to all purchasers in a line of purchases, a transmissible warranty of quality of indefinite duration. Douglas J agreed with Thomas JA as did in substance McMurdo P. It was accordingly held that the stated case should be answered adversely to the appellant, that is, no.
The appeal to this Court
The appellant's arguments
The appellant first submitted that a subsequent purchaser of premises is not absolutely precluded from recovering damages in the nature of pure economic loss from a building professional who was negligent in the design or supervision of a building premises, merely because the design is adapted to a commercial application rather than a residential one: that the building may or may not be a permanent dwelling house, although undoubtedly a relevant matter, is not a conclusive one. In the case of a commercial building – to adapt the words of Mason CJ, Deane and Gaudron JJ in Bryan v Maloney277 – it is plainly foreseeable by any engineer that the construction of a negligently designed building will be likely to cause economic loss to its owner at the time when the inadequacy of the design becomes manifest. There is current authority that would make the engineer liable for physical damage to any person or other property caused by the collapse of the building278, whether it was a commercial building or not279. Any distinction between damages caused in those circumstances and those claimed in the present case is artificial and is not, it was submitted, justified280.
The appellant's submissions continued, that to treat the potential for liability as limited to a "permanent dwelling house", and not applicable to other buildings gives rise to significant definitional issues. Many Australians do not reside in a simple, single dwelling house on one allotment. To highlight the anomalous state of the law on the basis of the holding of the Court of Appeal the appellant called in aid some observations of Brooking JA in Zumpano v Montagnese281:
"(a) …
(ii) Does Bryan v Maloney apply not only to dwelling houses in the narrow sense but also to other dwellings, for example, residential apartments in a multi-storey development, like the building in Opat v National Mutual Life Association of Australasia Ltd282? Does it apply to 'mixed' buildings, like a shop and dwelling or a building comprising a dwelling and commercial art gallery or a general practitioner's residence combined with surgery? In the case of a 'mixed' building, if the decision is applicable, then does it apply to the whole building, or only to the residential part of it, or does the answer to this question depend on some such notion as that of 'dominant use'?
(iii) Does the decision apply to dwellings which are not the principal residence of the purchaser, for example, an apartment in or near the city for occasional use, or a holiday home?
(iv) What if the value of the dwelling is only a small part of the total value of the house and land, as where a modest dwelling is bought which stands on a very large piece of land or on land which is, by reason of its location, exceptionally valuable? What of a house forming part of a large rural property stocked with cattle or used for viticulture? What of a rural property with two houses, one intended for occupation by a manager? Do the houses in the last two examples answer the description of Toohey J283, 'a house that is a non-commercial building'?
(b) If the decision is not confined to houses, or to houses and other dwellings, then to what other buildings does it apply? The joint judgment284 left open the position of buildings other than permanent dwelling houses, while Toohey J, as just mentioned, limited his decision to 'a house that is a non-commercial building'. In Western Australia, Malcolm CJ has accepted the existence of a duty of care to a subsequent occupier on the part of the builder of a commercial greenhouse285."
The questions raised by Brooking JA do not, as will appear, exhaust the catalogue of questions and anomalies to which the decision in Bryan v Maloney gives rise.
The appellant also seeks to rely on some statements in the judgments of this Court in Perre v Apand Pty Ltd286, in particular in the reasons of McHugh J. It urged that some language of his Honour there could readily be adapted to this case. Six propositions were advanced as relevant.
Conditions of the kind referred to in that case were present here. The losses suffered by the appellant were a reasonably foreseeable consequence of the respondents' failure to design appropriate foundations and supervise the construction of them. The appellant is a member of a class of subsequent owners of premises from time to time whose membership was readily ascertainable by the respondents. The appellant's business was vulnerably exposed to the respondents' conduct because the appellant was not in a position to protect itself against the effects of the respondents' negligence. The imposition of a relevant duty on the respondents does not expose them to "indeterminate" liability. Nor does it unreasonably interfere with their commercial freedom because they were already under a duty of care to the original owner to take reasonable care. And the respondents knew or ought to have known of the risk to the owner of the building from time to time, and the consequences of the realization of that risk.
The imposition of such a duty is unobjectionable in principle, or on grounds of policy. The approach of the Court of Appeal was based, at least in part, upon the assertion that the vulnerability of purchasers of commercial premises may be thought to be significantly less than that of purchasers of dwelling houses. That assumption is not justified. Commercial purchasers, in appropriate circumstances, may be just as vulnerable as residential purchasers. Why is a sole trader, the appellant asks, who purchases a building from which to operate a business, more vulnerable in purchasing a dwelling house than in purchasing commercial premises? The distinction between a purchaser of residential premises and of commercial premises is in reality no more than arbitrary.
A finding that a duty of care is owed is efficient and encourages responsible commercial and professional behaviour. As to the respondents' suggestion that the appropriate way for a buyer to protect itself is to obtain a contractual warranty, the appellant's answer is that a vendor who is liable would almost certainly join the negligent professional responsible for the defect: in consequence, the loss would ultimately be borne by the same party, but only after additional legal costs (incurred by the seller) are expended.
Reasoning
I am unable to accept the appellant's submissions for several reasons. The joint judgment of Mason CJ, Deane and Gaudron JJ in Bryan v Maloney repeatedly emphasized that it was because the Court was concerned with a dwelling house and purchaser of it287 that their Honours were drawn to the conclusion that they reached. Their Honours also made assumptions including that a purchaser, in buying a dwelling house in this country is probably making the most significant investment that he or she will make in a lifetime288. Others were that "a subsequent owner is likely to be unskilled in building matters and inexperienced in the niceties of real property investment."289
With respect, I think that what was said by Brennan J in Bryan v Maloney is more persuasive290:
"It would be anomalous to have claims relating to the condition of the building by an original owner against the builder determined by the law of contract if the relief claimed by the remote purchaser against the builder would be determined by the law of tort. Such a situation would expose the builder to a liability for pure economic loss different from that which he undertook in constructing the building and would confer a corresponding right on the remote purchaser which the purchaser had not sought to acquire from the vendor291. It would be tantamount to the imposition on the builder of a transmissible warranty of quality. In some jurisdictions, Parliament has provided such a remedy by statute. The social question whether building costs should be inflated to cover the builder's obligation under such a transmissible warranty is an appropriate question for parliaments to consider but, in the absence of compelling legal principle or considerations of justice reflecting the enduring values of the community, the courts should not decide to extend remedies not hitherto available to remote purchasers of buildings without considering the cost to builders and the economic effect of such an extension. Those are questions which the courts are not suited to consider. The extension of remedies in that direction is properly a matter for Parliament."
I regard myself as free to adopt that passage in this, a case of a commercial structure, to which it has in my opinion, a particular relevance, even though his Honour's judgment was a dissenting judgment. This case is distinguishable from Bryan v Maloney, and, if the appellant's claim here were to be allowed, would represent a marked and unwarranted extension of it.
There is in my respectful opinion, in any event, reason to question the correctness of Bryan v Maloney itself. It was decided at a time when the jurisprudence of this Court in cases of tort was more heavily influenced by notions of proximity292 than it currently is. But it is not for that reason only that I would question its correctness.
Neither the appellant here, nor indeed a purchaser of any premises, whether a dwelling or otherwise, is especially vulnerable, and unable to protect itself as the appellant contends. Here the appellant chose to seek an inspection and report by the local authority under s 53 of the Building Act 1975 (Q) which provided as follows:
"Building etc dangerous, neglected or unfit for use or occupation
53 (1) If in the opinion of a local authority formed on reasonable grounds any building or other structure or any part of a building or other structure is dangerous, the local authority may, subject to section 54, by notice in writing, require the owner of the building or structure to do any 1 or more of the following:-
(a) shore‑up or otherwise secure such building or structure or part;
(b) erect a proper hoarding or fence for the protection of persons using any road, path or way upon which the building or structure or part abuts;
(c) demolish or take down the building or structure or part;
(d) repair the building or structure or part;
(e) remove the building or structure or part;
as the local authority directs within the time specified in the notice.
(2) If in the opinion of a local authority formed on reasonable grounds any building or other structure or any part of a building or other structure is a ruin or so far dilapidated as to be unfit for use or occupation or is, from neglect or other cause, in a structural condition prejudicial to the inhabitants of or to property in the neighbourhood, the local authority may, subject to section 54, by notice in writing, require the owner of the building or structure to do any 1 or more of the following:-
(a) demolish the building or structure or part;
(b) repair the building or structure or part;
(c) remove the building or structure or part;
(d) fence the land on which the building or structure or part stands;
(e) repair any fence that encloses or is on that land;
(f) secure the building or structure or part;
within the time specified in the notice.
(3) If in the opinion of a local authority formed on reasonable grounds any building or other structure or any part of a building or other structure is in a filthy or dilapidated condition, or is infected with disease, or is infested with lice, bugs, rats or other vermin, or is improperly constructed, or from any other cause is unfit to be used or occupied, the local authority may, subject to section 54, by notice in writing, require the owner of the building or structure to do any 1 or more of the following:-
(a) demolish the building or structure or part;
(b) cleanse, purify and disinfect the building or structure or part so as to make it fit to be used or occupied;
(c) repair the building or structure or part so as to make it fit to be used or occupied;
(d) alter the building or structure or part so as to make it fit to be used or occupied;
(e) remove the building or structure or part;
within the time specified in the notice.
