[2020] NSWCATAP 143
NCAT Appeal Panel
2020-02-24
Original judgment source is linked above.
Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115 at [55] Kostas v HIA Insurance Services Pty Ltd [2010] HCA 32 Lawrence v Ciantar [2019] NSWSC 464 Minister for Immigration and Multicultural Affairs v Al-Miahi [2001] FCA 744 Re Bleriot Manufacturing Aircraft Co (1916) 32 TLR 253 Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR 359 TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93 Wesiak v D&R Constructions (Aust) Pty Ltd [2016] NSWCA 353. Texts Cited: None cited Category: Principal judgment Parties: Anne Nyunt: (Appellant) North Shore Homes Pty Ltd (Respondent) Representation: Counsel B DeBuse (Appellant) A Kaufmann (Respondent)
Solicitors McCooe Raves & Poole (Appellant) BWT Legal Pty Ltd (Respondent) File Number(s): AP 19/54732 Publication restriction: Nil Decision under appeal Court or tribunal: Civil and Administrative Tribunal Jurisdiction: Consumer and Commercial Division Citation: N/A Date of Decision: 12 November 2019 Before: G Burton SC, Senior Member File Number(s): HB 18/46940; HB 18/48386
Introduction
Background
Summary of the Tribunal's Decision and Orders
Further Policy of Insurance Obtained by the Builder and Application to re-list
Appeal Grounds
Grounds 1 to 4
Statutory Basis of the Appeal
Grounds 1 to 4: the builder's entitlement to claim on a quantum meruit
Grounds 5 to 8: the owner's entitlement to terminate the contract by reason of the builder's contraventions of the HBA
Grounds 10 and 11: whether the builder has complied with Order 2 of the Tribunal's Orders in relation to the provision of insurance.
Respondents' Submissions
Grounds 1 to 4: the builder's entitlement to claim on a quantum meruit
Grounds 5 to 8: the owner's entitlement to terminate the contract by reason of the builder's contraventions of the HBA.
Grounds 10 and 11: whether the builder has complied with Order 2 of the Tribunal's Orders in relation to the provision of insurance.
Grounds 1 to 4: the builder's entitlement to claim on a quantum meruit
The Evidence of Deliberateness and Cross Examination of the Builder's Principal
Grounds 5 to 8: the owner's entitlement to terminate the contract by reason of the builder's contraventions of the HBA
Statutory Construction
Legislative Intention to Exclude a Right To Terminate
Evidence of Seriousness of Breach
Other grounds relied upon by the owner to terminate the contract
Conclusion on Grounds 5-8 of the Appeal
Grounds 10 and 11: whether the builder has complied with Order 2 of the Tribunal's Orders in relation to the provision of insurance.
Fresh Evidence
Exhibit 1
Exhibit 2
Exhibit 3
Disposition of the Appeal
Costs of the Appeal
Orders 1. Leave to appeal on grounds 1-4 of the Amended Notice of Appeal is granted. 2. The appeal is allowed. 3. Orders made by the Tribunal on 12 November 2019 and 9 December 2019 are set aside. 4. In substitution for orders made by the Tribunal on 12 November 2019 and 9 December 2019, the following orders are made: 1. North Shore Homes Pty Ltd is to pay Ann Nyunt the sum of $46,728.13 within 28 days of the date of these orders. 2. North Shore Homes Pty Ltd is to pay two-thirds of Ann Nyunt's costs of the Tribunal proceedings, on the ordinary basis, as agreed or assessed. 1. North Shore Homes Pty Ltd is to pay Ann Nyunt's costs of the appeal including any costs of the stay application, on the ordinary basis, as agreed or assessed. 2. If either party contends for a different costs order, order 5 above ceases to have effect and the following orders apply: 1. The party contending for a different costs order (the costs applicant) is to file and serve evidence and submissions on costs within 14 days of the date of these orders including submissions as to whether a hearing on the question of costs should be dispensed with pursuant to s 50(2) of the Civil and Administrative Tribunal Act 2013. 2. The costs respondent is to file and serve any evidence and submissions within 14 days thereafter including submissions as to whether a hearing on the question of costs should be dispensed with pursuant to s 50(2) of the Civil and Administrative Tribunal Act 2013. 3. The costs applicant is to file and serve any evidence and submissions in reply within 7 days thereafter.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 17 July 2020
Nyunt
North Shore Homes Pty Ltd
(2007) 233 CLR 115
(1931) 45 CLR 359
(1998) 194 CLR 355
(1987) 10 NSWLR 468
(2019) 93 ALJR 1164
(1951) 83 CLR 322
(1988) 166 CLR 245
(1989) 166 CLR 623
[2000] HCA 64