(4) If an owner of a building or other structure to which a notice given to the owner under any provision of this section relates fails to comply with such notice, then:-
(a) the local authority may itself cause such steps to be taken and such things to be done as it has, by the notice, required the owner of the building or structure to take or do; and
(b) the owner commits an offence against this Act.
(5) A notice under this section must state that the person to whom it is given has a right of objection under section 57."
It may be, as counsel for the appellant accepts, that the failure of the Council here to discover the defective state of the foundations, could arguably give rise to a right of action against the local authority. The real point however is that a purchaser does have several means of protecting itself, one only of which may be by the obtaining of a report by a local authority. Insistence on a warranty, or condition of fitness or soundness, or the seeking of an inspection and report by an expert, who by making them, will become liable if negligent in not discovering and reporting relevant defects, are others.
It is true, as both Brooking JA in Zumpano293 and Thomas JA in this case294 pointed out, that some cases will involve buildings of mixed residential and commercial uses, that the purchase of a small commercial building with or without a dwelling attached, may itself be a major, indeed the most significant investment by a purchaser in his or her lifetime, and that therefore lines of demarcation of cases of liability may not be able tidily and without anomaly to be drawn. The law is not in other areas295 without anomalies. The guarded, incremental approach of the courts to cases of economic loss will inevitably give rise to apparent and perhaps temporary anomalies as principle is developed.
The better view may however be that abstention from extending the operation of Bryan v Maloney to structures other than residences is not anomalous, but that it is the decision in Bryan v Maloney itself that is the anomaly. I mentioned that there were reasons to question its correctness in addition to those mentioned by Brooking JA in Zumpano and Brennan J in his dissenting judgment in Bryan v Maloney.
What degree of seriousness of defect must exist before liability can be established; a defect in paintwork296, a departure from one or more of the Australian Standards, and which standards, the presence of ten, twelve, fifty or a hundred loose tiles on a roof, or a crumbling but repairable foundation in one corner only? This is another question to be added to those to which I elsewhere refer and to which Bryan v Maloney gives rise.
In Bryan v Maloney the majority made the assumption, it may or may not be correct – no evidence about it was given in the case – that for most people in Australia the purchase of a dwelling will be the most significant investment that a person will make in his or her lifetime. Reliance essentially on assumptions of this kind is fraught with risk. Quite apart from dangers of misapprehension by judges in the absence of evidence, of what is happening in the community, there is also a serious risk of incompleteness.
"[t]heir Lordships' view … seems to us … to have rested upon a narrower view of the scope of the modern law of negligence and a more rigid compartmentalization of contract and tort than is acceptable under the law of this country."
Contrary to their Honours' view however, the subsequent case of Astley v Austrust Ltd303 demonstrates that a clear compartmentalization remains a live, indeed a flourishing plant in Australian jurisprudence.
Perre v Apand Pty Ltd was referred to extensively in argument. The respondents' submission in relation to it is generally correct. The plaintiffs there were in a very exceptional and vulnerable position in which they had no opportunity of protecting themselves by a contractual term or condition. It was the combination of foresight of the likelihood of harm, knowledge of an ascertainable class of vulnerable persons, the latter's helplessness in the circumstances, the control exercised by the defendant, and the causal link between the control and the damage that proved decisive there. The appellant's attempt to rely on Perre v Apand Pty Ltd here was ill-founded in many respects. I will deal with each of the matters relied on by the appellant.
That damage might be suffered as a result of defective design was plainly foreseeable, but little in human affairs is not. Foreseeability, that is reasonable foreseeability, although a necessary element, is of itself not enough to establish liability. Purchasers of a building are members of an identifiable class, but not all of them would have the same use in mind of the building purchased, and over its lifetime the numbers of purchasers could vary greatly.
It is quite wrong however to assert that the appellant or indeed any purchaser is vulnerable. Means of protection are readily to hand as I have already indicated. Furthermore, vulnerability alone does not suffice to ground liability.
The appellant denies an indeterminacy of liability. "Indeterminacy" had three elements in its famous first formulation by Cardozo CJ304:
"an indeterminate amount for an indeterminate time to an indeterminate class."
The appellant's submissions selectively focus on one only of these, of determinacy of class.
Commercial freedom may well be put at risk by the imposition of liability on the respondents here. The contract that was freely made between the first respondent and the first owner was one under which the latter chose to take such risks as flowed from its decision not to have a geotechnical investigation made. Parties to a contract between themselves are entitled to allocate risks, obligations and rights as they choose. They should not be obliged to do so in order to give some unknown person in the future rights against one or other of them. If commercial freedom is to be impaired in this way it is better done by statutory intervention. In the meantime the rule of caveat emptor, which is little more than a rule that people should act diligently, prudently and carefully in their own interests should apply. As Stonham in The Law of Vendor and Purchaser puts it305:
"The rule of caveat emptor applies to contracts of sale of land. The purchaser takes that which he sees, or which, as a prudent and diligent purchaser, he ought to have seen, and is not entitled to have anything better."
Everyone knows that the durability of a building depends upon the soundness of its foundations. The fact that they are below ground does not mean that they cannot be professionally examined and tested. Their state is relevantly there to be seen and assessed.
The appellant resorted to social policy. This is a matter for parliament rather than the courts to weigh. In my view, the social considerations which the appellant invoked are probably outweighed in any event by the other matters to which I have referred. The same may be said of the appellant's claims of economic efficiency, an end which is likely to be just as well served by personal prudence by all purchasers as by obligations imposed after the event by the courts.
In Perre v Apand Pty Ltd, McHugh J contrasted the position of the plaintiffs there with that of plaintiffs in other situations306:
"If the plaintiff has taken, or could have taken steps to protect itself from the defendant's conduct and was not induced by the defendant's conduct from taking such steps, there is no reason why the law should step in and impose a duty on the defendant to protect the plaintiff from the risk of pure economic loss."
To put the matter another way, the appellant has failed to point to a sufficiency of the kind of factors which need to be present and which I thought most relevant in Perre v Apand Pty Ltd307. They need no repetition here. In this area of claims, for economic loss, an evolving area of the law, cases will in practice only be resolved by closely and carefully examining the facts to ascertain whether a sufficiency of factors of a sufficient degree of relevance and importance has been demonstrated. It is better I think to acknowledge and apply that reality than to attempt to state an inflexible principle which is bound, at this stage at least, to fail to meet the justice of the cases which are likely to arise in the future.
It is unnecessary to deal with cases in other jurisdictions in any detail. They are summarized in the judgment of Brennan J in Bryan v Maloney. That summary indicates that the question for decision here has been given different answers in different jurisdictions at different times.
What the debate in this appeal does show however is that this particular area is better regulated, as it has already in many respects and places been, by legislators308.
The appeal should be dismissed with costs.
The Case Stated generally spoke of the structure on which the building stood as its "foundations" rather than "footings" and of the material on which those structures sat as material "below the foundations" rather than "foundations". We adopt the language of the Case Stated in these reasons. ↩
Bass v Permanent Trustee Co Ltd (1999) 198 CLR 334 at 357‑358 [51]-[53]. ↩
(1999) 198 CLR 334 at 359 [56]. See also Malika Holdings Pty Ltd v Stretton (2001) 204 CLR 290 at 308‑309 [61]. ↩
Woolcock St Investments Pty Ltd v CDG Pty Ltd (2002) Aust Torts Reports ¶81‑660. ↩
(2002) Aust Torts Reports ¶81-660 at 68,793 [3]. ↩
(2002) Aust Torts Reports ¶81-660 at 68,795 [24]. ↩
(2002) Aust Torts Reports ¶81-660 at 68,799 [43]. ↩
(1995) 182 CLR 609. ↩
(2002) Aust Torts Reports ¶81-660 at 68,794 [8] per McMurdo P, 68,799 [40] per Thomas JA. ↩
(2002) Aust Torts Reports ¶81-660 at 68,799 [40]. ↩
[1999] 2 Qd R 236. ↩
(2002) Aust Torts Reports ¶81-660 at 68,793 [5].
Woolcock Street Investments Pty Ltd
CDG Pty Ltd [2004] HCA 16; 216 CLR 515; 205 ALR 522; 78 ALJR 628
(1999) 198 CLR 334
(2001) 204 CLR 290
(1995) 182 CLR 609
(1997) 188 CLR 159
(1998) 192 CLR 330
(1999) 198 CLR 180
(2000) 205 CLR 254
Appeal dismissed with costs. The Court of Appeal's negative answer to the Case Stated stood.
In other cases of pure economic loss (Bryan v Maloney is an example) reference has been made to notions of assumption of responsibility and known reliance. The negligent misstatement cases like Mutual Life & Citizens' Assurance Co Ltd v Evatt47 and Shaddock & Associates Pty Ltd v Parramatta City Council [No 1]48 can be seen as cases in which a central plank in the plaintiff's allegation that the defendant owed it a duty of care is the contention that the defendant knew that the plaintiff would rely on the accuracy of the information the defendant provided. And it may be, as Professor Stapleton has suggested49, that these cases, too, can be explained by reference to notions of vulnerability. (The reference in Caltex Oil to economic loss being "inherently likely" can also be seen as consistent with the importance of notions of vulnerability.) It is not necessary in this case, however, to attempt to identify or articulate the breadth of any general proposition about the importance of vulnerability. This case can be decided without doing so.
After discovering the subsidence, Woolcock sued the respondents in the Supreme Court of Queensland for damages claiming that it had suffered economic loss as a result of the respondents' negligent design or negligent supervision during the construction of the building. Subsequently, Atkinson J stated a Case for the Court of Appeal of the Supreme Court of Queensland. The Case Stated asked a single question:
One can be sure that the Law Lords who decided Hedley Byrne did not foresee the consequences that their decision would have for the law of negligence. Although their Lordships' reasons differ, they appear to have believed that, in the case of negligent statements, a claim for economic loss would lie only where the defendant had or could be supposed to have assumed responsibility for the statement. But, once the Law Lords indicated that the so-called exclusionary rule concerning economic loss was no longer exclusionary, actions for "pure" economic loss could not be confined to claims of negligent statement. As a result, appellate courts in the United Kingdom, Canada, New Zealand and Australia have spent much time deciding whether or not defendants owed a duty of care to prevent pure economic loss to plaintiffs. It is not unfair to say that the results have been less than successful. Not only have the courts of different jurisdictions formulated different principles and rules for determining the issue of duty but ultimate appellate courts have reached conflicting decisions in cases where the material facts were similar, if not identical. Nowhere has the conflict in the ultimate appellate courts of various jurisdictions been more obvious than in the law of negligence concerning defective premises.
Their Honours said that a relationship of proximity clearly existed between the builder and Mrs Manion with respect to ordinary physical injury to her person or property. Accordingly, the builder was under a duty to exercise reasonable care in relation to the building work to avoid any reasonably foreseeable risk of such injury. While the relationship between the builder and Mrs Manion concerning physical injury had to be distinguished from the relationship between them concerning mere economic loss, the significance of the distinction varied according to the particular kind of economic loss. The distinction between physical damage to a house by external cause and mere economic loss in the form of diminution in its value when the inadequacy of its footings became manifest by consequent damage to its fabric was "an essentially technical one"112.
"Moreover", said their Honours, "the policy considerations underlying the reluctance of the courts to recognize a relationship of proximity and a consequent duty of care in cases of mere economic loss are inapplicable to a relationship of the kind which existed between Mr Bryan and Mrs Manion as regards the kind of economic loss sustained by Mrs Maloney."113 To the contrary, there were strong reasons for acknowledging the existence of a relevant relationship between the builder and the first owner with respect to that kind of economic loss114. Their Honours said115:
The present case proceeded by way of Case Stated. There is no agreed fact as to whether it is a common practice for builders and their sub-contractors to agree to obligations concerning the condition of premises that might be enforced by the first owner of the premises. Leading writers on Australian construction law suggest a prudent principal should enter into a collateral contract with sub-contractors that contains appropriate warranties130. In Australia, professional institutions have endorsed particular contractual warranties whose purpose is to make the sub‑contractor liable to the principal131.
A subsequent purchaser of a commercial building also has means of protecting him or herself against economic loss arising from the condition of the building. That person can obtain warranties from the vendor. The subsequent purchaser can also have the building examined by relevant experts. But even expert examination may not reveal the presence of latent defects. Moreover, some areas of concern – such as the stability of the foundations of the building – may be examined and tested only at considerable expense.
Although the first and subsequent owners may take steps to protect themselves contractually, it is clear that in some cases contractual remedies may not be sufficient to protect an owner against pure economic loss. In these cases, the owner will be compensated for economic loss only if the law of torts provides a cause of action.
There are many means of protection open to first owners and purchasers of commercial buildings to cover the risk that the building may have latent defects. The first owner can enter into contractual arrangements with those involved in the construction. Those arrangements can include warranties concerning the fitness of the building for the purpose for which it was constructed. The first owner can supplement the contractual arrangements with those directly involved by obtaining similar warranties from directors and other persons connected with the construction of the building. The first owner can employ other professionals to check the work of those directly involved in the project. Subsequent purchasers can protect themselves by entering into similar arrangements with their vendor. They can take an assignment of the vendor's rights (if any) against the builders and others. They can minimise the risks of loss from physical defects by obtaining expert investigations of the building.
Of course, for the reasons that I have given, contractual protections and expert investigations may turn out to be inadequate. In that event, a remedy in tort – particularly a remedy against secondary parties such as architects, engineers and sub-contractors – would be desirable. But cases where contractual protection will be found deficient are likely to be the exception rather than the rule. Whether exceptional or not, the ultimate question is whether the residual advantages that an action in tort would give are great enough to overcome the disadvantages to which I have referred. This involves a value judgment, and the data that might permit that judgment to be made, if the data exists at all, is not before us. Because that is so, the better view is that this Court should not take the step of extending the principle of Bryan v Maloney to commercial premises. That is, this Court should hold that, in the absence of a contract between the owner of commercial premises and a person involved in the design or construction of those premises, the latter does not owe a duty to the current owner to prevent pure economic loss. Where a contract exists, however, the concepts of assumption of responsibility and reliance may create a duty of care in tort as well as obligations in contract.
In Perre v Apand Pty Ltd167, I said:
The nature of the respondents' defaults: The respondents proposed to the original developer that a site investigation by a competent expert should be undertaken. This would have involved the digging of auger holes at various locations of the site and the expert testing of soil samples, by inference, to ensure that the planned foundations were stable and carefully secured against subsidence. The original developer advised that it did not agree to pay for such geotechnical investigations. The respondents acquiesced in that decision. The building went ahead. Now the appellant, a subsequent purchaser, is confronted with evidence of subsidence. By inference, left unattended, this could in time cause direct injury to persons or property.
The common law undoubtedly provides that a person who suffers physical injury as the result of defective design or execution of building work may sue in tort187. It would be anomalous if someone seeking to prevent such physical injury from happening could not recover the costs of doing so. Prevention is usually better than cure. In the words of the majority in Bryan188:
Negligence law is a common law invention. Normally, it will offer solutions that will be considered fair and reasonable to the ordinary person. Courts such as this Court need constantly to remind themselves of this fact. Following the brief description of events set out in the case stated and pleadings, the appellant asked the ultimate question: would it not be fair and reasonable to hold the respondents liable to the appellant for their failure to foresee the likelihood of what so quickly ensued? Clearly, the legal obligation to persuade the Court of its entitlements rests upon the appellant. However, in the sequence of events described, it would not, in my view, be unreasonable to suggest that a forensic burden rests on the respondents to invoke a clear rule of law to exculpate themselves from liability for their apparent carelessness, with its readily foreseeable consequences. Most especially would this be so where the respondents seek summary relief in advance of a full trial of the issues.
In Bryan, Toohey J expressly confined his conclusion to a case relating to "the building of a house that is a non-commercial building"197. Such a precise limitation of application was not stated in the joint reasons of Mason CJ, Deane and Gaudron JJ who, together with Toohey J, constituted the majority. Nevertheless, it is difficult to read the joint reasons in that case in any other way. Not only was that the only factual circumstance considered in Bryan. There are many references throughout the joint reasons that indicate that it was this feature of the building in question that weighed most heavily in overcoming the considerations against upholding a duty of care, which Brennan J collected in his dissent198. Thus the joint reasons referred to the particular relationship between the builder of a dwelling house and its subsequent owners199; the fact that "in this country [such a house] is likely to represent one of the most significant, and possibly the most significant, investment which the subsequent owner will make during his or her lifetime"200; and that "the nature of the property involved, namely a building which was erected to be used as a permanent dwelling house, constitutes an important consideration supporting the conclusion that a relevant relationship … existed between … the builder … and …. a subsequent owner"201.
On the face of things, therefore, the ratio decidendi in Bryan is concerned, and concerned only, with the duty of a builder (or like person) to subsequent purchasers of a dwelling house. Bryan establishes no wider principle; certainly none as a binding legal rule governing Australian courts; certainly not one binding until re-expressed by this Court or imposed by legislation.
Responses to Bryan's defects: The result of these defects of reasoning in Bryan led to various responses by the parties to this appeal concerning what the Court should do in relation to that decision. In summary, the parties severally submitted:
I cannot forbear to mention two features of more recent developments that lead me to nurture the hope that this Court may, even yet, come in time to endorse the Caparo approach. The first is the fact that Caparo continues to be observed in the courts of our region and beyond. Thus, in Pacoil Fiji Ltd v The Attorney General of Fiji233, decided since Sullivan v Moody234, the Supreme Court of Fiji Islands preferred to follow the Caparo approach in deciding whether a cause of action in negligence existed rather than to resort to whatever guidance the decisions of this Court could offer on that point. Our guidance, to say the least, is less than clear. It has driven trial judges and intermediate courts in Australia back to the original Atkinian idea that a duty arises from a "close relationship"235, opaque though that expression is. Alternatively, it has sent them searching for collections of "salient features" of the evidence or notions of "vulnerability", which are at best open-ended and somewhat confusing and at worst question begging.
Relevant policy considerations: I would also point out that, doubtless influenced by the arguments of the parties, the reasons of the other members of the Court in the present appeal expressly address questions of legal policy, much as Caparo mandates. Callinan J states that "social policy … is a matter for parliament rather than the courts to weigh"236. With respect, this fits ill with what all members of the Court did, and said, in Cattanach237. There Callinan J, in particular, remarked238:
Autonomy: Nor would it unduly interfere in the commercial freedom of the respondents to uphold a duty of care. They were already under a clear duty of care to the original owner. The content of that duty in respect of the appellant would not be different. The only question is whether the duty is taken to have been terminated at the happening of a causally irrelevant event, namely the sale of the building to its first and subsequent purchasers. As such sale might have occurred within a very short time, or after a comparatively long interval (over which the respondents had no control, and which they could not foresee), the termination of their liability by reference to such an event is arbitrary, capricious and unreasonable. It does not, therefore, control the duration and scope of the respondents' professional liability according to the common law of negligence. Such liability depended on considerations more closely connected with the nature and foreseeable consequences of the professional conduct of the respondents as civil engineers.
Vulnerability: The vulnerability of the appellant arises from the circumstances of the case. Vulnerability is not confined to cases of poverty, disability, social disadvantage or relative economic power as the majority suggest250. It extends to those who, like the plaintiffs in Perre, might be carrying on a profitable economic enterprise but who are exposed to an insidious risk by the acts of others about which they were unaware and against which they could not reasonably protect themselves. That is also the case here.
I accept that the capacity of an entity to protect itself and its interests is an important factor in determining vulnerability. However, it is not the only one. In a commercial context there may be many more to be considered – assumption of risk, known reliance and commercial pressures, to name but a few. With the benefit of hindsight it is easy to suggest that an entity should have protected itself. However, courts should be reluctant to assume that a commercial entity lacked vulnerability simply because of its commercial character.
In the way the present case proceeded, there is no evidence as to the negotiations that took place in relation to the purchase of the property. Evidence at trial might disclose that pressure was placed upon the appellant or that some degree of urgency in the purchase made the appellant vulnerable to the undisclosed defect. There is no evidence that suggests that the appellant constituted a large commercial enterprise with large resources, skill or experience. In my view, it is a mistake to assume that the appellant possessed such characteristics.
No doubt the pre-purchase tests that the majority have suggested should have been carried out, would have involved great expense. McHugh J suggests that an entity might be vulnerable to risk as a result of "economic constraints"251. There is no evidence on that point one way or the other. There is no guarantee that tests would have disclosed latent defects in the building. The majority suggest that the appellant could, and should, have obtained contractual warranties from the vendor. Again, there is no evidence to suggest that the appellant had any reason to negotiate such warranties. It is dangerous to assume that, simply by virtue of the commercial character of the entity (or the premises), warranties should have been sought, still more that they would have been agreed to.
The very nature of building foundations is that, once put in place, they tend to be concealed by the superstructure of the building erected above them. That was so in the appellant's building. It was still a comparatively new structure. It was a very valuable asset in a regional city. It had been erected under the supervision of professional engineers. The appellant would normally have had no reason to suspect that it was otherwise than properly built upon stable and secure foundations as professionally advised. Its tendency to subside was latent.
In my view, the suggestion that the appellant or its solicitor should have obtained an express warranty involves a great deal of wisdom after the event. Such an answer could be proffered in virtually every instance of economic loss and many cases of physical and property damage as well. It cannot represent a general rule of liability exclusion. The negligence of the respondents, so it is said, involved wisdom before the event. The possibility of other remedies and other precautions involving other persons is ultimately irrelevant. The appellant was vulnerable because of the fact that it had no reasonable intermediate opportunity of discovering, and protecting itself against, the latent defect of which it now complains252. That defect was under the ground and beneath the building. According to the pleadings, it only became known to the appellant when the "distress", which the defect caused to the building, first began to manifest itself in outward signs.
Knowledge: The respondents knew, or ought to have known, of the risk to the owner and the consequences of that risk's occurring253. That was the very reason why the respondents had been retained as civil engineers to provide their professional services for the erection of the building. The fact that they recommended special tests indicates that they appreciated that a risk of subsidence existed. That precise risk is now alleged to have manifested itself.
Conclusion: a viable case: The preconditions for the existence of a duty of care stated in Perre are therefore made good, certainly on the basis of the reasonable arguability of the appellant's pleaded cause of action. The appellant should have its opportunity at trial, by evidence and argument, to establish that a duty of care existed and was breached in the circumstances. In the state of the authorities of this Court, it cannot be said that the appellant is bound to fail. No insuperable barrier of legal authority exists because of the suggestion that the appellant's claim is, or is substantially, to be classified as one for economic loss. No principled barrier could exist because the appellant is a corporation or because its investment was in a commercial building.
Applying limitations law: It is suggested that allowing claims against building professionals for latent defects in buildings which they design, supervise or build will subvert any statute of limitations and the policy behind such statutes because the cause of action will not arise until the damage manifests itself, possibly many years later258. It is said that this would have a serious and unfair effect on the conduct of such building professionals. In my view, such considerations of delay can be adequately dealt with when a court decides the appropriate standard of care and whether there has been a breach of duty in the circumstances. It is not determinative of the question of whether a duty of care is imposed by the law. If the damage does not manifest itself for many years, this will often have a direct bearing on the standard of care of the builder, architect or engineer259 and also on whether there has been a breach. It will often suggest that the work was carried out to the appropriate standard and thus that no liability arises.
In any case, if there is negligence it is unfortunately the nature of the services that such building professionals provide that defects can sometimes manifest themselves years later, with very serious economic and other consequences for those affected. If that is part of the risk of performing such professional building services, those who are neglectful of their duties should not escape ordinary liability which includes the operation of the normal statute of limitations. Otherwise, for a consequence that would ordinarily flow from proved negligence, the statute of limitations is elevated to a new and larger effect than its words provide in shaping the existence of the duty of care. This presses the statute to a protection beyond its language or proper purpose.
Applying the incremental approach: I accept that an "incremental approach" is required by authority. However, it is not enough to demand such an approach260. The holding that the professional engineers were liable to the appellant in the circumstances of this case is as incremental as was the decision of this Court in Perre. The criterion of incrementalism is, in any case, rather unhelpful. It simply means that a global approach, as suggested by Caparo, is not accepted. Instead, this Court has elected to proceed from instance to instance, in search of an ultimate principle that, at this time, we can only perceive imperfectly.
Proved negligence and investors' rights: The fact that the appellant is an investor for economic reward is also irrelevant261. The appellant is entitled to equal justice and the neutral application to its case of applicable legal principles. Equality before the law is a postulate of the rule of law. There is now no absolute rule against the existence of a duty of care even in a case of pure economic loss – assuming this to be such a case. The appellant is an entrepreneur; but none the worse for that fact. It seeks a profit; but that is its legal duty to its shareholders. Corporations such as the appellant are not outside the protection of the tort of negligence. The appellant, like the plaintiffs in Perre, is entitled to invoke the courts for the ascertainment and enforcement of its legal rights. Particularly where the applicable law is in a state of development, this Court should not jump to a conclusion that the appellant's case would not be reasonably arguable once all the evidence is adduced at a trial.
In Malaysia, the courts have declined to follow the approach of the House of Lords in Murphy269. So has the Singapore Court of Appeal270. Within the courts of high authority in the Commonwealth of Nations, the decision of this Court in the present appeal will therefore appear as one that is out of step with majority judicial opinion.
As noted by Brennan J in Bryan271 and Thomas JA in the Court of Appeal in this case272, in the United States of America there have been many voices. No clear trend has emerged. For example, the divided opinion of the Supreme Court of California in Aas v Superior Court273 shows how universal this legal problem is for all jurisdictions of the common law. At least in my opinion, the dissentients in Aas274 had the better of the argument. George CJ described the conclusion of the majority as an "unfortunate misstep in the development of the law"275; a description I also adopt in relation to the views of the majority of this Court in this appeal.
Regional and global consistencies: Wherever precisely the cards fall in the present state of American decisional law, the trend of authority elsewhere, on the whole, lends support to the appellant. In the global and regional economy that is such a feature of the present age and in which Australian investors and civil engineers must now compete, it is undesirable that we should adopt a more restrictive right of recovery whilst our businesses elsewhere are subject to a larger legal duty. At the least, the trend of the case law reinforces the conclusion that the law on this subject remains in a state of active development. That affords further reinforcement for my view that the respondents should be denied what is effectively summary relief. The appellant should be allowed the ordinary facility of a trial of its claim on the basis of all of the relevant evidence that it can adduce.
Another, in my view equally reasonable assumption may be that most purchasers will need to borrow to buy, and that any prudent lender will insist, before lending, for the lender's and the buyer's protection, upon a professional survey of the structure. And as to the assumption that all, indeed most buyers of houses are seeking merely to put a roof over their heads under circumstances of vulnerability, two matters should be noted. The first is that most sellers of residences will shortly become buyers, that therefore, they will at some time be as much in need of a relevant warranty or condition as the buyers to whom they have sold. The second matter is that the majority in Bryan v Maloney failed to have regard to the capital gains tax regime298, which since 1985 has provided for exemptions from capital gains tax on a profitable sale of a principal place of residence, occupied for no fewer than twelve months by the seller, and which almost certainly encourages de facto business investment in houses. Another equally valid assumption in more recent times may be that house ownership for future investment purposes has increased because of cash grants made under the First Home Owner Grant Act 2000 (Q), an enactment forming part of a co-operative endeavour by State and federal governments. It is unnecessary to explore the validity and completeness of the assumptions made by the majority in Bryan v Maloney any further. Nor is there any need to express any final opinion as to the correctness or otherwise of that decision in order to resolve this case, of a purchase of commercial premises.
For the purposes of this appeal it is unnecessary to decide when any relevant period of limitation commenced and whether any limitations enactment could be invoked here. The best position for the purchaser would be that time would not begin to run until the defect manifested itself. If that be the correct position, there may still be problems of indeterminacy, indeterminacy of time, and if not actual indeterminacy of damages, at least uncertainty as to their correct measure. Take the case of a structure, even a dwelling house, theoretically built to last, say forty or fifty years. Assume a buyer acquires the property with the structure erected on it fifteen years into its lifetime. A serious structural defect manifests itself three years later299. I do not say that the law necessarily lacks the ingenuity to devise a means of assessing the loss or damage to the buyer, but any formula for doing so is bound to be complicated, and to involve a large number of imponderables themselves further complicated by such considerations as the need to take account of changes in value of the land in its unimproved state, the relative values of the land and the structure, whether the first eighteen years of life of a structure have an intrinsically greater value than the balance of its life during which the need to provide for natural wear and tear may be greater and more costly, other matters referred to by Brooking JA in Zumpano and the prospect that the structure, even if it had remained sound, would have been demolished or altered in response to changing fashions, diminishing utility or otherwise. All of these matters, and no doubt others that a purchaser's ingenuity may devise, could fall to be considered in litigation against the builder, brought many, many years after the events forming the basis of the action.
In Bryan v Maloney, in their Honours' joint judgment, Mason CJ, Deane and Gaudron JJ sought to explain their divergence from the decisions of the House of Lords in D & F Estates Ltd v Church Commissioners for England300 and Murphy v Brentwood District Council301 on the ground that302:
(2002) Aust Torts Reports ¶81-660 at 68,794 [8]. ↩
(1995) 182 CLR 609 at 617, 619. ↩
(1995) 182 CLR 609 at 663. ↩
(1995) 182 CLR 609 at 628 per Mason CJ, Deane and Gaudron JJ, 665 per Toohey J. ↩
(1995) 182 CLR 609 at 622. ↩
(1995) 182 CLR 609 at 622‑623. ↩
(1995) 182 CLR 609 at 623. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 625. ↩
(1995) 182 CLR 609 at 625. ↩
(1995) 182 CLR 609 at 625. ↩
(1995) 182 CLR 609 at 627. ↩
(1995) 182 CLR 609 at 624. ↩
See, for example, I N Duncan Wallace, "Murphy Rejected: The Bryan v Maloney Landmark", (1995) 3 Tort Law Review 231; Allsop, "Bryan v Maloney and Other Developments in Relation to the Duty of Care in Tort", (1996) 7 Insurance Law Journal 81; Mead, "The Recovery of Economic Loss Arising from Defective Structures – Policy, Principle and the Amorphous Notion of Proximity as a General Concept", (1996) 12 Building and Construction Law 9; Brooking, "Bryan v Maloney – Its Scope and Future", in Mullany and Linden (eds), Torts Tomorrow – A Tribute to John Fleming, (1998) 57. ↩
[1997] 2 VR 525 at 528‑536. ↩
For example, Zumpano v Montagnese [1997] 2 VR 525 at 528‑529 per Brooking JA. ↩
(1995) 182 CLR 609 at 619. ↩
Hill v Van Erp (1997) 188 CLR 159 at 176‑179 per Dawson J, 189 per Toohey J, 210 per McHugh J, 237‑239 per Gummow J; Pyrenees Shire Council v Day (1998) 192 CLR 330 at 360‑361 [76] per Toohey J, 414 [238] per Kirby J; Perre v Apand Pty Ltd (1999) 198 CLR 180 at 209‑210 [74]‑[76] per McHugh J, 284 [281]‑[282] per Kirby J, 302 [333] per Hayne J; Crimmins v Stevedoring Industry Finance Committee (1999) 200 CLR 1 at 13 [3] per Gleeson CJ, 32‑33 [73], 33‑34 [77] per McHugh J, 56 [149] per Gummow J, 80 [222] per Kirby J, 96‑97 [270]‑[274] per Hayne J; Modbury Triangle Shopping Centre Pty Ltd v Anzil (2000) 205 CLR 254 at 275 [61] per Kirby J; Brodie v Singleton Shire Council (2001) 206 CLR 512 at 630‑631 [316] per Hayne J; Sullivan v Moody (2001) 207 CLR 562 at 578‑579 [48] per Gleeson CJ, Gaudron, McHugh, Hayne and Callinan JJ; Tame v New South Wales (2002) 211 CLR 317 at 355‑356 [104]-[107] per McHugh J, 409 [268] per Hayne J; Graham Barclay Oysters Pty Ltd v Ryan (2002) 211 CLR 540 at 583 [99] per McHugh J, 624‑625 [234]‑[236] per Kirby J. ↩
Dutton v Bognor Regis Urban District Council [1972] 1 QB 373 at 396 per Lord Denning MR; Anns v Merton London Borough Council [1978] AC 728 at 759 per Lord Wilberforce. ↩
(1985) 157 CLR 424 at 446‑447 per Gibbs CJ, 466 per Mason J, 471 per Wilson J, 490 per Brennan J, 504 per Deane J. ↩
(1995) 182 CLR 609 at 617 per Mason CJ, Deane and Gaudron JJ, 657 per Toohey J; cf at 643 per Brennan J. ↩
[1991] 1 AC 398. ↩
(1995) 182 CLR 609 at 632. ↩
See per Lord Reid in Dorset Yacht Co v Home Office [1970] AC 1004 at 1027. ↩
Ultramares Corporation v Touche 255 NY 170 at 179 (1931) [174 NE 441 at 444]. ↩
(1976) 136 CLR 529. ↩
(1875) LR 10 QB 453. ↩
Caltex Oil (Australia) Pty Ltd v The Dredge "Willemstad" (1976) 136 CLR 529 at 576‑578. See also Hill v Van Erp (1997) 188 CLR 159 at 233‑234; Pyrenees Shire Council v Day (1998) 192 CLR 330 at 389 [168]; Perre v Apand Pty Ltd (1999) 198 CLR 180 at 254 [201] per Gummow J. ↩
(1976) 136 CLR 529 at 576. ↩
(1999) 198 CLR 180. ↩
Stapleton, "Comparative Economic Loss: Lessons from Case‑Law‑Focused 'Middle Theory'", (2002) 50 UCLA Law Review 531 at 558‑559. ↩
(1997) 188 CLR 159. ↩
(1997) 188 CLR 241. ↩
(1968) 122 CLR 556; (1970) 122 CLR 628; [1971] AC 793. ↩
(1981) 150 CLR 225. ↩
(2002) 50 UCLA Law Review 531 at 558‑559. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 619. ↩
(1995) 182 CLR 609 at 624‑625. ↩
(1963) 110 CLR 74 at 85. ↩
See also Hill v Van Erp (1997) 188 CLR 159 at 167 per Brennan CJ. ↩
cf Woollahra Municipal Council v Sved (1996) 40 NSWLR 101 at 120 per Priestley JA. ↩
(1995) 182 CLR 609 at 665. ↩
Building Act 1975 (Q), s 53(2). ↩
(1995) 182 CLR 609 at 625. ↩
Winnipeg Condominium Corporation No 36 v Bird Construction Co [1995] 1 SCR 85; Martel Building Ltd v Canada [2000] 2 SCR 860; Cooper v Hobart [2001] 3 SCR 537. ↩
Invercargill City Council v Hamlin [1996] AC 624. ↩
Arab‑Malaysian Finance Bhd v Steven Phoa Cheng Loon [2003] 1 MLJ 567. ↩
RSP Architects Planners & Engineers (Raglan Squire & Partners FE) v Management Corporation Strata Title Plan No 1075 [1999] 2 SLR 449. ↩
(1995) 182 CLR 609. ↩
[1964] AC 465. ↩
Candlewood Navigation Corporation Ltd v Mitsui OSK Lines Ltd [1986] AC 1 at 15-17. ↩
Ultramares Corporation v Touche 174 NE 441 at 444 (1931). ↩
Perre v Apand Pty Ltd (1999) 198 CLR 180 at 221 [106]. ↩
Commissioner for Railways (NSW) v Scott (1959) 102 CLR 392. ↩
[1978] AC 728. ↩
[1978] AC 728 at 751-752. ↩
[1978] AC 728 at 760. ↩
[1978] AC 728 at 759. ↩
[1983] 2 AC 1 at 16. ↩
[1932] AC 562. ↩
[1983] 1 AC 520. ↩
[1989] AC 177. ↩
[1991] 1 AC 398. ↩
[1989] AC 177 at 207. ↩
[1984] 2 SCR 2. ↩
[1986] 2 SCR 147 at 224. ↩
[1995] 1 SCR 85. ↩
[1995] 1 SCR 85 at 116. Other suggested criteria were: "a substantial danger to the health and safety of the occupants" at 121 and "foreseeable and substantial danger to the health and safety of the occupants" at 129. ↩
Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394; Mount Albert Borough Council v Johnson [1979] 2 NZLR 234; Stieller v Porirua City Council [1983] NZLR 628; [1986] 1 NZLR 84; Brown v Heathcote County Council [1986] 1 NZLR 76; Chase v de Groot [1994] 1 NZLR 613; Invercargill City Council v Hamlin [1994] 3 NZLR 513. ↩
[1977] 1 NZLR 394 at 410, 414, 417, 422-423. ↩
[1979] 2 NZLR 234. ↩
[1979] 2 NZLR 234 at 239. ↩
[1979] 2 NZLR 234 at 239. ↩
[1994] 3 NZLR 513. ↩
[1994] 3 NZLR 513 at 522-524. ↩
[1996] AC 624 at 648. ↩
[1991] 1 AC 398. ↩
Voli v Inglewood Shire Council (1963) 110 CLR 74; Florida Hotels Pty Ltd v Mayo (1965) 113 CLR 588*.* ↩
(1985) 157 CLR 424. ↩
(1985) 157 CLR 424 at 447. ↩
(1985) 157 CLR 424 at 505. ↩
Hawkins v Clayton (1988) 164 CLR 539 at 588. ↩
Bryan v Maloney (1995) 182 CLR 609 at 617. ↩
(1995) 182 CLR 609. ↩
See generally Llewellyn, The Case Law System in America, (1989) at 14-15, based on lectures given by Karl Llewellyn in 1928-1929 at the Leipzig Faculty of Law while on leave from Columbia University. ↩
[1932] AC 562. ↩
cf Grant v Australian Knitting Mills Ltd (1935) 54 CLR 49 at 62-68. ↩
Mason CJ, Deane and Gaudron JJ. (Toohey J in a separate judgment reached the same result.) ↩
(1995) 182 CLR 609 at 615. ↩
(1995) 182 CLR 609 at 616. ↩
(1995) 182 CLR 609 at 617. ↩
(1995) 182 CLR 609 at 618 citing Ultramares Corporation v Touche 174 NE 441 at 444 (1931). ↩
(1995) 182 CLR 609 at 618. ↩
(1995) 182 CLR 609 at 619-620. ↩
(1995) 182 CLR 609 at 621. ↩
(1995) 182 CLR 609 at 622. ↩
(1995) 182 CLR 609 at 622. ↩
(1995) 182 CLR 609 at 623. ↩
(1995) 182 CLR 609 at 623. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 624-625. ↩
(1995) 182 CLR 609 at 625. ↩
(1995) 182 CLR 609 at 627. ↩
(1995) 182 CLR 609 at 617. ↩
(2001) 207 CLR 562. ↩
(1999) 198 CLR 180 at 220 [105]. ↩
Moneypenny v Hartland (1826) 2 Car & P 378 [172 ER 171]; Columbus Company v Clowes [1903] 1 KB 244; cf Auburn Municipal Council v ARC Engineering Pty Ltd [1973] 1 NSWLR 513 at 518, 519. ↩
Sullivan v Moody (2001) 207 CLR 562 at 576 [42]. ↩
(1997) 188 CLR 159 at 211. ↩
Perre v Apand Pty Ltd (1999) 198 CLR 180 at 224 [115]. ↩
Bryan v Maloney (1995) 182 CLR 609 at 623-624. ↩
Young & Marten Ltd v McManus Childs Ltd [1969] 1 AC 454. ↩
Invercargill City Council v Hamlin [1996] AC 624 at 634. ↩
Dorter and Sharkey, Building and Construction Contracts in Australia: Law and Practice, 2nd ed (looseleaf service) at [5.630]. ↩
Bailey, Construction Law in Australia, 2nd ed (1998) at 156. ↩
Smith v Leurs (1945) 70 CLR 256 at 262; Modbury Triangle Shopping Centre Pty Ltd v Anzil (2000) 205 CLR 254 at 263-264 [18]-[21], 291-293 [108]-[113]. ↩
[1989] AC 177. ↩
[1964] AC 465. ↩
Candlewood Navigation Corporation Ltd v Mitsui OSK Lines Ltd [1986] AC 1 at 17; Leigh and Sillavan Ltd v Aliakmon Shipping Co Ltd [1986] AC 785 at 818-819. ↩
[1989] AC 177. ↩
[1989] AC 177 at 207. ↩
[1932] AC 562. ↩
[1995] 2 AC 207. ↩
(1997) 188 CLR 159. ↩
[1995] 2 AC 207 at 269. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 624. ↩
Groom v Crocker [1939] 1 KB 194; Bagot v Stevens Scanlan & Co Ltd [1966] 1 QB 197. ↩
[1995] 2 AC 145. ↩
[1990] 1 AC 831. ↩
(1995) 182 CLR 609 at 627-628. ↩
Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394 at 419, 422; cf Esanda Finance Corporation Ltd v Peat Marwick Hungerfords (1997) 188 CLR 241 at 283-284. ↩
Esanda Finance Corporation Ltd v Peat Marwick Hungerfords (1997) 188 CLR 241 at 286-287. ↩
cf Junior Books Ltd v Veitchi Co Ltd [1983] 1 AC 520 at 533. ↩
[1995] 2 VR 594 at 598. ↩
Sullivan v Moody (2001) 207 CLR 562 at 581 [55]. ↩
Lynn v Bamber [1930] 2 KB 72 at 74. ↩
[1932] AC 562. ↩
(1996) 186 CLR 541 at 551. ↩
R v Lawrence [1982] AC 510 at 517. ↩
(1996) 186 CLR 541 at 552-553. ↩
Jones v Bellgrove Properties Ltd [1949] 2 KB 700 at 704. ↩
RB Policies at Lloyd's v Butler [1950] 1 KB 76 at 81-82. ↩
New South Wales Law Reform Commission, Limitation of Actions for Personal Injury Claims, Report No 50, (1986) at 3; Law Reform Commission of Western Australia, Limitation and Notice of Actions, Discussion Paper, Project No 36, Pt II, (1992) at 11. ↩
In Limitation of Actions for Latent Personal Injuries, Report No 69, (1992) at 10, the Law Reform Commissioner of Tasmania said: "The need for certainty can be justified in many cases. For example, manufacturers need to be able to 'close their books' and calculate the potential liability of their business enterprise with some degree of certainty before embarking on future development. Under modern circumstances, an award of damages compensation may be so large as to jeopardise the financial viability of a business. The threat of open-ended liability from unforeseen claims may be an unreasonable burden on a business. Limitation periods may allow for more accurate and certain assessment of potential liability." ↩
New South Wales Law Reform Commission, Limitation of Actions for Personal Injury Claims, Report No 50, (1986) at 3. ↩
Kelley, "The Discovery Rule for Personal Injury Statutes of Limitations: Reflections on the British Experience", (1978) 24 Wayne Law Review 1641 at 1644. ↩
"Developments in the Law – Statutes of Limitations", (1950) 63 Harvard Law Review 1177 at 1185. ↩
The vast majority of defendants in personal injury actions are insured. Consequently, the amount of the verdict will not be met by the defendant. Nevertheless, it is a charge on the revenue of the insurer for the relevant year and is ultimately met by the shareholders of the insurer or the individual proprietors of the insurance business if the insurer is not incorporated. Although the burden of the plaintiff's claim is spread in such cases, the consequences for the proprietors of the insurance business can be significant. When a large number of claims are allowed to be brought out of time, as has been the case in respect of some types of injuries or in some industries in recent years, the financial consequences for an insurer can be drastic. ↩
New South Wales Law Reform Commission, Limitation of Actions for Personal Injury Claims, Report No 50, (1986) at 3; Law Reform Commission of Western Australia, Limitation and Notice of Actions, Discussion Paper, Project No 36, Pt II, (1992) at 11. ↩
(1999) 198 CLR 180 at 225 [118]. ↩
(1995) 182 CLR 609. ↩
[1997] 2 VR 525 at 528. ↩
Mead, "The Recovery of Economic Loss Arising from Defective Structures – Policy, Principle and the Amorphous Notion of Proximity as a General Concept", (1996) 12 Building and Construction Law 9. ↩
(1995) 182 CLR 609. ↩
[1997] 2 VR 525 at 528. ↩
Grimal, The Dictionary of Classical Mythology, (1986) at 343. ↩
[1997] 2 VR 525 at 528. ↩
[1997] 2 VR 525 at 528 referring to the opinion of Clarke JA in Woollahra Municipal Council v Sved (1996) 40 NSWLR 101 at 134. ↩
[1997] 2 VR 525 at 534. ↩
Reasons of Gleeson CJ, Gummow, Hayne and Heydon JJ ("joint reasons") at [1]-[2]; reasons of McHugh J at [39]-[41]; reasons of Callinan J at [194]-[199]. ↩
Joint reasons at [3]-[7]. ↩
Joint reasons at [8]; reasons of McHugh J at [42]-[43]; reasons of Callinan J at [200]. ↩
Woolcock St Investments Pty Ltd v CDG Pty Ltd (2002) Aust Torts Rep ¶81-660. ↩
Joint reasons at [10]-[15]; reasons of McHugh J at [63]-[73]. ↩
Joint reasons at [16]-[18]; reasons of Callinan J at [209]-[211]. ↩
As in Hill v Van Erp (1997) 188 CLR 159; Pyrenees Shire Council v Day (1998) 192 CLR 330; Perre v Apand Pty Ltd (1999) 198 CLR 180; Crimmins v Stevedoring Industry Finance Committee (1999) 200 CLR 1. ↩
As in Romeo v Conservation Commission (NT) (1998) 192 CLR 431. ↩
See eg Hill v Van Erp (1997) 188 CLR 159 at 225-231 citing White v Jones [1995] 2 AC 207 at 223-224; Astley v Austrust Ltd (1999) 197 CLR 1 at 20 [44], 23 [48]. ↩
Cattanach v Melchior (2003) 77 ALJR 1312 at 1348 [179]; 199 ALR 131 at 180. ↩
Voli v Inglewood Shire Council (1963) 110 CLR 74. ↩
(1995) 182 CLR 609 at 628. ↩
Todd, "Negligence and Policy", in Rishworth (ed), The struggle for simplicity in the law, (1997) 105 at 107-108. ↩
Stapleton, "Comparative Economic Loss: Lessons from Case-Law-Focused 'Middle Theory'", (2002) 50 UCLA Law Review 531 at 559. ↩
Dey v Victorian Railways Commissioners (1949) 78 CLR 62 at 91. ↩
See E (A Minor) v Dorset County Council [1995] 2 AC 633 at 694 per Sir Thomas Bingham MR; X (Minors) v Bedfordshire County Council [1995] 2 AC 633 at 740-741; Barrett v Enfield London Borough Council [2001] 2 AC 550 at 557 per Lord Browne-Wilkinson; cf National Mutual Life Association of Australasia Ltd v Coffey & Partners Pty Ltd [1991] 2 Qd R 401 at 407. ↩
Oceanic Sun Line Special Shipping Co Inc v Fay (1988) 165 CLR 197 at 252; Northern Territory v Mengel (1995) 185 CLR 307 at 347. ↩
(1995) 182 CLR 609. ↩
(1999) 198 CLR 180. ↩
As suggested in the Court of Appeal: Woolcock St Investments Pty Ltd v CDG Pty Ltd (2002) Aust Torts Rep ¶81-660 at 68,794 [8] per McMurdo P, 68,799 [40] per Thomas JA. ↩
(1995) 182 CLR 609 at 665. ↩
(1995) 182 CLR 609 at 645-648. ↩
(1995) 182 CLR 609 at 624. ↩
(1995) 182 CLR 609 at 625 (original emphasis). ↩
(1995) 182 CLR 609 at 630. ↩
[1997] 2 VR 525 at 528-536. ↩
Joint reasons at [16]; reasons of Callinan J at [202]-[203]. The reasoning of Brooking JA cuts both ways. The respondents used it to urge the overruling or confinement of Bryan as a flawed decision. The appellant used it to show that Bryan was correctly decided but that it needed to be placed on a broader, and more convincing, legal basis. ↩
(1995) 182 CLR 609 at 617, 624-625, 627, 628, 663-665. ↩
Joint reasons at [12]-[13], [18]; reasons of McHugh J at [66]-[70], [72]; reasons of Callinan J at [211]. ↩
Perre v Apand Pty Ltd (1999) 198 CLR 180 at 210 [75], 284 [281], 300-301 [330]. ↩
Donoghue v Stevenson [1932] AC 562 at 580. ↩
Sullivan v Moody (2001) 207 CLR 562 at 578-579 [48]. ↩
This appears to have been the view of Brooking JA in Zumpano v Montagnese [1997] 2 VR 525 at 528 although he was too polite to say so. ↩
This was the view suggested by Clarke JA in Woollahra Municipal Council v Sved (1996) 40 NSWLR 101 at 134. ↩
See joint reasons at [16]-[18]. ↩
eg Stapleton, "The golden thread at the heart of tort law: Protection of the vulnerable", (2003) 24 Australian Bar Review 135 at 142. ↩
Pilmer v Duke Group Ltd (In Liq) (2001) 207 CLR 165 at 217-218 [136.2]; Finn, "The Courts and the Vulnerable", (1996) 162 Law Society of the Australian Capital Territory Gazette 61. ↩
Stapleton, "The golden thread at the heart of tort law: Protection of the vulnerable", (2003) 24 Australian Bar Review 135 at 140 referring to Luntz, "Torts Turnaround Downunder", (2001) 1 Oxford University Commonwealth Law Journal 95. ↩
See reasons of McHugh J at [73]. ↩
(2003) 77 ALJR 1312; 199 ALR 131. ↩
Tame v New South Wales (2002) 211 CLR 317 at 329 [6]; Cattanach v Melchior (2003) 77 ALJR 1312 at 1342 [148]; 199 ALR 131 at 171-172. ↩
The words of Cardozo CJ in Ultramares Corporation v Touche 174 NE 441 at 444 (1931) are normally cited, as they were by Brennan J in his dissent in Bryan. See also Perre v Apand Pty Ltd (1999) 198 CLR 180 at 267-268 [243]; cf joint reasons at [21]; reasons of McHugh J at [46]-[47]; reasons of Callinan J at [225]. ↩
(2003) 77 ALJR 1312 at 1327 [67]-[68], 1342 [148]-[149], 1371 [300]; 199 ALR 131 at 151, 171-172, 212. ↩
(2003) 77 ALJR 1312 at 1316-1317 [19], 1319-1320 [30]; 199 ALR 131 at 136, 140-141. ↩
Woolcock Street Investments Pty Ltd v CDG Pty Ltd transcript of proceedings, 23 June 2003 at 14. ↩
See eg Voli v Inglewood Shire Council (1963) 110 CLR 74. ↩
See Bryan v Maloney (1995) 182 CLR 609 at 623 where the joint reasons described it as "essentially technical"; see also at 657 per Toohey J. ↩
Old Gate Estates Ltd v Toplis [1939] 3 All ER 209 at 217. ↩
Candler v Crane, Christmas & Co [1951] 2 KB 164 at 179 per Denning LJ (diss). ↩
[1964] AC 465. ↩
(1976) 136 CLR 529 at 576. ↩
(1999) 198 CLR 180 at 268-275 [246]-[258]. See eg Pyrenees Shire Council v Day (1998) 192 CLR 330 at 419-420 [243]-[244]. See also reasons of McHugh J at [45]-[48]. ↩
(1999) 198 CLR 180 at 275 [259]. ↩
[1990] 2 AC 605 at 617-618 per Lord Bridge of Harwich; cf X (Minors) v Bedfordshire County Council [1995] 2 AC 633 at 749; Graham Barclay Oysters Pty Ltd v Ryan (2002) 211 CLR 540 at 626-627 [238]. ↩
In Graham Barclay Oysters Pty Ltd v Ryan (2002) 211 CLR 540 at 624-627 [236]-[238]. ↩
Most especially in Sullivan v Moody (2001) 207 CLR 562 at 579 [49] a case in which I did not participate. ↩
Unreported, Supreme Court of Fiji Islands, 11 July 2003 per Gault, Mason and French JJ. ↩
(2001) 207 CLR 562. ↩
Avenhouse v Hornsby Shire Council (1998) 44 NSWLR 1 at 8 noted in Perre v Apand Pty Ltd (1999) 198 CLR 180 at 253 [198]. ↩
Reasons of Callinan J at [229]. ↩
(2003) 77 ALJR 1312; 199 ALR 131. ↩
(2003) 77 ALJR 1312 at 1369 [291]; 199 ALR 131 at 209. ↩
See eg Osmond v Public Service Board of New South Wales [1984] 3 NSWLR 447 at 462-464; Soulemezis v Dudley (Holdings) Pty Ltd (1987) 10 NSWLR 247 at 259-261; Hartigan Nominees Pty Ltd v Rydge (1992) 29 NSWLR 405 at 418-421; Wong v The Queen (2001) 207 CLR 584 at 621-622 [101]-[102]; Johnson v The Queen [2004] HCA 15 at [41]. ↩
See reasons of McHugh J at [88]-[105]. ↩
(1999) 198 CLR 180 at 192 [5] per Gleeson CJ, 199-200 [32]-[33] per Gaudron J, 204 [50] per McHugh J, 241 [168]-[169] per Gummow J, 289-290 [298]-[300] of my own reasons, 299-300 [329] per Hayne J, 322 [395], 324 [402] per Callinan J. ↩
See Perre v Apand Pty Ltd (1999) 198 CLR 180 at 217 [94]. ↩
cf Mutual Life & Citizens' Assurance Co Ltd v Evatt (1968) 122 CLR 556 at 569. ↩
Perre v Apand Pty Ltd (1999) 198 CLR 180 at 253 [198]. ↩
(1976) 136 CLR 529 at 576. ↩
Perre v Apand Pty Ltd (1999) 198 CLR 180 at 219-220 [102]-[105]. ↩
Reasons of McHugh J at [97]. ↩
cf reasons of McHugh J at [74]-[87]. ↩
Invercargill City Council v Hamlin [1996] AC 624 at 648 (PC). ↩
cf Hodgkinson v Simms [1994] 3 SCR 377 at 412; reasons of McHugh J at [80]. ↩
Reasons of McHugh J at [80]. ↩
cf Kriegler v Eichler Homes Inc 74 Cal Rptr 749 at 752-753 (1969). ↩
Esanda Finance Corporation Ltd v Peat Marwick Hungerfords (1997) 188 CLR 241. ↩
Joint reasons at [35]; reasons of Callinan J at [233]. ↩
Reasons of Callinan J at [227]. ↩
cf Winnipeg Condominium Corporation No 36 v Bird Construction Co [1995] 1 SCR 85 at 126-128 per La Forest J. ↩
Reasons of Callinan J at [212]. ↩
Reasons of McHugh J at [102]-[105]. ↩
As to the standard of care of architects see Voli v Inglewood Shire Council (1963) 110 CLR 74 at 84 per Windeyer J. The same principle applies to engineers: Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners [1975] 1 WLR 1095 at 1101 (CA); [1975] 3 All ER 99 at 104-105. ↩
Reasons of Callinan J at [214]; cf Sutherland Shire Council v Heyman (1985) 157 CLR 424 at 481; Caparo Industries Plc v Dickman [1990] 2 AC 605 at 617-618. ↩
Reasons of Callinan J at [206]. ↩
[1991] 1 AC 398. ↩
[1978] AC 728. ↩
Bellefield Computer Services v E Turner & Sons Ltd [2003] Lloyd's Rep PN 53; Sahib Foods Ltd v Paskin Kyriakides Sands (a firm) [2003] Lloyd's Rep PN 181. ↩
[1978] AC 728. See City of Kamloops v Nielsen [1984] 2 SCR 2 noted in Bryan v Maloney (1995) 182 CLR 609 at 648-651. ↩
[1995] 1 SCR 85 at 121 [43]. ↩
[1977] 1 NZLR 394. ↩
Invercargill City Council v Hamlin [1996] AC 624. See reasons of McHugh J at [55]. ↩
Dr Abdul Hamid Abdul Rashid v Jurusan Malaysia Consultants [1997] 3 MLJ 546 (High Court); see also Arab-Malaysian Finance Bhd v Steven Phoa Cheng Loon [2003] 1 MLJ 567 (CA) where reasonable foreseeability appears to have been adopted as the critical test. ↩
RSP Architects Planners & Engineers v Ocean Front Pte Ltd [1996] 1 SLR 113; RSP Architects Planners & Engineers v Management Corporation Strata Title Plan No 1075 [1999] 2 SLR 449. ↩
(1995) 182 CLR 609 at 651-652. ↩
Woolcock St Investments Pty Ltd v CDG Pty Ltd (2002) Aust Torts Rep ¶81-660 at 68,796 [25]. ↩
12 P 3d 1125 (2000). ↩
George CJ and Mosk J. ↩
12 P 3d 1125 at 1156 (2000). This is an area of the law where "wrong turning[s]" are endemic, as Lord Bridge of Harwich acknowledged in Caparo Industries Plc v Dickman [1990] 2 AC 605 at 619 by reference to Le Lievre v Gould [1893] 1 QB 491. After that decision it took 70 years to be set once again on a "right path". This occurred in Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465, upholding Denning LJ's dissent in Candler v Crane, Christmas & Co [1951] 2 KB 164. ↩
(1995) 182 CLR 609. ↩
(1995) 182 CLR 609 at 625. ↩
Voli v Inglewood Shire Council (1963) 110 CLR 74. ↩
The hall in Voli was being hired out at the time. ↩
In Bryan v Maloney (1995) 182 CLR 609 at 623 Mason CJ, Deane and Gaudron JJ described it as "essentially technical"; Toohey J at 657 regarded the classification of the loss as pure economic loss as "debatable". ↩
[1997] 2 VR 525 at 528-529. ↩
[1992] 1 VR 283. ↩
Bryan v Maloney (1995) 182 CLR 609 at 665. ↩
Bryan v Maloney (1995) 182 CLR 609 at 630. ↩
CAI Fences Pty Ltd v A Ravi (Builder) Pty Ltd unreported, Supreme Court of Western Australia, 27 December 1990. ↩
(1999) 198 CLR 180. ↩
(1995) 182 CLR 609 at 625-627. ↩
(1995) 182 CLR 609 at 625. ↩
(1995) 182 CLR 609 at 627. ↩
(1995) 182 CLR 609 at 644. ↩
See Winnipeg Condominium Corp No 36 v Bird Construction Co (1993) 101 DLR (4th) 699 at 711. The observation of Huband JA with reference to "caveat emptor" is apposite to a remote purchaser's rights in respect of mere defects in a building. The decision of the Manitoba Court of Appeal was reversed by the Supreme Court which considered the defects to be a substantial danger to the health and safety of the occupants: [1995] 1 SCR 85. ↩
See for example (1995) 182 CLR 609 at 625 per Mason CJ, Deane and Gaudron JJ. ↩
[1997] 2 VR 525 at 528-529. ↩
(2002) Aust Torts Reports ¶81-660 at 68,797 [32]. ↩
For example, see Meagher, Heydon and Leeming, Meagher, Gummow and Lehane's Equity: Doctrines and Remedies, 4th ed (2002) at 417 which outlines that the equitable doctrine of marshalling may be invoked where one claimant has the right to satisfy a claim from two funds and another claimant has the right to resort to one only of the two funds. In such a situation equity may intervene so that the double claimant must exercise its security over the fund to which the single claimant has no claim. ↩
Goulding v Kirby [2002] NSWCA 393. ↩
cf Woods v Multi-Sport Holdings Pty Ltd (2002) 208 CLR 460 at 512-513 [166] per Callinan J. ↩
See now Pt 3-1, Div 118, sub-div 118-B of the Income Tax Assessment Act 1997 (Cth). ↩
cf D & F Estates Ltd v Church Commissioners for England [1989] AC 177 where the defect manifested itself 17 years after the construction. ↩
[1989] AC 177. ↩
[1991] 1 AC 398. ↩
(1995) 182 CLR 609 at 629. ↩
(1999) 197 CLR 1. ↩
Ultramares Corporation v Touche 174 NE 441 at 444 (1931). ↩
Stonham, The Law of Vendor and Purchaser, (1964) at 228 [355]. ↩
(1999) 198 CLR 180 at 225 [118]. ↩
(1999) 198 CLR 180 at 326-329 [406]-[422]. ↩
Statutory warranties that enure for the benefit of owners and successors in title are implied in contracts for residential building work in New South Wales (Home Building Act 1989 (NSW), ss 18A-18G), Victoria (Domestic Building Contracts Act 1995 (Vic), ss 8-10), South Australia (Building Work Contractors Act 1995 (SA), s 32), Tasmania (Housing Indemnity Act 1992 (Tas), ss 7‑9) and the Australian Capital Territory (Building Act 1972 (ACT), s 62). Further, statutory insurance or guarantee schemes for residential building work enure for the benefit of owners and successors in title in all States and the Australian Capital Territory: see Home Building Act 1989 (NSW), ss 90‑99; House Contracts Guarantee Act 1987 (Vic), ss 5‑8; Building Work Contractors Act 1995 (SA), ss 33-35; Queensland Building Services Authority Act 1991 (Q), ss 68-69 and Sched 2; Home Building Contracts Act 1991 (WA), ss 25A-25D; Housing Indemnity Act 1992 (Tas), ss 11-14; Building Act 1972 (ACT), ss 64-65. ↩
(2001) 206 CLR 512
(2001) 207 CLR 562
(2002) 211 CLR 540
(1985) 157 CLR 424
(1976) 136 CLR 529
(1997) 188 CLR 241
(1968) 122 CLR 556
(1970) 122 CLR 628
(1981) 150 CLR 225
(1963) 110 CLR 74
(1996) 40 NSWLR 101
(1959) 102 CLR 392
(1965) 113 CLR 588
(1988) 164 CLR 539
(1935) 54 CLR 49
(1945) 70 CLR 256
(1996) 186 CLR 541
(1999) 200 CLR 1
(1998) 192 CLR 431
(1999) 197 CLR 1
(2003) 77 ALJR 1312
(1949) 78 CLR 62
(1988) 165 CLR 197
(1995) 185 CLR 307
(2001) 207 CLR 165
(2002) 211 CLR 317
(1998) 44 NSWLR 1
(1987) 10 NSWLR 247
(1992) 29 NSWLR 405
(2001) 207 CLR 584
(2002) 208 CLR 460